Sie sind auf Seite 1von 2

Construction Loads

and Cracking
Q. We’re constructing a parking garage and want to
place concrete in some interior columns by using a
forklift to carry a concrete bucket. We will be running the
the specified compressive strength, fc'. Thus, the EOR’s
requirement that you not exceed the design load is a
reasonable one if the concrete strength on the newly
forklift and loaded bucket on the newly completed elevated completed slab has reached fc'. The forms for elevated
slab. The Engineer of Record (EOR) has indicated that the slabs are usually stripped when the concrete field
slab is designed for a live load of 50 psf (3 kPa) uniform strength is 70 to 75% of fc'. Because of the construction
load or 3000 lb (1350 kg) concentrated wheel load over a schedule, most contractors choose a concrete mixture
20 in.2 (13,000 mm2) area. Also, the EOR will allow us to that reaches this level in 2 to 3 days; so by 7 days, it’s
match, but not exceed, the controlling live load as a likely that fc' will be reached. This strength level should be
construction load. We can do this with a forklift that will verified for the project before applying construction
raise the bucket to the desired height above the column by loads that equal the design service loads.
controlling the volume of concrete in the bucket so as not to The CM’s response is not compatible with that of the
exceed the live load. EOR. It’s not economical, or necessary, to avoid flexural
The Construction Manager (CM) disapproves of this cracking at design service load levels. Thus, applied
placing method and says we’ll be responsible for slab design service loads or construction loads equal to the
cracking due to construction loads that include the use of design service loads will produce visible flexural cracking
the forklift and loaded concrete bucket. We’re worried that in the slab. The EOR would be aware of this, but the CM
the CM will hold us responsible for any flexural cracking if is probably not familiar enough with design practice to
we put a forklift and loaded bucket on the slab. Are the understand that cracking is expected.
responses by the EOR and CM compatible? Also, cracking Statements in Sections R10.6.1 and R10.6.4 of the
caused by drying shrinkage, thermal contraction, or both is Commentary for “Building Code Requirements for
common but we fear this cracking too will be attributed to Structural Concrete (ACI 318-08)”1 indicate that visible
our use of the forklift for placing concrete. How can we flexural cracking should be expected:
protect ourselves against claims by the CM that we are “R10.6.1 — Many structures designed by
responsible for repairing all cracks in the elevated slab? working stress methods and with low steel stress
served their intended functions with very limited

A. Typically, construction loads are limited to the


design loads or less if the concrete has not reached
flexural cracking. When high strength reinforcing
steels are used at high service load stresses,
however, visible cracks should be expected,
Questions in this column were asked by users of ACI documents and steps should be taken in detailing of the
and have been answered by ACI staff or by a member or members reinforcement to control cracking. For reasons of
of ACI technical committees. The answers do not represent the durability and appearance, many fine cracks are
official position of an ACI committee. Only a published committee
document represents the formal consensus of the committee and preferable to a few wide cracks.”
the Institute. “R10.6.4 — This section was updated in the
2005 edition to reflect the higher service stresses
We invite comment on any of the questions and answers published
in this column. Write to the Editor, Concrete International, 38800 that occur in flexural reinforcement with the use
Country Club Drive, Farmington Hills, MI 48331; contact us by fax at of the load combinations introduced in the 2002
(248) 848-3701; or e-mail Rex.Donahey@concrete.org. Code. The maximum bar spacing is specified
directly to control cracking. For the usual case of

Concrete international / january 2010 75


beams with Grade 60 reinforcement and 2 in. Shrinkage and temperature cracking aren’t related to
clear cover to the main reinforcement, with fs = the applied design service loads or to construction
40,000 psi, the maximum bar spacing is 10 in. loads. Such cracking should be expected regardless of
Crack widths in structures are highly variable. construction loading. Section 7.12.2 of ACI 318-08
In Codes before the 1999 edition, provisions were mandates the required ratios of shrinkage and temperature
given for distribution of reinforcement that were reinforcement area to gross concrete area that are
based on empirical equations using a calculated needed to hold crack widths to an acceptable level. You
maximum crack width of 0.016 in. The current can protect yourself against claims by the CM that you
provisions for spacing are intended to limit are responsible for repairing all cracks in the elevated
surface cracks to a width that is generally slab by citing and discussing the information provided
acceptable in practice but may vary widely in a in this Q&A, and perhaps by including the EOR in
given structure. the discussions.
The role of cracks in the corrosion of reinforce-
ment is controversial. Research shows that References
corrosion is not clearly correlated with surface 1. ACI Committee 318, “Building Code Requirements for
crack widths in the range normally found with Structural Concrete (ACI 318-08),” American Concrete Institute,
reinforcement stresses at service load levels. Farmington Hills, MI, 2008, 465 pp.
For this reason, the former distinction
between interior and exterior exposure has Thanks to S.K. Ghosh, S.K. Ghosh Associates, Inc.,
been eliminated.” Palatine, IL, for reviewing the answer to this question.

2010 Honors and Awards


Program Nominations
The American Concrete Institute is seeking your nominations
for the 2010 Honors and Awards Program! Nominations are
now being accepted for ACI’s Honorary Member and Fellow
of the Institute honors as well as for ACI’s personal awards
for individual or organizational merit and the Young Member
Award for Professional Achievement.

To provide a nomination for an ACI honor or award, go to


www.concrete.org and click on About ACI and then Honors
and Awards to choose an honor or personal award you wish
to nominate an individual or organization for. Nomination
forms are available under each individual award category as
downloadable Word documents.

If you have any questions regarding the nomination process,


please contact Diane Pociask at Diane.Pociask@concrete.org.
Please submit your nominations by February 15, 2010.
Nominations for Fellow of the Institute must be submitted
by May 30, 2010.

76 January 2010 / Concrete international

Das könnte Ihnen auch gefallen