Beruflich Dokumente
Kultur Dokumente
The Samuel W. Shaw Middle School (SWS known in construction as the Shawnessy/Somerset Middle
School) 6,406m middle school for 550 grade 5-9 students, operated by the Calgary Board of Education.
The school is located in the South-West Calgary neighbourhood of Shawnessy, on a 1.92 hectare site.
1,427m of space is available in modular, relocatable classrooms (which are not included as part of the
LEED submittal).
The intent of this case study is to inform the design of other buildings based on the successes of this
project. This in-depth technical document will provide other designers with insight into the LEED
process. For ease of use, this document is broken down by targeted LEED prerequisites and credits.
LEED Project Workflow
Adapting the LEED system to established project workflows can be challenging. In order to simplify and
expedite the process, there are two suggested phases of LEED documentation: design and construction.
Design phase credits may be documented before construction is complete. They generally rely on
adherence to the contract documents or can be documented independently of the buildings
construction. Examples include specifying air handling units that are free of CFC-based refrigerants and
public transportation options. By completing design credit documentation before the construction
phase, the LEED project team is able to allocate time and resources to credits when their completion is
most crucial. Documenting design credits early in the project can save money associated with late
changes and replacements.
The construction phase credits rely on the methods or results of building construction. Many
construction credits are documented through tracking materials entering or leaving the site, largely the
responsibility of the contractor. In the case of this project, approximately 2/5 of the credits could have
been documented before the construction of the school was completed.
Phase
Responsibilty
LEED Consultant
2
Architect
Mechanical Engineer
Design
39%
4
14
61%
Energy Engineer
CxA
Construction
6
2 2
1
Electrical Engineer
Contractor
Owner
Although the LEED system emphasises teamwork and synergies, allocating individual responsibility is key
to meeting project goals. A lack of commitment to the LEED goals from any one consultant can
jeopardize the projects overall targets. The Responsibility graph above shows the number of credits
pursued on this project, per party. Descriptions of their roles and workflows are as follows:
- LEED Consultant: The LEED Consultant coordinates with subconsultants, contractors and
owners. They ensure credits are being correctly documented at the appropriate stage of the
design and construction phases, while clarifying issues regarding LEED compliance and credit
intent.
- Architect: The architect designs the space and specifies envelope components. All of the credits
the architect is responsible for may be documented before construction is complete, as long as
the construction documents are followed.
- Mechanical Engineer: Like the architect, the mechanical credits are design-based, and may be
documented before the project is completed.
- Electrical Engineer: There are relatively few credits the electrical engineer is responsible for, all
of which may be completed in the design phase.
- Energy Engineer: The function of the energy engineer is to inform the design in ways to reduce
energy consumption, and to provide an energy model of as-built conditions. This work may be
completed in the design phase but should be updated to reflect any mid-construction changes.
- Commissioning Authority (CxA): The commissioning authoritys work begins in the design phase
by writing the commissioning plan which will be completed in the construction phase, once
there are building systems to commission.
- Contractor: At the beginning of the construction phase, following the award of the construction
contract, the contractor will produce several LEED plans (ESC, IAQ, construction waste
management). The bulk of the contractors credit documentation will occur at the end of the
construction phase, once theyve completed all material tracking.
Owner: The owner must be very involved during the design phase. They will produce the
owners project requirements (OPR) document which the commissioning authority will use to
ensure the design fulfills the owners needs. School board input is required in several policybased credits green cleaning and green education for instance so the earlier these
discussions can be initiated, the better.
Sustainable Sites
Prerequisite 1: Construction Activity Pollution Prevention
Required
Responsibility: Contractor
Phase: Construction
Before its construction, the SWS site was an empty lot that had been graded when the surrounding area
was initially developed. As part of the City of Calgarys Development Site Servicing Plan (DSSP) process,
the ESC consultant produced an ESC plan drawing as part of the tender documents that contractors
would be bidding on. This plan was then reviewed by the LEED consultant. The intent was to reduce
pollution from construction activities by controlling soil erosion, waterway sedimentation and airborne
dust generation. Site access was limited to two entrances with a gravel pad at each to eliminate
sediment being tracked offsite. In order to protect the surrounding stormwater infrastructure from
sedimentation, catch basins were covered with filter fabric, and a silt fence was installed along the
perimeter of the construction site. Temporary seeding helped to mitigate dust erosion of exposed
subsurface and material stockpiles, and sod was installed over topsoil as soon as possible in the
construction schedule.
Documentation: Per the specifications, the ESC consultant provided weekly inspection logs and photos.
Any deviations from the ESC plan were noted and corrective action was taken immediately.
Resources: City of Calgary Guidelines for Erosion and Sediment Control.
Water Efficiency
Credit 1: Water Efficient Landscaping
2 Points
Responsibility: Architect
Phase: Design
An owners project requirement was to limit the amount of water used for irrigation on school
properties. To accommodate this, the architect selected shrub and tree species known for their native
characteristics, drought tolerant nature and/or Chinook hardiness. Turf grassed areas were minimised,
and a seed mix that has the ability to lie dormant in drought conditions was used wherever possible. The
combination of these measures permitted no permanent irrigation system to be installed.
Credit 3: Water Use Reduction
2 Points
Responsibility: Mechanical Engineer
Phase: Design
The owners project requirement of minimising water use was carried through to the interior of the
building, as shown in the flow and flush fixture selection. While waterless urinals were not deemed
appropriate for a school setting, the 0.5 LPF urinals installed onsite use a fraction of the water of typical
urinals. Low-flow lavatories were also specified throughout the school. The sinks in the classrooms have
a 5.7 LPM flow rate, which is a compromise between water efficiency and functionality e.g. a 1.3 LPM
faucet in a home economics classroom would make filling pots with water inconvenient.
Required
Phase: Construction
The fundamental commissioning authority for this project was engaged by the project owner, and
ensured that the owners design intent was followed throughout the construction documents. The CxAs
thorough review of the construction documents noted that the specified air system motors did not meet
the owners energy use requirements, so the plans were amended before the project was tendered,
saving time and money.
Prerequisite 2: Minimum Energy Performance
Required
Credit 1: Optimize Energy Performance
6 Points
Responsibility: Energy Engineer
Phase: Design
With energy efficiency being a driving factor in the projects design, the energy engineer pushed for
enhancements to the building envelope, efficiencies in the mechanical system, building lighting design
and power densities, and process energy consumption. During fit-up, the school board purchased
Energy STAR compliant office and computer equipment. This resulted in a 48% savings in energy usage
compared to the Model National Energy Code of Canada for Buildings 1997 (MNECB) reference building.
The project was also able to successfully meet the requirements of NRCans ecoENERGY Validation of
New Building Designs program.
Resources: Best practice measures regarding assemblies, among other building issues, can be found
online at www.buildingscience.com
Clean wood was separated from other recyclables and construction waste.
Structural components such as steel and concrete may contain large amounts of recycled and regional content.
Pathway Interruption: Areas where fireproofing was being spray applied were
separated from areas with other ongoing work.
Scheduling: The walls were primed and painted before porous materials such as ceiling tiles were
installed. Air handling units were not operated during construction.
Credit 4.1: Low-Emitting Materials Adhesives & Sealants
1 Point
Responsibility: Contractor
Phase: Construction
The adhesives and sealants used on this project conform to the VOC content limits of the South Coast
Air Quality Management District (SCAQMD) Rule #1168.
Documentation: It is critical to stress the importance of meeting the VOC limits listed in the Reference
Guide/ Rule #1168, so provide a list of the thresholds in the project specifications. A material
information sheet provided in the front-end matter of the specification will provide an area for the
contractor to fill out the VOC category/limit and content of the products.
Resources: Many adhesives and sealants fall under more than one VOC limit category, so a quick check
of the SCAQMD Rule #1168 (http://www.aqmd.gov/rules/reg/reg11/r1168.pdf) will allow the most
accurate and stringent category to be applied.
Credit 4.2: Low-Emitting Materials Paints & Coatings
1 Point
Responsibility: Contractor
Phase: Construction
All of the paint used in SWS contained no VOCs, and while primers and gym floor coatings contained
VOCs, the content was well below the VOC limit prescribed by LEED.
Resources: As a result of market demand, nearly all manufacturers produce low-VOC or VOC-free
interior coatings. The Master Painters Institute has created an index of environmentally friendly paints,
and coatings, which is constantly being updated: http://specifygreen.com/
Low VOC and VOC-free finishes provide a safe indoor environment for students and staff.
Innovation in Design
Credit 1.1: Sustainability Documentation
1 Point
Responsibility: Owner & LEED Consultant
Phase: Design
The creation of this in-depth case study qualifies as the active education measure required in the LEED
Reference Guide. It is intended to inform the designers of similar buildings in the future of the struggles,
successes and innovations of this project. It is intended to be available on the LEED consultants website
and to be distributed by social media. Additionally a shorter, one-page project overview/brochure
intended for a wide audience who is not necessarily familiar with LEED or the construction industry was
produced. This second document fulfils the CaGBC requirement for a passive educational material, and
was provided to the school for distribution.
Credit 1.2: Green Housekeeping Policy
1 Point
Responsibility: Owner & LEED Consultant
Phase: Design
A green housekeeping policy was written for this project. Produced by the school board and reviewed
for accuracy by the LEED consultant, it is intended to give the maintenance staff information on proper
cleaning procedures and techniques. It is supplemented by a green housekeeping plan produced by the
LEED consultant in conjunction with the schools own maintenance staff, which outlines cleaning goals,
staff training, performance standards, and approved/prohibited products.
Abandoned Credits
Although the following credits were initially pursued, they were abandoned at some point during
project. Where possible, aspects of the credit requirements were incorporated into the final building.
IEQc3.2 Construction IAQ Management Plan: Testing Before Occupancy
An error in the floor area used for the calculation of the flushout duration precluded this credit from
being achieved. While the air handling units were operated at 100% outside air, the length of the
flushout period was incorrect. With occupancy fast approaching, it was not realistic to continue with the
flushout.
IEQc7.2 Thermal Comfort, Monitoring
This credit was abandoned due to the lack of humidity sensors in some of the regularly occupied spaces,
something initially overlooked by the project team.