Beruflich Dokumente
Kultur Dokumente
Project Scenario:
You are a "fast tracker" at the A-1 Cement Company, looking for an opportunity to impress your superiors.
Management has assigned you to over-see the construction of Cement Dune Buggy for the president's son. After
consultation with a variety of builders, and in consideration of your career prospects, you decide that this project
must be completed on time and within budget, and that a proper CPM must be constructed to plan and control
the activities of the project.
After consulting one of your colleagues who has completed the McGill Executive Institute Advanced Project
Management Course, you decide that your first step will be to determine distinct "Phases" for your project. The
end of each phase will mark a project "Milestone", at which point you will conduct a formal review with
Management. You decide that a logical delineation would be Design/Procure/Construct/Test.
With planned Project Phases in place, you proceed with detailed planning of your activities, each of which will fall
within a single Phase. At this point, you choose to concentrate your planning efforts on the Construction Phase.
You therefore proceed to break down the construction activities into logical tasks, leaving the other phases to
remain as single tasks for the time being. Construction can proceed as three concurrent "mini-projects"; the
engine development, the construction of the body shell, and the frame.
The engine will be purchased, but will require assembly and testing prior to installation of the frame.
The 4 frame sub-assemblies (frame/seats, suspension, drive train, wheels/axles/steering) will be ordered complete.
The latter three items must be assembled on to the frame. The suspension must be added to the frame firstly.
Then, the drive train and wheels/axles/steering may be added concurrently.
Once the frame is totally assembled, then the engine may be installed, except that you would like to "test fit" the
body shell to the completed frame prior to installation of the engine.
The cement body shell will be cast on the premises. Hardening will take 3 days. Then, it will be sand blasted and
primed, and be available for the "test fit". Successful completion of the "test fit" will then enable final painting to
be accomplished.
Once the engine is attached to the completed frame, then the painted body may be attached. Internal accessories
may then be installed, so that a final road test may be completed, along with the project.
EXERCISE 1
Through a team planning session, you have derived a list of major activities listed on the next page, along with
durations in days. Through a wall chart exercise you have been able to identify, for each activity, the predecessor
activities which must be completed in order to begin.
How long will the project take? What is the critical path?
L.Bartlett
ACTIVITY DESCRIPTION
PREDECESORS
TIME (days)
Design:
A
Nil
10
15
Procure:
B
Construct:
C
Install Engine
G,C
Attach Body
J,K
Install Accessories
L.Bartlett
I,F,E
Test:
N
L.Bartlett
Road Test
ACTIVITY
TEAM SIZE
A
B
C
D
E
F
G
H
I
J
K
L
M
N
2
1
5
4
1
2
3
2
1
2
3
3
2
2
L.Bartlett
L.Bartlett
________________________________________________________________
ACTIVITY
TIME
TIME DIRECT $
DIRECT $
COST
SLOPE
MAX
REDUCTION
10
10
10
10
_______
________
15
05
12
08
_______
________
13
08
12
10
_______
________
06
30
03
60
_______
________
03
07
01
11
_______
________
04
10
02
20
_______
________
01
03
01
03
_______
________
05
12
04
16
_______
________
03
03
02
04
_______
________
03
06
02
12
_______
________
05
01
05
01
_______
________
02
06
01
08
_______
________
03
10
01
16
_______
________
02
02
01
03
_______
________
113
182
Now, recognizing the large impact on costs if all the work was to be crashed in order to be reduce the
project duration, you employ the logic embedded in your Critical Path Network, in order to reduce
duration in a cost-effective manner.
L.Bartlett
Step 2 - Given the Normal and Crash Direct Costs you have determined above, determine the total direct
costs for the Cement Dune Buggy Project, for each unit reduction of time. Examine the cost impact of
reducing the time of the project, investigating each project duration scenario down to a value of 42 days.
(Begin the exercise assuming the project duration calculated from Exercise 5.)
Use the following worksheet template for your solution:
STEP #
ACTIVITY ID
INCR. COSTS
--------
TOTAL
DURATION
__________
__________
__________
__________
__________
__________
__________
__________
__________
__________
__________
__________
L.Bartlett
L.Bartlett
__________
Indirect Costs
$ 110
$ 100
$ 93
$ 88
$ 85
$ 82
$ 79
$ 77
$ 75
Using the above indirect costs, and the direct costs established from Step 2 above, determine the optimum
schedule and minimum cost for this project. (Again, begin the exercise assuming the project duration
calculated from Exercise 5.)
STEP #
PROJECT
DIRECT
DURATION
COST
(ABOVE)
(ABOVE)
INDIRECT COST
COST
(ABOVE)
_______
_____________
__________
_____________
____________
_______
_____________
__________
_____________
____________
_______
_____________
__________
_____________
____________
_______
_____________
__________
_____________
____________
_______
_____________
__________
_____________
____________
_______
_____________
__________
_____________
____________
_______
_____________
__________
_____________
____________
_______
_____________
__________
_____________
____________
_______
_____________
__________
_____________
____________
_______
_____________
__________
_____________
____________
L.Bartlett
TOTAL
COST
L.Bartlett
EXERCISE 7 - Estimating
Stimulated by the commercial interest in the Cement Dune Buggy, Management has decided to develop a
complete bottom-up estimate, factoring not only labour and indirect (overhead) costs, but also material
costs, contingencies, and profits in order to determine a complete competitive price for the Cement Dune
Buggy.
The goal of this exercise is to determine a (single) base price for the Dune Buggy.
Employ the schedule and resource assignment data found on the following page. This schedule has been
modified to reflect further adjustments, and spanning 54 days total.
Apply the following information:
Profit
Overhead
Labour Rates
: 10 % of all-up costs
: 35 % of all labour charges
: 10 % of all material costs
: skill level 1 - $ 80/day
: skill level 2 - $ 100/day
: skill level 3 - $ 120/ day
Note - rates for skill levels 1 & 2 will increase by
5% starting on day 41 of the project.
Contingencies:
Design:
7 % of total project direct cost
(i.e. lab and materials)
Estimating:
3 % of activity labour & material costs that involve
concrete casting, finishing & painting (i.e. H, I, J)
7 % of activity labour costs of assembly tasks
(i.e. D,E,F,K,L,M)
100 % of labour for major testing activities
(i.e. G,N,C)
Material:
3 project days worth of total project labour costs
L.Bartlett
Durn
10
12
11
06
03
04
01
05
03
03
05
01
03
02
Start
01
11
23
24
34
31
43
35
40
44
44
49
50
53
Finish
10
22
33
29
36
34
43
39
42
46
48
49
52
54
Man-days
Res 1
Res 2
Res 3
00
05
04
06
06
08
02
08
06
09
03
02
01
00
05
00
20
06
02
03
00
01
00
02
07
01
06
02
20
00
02
00
00
00
00
00
00
00
02
00
00
02
L.Bartlett
- 1000 Kg
-1
-1
-1
-1
- 40 litres
-3
(ACTIVITIES
AFFECTED)
;$ 1 / Kg
;$ 550
;$ 250
;$ 300
;$ 300
;$ 2.50 /litre
;$ 325 (total)
H
C
E
D
E
I,J(half &half)
H
A
B
C
D
E
F
G
H
I
J
K
L
M
N
Description
Durn
Start
Finish
Cost
10
12
11
06
03
04
01
05
03
03
05
01
03
02
01
11
23
25
34
31
43
35
40
44
44
49
50
53
10
22
33
30
36
34
43
39
42
46
48
49
52
54
3915
540
4061
2063
1248
1269
227
2457
725
1359
1673
369
964
608
21,478
L.Bartlett
--PERIOD 2--
% COMPLETED
ACTUAL
COSTS
5,630
100 %
--PERIOD 8-ACTUAL
COSTS
3,915
5,630
100 %
100 %
540
446
10 %
406
300
TOTAL
BUDGET
3,915
5,630
3,915
100 %
540
446
540
100 %
4,061
3,700
4,061
100 %
2,063
1,800
2,063
100 %
1,248
1,200
1,248
100 %
1,269
950
1,269
100 %
227
120
227
100 %
2,457
2,100
2,457
33 %
242
900
725
0%
1,359
0%
1,673
0%
369
0%
964
0%
608
100 %
0%
3,915
TTL
3,915
5,630
EV
TOTAL
ACTUAL
COSTS
EV
--PERIOD 5--
4,861
6,376
EV
16,022
16,846
1. To each of Days 10, 25 and 40 calculate the following for the project:
EV
AC
ETC
EAC
COST VARIANCE
SCHEDULE VARIANCE
2. For each of Days 10, 25 and 40, where does the project stand with respect to costs, and schedule?
3. What is the trend pattern?
L.Bartlett
21,478
L.Bartlett