Beruflich Dokumente
Kultur Dokumente
371-384
Table 1
Introduction
IN JUNE OF 1976, the U. S. Army Corps of Engineers embarked
on a program to design three new hopper dredges as a first step
in the establishment of a reduced but modern state-of-the-art
hopper dredge fleet. The fleet reduction is in conformance with
recently enacted legislation (PL 95-269) which indicates t h a t an
increasing share of the national dredging work is to be performed
by commercially owned plant, which is the reason why contractors are now building hopper dredges.
The three new dredges which have been designed and are now
under construction for the Corps are outlined in Table 1, and
preliminary design profiles are shown in Figs. 1, 2 and 3.
The philosophy governing the reduced fleet is that the new
designs will be capable of operating on all coasts and will be
available on short notice for national defense needs or for military
or civil emergencies anywhere in the United States or in any of
its overseas interests. In the absence of such emergencies, the
dredges will be kept in readiness by continuous operation in
regular dredging assignments. Nevertheless, some special capabilities may be provided. The Yaquina is designed to be especially
suitable for operation at shallow draft in such inlets as are found
on the West Coast. The large-class hopper dredge (LCHD) is
intended to have enough power to operate all four of its dredge
pumps simultaneously. It has the usual two side dragarms, each
carrying a submerged dredge pump, and, in addition, a third
dragarm in a centerwell capable of feeding two dredge pumps.
W i t h all four pumps operating, the dredge can be especially effective when working in the agitation mode, t h a t is, simply overflowing from the hoppers continuously, allowing the material
to be broadcast over the water on both sides of the dredge and
letting the current carry the solids to be deposited outside of the
channel boundaries. This dredge is expected to be particularly
effective in dealing with the shoaling which occurs in the Mississippi River passes, which occasionally has required attack by
a sizeable dredging fleet.
The medium-class hopper dredge (MCHD) can be considered
a general-purpose dredge, designed to be efficient and effective
in all assignments. Its dimensions are average, and its loaded
draft can be tolerated by the majority of authorized dredging
projects.
The author has been continuously involved with the design,
1 Chief, Marine Design Division (Ret.), Philadelphia District, U. S.
Army Corps of Engineers.
Presented at the December 7, 1979 meeting of the Philadelphia Section
of THE SOCIETY OF NAVALARCHITECTS AND MARINE ENGINEERS.
The opinions expressed herein are the views of the author and not
necessarily those of the U. S. Army Corps of Engineers or the U. S. Army
at large.
OCTOBER 1980
Yaquina
Length OA, ft
200
Length BP, ft
193
Beam, molded, ft
58
Depth amidships, molded, ft
17
Hopper volume, yd ~
825
Hopper capacity, sand (min.), yd3
650
Propulsion power, shp
2 1125
Design draft, loaded (est.), ft
12
Displacement at loaded draft, LT
2963
Speed, loaded (est.), knots
10
Dredge Pumps, inboard:
number
2
discharge dia, in.
16
bhp, each
565
Dredge pumps, dragarm-mounted:
number
0
discharge diameter
...
Bhp, each
.
Maximum dredging depth, ft
"4'5
No. in crew
28
MCHD
LCHD
350
333
68
35
6000
4818
2 3500
27
13 950
13.4
409
384
78
39
8400
6000
2 5200
29.5
19 000
14.5
2
26
3000
2
30
3600
2
26"
1450
80
38
2
26'/
1600
80
40
0025-331618011704-0371500.5310
371
.....
.....
I I
Fig. 1
....
...........
! ........
o:'
"Y"'"
Damage stability
Heretofore, the U. S. Coast Guard has had no rules enforcing
the subdivision of cargo ship hulls. The Load Line Regulations
make provision for the assignment of lesser freeboards to vessels
if they are designed to "remain afloat in a satisfactory condition
of equilibrium after flooding" of any single or any adjacent pair
of damaged compartments. However, such subdivision is not
mandatory. In the absence of any such regulation the Corps long
ago, commencing with dredges built in the 1930's, adopted a
policy that all dredge hulls would, where practicable, be designed
to survive flooding of any two adjacent compartments. An exception was made for small dredges like the Hains class and the
372
" ......
oo
oo
oo
," . . . . .
,;o
cc~s a, ~ E ~ S
US ARMY
oo
r, ; jl
,,i . . . . ! !~! ~ . . . . .
:7~: . . . . . . . .
,~ . . . . . .
::'~-:--:,~:-
x'
,2 _ ) "
Fig, 2
At the time that the U. S. Coast Guard made this letter public,
the Corps had virtually completed the design of the shallow-draft
dredge Yaquina to a one-compartment standard. Considerable
redesign was necessary to meet the two-compartment subdivision
required by the conditions of Appendix 1, including an increase
in beam from 56 to 58 ft and the introduction of some longitudinal
subdivision and cross-flooding provisions.
Examination of the conditions set forth in Appendix 1 reveals
two interesting points:
(a) A length of damage is specified, namely, 0.495L2/3. In some
areas of a hull, this length may very well span three compartments.
(b) There is no reference to a margin line as the limit of submergence. Thus the decks may very well be awash. It is simply
required that an equilibrium position be established with the
final angle of heel not exceeding 30 deg, with positive righting arm
of at least 4 in. over a range at least 20 deg beyond equilibrium.
As the Yaquina hull was recalculated in accordance with Appendix 1, it further developed that advantage could be taken of
the spillage which occurs from the hoppers as the vessel heel increases. This represents an appreciable help because the hoppers
are considered to be loaded with a fluid having a specific gravity
of 2.0. This is a penalizing factor when figuring free-surface effect
in calculations of intact stability, but it helps in calculations of
damage stability.
Superstructures
A major change from previous practice is the location of the
_2
,,
....
-::
.....
::::::i
......
a
:
..... ,
.......
.
..........
.........
..,[/
...............................
J,
:: , . . .
Fig. 3
OCTOBER 1980
373
Table 2
Vessel
LBP, ft
Yaquina
193
333
384
MCHD
LCHD
5.33
13.93
9.67
Position
No.
Function
Pumps
Used
Discharge
Destination
1
2
3
dredging
dredging
unloading
overside
inboard
inboard
unloading
inboard
dredging
(agitation)
inboard
overside
dredging
dredging
(agitation)
inboard
overside
inboard
overside
hopper loading
hopper loading
port discharge
to shore
starboard discharge
to shore
overboard
to hoppers
and overflows
to hoppers
to hoppers
overboard
overboard
374
VESSEL
C R E W SIZE
Large
Large
Medium
Medium
Small
Small
Essayons
110
42
90
38
42
28
LCHD
Comber
MCHD
Pacific
Yaquina
The comparisons in the large and medium classes are not totally
fair, as the Essayons and Comber are steam turbine-electric
vessels with firemen, watertenders and electricians in their watch
complements, whereas the new dredges are diesel-propelled. '
An appreciable part of the crew reduction is attributable to the
decision to introduce extensive automation. Additionally, it was
decided to build into these vessels the capability for unattended
engine room operation, following the precepts of U. S. Coast
Guard Navigation and Inspection Circular No. 1-69 dated 8
January 1969. To this end, the vessels are to be inspected and
classed by the American Bureau of Shipping (ABS) with Maltese
Cross ACCU 2 certification. However, it is not intended to operate
immediately without engine room watch personnel, and the figures tabulated in the preceding do not reflect such possible further personnel reductions.
Extensive automation of dredging machinery and equipment
operation is specified. To begin with, a process will be dialed, be
it hopper loading, agitation, direct pumpout, etc. For example,
Table 3 outlines the processes which can be selected on the
LCHD. Upon dialing and pressing the "execute" button, the
proper valves will be automatically opened and closed, and lights
on a mimic diagram will show the status of each valve and the
flow path.
In addition, power for the dredge pumps is derivable from more
than one source. Again using the LCHD as an example, Fig. 4(a)
shows the main p u m p power system diagram and Fig. 4(b) the
power routes t h a t can be selected. The proper circuit breakers
will be opened or closed upon selection and execution of power
paths, and lights will show the status of each circuit breaker.
A dredge control officer (DCO) on the bridge will make all
process decisions and operate the dredging system. During actual
dredging he will be seated at a console housed in a glass blister,
"front" and center of the pilothouse, at a lower level so as not to
interfere with the helmsman's vision. Before initiating dredging
the DCO will first note at his console whether the pumping power
engines are warm. If so, and if they are not running, he can restart
them at the console. If they are not warm, they must be started
by the engineer.
With engines running, and with draghoist motor-generator sets
running, the DCO now presses a button to initiate d r e d g i n g - actually, a button for each dragarm. This deploys the dragarm,
lifting it from its stowed position on the deck, breasting it outboard, then lowering it down the ship's side to a horizontal reference position, with the trunnion properly seated in the operating position. The mechanisms will stop at this point and a light
will advise the DCO t h a t all is ready for dredging.
Next the DCO will press a "lower" button. The dragarm will
now pivot around the trunnion, thereby lowering the draghead
to dredging depth. When the latter touches bottom, the swell
compensator will assume control, stopping the lowering action.
The swell compensator will automatically keep the draghead in
proper contact with the bottom, an a d j u s t m e n t having been
2 Paragraph 41.7 of ABS rules defines this symbol as "Automatic
Control System for Unattended Engine Room Certified."
MARINE TECHNOLOGY
37~75o vD.c.
37s./zso ~c~c
D.C. SWITCHING
.ooo l.ow
4T_
2 3 4 5 6 7
1 DREDGING RECTIFIER NO 1
X O 0 O X 0 X
2 DREDGING RECTIFIER NO 2
c~('DREDGING WITH
3 ~'-LOUTBOARD PUMP ONLY~
4 PUMPOUT
0 0 0 X 0 X X
0 0 0 0 0 0 0
X X X X 0 O 0
T I
ABCDE
NC AC. SWITCHING
I DREDGING--PORT GENERATOR TO OVERSIDE PUMPS O 0 0 X O
~BD
~sPUMP~/MI~(oT~#T)R
AGITATION DREDGING
4
5
PUMPOUT
DREDGING-STBO GENERATOR TO INBOARD PUMPS
(B)THROUGH RECTIFIER NO 2
6
B
4160v i
XlOXO0
O:XXO0
olxlololo
olxlololx
CA)THROUGH RECTIFIER NO l
OlD,O,
x o o
POWER
FACTOR
CORP
(a)
(b)
Fig. 4
preset to determine how big a "bite" the head will take, t h a t is, option, course correction information can be fed to the automatic
the degree of e m b e d m e n t into the bottom material. This ad- pilot to hold the dredge on the cut.
Because of the plan eventually to operate on the basis of an
j u s t m e n t establishes what portion of the draghead weight is
supported by the hoisting cables and what portion by the channel unattended engine room, much automation has been introduced
bottom. The swell compensator is a hydraulic cylinder with a in the area of propulsion and auxiliary machiaery operation. Due
stroke of 12 ft, or 4- 6 ft above and below a median. This permits to limitations of space, however, this particular automation
the draghead to follow unevenness of the channel bed within cannot be discussed here. As a final note on this matter, however,
these limits without operation of the drag hoist winches. If a large recognition should be given to the provision of some degree of
hole or hill is encountered, the hydraulic ram will travel to one automation in keeping the ship's log. In the pilothouse the opor the other end of the stroke and automatically start the winches erator will have available an automatic event logger, having a
to hoist or lower the draghead until the ram returns to the median keyboard, a printer and a clock mechanism. By striking the appropriately numbered key, he can cause to be printed the identity
point.
Other automatic dragarm devices keep the draghead from and the time of occurrence of such events as starting and stopping
of dredge pumps, going to and returning from the dump, interdrifting under the ship's hull.
At completion of dredging, the same automatic features pre- ruption and resumption of operation, and any other events t h a t
vail, as needed, in the reverse direction for stowing the dragarms. the dredge master might care to have automatically recorded.
Or, if the dredge is to be turned 180 deg for a reverse cut, raising
the dragarms out of the water is also a pushbutton operation.
Centerwell dragarm
Still other automatic devices will govern the loading in the
The large-class hopper dredge will be particularly distinhoppers and raising and lowering overflow levels forward or aft,
port or starboard, in response to preset instructions and to vessel guished by a third dragarm located in a centerwell designed into
the hull in the hopper area along the centerline. The dragarm is
trim or list,
When the vessel is dumping, automatic controls will open the raised and lowered and permanently located in this well.
Despite the presence of the centerwell, the hull model tests
doors in timed sequence in accordance with preset instructions,
automatically interrupting the dumping operation and advising indicate t h a t a full-power loaded draft speed of about 14 knots
the DCO if the ship starts to take an improper attitude or if some may be expected. The model testing revealed that the centerwell
adds about 21 percent resistance at speeds of 12 knots and higher.
other fault occurs.
If the vessel is unloading its hoppers by direct pumpout, the Two other interesting points were evidenced by the model tests:
automatics are designed to prevent line plugging, as well as to (1) It is better to keep the dragarm low in the centerwell, forming
a sort of rough closure of the well when the ship is underway. This
effect unloading control.
The DCO is provided with remote controls at his station or in prevents oscillation of the water level in the well, which if allowed
the bridge for all details of the dredging, loading and unloading would represent added resistance and a dissipation of energy. (2)
operations. There is also a wealth of instrumentation to tell him By eliminating transverse keelsons between the hopper bottom
what is going on and how well his equipment and systems are doors, hitherto used to form individual hopper door wells, or
functioning. The hopper load is continuously displayed, and so recesses, the hull resistance was decreased about 13 percent at
is the loading rate, so that he can quickly deduce when he has speeds of 12 knots and higher. Thus, a new feature for the LCHD
achieved an "economic load" in the hoppers. Position indicators and M C H D will be a single hopper door trough on each side, inand recorders verify that the ship and the dragheads are actually stead of individual door recesses.
The centerwell dragarm will feed the two inboard dredge
working exactly where desired on the shoaled areas. At the mate's
OCTOBER 1980
375
o
I
z
Overside pumps
~5000
0
EXISTING
DRAGARM
\\
,ELONGATED
DRAGARM
~4000
40
50
60
70
80
90
]00
DREDGING DEPTH-FT
Fig. 5 Calculated pump performance of dredge Essayons(with existing
36-in.-inside-diameter dragarms and with added pipe lengths hypothesized
for depths greater than 60 ft)
Two of the three new hopper dredges will have dredge pumps
mounted on the dragarms, so that during dredging these pumps
will be well submerged. This, of course, greatly increases the
weight of each dragarm and makes for increased dragarm handling problems, such as winch power, wire rope sizes and supporting davit structure. However, they are essential, for deep
dredging projects which are planned for the future, and their
increased effectiveness is usable on projects at current depths.
The performance of centrifugal pumps is limited by suction
lift considerations. Heretofore, dredge pumps on hopper dredges
have been installed inboard. The pumps have been so installed
as to place the suctions as low in the hull as hull structural considerations would permit. Even so, when dredging at, say, 40-ft
depth and pulling in a solids/water mixture of perhaps 1.2 average
specific gravity, the pump will pull a vacuum in the range of 22
to 28 inHg, regardless of the fact t h a t the p u m p centerline may
actually be several feet below the outside water surface.
Theoretically, if the pump were to be placed at the channel
bottom, the p u m p suction would always be under a high static
head and the p u m p would never pull a vacuum. The limitation
on pump performance then would be the available power for
pushing the solids/water mixture up the dragarm piping and into
the hoppers.
One dredge was built in Europe with the dredge pump actually
placed at the draghead on the channel bottom. Dredges built later
than this one placed the dredge p u m p about half way up the
dragarm, apparently to reduce handling problems and problemsarising from sending hydraulic or electric power down the dragarm to such depths. On the Corps' medium- and large-class
dredges the pumps are placed about halfway up each dragarm.
Figure 5 demonstrates the need for the submerged dredge
pumps for deep dredging. It shows the calculated pump performance on the dredge Essayons (presently the Corps' largest
dredge) at various dredging depths, with extended suction pipe
hypothesized to reach the greater depths. The pumps are placed
inboard on this dredge and thus are limited in performance by
the increased vacuum exerted at greater depths. Performance
is seen to be acceptable up to about 60- to 65-ft depth, but a sharp
drop-off in performance is seen to start at about 70 ft.
The medium- and large-class hopper dredges will have inboard
dredge pumps in addition to the dragarm-mounted pumps. These
are needed primarily for direct p u m p o u t operation so t h a t the
dredges can unload themselves into a shore disposal area. However, piping connections are such t h a t either or both of the inboard pumps can also be used for dredging in the event the overside pumps are down for repairs. In such a case, the p u m p /
motor module of the d r a g a r m is replaced by a length of pipe, on
the medium-class dredge. On the large-class dredge, the inboard
pumps will take suction from the centerwell drag, and the side
dragarms will be stowed out of service:
T h e pumps and motors of the dragarm-mounted units will be
close-coupled. The pumps will have 28-in. inside diameter suction
and 26-in. inside diameter discharge. The motors will be 3-phase
squirrel-cage induction type, operating at 2400 V and oil-cooled.
Enclosures and seals will be specially designed for submerged
operation.
Motor speed i s controlled by control of engine speed, t h a t is,
by control of ac frequency produced by the generator. Speed
control is automatic, but the operator can change over to manual
control if the situation so requires.
Pump p o w e r
Careful consideration has been given to the dredge p u m p
MARINE TECHNOLOGY
Table 4
Dredge
Comber class
Essayons
Goethals
Lyman class
Harding
McFarland
Markham
Pacific
West Coast
Large class b
Medium class
Area of bay, ft 2
Volume of Bay, yd 3
Area of Door, ft 2
300
450
369
196
368
286
433
304
315
404 to 644
425
255
345
401
115
340
262
340
125
150
516 to 743
502
19.5
23.86
23.43
13.77
21.0
18.0 a
20.2a
16.0
24.0
66.0
64.0
6.5
5.3
6.3
7.0
5.7
6-3a
4.7 a
5.3
7.6
16.3 to 10.2
15.0
7.6
6.9
5.8
12.0
6.2
6.8
5.9
12.8
16.0
12.8 to 8.9
12.8
a These are projected areas, half of actual. Doors are on a slope of 60 deg.
b NOTE: Hopper bays not uniform due to hopper arrangement. Data represent span of characteristics.
c Square footage of hopper door area per 100 yd 3.
power requirements, especially for dredging. There was a time
when it was thought t h a t the more power one could apply to a
pump, the better the operation. This thinking was justified when
pumps driven by large low-pressure reciprocating steam engines
were actually underpowered. The advent of the compact electric
motor drive encouraged the use of higher pump power, and
eventually some dredges were built with too much pump power.
This resulted in fluid being discharged into the hopper so fast as
to create a degree of turbulence that inhibited the settling of
solids in the hoppers. Under these conditions, solids were being
washed past the overflows at a rapid rate. T h e pumps had to be
slowed down in order to improve the hopper retention rate, that
is, the settling rate of solids in the hoppers.
An analysis of this situation revealed that there is an optimum
average discharge rate from the pumps into the hoppers and that
this rate is proportional not to the hopper volume b u t to the
h o p p e r surface area. Mathematically, this is expressed as
Q = KA
quired power may vary with line length, the discharge head to be
developed and the density of the mixture t r a n s p o r t e d to shore.
The power level can be established somewhat arbitrarily, from
practical machinery considerations, b u t it is i m p o r t a n t to consider the head to be developed for the largest combination of line
length and discharge elevation, as this will influence the impeller
diameter and rpm. Since it will be desired to p u m p out with full
power on short lines as well as intermediate and long lines, a range
of r p m with 100 percent power capability m u s t be provided. I t
is for this reason t h a t dc motors will drive the inboard dredge
p u m p s of both the M C H D and the LCHD.
Hopper
door areas
A significant change in hopper door sizing has been accomplished in the three new dredges, to make them faster dumpers,
again to chop a minute or two off the cycle time. A step taken on
two preceding dredges to speed up dumping was the establishm e n t of unsymmetrical hopper slopes, to prevent arching of
material, particularly sand, in the hoppers. T h e next logical
course was to increase the door size to the m a x i m u m p e r m i t t e d
by structural design.
Table 4 shows statistics for the hopper doors of existing dredges
and of the three new dredges. The improvement in the latter is
evident.
The size and number of hopper door openings in the three new
dredges are as follows:
DREDGE
NO. OF D O O R
OPENINGS
SIZE OF O P E N I N G S
L W
Yaquina
MCHD
LCHD
6
12
14
6 ft 9 in. 3 ft 8 in.
8 ft 0 in. x 8 ft 3 in.
8 ft 0 in. X 8 ft 3 in.
of wider application. This requires provision of large high-pressure high-power pumping plants forward, not easily accommodated in the half hulls of the split-hull design. The split hull might
have been adopted for the small dredge Yaquina, which is not
equipped for direct pumpout capability, but this dredge is required to operate at shallow draft with a 300-yd load as well as
at 12- and t3-ft drafts with heavier loads. Special problems would
have been encountered designing split hulls with provision for
the self-opening and self-closing capability at several drafts,
which is normally expected of this type vessel at a single draft.
C o n t r o l l a b l e - p i t c h propellers
The application of controllable-pitch (CP) propellers for a
hopper dredge is no longer new, since the Corps began this on the
dredge Harding in 1958 and again on the dredge McFarland,
completed in 1967. The Harding wheels were each 2000 hp and
those on the McFarland 3000 shp. The dredge Pacific, repowered
in 1977, was fitted with two CP wheels, each absorbing 1050 shp.
For the large-class dredge each wheel will absorb 5000 shp, and
on the medium-class dredge 3350 shp. On the small dredge Yaquina each propeller will absorb about 1050 hp.
This will bring to six the total number of Corps dredges fitted
with CP propellers, constituting evidence of the eminent suitability of such propellers for dredge service. This is so because
dredges operate basically in three propulsion modes: (1) While
dredging, the vessel is in a towing mode, "towing" its dragarms
against the resistance of the channel bottom; (2) when loaded,
it is in a free-running mode at deep draft, going to the dump; and
(3) when light, it is in the free-running mode at light draft with
trim by the stern, returning to the dredging area. For maximum
working effectiveness it is desirable to use full or nearly full
propulsion power in each of these conditions. With a fixed-pitch
propeller system this is not possible. With a controllable-pitch
propeller system, the diesel engine (and propeller) can be operated at 100 percent speed and the pitch can be adjusted to allow
the engine to deliver 100 percent power in any mode.
Prior to the advent of CP propellers, the Corps used dc electric
motor propulsion with fixed-pitch wheels. Automatic controls
responding to electric current level in the power loop between
propulsion generator and motor armatures adjust the propeller
rpm for the free-running conditions, so that full horsepower is
utilized whether the ship is at loaded or light draft. For the
dredging mode, however, the establishment of a good dredging
speed, usually about 3 knots, requires lowering of the motor
terminal voltage, so that full power cannot be developed. Full
propulsion power when dredging is not always necessary, but
there are many times when the dredges are working against
strong currents and need to generate high thrust to maintain
reasonable headway while "towing" the drags against bottom
resistance.
The availability of full power under any operating mode can
help to cut a minute here and a minute there off the dredging
cycle. These reductions translate in increases in production.
Assuming again the 180-min dredging cycle referred to earlier,
each individual minute cut off this cycle time represents better
than a 0.5 percent increase in production. That is one reason why
CP propellers for dredges are here to stay. Additionally, the CP
propulsion equipment is lighter and less costly than the equivalent motor and generator and electric controls, and somewhat
more energy-efficient. The additional maintenance problems
presented by the CP propulsion control mechanisms are somewhat offset by the elimination of propulsion generator and motor
and control maintenance.
without exceeding the designloaded draft of the hull when all fuel
and water tanks are full. As the consumables are expended, the
vessel can obviously carry more sand load without exceeding the
permissible loaded draft. If, for example, the vessel carries 1170
LT of fuel and water, then, at the 90 percent burnout point, the
hoppers could contain an additional 702 yd 3 of sand without
exceeding the loaded draft, provided, of course, that the hopper
volume is sufficient to hold the extra sand.
But the dredges do not operate exclusively in sand. Frequently,
they dredge much lighter bottoms, in some cases encountering
bottom material densities as light as 75 lb/ft s, or about 0.9 LT/
yd 3. It would take 11 170 yd 3 of this light material to have a
weight equal to 6702 yd 3 of wet sand! A commonly encountered
mud has a density of about 1.2 LT/yd3; 8378 yd 3 of this material
is equal in weight to 6702 yd 3 of wet sand.
It is not practical to design a hopper dredge with hoppers of
such depth as to accommodate the entire spectrum of bottom
densities in sufficient volume always to load the hull to its designed draft. A limit is reached when the center of gravity of the
load in the hoppers gets so high as to affect adversely the vessel
stability. Contributing to this effect is the fact that the weights
of the hopper distribution piping, valves, hopper structure and
all other appurtenances over the hopper area are also moving
upward as the hopper coamings are raised in the effort to enclose
more hopper volume.
Nevertheless, within this limitation the effort should be made
to accommodate a reasonably wide range of densities. With the
three new dredges it has been found that this could be done.
Figure 6 is a chart showing the capabilities in this respect of the
LCHD. This dredge is intended to carry 6000 yd 3 of wet sand at
29.5-ft draft with all tanks full. At 90 percent burnout it will carry
about 6700 yd 3 of sand. The maximum hopper volume was set
at 8400 yd 3. Depending on the specific gravity of the hopper load,
the volume of material that can be carried at any condition of
burnout at 29.5-ft draft is shown in Fig. 6.
A similar chart for the MCHD, designed to carry 4800 yd 3 of
wet sand (1.5 LT/ydU), would show the volumes of lighter densities that can be carried at its loaded draft of 27 ft, up to its
maximum hopper volume of 6000 yd 3.
A dredge can fill its hoppers only to the level of its overflow
weirs. At this point the hopper fluid spills over the weirs and is
conducted via overflow troughs and ducts to the sea, or surrounding water. Most dredges operate with one or more fixed
overflow levels, selected by opening or closing louver-type
structures in the hopper coaming or sides. The location of the
overflow level is now determined with some regard for promoting
the maximum production capability of the dredge during the
burnout cycle. This is best illustrated by example.
One requirement of the small shallow-draft dredge Yaquina
is that it must be capable of carrying 300 yd 3 of wet sand at a draft
not in excess of 10 ft when all fuel and water tanks are full. Since
there had to be provided enough consumables for 12 days of operation, the tank contents, 180 LT, constitute a respectable
percentage relative to the hopper load. In this p~lrticular instance,
the sand used in design computations had a wet density of 1.35
LT/yd 3. Thus the weight of a 300-yd load is 405 LT. At the 90
percent burnout point, therefore, the dredge theoretically could
carry 567 LT or 420 yd 3 of sand.
Consider, now, the two extremes: (1) If the overflow level is set
at 300 yd 3, then the dredge can initially load up to 300 yd, but as
fuel and water are consumed it will be unable to hold any more
than 300 yd. Thus, as burnout occurs, the ship will not be loaded
to design draft. (2) At the other extreme, suppose the overflow
Hopper capacities
level is set at 420 yd. Initially, then, the hoppers must be limited
A hopper dredge is nominally designed to carry, say, 6000 yd 3 to that weight of sand plus water above the sand such that toof wet sand having a density of 1.5 long tons (LT) per cubic yard gether the total weight of hopper contents does not exceed 405
378
MARINE TECHNOLOGY
85OO
MAX
HOPPER
. . . .
VOLUME:8400
-~Z
CU YDS
d)
123
rr"
130
ch
_ _ ~ ~'3_2~
~ ~
j.-/
650C
60C0
IO
20
30
40
50
PERCENT BURNOUT
60
70
80
90
Fig. 6 LCHD hopper capacity. Carrying capacity of vessel at 29.5-ft draft, based on
preliminary design trim and stability conditions as affected by material density. Burnout
includes potable and fresh waters, fuel oil and domestic stores
C=Y, 4
C = 300 4
i j
//
200
/ /
Jl
/1t
I
I
I
I
j -
350
CI)
3oo
u~
Sw Tb
Ss
1 . 3 5 - 0.771 162
= 351
1.35
1.35
./..--~ ~
--
Ss
400
a
<
Ss
I
I
1
u~
100
I
I
I
!
I
10
20
30
40
50
60
70
80
90
PERCENT BURNOUT
Fig. 7
OCTOBER
1980
Yaquina
379
420
400
9 3oo-'~-~
&
233
200
. . . . .
Q
Z
~oe
I
0
Fig. 8
I0
20
30
40
50
PERCENT BURNOUT
60
70
80
90
Difference in total cycle production between variable and fixed overflow levels
C o n t i n u o u s l y variable o v e r f l o w s
It follows logically from the preceding discussion of overflow
level that if this level could be made continuously adjustable,
operators could take advantage of burnout continuously.
Pursuing the example of the dredge Yaquina in the previous
section, the initial sand load, when all tanks are full, could be 300
yd 3, which would be obtained by depressing the variable overflows to the 300-yd level. For succeeding loads, the overflows
would be raised a little to take advantage of consumables expended in the interim. Eventually, at the 90 percent burnout
point, the sand load could be 420 yd 3. A straight line can be drawn
between 300 and 420 yd to show how much sand can be carried
at intermediate points of the burnout cycle.
This has been done in Fig. 8, and the shaded area represents
the difference in total cycle production between continuously
variable overflow and o p t i m u m fixed overflow level. A comparison of the areas will show a production capability increase of
better than 10 percent. If compared with that for a fixed overflow
at the 300-yd level, the production increase is over 20 percent!
In view of this possibility for increased productivity, continuously variable overflows are being provided on all three new
hopper dredges.
The variable overflows are vertical large-diameter tubes which
penetrate the hull bottom and which (on the LCHD and MCHD)
are tapered out to form a large-diameter round basin at the top.
The latter feature provides a long weir edge. (On the small dredge
Yaquina, the overflow basins are rectangular.) Four such overflows are being provided, arranged one each port and starboard
forward and aft in the hopper area. The top segment telescopes
in and out of the lower fixed segment for adjustability of level.
T h e overflows are remotely controlled by the dredging control
officer in the pilothouse. They are also incorporated in the automation system for certain types of dredging.
D e c k cranes
Conclusion
The scope of this paper has been purposely limited to a presentation of those features which could be considered "new and
different" in the design of the three new hopper dredges. No att e m p t has been made to delineate the design of any one or more
of the dredges, so there is no presentation and discussion of arrangement plans, scantling plans, compartmentation, outfitting,
380
MARINE TECHNOLOGY
etc. This task is left for others who might wish to and may prepare
one or more papers dealing specifically with each of these dredges
upon their completion and delivery. Nevertheless, this paper
should serve to demonstrate that the design of dredges is not a
static endeavor. There is a continuous motivation to make the
dredging process more effective and to decrease the cost of operation. Holding down the initial cost of the vessel must be
compatible with these two objectives and with the requirement
to build an inherently safe vessel, as dictated not only by Coast
Guard and classification society rules, but also by the hazards
peculiar to dredge operation.
Nor do these designs represent the ultimate. As these dredges
go into construction, advances will continue to be made in materials, equipment and controls. Future designs will take advantage of such new developments and also address new problems that are and will be surfacing, such as even greater energy
conservation. The challenges are unending, but it has been a great
source of satisfaction to the author to have played a part in the
design of these three new hopper dredges that include many
design features new to the United States.
Acknowledgment
This paper has been cleared for publication pursuant to review
by personnel of the Office of the Chief of Engineers, U. S. Army,
Washington, D. C. Comments furnished by Mr. William R.
Murden, of that office, are gratefully acknowledged.
Discussers
George R. Knight, Jr.
Eugene R. Santhin
Frank L. Pavlik
George A. Johnson
W. A. Cleary, Jr.
Hugh P. McManus
Merville Willis
Appendix 1
Letter, 23 June 1977, from U. S. Coast Guard
(G-MMT-5/82) to C. F. Bean Corporation.
C. F. Bean Corporation
Attn: Allen J. Dupont
One Shell Square, Suite 3700
New Orleans, La 70139
Gentlemen:
Subj:
C.F. Bean Corporation
Self-Propelled Trailing Suction Hopper Dredge
Freeboard and Damage Stability
Ref:
Reference (a) requested a reduced freeboard for a selfpropelled trailing suction hopper dredge when dredging which
is less than that for load line certification. The Load Line
Regulations do not at present permit freeboards less than the
minimum permitted under 46 CFR 42.20 for Coastwise or
International voyages. However, the Coast Guard published
an advance notice of proposed rulemaking in the 2 August
1976 issue of the Federal Register concerning the need for
OCTOBER 1980
Appendix 2
Excerpt of noise and vibration control
requirements from MCHD specifications
GT-09 NOISE AND VIBRATION CONTROL
63
125
250
500
1000
2000
4000
8000
CATEGORY
A
83
78
75
72
64
58
53
50
CATEGORY
CATEGORY
C
78
70
64
58
54
52
50
49
100
95
90
90
85
85
85
85
CATEGORY
D
100
90
83
75
73
71
71
71
MARINE TECHNOLOGY
383
384
MARINE TECHNOLOGY