Beruflich Dokumente
Kultur Dokumente
Start
11:00 AM
End
12:00 PM
Purpose
2014 Construction Meeting #27
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP /
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric
Next Time
10:00 AM
Prepared By
Nicole Mason / Jess Buckley
Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross, Eamonn Hutton (A), Kimberly Michaels (A) TWM
Dan Walker, James Matzat (A)
Ralph Avery (A), Andy Breznay, Matt Thomas (A), Roberto DeVincentis,
Bob Bellavigna (A), Ken Height ACP
Lou Zupan (A), Bill Planert
Gloria Moran (A), Jeff Utter (A)
Doug Stafford (A), Jack Barker (A), Dawn Stillwell (A), John Mattiace (A)
Jeff Bubb (A), Flint Brann (A)
Jack Czapranski (A), Dennis Kuhn (A)
Item / Description
1. RFIs, SUBMITTALS
1.1. Vacri (Contract #3A):
1.1.1.Structural Soil (#90R2): Vacri to
update on status of re-submittal;
Need delivery of material for State
Street 9/29/14
1.1.2.Topsoil (#104R2): Sasaki reviewed
9/15; Must be mixed with other
components to form Planting Soil
per spec
1.1.3.Gateway (#106, #114a/b): Vacri to
advise on schedule for delivery
1.1.4.Play Benches (#117): Vacri issued
9/17/14; Sasaki to review
1.1.5.Trolley Circle Sculpture: Vacri to
submit sample of etched paver for
Sasaki to review
1.1.6.Bronze Inlays: Vacri to provide
submittal for bronze play pieces
1.1.7.Etched Pavers (Play Pieces): Sasaki
waiting for Hanover sample
Notes
1.1.1 Last test was Sand 23.6%. Silt 47.6%
pH 6.8 organic 3.87% Clay 18.8%
(minimum spec is 20%). Vacri will order
40 CY for Bank Alley green screen area
and submit current mix to document
exactly what it is. M Kuo approved
pulling back structural soil limits from
next to the northern seat wall so
concrete pour is not held up tomorrow.
Pogo said they now have all the
components for the mix that meets every
spec believe that they have a good
source of clay, they are waiting for a
nutrient test.
1.1.2 Going to get each component
approved and then mix it to spec. Need
to submit on mix as well as components.
Page 1 of 4
Due
Page 2 of 4
Page 3 of 4
B. Planert asking about size of lightpole base cover, needs to be big enough to cover width of
paving band diagonals.
Helical pile installation pushed back 2 weeks to the week of Oct 20.
Page 4 of 4