Beruflich Dokumente
Kultur Dokumente
The statement of work provided by the city to the PMT was vague in the design
phase.
• The DIA was based upon a “house-on-the-Range” design. The city wanted a
wide open entry point for visitors.
• The city wanted a thing of beauty rather than an easy to clean airport which the
airport personnel needed.
• This created a problem for the design team because the project’s requirements
specified that the design reflect a signature image of the airport. The major
reasons for the same can be seen from the failure of PMT in achieving the
following.
• PMT failed to sort out the differences between the city’s aspirations and the
maintenance orientation of the operators.
• PMT failed to detect the cost and constructability issues with the first design
even though the partners had in house expertise.
• PMT did not appear to be aware that the first design may not have met the
project standards.
No, it does not reflect up on the capabilities of the PMT. They were correct in
taking action; the timing of the intervention again reveals something about the internal
dynamics of the project. By the time they took the action, the airport was already 6
months behind schedule and four opening dates had already been missed. In addition
the disastrous demonstration of the system had shown to the world how bad the state
of the project really was.
The four missed opening dates and the disastrous demonstration indicate that
those at the highest level really had little idea what the true status of the project was.
Bringing in an external consultant to review the project was certainly a good decision,
but again it was a decision that was made far too late. A project of this size,
complexity and risk should have had a number of such reviews along the way and
independent expert assessment should have been a continual part of the project.
Yes, The PMT should definitely be qualified to perform risk analysis as DIA was
facing Recessionary problems. The Risk Analysis includes Risk Assessment, Risk
Management and Risk Communication. The case involves three preliminary risk
areas-
• Cost.
• Human resources.
• Bad Weather.
Also, one of the function or role of the Project Manager is to do risk analysis which is
important part of the project. PMT needs to make various Risk Checklists-
• Customer risk
• Quality risk
• Resource risk
• External environment risk
• End/deliverable risk
• Requirement risk
Therefore, PMT should be qualified to perform risk analyses.
24. Why were the architects co-ordinating the changes at the construction site?
The architects were co-ordinating the changes at the construction site to reduce
paper work and maintain the schedule. Architects heavy involvement during the
construction phase is highly unusual and the reason was that the PMT was abdicating
control to the architects who will be responsible for the coordination.
It was because of the PMT’s failure to sort out the differences between the
city’s aspirations and the maintenance orientation of the operators; their failure to
detect the cost and constructability issues with the first design that led to the burden of
responsibilities on the shoulders of the architects.
Yes, the PMT should have been replaced for the followings reasons-
• There was change in Strategy at the onset of the project itself. The project
management team needed to do a better job of planning prior to the start of the
project.
• The PMT failed to sort out the differences between the city’s aspirations and
the maintenance orientation of the operators.
• They failed to detect the cost and constructability issues with the first design
even though both PMT partners had vast-in house expertise.
• The PMT also did not appear to be aware that the first design may not have met
the project’s standards.
• PMT did not know what to do with the Destination Coded Vehicle system. The
risks were unknown. The complexities of the system was unknown especially
Software Requirements.
• PMT was also abdicating control to the architects who would be responsible
for coordination.
• The trust that had developed during the early phases began evaporating.
27. Why did the United Airlines decide to act as the project manager for the
baggage handling system on concourse B?
Denver, after some consideration concluded that all the concourses at the
airport would operate on the automated high speed baggage handling system, not
limiting it only to United Airlines.