Beruflich Dokumente
Kultur Dokumente
and Cracking
Q. We’re constructing a parking garage and want to
place concrete in some interior columns by using a
forklift to carry a concrete bucket. We will be running the
the specified compressive strength, fc'. Thus, the EOR’s
requirement that you not exceed the design load is a
reasonable one if the concrete strength on the newly
forklift and loaded bucket on the newly completed elevated completed slab has reached fc'. The forms for elevated
slab. The Engineer of Record (EOR) has indicated that the slabs are usually stripped when the concrete field
slab is designed for a live load of 50 psf (3 kPa) uniform strength is 70 to 75% of fc'. Because of the construction
load or 3000 lb (1350 kg) concentrated wheel load over a schedule, most contractors choose a concrete mixture
20 in.2 (13,000 mm2) area. Also, the EOR will allow us to that reaches this level in 2 to 3 days; so by 7 days, it’s
match, but not exceed, the controlling live load as a likely that fc' will be reached. This strength level should be
construction load. We can do this with a forklift that will verified for the project before applying construction
raise the bucket to the desired height above the column by loads that equal the design service loads.
controlling the volume of concrete in the bucket so as not to The CM’s response is not compatible with that of the
exceed the live load. EOR. It’s not economical, or necessary, to avoid flexural
The Construction Manager (CM) disapproves of this cracking at design service load levels. Thus, applied
placing method and says we’ll be responsible for slab design service loads or construction loads equal to the
cracking due to construction loads that include the use of design service loads will produce visible flexural cracking
the forklift and loaded concrete bucket. We’re worried that in the slab. The EOR would be aware of this, but the CM
the CM will hold us responsible for any flexural cracking if is probably not familiar enough with design practice to
we put a forklift and loaded bucket on the slab. Are the understand that cracking is expected.
responses by the EOR and CM compatible? Also, cracking Statements in Sections R10.6.1 and R10.6.4 of the
caused by drying shrinkage, thermal contraction, or both is Commentary for “Building Code Requirements for
common but we fear this cracking too will be attributed to Structural Concrete (ACI 318-08)”1 indicate that visible
our use of the forklift for placing concrete. How can we flexural cracking should be expected:
protect ourselves against claims by the CM that we are “R10.6.1 — Many structures designed by
responsible for repairing all cracks in the elevated slab? working stress methods and with low steel stress
served their intended functions with very limited