Sie sind auf Seite 1von 3

MEETING MINUTES

Ithaca Commons Repair & Upgrade Project


Date
08/19/2014

Start
10:00 AM

End
11:00 AM

Purpose
2014 Construction Meeting #22
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP /
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric

C#3A Surface, C#3B Electric


Next Date
08/26/2014

Next Time
10:00 AM

Prepared By
Jessica Buckley

Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross, Eamonn Hutton (A), Kimberly Michaels TWM
Dan Walker, James Matzat (A)
Ralph Avery, Andy Breznay, Matt Thomas (A), Roberto DeVincentis (A),
Bob Bellavigna ACP
Lou Zupan, Bill Planert (A)
Gloria Moran, Jeff field rep subbing for James
Doug Stafford (A), Jack Barker (A), Dawn Stillwell (A), John Mattiace (A)
Jeff Bubb (A), Flint Brann (A)
Jack Czapranski (A), Dennis Kuhn (A)

Item / Description
1. RFIs, SUBMITTALS
1.1. Vacri (Contract #3A):
1.1.1.Granite Coordination (#87R1)
coordinate locations of EX6 stubs
with PCG
1.1.2.Gateway (#106) see Bulletin #18
for steel cuts; need 2 diameter hole
in base plates for electric feeds
1.1.3.Irrigation (#98) Yellowwoods not
roughed out; annual vs. perennial
irrigation on State?
1.1.4.Structural Soil (#90R2) What is
issue with Sultana and
Paolangeli/Angelo material?

Notes
RFI 29 ACP to coordinate with granite
supplier to meet EX6 light location; LZ to
ask Dennis (electrician) if sheath cable is
needed; BB to review submittal 87 on
bench blocks; Vacri/ACP is to coordinate
with granite supplier on location of
conduit for west seatwall lights; Vacri is
to send revised location of pavilion
electrical receptacle to steel fabricator;
DW to locate hole in base plate for EX9
and EX2 light conduits; SR to review if a
separate submittal is needed for each
gateway structure; Location of RPZ in
irrigation layout is to be determined and
included in response to submittal 110;
Response to RFI 27 is to install CU
jumper to irrigate yellow wood planter
below foundation irrigation to yellow
wood planter; Footers for yellow wood
planter to be excavated tomorrow any

Page 1 of 3

Due

1.2. P&CG (Contract #3B):


1.2.1.Lighting Submittal #13R4 PCG to
resubmit on EX1 poles, EX4 fixtures
and mounting arm for EX8 not
approved
1.2.2.Catenary Cabling #??? PCG to issue
submittal
2. DESIGN, FIELD DIRECTIVES
2.1. TTC Alley: Sasaki to issue grading for alley
2.2. Bulletin 17: AC+P has suggested alternate
reinforcing detail for curb backer
2.3. Bulletin 18: Electrical changes to
gateways and pavilion
2.4. 139 Benchwarmers Vault: Site survey
8/21/14 at time TBD (7-9:45, 10-12:30,
2:30-4)
3. CRITICAL PATH ITEMS
3.1. Water Feature Vault: Vacri to install
sanitary lateral and vault 8/25
3.2. Gateways: @Aurora: Vacri to dig test pit
this week to verify if pier is in conflict
with vault wall at 224 E State; @Cayuga:
Verizon to schedule crew to relocate DB;
schedule for helical pile installation?
3.3. Vacri (Bank Alley): Sasaki issued 18 curb
detail; Start pouring ribbon footers
3.4. NYSEG Gas: schedule to complete 4
services and purge mains?; punchlist:
remove surplus fill on State St, finish
paving at Cayuga/Aurora, adjust gas valve
boxes throughout, cut out main at Trolley
Circle CB 1.A, cut out mains at light pole
bases
3.5. Pavilion Lighting: Vacri to advise on
additional costs to add HHs, delivery date
for steel
4. M&PTP: MAINTENANCE & PROTECTION
OF TRAFFIC & PEDESTRIANS
4.1. Site Maintenance: NYSEG to remove
surplus fill to re-establish site to subgrade; All trash and debris must be
removed on a weekly basis

piping into the planter needs to be


complete; KM to call Pogo for structural
soil; AB is ready to have soil delivered by
the end of next week; Structural soil
submittals have not met specs
BP to have resubmit lighting submittal
today; SR is to determine if the EX4 needs
separate circuit; SR to discuss pavilion
junction box with lighting consultant

Sasaki to issue bulletin today


SR to respond to JB email on doweling
reinforcing into footer
Vacri to request quote for changes to
pavilion in bulletin 18
Meeting with property owner on 08/21 to
determine whether to repair or infill vault

Vacri install san lat to WF vault on 08/25


Verizon will have crew on site tomorrow
to relocate DB

Clsd
Abandoned gas main sections to be cut
out for light pole foundations

Rock from NYSEG trench in Cayuga St hit


pedestrian, reminder to keep streets clean

Page 2 of 3

5. New Business

Inlet glass will be working on windows of


Rothschild

Page 3 of 3