Beruflich Dokumente
Kultur Dokumente
Distributed Generation:
Distributed Generations are parallel and stand-alone electric generation units located
within the electric distribution system at or near the end user.
competitive landscape for power generation and has opened the transmission system to
access. A significant shift in the U.S. regulatory system began with the Energy Policy Act
(EPAct) of 1992, which requires interstate transmission line owners to allow all electric
generators access to their lines. Many states today are at various stages of electric utility
deregulation.
Utility deregulation is one reason for the high level of interest in Distributed Generation.
Other benefits associated with distributed generation
Reliability
Power Quality
Transmission Benefits
Environmental Benefits
Some well known types of Distributed Generation
Fuel Cells
Micro turbines
Wind farm
Photovoltaic Cells
Internal Combustion Engine
Processes that would cause sizeable financial losses if power outages occurred.
Power outages cause loss of quality control in batch processesfound at
2
Equipment and processes for which operation is not time-critical. Operating this
type of equipment, such as a cooling system with a large, cool storage tank, can
be deferred to off-peak times; switched to an alternate source, such as an engine
generator; or switched to an alternate fuel, such as an electric heating system with
fuel-oil backup.
There are many ways to increase the reliability of power. Redundant power supplies do
not always improve reliability. If two redundant feeders supply power to an industrial
facility but originate at the same utility substation and are carried on the same set of
power poles, reliability will be lower than if they originate at separate substations and
travel to the site on different sets of power poles. The problem with redundant feeders
carried on the same set of poles is that a single-point failure (e.g., a weather-related event,
pole fire, or traffic accident) could cause simultaneous outages on both sources.
To improve power reliability by installing standby generation, uninterruptible power
supplies (UPS), flywheels, or fuel cells.
Reliability is the most important feature of electric power distribution system.
Quantification of distribution system indices is the best indices of whether the system
with distributed generation has increased reliability or not.
The following indices are generally used by utilities (IEEE standard 1366, 2001) to
measure the reliability.
System Average Interruption Duration Index (SAIDI):
SAIDI
CAIDI
SAIFI
CAIFI
The following is a short example taken from [7]. The system is a two 22 KV feeders as
the main incoming feeders in the station, followed by two 10 MVA, 22KV/11KV
transformers. Both the transformers share the total load of about 2 MW with
around15000 customers
Customer 327
Customer 220
System without DG
Customer 327
Customer 220
System with DG
If there is a fault on feeder 1 all 327 customer of society 1 attached to it get affected, if
the fault leads to sustained interruption then there is no alternate feed is for these
customers. In such situations a strategically placed DG will be able to take care of all
these 327 customers of society 1 in the event of fault in feeder 1, the same will be true in
the event of fault in feeder 2 catering to 220 customers of society 2.
Total no of
customer
interruption
Feb-03
Aug-03
Dec-03
2020
6106
5012
Feb-03
Aug-03
Dec-03
CAIFI
Without
DG
1
1.409
1.02
Sum
of
interruption
duration in
minutes
74537
241012
66983
With DG
1.194
1.523
1.09
No of affected customers
Total no of customers
served
Without
DG
2018
4334
4916
Without
DG
12336
15101
15497
With
DG
12663
15428
15824
SAIDI
Without
DG
6.042
15.96
4.322
With
DG
5.886
15.62
4.233
SAIFI
Without
DG
0.163
0.404
0.323
With DG
1691
4007
4589
With DG
0.159
0.396
0.316
The above results show that by optimally placing DG, the reliability indices have
improved. The improvement may have been significant in the case of DG supplying a
larger part of the network.
Power Quality Power Quality of any power system can be judged by the voltage profile
and line losses. The index VPII and LLRI gives the result of benefits of the system with
DG in comparison to system without DG.
[4]
The above fig shows the single line diagram of 12 bus system used to obtain VPII and
LLRI. The system consists of three conventional generators at bus 1, bus 5 and bus12
with ratings of 1.0, 0.75 and 0.625 respectively. Total load of 2.013 pu located unevenly
on every bus is assumed. The resistance and reactance of all the distribution and
transmission lines are assumed to be 0.000625 pu/km and 0.000375 pu/km. The lengths
of the distribution lines are as below
[4]
VPw / DG
VPwo / DG
VP Vi Li ki
With
i 1
k
i 1
The weighting factors are chosen based on the importance and criticality of different
Loads
[4]
7
To study the impact four sets of bus weighing factor set 1 through 4 as listed above were
selected. The results thus obtained are shown below.
[4]
The VPII for all the four cases have value greater than 1 showing the improvement of
VPII in comparison to system without DG. The VPII exhibits the highest value under
weighting factor set 1(equal weights). With weighting factor set 4(importance given to
high load buses), VPII has the lowest value, this is due to the fact that voltages at high
load buses before employing DG(base case) are relatively high as compared to low load
buses.
D.G rating plays a significant role in determining VPII. As DG rating increases, so does
VPII
LLRI
LLw / DG
LLwo / DG
2
LLw / DG I Ai
Ri Di
i 1
LLwo / DG I Li2 Ri Di
i 1
I Ai
is the per unit line current in distribution line i, with the employment of DG
is the per unit line current in distribution line I, without the employment of DG.
[4]
The above result of the simulation of the 12 bus system shows that DG significantly
reduces the electrical line losses. The rating location and operating power factor of DG
are all very important contributing factors in determining the amount of line-loss
reduction. However higher DG penetration cannot always guarantee lower line losses
transmission line can prove economical to the utility. Utilities are already installing DG
for large stores, factories, Prisons, recreational areas and remotely located resort
complexes. These are usually large internal combustion generators. On the other hand,
the utilities will not get any benefit if a new large customer builds its own generation to
meet its own energy demand but intends to lean on the utility for back up power
especially at time of peak. In that instance, the utility may still have to reinforce its
transmission or distribution facilities to serve the customers peak demand.
Environmental Benefits:
The quantification of environmental benefits of any system with distribution generation
in comparison to the system without distributed generation can be obtained by EIRI
EIRI
i
PE
PE
iw / DG
iwo / DG
PE iwo / DG ( EG ) j ( AE ) ij
j 1
j 1
k 1
MWh
( AE)ik is the amount of emission of ith pollutant for the kth DG power plant per MWh of
energy generated
In reality, power plants emit many pollutants into atmosphere. Thus, it is useful to define
a composite index to include all the major pollutants. The index can be formulated as
NP
EIRI ( EI ) i ( EIRI ) i
i 1
With 0 ( EI ) i 1
NP
And
( EI )
i 1
Where (EI)i is the weighting factor for the ith pollutant and NP is the total number of
pollutants of interest.
10
[4]
The result of simulation includes only three major ones (CO 2, SO2, NOx). It is assumed
that all the pollutants are equally weighted. The result shows that DG reduces pollutant
emissions. The EIRI also depends on rating and locations of DG.
Proper Planned and operated DG can provide consumers and society a wide variety of
benefits,
including
economic
saving,
reliability
and
improved
environmental
11
12
INTRODUCTION
The cogeneration of heat and power (CHP) is a method of production whose use of fuel
has a dual effect: the simultaneous generation of heat and power. Plants of this type are
substantially more efficient than those engaged in the separate production of heat and
power, and have a significantly lower impact on the environment (e.g. greenhouse gas
emissions). Moreover, these generating plants are usually located closer to users, which
reduces losses that occur during electricity transmission. The cogeneration of heat and
power will be an important factor in ensuring reliability of energy supply, reducing
greenhouse gas emissions and meeting requirements for increased energy efficiency.
Despite its clearly defined advantages, cogeneration still requires a certain level of
support, which must be provided by the state, if it is to be competitive on the market. The
proper form and level of support is key to the successful development of cogeneration,
which also has wide multiplying effects on the economy, such as an increase in
competitiveness, reliability of energy supply, the creation of new jobs and the
achievement of more balanced economic development.
Appropriate determination of the reference costs of electricity is the first and most crucial
step in determining the required level of support for cogeneration. The methodology for
determining the reference costs must be as objective and transparent as possible.
PREMISES FOR preparation OF THE METHODOLOGY
In preparing a methodology for calculating the reference costs for the production of
electricity (RCE) through cogeneration, we shall proceed from EU legislation and
documents in the area, the guidelines for the allocation of environmental aid, to which
support for cogeneration and reduction in greenhouse gas emissions belong. The
regulations and guidelines are as follows:
schemes, we have used similar approaches and the same methodological premises as far
as possible and where appropriate. This will make it easier to compare and implement
both support schemes. The premises of the methodology for determining RCE are the
same for CHP and RES.
The basic principle of the allocation of support to eligible electricity producers is that
support may be allocated only if the costs of electricity production in these generating
plants exceed the price of electricity from these plants on the open electricity market. For
determining the price of electricity from these plants on the market, the costs of
electricity production in individual types and size classes of generating plant must be
calculated.
In compiling the RCE, we shall pay due regard to the following points of departure:
14
Methodology
The methodology for determining RCE is based on a determination of the overall annual
costs of operation of CHP generating plants, which are in turn based on the following
technological and operating parameters, variables, cost categories and revenues:
1.
=
annual
electricity
generated
= installed power (MWel) * annual operating hours (h)
(MWh)
15
Since the size of a CHP generating plant has an important effect on the method of
operation, and above all on the specific investment costs involved, it makes sense, from
the point of view of determining the level of support, to introduce size classes that are at
least typical and for which typical specific investment and other costs can be determined.
16
CHP generating plants are classified by size/total nominal electrical power into 6 size
classes, as shown in Table.
Size classes of CHP generating plants
Size class
1.
Micro
2.
Small-scale
3.
Medium-sized lower
4.
Medium-sized higher
5.
Large lower
6.
Large higher
Types of fuel
CHP generating plants are divided into two groups in terms of the fuel source used:
1. fossil fuels (all fuels), where the reference energy product is natural gas
2. wood biomass
The RCE for CHP generating plants using fossil fuels are determined with reference to
the costs of use of natural gas, which is the fossil-based energy product with the lowest
specific emissions of greenhouse gases. The RCE thus obtained are also used for CHP
generating plants using other fossil-based sources if they achieve specific CO 2 emissions
in electricity production of less than 600 kgCO2/MWhel, in accordance with the
methodology presented here.
Only those plants that use wood biomass as their input fuel source are classified as CHP
generating plants using wood biomass; all other CHP generating plants using RES are
dealt with by the RCE methodology for the production of electricity from RES.
Determination of specific emissions of CO2 in electricity production
Specific emissions in the production of electricity by a CHP generating plant are
determined on the basis of the following equation:
SESPTE = 1 / IzkEl * EFg * 3.6 PT/PEl * 200
where:
SESPTE
IzkEl
EFg
PT
PEl
200
18
Cogeneration technologies
All technologies referred to in Directive 2004/08/EC are included in the treatment of
high-efficiency cogeneration units:
1. combined cycle gas turbines with heat recovery;
2. steam backpressure turbines;
3. steam-condensing extraction turbines;
4. gas turbines with heat recovery;
5. internal combustion engines;
6. steam engines;
7. microturbines
8. Stirling engines;
9. fuel cells;
10. engines with organic Rankine cycles;
11. any other type of technology in CHP.
For mature market technologies (17), RCE are determined for selected representative
technologies and typical generating plants by individual size class and for both groups
with regard to type of fuel used.
For all other technologies (811), RCE are determined individually, on the basis of
the prescribed application and in accordance with this Methodology.
Representative CHP technologies for CHP generating plants using fossil fuels
Representative technologies have been determined for individual classes with reference
to the current state of cogeneration technology and the data on the most common cases of
use in Slovenia and the EU, and are shown in Table.
The table also gives the nominal electrical power for typical sizes of CHP generating
plant operating in pure cogeneration mode by individual size class for which RCE are
determined.
Representative technologies for CHP generating plants using fossil fuels
Size class
1
.
2
.
3
.
4
.
5
.
6
.
Representative technology
less than 50 kW
less than 1,000
internal combustion engine
kW
0.005
15 MW
525 MW
2550 MW
50200 MW
0.5
10
40
150
19
The internal combustion engine is the predominant technology for CHP generating plants
for the first three size classes (up to 5 MW), where small gas turbines appear only
exceptionally (where process steam is required). Available data in Slovenia indicates that
no other technologies are used in newer CHP generating plants (i.e. those less than 10
years old) in this size class, except for gas engines.
In the upper half of the 525 MW size class, there is mainly an overlap between the use
of gas turbines with heat recovery and combined cycle with gas turbine. Plants with a
larger number of gas engines are also possible, and are placed in this group because of
their power. Since the largest number of new CHP generating plants for process purposes
in industry can be expected in this size class in the future, where the gas turbine is the
most suitable technology, this technology was selected as representative.2 Slovenia
currently has only one new CHP generating plant, with four gas engines, classified in this
size class. Several feasibility studies have been drawn up for units with gas turbines and
combined cycles in industry.
Owing to its fairly high efficiency levels, the combined cycle with gas turbine and heat
recovery is a representative and priority technology for both of the largest classes of CHP
generating plant.
Representative CHP technologies for CHP generating plants using wood biomass
Steam technology, which is based on the burning of wood biomass (chips) on grates in
steam boilers, steam engines and steam turbines (steam backpressure or steam
condensing), is still the most common mature and established market technologies for
cogeneration using wood biomass. For this reason, this technology was selected as
representative, as shown in Table.
There is currently no available technology established on the market (the most promising
being the Stirling engine) for micro CHP generating plants; individual treatment is
therefore envisaged for this size class (RCE are not determined).
The volume of heat consumption in Slovenia means that we do not anticipate the arrival
of CHP generating plants using wood biomass with a nominal power of over 50 MWel.
Reference costs for the largest (6th) size class are therefore not determined.3
Representative technologies for CHP generating plants using wood biomass
Size class
1
.
2
.
3
.
4
.
5
.
6
.
/
less than 50 kW
less than 1,000 Steam engine and boiler (gratekW
fired)
15 MW
525 MW
/
1
5
2550 MW
50200 MW
Representative technology
25
50
2
3
20
Representative
technology
PEl (MWEl)
IzkEl
IzkT
Gas
engine
0,005
27%
63%
Gas
engine
0,5
38%
47%
Gas
engine
3
40%
42%
Gas
turbine
10
31%
48%
5
Combined
cycle with
gas turbine
40
38%
42%
6
Combined
cycle with
gas turbine
100
42.5%
40.0%
1
/
Steam
engine
0,5
12%
Steam
turbine
5
17%
Steam
turbine
20
27%
Steam
turbine
35
28%
6
/
21
IzkT
71%
66%
58%
56%
period)
Companies generally opt for the prescribed or lower calculation rate, since by doing
so they ensure that the calculated depreciation is treated entirely as expenditure for
tax purposes. This does not mean that the company cannot calculate depreciation
under the lower rate; however, in this case, depreciation costs may only form part
of costs for tax purposes at the end of the year up to the level or rate prescribed by
the Act.
The lifetime of most CHP generating plants is around 15 years. The share of the
value of built facilities and land in the entire investment is usually comparatively
small (minimal in the case of installation into existing facilities or compact
containers, which require minimal construction interventions) and usually comprise
4
22
up to 10% of the entire value of the investment. The share of the value of
equipment is between 50 and 70% of the total investment value. Taking into
account the prescribed maximum permitted depreciation rate on the given shares of
investment costs, the average depreciation period of CHP generating plants is
around 10 years.
Discount rate
In determining the RCE, a 12% discount rate is used for evaluation of the annual capital
costs. This rate is based on the following premises:
1. Required return on own invested funds: 20%
This rate of return reflects current conditions in Slovenia, where the returns
demanded by investors on account of the possibility of production being moved to
other countries are relatively high, the cogeneration market itself is not yet fully
developed and, at the same time, the returns achieved from investment in the
basic activity reach the given rate of return.
2. Loan costs: 6.5%
An assessment of capital costs is based on the Euribor interbank interest rate,
which fluctuated around the 4.7% mark in 2008 on the annual level, and the
average margin of 1.8%, which includes all costs of approval, insurance and
intercalary interest prior to the commencement of repayment of a loan with a 10year repayment period. The value of the loan costs used is also in line with the
fixed interest rate which was offered by banks for comparable loans with a
repayment period of 10 years at the end of 2008.
3. Structure of investment funds:
The envisaged structure of funds for investment is shown in Table 6, where the
ratio between own funds and external sources of financing (loans) is 40:60.
Structure of envisaged investment funds and calculation of the discount rate
Funds
Own
Loans
Total discount rate
Return/inter
est
20%
6,5%
12%
Share
40%
60%
Taking into account the required returns on own funds and loan interest rates, the
total required return is 12%, which is used as the discount rate in economic
calculations of cogeneration operations and determination of the level of support.
Calculation of the required return is based on a calculation of the weighted average of
capital costs (WACC), which is calculated using the following equation:
WACC = wLS * rLS + wKR * rKR = 0.4 * 20% + 0.6 * 6.5% = 12%
23
where:
wLS
wKR
rLS
rKR
The Community Guidelines on State Aid for Environmental Protection outline the
premises for determining the discount rate; they allow operating aid to cover the
difference that arises between the production costs of electricity from cogeneration and
the market price of electricity. The Guidelines stipulate that production costs also include
investment depreciation costs and normal return on capital. However, they do not explain
what the value of normal return is. In practice, every country should decide itself, when
setting up the support scheme, what the normal return is.
In economic theory, normal return on funds for risk-free investments is between 7 and
10%, while normal return for more risky investments is between 15 and 25%.
Investments in CHP may not be classified either as risk-free investments or investments
with high risk, and we cannot ignore these two facts:
(1) that despite the certain level of security offered by the existence of the scheme
itself, which guarantees investors coverage of the difference between production
costs and market price, the CHP market remains an undeveloped market, and that
market mechanisms (applying to suppliers of equipment and services, as well as
to electricity production itself) do not operate according to the laws characteristic
of developed markets;
(2) CHP technologies are entering a more mature phase in relation to conventional
methods of electricity production, but the gap is still considerable, which presents
comparable additional risks.
Despite the existence of the support scheme for the production of electricity through
CHP, which will significantly reduce the price risk on the energy market, there remains a
large risk in relation to consumption of heat. This is particularly pronounced in industrial
projects, where heat consumption at the location is dependent on the future production
process at the location, which in times of economic uncertainty constitutes a large
uncertainty and risk for investors. If it wishes to ensure a sufficiently high level of
interest in investment on the part of private investors, the state must take this risk into
account when setting the discount rate, which brings investors a normal return on the
funds they have invested and covers the potential risk.
In times of economic crisis, guaranteeing a suitable return on environmental investment
funds is of even greater importance, above all because, by promoting investments in CHP,
the state is actively influencing the restructuring of the economy, indirectly promoting the
use and development of new technologies with high added value, achieving positive
effects on the environment, employment and reliability of energy supply, and reducing
dependence on imports.
Investment costs
Investment costs include the entirety of the investment costs for implementation of a
CHP project. They are defined as typical costs5 for the selected technology and the size
5
24
of the CHP generating plant by size class of technology and expressed as specific
investment costs in relation to installed electrical power (/kWel).
Investment costs include the following costs:
purchase or leasing of land
purchase of machinery and electrical equipment
execution of required construction works
costs of construction, start-up and tests
costs of connection to the grid
costs of project design and licence acquisition
The specific investment costs of CHP generating plants using fossil fuels are shown in
Table 7 and of CHP generating plants using wood biomass in Table 8.
In determining RCE, the annual investment costs (An) are taken into account; these are
determined using the annuity method, where annual investment cost is calculated by
multiplying the annuity factor by the entire investment costs of the CHP generating plant,
using the following equation:
An = I0 * ar,n
where
An
I0
ar,n
where
r
is the discount rate
n
is the economic period of the project (years)
Specific investment costs for CHP generating plants using fossil fuel
Size class
Representative
technology
Gas
engine
Gas
engine
Gas
engine
Gas
turbine
5
6
Combined
cycle with Combined
gas turbine6 cycle with
gas turbine7
25
PEl (MWEl)
Specific
investment
costs (/kWEl)
0.005
0.5
10
40
100
2,900
1,400
1,100
1,000
1,200
1,100
Table 8: Specific investment costs for CHP generating plants using wood biomass
Size class
Representative
technology
PEl (MWEl)
Specific
investment
costs (/kWEl)
Steam
engine
0.5
Steam
turbine
5
Steam
turbine
20
Steam
turbine
35
4,500
3,500
2,500
2,000
Labour costs:
o number of employees required for operation of the CHP generating plant8
o annual cost of employment: 25,000 per employee 9
The annual operating costs are calculated using the following equation:
Operating costs (EUR) =:
= Electricity
(EUR/MWhEl)
produced
(MWh)
Specific
maintenance
cost
26
4
Gas
turbine
10
5
Combined
cycle with
gas turbine
40
6
Combined
cycle with
gas turbine
100
Representative
technology
PEl (MWEl)
Maintenance
costs
(/MWhel)
No.
of
employees
Insurance and
other costs
Gas
engine
0.005
Gas
engine
0.5
Gas
engine
3
15
0.5
15
40
1.5% of investment
Representative
Steam
technology
/
engine
PEl (MWEl)
0,5
Maintenance
costs (% of
investment)
2%
No.
of
employees
1
Operating
costs
0.8% of investment
Insurance and
other costs
1.2% of investment
Steam
turbine
5
Steam
turbine
20
Steam
turbine
35
2%
2%
2%
12
15
Fuel costs
When determining RCE, fuel costs for CHP generating plants are based on forecasts of
the reference market prices of energy drawn up by the Energy Agency and on the price
models of the methodology for determining RCE.
27
The annual fuel costs are calculated using the following equation:
Annual fuel cost (EUR) = Fuel consumption (MWh) * Price of fuel (EUR/MWh)
2.
3.
network charge:
transmission network
distribution network
4.
5.
This has varying effects on the final price according to the size of the CHP generating
plant.
The natural gas price for CHP generating plants is determined, for all six size classes, on
the basis of the calculation model, which includes the above-mentioned components. As
shown in Table 11 and the equation below:
Components of the model for determining the price of natural gas according to CHP
size classes
Siz
e
cla
ss
CB
pric
e
Suppleme
nt (fixed
part)
1.
CB
2.
Network
charge
(transmissi
on)
Network
charge
(distributio
n)
CO2
coupo
ns
Environmen
tal tax on
CO2
SF1
NCD1CDK6
from
2013
Yes
CB
SF2
NCD2CDK12
from
2013
Yes
3.
CB
SF3
NCT3CPK3
from
2013
No
4.
CB
SF4
NCT4CPK5
from
2013
No
10
11
28
5.
CB
SF5
NCT5CPK7
from
2013
No
6.
CB
SF6
NCT6CPK7
from
2013
No
o Acts Determining the Network Charge for the Natural Gas Distribution
Network in the geographical areas of the city municipalities of Maribor,
Celje and Ljubljana, and the areas in which the activity of the natural
gas distribution network system operator is performed by Adriaplin
d.o.o. The model uses the average of the calculated network charges for
all the abovementioned areas:
12
29
Electrical
power of
CHP
generatin
g plant
Oper
ating
hours
%
h/a
27.0% 5,500
Annual
Maxi
consumpt mum
ion
daily
consu
mptio
n
Sm3/d
3
Sm /year ay
10,759
47
IzkEl
Maxi
mum
power
up to 50 kW
50100 kW
0.500
38.0% 5,500
764,455
3,336
1,316
15 MW
40.0% 5,500
4,357,394
19,014
7,500
Micro
Smallscale
Mediu
m-sized
1
Mediu
m-sized
2
MWEl
0.005
525 MW
10
31.0% 5,500
Large 1
40
38.0% 5,500
Large 2
up to 50 MW
up to 200
MW
100
42.5% 5,500
18,741,48
1
61,156,41
2
136,702,5
68
81,781
266,86
4
596,52
0
32,258
105,26
3
235,29
4
1
2
3
kW
19
30
In order to make it easier to take a model-based approach, the final price of natural gas is
made up of the variable price (CB) and the fixed supplement, which included all other
components of the price, as shown in Table .
Composition of the final prices of natural gas by CHP generating plant for 2009
EUR/S
m3
VARIABLE
PRICE
SUPPLEMENT Di
Size
class
CB price
Supplem
ent (fixed
part)
1.
0.240
2.
Network
charge
(transmis
sion)
Network
charge
(distributi
on)
CO2
coupons
Environ
mental
tax on
CO2
0.072
0.117
0.0238
0.240
0.059
0.100
0.0238
3.
0.240
0.040
0.023
4.
0.240
0.035
0.021
5.
0.240
0.030
0.019
6.
0.240
0.025
0.019
Final prices of natural gas by size class of CHP generating plant for 2009 (EUR/Sm 3)
Size
class
VARIABLE
PRICE
SUPPLE
MENT Dj
TOTAL
EUR/Sm3
EUR/Sm3
EUR/Sm3
EUR/MW
h
1.
0.240
0.213
0.453
47.8
2.
0.240
0.183
0.423
44.7
3.
0.240
0.063
0.303
32.0
4.
0.240
0.056
0.296
31.2
5.
0.240
0.049
0.289
30.6
6.
0.240
0.044
0.284
30.1
31
Figure 1: Final prices of natural gas by size class of CHP generating plant for 2009
(EUR/Sm3)
In the event of pronounced changes in formulation of the natural gas price or the
introduction of new taxes or significant changes thereto, the methodology is appropriately
adjusted to the new conditions, with the aim of achieving more objective determination of
natural gas prices.
Prices of wood biomass
The reference starting market price of wood biomass is determined on the basis of
statistical data on quantity [kg] and the export value of chipboard [EUR], woodchips and
similar, i.e. for conifers. The Energy Agency publishes the reference starting market price
of wood biomass for the next year [EUR/kg] in its forecast.
The final basic price of wood biomass CLB (green wood chips) is the same for all size
classes and comprises two parts:
1. reference starting market price [EUR/kg]
2. additional costs of handling, storage and transport
Pursuant to an assessment of the state of the wood biomass market in Slovenia and
expectations for the next year, the final basic price of wood biomass C LB for 2009 is
23/MWh.
Value of heat from cogeneration
Useful heat is the main advantage of cogeneration and constitutes an operating revenue
which, when determining reference prices in accordance with the guidelines on
environmental state aid, must be appropriately included in the calculation.
The actual value of heat varies greatly between plants, particularly with regard to:
2.
where:
VT(i)
is the value of heat for year i
CZPj(i)
is the price of natural gas in year i with regard to the size
class of the CHP generating plant
CLB(i)
is the price of wood biomass for year i
0.95 and 0.86 are the efficiencies of separate production of heat
The used values of heat for 2009 with regard to the price of natural gas and wood
biomass are shown in Table 15.
The annual revenue from useful heat is calculated according to the following equation:
Revenue from heat (EUR) = Useful heat (MWh) * Value of heat (EUR/MWh)
1
50.3
26.7
2
47.0
26.7
3
33.7
26.7
4
32.9
26.7
5
32.2
26.7
6
31.6
26.7
33
Calculation OF RCE
On the basis of the input parameters presented and the methodology for calculation of
RCE (EUR/MWhel), we can summarise the methodology using the following equations:
RCE = [COSTS (investment + M&O +fuel) REVENUES (heat)] / ELECTRICITY
RCE are divided into two parts:
1. FPRC fixed part (/MWhel):
FPRC = [COSTS (investment + M&O)] / ELECTRICITY
2. VPRC variable part (/MWhel):
VPRC = [COSTS (investment + M&O +fuel) REVENUES (heat)] /
ELECTRICITY
The purpose-built tool RSEE_SPTE.xls (MS Excel environment) is used for the
calculation and determination of RCE.
The calculations of RCE for 2009 for CHP generating plants using fossil fuels and wood
biomass are presented below.
CHP using fossil fuels
Figure 2 and Figure 3 show the structure of RCE for CHP generating plants using fossil
fuels with up to and over 4,000 operating hours a year. The only difference between the
two groups of plants is in investment costs, which for the second group are lower by 35%
for longer operating hours. There are no differences in respect of the other specific costs
and revenues.
A summary of the results of the calculations of RCE for CHP generating plants using
fossil fuels is shown in Figure 4. Reference costs for units with over 4,000 operating
hours are around 20% lower than for units with up to 4,000 operating hours. They are
expected to be much higher in micro units, falling to below 100/MWh up to mediumsized units, and at around 80/MWh for the largest units.
The division of RCE into fixed and variable parts is shown in Figure 5. The variable part
is fairly similar for all size classes at around 40/MWh el; the fixed part is significantly
higher for smaller size classes (80% share of RCE), and is then reduced, reaching
between 50 and 60% of total RCE.
34
Figure 6: Reference costs for cogeneration using wood biomass with up to and over 4,000
operating hours a year
CgorivaSPTE
IzkLPTop
K
The prices of CHP fuel (i.e. of natural gas and wood biomass) are, in the price
determination model, dependent on the published reference market price of fuel and
provided by the equations:
CZPj = CB + Dj
CLB = CLBRef * M
Final dependence of the VPRC on the reference market price of fuel may therefore be
written using the equation:
VPRCZP = (CB + Dj)* K
VPRCLB = (CLBRef * M)* K
We wish to tie harmonisation of VPRC to the starting value of the VPRC and the index of
the change in the reference price of the fuel, which is given for both fuels in the following
sections.
CHP generating plants using wood biomass
Since the VPRC with wood biomass is expressed as a product of the reference price of
the wood biomass and two constants, we can express the annual harmonisation of the
VPRC using the following equation:
VPRCLB (i) = ILB (i) VPRCLB(0)
where:
VPRCLB (i)
VPRCLB (0)
ILB (i)
36
CLB (i)
CLB (0)
VPRCZP (0)
IZP(i)
CB(i)
CB(0)
Dj(i)
37
1.25
1.33
1.39
1.60
1.47
1.36
D (/MWh)
22.45
19.32
6.69
5.89
5.23
4.70
N (/MWh)
28.01
25.68
9.33
9.40
7.68
6.40
The cost tables with a calculation of RCE for individual cogeneration groups are given
below.
38
initial fixed part of RCE, which is given in the decision on the allocation of
support15
In this process, the following features of CHP generating plants shall be taken into
account when determining support:
In accordance with the Decree, the fixed part of RCE for a CHP generating plant
that received any aid that could be regarded as a subsidy is reduced by the
calculated amount of that subsidy.
In accordance with the Decree on Support, the variable part of the RCE may, for
generating plants using wood biomass:
be reduced by 10% for the use of by-products and residues from the
wood-processing industry
Fixed part of the GPP equal to the fixed part of the RCE
2.
Variable part of the GPP equal to the variable part of the RCE determined
for the current year
Fixed part of the GPP does not change for a CHP generating plant for the entire duration
of the contract on guaranteed purchase and is determined in the first decision on the
allocation of support.
Variable part of the GPP is determined annually with reference to the forecast of the
reference market prices and the methodology for calculation of the variable part of RCE,
and is the same for all comparable CHP generating plants in an individual size class.
The GPPs determined for 2009 on the basis of the RCE calculated for CHP generating
plants using fossil fuels are shown in Figure 7 and for wood biomass in Figure 9 (GPP
determined only for small-scale plants).
15
39
Operating support
Operating support (OS) may only cover the difference between the RCE of the CHP
generating plant and the market price of electricity that the CHP generating plant is able
to achieve on the electricity market.
The reference market price of electricity is determined by the Energy Agency in its report
on reference market prices of electricity. The actual market price which a CHP generating
plant is able to achieve on the market depends on other additional factors:
the amount of time and method of operation of the plant (number of operating
hours, daily or band operation, etc.)
Factor B reflects these factors for individual size classes and scope of operating hours of
CHP generating plants; the actual market price that the CHP generating plant is able to
achieve on the electricity market is therefore determined using the following equation:
CElSPTE = CElRef * B
where:
CElSPTE
CElRef
The values of factor B for the 6 size classes and both groups of operating hours are
shown in Table
The actual market prices of electricity from CHP generating plants in relation to the
forecast reference market price of electricity for 2009 (EUR 65/MWh) are shown in Table
.
40
Operating
hours < 4,000
Operating
hours > 4,000
0. 85
0.90
0.88
0.92
0.93
0.94
0.93
0.94
0.96
0.97
0.96
0.97
Market prices of electricity from CHP generating plants for 2009 (EUR/MWh)
Size class
Micro (< 50 kW)
Operating
hours < 4,000
55.25
Operating
hours > 4,000
58.50
Small-scale (<1MW)
57.20
59.80
60.45
61.10
60.45
61.10
62.40
63.05
62.40
63.05
65.00
The equation below is used to determine the OS annually in relation to the calculated
RCE and the forecast reference market price of electricity:
OPj(i) = RCEj(i) - CElRef(i) * Bj
where:
OPj(i)
42