Beruflich Dokumente
Kultur Dokumente
MAIN REPORT
FINAL
PREPARED BY
PREPARED FOR
DECEMBER 2009
FOREWORD
FOREWORD
FEASIBILITY STUDIES FOR THE 16 CENTRAL IRRIGATION SYSTEMS IN
MOLDOVA PROPOSED FOR MCC FUNDING
This report presents the findings of rapid feasibility studies for the 16 Central Irrigation Systems
(CIS) in Moldova. MWH was retained by the Millennium Challenge Corporation (MCC) to
conduct these studies for the proposed rehabilitation of these existing 16 irrigation system
infrastructure that were identified by the Government of Moldova for funding from MCC. This
assignment was divided into two tasks:
Task 1 Feasibility Studies for Infrastructure Rehabilitation
Task 2 Environmental & Social Assessment of the Proposed Rehabilitation
The findings of Task 1, summarized in this report, are the result of activities undertaken over a
four and half month period between January 26, 2009 and June 19, 2009. This Feasibility Report
includes:
A Main Report
Annex 1 through 16
The findings of Task 2 are summarized in the report titled: Environmental & Social Impact
Assessment for the Proposed Rehabilitation of the 16 Central Irrigation Systems in Moldova.
Table of Contents
Table of Contents
PAGE
List of Abbreviations ...................................................................................................................... i
Executive Summary ................................................................................................................ES-1
1.0
Introduction
.................................................................................................................. 1-1
1.1 Project Background ................................................................................................. 1-1
1.2 Project Objectives ................................................................................................... 1-3
1.3 Scope of Work ........................................................................................................ 1-4
1.4 Organization of the Report...................................................................................... 1-9
2.0
3.0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
i
December 2009
Table of Contents
3.1.2
3.1.3
3.1.4
3.1.5
3.1.6
3.1.7
3.1.8
3.2
4.0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ii
December 2009
Table of Contents
4.6.3
5.0
6.0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
iii
December 2009
Table of Contents
6.2.5
6.2.6
6.2.7
6.2.8
6.2.9
6.2.10
6.2.11
6.2.12
6.2.13
6.2.14
6.2.15
6.2.16
7.0
Feasibility Level Cost Estimates for the Proposed Rehabilitation Projects ........................ 7-1
7.1 Summary ................................................................................................................. 7-1
7.2 Development of Units Cost ..................................................................................... 7-2
7.2.1
Pipe Network ........................................................................................... 7-2
7.2.2
Primary Civil Works ................................................................................ 7-3
7.2.3
Mechanical &Electrical Equipment ......................................................... 7-3
7.3
7.4
7.5
7.6
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
iv
December 2009
Table of Contents
8.3 Prevailing Assumptions Associated with Proposed Institutional Plans.................. 8-5
8.4 Risks and Remedial Actions ................................................................................... 8-7
8.5 Technical Assistance............................................................................................. 8-13
8.5.1
Technical Assistance to Apele Moldovei for Implementation of CIS
Rehabilitation ......................................................................................... 8-13
8.5.2
Expanding Technical Assistance as Part of the IMT Program .............. 8-15
9.0
Table of Contents
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
vi
December 2009
List of Tables
List of Tables
PAGE
ES-1
ES-2
ES-3
ES-4
ES-5
ES-6
Estimated Breakdown for the Unit Cost of Water for Year 2014 Assuming CIS under
WUO Management ......................................................................................................ES-17
ES-9
Estimated Breakdown for the Unit Cost of Water for Year 2014 Assuming CIS under
STI/AM Management ..................................................................................................ES-18
ES-10 Estimated Unit Cost of Water (MDL/m3) for Year 2020 & 2025 ...............................ES-19
ES-11 Planning Level Cost Estimates for WUO O&M Capacity Building ...........................ES-20
ES-12 Estimated Tariff Levels (MDL/m3) Based on Assumptions ........................................ES-26
ES-13 FIRR (2014-2040) ........................................................................................................ES-27
ES-14 Total Estimated Revenue Shortfall through 2025 Based on Current Assumptions .....ES-28
ES-15 Proposed MCC Investment for the Rehabilitation of 16 Proposed CIS ......................ES-29
1-1
2-1
2-2
2-3
2-4
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
vii
December 2009
List of Tables
2-5
2-6
2-7
2-8
2-9
2-10
2-11
2-12
2-13
2-14
2-15
2-16
2-17
2-18
3-1
3-2
Areas irrigated in 2008 within the CIS under Consideration ........................................... 3-9
3-3
3-4
3-5
3-6
3-7
3-8
3-9
3-10
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
viii
December 2009
List of Tables
3-11
3-12
3-13
3-14
3-15
3-16
3-17
3-18
4-1
4-2
4-3
Overview of Site Conditions at the 16 CIS being considered for Rehabilitation ............ 4-4
4-4
ECsw of Measured Soil Salinity and Sodicity Status at Crpinenii de Sus....................... 4-6
4-5
ECsw of Measured Soil Salinity and Sodicity Status at Chircani-Zrneti ....................... 4-7
4-6
ECsw of Measured Soil Salinity and Sodicity Status at Cahul ......................................... 4-8
4-7
ECsw of Measured Soil Salinity and Sodicity Status at Talmaza ..................................... 4-8
4-8
ECsw of Measured Soil Salinity and Sodicity Status at Suvorov ..................................... 4-9
5-1
5-2
5-3
5-4
5-5
5-6
5-7
5-8
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ix
December 2009
List of Tables
5-9
5-10
5-11
5-12
5-13
5-14
Water Source Characteristics for Tetcani & Crpinenii de Sus ..................................... 5-34
5-15
5-16
5-17
5-18
Affect Of Climate Change on the Availability of Water for the Prut River Basin
Water through Year 2040............................................................................................... 5-39
5-19
Affect Of Climate Change on the Availability of Water for the Nistru River Basin Water
through Year 2040 ......................................................................................................... 5-39
6-1
6-2
6-3
6-4
6-5
6-6
6-7
7-1
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
x
December 2009
List of Tables
Projects............................................................................................................................. 7-1
7-2
7-3
Inflation & Currency Exchange Factors used for Price Escalation ............................... 7-11
8-1
9-1
Actual O&M Expenditure between 2004-2008 (in million MDL) .................................. 9-3
9-2
9-3
STI Revenues from Irrigation & Irrigation as a Percentage of Total STI 2004-2008 ..... 9-4
9-4
Calculated Shortfall in STI Operation of the Irrigation Services between 2004-2008 .... 9-5
9-5
State Support (in million MDL) to the STI between 2004-2008 ..................................... 9-6
9-6
9-7
Chisinau STI O&M Expenditure Estimated at the Beginning of 2008 Season ............... 9-8
9-8
9-9
Estimated Breakdown for the Unit Cost of Water for Year 2014 Assuming CIS under
WUO Management ..................................................................................................... 9-14
9-10
Estimated Breakdown for the Unit Cost of Water for Year 2014 Assuming CIS under
STI/AM Management .................................................................................................... 9-15
9-11
Estimated Unit Cost of Water (MDL/m3) for Year 2020 & 2025 ................................. 9-16
9-12
Planning Level Cost Estimates for WUO O&M Capacity Building ............................. 9-21
9-13
Planning Level Cost Estimates for STI O&M Capacity Building ................................. 9-22
10-1
11-1
11-2
11-3
Total Estimated Revenue Shortfall through 2025 Based on Current Assumptions ....... 11-5
11-4
Revenue Shortfall through 2025 if Water Consumed is 50% less than Estimated Demand11-7
12-1
Proposed MCC Investment for the Rehabilitation of 16 Proposed CIS ........................ 12-1
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
xi
December 2009
List of Tables
12-2
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
xii
December 2009
List of Figures
List of Figures
PAGE
ES-1
ES-2
ES-3
ES-4
1-1
2-1
2-2
5-1
5-2
5-3
Surface Water Flow Hydrographs For The Prut And Nistru Rivers, Moldova. 5-11
5-4
Annual Flow (Million m3/year) At Hrusca Station On The Nistru River From 1968
2007.5-12
5-5
Flood Events On The Nistru River Hrusca Gauging Station, Moldova. 5-13
5-6
5-7
Annual Flow (Million M3/Year) at Ungheni Station on the Prut River from 1961
2007.... 5-15
5-8
Flood Events On The Prut River Sireuti Gauging Station, Moldova. 5-16
5-9
5-10
5-11
5-12
5-13
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
xiii
December 2009
List of Figures
5-14
5-15
5-16
5-17
5-18
7-1
7-2
10-1
Contractual Relationships.........................................................................................10-12
10-2
11-1
11-2
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
xiv
December 2009
List of Appendices
List of Appendices
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
xv
December 2009
List of Annexes
List of Annexes
(Under Separate Cover)
Annex 1:
Annex 2:
Annex 3:
Annex 4:
Annex 5:
Annex 6:
Annex 7:
Annex 8:
Annex 9:
Annex 10:
Annex 11:
Annex 12:
Annex 13:
Annex 14:
Annex 15:
Annex 16:
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
xvi
December 2009
List of Abbreviations
List of Abbreviations
ACSA
AIPRE
AM
CEE
CIS
CITES
CNFA
DWS
EMEP
EU
EURO
FAO
FAS
GDP
GEF
GIS
GoM
HMS
ICP
IFAD
IMT
IMTPSP
INECO
ISO
IUCN
IPCC
LEAP
MAC
MAFI
MCA
MCC
MDL
MECTD
MENR
MRDA
MWH
NATO
NGO
OSCE
PIU
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report - Final
i
December 2009
List of Abbreviations
RFP
SAR
SEI
SOW
STI
TACIS
TOR
UN
UNDP
UNECE
UNEP
USA
USAID
USDA
USEPA
USU
VFD
WDC
WHO
WMO
WPI
WUO
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report - Final
ii
December 2009
Executive Summary
Executive Summary
1.0 Introduction
Millennium Challenge Corporation (MCC) has been requested to assist Moldova with
transitioning to High Value Agriculture (HVA) for the purpose of increasing production
of high value-added fruits and vegetables. This is in keeping with MCCs goal of
fostering economic growth and alleviating poverty. Consistent with this goal, the
Government of Moldova (GoM) has requested MCCs assistance for the rehabilitation of
up to 16 Central Irrigation Systems (CIS).
The 16 CIS systems are supplied by surface waters contained within the Black Sea Basin,
in the watersheds of Moldovas two main rivers, the Nistru in the eastern portion of the
country and the Prut in the west. A list of the CIS considered for rehabilitation is
identified in the table below.
Table ES-1
List of 16 CIS Proposed for Rehabilitation
Prut River
Nistru River
1-1 Tetcani
3-2 Blindeti
3-6 Grozeti
4-5-1 Crpinenii de Sus
5-4 Leova Sud
11-7 Lopatna
12-3 Conia
14-2 Criuleni
14-6 erpeni
14-11 Puhceni
14-13 Rocani
17-2 Talmaza
17-3 Suvorov
6-6 Chircani-Zrneti
6-9 Cahul
* Cahul, Talmaza and Serpeni can be found under the name Masivul Cahul, Masivul Talmaza and Masivul
Suvorov, referring to the same area under irrigation command.
Figure ES-1 illustrates the location of the 16 CIS proposed for rehabilitation.
In addition to rehabilitating the CIS, MCC is also considering investing in the Irrigation
Management Transfer (IMT) program to establish and strengthen water users
organizations (WUOs) for the administration, operation, and maintenance of rehabilitated
CIS. The working premise of the MCC investment is that with the rehabilitation of the
CIS and transfer of management responsibilities to the water users (farmers), along with
providing access to on-farm irrigation equipment and market for their produce, farmers
will gradually move to more diversified crops and HVA production that will result in
increased farm incomes. This report addresses the findings of feasibility studies that is
limited to the rehabilitation of the CIS infrastructure.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
ES-1
Nistru River
1-1 Tecani
Ukraine
11-6 Jora de Jos
11-7 Lopatna
Prut River
14-2 Criuleni
12-3 Conia
3-2 Blindesti
3-6 Gozeti
14-6 Serpeni
4-5-1 Crpinenii de
sus
14-11 Pugcenii
Nistru River
Romania
14-13 Roscani
Key:
Prut River
Giurgiulesti - Danube
River port
Transnistria region
Proposed MCC road segments
Not to Scale
FIGURE ES-1
LOCATION OF THE 16 CIS
PROPOSED FOR REHABILITATION
DECEMBER 2009
Executive Summary
2.0
Table ES-2 provides an overview of the irrigation area within each CIS that is being
considered for rehabilitation.
Table ES-2
Irrigation Area within Each CIS1
CIS Rehabilitation
Area of Irrigation
Project
(Hectares-Ha)
Tetcani
1,258
Blindeti
521
Grozeti
1,018
Crpinenii de Sus
1,815
Leova Sud
963
Chircani-Zrneti
4,417
Masivul Cahul
1,930
Jora de Jos
1,165
Lopatna
506
Conia
2,800
Criuleni
677
erpeni
1,107
Puhceni
856
Rocani
682
Masivul Talmaza
Masivul Suvorov
Total
2,468
13,394
35,577
Executive Summary
Drainage System
Since, three of the CIS under consideration are located in the low plains of the Prut or
Nistru, engineering drainage systems are provided to remove excess water from the
irrigated fields. The source of this excess of water is mainly rivers (during high levels),
rainfall and irrigation. Draining excess water from the soil surface and the profile below
is necessary to maintain the water table below the root zone. This is essential for avoiding
salt accumulation around the root zone that would eventually contribute to soil salinity
conditions. Saline soils affect the crop yield of an irrigated area. The drainage systems
consist of a network of drainage canals collecting the excess of water from the fields
through which it is pumped back to either the Prut or Nistru rivers.
Pump Stations
An overview of the pump stations serving each of the 16 CIS is provided in the table
below.
Pump
Station
Table ES-3
Pump Stations Serving the 16 CIS
Irrigation
Number of Total Pump
Area
Pump
Capacity
(Ha)
Units
(lps)
SP-1
SP-1
SP-2
SP-2
313
Transit to SP-2
445
500
SR-3
SP-4
Transfer to SP-4
Transfer to SP-7
SP-4
260
SP-7
261
SP-11
SPR-12
SPR-12
SPR-12
SPR-12
Transfer
to SPR-12
389
240
240
140
NSG-1
NSP-1
Tetcani
3
2
3
2
Blindesti
3
2
1
1
2
4
Grozeti
3
3
2
2
Crpinenii de Sus
Transfer to NSP6
1
Transfer to NSP4
2
Head
(m)
330
880
330
440
105
90
105
57
380
360
180
90
105
500
63
92
90
50
120
95
660
Gravity Fed
420
360
120
139
2400
2200
92
100
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
ES-5
65
87
36
Executive Summary
Pump
Station
NSP-2
NSP-4
NSP-4
NSP-7
NSP-7
S-28
S-2
S-5
Irrigation
Area
(Ha)
Number of
Pump
Units
Transfer to NSP4
280
2
3
648
3
567
2
320
1
Leova Sud
Transfer to S-2
6
9
(all
963
missing)
Chircani-Zrneti
1980
S-1
S-6
SPD-4
Drainage
3
3
2
SPD-5A
Drainage
SPP-3A
SPP-1
SPP-2
SPP-3
SPP-1
SPP-2
SP-1
SP-2
SPP
SP
SP-1
SP-2
SP-3
S-1
2437
449
806
Drainage
675
Drainage
Drainage
235
Transfer to SP-1
100
259
Transfer to SP-2
80
278
213
Transfer to SP
358
148
986
353
Transfer to S-1
620
Cahul
4
4
2
3
3
3
Jora de Jos
2
3
2
2
2
2
2
2
Lopatna
8
2
Conia
6
6
2
3
Total Pump
Capacity
(lps)
Head
(m)
2160
230
550
415
255
26.5
61
92
89
65
1560
898
128
53-91
660
200
750
670
800
57
57
54
57
13
3500
22
880
1200
1400
700
1200
3000
57
54
17
10
21
20
220
630
110
360
500
120
140
210
75
60
95
90
195
92
53
44
468
By gravity
180
110
880
440
1100
660
57
98
14
85
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
ES-6
50
Executive Summary
Pump
Station
SP-4
NSP-1
NSP-2
NS-3
S-10
Irrigation
Area
(Ha)
578
263
459
122
Transfer to NS-3
96
S-14
Transfer to S-12
670
Transfer to S-14
437
S-17
S-18
438
418
S-20
S-22
Transfer to S-22
682
ONS-1
NS-2
Transfer NS-2
465
801
1202
Drainage
Drainage
Drainage
S-12
T-2
D-1
D-2
T-3
GNS
NSP
PNS-1
PNS-1
PNS-1
PNS-2
PNS-3
PNS-4
PNS-5
PNS-6
PNS-7
PNS-7
Transfer to NSP
Transfer to PNS1
1827
430
Transfer to PNS2
2069
939
2206
159
200
340
320
Number of
Pump
Units
Total Pump
Capacity
(lps)
Head
(m)
2
3
Criuleni
2
1
1
2
erpeni
2
4
4
2
Puhceni
3
3
Rocani
460
395
155
50
360
180
360
160
62
50
50
70
700
560
40
350
70
70
70
85
420
300
65
45
3
4
Talmaza
4
3
4
3
2
2
2
3
Suvorov
4
4
3
3
2
6
3
3
4
2
2
2
780
960
92
92
2800
660
800
1200
330
330
800
3000
5.5
70
90
90
10
10
20
20
6200
6200
2200
2200
1500
1620
710
2100
880
500
395
300
80
80
85
85
51
80
73
80
57
84
Fed by
gravity
55
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
ES-7
Executive Summary
Pump
Station
Irrigation
Area
(Ha)
Number of
Pump
Units
Total Pump
Capacity
(lps)
Head
(m)
S-1
S-2
S-2
S-2
S-3
S-3
Transfer to S-2
770
1380
Transfer to S-3
2017
737
5
4
6
4
6
3
2260
720
1290
1650
1470
600
90
57
66
40
90
68
Note: Existing pump capacities are based on best available, reliable data. This will
need to be verified prior to detailed design.
For additional details on each of the CIS, please refer to its corresponding annex.
Piping Network
The area of 35,577 ha within the 16 CIS is covered by a total of 997.68 km of principal,
secondary and tertiary pipes varying in diameter from 1000 mm to 100 mm. Pipe
materials vary from concrete, asbestos cement and steel. From the underground pipe
network the water is distributed to the field through hydrants and sprinkler equipment.
Hydrants for sprinkler equipment are spaced at 50 72 m along tertiary pipes. The
distance between tertiary pipes varies in the range between 600 to 800 m.
In-field irrigation equipment, normally of 200 400 m length fitted with sprinklers
distributes the water under pressure to the crops. Sprinkler spacing is normally 18 x 24 m
up to 24 x 24m. Design pressure at the hydrant is of 3 6 bars and at the sprinkler
nozzles are normally 2.5 - 5 bars.
Dams
Dams are currently part of three CIS: Tetcani, Crpinenii de Sus and Suvorov.
Tetcani CIS was originally designed to be supplied with water entirely from a manmade
lake impounded by a dam. The dam is a compacted clay, earth dam, 13.6 m in height and
capable of storing a volume of water of up to 930,000 m3.
Suvorov CIS is partly (4,904 ha out of the total 13,389 ha) supplied by a manmade lake
impounded by a dam, 15 m in height and can store a volume of water of up to 8,000,000
m3. This is also a compacted clay earth dam.
Crpinenii de Sus was originally designed to supply the entire irrigation area (1,815 ha)
via a man-made lake impounded by a dam. The dam is also a compacted clay, earth dam,
13.5 m in height and capable of storing a volume of water of up to 12,206,000 m3.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
ES-8
Executive Summary
Institutional Background
The CIS in Moldova are owned by the Apele Moldovei (AM), an existing governmental
entity, and its operations are managed at the regional level by 12 State Controlled
Technical Irrigation Stations (STI).
AMs principle functions are to provide the policy direction and implementation for
water resources management. Responsibility for operation and maintenance of the
systems (CIS and potable water) rests ultimately with AM although the daily operation,
tariff setting and collection, and maintenance functions are delegated to the 12 STIs.
3.0
The existing CIS infrastructure was built in the early 1960s and subsequently
rehabilitated and expanded over the years, with the last wave of rehabilitation occurring
around the late 1980s. The total area under irrigation in 2008 is provided in provided in
Table ES-4.
Table ES-4
Areas irrigated in 2008 within the
CIS under Consideration
CIS
Area Irrigated (ha) 1
Tetcani
Blindeti
Grozeti
Crpinenii de Sus
Leova Sud
Chircani-Zrneti
Cahul
Jora de Jos
Lopatna
Conia
Criuleni
erpeni
Puhceni
Rocani
Talmaza
Suvorov
Total Area
52
0
20
69
0
0
0
119
47.5
642.9
46.5
0
55
123.9
85
2,528.9
3,789.7
Discussions with AM and the respective STI provided a myriad of reasons for this
decline, ranging from dilapidated, unreliable CIS infrastructure to land fragmentation and
foreign migration that has contributed to a general decline in agricultural activities. Due
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
ES-9
Executive Summary
to limited resources AM has not been able to maintain or rehabilitate systems as required.
Based on its previous assessments, due to unfavorable locations and subsequent high
costs of pumping water, rehabilitation of some pump stations and some segments of the
pipe network were deemed unfeasible.
For additional details on the assessment of existing infrastructure please refer to Section
3.0 and the annexes corresponding to each CIS.
4.0
Rehabilitation plans for each CIS were developed based on the assessment of its existing
conditions, and the existing CISs ability to deliver the required water for HVA crop
cultivation, as recommended in the USU report and as directed by MCC. Based on these
crop water requirements, the following criteria established the basis for infrastructure
needs:
Ability for the CIS to supply a flow of 1 lps/ha (established based on MCCs
acceptance of USU recommendation);
A minimum water pressure at the hydrants of 4 bars (established based on
discussions between MCC, MCA-Moldova and Apele Moldovei);
Energy efficient systems.
In defining the infrastructure requirements for the above criteria, the following
assumptions were made:
The typical watering equipment is assumed to be Reel Hose, Hand-moving
laterals, Drip irrigation equipment or of similar kind that function at the
minimum pressure identified.
Discharge rate of the water equipment is assumed to be 20 lps.
Pressure pump stations would need to have adequate capacity to meet the 1 lps/ha
criteria.
5.0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
ES-10
Executive Summary
New pump stations at Tetcani and Crpinenii de Sus to feed the CIS directly from
the Prut River instead of their existing source, which in both cases are lakes
impounded by existing dams. In the case of Tetcani, water volumes in the lake is
not adequate to supply water at the desired capacity, while at Crpinenii, the
water in the lake was found to be highly saline and not conducive for long term
irrigation.
For additional details on the specific rehabilitation plans within each CIS, please refer to
Section 6.0 and the annexes corresponding to each CIS.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-11
December 2009
Executive Summary
8.0
Traditionally, the budget for operating and managing the CIS are prepared by each STI
using the methodology and guidelines mandated in 2007. According to this mandate,
STIs must reflect all costs for operation so that they are self supporting. This budget, in
effect, should have two components: fixed cost (operation and maintenance of the
infrastructure, or O&M Cost) and energy cost. The O&M cost and the energy cost are
identified at the beginning of the season based on estimates of total water requested by
the farmers within its service area.
The amount of water needed per farm is determined by contracts signed between the STI
and the individual farmer prior to the beginning of irrigation season each year. The O&M
cost (cost for labor & materials) is estimated at each CIS by the managing STI by
employing a formula that takes into account the total amount of water requested by all the
farmers within its service area. Energy cost, which reflects the power (electricity) needed
to pump this contracted water, is estimated by the STI based on the cost per kilowatthours (KWH) for that particular CIS.
Based on current practices, energy cost is subsidized by the government. For this reason,
the energy cost component does not show up as a cost (or expenditure) on the STI
accounting sheets for past budgets. It should also be noted that the fixed component is
also subsidized by the state (O&M irrigation service subsidy). So the STI expenditure
only identifies O&M cost not covered by energy or O&M irrigation service subsidies.
The STI expenditure is typically estimated at the beginning of the season for identifying
tariff levels for that season.
Assumptions for Estimating Future O&M Budgets
The O&M budgets for the rehabilitated CIS assume that some CIS would be online by
2014. For the purpose of consistency, the annual O&M budget has been identified for all
CIS starting with at 2014.
Since the cost of operating and maintaining the system is based on delivering the total
water required each season, the annual O&M cost will increase with the increase in water
requirements over this period due to increased crop-water demand. This demand will
depend on the total area within each CIS being irrigated and the percentage of this area
being irrigated for HVA. This demand would increase as more farmers get organized and
begin irrigating and simultaneously transitioning to HVA crops. The assumption for %
HVA crops and areas being irrigated over the subsequent 12 years of operation was
provided by MCC and identified in Table ES-7.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-12
December 2009
Executive Summary
CIS
Tetcani
Blindeti
Grozeti
Crpinenii
de Sus
Leova Sud
ChircaniZrneti
Cahul
Jora de Jos
Lopatna
Conia
Criuleni
erpeni
Puhceni
Roscani
Talmaza
Suvorov
Table ES-7
Basis of Annual Water Requirement Assumptions1
2014
2020
2025
% of Total
% of Total
% of Total
%
Area
Area
% HVA
Area
% HVA
HVA
Irrigated
Irrigated
Irrigated
45%
45%
45%
78%
42%
76%
92%
65%
86%
83%
66%
78%
93%
78%
99%
83%
67%
78%
45%
47%
68%
68%
80%
69%
45%
49%
69%
68%
82%
68%
45%
51%
70%
70%
83%
71%
45%
45%
45%
45%
45%
45%
45%
45%
45%
45%
33%
58%
69%
42%
56%
42%
60%
73%
36%
36%
60%
76%
82%
66%
74%
66%
76%
87%
61%
61%
62%
71%
76%
65%
70%
65%
74%
74%
62%
64%
72%
89%
95%
79%
86%
78%
88%
100%
72%
74%
64%
71%
76%
66%
71%
65%
74%
73%
64%
65%
1. Assumptions provided by MCC. Water Requirements between the years are assumed to grow linearly.
Other relevant assumptions made in developing the annual O&M budget include the
following:
Farmers will be adequately equipped, resourced and organized by 2014 to support the
assumptions in Table ES-7.
WUOs will be certified, and in place with adequate capacity to start irrigation
operations during this period.
The unit price of energy (per KWH) is assumed to increase at an annual rate of 12%
as per discussions with Union Fenosa. Given, historic energy prices, this can be
considered conservative for the purpose of this feasibility study. Historic energy
prices in Moldova are provided in Appendix J.
Replacement cost for equipment is included in the O&M budget at a rate of 4% per
annum (based on a straight line replacement cost schedule per asset life of 25 years).
While the STI budgets include depreciation, for this study there is no depreciation
line item in the rehabilitated system budget.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-13
December 2009
Executive Summary
Fixed cost for the centralized management of a single rehabilitated CIS was based on
O&M costs from 2007 STI expenditures, normalized over the total area irrigated and
number of pump stations, and pro-rated for operating the rehabilitated CIS. This was
adjusted to account for an inflation of 12.7% to get it to 2009 cost.
2009 Labor cost for WUO management is based on minimum personnel requirement.
The remaining components of the fixed cost were estimated to maintain parity with
historic STI expenditure for these items and adjusted by CIS based on discussions
with AM and information provided.
All costs are brought up to 2010 values using an inflation factor of 4 %. Costs are
inflated on an annual basis at 4 % for 2009 and 2010, then increased to 6% in 2011,
then increased to 9.3% per annum until 2025, when it is assumed production and
capacity have stabilized, and then are held flat until 2040.
Annual O&M Budget for Centralized (STI/AM) Management & Decentralized
(WUO) Management
The annual O&M budget contains the following components:
Fixed Cost.
Energy Cost.
Replacement Cost.
As per the above discussion, the main factor determining the O&M budget is the
estimation of the total water requirements. Further, based on the assumptions, fixed cost,
energy cost and replacement cost components were identified for each CIS starting in
year 2014 and through 2025. The total annual O&M budget was divided by the total
water requirement for that year to identify the unit cost of water.
Table ES-8 identifies the provides the breakdown for the three components of the unit
cost of water for the year 2014 assuming the total water requirements estimated based on
governing assumptions (Table ES-7) and WUO management.
Table ES-8
Estimated Breakdown for the Unit Cost of Water for Year 2014
Assuming CIS under WUO Management
Energy
Unit
Fixed
Energy Replacement
Cost as %
Cost of
CIS
Cost
Cost
Cost
of Cost of
Water
(MDL/m3) (MDL/m3)
(MDL/m3)
3
Water
(MDL/m )
Tetcani
0.50
2.87
1.06
4.43
65%
Blindeti
0.54
1.78
0.33
2.65
67%
Grozeti
Crpinenii de
Sus
0.2
1.86
0.41
2.47
75%
0.21
2.29
1.05
3.55
65%
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-14
December 2009
Executive Summary
CIS
Fixed
Energy Replacement
Cost
Cost
Cost
(MDL/m3) (MDL/m3)
(MDL/m3)
Unit
Cost of
Water
(MDL/m3)
Energy
Cost as %
of Cost of
Water
Leova Sud
ChircaniZrneti
Cahul
0.18
1.66
0.23
2.07
80%
0.19
0.67
0.25
1.11
60%
0.51
0.66
0.31
1.48
45%
Jora de Jos
0.27
1.95
0.37
2.59
75%
Lopatna
0.39
1.08
0.16
1.63
66%
Conia
0.13
0.94
0.17
1.24
76%
Criuleni
0.38
0.69
0.17
1.24
56%
erpeni
0.24
1.78
0.42
2.44
73%
Puhceni
0.21
0.74
0.22
1.17
63%
Roscani
0.28
1.49
0.25
2.02
74%
Talmaza
Suvorov
0.18
0.1
0.65
2.56
0.27
0.39
1.10
3.05
59%
84%
Similar breakdown is provided for the rehabilitated CIS assuming STI/AM management
in Table ES-9.
Table ES-9
Estimated Breakdown for the Unit Cost of Water for Year 2014
Assuming CIS under STI/AM Management
Energy
Unit
Fixed
Energy Replacement
Cost of Cost as %
CIS
Cost
Cost
Cost
of Cost of
Water
(MDL/m3) (MDL/m3)
(MDL/m3)
3
Water
(MDL/m )
Tetcani
0.11
2.87
1.06
4.04
71%
Blindeti
0.04
1.78
0.33
2.15
83%
Grozeti
0.03
1.86
0.41
2.30
81%
Crpinenii de Sus
0.09
2.29
1.05
3.43
67%
Leova Sud
0.03
1.66
0.23
1.92
86%
Chircani-Zrneti
0.14
0.67
0.25
1.06
63%
Cahul
0.26
0.66
0.31
1.23
54%
Jora de Jos
0.42
1.95
0.37
2.74
71%
Lopatna
0.21
1.08
0.16
1.45
74%
Conia
0.25
0.94
0.17
1.36
69%
Criuleni
0.02
0.69
0.17
0.88
78%
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-15
December 2009
Executive Summary
CIS
Fixed
Energy Replacement
Cost
Cost
Cost
(MDL/m3) (MDL/m3)
(MDL/m3)
Unit
Cost of
Water
(MDL/m3)
Energy
Cost as %
of Cost of
Water
erpeni
0.03
1.78
0.42
2.23
80%
Puhceni
0.02
0.74
0.22
0.98
76%
Roscani
0.02
1.49
0.25
1.76
85%
Talmaza
Suvorov
0.18
0.39
0.65
2.56
0.27
0.39
1.10
3.34
59%
77%
The difference in the unit cost of water between the two management options is in the
fixed cost. Energy cost and replacement cost, being system specific, will be the same
under either management. However, the STI managed systems would have a slight
advantage in pooling its labor and material resources to operate multiple CIS, thus
resulting in a lower fixed cost component than that under WUO management. For more
details on the development of the unit cost of water, please refer to the supporting
annexes.
More importantly, Table ES-8 and ES-9 illustrate that regardless of the management, the
predominant factor driving the unit cost of water is the energy cost. Since the CIS in
Moldova relies on pumping water from the low river levels to higher elevations where
most of the CIS under consideration are located, the cost of pumping would be a
significant component of the cost of water. As these above tables illustrate, the energy
cost can be as low at 45% for a low lying CIS like Cahul, and as high as 84% for a
system like Suvorov, which relies of multiple lift stations in series to get water to the
irrigation areas. The fixed and replacement cost factors are relatively smaller in
comparison.
The estimated unit cost of water for 2020 and 2025 are provided in Table ES-10.
Table ES-10
Estimated Unit Cost of Water (MDL/m3) for Year 2020 & 2025
2020
2025
CIS
Centralized Decentralized Centralized Decentralized
Tetcani
6.40
6.73
10.90
11.40
Blindeti
3.84
4.39
6.54
7.26
Grozeti
3.96
4.11
6.78
6.99
Crpinenii de Sus
5.47
5.59
8.97
9.14
Leova Sud
3.49
3.65
6.01
6.22
Chircani-Zrneti
1.66
1.72
2.72
2.79
Cahul
1.90
2.20
2.99
3.37
Jora de Jos
4.53
4.37
7.60
7.40
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-16
December 2009
Executive Summary
CIS
2020
Centralized Decentralized
2025
Centralized Decentralized
Lopatna
2.44
2.61
4.14
4.36
Conia
2.27
2.14
3.77
3.60
Criuleni
1.51
1.87
2.56
3.03
erpeni
Puhceni
Roscani
3.89
1.64
3.12
4.12
1.84
3.36
6.59
2.76
5.39
6.90
3.03
5.71
Talmaza
1.70
1.71
2.77
2.78
Suvorov
5.86
5.51
9.84
9.39
Details of the total O&M budget (estimated unit cost of water) for each CIS through 2025
are presented in their respective annexes (Annex 1- 16) supporting this report.
O&M Capacity Building Support
A preliminary assessment for building O&M capacity for the decentralized (WUO)
management was identified. WUO capacities will need to be built from scratch to enable
it to takeover operation & maintenance management responsibilities. In the interest of
being self reliant, it would be ideal for each WUO to not have to depend on its respective
STI to borrow tools & equipment.
9.0
MWH recommends that MCA-Moldova contract the following parties directly for
implementation of the project:
Technical Assistance (TA) for the Implementing Entity (discussed in Section 8
and later in this Section);
An engineering firm to conduct the final design of the work and to prepare the
contract documents;
A supervising engineer to oversee that the construction contractor(s) adhere to the
requirements of their contract; and, naturally,
The construction contractor(s).
With regard to the construction contract(s), the overall project lends itself better to a
conventional design-bid-build (DBB) contract than a design-build (DB) contract, for the
following reasons:
DB contracts do not lend themselves well to underground work, nor to projects in
which rehabilitation is involved. The CIS includes both. It is better to have the
designer explore these issues in the field and define the scope in more detail, prior
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-17
December 2009
Executive Summary
to the project being bid. Otherwise, bidders would either include contingencies in
their bid and thus inflate their bid price, or bid the project low and pursue claims
later.
As the projects have been studied in some detail already, it is best to leverage that
information and complete the designs as soon as possible, instead of waiting for
the eventual successful bidder to engage a designer who, later on, would still have
to undergo a learning curve.
Under a DBB approach, field investigations and design work can conducted and
simultaneously with the prequalification process for contractors. Such work
could also occur simultaneously with implementation of the IMT program.
One normal advantage of a DB contract, simultaneous design and construction
work, does not truly exist on this project.
The sheer nature of this particular MCC program makes a DBB approach the only viable
option. It would be less expensive, take less time, and be less risky than a DB approach.
It is also recommended that larger international bidders be permitted to bid on the project.
The current international construction market is such that there should be significant
interest in the project. While this may change before any award of any CIS construction
contract, it is currently believed that the industry should still be fairly competitive in the
upcoming year or so.
Construction Packaging
As discussed in previous sections of this report, the overall project is made up of
numerous individual projects, which consist primarily of rehabilitation and/or
replacement of existing agricultural infrastructure. To increase the pool of potential
bidders, it may be advisable to afford bidders the option of bidding all projects or certain
groups of projects. This would attract larger contractors, who may otherwise find it
difficult to compete with medium-sized contractors, to bid on the overall project. A
single project (or fewer projects), in practice is easier to manage than having multiple
smaller projects.
For the sake of this study, the following bid packaging was assumed:
Bid Package 1 Rehabilitation of seven Prut River CIS projects (Tetcani,
Blindesti, Grozeti, Crpinenii de Sus, Leova Sud, Chircani-Zrneti, and Cahul).
Bid Package 2 Rehabilitation of nine Nistru River CIS projects (Jora de Jos,
Lopatna, Cosnita, Criuleni, Serpeni, Puhceni, Rocani, and Talmaza).
Bid Package 3 Rehabilitation of the Suvorov CIS in the Nistru River Basin.
This project was isolated as a separate bid package due to its size and technical
nature. Per Table ES-5, its implementation cost represents 47% of the total cost
of all CIS projects addressed in this study. Additionally, unlike all the other CIS
projects, its scope contains dam rehabilitation work, which require specialized
construction.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-18
December 2009
Executive Summary
Final bid packaging would be dependent on MCCs selection of which CIS projects it
intends to fund, and refinements that would occur during the detailed design and bid
document preparation stage. The contractor prequalification stage may also warrant
further optimization of the bid packaging approach.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-19
December 2009
Executive Summary
Implementation Plan
A detailed project implementation plan is provided as Figure ES-3. Five-day work weeks
were assumed to develop the schedule. Where days are shown on the schedule, they
should be considered as work days. The sequence shown on the schedule in which the
various projects are constructed reflect one set of possibilities; the actual sequence of
construction and intermediate milestones contained in the eventual construction
contract(s) should be determined nearer to the time of bid document issuance based on
which project areas, and which WUOs, are ready first. As little such information exists
as of the writing of this study, the sequence can be shuffled in any manner at this time.
An analysis of this schedule indicates that:
The time frame of five years is sufficient to undertake all the projects being
considered.
The establishment and registration of WUOs (December 1, 2010) is on the
projects critical path.
The construction / rehabilitation work is expected to last 2 to 3 years for all bid
packages.
Bid Package #3, which only includes the Suvorov CIS, involves rehabilitation of a
dam. Such work may require cofferdams and may be sensitive to high river flows.
As with all the of the CIS projects, the duration of the projects should be reevaluated as the design work proceeds.
Some flexibility exists in the schedule to postpone the issuance of bid documents
somewhat if delays occur in the registration of WUOs after December 1, 2010;
however, this would result in higher construction costs to accelerate construction
if the delays end up being significant, or would result in less time after
construction to monitor the performance of the constructed improvements and the
effectiveness of the WUOs, or both.
Similar flexibility exists in the schedule to handle potential delays resulting from
changed condition claims.
As some of the projects are relatively small, their performance, as well as that of
their respective WUOs, may be measured through two growing seasons, provided
they are scheduled to be among the first completed. Unless there are delays, it
should be possible to make such observations for at least one growing season on
all projects.
At this time, MWHs biggest concern relating to schedule risk (and thus also cost risk) is
the timely establishment of WUOs.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-20
December 2009
Task Name
Compact Signing
Duration
0 days
Start
Thu 10/1/09
Finish
Thu 10/1/09
0 days
Tue 12/1/09
Tue 12/1/09
0 days
Mon 3/1/10
Mon 3/1/10
261 wks
Mon 3/1/10
Fri 2/27/15
0 days
Wed 12/1/10
Wed 12/1/10
105 days
Thu 10/1/09
Wed 2/24/10
8 wks
Thu 10/1/09
Wed 11/25/09
MCA-M Approval
1 wk
Thu 11/26/09
Wed 12/2/09
MCC Approval
1 wk
Thu 12/3/09
Wed 12/9/09
10
Proposal Period
4 wks
Thu 12/10/09
Wed 1/6/10
11
Evaluate Proposals
3 wks
Thu 1/7/10
Wed 1/27/10
12
MCA-M Approval
1 wk
Thu 1/28/10
Wed 2/3/10
13
MCC Approval
14
15
1 wk
Thu 2/4/10
Wed 2/10/10
2 wks
Thu 2/11/10
Wed 2/24/10
1305 days
Mon 3/1/10
Fri 2/27/15
16
4 wks
Mon 3/1/10
Fri 3/26/10
17
6 wks
Mon 3/29/10
Fri 5/7/10
18
6 wks
Mon 3/29/10
Fri 5/7/10
19
257 wks
Mon 3/29/10
Fri 2/27/15
20
105 days
Thu 10/1/09
Wed 2/24/10
8 wks
Thu 10/1/09
Wed 11/25/09
1 wk
Thu 11/26/09
Wed 12/2/09
21
22
MCA-M Approval
23
MCC Approval
1 wk
Thu 12/3/09
Wed 12/9/09
24
Proposal Period
4 wks
Thu 12/10/09
Wed 1/6/10
25
2 wks
Thu 1/7/10
Wed 1/20/10
26
1 wk
Thu 1/21/10
Wed 1/27/10
27
MCA-M Approval
1 wk
Thu 1/28/10
Wed 2/3/10
28
MCC Approval
29
1 wk
Thu 2/4/10
Wed 2/10/10
2 wks
Thu 2/11/10
Wed 2/24/10
1137 days
Mon 3/1/10
Tue 7/8/14
6 wks
Mon 3/1/10
Fri 4/9/10
30
31
32
Field Investigations
22 wks
Mon 4/12/10
Fri 9/10/10
33
Finalize Designs
34 wks
Mon 4/12/10
Fri 12/3/10
34
65.4 wks
Mon 4/12/10
Tue 7/12/11
35
28 wks
Mon 5/31/10
Fri 12/10/10
36
37
38
2 wks
Wed 6/29/11
Tue 7/12/11
156 wks
Wed 7/13/11
Tue 7/8/14
327 days
Mon 4/12/10
Tue 7/12/11
5 wks
Mon 4/12/10
Fri 5/14/10
39
40
MCA-M Approval
1 wk
Mon 5/17/10
Fri 5/21/10
41
MCC Approval
1 wk
Mon 5/24/10
Fri 5/28/10
42
Advertise Project
6 wks
Mon 5/31/10
Fri 7/9/10
43
8 wks
Mon 7/12/10
Fri 9/3/10
44
5 wks
Mon 9/6/10
Fri 10/8/10
2009
Qtr 2
Qtr 3
Qtr 4
10/1
Qtr 1
2010
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2011
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2012
Qtr 2
Qtr 3
Qtr 4
12/1
3/1
12/1
Task
Progress
Summary
External Tasks
Split
Milestone
Project Summary
External Milestone
Page 1
Deadline
Qtr 1
2013
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2014
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2
Qtr 2
Task Name
MCA-M Approval
Duration
3 wks
Start
Mon 10/11/10
Finish
Fri 10/29/10
2 wks
Mon 11/1/10
Fri 11/12/10
2 wks
Wed 12/1/10
Tue 12/14/10
16 wks
Wed 12/15/10
Tue 4/5/11
46
MCC Approval
47
48
Bidding Period
49
Evaluation of Bids
6 wks
Wed 4/6/11
Tue 5/17/11
50
MCA-M Approval
2 wks
Wed 5/18/11
Tue 5/31/11
51
MCC Approval
1 wk
Wed 6/1/11
Tue 6/7/11
52
3 wks
Wed 6/8/11
Tue 6/28/11
53
54
Notice to Proceed
BP#1 Rehab Work - Prut River
2 wks
Wed 6/29/11
Tue 7/12/11
715 days
Wed 7/13/11
Tue 4/8/14
55
Mobilization
8 wks
Wed 7/13/11
Tue 9/6/11
56
Tetcani
73 wks
Wed 9/7/11
Tue 1/29/13
57
Blindesti
37 wks
Wed 1/30/13
Tue 10/15/13
58
Grozesti
45 wks
Wed 9/7/11
Tue 7/17/12
59
Carpenenii de Sus
90 wks
Wed 5/23/12
Tue 2/11/14
60
Leova Sud
37 wks
Wed 9/7/11
Tue 5/22/12
61
Chircani-Zirnesti
91 wks
Wed 9/7/11
Tue 6/4/13
62
Cahul
69 wks
Wed 7/18/12
Tue 11/12/13
63
64
8 wks
Wed 2/12/14
Tue 4/8/14
700 days
Wed 7/13/11
Tue 3/18/14
65
Mobilization
8 wks
Wed 7/13/11
Tue 9/6/11
66
Jora de Jos
45 wks
Wed 9/7/11
Tue 7/17/12
67
Lopatna
20 wks
Wed 7/18/12
Tue 12/4/12
68
Cosnita
50 wks
Wed 12/5/12
Tue 11/19/13
69
Criuleni
37 wks
Wed 9/7/11
Tue 5/22/12
70
Serpeni
50 wks
Wed 5/23/12
Tue 5/7/13
71
Puhaceni
45 wks
Wed 9/7/11
Tue 7/17/12
72
Roscani
37 wks
Wed 5/8/13
Tue 1/21/14
73
Talmaza
77 wks
Wed 7/18/12
Tue 1/7/14
74
75
76
Mobilization
77
Suvorov
78
79
80
81
Compact Completion
8 wks
Wed 1/22/14
Tue 3/18/14
705 days
Wed 7/13/11
Tue 3/25/14
8 wks
Wed 7/13/11
Tue 9/6/11
125 wks
Wed 9/7/11
Tue 1/28/14
8 wks
Wed 1/29/14
Tue 3/25/14
98 wks
Wed 5/23/12
Tue 4/8/14
144 wks
Wed 5/23/12
Tue 2/24/15
0 days
Fri 2/27/15
Fri 2/27/15
2009
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2010
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2011
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2012
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2013
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2014
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2
Qtr 2
2/27
Task
Progress
Summary
External Tasks
Split
Milestone
Project Summary
External Milestone
Page 2
Deadline
Executive Summary
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-22
December 2009
Executive Summary
Appropriate Tariff Levels
The appropriate level of tariff represents the charge per unit of water that a farmer will
pay for the cost of that water. From a WUOs perspective, the tariff level that is
appropriate is that which will meet the unit cost of supplying water on an annual basis.
The cost of water for the years 2014, 2020 and 2025 was previously identified in Table
ES-8 and ES-9, respectively. The corresponding tariff level based on the above
assumption is provided in Table ES-12.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-23
December 2009
Executive Summary
This varies from 4.85 million MDL in Criuleni to over 276 million MDL in Suvorov.
Despite that FIRR show these systems to be sustainable in the long run, the sustainability
in the short term would be a concern if the WUO do not have another source of revenue
to overcome these losses on a yearly basis during these initial years.
In looking at a potential funding source, it can be assumed that the current subsidies will
continue (at minimum, the energy component) in the near future even under the
decentralized (WUO) management. In which case, the percentage of energy subsidy
required to offset the identified shortfall is illustrated in Figure ES-4.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-24
December 2009
Executive Summary
Figure ES-4
% Energy Subsidy Required to Offset Shortfall in Table ES-14
The level of subsidy in terms of percentage of the energy cost would vary from system
ranging from 12% at Chircani-Zrneti to approximately 44% at Tetcani. The total
subsidy over the period for each of the CIS would equal the shortfall identified in Table
ES-14.
Executive Summary
meet its desired objectives. This will help identify potential shortfalls ahead of
time, and an opportunity for the Government of Moldova to seek supplemental
funding from other sources to ensure the completion of the MCC objectives in
Moldova.
AM would be the implementing entity for the MCC funded rehabilitation
program. However, technical assistance would be required to assist AM with its
responsibilities to ensure that the projects are implemented on time and on budget.
Although there are not inherent fatal flaws to any of the CIS under consideration,
several major risks were identified with the assumptions and the process
associated with the proposed IMT program as proposed in Section 8, which would
have near term sustainability impacts on the MCC investment, if the process and
the establishment of the WUO are not adequately incorporated or brought up to
capacity.
Based on current MCC plans of tying the IMT process with the rehabilitation
works, delays in the registration of the WUO would have an impact on the
construction schedule and risk the project not being completed on time and on
budget. To mitigate this risk, it would be critical for the IMT Consultant and the
Design Engineer to coordinate periodically so the IMT process informs the
rehabilitation schedule and the Design Engineer can develop the priority of
construction accordingly.
Assessment of the current financial practices in the irrigation sector identified the
following:
Energy subsidies are supposed to cover up to 100% of the energy cost.
However, there are still shortfalls in the payment to cover energy cost that
cannot be reconciled. The second subsidy (irrigation service subsidy)
provided by AM supposedly covers approximately 50% of the fixed cost.
However, the subsidies seem to be me significantly higher.
The revenues collected by STI from irrigation are a small fraction
compared to the state financing that goes to sustain irrigation operation.
Farmers current and historic tariff payments are significantly lower than
the levels needed to sustain irrigation operation without state financing.
Contracts for water often exceed actual amount irrigated. However, since
the fixed cost is based on the water required, the water tariff (in terms of
cost per cubic meter of water) ends up being lower at the beginning of the
year than what is required, which is only known at the end of the year.
This often results in revenues not being adequate to cover expenses that
are fixed.
Given the non-standardized and non-transparent accounting practices, its
not clear how the STI continues to maintain its operations with shortfalls
even with subsidies. It is assumed that STI offset revenues from other
services to balance its sheets.
In assessing future O&M budgets and the financial sustainability of the
rehabilitated system, the following should be taken into consideration:
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-26
December 2009
Executive Summary
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
ES-27
December 2009
Section 1 - Introduction
1.0
INTRODUCTION
This document presents the findings of the feasibility studies for the rehabilitation of the
16 Central Irrigation Systems (CIS) in Moldova.
1.1
Project Background
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
1-1
Nistru River
1-1 Tecani
Ukraine
11-6 Jora de Jos
11-7 Lopatna
Prut River
14-2 Criuleni
12-3 Conia
3-2 Blindesti
3-6 Gozeti
14-6 Serpeni
4-5-1 Crpinenii de
sus
14-11 Pugcenii
Nistru River
Romania
14-13 Roscani
Key:
Prut River
Giurgiulesti - Danube
River port
Transnistria region
Proposed MCC road segments
World Bank/EBRD/EIB roads segments (ongoing)
Not to Scale
FIGURE 1-1
LOCATION OF THE 16 CIS
PROPOSED FOR REHABILITATION
DECEMBER 2009
Section 1 - Introduction
The fundamental basis for the HVA project is that Moldovas climate, topography, and
fertile agricultural soils provide the country with a potential comparative advantage in
HVA. The HVA proposal aims to support agricultural production of higher value-added
crops, requiring investment in CIS infrastructure and on-farm equipment. In conjunction
with its investment in the physical rehabilitation works, MCC is also considering
investing in the Irrigation Management Transfer (IMT) program to establish and
strengthen water users organizations (WUOs) for the administration, operation, and
maintenance of rehabilitated CIS.
The working premise of the MCC investment is that with the rehabilitation of the CIS
and transfer of management responsibilities to the water users (farmers), along with
access to on-farm irrigation equipment and market for their produce, farmers will
gradually move to more diversified crops and HVA production that will result in
increased farm incomes. However, this feasibility study is limited to the rehabilitation of
the CIS.
1.2
Project Objectives
The primary objective of this assignment was to undertake feasibility studies to provide
the necessary information related to the technical, financial, institutional, environmental
and social aspects of the proposed rehabilitation of the 16 CIS in Moldova to benefit
MCC in its investment decision, and subsequently develop preliminary designs for the
selected investment.
In this capacity, MWH:
Analyzed prior work to gain a full understanding of the basis for proposed
investment, and frame the recommendations for technical, financial, and
institutional aspects of a successful program;
Assessed the environmental and social impacts of the proposed interventions in
light of prevailing local laws and MCC Environmental Guidelines, and
recommended a plan to mitigate potential negative impacts;
Worked in close and constant coordination with MCC, MCA-Moldova and
relevant GoM representatives early on to hone in on the key issues that will guide
the assessment and its outcomes;
Mobilized key expatriate technical staff with subject matter expertise in the
appropriate disciplines in a timely, concerted manner that allows for smooth
integration of multiple inputs into a holistic guidance document;
Identified conceptual plans for rehabilitation projects, project cost and associated
annual Operations & Maintenance Cost (O&M);
Conducted financial sustainability analysis for the rehabilitated systems and
identified appropriate tariff levels for sustaining the MCC investment;
Identified Technical Assistance to enhance local institutional capabilities for the
success of implementing the MCC investment within a five-year period, and to
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
1-3
Section 1 - Introduction
sustain the investment by building up their O&M capacity to sustain this
investment for the long run; and
Summarized the assessments and discussed the findings with MCC prior to
developing designs for the selected interventions;
The scope of work of this project is divided into two tasks:
Task 1 Feasibility Studies for Infrastructure Rehabilitation
Task 2 Environmental & Social Assessment of the Proposed Rehabilitation
This report summarizes the findings of Task 1.
MWH completed the technical analysis and assessment based on review of existing
available information, and on information from on-going projects received during the
period allocated for the assigned tasks. In the process, MWH used professional judgment
in its assessment to compensate for gaps in information, if any, which could not be
readily addressed through available information sources within the time frame of the
assigned tasks.
1.3
Scope of Work
The scope of work designed to meet the study objectives as defined in the Terms of
Reference (TOR) for Task 1 includes the following subtasks:
1. Identify Technical and Environmental Fatal Flaws
This task included:
Collecting data, conducting site visits, and undertaking interviews with relevant
agencies responsible for project implementation.
Analyzing implementation schedule(s) to determine whether the projects can be
done in five years.
Assessing compliance with MCC environmental guidelines and Section 605(E)(3)
& local Moldova laws.
Determining if a technical, environmental, and/or social fatal flaw exists
Identifying major risks that could affect project implementation, cost,
performance, durability & environmental/social impact etc.
Developing Technical Memorandum on discovered fatal flaws.
The results on this subtask were summarized in the Technical Memorandum and
submitted under separate cover as draft on March 27, 2009. The final memorandum was
submitted on May 13, 2009.
2. Systems under Consideration
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
1-4
Section 1 - Introduction
This task entailed:
Compiling background for each CIS project in conjunction with evaluation of the
existing condition for the 16 CIS.
Identifying Project Definition in coordination with identifying rehabilitation
requirements for each CIS.
Identifying linkages to and impact of other donor ongoing and proposed projects.
3. Analysis of Site Conditions
This task involved:
Collecting & reviewing available site and soil relevant data.
Identifying potential risks associated with prevailing soil conditions while
developing rehabilitation needs and identifying rehabilitation interventions for
each CIS.
Based on risk identified, assessing if necessary mitigation measures for the risks
has been considered in project design and cost.
Developing Scope of Work for undertaking soil and groundwater sampling to
address immediate soil salinity and drainage condition concerns.
4.
Section 1 - Introduction
and assess the adequacy of these sources to meet present and future demands.
Based on available data, assessing the quality of the groundwater and its viability
to support demands dependant on it.
If the groundwater sources are determined to deteriorate, reviewing the viability
of shifting these demands to be met by the available surface water sources and its
impacts.
Based on available data, assessing the impacts of climate change on these surface
& ground water sources.
Assess the impact of changes in the water discharge in the Prut & Nistru Rivers
due to water use actions by other countries that are also dependent on these rivers.
6. Project Justification
This task included:
Identifying rehabilitation requirements within each CIS.
Developing a summary of the initial evaluation for each CIS for identifying
ballpark cost estimates.
Developing list of rehabilitation interventions for each of the 16 CIS.
7. Project Design
This subtask was proposed in two phases:
Phase 1 Project Definition - Feasibility Study.
Phase 2 Preliminary Design - Post-Feasibility Study. This task involved
digitizing existing infrastructure maps for each of the 16 CIS and incorporating it
with the GIS database developed by National Agency for Rural Development
(ACSA) for MCC.
This report only covers Phase I of this subtask. This involved:
Collecting data, undertaking field reconnaissance missions & interviews with
relevant stakeholders/agencies responsible for project implementation, and
developing methodology for data compilation and evaluation based on data
collected/available.
Evaluating the existing condition for the 16 CIS.
Identifying rehabilitation requirements for each CIS.
Developing rehabilitation intervention plans within each CIS including costs.
8. Project Cost
This task entailed:
Reviewing cost estimates for CIS infrastructure rehabilitation developed in the
USU Study.
Gathering latest unit cost data for items that require rehabilitation, and assisting in
development of ballpark cost estimates.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
1-6
Section 1 - Introduction
Developing a planning level cost estimate for each proposed rehabilitation
intervention that includes all necessary activities for the successful
implementation and subsequent operation, with accommodation for contingencies
and future price escalations from inflation and currency fluctuations.
Identifying O&M cost for the rehabilitated systems.
Develop a disbursement schedule over the implementation period.
9. Financial Sustainability
This task included:
Collecting data on tariffs, entities revenue collection process etc.
Reviewing O&M costs & including all associated sinking funds for developing
cash flow scenarios.
Calculating FIRR.
Conducting uncertainty or probabilistic and sensitivity analyses.
Developing recommendations based on financial analysis on appropriate tariff
levels for O&M cost recovery.
10. Operations & Maintenance
This task involved:
Conducting informational interviews with responsible, relevant entities.
Comparing past performance of agencies (Performance of Quality vs. budget).
Identifying costs and budget to sustain the rehabilitated system assuming the
existing centralized system and a potentially future decentralized system.
Based on information gathered, assessing adequate O&M budget for each
intervention and based on input from the financial sustainability task
recommending methods for increasing O&M funding.
Identifying recommendations on sound practice for O&M that protects MCCs
investment, including need for resource and equipment if not available in
Moldova.
11. Institutional Capacity & Capability
This task entailed:
Reviewing USU Study recommendation for future institutional arrangements.
Based on information gathered from previous tasks, assessing adequacy, quality
and competency of the responsible entities and the various water user
associations.
Identifying risks associated with the responsible entity and the recommended
USU plan, and identifying remedial actions to mitigate the risks.
Evaluating need for technical assistance (part of the remedial action), if necessary,
to be included as part of the MCA Program.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
1-7
Section 1 - Introduction
12. Implementation Management
Based on existing available information, this task entailed:
Reviewing information on:
a. Local construction capacity, and
b. Material & equipment availability.
Recommending the most appropriate implementation arrangement and specifying
Executing Agency and appropriate staff.
Recommending construction approaches (Design-Build, Design-Bid-Build etc.) to
mitigate delays and cost overruns.
Developing an implementation schedule based on the recommended
implementation arrangement and approach.
13. Technical Assistance
This task entailed proposing Technical Assistance (TA) to AM or other service entities to
assure successful implementation and sustainability of the MCC investment. (Terms of
Reference for the TA were not requested by MCC as part of this study).
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
1-8
Section 1 - Introduction
1.4
The report provides a detailed description of the findings of this study in 14 sections with
a supporting appendix. A summary of each section is as follows:
Section 1 Introduction: Provides an overview of the study and the objectives of this
study.
Section 2 Systems under Consideration: Provides an overview of the 16 CIS under
consideration.
Section 3 Assessment of Existing CIS Infrastructure: Provides an overview of the
assessment of the existing CIS infrastructure to identify rehabilitation requirements.
Section 4 - Assessment of Site Conditions: Provides an overview of the soil salinity and
drainage conditions at potentially problematic CIS.
Section 5 Assessment of Water Resources & Water Quality: Provides an overview of
the assessment on adequacy of water resources to support the CIS rehabilitation projects
and the quality of the water.
Section 6 Proposed Rehabilitation Plan: Provides an overview of the rehabilitation
plans based on the rehabilitation requirements to sustain the proposed water demand
needed for HVA agriculture.
Section 7 Feasibility Level Cost Estimate for the Proposed Rehabilitation Projects:
Provides a planning level cost estimate for the implementation of each CIS rehabilitation
project.
Section 8 Assessment of Institutional Capacities: An overview and assessment of the
capacity and capabilities of the institution(s) expected to assume ownership, undertake
implementation and responsible for the operations and maintenance.
Section 9 - Assessment of Operation & Maintenance Plans: Identifies and assess the
required operations & maintenance capacity of the responsible institution to ensure
sustainability of the MCC investment.
Section 10 Project Implementation Plan: A summary of the proposed implementation
plan and schedule, including an assessment of material, equipment and construction
capabilities.
Section 11 Assessment of Financial Sustainability: An overview of the overall
financial sustainability given the anticipated revenues generated in light of the
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
1-9
Section 1 - Introduction
appropriate tariff levels for the proposed investment and cost of operating and
maintaining the proposed rehabilitated CIS.
Section 12 Summary & Conclusions: Presents the summary of the findings and
overview of the conclusion based on these studies.
References: List of references referred to during the course of this project.
Appendices Appendix A K providing supporting detailed data.
Annexes 1-16: Accompaniment to this main report that provides detailed descriptions,
assessment and system information specific to each of the 16 CIS.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
1-10
2.0
This section provides a description of each of the CIS rehabilitation projects that are
being considered by MCC for funding. The description includes:
Overview of irrigation system in Moldova; and
Description for each CIS based on existing available information.
2.1
Most of the irrigation development in Moldova occurred between 1960 and 1990. During
this period the irrigated area in the country increased from 75,000 ha to 310,000 ha.
About 110,000 ha of this total were developed in Transnistria east of the Nistru River.
The water sources for the irrigation systems are the Nistru River, the Prut River, and
artificial reservoirs and natural lakes in the interior of the country. At one time,
approximately 210,000 ha of the total area were served by irrigation systems located
along the Nistru and the Prut Rivers. The balance of the systems utilized the inland rivers
and lakes as a water source. Most of the systems are located in the central and southern
climatic zones of the country.
Prior to the breakup of the Soviet Union, farmers received their water through agreements
between the Department of Water Resources, an agency under the direction of the
Ministry of Agriculture and Food Industry (MAFI), and the farm on which they worked
(either a collective or a State farm). Irrigation was used on the collective and State farms
to produce large quantities of food both for home consumption and export within the
Soviet Union. In addition wine, nuts and other high-value crops were produced in the
country. However, there was little if any consideration of the pumping costs, nor concern
for the long-term replacement costs of the pumps and distribution system. Operation and
maintenance of the main pumping and distribution system was the responsibility of the
State while operation and maintenance of the on-farm irrigation system was the
responsibility of the collective and State farms. Similarly, the main pumping and
distribution system was owned by the State while the on-farm irrigation pumping and
distribution system belonged to the collective and State farms.
After the breakup of the Soviet Union in the early 1990's, land ownership was fragmented
when the farms were privatized and the land distributed based on equity considerations.
Moreover, ownership of the tertiary water delivery system that underlay the land was also
given to each landowner. When the land was distributed in many fragmented plots it
became difficult to operate the irrigation system. As a result of the collapse of the
collective farms there was drastic decline in the irrigation areas commanded by the old
systems. This was partly due to lack of maintenance, vandalism of the irrigation facilities,
and smaller farming operations coupled with higher market-based electric energy costs.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-1
27,980
18.0
50 to 99
100 to 149
150 to 199
200 to 299
300 and
above
Total
18,367
35,018
40,286
29,449
11.8
22.5
25.9
18.9
4,722
03.0
155,822
100.0
Note: Table 2-1 does not include Transnistria (110,780 ha), small-scale irrigation in the
interior of the country (21,300 ha), and other smaller schemes around the country.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-2
Not to Scale
FIGURE 2-1
TYPICAL CIS SCHEME
DECEMBER 2009
2.2
As identified in Section 1.0, MCC is currently considering investing in some or all the 16
CIS proposed for rehabilitation. Table 2-2 provides an overview of the irrigation area
within each CIS.
Table 2-2
Irrigation Area within Each CIS1
CIS Rehabilitation
Area of Irrigation
Project
(Hectares-Ha)
Tetcani
1,258
Blindeti
521
Grozeti
1,018
Crpinenii de Sus
1,815
Leova de Sud
963
Chircani-Zrneti
4,417
Masivul Cahul
1,930
Jora de Jos
1,165
Lopatna
506
Conia
2,800
Criuleni
677
erpeni
1,107
Puhceni
856
Rocani
682
Masivul Talmaza
Masivul Suvorov
Total
2,468
13,394
35,577
Given the scope and nature of the proposed investment, the rehabilitation of the CIS did
not include expanding the existing irrigation area.
The primary system consists of a river intake, a primary pump station located near the
river intake, from which water is pumped to another pump station (for additional lift) or
storage reservoirs with secondary pump stations and/or open channels to convey water to
the tertiary (pressure) pump stations.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-4
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-5
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-6
Based on the above convention, the medium voltage power lines (35 kV, 10 kV, and 6
kV), the main power transformers, and the associated equipment (disconnect switches,
circuit breakers, fuses) are maintained by the Utility. There are several situations where
the above equipment is missing due to vandalism and/or theft. In such cases, as stipulated
by the national regulations, the Utility does NOT take the responsibility to rebuild the
power supply; this would remain as the burden of the Government, more specifically the
Ministry of Energy (ME). The same approach applies if the transformers for instance
need to be upgraded due to higher power demand by Apele Moldovei. The consumer (in
this case Apele Moldovei) is expected to pay for the upgrades/re-construction, and the
electrical equipment is then transferred to the Utility for maintenance. A preliminary
inventory of such equipment that would need to be rehabilitated is included in the present
report as Appendix K.
After discussions with Union Fenosa to find a compromise on this issue and to eliminate
a burden to the project, the Utility suggested that all these situations to be inventoried and
submitted to the ME. The ME has the authority to include such kind of works into the
Development Plan paid for by the Utility. This subject matter is worth pursuing with
ME since the estimated costs to fix the power supplies can reach as much as $1.5 million.
For the purpose of this study, this has been included in the feasibility level cost estimates.
Other issues like category of consumer, allowable voltage/frequency variations, and
maximum duration of power outages are not clearly defined in the contract with the
Utility. Union Fenosa proposes to review these clauses on a case by case basis, looking at
various factors like the condition of power supply, length, age, loads, demand, etc.
Currently, there is no Load Shedding program in effect in Moldova, since there is enough
power generated in the country to satisfy consumers around the clock. All pump stations
are fed with power from one source, only. If that fails, the pumps are dormant until power
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-7
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-8
2.3
The source of irrigation water for the 16 CIS under consideration is either the Prut River
or the Nistru River, or a lake impounded by a dam. Six of these CIS rely on the Prut
River, while the remaining nine are supplied via the Nistru River. The dams off the Prut
and Nistru Rivers are part of three of these CIS: Tetcani, Crpinenii de Sus, and a portion
of Suvorov. All 16 CIS require water to be pumped from the water source. A description
of each of the 16 CIS is provided below.
2.3.1 Tetcani
This CIS derives water from a dam on the Vilia River, a tributary of Prut River. The dam
is 13.6 m in height, 6.0 m in width and 125 m in length. It was built in 1963, made of
compacted clay. The maximum volume of water stored in the lake is 930,000 m3 and the
minimum volume is 222,000 m3. The slopes are protected with grass. The system is
served by one primary pump and one pressure pump station. Details of the pump stations
capacities are provided in Table 2-3.
Pump
Station
Table 2-3
Pump Stations Serving Tetcani CIS
Irrigation
Number of Total Pump
Area
Pump
Capacity
(Ha)
Units
(lps)
Head
(m)
3
330
105
2
880
90
Transit to SP-2
443
4
380
105
500
2
440
57
Note: Existing pump capacities are based on best available, reliable data. This will
need to be verified prior to detailed design.
SP-1
SP-1
SP-2
SP-2
313
The total irrigation area under this CIS is estimated to be 1,258 ha. The system was
previously designed assuming on-farm irrigation such as sprinkler irrigation using a
number of 18 laterals type DNEPR.
The pipe network comprises:
Total Length 31,759 m;
Diameter range 100 mm to 1000 mm;
Pipe Material Steel, Asbestos-cement, Reinforced precast concrete, RTNS
(concrete-encased steel)
STI Briceni, a branch of Apele Moldovei a governmental agency - currently manages
the CIS. For additional details on the Tetcani CIS, please refer to Annex 1.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-9
Pump
Station
Table 2-4
Pump Stations Serving Blindeti
Irrigation
Number Total Pump
Area
of Pump
Capacity
(Ha)
Units
(lps)
SR-3
SP-4
Transfer to SP-4
Transfer to SP-7
SP-4
260
SP-7
261
Head
(m)
3
2
1
1
380
360
180
90
63
92
90
50
2
4
105
500
120
95
Note: Existing pump capacities are based on best available, reliable data. This will need
to be verified prior to detailed design.
This CIS will cover an area of 521 ha. The system was previously designed assuming onfarm irrigation such as sprinkler irrigation using a number of 13 laterals type DNEPR,
and one lateral self-propelled type FREGAT. The pipe network consists of:
Total Length 20,195 m;
Diameter range 100 mm to 500 mm;
Pipe Material Steel, Asbestos-cement, Reinforced precast concrete, and RTNS
(concrete-encased steel).
STI Ungheni currently manages this CIS. For additional details on the Blindeti CIS,
please refer to Annex 2.
2.3.3 Grozeti
This CIS derives water from the Prut River. The system is served by one primary pump
and one pressure pump stations. Details of the pump stations capacities are provided in
Table 2-5.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-10
Pump
Station
SP-11
SPR-12
SPR-12
SPR-12
SPR-12
Table 2-5
Pump Stations Serving Grozeti
Irrigation
Number of Total Pump
Area
Pump
Capacity
(Ha)
Units
(lps)
Transfer
to SPR-12
389
240
240
140
Head
(m)
660
139
3
2
2
Gravity Fed
420
360
120
65
87
36
Note: Existing pump capacities are based on best available, reliable data. This will
need to be verified prior to detailed design.
The system will cover an area of 1,018 ha. The system was previously designed
considering on-farm irrigation such as sprinkler irrigation using 4 laterals type DNEPR,
8 laterals type DS 25/300, and 7 self propelled center pivot FREGAT. The
underground pipe network comprises:
Total Length 41,423 m;
Diameter range 100 mm to 700 mm;
Pipe Material Steel, Asbestos-cement, Reinforced precast concrete, RTNS
(concrete-encased steel)
STI Ungheni currently manages this CIS. For additional details on the Grozeti CIS,
please refer to Annex 3.
2.3.4 Crpinenii de Sus
This CIS derives water either from the Prut River or from Lake Minjir on the Lpunita
River, a tributary of the Prut River. The lake is impounded by a dam. The dam is 13.5 m
in height, 6.0 m in width and 624 m in length, and was built in 1982 and is made of
compacted clay. The maximum storage volume of the lake is 12,206,000 m3 and the
minimum volume is 1,023,000 m3. The outer slope is protected with grass and the inner
slope is protected with reinforced precast concrete slabs.
The system is currently served by one primary pump station, two secondary pump
stations and two pressure pump stations. Details of the pump stations capacities are
provided in Table 2-6.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-11
Pump
Station
NSG-1
NSP-1
NSP-2
NSP-4
NSP-4
NSP-7
NSP-7
Table 2-6
Pump Stations Serving Crpinenii de Sus
Number of Total Pump
Irrigation Area
Pump
Capacity
(Ha)
Units
(lps)
Transfer to NSP-1
Transfer to NSP-2
Transfer to NSP-4
280
648
567
320
6
4
2
3
3
2
1
2400
2200
2160
230
550
415
255
Head
(m)
92
100
26.5
61
92
89
65
Note: Existing pump capacities are based on best available, reliable data. This will need
to be verified prior to detailed design.
The CIS covers an area of 1,815 ha. The system was previously designed for considering
on-farm irrigation such as sprinkler irrigation using 51 laterals type DS 25/300, and 16
self propelled center pivot FREGAT. The pipe network consists of:
Total Length 39,671 m;
Diameter range 100 mm to 1000 mm;
Pipe Material Steel, Asbestos-cement, Reinforced precast concrete, RTNS
(concrete-encased steel)
STI Hincesti currently manages this CIS. For additional details on the Carpineni CIS,
please refer to Annex 4.
2.3.5 Leova Sud
This CIS derives water from the Prut River. The system is served by one primary pump
and one pressure pump stations. Details of the pump stations capacities are provided in
Table 2-7.
Table 2-7
Pump Stations Serving Leova Sud
Irrigation
Number of Total Pump
Pump
Head
Area
Pump
Capacity
Station
(m)
(Ha)
Units
(lps)
S-28
S-2
Transfer to S-2
963
6
9 (all missing)
1560
898
128
53-91
Note: Existing pump capacities are based on best available, reliable data. This will
need to be verified prior to detailed design.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-12
1980
2437
Drainage
Drainage
4
3
3
2
4
660
200
750
670
800
3500
57
57
54
57
13
22
Note: Existing pump capacities are based on best available, reliable data. This will
need to be verified prior to detailed design.
The rehabilitated CIS is anticipated to cover an area of 4,417 ha. The system was
previously designed assuming on-farm irrigation such as sprinkler irrigation using 48
laterals type DDA-100 MA. The pipe network includes:
Total Length 90,660 m;
Diameter range 250 mm to 700 mm;
Pipe Material Steel, Asbestos-cement, Reinforced precast concrete, RTNS
(concrete-encased steel).
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-13
Pump
Station
SPP-3A
SPP-1
SPP-2
SPP-3
Table 2-9
Pump Stations Serving Cahul
Irrigation
Number
Total Pump
Area
of Pump
Capacity
(Ha)
Units
(lps)
449
806
Drainage
675
Drainage
Drainage
4
4
2
3
3
3
Head
(m)
880
1200
1400
700
1200
3000
57
54
17
10
21
20
Note: Existing pump capacities are based on best available, reliable data. This will
need to be verified prior to detailed design.
The system will cover an area of 1,930 ha. The system was previously designed
considering on-farm irrigation such as sprinkler irrigation using 45 laterals type DDA100 MA. The pipe network comprises:
Total Length 39,790 m;
Diameter range 300 mm to 1000 mm;
Pipe Material Steel, Asbestos-cement, Reinforced precast concrete, RTNS
(concrete-encased steel)
STI Cahul manages this CIS. For additional details, please see Annex 7.
2.3.8 Jora de Jos
This CIS derives water from the Nistru River. The system is served by two primary pump
stations and two pressure pump stations. Details of the pump stations capacities are
provided in Table 2-10.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-14
Pump
Station
SPP-1
SPP-2
Table 2-10
Pump Stations Serving Jora de Jos
Number Total Pump
Irrigation Area
of Pump
Capacity
(Ha)
Units
(lps)
235
Transfer to SP-1
100
259
Transfer to SP-2
80
272
213
SP-1
SP-2
2
3
2
2
2
2
2
2
Head
(m)
220
630
110
360
500
120
140
210
75
60
95
90
195
92
53
44
Note: Existing pump capacities are based on best available, reliable data. This will
need to be verified prior to detailed design.
The system will cover an area of 1,159 ha. The system was previously designed
considering on-farm irrigation such as sprinkler irrigation using 5 laterals type DNEPR,
20 laterals type DS 25/300, and 5 self propelled center pivot FREGAT. The pipe
network consists of:
Total Length 37,629 m;
Diameter range 150 mm to 500 mm;
Pipe Material Steel, Asbestos-cement, Reinforced precast concrete, RTNS
(concrete-encased steel)
STI Orhei currently manages the CIS. For additional details, please refer to Annex 8.
2.3.9 Lopatna
This CIS derives water from the Nistru River. The system is served by two primary pump
stations and two pressure pump stations. Details of the pump stations capacities are
provided in Table 2-11.
Table 2-11
Pump Stations serving Lopatna
Pump
Station
Irrigation
Area
(Ha)
Number
of Pump
Units
Total Pump
Capacity
(lps)
Head
(m)
SPP
Transfer to SP
468
110
358
148
SP
By gravity
180
50
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-15
The system will cover an area of 506 ha. The system was previously designed for
considering on-farm irrigation such as sprinkler irrigation using 13 laterals type DDN70. The pipe network comprises:
Total Length 29,223 m;
Diameter range 150 mm to 600 mm;
Pipe Material Steel, Asbestos-cement, Reinforced precast concrete, RTNS
(concrete-encased steel)
STI Orhei currently manages this CIS. For additional details, please see Annex 9.
2.3.10 Conia
This CIS derives water from the Nistru River. The system is served by five pump
stations. Details of the pump stations capacities and areas served are provided in Table
2-12.
Pump
Station
SP-1
SP-2
SP-3
S-1
SP-4
Table 2-12
Pump Stations Serving Conia
Irrigation
Number Total Pump
Area
of Pump
Capacity
(Ha)
Units
(lps)
986
353
Transfer to S-1
620
578
263
6
6
2
3
2
3
Head
(m)
880
440
1100
660
460
395
69
98
14
85
155
50
Note: Existing pump capacities are based on best available, reliable data. This will
need to be verified prior to detailed design.
This system will cover an area of 2,800 ha. The system was previously designed for
Sprinkler irrigation laterals DNEPR, sprinkler hand-move aluminum laterals, and
DDA 100MA a side-move sprinkler lateral pulled by a tractor, and Fregat center
pivot type. The pipe network includes:
Total length 105,770 m;
Diameter range 150 mm to 800 mm;
Pipe Material Steel, reinforced concrete, RTNS (concrete-encased steel), and
asbestos-cement;
STI Dubasari currently manages this CIS. For additional details, please refer to Annex
10.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-16
2.3.11 Criuleni
This CIS derives water from the Nistru River. The system is served by three irrigation
pump stations. Details of the pump stations capacities and areas served are provided in
Table 2-13.
Pump
Station
NSP-1
NSP-2
NS-3
Table 2-13
Pump Stations Serving Criuleni
Irrigation
Number
Total Pump
Area
of Pump
Capacity
(Ha)
Units
(lps)
459
122
Transfer to
NS-3
96
Head
(m)
2
1
360
180
62
50
1
2
360
160
50
70
Note: Existing pump capacities are based on best available, reliable data. This will need to
be verified prior to detailed design.
This system will cover an area of 677 ha. The system was previously designed for
sprinkler irrigation using laterals type Sigma, DD-30 and Dnepr. The on-farm watering
system for NSP-2 was the side-move sprinkler system pulled by a tractor; water was
suctioned by an auxiliary pressurizing pump attached to the lateral. The pipe network
comprises:
Total length 55,299 m;
Diameter range 150 mm to 800 mm;
Pipe Material Steel, reinforced concrete, concrete-encased steel, and asbestoscement;
STI Chisinau currently manages this CIS. For additional details on the Criuleni CIS,
please see Annex 11.
2.3.12 erpeni
This CIS derives water from the Nistru River. The system is served by three irrigation
pump stations. Details of the pump stations capacities and areas served are provided in
Table 2-14.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-17
Pump
Station
S-10
S-12
S-14
Table 2-14
Pump Stations Serving erpeni
Total
Number
Irrigation Area
Pump
of Pump
(Ha)
Capacity
Units
(lps)
Transfer to S-12
670
Transfer to S-14
437
Head
(m)
2
2
700
280
70
70
280
70
350
85
Note: Existing pump capacities are based on best available, reliable data. This will
need to be verified prior to detailed design.
This system will cover an area of 1,107 ha. The system was previously designed for
sprinkler irrigation laterals Fregat a center pivot type, a side-move sprinkler lateral
DNEPR, the DD-100MA, and sprinkler hand-move aluminum laterals. The pipe
network consists of:
Total length 27,968 m;
Diameter range 181mm to 530 mm;
Pipe Material Steel, reinforced concrete, and asbestos-cement;
STI Chisinau currently manages this CIS. For additional details, please see Annex 12.
2.3.13 Puhceni
This CIS derives water from the Nistru River. The system is served by two pump stations
independent from each other. Details of the pump stations capacities and areas served
are provided in Table 2-15.
Pump
Station
S-17
S-18
Table 2-15
Pump Stations Serving Puhceni
Total
Irrigation
Number of
Pump
Area
Pump
Capacity
(Ha)
Units
(lps)
438
418
3
3
420
300
Head
(m)
65
45
Note: Existing pump capacities are based on best available, reliable data. This will
need to be verified prior to detailed design.
This will cover an area of 856 ha. The system was previously designed for sprinkler
irrigation using hand-move aluminum laterals. The pipe network comprises:
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-18
Pump
Station
S-20
S-22
Table 2-16
Pump Stations Serving Rocani
Number of Total Pump
Irrigation Area
Pump
Capacity
(Ha)
Units
(lps)
Transfer to S-22
682
3
4
780
960
Head
(m)
92
92
Note: Existing pump capacities are based on best available, reliable data. This will
need to be verified prior to detailed design.
This system will cover an area of 682 ha. The system was previously designed for
sprinkler irrigation Fregat, a type of center pivot sprinkler on-farm irrigation system;
these are no longer in use or are too old for efficiently distributing the water. The pipe
network includes:
Total length 13,501 m;
Diameter range 200 mm to 500 mm;
Pipe Material Steel and concrete-encased steel (RTNS);
STI Chisinau manages the CIS. For additional details on the Rocani CIS, please refer to
Annex 14.
2.3.15 Talmaza
This CIS derives water from the Nistru River. The system is served by three irrigation
pump stations and thee drainage pump stations. Details of the pump stations capacities
and areas served are provided in Table 2-17.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-19
Pump
Station
ONS-1
NS-2
Table 2-17
Pump Stations Serving Talmaza
Irrigation
Number of Total Pump
Area
Pump
Capacity
(Ha)
Units
(lps)
D-1
D-2
Transfer NS-2
465
801
1202
Drainage
Drainage
T-3
Drainage
T-2
4
3
4
3
2
2
2
3
2800
660
800
1200
330
330
800
3000
Head
(m)
5.5
70
90
90
10
10
20
20
Note: Existing pump capacities are based on best available, reliable data. This will
need to be verified prior to detailed design.
This system will cover an area of 2,468 ha. The system was previously designed for
sprinkler irrigation using laterals Fregat (center pivot type), DDA-100 equipment,
and the hand-move aluminum sprinkler type. The pipe network comprises:
Total length 92,774 m;
Diameter range 150 mm to 700 mm;
Pipe Material Steel, reinforced concrete, RTNS (concrete-encased steel), and
asbestos-cement;
STI Stefan Voda currently manages this CIS. For additional details, please see Annex
15.
2.3.16 Suvorov
This CIS derives water from the Nistru River. The Caplani reservoir, a part of the
Suvorov scheme, provides irrigation water storage retained by an earth dam made of
compacted clay. The height of the dam is of 15 m providing a maximum storage volume
of the reservoir is 8,300,000 m3 and a minimum volume of 1,000,000 m3. The
downstream slope is protected with grass and the upstream slope is protected with
reinforced precast concrete slabs. Details of the pump stations capacities and areas
served are provided in Table 2-18.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-20
Pump
Station
GNS
NSP
PNS-1
PNS-1
Table 2-18
Pump Stations Serving Suvorov
Irrigation
Number
Total Pump
Area
of Pump
Capacity
(Ha)
Units
(lps)
Transfer to
NSP
Transfer to
PNS-1
1827
Head
(m)
6200
80
6200
80
2200
85
2200
85
1500
51
PNS-2
430
Transfer to
PNS-2
2069
1620
80
PNS-3
PNS-4
939
2206
3
3
710
2100
73
80
PNS-5
159
880
57
PNS-6
200
500
PNS-7
340
395
PNS-7
320
300
84
Fed by
gravity
55
S-1
S-2
Transfer to S-2
770
5
4
2260
720
90
57
S-2
1380
1290
66
S-2
Transfer to S-3
1650
40
S-3
S-3
2017
737
6
3
1470
600
90
68
PNS-1
Note: Existing pump capacities are based on best available, reliable data. This will need
to be verified prior to detailed design.
This system will cover an area of 13,394 ha. The system was previously designed for
sprinkler irrigation applied using center pivots type Fregat, DNEPR, DDA-100, and
solid set. The piping network consists of:
Total length: 327,601m;
Diameter range 150 mm to 800 mm;
Pipe Material Steel, reinforced concrete, concrete-encased steel, and asbestoscement;
STI Stefan Voda currently manages this CIS. For additional details on the Suvorov CIS,
please see Annex 16.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-21
2.4
There are several international donor agencies involved in the irrigation sector in
Moldova. The following donor projects are not directly linked to the rehabilitation of the
CIS and some are not directly related to the irrigation sector, however they may have
links to the success of the outcome of the MCC investment, namely in the transition to
HVA.
World Bank: RISP II the second phase of the Rural Investment and Services
Program. The RISP II objective is to provide long-term support to accelerate
agricultural recovery and growth as a basis for future income growth and poverty
reduction by improving access of farmers and rural entrepreneurs to know-how,
knowledge and financial services, while building the capacity of the private and
public institutions to ensure the sustainability of these activities. It includes
irrigation finance services.
World Bank: AG Pollution Control (GEF) The project aims to increase the
use of mitigation measures by agro-industry and farmers to reduce nutrient
discharge into the surface and ground water bodies in Moldova.
World Bank: Road Sector Program Support Project This support aims to
reduce road transport costs for road users in Moldova by improving the condition
and quality of its road network and the way it is managed.
EU: European Neighborhood and Partnership Programme This program,
amongst other objectives, aims to contribute to poverty reduction and economic
growth in part by improving regional and municipal infrastructure, and border and
customs regimes to support trade.
United Nations Development Programme: Moldova Country Programme The overall objective is to facilitate Moldovas achieving the Millennium
Development Goals. It includes a good governance program and a regional and a
local development program.
The Swedish International Development and Cooperation Agency (SIDA)
concentrates on pro-poor economic growth amongst other areas.
The Swiss Agency for Development and Cooperation's (SDC) programs in
Moldova include the promotion of the access to financial services for the rural
population.
The United Kingdom's Department for International Development (DFID)
provides aid to Moldova part of which is aimed at encouraging pro-poor
economic growth.
From April 2001, the Republic of Moldova has benefited from a technical grant
provided by the Japanese Government through the 2KR Moldovan-Japanese
Program for implementation of Increase of Food Production Project in
agriculture. Moldova Agricultural Producers Association is responsible for
running the project as the representative of associated farmers. The project helps
the farmers to procure (leasing) agriculture machinery including irrigation
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-22
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
2-23
3.1
Assessment Methodology
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-1
December 2009
Pump and motor units were assessed as good when all visual observations of the previous
criteria yielded favorable results. The pumping units were in good working order, and
should provide long equipment life. An assessment of fair was given to pumping units
that required minimum work to repair based on the above criteria. An assessment of poor
was rendered to equipment that was inoperable and required substantial repairs or
replacement.
The pump station piping was assessed as good, fair or poor primarily based on visual
inspection of the coatings. Piping assessed as good exhibited no visible defects along
with an intact coating. This type of piping was viewed as maximizing the life of the pump
station piping. An assessment of fair was given to piping that exhibited only slight
corrosion or required minor repairs. An assessment of poor was provided to piping that
showed considerable structural damage or corrosion.
Pump station valves, both isolation and check, were also assessed based on visual
observations. Assessment was primarily based on visible structural damage to the valve
or valve operator, signs of damaged seals or corrosion to the valve body and operator
comments. An assessment of good was provided to valves that were in good working
order and did not show signs of coating damage or corrosion. An assessment of fair was
provided to valves that were functional, but exhibited signs of corrosion or damage. An
assessment of poor was provided to valves that were inoperable.
Smaller ancillary systems were assessed based on missing components and corrosion on
the piping or valves.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-2
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-3
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-4
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-5
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-6
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-7
December 2009
3.2
Available data was compiled to assess the total area being irrigated within each STI. This
list is limited to the eight (8) STI where rehabilitation of CIS is being proposed. A
summary of the irrigation areas under each STI based on 1998, 2007 and 2008 records is
provided in Table 8-1.
Table 3-1
Area under Irrigation in Moldova
Area under Irrigation (Ha)
STI
19981
20071
20082
Briceni
8,519
7,582
7,582
Ungheni
9,155
11,019
11,019
Hincesti
12,446
12,046
9,593
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-8
December 2009
20071
20082
Cahul
34,181
29,563
20,529
Orhei
3,737
3,242
2,464
Dubasari
7,621
8,184
8,184
Chisinau
21,889
24,891
22,202
Stefan-Voda
25,506
26,379
24,248
Total Area
123,054
122,906
105,821
1.
2.
The data on the total available irrigation area within each of the STI was neither coherent
or consistent, so it was not possible to assess the percentage of the total available area
being irrigated. Also, data for area irrigated for years between 1998 and 2007 was not
readily available.
Between 1998 and 2007, although there were fluctuations within individual STIs, the
total combined area under irrigation for all eight STI was relatively stable. However,
there was a 14% decline in the total combined area irrigated between 2007 and 2008.
Discernible declines in area under irrigation occurred in Cahul, Hincesti, Stefan Voda and
Chisinau. Discussions with AM and the respective STI provided a myriad of reasons for
this decline, ranging from dilapidated, unreliable CIS infrastructure to land fragmentation
and foreign migration that has contributed to a general decline in agricultural activities.
Data was also compiled specific to the CIS under consideration for rehabilitation. The
total area under irrigation in 2008 is provided in provided in Table 3-2.
Table 3-2
Areas irrigated in 2008 within the
CIS under Consideration
CIS
Area Irrigated (ha) 1
Tetcani
Blindeti
Grozeti
Crpinenii de Sus
Leova Sud
Chircani-Zrneti
Cahul
Jora de Jos
Lopatna
Conia
Criuleni
erpeni
52
0
20
69
0
0
0
119
47.5
642.9
46.5
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-9
December 2009
Puhceni
Rocani
Talmaza
Suvorov
Total Area
55
123.9
85
2,528.9
3,789.7
3.2.1 Tetcani
The table below provides an overview of the assessment of the existing CIS infrastructure
at Tetcani.
Table 3-3
Assessment of Existing Infrastructure at Tetcani CIS
Need to be
Need to be
Components
Replaced
Repaired/ or Remarks
River Intake
Fish protection structures
Sets
Pipes Length (m)
Valves Number
Pump Stations
Number of Pumps
Number of Motors
Station Piping length (m)
Number of Station Valves
Number of Ancillary
Systems
Suction and discharge
pipe Length (m)
Number of Basins
Electrical Systems
10 kV Power Line
10 kV/0.4 kV Transformer
6 kV Switchgear
0.4 kV Switchgear/Control
Panels
Automation Panels
Motor Starting Devices
Power Cables/Racks
Control Cables
Underground Pipe Network
0
0
0
0
1
5
60
34
19
15
535
26
6555
2
3
2 Lineups
0
1 Lineup
2 Lineups
2 Lineups
0
0
2
2
0
0
0
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-10
December 2009
Need to be
Replaced
Need to be
Repaired/ or Remarks
8,446
103
32
0
184
0
Condition unknown
Pipe condition unknown.
Exterior asphalt corrosion
protection is significantly
weathered. Exterior corrosion
protection needs to be added.
Conduit
Spillway
Remove and
replace
Inlet
Conduit
Stilling Basin
Remove and
replace
May be needed
Emergency Spillway
Instrumentation
Add piezometers
and movement
monuments
3
0
0
Pump Stations
0
13
0
0
0
13
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-11
December 2009
Need to be
Replaced
Need to be
Repaired
135
16
2
0
0
0
1 Lineup
1 Lineup
0
0
0
0
0
0
0
0
0
0
4
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-12
December 2009
Need to be
Replaced
Need to be
Repaired
27
22
1
0
1
0
1 Lineup
2 Lineups
0
0
0
0
0
294
0
3
0
0
Pump Stations
29
29
0
0
0
0
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-13
December 2009
Upstream Slope
Crest and Toe Road
Downstream Slope
Toe Drain
Inlet
Conduit
Stilling Basin
Inlet
Conduit
Stilling Basin
Emergency Spillway
Need to be
Replaced
Need to be
Repaired/ or Remarks
540
85
10
238
30
0
1170
0
Electrical Systems
4 Lots
4 Lots
3
5 Lineups
4
0
0
0
0
0
0
0
0
5 Lots
0
5 Lots
0
Underground Pipe Network
7,900
0
438
188
0
43
Dam
Concrete slope
protection needs to be
replaced
Crest road needs regarding,
addition of sub base and base
course road surfacing.
Some regarding in areas that are
irregular.
Remove and replace
manholes, add
seepage weirs
Condition unknown
Condition unknown
Remove and replace
Remove and replace
Condition Unknown. Add
seepage diaphragm around
conduit.
Remove and replace
May be needed
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-14
December 2009
Components
Instrumentation
Need to be
Repaired/ or Remarks
This CIS is being reconfigured to pump directly from the River Prut, by adding 3 new PS
to pump directly to NSP-4 and NSP-7, and abandoning NSG-2 and the associated dam.
For more detailed assessment, please refer to Annex 4.
3.2.5 Leova Sud
The table below provides an overview of the assessment of the existing conditions at
Leova Sud.
Table 3-7
Assessment of Existing Infrastructure at Leova Sud CIS
Need to be
Need to be
Components
Replaced
Repaired
River Intake
Fish protection structures
Sets
Pipes Length (m)
Valves Number
Pump
Motors
Station Piping
Station Valves
Ancillary Systems
Suction and discharge
pipes-Length (m)
Basins
2
0
0
Pump Stations
6
12
0
3
2
80
0
Electrical Systems
10 kV Power Line,
Transformers, CBs, DSs
6 kV Switchgear
Control Panels for 6 kV
pumps
0.4 kV Switchgear/Control
Panels
Automation Panels
Motor Starting Devices
0
0
0
3
0
0
21
0
0
2
1 Lot
1 Lot
1 Lineup
2 Lineups
0
0
0
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-15
December 2009
Need to be
Replaced
2 Lots
2 Lots
Underground Pipe Network
Pipes Length (m)
3,055
Number of Hydrants
79
Number of Valves
40
Power Cables/Racks
Control Cables
Need to be
Repaired
0
0
0
247
0
9
0
0
Pump Stations
14
20
125
34
9
1030
0
Electrical Systems
4 Lots
4 Lots
0
0
0
6
0
175
9
0
0
0
2 Lineups
0
0
0
5 Lineups
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-16
December 2009
Components
Motor Starting Devices
Power Cables/Racks
Control Cables
Pipes Length (m)
Number of Hydrants
Number of Valves
Channels Length (m)
0
5 Lots
5 Lots
Underground Pipe Network
30,130
745
101
Drainage Channel Network
0
Need to be
Repaired
0
0
0
0
0
0
69,240
1700
0
Pump Stations
7
Pump Number
18
Motors Number
0
Station Piping Length (m)
18
Station Valves Number
Ancillary Systems
9
Number
Discharge pipe Length
1380
(m)
0
Basins Number
Electrical Systems
0
10 kV Power Line
1
10 kV/0.4 kV Transformer
0
6(10) kV Switchgear
0.4 kV Switchgear/Control
1 Lineup
Panels
0
0
0
9
0
385
37
1
0
0
0
0
3 Lineups
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-17
December 2009
Need to be
Replaced
0
Automation Panels
0
Motor Starting Devices
1 Lot
Power Cables/Racks
1 Lot
Control Cables
Underground Pipe Network
Pipes Length (m)
10,567
Number of Hydrants
417
Number of Valves
50
Drainage Channel Network
Channels Length (m)
0
Need to be
Repaired
0
0
0
0
0
0
0
96,770
0
0
0
8
0
268
38
6
0
0
1 Lineup
4 Lineups
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-18
December 2009
Need to be
Replaced
0
Motor Starting Devices
0
Power Cables/Racks
0
Control Cables
Underground Pipe Network
8458
Pipes Length (m)
497
Number of Hydrants
109
Number of Valves
Need to be
Repaired
0
0
0
0
0
0
0
0
0
6
0
6
0
34
0
0
1 Lineup
0
0
0
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-19
December 2009
Need to be
Replaced
Need to be
Repaired
0
199
89
0
0
0
0
0
0
3
0
404
26
12
0
0
0
0
2 Lineups
0
0
0
0
0
0
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-20
December 2009
0
0
0
0
0
45
9
3
0
0
0
3 Lineups
0
0
0
0
0
18
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-21
December 2009
0
0
0
0
0
65
6
5
1
0
0
0
2 Lineups
0
0
0
0
0
0
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-22
December 2009
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-23
December 2009
0
0
0
3
0
0
15
3
0
0
0
0
0
0
0
0
0
8
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-24
December 2009
0
0
0
19
0
575
61
6
3
0
0
0
0
0
0
0
0
10
15
48,000
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-25
December 2009
Upstream Slope
Toe Drain
12
570
0
Pump Stations
34
68
130
46
9
0
Electrical Systems
0
0
0
38
0
891
168
20
10
2 Lots
6 Lineups
4 Lineups
7 Lineups
7 Lineups
0
0
7 Lots
8 Lots
Underground Pipe Network
87,579
2,591
446
Caplani Dam
Concrete slope
protection needs to
be replaced
Remove and replace
manholes, add
seepage weirs
0
0
0
0
0
124
0
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-26
December 2009
Need to be
Replaced
Inlet
Conduit
Condition unknown
Condition unknown
Remove and Replace 10
meters of reinforced concrete
pipe
Conduit
Stilling Basin
Emergency Spillway
Instrumentation
Need to be
Repaired/ or Remarks
May be needed
Rehabilitate existing
piezometers
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
3-27
December 2009
http://eb.adbureau.net/jnserver/acc_random=3819702098/site=DARWIN_C/area=ARTICLES/aamsz=400x50/pageid=19112
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
4-2
December 2009
Very low
low
moderate
high
> 16,000
very high
Table 4-2
Soil Sodicity through ESP Level
Exchangeable
Sodicity Risk Level
Sodium
that Affect Soil
Percentage
<3
3-6
6 - 10
10 - 15
Very low
low
moderate
high
> 15
very high
In general, soil salinity and high water table are closely related. At the CIS reported with
potential salinity-sodicity problems, drainage has been a concern and likely the probable
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
4-3
December 2009
Tetcani
Blindeti
Topography
This CIS relief is undulated, located
in a medium elevation plateau. The
maximum elevation difference across
the CIS is approximately 50 m, with
slopes varying from 0.01 to 0.07.
This CIS terrain is relatively flat. The
maximum elevation difference is
about 40 m within the command area
of pump station SP-7.
Soil Type1
Drainage
Chernozem,
Chernozem
Carbonated
Chernozem,
which has
medium to
good potential
for HVA.
Grozeti
Crpinenii
de Sus
Chernozem
Leova
Sud
Chernozem
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
4-4
December 2009
Topography
Soil Type1
Drainage
protection is needed.
ChircaniZrneti
Cahul
Jora de
Jos
Lopatna
Chernozem
Chernozem
Chernozem
Chernozem
Conia
Chernozem
Criuleni
Chernozem
erpeni
Chernozem
Puhceni
Chernozem
Rocani
Chernozem
Talmaza
Chernozem
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
4-5
December 2009
Topography
Soil Type1
Drainage
4.5
As mentioned above, soil salinity and sodicity assessment was undertaken at the
following CIS:
Crpinenii de Sus
Chircani-Zrneti
Cahul
Talmaza
Suvorov
Maximum
Minimum
Average
0-30
30-60
0-30
30-60
0-30
30-60
999
806
313
316
566
556
Maximum
0-30 cm
1.73
30-60 cm
1.42
Minimum
0-30 cm
0.81
30-60 cm
0.54
Average
0-30 cm
1.27
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
4-6
December 2009
30-60 cm
0.98
Maximum
Minimum
Average
0-30
30-60
0-30
30-60
0-30 cm
30-60
3,040
4,100
338
349
1,050
1,209
Maximum
0-30 cm
0.56
30-60 cm
5.29
Minimum
0-30 cm
0.39
30-60 cm
0.37
Average
0-30 cm
0.46
30-60 cm
2.26
The table above shows that salinity values are mostly within the low category for
salinity content risk to crops (i.e. between 2000-4000 as per Table 4-1). Maximum values
in the range of 3,000 to 4,100 S/cm were from samples taken in fields under
waterlogged conditions along the area east of pump station S-5. Soils in these areas could
be classified as saline. Please refer to Appendix H for more details including location of
these areas considered saline.
There are no sodicity problems. The exchangeable sodium percentage for both depths is
below the very low level threshold (less than 3%). The occurrence of water on the soil
surface is an indication of poor or non-existent drainage. Lack of movement of the water
through the soil profile and surface water evaporation may temporarily increase the salt
concentration; however, it does not necessarily mean that the soil is saline. If the situation
is not remediated by providing proper removal of excess water (drainage), with time the
soil will become saline.
To facilitate sustainable irrigation, drainage system at this CIS should be rehabilitated
and be maintained in a properly functioning manner. An annual monitoring program
should also be established to monitor groundwater tables, electro-conductivity and
specific salts as necessary to conduct salinity & sodicity assessments.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
4-7
December 2009
Maximum
Minimum
Average
0-30
30-60
0-30
30-60
0-30
30-60
1,595
1,800
344
502
1,061
1,074
Maximum
0-30 cm
1.02
30-60 cm
0.3
Minimum
0-30 cm
0.1
30-60 cm
0.12
Average
0-30 cm
0.42
30-60 cm
0.19
The results from the salinity tests are clustered around an average value of 1,000 S/cm,
which are classified as low salinity risk. The maximum values are also less than 2000,
further substantiating the low range of soil salinity risk for crops. The ESP results show a
very low risk of sodicity problems.
There are indications that lack of proper drainage could create a salinity problem over
time in the future. As such it is recommended that the drainage system be rehabilitated
and be maintained. Also, an annual monitoring program should be established to monitor
groundwater tables, electro-conductivity and specific salts as necessary to conduct
salinity and sodicity assessments.
For more detailed discussion of this assessment, please refer to Appendix H.
4.5.4 Talmaza
The summary of data sampled and analyzed for this CIS is provided in Table 4-7.
Table 4-7
ECsw of Measured Soil Salinity and Sodicity Status at Talmaza
Parameter
Depth (cm)
Salinity - ECsw
(S/cm)
ESP
(Exchangeable
Sodium %)
Maximum
Minimum
Average
0-30
30-60
0-30
30-60
0-30
30-60
1,953
2,061
394
342
1,285
1,404
Maximum
Minimum
Average
0-30 cm
30-60 cm
0-30 cm
30-60 cm
0-30 cm
30-60 cm
3.01
3.23
0.53
0.55
1.77
1.89
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
4-8
December 2009
Maximum
Depth (cm)
Salinity - ECsw
(S/cm)
ESP
(Exchangeable
Sodium %)
Minimum
Average
0-30
30-60
0-30
30-60
0-30
30-60
808
743
787
690
798
717
Maximum
Minimum
Average
0-30 cm
30-60 cm
0-30 cm
30-60 cm
0-30 cm
30-60 cm
0.51
0.53
0.51
0.53
0.51
0.53
The salinity measurement results currently indicate a very low risk condition. The
sodicity assessment also indicates no cause for concern. For more detailed assessment,
please refer to Appendix H.
Chircani-Zrneti
Cahul
Talmaza
Suvorov
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
4-9
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
4-10
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
4-11
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
4-13
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
4-15
December 2009
5.0
This section presents an overview of viability of the water resources in Moldova based on
available water quality and quantity data to support irrigation. In addition, an evaluation
of availability of water from existing sources to support prevailing water demands and
those resulting from the rehabilitation of CIS, including an assessment of the impacts of
climate change on these resources, is also provided.
5.1
Summary
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-1
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-2
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-3
December 2009
5.2
Data Collection
Water resources management responsibilities lies within four State agencies. Each has
direct responsibilities for the collection and processing of data on water and the reporting
of this information to different international institutions and committees (Tafi, 2005).
These are:
Apele Moldovei (AM) - The State Water Agency under the Ministry of
Agriculture, is the authority that approves the water use, coordinates the
authorization of water use, and controls the use of water for irrigation, water
abstraction, and the supply and discharge of water for industry, municipalities,
and farms. They are the main source for statistical reporting on water use.
Ministry of Ecology and Natural Resources (MENR) - The governing body for
environmental protection of water and the only authority entitled to issue the
water use permit. Four institutional departments and agencies of the ministry
participate in water resource surveillance. These are:
State Ecological Inspectorate, which consists of 12 territorial
organizations and 4 zonal laboratories.
Hydro-meteorological service Hydrometeo (HMS).
State Geological Agency MoldaGeoM.
National Institute of Ecology.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-4
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-5
December 2009
5.3
Climate
Moldova's climate is moderately continental: the summers are warm and long, with
average July daily temperatures of about 20C with a range between 23oC and 17oC; the
winters are relatively mild and dry, with January temperatures averaging -4C with a
range between -14oC and 2.8oC.
As presented in Figures 5-1, precipitation varies from up to 603 mm/year in the north of
the country to up to 482 mm/year in the south with potential evaporation ranging from
600 mm/year in the north to 790 mm/year in the south.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-6
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-7
December 2009
These agreements provide for a 50 50 split in ownership of the water, but do not specify
an environmental (base) river flow or a specific flow that needs to be released from
reservoirs. Since about 90% of the water available to Moldova originates outside its
borders, ensuring that these agreements are maintained is of vital importance to Moldova
for sustaining the rehabilitated CIS over the long run.
There are major dams controlling water entering Moldova:
The Dnestrovsky (or its alternatively seen spelling Dniestrovsky) Dam and a
downstream buffer dam located just above the Moldovan border with Ukraine.
These dams control the flow and to some extent the overall water quality of the
Nistru River, especially the temperature since the outlet for the water is 12 meters
below the water surface. The downstream buffer dam is supposed to warm the
water but this dam is used for storage and a pumping system to move the water to
another reservoir. Flows are quite variable at the outlet to the Dniestrovsky and
over a period of 33 days during peak runoff (March 13 to April 15) the flow
varied from 647 m3/sec to 1,250 m3/sec with peak flows occurring on March 16.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-8
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-9
December 2009
Major tributaries in Moldova include the Bic which runs through Chisinau, Raut, Botna,
and Ichel (Brlund et al, 2005). Near Ciobruci Village in Moldova (148 km from the
mouth), the navigable channel of the Nistru River bifurcates to form the Turunchuk, or
Novy (New) Nistru, which joins the main Nistru River channel further downstream, near
Belyaevka Village (21 km from the mouth) . The Turunchuk Branch receives about 60%
of the Nistrus total flow. This area has an extensive system of natural lakes that are
located along the Nistru and Turunchuk channels. The largest of them include the
Kuchurgan Liman, Beloe Lake, Putrino Lake, and Tudorovo Lake. This area is
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-10
December 2009
Source: Merkley Et Al, 2009 And Moldova Hydro- Meteorological Service, 2009)
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-11
December 2009
Drought-related statistics were computed for the period of record, using annual flow
below the median value to indicate a drought. Eight droughts occurred during the period
of record (1968, 1972-1973, 1977, 1983-1995, 2000, 2003-2004, and 2007). The longest
of these droughts (drought of record) is over the 13-year period from 1983-95, which
contributed to a total deficit in water of 22,069 million m3 and an intensity of 1,698
million m3/year. Several other, shorter droughts had similar intensities.
Flooding has also occurred with the banks of the Nistru being overtopped on numerous
occasions. For the Nistru, flooding in Moldova is caused by large storm events or rapid
snowmelt occurring in the upper river basin (in Ukraine). Major flooding events have
occurred in 1941, 1955, 1969, 1974, 1980, and the summer of 2008. As illustrated in
Figure 5-5, the events of 1969, 1980, and 2008 had discharges in the Nistru River of over
3000 m3/sec. The 2008 flood was considered the most destructive flood in over 200 years
(Cazac, 2008). The peak flow of this event at the gauging station at Hrusca was around
3362 m3/sec.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-12
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-13
December 2009
Since, like the Nistru, a dam regulates the Prut and with most of its flow originating in
the Ukraine, it is difficult to evaluate the affects of drought on the Prut Rivers flow as no
data was available from gauging stations in the Ukraine. However, flow records were
evaluated for the period from 1961 to 2007 at the Ungheni Station on the Prut River and
illustrated in Figure 5-7. The horizontal black line represents the mean flow for the
period (2818 million m3/year), while the red line represents the 75-percentile flow (1684
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-14
December 2009
Drought-related statistics were computed for the period of record, using annual flow
below the mean value to indicate a drought. Similar to Nistru, tight droughts are
observed during the period of record (1961-1964, 1966-1968, 1983-1987, 1989-1990,
1992-1995, 2000, 2003-2004, and 2007). The longest of these droughts (drought of
record) was over a 5-year period from 1983-87, which had a total water deficit of 3,768
million m3 with an intensity of 754 million m3/year. Several other, shorter droughts had
similar intensities.
Like the Nistru River, the Prut River is also susceptible to flooding. Major events have
occurred in 1941, 1955, 1969, 1974, 1980, and the summer 2008. As illustrated in Figure
5-8, the events of 1969, 1980, and 2008 had discharges of the Prut River over 3000
m3/sec. The 2008 flood was considered the most destructive flood in over 200 years
(Cazac, 2008). The peak flow of this event at the gauging station at Sireuti gauging was
around 3400 m3/sec.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-15
December 2009
5.5 Groundwater
Groundwater in Moldova is extracted from 17 aquifers of different ages that are unevenly
distributed throughout the country. Water from these aquifers varies in water quality
between fresh to sweet to highly mineralized. Six aquifers are considered the most
important due to their sweet water quality nature, hydraulic characteristics and their
aerial extent. These six aquifer systems have been identified in various geologic
formations. These formations are numbered based on geologic age. Geologic age,
formation number, and estimated reserves for each of these six aquifer systems is as
follows:
Phreatic Quaternary (2.5 million years to present) which are normally found along
rivers including the Prut and Nistru (aquifer Q) -22 million m3.
Tertiary/Neogene (2.5 million to 23 million years).
Upper Sarmatian and Pontic (aquifers N2P NIS3+N1M) - 44 million
m3;
Middle Sarmatian (aquifer N1S2) - 110 million m3.
Lower Sarmatian Badenian (aquifer N1S1) - 770 million m3.
Cretaceous (75 million to 135 million years old) (aquifer K2S1+S) - 110 million
m3.
Figure 5-9 illustrates the hydrogeology columnar section based on Moraru and Anderson
(2005) description of the various aquifers in Moldova. This section presents a graphic
description of each geologic formation including formation number, its geologic age, and
hydro-geologic properties. It should be noted that formations including N1S3, portions
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-16
December 2009
Quaternary
Graphic
N2P
N1S3
N1S2
Cenezoic
N1S3+N1m
N1S2
Neogene
N1S2
N1S2
N1S2
N1S1
N1b
PreSilurian
Paleozoic
Silurian
Mesozoic
K2S1+S
Jurassic
Cretaceous
K2S2+N1b
GeologicDescription
HydrogeologicProperties
Alluvial,co l l uvi a l ,e ol i a n ,a nd
Th e s e a re i mpo rta n ta q ui fe rs
l a cu s tri ne we re forme d u ptopo f
i n ri ve rva l l e ys e s pe ci a l l yth e
Ne oge ns tra ta i nri ve rva l l e ys ,d own
Ni s trua ndthe Prut.I nth e
s l o pe fro mhi l l s ,i nfl a ta re s ,a nd i n o l d north e rnpa rtofthe coun try
th e s e a q ui fe rs dra i n di re ctl y
l a ke be ds .Th e s e d e po s i ts co ns i s to f
u ncon s ol i da te dto s e mi cons ol i da te d i n tothe ri ve rs ora re
re cha rge d.I nth e s ou the rn
cl a y,s a n d,gra ve l ,s i t,a nd pa l e o s o i l .
The s e de p os i ts ra n ge i n thi ckne s s from pa rto fthe s e d ra i na ge s ,cl a y
1 m to gre a te r th a n 25 m.
ofte n ove rl i e s the a qui fe r
Toton i a n ,Sarmatian(upper,middleand Ma n yde e pwe l l s pe n tra te
lower),Me oti ci a n,a n dPon ti ci a na ge d th e s e de e pa qui fe rs ys te ms .
rocks a re we l l de ve l o pe d i n Mol dova . Prod ucti o na n ddra wdownva ry
The To to ni a nrocks ,fou ndi nno rth,
con s i de ra b l yd e pe nd i ngon
we s t,a nds ou th e a s tp a rtofth e co untry th e ge ol ogi cs tru ctu re .We l l s
,co ns i s to fl i me s ton e a n dcl a ya n dva ry s u pp l yi ngwa te rfo ri ndu s tryor
i nth i ckn e s s b e twe e n1a n d20m
fo rme rs ta te fa rms mos tl i ke l y
Sa rma ti a nrocks a re di vi de di ntoth re e ha ve fo rme dl a rge cone s o f
h ori zon s a nd a re fou nd ge ne ra l l y
de p re s s i on.Re cha rge o ccurs
througho utthe cou ntry.The l i tho l ogyo f i n o utcro pa re a s a nd
the s e forma ti o ns con s i s tofl i me s ton e , downwa rdl e a ka ge from
s a n d,a n dcl a ya n da re up tos e ve ra l
ove rl yi n gQu a te rn a ryma te ri a l .
h und re ds ofme te rs th i ck.Ponti ci a n
Th e re a re s i xs e ts ofa qui fe rs
s e pa ra te d bycl a ya q ui ta rds .
a ndMe oti ci a n d e p os i ts a re ma i nl y
Th e s e a qui fe rs con s i s tof
foun di nte hs outhe rn p a rtofth e
s a nd s ta n dorl i me s to ne .
co untrya nd cons i s tofcl a y,fi n e
i d
d
dl
l
i
f
The s e ro cks a re e xpos e di n the va l l e y Aqu i fe ri s pre s e ntbu ti s
o fth e Ni s tru a nd i ts tri buta ri e s a nd
bra cki s hi nna tu re .
co ns i s to fch a l ki nte rb e d de d wi th fi ne
gra i n e dma s s i ve l i me s to ne .I ti s
e s ti ma te dtobe 510mth i ck.
The s e de p os i ts a re fo und we l l
Noa q ui fe r
d e ve l op e di nthe Dobroji a nde s s i oni n
s ou th e rn Mol do va .Ra ngi n gfro m
s a n ds to ne a ndcl a ys tone i n the l o we r
p orti o ntocl a y,l i me s tone wi th mi n or
b e ds ofgyps uma nda nhyd ri te i n the
u ppe rmo s tpo rti o nofs e que nce .Th e
tota l thi ckne s s i s be twe e n 70a nd1330
m.
The s e ro cks co ns i s to fs ha l e gra di ng
Noa q ui fe r
i ntoa gre e ni s hgra yq ua tzi te whi ch
u ncon fo rma l l yove rl i e s the cryta l l i ne
b a s e me nt.Ea rl yPa l oe zoi cs tra ta
a ppe a rs tobe mi s s i n go ve rmos to fthe
co untry.The th i ckne s s ofth e Si l uri a n
ra nge s fro ms e ve ra l me te rs to930m
i ncre a s i ngi n the s o uth
On l yi nth e s outhe rn p a rtofMo l do vi a Noa q ui fe r
i ncl os e proxi mi tytoth e Dob roji a n
d e pe s s i on.Ordovi ci a n,De voni a n ,
Ca rbo ni fe rou s ,a n dPe rmi n a re
p roje cte dto be p re s e ntb utha ve be e n
s tu di e dl i ttl e .
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-17
December 2009
10-15
1-3
150,000
100-300
2-10
500
50-100
3,000
2-100
500
3-10
50-100
5-10
50
N 50
C-100-200
S-200-260
N50-100;
NC-150-200
100-200 m in
the Prut
valley
100-200 m in
the Prut
valley
The phreatic (Quaternary) aquifer has the highest number of wells. These wells are often
hand dug and are very shallow. These wells usually have a low yield and serve mainly for
domestic water use. The distribution of the deep aquifers varies throughout the country
with the Middle Sarmatian and Lower Sarmatian-Badenian aquifers being the most
widespread. Deeper aquifers can have yields of up to 100 m3/hr. It is uncertain if the
number of wells in these deeper aquifers is accurate for it is based on limited data.
According to Moraru et al (2005) of over 6,600 wells that have been drilled into the
deeper aquifers only about 3,100 are active. For the most part, the inactive wells remain
unplugged and act as a conduit for pollution from shallow groundwater and surface water
to reach the deeper aquifer systems.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-18
December 2009
Water
Surface, km2
Racovat
1989
4.9
2.1
1.0
6.26
Bic
Bic
1963
32.8
7.42
40.0
490.0
240.0
8.3
4.1
2.8
4.0
9.9
3.3
735.0
88.0
21.7
1.5
12.2
3.4
2.2
62.0
2.2
1.7
1.6
12.0
8.0
67.5
99.2
1.5
2,8
1.0
1.7
4.9
1.8
59.0
27.3
4.4
2.3
2.6
1.9
1.5
15.1
0.7
0.9
0.8
1.9
1954
Caplani
Ceaga
Sarata
Ialpug
Ialpug
Botna
1983
1960
1967
1957
1961
1962
1976
CuciurganIsnovat
1978
Lapusna
Botna
Sarata
Ialpug
Botna
Cainari
Bobei
Bobei
1982
1963
1967
1988
1961
1980
1957
1988
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-19
December 2009
Statistics
SO4 -
Average
Maximum
Minimum
Median
Std. Dev.
85.18
119.34
55.96
87.24
17.01
Statistics
SO4 --
Average
Maximum
Minimum
Median
Std. Dev.
74.93
106.20
45.68
71.80
19.43
Table 5-3
2008 - Prut River Water Quality Summary
HCO3 -- Cl - ++ Mg ++ Na + K + TDS
184.52
222.72
154.08
183.06
21.26
19.79
23.98
14.56
19.55
2.49
53.11
64.13
46.09
53.11
4.93
12.72
17.63
8.51
12.77
2.48
Table 5-4
2008 Nistru River Water Quality Summary
HCO3 - Cl - ++ Mg ++ Na + K + TDS
190.17 31.5
213.70 47.86
167.81 20.84
189.95 27.75
13.42 8.94
63.02
71.14
52.10
63.11
6.45
13.07
26.40
6.00
12.38
4.38
22.73
37.10
2.10
23.40
10.17
11.72
50.50
0.90
10.00
10.39
405.91
478.10
311.72
408.70
53.38
SAR
Hardness
0.91
1.21
0.59
1.00
0.26
185.00
222.74
155.17
183.95
18.41
SAR Hardness
0.68
1.18
0.07
0.69
0.31
212.21
263.85
180.19
209.63
24.64
Figures 5-9 and 5-10 are Piper diagrams based on the above data. Piper diagrams are one
method used to show variations in water quality based on major anion and cation
concentrations. These diagrams indicate that waters from both rivers are dominated by
calcium-magnesium-bicarbonate ions, an indicative of the rainwater origin and calcium
rich soils over which rains fall
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-20
December 2009
Piper Plot
Legend
Legend
60
60
Cl
+
40
Mg
40
BE
E
D
C
E DC
EECB
BEE
DE
C
ABC
CBC
EDAED
C
BE
CDAD
CB D
C CE
20
A
B
C
C
D
D
E
E
B
E
C
80
+
Ca
<=
SO
4=
>
80
Camenca
Naslavcea
Palanca
Soroca
Sucleia
Vadul-lui-Voda
Valcinet
Varnita
Dubasari, Cocieri
Dubasari, Erjovo
Dubasari, Goieni
20
Mg
SO4
80
80
60
60
40
40
ED
A
C
C E
E
D
D
D
D EC
E
DB
D
E
C
C
C
E
B
C
ABE
C
C
E
E
B
A
BC
E
D
C
E
B
Na+K
80
40
20
20
40
60
80
Ca
20
60
EB
C C
E
C
C
D
EACDDDD
C
AE
20 B
EC
E BC EB
D
C
DC C
E AD
BE
BB E
C
HCO3
Cl
Figure 5-11
Piper Diagram-Nistru River Water Quality Characteristics
Piper Plot
Legend
Legend
60
60
40
40
g
+M
Cl
J
I
H
C
A
E
D
C
B
A
80
Ca
<=
+S
O4
=>
80
J
20
JA
C
HC
IH
IJH
AA
r.Prut, Leuseni
r.Prut, Leovo
r.Prut, Djiurdjiulesti
r.Prut, Caslita-Prut
r.Prut, Cahul
r.Prut, Branesti
80
60
60
40
C
C
A
E
C
D
B
H
A
C
JC
A
I
A
HJ
IJH
EA
C
B
D
C C
Na+K
HCO3
80
60
40
20
20
20
40
60
80
Ca
r.Prut, Sculeni
SO4
40
rez.Costesti-Stanca,sect.inferior
EC
A
C
D
BC
80
20
rez.Costesti-Stanca,sect.mediu (Cucunesti)
20
Mg
C
I HAA
JHH
A
I
Cl
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-21
December 2009
250
250 - 750
750 - 2000
2,000 3,000
> 3,000
175
175 - 525
525 1,400
1,400 2,100
> 2,100
Table 5-6 presents a statistical analysis of 2008 water quality data for Prut and Nistru
Rivers. When compared to the values in Table 2-5, these data indicate that, for the most
part, the irrigation waters used from both rivers are within the good range.
Table 5-6
Total Dissolved Solids in Prut and Nistru Rivers
Prut River
Nistru River
Statistic
TDS (mg/l)1
TDS (mg/l)2
Mean
Maximum
Minimum
Median
Std. Dev.
396.77
501.10
319.90
392.35
52.59
405.91
478.10
311.72
408.70
53.38
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-22
December 2009
1- 10
10 -18
18 - 26
>26
Calcium and magnesium, if present in the soil in large enough quantities, will counter the
effects of the sodium and help maintain good soil properties. This appears to be the case
for Prut and Nistru Rivers (See Table 5-8). This is due to the high calcium content of the
water originating from calcarenite aquifers, which is discharged into these rivers.
Table 5-8
Sodium Adsorption Ratio
Prut and Nistru Rivers
Prut River
Nistru
Statistics
SAR1
River SAR2
Mean
Maximum
Minimum
Median
Std. Dev.
0.91
1.21
0.59
1.00
0.26
0.68
1.18
0.07
0.69
0.31
Finally, seasonal trends give a good indication on how water quality varies with flow.
Figures 5-11 and 5-12 illustrate variations in water quality at Sculeni on the Prut River
and Vadul-lui-Voda on Nistru River. Both of these graphs show that during July of 2008,
substantial dilution took place in both rivers. This corresponds to a major flood event.
During low flows, both rivers had higher concentrations of salts.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-23
December 2009
Figure 5-13
Seasonal Variations in TDS and SAR Components
Nistru River
5.7.2 Groundwater
According to Moraru et al (2005), ten water quality parameters used to assess ground
water quality against standards developed by U.S. Environmental Protection Agency
(USEPA), the Moldovan drinking water standards established in 1982, and the World
Health Organization (WHO). These include: pH, total dissolved solids (TDS), total iron
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-24
December 2009
Std. Units
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
6.5 8.5
500
0.3
0.05
0.01
4
2
250
10
250
0.05
6.0 9.0
1000
0.3
0.1
0.05
1.5
350
45
500
0.01
9.5
1000
0.3
0.4
0.01
1.5
250
50
500
0.01
In evaluating over 400 samples from the shallow phreatic aquifer and over 300 samples
from the deeper aquifers, Moraru et al (2005) determined that the shallow aquifer has
elevated levels above standards for each of the parameters with the exception of iron. The
deeper aquifers exceed standards for nitrates, sulfates, chlorides, fluoride, selenium, and
total dissolved solids.
Based on WHO standards, an evaluation was made of the deeper aquifers areas that are
suitable for drinking water (all parameters meeting standards). The results of this study
are presented in Figure 5-13. The green areas indicate ground water unsuitable for
drinking water consumption, while white (uncolored) areas indicate areas that are
suitable. Clearly the majority of the deep aquifer is not suitable. Similarly assessment for
shallow aquifers also came to the conclusion that this source is also unsuitable throughout
the country for drinking water.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-25
December 2009
Unsuitable
Suitable
Pollution can be natural due to high iron concentrations in the formation, or due to man.
Table 5-10 presents a summary of the main pollutants that affect the major aquifers in
Moldova. Pollutant sources are many and can be directly attributed to farm practice and
the poor disposal of waste.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-26
December 2009
Aquifer
Main
Pollutants
Quaternary
(Phreatic)
NO3-, NH4+,
SO42-, NO2-,
pesticides, oil
products
Middle
Sarmatian
BadenSarmatian
Inferior
Cretaceous
Superior
Sarmatian
(Prut Valley)
Pontic (Prut
Valley)
Pollution sources
Waste dumps, storage
places of pesticides,
fertilizers, septic
systems and oil
products
Fe in sand
Waste dumps, storage
places of fertilizers,
natural Ca and Mg
Natural Ca and Mg
Sand
Fe in sand
Sand
Fe in sand
716
135
852
690
119
583
44
35
According to AM, per capita annual water use is estimated to be approximately 224 m3,
and approximately 34 m3 for drinking.
The variations in water use within the various regions of the country are illustrated in
Figure 5-14. In short, water usage has declined from peak usage rates in 1990 to
substantially lower levels in 2007. Basin water demand data is provided in Appendix C.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-28
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-29
December 2009
Figure 5-17
1990 Water Use in The Nistru Basin
Figures 5-15 and 5_16 need units. I assume these are million m3 per year (MCM). For
groundwater, the water of potable quality in fresh water aquifers (the Quaternary and
Neogene aquifers) constitutes about 50% of the reserves, except for the phreatic horizon,
where it is lower (20-30%) because of pollution. The deep groundwater reserves make up
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-30
December 2009
5.9
Water Availability
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-32
December 2009
1697
1008
240
240
729
384
51
51
12
12
665
321
(million m3)
1. Assuming extraction of 1 lps/ha by all seven CIS proposed for rehabilitation
Table 5-13
Nistru River Water Availability after CIS Withdrawal1
(Mid-April through September)
Average
Drought
Nistru River
Flow
Conditions
Conditions
Seasonal Discharge (million m3)
4870
3391
1632
1632
1619
879
98
98
111
111
1410
670
1. Assuming extraction of 1 lps/ha for all nine CIS proposed for rehabilitation.
261
0.57
0.31
0.17
930,000
220,000
710,000
377
0.24
12,206,000
1,023,000
11,183,000
1.3
1.8
0.69
11.9
1.56
83
Based on data in the table above, it is apparent that the existing sources serving Tetcani
and Crpinenii de Sus are not adequate to meet water required for irrigation. Previous
analysis for Prut River (Table 5-12) includes these systems, so evaluation of an alternate
source of water supply would entail extracting water directly from the Prut.
Recognizing this deficit in water, the proposed rehabilitation plans for Crpinenii de Sus
call for extracting water directly from the Prut River. This also mitigates the issue of
salinity that is inherent with the use of water from the Lpunita River.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-34
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-35
December 2009
This above figure indicates that overall, groundwater makes up about 40% of municipal
water supply and 20% of industrial water. And
It is uncertain at this time, if groundwater use will increase. Increasing pollution would
indicate that the volume of groundwater extracted will continue to decline even through
there are sufficient groundwater resources to meet future demands assuming that climate
change does not significantly alter the recharge of aquifer systems. However, with
increasing in-house treatment of groundwater at the taps, the usage of groundwater may
remain steady.
Using the Prut and Nistru River as an alternative to groundwater is possible but pumping
and treatment costs could render to be expensive. Currently, for shallow groundwater
used for villages and for domestic water supplies, NGOs are working with villagers to
treat the water prior to use. However, most low-cost treatment technologies are not
adequate for treating nitrates, pesticides, trace metals, and other potential pollutants found
in groundwater.
For deep aquifers, preventing contamination would ensure its continued viability as a
reliable source where available. The development of wellhead protection programs which
keep pollution sources away from wells, and plugging of abandoned wells, and other
programs specifically designed to reduce the potential of pollution from entering these
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-36
December 2009
High
Medium
High
Medium/high
Low
Slow
Regional
Medium
Medium
Medium
Medium
Medium
Medium
Dynamics as usual
Temperature and precipitation averages for the 1961-1990 30-year normal time period
were used as the basis for Global Climate Model (GCM) derived climate change
predictions. Srodoev and Knight (2007) state that these changes would result in:
Warm winters with very short snow cover period.
Redistribution of precipitation among seasons, negatively affecting the storing
capacity during winter time and flow regime during the growing season.
Rising temperature and evapo-transpiration.
Increasing risk, severity, and area affected by droughts.
Growing severity and risk of extreme meteorological events.
There is a considerable concern of drought in Moldova as much of the agricultural crop
production is rainfed.
(Source: http://www.eoearth.org/article/Water_profile_of_Moldova).
Projections by Corobov, 2008; Lalykin and Syrodoev, 2004; Srodoev and Knight, 2007
and Srodoev I.G., 2008 for Moldovas climate for future periods (up to 2069) indicate
(See Table 5-16):
An increase in temperatures of 0.9 to 3.8C.
A decrease in precipitation decrease in the summer and autumn of about 4 to
20%.
An increase in the winter and spring of about 2 to 13%.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-37
December 2009
C
-2.1
9.5
19.9
9.7
9.2
C
1.2
0.9
1.9
1.4
1.3
%
56.4
9.8
9.5
14.6
14.5
Winter
Spring
Summer
Autumn
Annual
mm
105
125
204
108
542
mm
3.3
2.1
-20.8
-5.3
-21.6
%
3.2
1.7
-10.2
-4.9
-4.0
%
142.2
23.4
19.1
28.5
31.7
C
2.4
1.8
3.4
2.7
2.5
%
113.3
18.7
16.9
27.6
27.5
%
7.4
4.4
-20.3
-6.9
-6.8
mm
13.2
16.4
-34.8
-4.0
-10.1
%
12.6
13.1
-17.1
-3.7
-1.8
Source: Corobov, 2008; Lalykin and Syrodoev, 2004; Srodoev and Knight, 2007 and Srodoev I.G., 2008
Projections for Moldovas stream flow for future periods (up to 2069) indicate (See Table
5-17):
Flow in Prut River decreases by up to 20%.
Flow in Nistru River decreases by up to 18%.
The implications of these changes include:
Increased irrigation water demands due to potentially higher evapo-transpiration.
Reduced rainfall during summer months.
Table 5-17
Projections of Average Annual Flow
Time Period Scenario Q (m3/s) Change (%)
2040-2069
2040-2069
River Nistru
Current
306
A2
260
B2
269
River Prut
Current
86
A2
72
B2
74
-18
-14
-20
-16
Source: Corobov, 2008; Lalykin and Syrodoev, 2004; Srodoev and Knight, 2007 and
Srodoev I.G., 2008)
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-38
December 2009
1392
827
240
240
576
293
51
51
12
12
513
230
Table 5-19
Affect of Climate Change on the Availability of Water for the Nistru River
Basin Water through Year 2040
Average Flow
Drought
Nistru River
Conditions
Conditions
Seasonal Discharge (million m3)
Environmental/Sanitary Flows (million m3)
International Agreement (million m3)
Rehabilitated CIS Irrigation Requirements
(million m3)
Other Demand including industry,
municipalities, etc. less Return Water (million
m3)
Available Water after Withdrawal (million m3)
3994
1632
1181
2780
1632
574
98
98
111
111
972
365
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
5-40
December 2009
6.1
Rehabilitation plans for each CIS were developed based on the assessment of its existing
conditions, and the existing CISs ability to deliver the required water for HVA crop
cultivation, as recommended in the USU report and as directed by MCC. Based on these
crop water requirements, the following criteria established the basis for infrastructure
needs:
Ability for the CIS to supply a flow of 1 lps/ha (established based on MCCs
acceptance of USU recommendation).
A minimum water pressure at the hydrants of 4 bars (established based on
discussions between MCC, MCA-Moldova and Apele Moldovei).
Energy efficient systems.
In defining the infrastructure requirements for the above criteria, the following
assumptions were made:
The typical watering equipment is assumed to be Reel Hose, Hand-moving
laterals, Drip irrigation equipment or of similar kind that function at the
minimum pressure identified.
Discharge rate of the water equipment is assumed to be 20 lps.
Pressure pump stations would need to have adequate capacity to meet the 1 lps/ha
criteria.
Additional details on the basis of rehabilitation plans can be found in Appendix E.
6.1.1 Rehabilitation Based on Proposed Design Criteria
Since the present capacities of existing pump stations and underground pipe networks are
lower or equal to the requested capacity criteria (1 lps/ha), hydraulic analysis was
undertaken for each of the 16 CIS to assess the capacity the system to satisfy the required
design criteria. Subsequently, pumps and pipes were identified for rehabilitation. The
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
6-1
6.2
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
6-2
With this new configuration, the dam would not be part of the CIS, thus no longer
considered for rehabilitation. The proposed schematic with these two pump stations are
provided in Exhibit 3 of Annex 1. The table below provides overview of the two
proposed pump stations.
Table 6-1
Overview of Proposed Pump Stations at Tetcani
Need to be
Need to be
Components
Replaced/Installed
Repaired
Mechanical Equipment
Rehabilitation old Pump Stations
NSG To pump from River
to accommodate the need for
NSP To lift to SP-1
pumping from the river.
9 (Total for both pump stations) to be repaired
Number of Pumps
1200 lps (per Pump Station)
Capacity of Pumps
Head of Pumps
Number of Motors
Station Piping length (m)
Number of Station Valves
Number of Ancillary Systems
Suction and discharge pipe Length
(m)
Number of Basins
18
2
6245
0
2 Lineup
2 Lineups
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
6-3
Need to be
Replaced/Installed
Need to be
Repaired
Automation Panels
Motor Starting Devices
Power Cables/Racks
Control Cables
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
6-4
Mechanical Equipment
Rehabilitation old Pump Stations to
NSG-1 (Pumping from River)
NSP-1 (Transit Pump to NSP-2)
accommodate the need for pumping
NSP-2 (Transit to Existing NSP-4)
from the river.
18
Number of New Pumps & Motors
1840 for each Pump Station
Capacity of Pumps (lps)
NSG-1 86m
NSP-1 - 90m
NSP-2 15m
660
85
2
Number of Basins
2270
2 existing basins to be repaired
3
3
3 Lineup
3 Lineups
3
3
3
3
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
6-5
4,060
80
The proposed schematic for the rehabilitated CIS is illustrated in Exhibit 3 of Annex 12.
6.2.13 Puhceni
The rehabilitation plans for Puhaceni entails:
Replacement/repair of the existing infrastructure as identified in Section 3.2.13.
Replacement of all existing pipes with larger diameter pipes to cope with the
increased capacity (1 lps/ha), and to reduce hydraulic energy losses.
Table 6-4 provides an overview of the replacement of the pipe network as part of this CIS
rehabilitation.
Table 6-4
Proposed Pipe Network at Puhceni
Recommended
Components
for Installation
Pipes Length (m)
Number of Hydrants
Valves
33,304
369
34
The proposed schematic for the rehabilitated CIS is illustrated in Exhibit 3 of Annex 13.
6.2.14 Rocani
The rehabilitation plans for Rocani entails:
Replacement/repair of the existing infrastructure as identified in Section 3.2.14.
Additional underground pipes to supply areas originally equipped with
FREGAT center pivot.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
6-7
860
16
The proposed schematic for the rehabilitated CIS is illustrated in Exhibit 3 of Annex 14.
6.2.15 Talmaza
The rehabilitation plans for Talmaza entails:
Replacement/repair of the existing infrastructure as identified in Section 3.2.15.
Additional underground pipes to supply areas originally equipped with
FREGAT center pivot.
The table below provides an overview of the additional pipe network to be installed as
part of the CIS rehabilitation at Talmaza.
Table 6-6
Proposed Additional Pipes & Hydrants at Talmaza
Recommended for
Components
Installation
Pipes Length (m)
Number of Hydrants
Valves
6,270
120
1
The proposed schematic for the rehabilitated CIS is illustrated in Exhibit 3 of Annex 15.
6.2.16 Suvorov
The rehabilitation plans for Suvorov entails:
Replacement/Repair of the existing infrastructure as identified in Section 3.2.16.
Addition of two (2) new pump stations.
The two new pump stations in series are required to pump water directly from the Nistru
River because the existing primary pump stations are not adequate to meet the desired
capacity. In addition, the existing pump station infrastructure and pump sizes limit the
ability to expand the pumping capacities, thus requiring parallel pump stations. These
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
6-8
Mechanical Equipment
2 (GNS-1 & PNS-1)
Number of Pump Stations
8
Number of Pumps
5000 per Pump Station
Capacity of Pumps (lps)
80m per Pump Station
Head of Pumps (m)
8
Number of Motors
100
Station Piping length (m)
24
Number of Station Valves
2
Number of Ancillary Systems
Suction and discharge pipe Length (m)
Number of Basins
New Electrical Systems
10 kV Power Line
10 kV/0.4 kV Transformer
6 kV Switchgear
0.4 kV Switchgear/Control Panels
Automation Panels
Motor Starting Devices
Power Cables/Racks
Control Cables
8,050
1
2
2
2 Lineup
2 Lineups
0
0
2
2
For additional details on the Suvorov CIS, please see Annex 16.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
6-9
Section 7 Feasibility Level Cost Estimate for the Proposed Rehabilitation Projects
7.0
7.1 Summary
The implementation cost includes construction costs for the rehabilitation of the irrigation
infrastructure, dams and drainage systems, first order environmental & social mitigation
costs, along with necessary contingencies based on current cost (2009). This cost also
reflects accommodation for projected inflation and currency exchange rates over the
proposed implementation period (March 2010 through March 2015).
These projects are still at the feasibility level. Therefore, the above cost estimate should
be considered for planning purposes only. This cost estimate does not include cost for
setting up the implementation unit, cost for MCA and/or MCC administration or
supervision of the compact and during project implementation. More accurate cost
estimates should be developed during detailed design. The details of the feasibility level
cost estimate for each of the proposed CIS rehabilitation projects are provided in their
respective annexes.
7.2
Unit costs were compiled based on the assumption that the proposed projects would be
exempt from import duty or VAT.
7.2.1 Pipe Network
A unit cost database for the material required for construction was independently
developed for the purpose of identifying the cost for the CIS rehabilitation. The unit cost
of pipe represents cost of pipe fully installed based on the common trench & lay
practice. This cost represents:
Cost of supply and delivery of pipe and fittings for each diameter (150 mm
1000 mm) to site were those provided by local pipe manufacturer representatives.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
7-1
December 2009
Section 7 Feasibility Level Cost Estimate for the Proposed Rehabilitation Projects
Cost for excavation, backfill and compaction as published in latest edition of
Monitorul Constructiilor, a quarterly publication developed by the Ministry of
Construction and Territorial Development of the Moldova Republic.
Labor cost as published in Monitorul Constructiilor.
The unit cost for replacement and/or repair of hydrants, valves, manholes, air release
values were also developed in this manner.
The cost of rehabilitating the drainage system at three CIS (please refer to Section 4 for
details) that includes cleaning of drainage canals, restoration of monitoring wells,
repairing bridges and culverts are so identified separately and included as part of the
rehabilitation cost for the CIS.
7.2.2 Primary Civil Works
The cost for rehabilitating primary civil works components consisted of:
The unit rates for labor and construction were determined in a similar way as for pipes.
7.2.3 Mechanical & Electrical Equipment
The cost for selected pump/motor equipment and associated control panels, cabling,
piping, etc were obtained from well established and reputable pump producers like Wilo
(United Kingdom), Grundfos (Denmark), Aversa (Romania), and from local suppliers of
Russian/Ukraine brand pumps. The installed cost for the equipment was developed as
follows:
Installation of pumps and motors was assumed to be 30% of the equipment price.
Installing of electrical equipment was assumed to be 25% of the equipment price.
Installation of ancillary (valves, hoisting, priming, water meters, and drainage)
equipment at pumping stations was assumed 30% of the price of the equipment.
Unit costs were complied based on the assumption that the proposed projects would be
exempt from import duty and VAT.
7.3
Preliminary & General (P&G) assumes costs associated with the Contractors contractual
requirements, establishment and operation of the camp, mobilization and demobilization
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
7-2
December 2009
Section 7 Feasibility Level Cost Estimate for the Proposed Rehabilitation Projects
costs, provision of facilities for the Engineer, and method/time related costs that are also
location & site specific. Generally, P&G includes:
Taking these assumptions into consideration, and in keeping with prevailing feasibility
level standards, a P&G factor of 25% was used to estimate the above costs.
7.4 Contingencies
Contingency can be broadly defined as covering:
... costs that may result from incomplete design, unforeseen and
unpredictable conditions, or uncertainties within the defined project
scope. The amount of the contingency will depend on the status of design,
procurement, and construction; and the complexity and uncertainties of
the component parts of the project. Contingency is not used to avoid
making an accurate assessment of expected cost.
A contingency allowance has been added to the construction cost estimates to cover the
uncertainties in the civil and electrical/mechanical works that were identified based on
available information, and uncertainties with the construction market to offer competitive
bids in Moldova during the MCC implementation period. These contingent costs are
treated separately and are added, after all the costs are estimated, as a contingency
allowance.
At this stage in the development of the project, many uncertainties exist that increase the
risk of budget variation. The purpose of the inclusion of contingency is to ensure that
these variables are covered in the budget. For this estimate, the contingency allowances
are included to provide reasonable coverage for the following:
Uncertainties attributable to unforeseeable adverse geological conditions (rock
excavation will vary significantly).
Modifications in design resulting in an increase of work effort.
Minor items not detailed at this time.
Overlooked and unforeseen items that may not be included in the present
feasibility-level quantity estimates.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
7-3
December 2009
Section 7 Feasibility Level Cost Estimate for the Proposed Rehabilitation Projects
The allowance for contingency included in the cost estimate does not include coverage
for the following:
Again, keeping with prevailing engineering practice, at this level of feasibility planning, a
contingency figure of 35% is applied to identify the total construction cost.
7.5
7.6
The implementation costs identified for each of the 16 CIS in Table 1 also includes first
order cost estimates for environmental and social mitigation and monitoring. A brief
overview of the development of these costs is provided below:
7.6.1 Waste Management
Asbestos roofing sheets and waste from electrical installations in pump stations:
The costs are based on the assumption that an average of 2 tons of demolition
wastes will be generated at each rehabilitated pump station. Quantities of asbestos
sheeting are expected to be low as visual inspection of the pump stations during
site evaluation indicated that only about 10% of pump station roofs are made from
such sheeting. The cost of disposal includes the cost of transport to the closest
landfill: either Tintareni landfill in Anenii Noi Raion (Carpinenii de Sus, Leova
Sud, Chircani-Zirnesti, Cahul, Jora de Jos, Lopatna, Cosnita, Criuleni, Serpeni,
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
7-4
December 2009
Section 7 Feasibility Level Cost Estimate for the Proposed Rehabilitation Projects
Pugaceni, Roscani, Talmaza and Suvorov) or Balti landfill in Balti Raion
(Tetcani, Blindesti and Grozesti), and a tipping fee. The asbestos roofing
materials will likely require additional management measures (immediate cover
with 15 cm of non-asbestos containing material such as soil or a dust suppressing
chemical), which may increase the landfill operator's cost. The median landfill
tipping fee in Holland, 90 Euros per load (1,350 MDL), (Source:
http://www.kape.gov.pl/PL/Wydarzenia/imprezy/20070618_20070619_a/prezenta
cje/18_czerwca/3_Huisman_SenterNovem.pdf) is used to account for this extra
cost to the landfill operator. This fee is slightly higher than that charged by the
Chisinau municipality to industries which accumulate industrial waste (1,250
MDL).
Replaced steel pipe and hydrants will be sold for scrap - income from scrap is
assumed to equal transport costs to scrap merchant.
All inert demolition waste will be disposed of locally.
7.6.2 Compensation for Loss of Earnings (Economic Displacement)
The compensation costs were estimated based on the following information:
Crop patterns and their relative portions in each CIS were determined from the
land user database.
Average earnings/hectare is based on the average of 2003 and 2007 earnings as
provided by ACSA.
It is considered likely that most land users will only lose one year's production
during rehabilitation.
Pipeline replacement and repair will require a 20 m wide easement.
Hydrants, valves and manholes on those sections of pipelines along which no
interventions occur are accounted for separately. Hydrant replacement requires a
20 m wide easement along a 7 m length of pipeline per replaced hydrant; hydrant
repair, and valve and manhole replacement and repair will disturb a 5 m x 5 m
area.
Where there is a series of hydrant, valve or manhole replacement and/or repair
interventions along a pipeline with no visible easement on the orthophotos, there
will be a need for a 20 m wide easement along the entire length of pipeline along
which interventions take place.
Pump station expansion in Chircani-Zrneti will require two 25 m x 25 m areas.
It is assumed pump station interventions will occur during off-seasons so as not to
impact irrigation.
7.6.3 Environmental Monitoring & Potential Remediation Costs
The cost identified includes weather monitoring and quarterly water quality monitoring
up and downstream of each CIS.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
7-5
December 2009
Section 7 Feasibility Level Cost Estimate for the Proposed Rehabilitation Projects
In addition, in Crpinenii, it has been brought to MCCs attention that there are signs of
soil contamination in the vicinity of a small pesticide blending station. This will require a
preliminary assessment, which if positive will dictate the need for a detailed assessment
which will include water samples from Lake Minjir (2 samples) and 8 shallow wells in
Voinescu. For the purposes of identifying a preliminary cost estimate, the contaminated
area is assumed to be 500 m x 500m to a depth of 5 m. At a dry soil density of 1.52/kg/m3
this amounts to 1,900 tons of soil. Cost is based on maximum predicted cost/ton (100
Euros/ton) in Finland for soil remediation for the period 2005-2025 (K. Jarvinnen, 2004.
Remediation costs of contaminated sites in Finland).
7.7
The total construction cost, developed from the above discussed unit rates, are base-cost
estimates based on 2009 cost estimates. Since the proposed projects will be implemented
over the next five years, for budgeting purposes, it is necessary to escalate the base-cost
project estimates to account for the following:
Price escalation/Inflation.
Exchange rate variation.
7.7.1 Assumptions
Escalation of the base cost estimates is assumed based on the works being undertaken
within the five-year period. It is assumed that 20% of the activities will be completed by
2011; 40% by 2012; 30% by 3013; and the remaining 10% by 2014.
7.7.2 Price Escalation
Typically, escalated cost of construction works is affected by changes in cost of labor,
engineering, materials, construction equipment and fuel. There are two components of
works that need to be looked at separately in this analysis. One is the escalation rate for
the foreign cost component of the works (which is assumed to be everything from outside
of Moldova) and the other is the local cost component.
At this stage it is anticipated that the construction contractor(s) selected would most
probably be foreign, and likely from neighboring countries like Romania or Ukraine. It is
assumed that with the exception of the pipe, the remaining equipment and materials
necessary for rehabilitation will also be procured from these neighboring countries. At
this stage, labor is anticipated to be the major portion of the local component of the
implementation cost.
To quantify the effect of price escalation, sound judgment is required, which is based on
an analysis of the historical trend of the variables affecting the proposed projects and
what can be expected over the next three to five years.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
7-6
December 2009
Section 7 Feasibility Level Cost Estimate for the Proposed Rehabilitation Projects
Inflation within Moldova
Prediction of inflation is at best an imprecise exercise subject to potential wide
fluctuations and often times skewed by political influence and externalities. In an attempt
to arrive at a base inflation rate and forecast inflation during the implementation period,
data and reports were reviewed from the IMF, the Moldovan Handbook of Statistics, The
Economist, Economy Watch, and the World Economic Report.
The historical trend in general inflation was first analyzed. The information was gathered
for the last five years and is illustrated in Figure 7-1 below.
Figure 7-1
Historical Average Annual Inflation Rates in Moldova
Section 7 Feasibility Level Cost Estimate for the Proposed Rehabilitation Projects
The IMF also forecasts that global growth would increase to 1.5-2.5% in the latter
part of 2010. This Global growth would translate into increased growth in
Moldova and presents an argument that liquidity and investment increase could
increase inflation.
Figure 7-1 illustrates gyrations in inflation from a high of 39% in 1999 to a significant
drop to 5.2% in 1998 then leveling to around 12% from 2000 to 2008, with an overall
average from 2001 through 2008 of 12.27%. Further, as evidenced by projections from
the various sources identified above, there is no clear consensus on what the inflation will
be next year or in the near future.
Therefore in an attempt to develop a conservative, yet supportable, inflation rate for
estimating the implementation cost for the CIS rehabilitation projects, the following is
assumed:
An inflation rate of 4% for 2009 and 2010 assuming the current economic
downturn will continue through 2010.
Assuming a global growth factor of 1.5%, the inflation rate is assumed to be 6%
in 2011.
Beyond 2011, the average inflation rate is assumed to be 9.3% and will hold
constant (at 9.3%) through 2014.
Inflation - Neighboring Countries
As identified above, majority of the mechanical and electrical equipment required as part
of the rehabilitation works might be procured from either Romania or Ukraine. The
Ukrainian currency, Hryvna (UAH), is tied to the US dollar and is subject to its
fluctuations. When the discount rate in the US falls, Ukraine prints UAH to buy US
Dollars thus resulting in a high inflationary environment; its current situation.
Subsequently, this also depreciates the value of the UAH against that of its neighboring
currencies, including MDL. Based on IMFs World Economic Outlook, inflation in the
Ukraine is 26% in April 2009 and unlikely to reduce in the near to mid term future.
In contrast, Romanias currency, New Leu, (RON), floats and its inflation is currently
around 6% depending on the source of data. The RON has recently slipped due to the
slowing of the economy.
Given the discrepancies in the inflation rates between these two neighboring countries,
the apparent complexities of identifying or projecting a foreign (outside of Moldova)
inflationary factor will have to studied in greater detail, which is beyond the scope and
duration of this feasibility study. However, recognizing the importance of identifying the
inflationary effects on the Moldovan Lei (MDL), which erodes external purchasing
power, local inflation rates were assumed for foreign cost components for the time being
while estimating the cost for implementation. This will have to be revisited by MCC as
more reliable information becomes available in future.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
7-8
December 2009
Section 7 Feasibility Level Cost Estimate for the Proposed Rehabilitation Projects
7.7.3 Exchange Rate
The MDL is considered to be a relatively stable currency. Three factors determine this
stability: remittances, foreign direct investment, and incomes from exports, which rose
significantly in 2008.
The economy has shown resilience during the current global economic downturn and its
currency has not declined precipitously as is the case with the UAH and RON.
Economists state Moldovan banks are as not exposed to the consequence of the current
global banking crises as those in its neighboring countries, but there are warnings that
Moldova would be vulnerable as remittances decrease or exports decline.
A summary of the average exchange rates over the past nine years are identified in the
table below.
Table 7-2
Historical Trends in Exchange Rate (MDL/US$)
Average Exchange
Period
Rate (MDL/US$)
January 2000-May 2009
12.52
11.19
10.52
11.26
11.24
Figure 2 provides an illustration in the trend of annual exchange rates since 2003.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
7-9
December 2009
Section 7 Feasibility Level Cost Estimate for the Proposed Rehabilitation Projects
Figure 7-2
Historical Trend in Currency Exchange (MDLUS$)
Based on the above data it is apparent that the rates are tending more towards a lower
exchange rate, with the average from the beginning of 2008 to present of 10.52. Another
source, The World Economic Outlook shows the average exchange rate from November
2008 to present to be an average of 10.4 with a low reaching 9.66 during this period.
Other sources, such as the Economic Intelligence Unit (EIU) of The Economist, forecasts
the exchange rate in 2010 to be 12.55 MDL/US$. In predicting future exchange rates, the
National Bank states that MDL is not likely to drop significantly against the Euro or
Dollar anytime soon and the bank has enough reserves to keep the currency afloat against
any sharp drop in remittances.
Given the nature of the current economic crisis and in view of the relative stability of the
MDL against the dollar, for the purpose of this study and in the interest of remaining
conservative in our cost estimates, a rate of 10.52 MDL/US$ is used for the
implementation period. These figures should be revised as better information and
analysis become available.
In summary, the inflation and currency exchange rates that are used to establish the
feasiblity level implementation cost for the CIS rehabiliation are provided in the table
below.
Table 7-3
Inflation & Currency Exchange Factors used for Price Escalation
2010
2011
2012
2013
2014
4%
6%
9.3%
9.3%
9.3%
Foreign Inflation
4%
6%
9.3%
9.3%
9.3%
Local Inflation
10.52
10.52
10.52
10.52
10.52
Exchange Rate MDL/$
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
7-10
December 2009
8.1
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
8-1
8.2
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
8-4
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
8-7
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
8-8
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
8-9
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
8-12
8.5
Technical Assistance
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
8-14
9.1
O&M Responsibilities
As identified in Section 8.0, the O&M duties in the irrigation sector is the responsibility
of AM and the STIs. The primary O&M responsibilities entails responding to water
requests from farmers, collecting revenue from sale of water, performing small repairs on
the pumping stations, while operating and maintaining the pump stations for day to day
operations.
However, for the rehabilitated CIS, the MCC proposed plan is to develop Water User
Organizations (WUO) through the Irrigation Management Transfer (IMT) program
supported by MCC in conjunction with the CIS rehabilitation program. The WUOs are
anticipated to assume its responsibilities of managing, operating and maintaining the
system infrastructure by the time the rehabilitation projects are completed.
9.2
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
9-3
9.3
As mentioned earlier in Section 9.1, the IMT program will facilitate the development of
the WUO to takeover the management of the rehabilitated CIS. However, for reasons
discussed in Section 8.0, the initial managerial and technical capacities of the WUOs are
likely at risk of not being fully adequate or appropriate to manage these systems. A
phased joint management approach with the STI would be a viable option to help build
the WUO capacity over the first season(s) of operation to ensure long-term independence
and sustainability of the MCC investment.
The minimum personnel requirement for WUO would include:
A General Manager/Supervisor.
An Accountant.
Operators/Technicians Assuming a minimum of 4 per pump station.
9.4
Given the assessment of the prevailing financial situation of the STI, it is critical to plan
ahead to identify the actual budget for operating, managing but more importantly,
sustaining the rehabilitated CIS.
For this purpose, O&M budgets for the rehabilitation systems were estimated for
centralized (STI/AM) and decentralized (WUO) management.
9.4.1 Assumptions
The O&M budgets for the rehabilitated CIS assume that some CIS would be online by
2014. For the purpose of consistency, the annual O&M budget has been identified for all
CIS starting with at 2014.
Since the cost of operating and maintaining the system is based on delivering the total
water required each season, the annual O&M cost will increase with the increase in water
requirements over this period due to increased crop-water demand. This demand will
depend on the total area within each CIS being irrigated and the percentage of this area
being irrigated for HVA. This demand would increase as more farmers get organized and
begin irrigating and simultaneously transitioning to HVA crops. The assumption for %
HVA crops and areas being irrigated over the subsequent 12 years of operation was
provided by MCC and identified in Table 9-8.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
9-4
% HVA
% of Total
Area
Irrigated
% HVA
45%
45%
45%
78%
42%
76%
92%
65%
86%
83%
66%
78%
% of
Total
Area
Irrigated
93%
78%
99%
45%
47%
68%
68%
80%
69%
45%
49%
69%
68%
82%
68%
45%
51%
70%
70%
83%
71%
45%
45%
45%
45%
45%
45%
45%
45%
45%
45%
33%
58%
69%
42%
56%
42%
60%
73%
36%
36%
60%
76%
82%
66%
74%
66%
76%
87%
61%
61%
62%
71%
76%
65%
70%
65%
74%
74%
62%
64%
72%
89%
95%
79%
86%
78%
88%
100%
72%
74%
64%
71%
76%
66%
71%
65%
74%
73%
64%
65%
% of Total
Area
Irrigated
% HVA
83%
67%
78%
1. Assumptions provided by MCC. Water Requirements between the years are assumed to grow linearly.
Other relevant assumptions made in developing the annual O&M budget include the
following:
Farmers will be adequately equipped, resourced and organized by 2014 to support the
assumptions in Table 9-6.
WUOs will be certified, and in place with adequate capacity to start irrigation
operations during this period.
The unit price of energy (per KWH) is assumed to increase at an annual rate of 12%
as per discussions with Union Fenosa. Given, historic energy prices, this can be
considered conservative for the purpose of this feasibility study. Historic energy
prices in Moldova are provided in Appendix J.
Replacement cost for equipment is included in the O&M budget at a rate of 4% per
annum (based on a straight line replacement cost schedule per asset life of 25 years).
While the STI budgets include depreciation, for this study there is no depreciation
line item in the rehabilitated system budget.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
9-5
0.50
2.87
1.06
4.43
65%
Blindeti
0.54
1.78
0.33
2.65
67%
Grozeti
Crpinenii de
Sus
0.2
1.86
0.41
2.47
75%
0.21
2.29
1.05
3.55
65%
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
9-6
CIS
Fixed
Energy Replacement
Cost
Cost
Cost
(MDL/m3) (MDL/m3)
(MDL/m3)
Unit
Cost of
Water
(MDL/m3)
Energy
Cost as %
of Cost of
Water
Leova Sud
ChircaniZrneti
Cahul
0.18
1.66
0.23
2.07
80%
0.19
0.67
0.25
1.11
60%
0.51
0.66
0.31
1.48
45%
Jora de Jos
0.27
1.95
0.37
2.59
75%
Lopatna
0.39
1.08
0.16
1.63
66%
Conia
0.13
0.94
0.17
1.24
76%
Criuleni
0.38
0.69
0.17
1.24
56%
erpeni
0.24
1.78
0.42
2.44
73%
Puhceni
0.21
0.74
0.22
1.17
63%
Roscani
0.28
1.49
0.25
2.02
74%
Talmaza
Suvorov
0.18
0.1
0.65
2.56
0.27
0.39
1.10
3.05
59%
84%
Similar breakdown is provided for the rehabilitated CIS assuming STI/AM management
in Table 9-10.
Table 9-10
Estimated Breakdown for the Unit Cost of Water for Year 2014
Assuming CIS under STI/AM Management
Energy
Unit
Fixed
Energy Replacement
Cost of Cost as %
CIS
Cost
Cost
Cost
of Cost of
Water
3
3
3
(MDL/m ) (MDL/m )
(MDL/m )
Water
(MDL/m3)
Tetcani
0.11
2.87
1.06
4.04
71%
Blindeti
0.04
1.78
0.33
2.15
83%
Grozeti
Crpinenii de
Sus
Leova Sud
ChircaniZrneti
Cahul
0.03
1.86
0.41
2.30
81%
0.09
2.29
1.05
3.43
67%
0.03
1.66
0.23
1.92
86%
0.14
0.67
0.25
1.06
63%
0.26
0.66
0.31
1.23
54%
Jora de Jos
0.42
1.95
0.37
2.74
71%
Lopatna
0.21
1.08
0.16
1.45
74%
Conia
0.25
0.94
0.17
1.36
69%
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
9-7
CIS
Fixed
Energy Replacement
Cost
Cost
Cost
(MDL/m3) (MDL/m3)
(MDL/m3)
Unit
Cost of
Water
(MDL/m3)
Energy
Cost as %
of Cost of
Water
Criuleni
0.02
0.69
0.17
0.88
78%
erpeni
0.03
1.78
0.42
2.23
80%
Puhceni
0.02
0.74
0.22
0.98
76%
Roscani
0.02
1.49
0.25
1.76
85%
Talmaza
Suvorov
0.18
0.39
0.65
2.56
0.27
0.39
1.10
3.34
59%
77%
The difference in the unit cost of water between the two management options is in the
fixed cost. Energy cost and replacement cost, being system specific, will be the same
under either management. However, the STI managed system would have a slight
advantage in pooling its labor and material resources to operate multiple CIS, thus
resulting in a lower fixed cost component than that under WUO management. For more
details on the development of the unit cost of water, please refer to the supporting
annexes.
However, more importantly, Table 9-9 and 9-10 illustrate that regardless of the
management, the predominant factor driving the unit cost of water is the energy cost. As
discussed previously, since the CIS in Moldova relies on pumping water from the low
river levels to higher elevations where most of the CIS under consideration are located,
the cost of pumping would be a significant component of the cost of water. As these
above tables illustrate, the energy cost can be as low at 45% for a low lying CIS like
Cahul, and as high as 84% for a system like Suvorov, which relies of multiple lift stations
in series to get water to the irrigation areas. The fixed and replacement cost factors are
relatively smaller in comparison.
The estimated unit cost of water for 2020 and 2025 are provided in Table 9-11.
Table 9-11
Estimated Unit Cost of Water (MDL/m3) for Year 2020 & 2025
2020
2025
CIS
Centralized Decentralized Centralized Decentralized
Tetcani
6.40
6.73
10.90
11.40
Blindeti
3.84
4.39
6.54
7.26
Grozeti
3.96
4.11
6.78
6.99
Crpinenii de Sus
5.47
5.59
8.97
9.14
Leova Sud
3.49
3.65
6.01
6.22
Chircani-Zrneti
1.66
1.72
2.72
2.79
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
9-8
2020
Centralized Decentralized
2025
Centralized Decentralized
Cahul
1.90
2.20
2.99
3.37
Jora de Jos
4.53
4.37
7.60
7.40
Lopatna
2.44
2.61
4.14
4.36
Conia
2.27
2.14
3.77
3.60
Criuleni
1.51
1.87
2.56
3.03
erpeni
Puhceni
3.89
1.64
4.12
1.84
6.59
2.76
6.90
3.03
Roscani
3.12
3.36
5.39
5.71
Talmaza
1.70
1.71
2.77
2.78
Suvorov
5.86
5.51
9.84
9.39
In summary, as in the case with Table 9-9 and 9-10, the unit cost in Table 9-11 is the
unsubsidized cost for water. In other words, this cost is based on the fixed cost (labor and
materials needed for daily operations & maintenance) and energy cost identified based on
water requirements, and capital replacement cost built calculated at a rate of 4% per year
based on a 25-year full straight line depreciation schedule. The unit energy cost beyond
2014 will continue to be a significant component of the CIS O&M cost. Further, the
energy cost will be dependent on the market variation in unit cost of electricity.
Since these costs are the actual unsubsidized cost, they are significantly higher than the
current rates being paid by farmers. In addition, inflation though 2014 and 2025, which
have also been taken into consideration, is also contributing to this increase in cost.
However as discussed above, a good share of the cost operating and managing the CIS is
currently made up from state financing, leaving the farmers share to be a small fraction
of the total cost of water. If these subsidies are eliminated, the farmer would be looking
at tariff level along the magnitude identified in Table 9-10.
Details of the total O&M budget (estimated unit cost of water) for each CIS through 2025
are presented in their respective annexes (Annex 1- 16) supporting this report.
9.5
The best managed systems are those with a combination of water users management and
minimal government intervention; in other words, farmed-managed irrigation systems.
Generally governments provide technology transfer and funding for large investments
that cannot be taken on by the farming communities alone. A critical development in this
context is the farmers achievement of independent management of the irrigation
systems. However, that independency is limited to their financial capabilities and the
government has to be responsible for the major facilities to ensure the rational use of the
resource.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
9-9
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
9-10
Maintenance issues.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
9-12
10.0
Moldova, Romania
Reinforcing steel
Moldova
Structural steel
Misc. metal fabrications (fish
protection structures, etc.)
Hydrants
Valves - gate
Valves - butterfly
Manholes
Pumps
Motors
10kV power line poles
10kV power line conductors
10kV power line accessories
6(10)kV switchgear
0.4kV switchgear/control
panels
Moldova diameters up to
250 mm. Romania larger
diameters.
Larger diameters are imported
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
10-4
Likely Source
Countries
Ukraine, Russia, Romania,
Western Europe
Ukraine, Russia, Romania,
Western Europe
Moldova, Ukraine, Russia,
Romania, Western Europe
Moldova, Ukraine, Russia,
Romania, Western Europe
Moldova, Ukraine, Russia,
Romania, Western Europe
(above listed countries)
Japan, Western Europe
Comments
Local contractors advise that importation of materials and equipment are rarely a
problem.
Natural construction materials such as sand, course aggregate, crushed stone, and fill will
naturally be obtained from sources in the vicinity of the various schemes.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
10-5
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
10-7
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
10-8
Deficient designs.
Deficient construction quality.
Insufficient management capacity.
Construction cost overruns.
Bid period difficulties.
Each of these risks has a major common element that can mitigate them, the
establishment of a Technical Assistance team (TA) formed within the AM organizational
structure. The TA unit should be formed as an outsourced entity responsible to AM, the
MCA, and the MCC for implementing the entire project. It is recommended that MCC
consider funding the cost of the TA as part of the project funding. The cost would be
budgeted to be approximately $3.0 million for the five-year program.
The details of the TA are furnished in Section 8.5 of this study. In addition to the
responsibilities indicated therein, the TA would be responsible for executing various risk
mitigation measures relating to project implementation such as:
Prequalification process.
Strategic bidding plan.
Standardized environmental management plan.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
10-9
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
10-10
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
10-11
M ILLENNIU M
CHALLENGE CORPORATION
UNITED STATES OF AMERICA
MILLENNIUM CHALLENGE
CORPORATION (MCC)
MILLENNIUM CHALLENGE
ACCOUNT IN MOLDOVA (MCA)
TECHNICAL ASSISTANCE
(TA) FOR AM
APELE
MOLDOVEI (AM)
CONSTRUCTION
CONTRACTOR(S)
FIGURE 10-1
CONTRACTUAL RELATIONSHIPS
DECEMBER 2009
Task Name
Compact Signing
Duration
0 days
Start
Thu 10/1/09
Finish
Thu 10/1/09
0 days
Tue 12/1/09
Tue 12/1/09
0 days
Mon 3/1/10
Mon 3/1/10
261 wks
Mon 3/1/10
Fri 2/27/15
0 days
Wed 12/1/10
Wed 12/1/10
105 days
Thu 10/1/09
Wed 2/24/10
8 wks
Thu 10/1/09
Wed 11/25/09
MCA-M Approval
1 wk
Thu 11/26/09
Wed 12/2/09
MCC Approval
1 wk
Thu 12/3/09
Wed 12/9/09
10
Proposal Period
4 wks
Thu 12/10/09
Wed 1/6/10
11
Evaluate Proposals
3 wks
Thu 1/7/10
Wed 1/27/10
12
MCA-M Approval
1 wk
Thu 1/28/10
Wed 2/3/10
13
MCC Approval
14
15
1 wk
Thu 2/4/10
Wed 2/10/10
2 wks
Thu 2/11/10
Wed 2/24/10
1305 days
Mon 3/1/10
Fri 2/27/15
16
4 wks
Mon 3/1/10
Fri 3/26/10
17
6 wks
Mon 3/29/10
Fri 5/7/10
18
6 wks
Mon 3/29/10
Fri 5/7/10
19
257 wks
Mon 3/29/10
Fri 2/27/15
20
105 days
Thu 10/1/09
Wed 2/24/10
8 wks
Thu 10/1/09
Wed 11/25/09
1 wk
Thu 11/26/09
Wed 12/2/09
21
22
MCA-M Approval
23
MCC Approval
1 wk
Thu 12/3/09
Wed 12/9/09
24
Proposal Period
4 wks
Thu 12/10/09
Wed 1/6/10
25
2 wks
Thu 1/7/10
Wed 1/20/10
26
1 wk
Thu 1/21/10
Wed 1/27/10
27
MCA-M Approval
1 wk
Thu 1/28/10
Wed 2/3/10
28
MCC Approval
29
1 wk
Thu 2/4/10
Wed 2/10/10
2 wks
Thu 2/11/10
Wed 2/24/10
1137 days
Mon 3/1/10
Tue 7/8/14
6 wks
Mon 3/1/10
Fri 4/9/10
30
31
32
Field Investigations
22 wks
Mon 4/12/10
Fri 9/10/10
33
Finalize Designs
34 wks
Mon 4/12/10
Fri 12/3/10
34
65.4 wks
Mon 4/12/10
Tue 7/12/11
35
28 wks
Mon 5/31/10
Fri 12/10/10
36
37
38
2 wks
Wed 6/29/11
Tue 7/12/11
156 wks
Wed 7/13/11
Tue 7/8/14
327 days
Mon 4/12/10
Tue 7/12/11
5 wks
Mon 4/12/10
Fri 5/14/10
39
40
MCA-M Approval
1 wk
Mon 5/17/10
Fri 5/21/10
41
MCC Approval
1 wk
Mon 5/24/10
Fri 5/28/10
42
Advertise Project
6 wks
Mon 5/31/10
Fri 7/9/10
43
8 wks
Mon 7/12/10
Fri 9/3/10
44
5 wks
Mon 9/6/10
Fri 10/8/10
2009
Qtr 2
Qtr 3
Qtr 4
10/1
Qtr 1
2010
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2011
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2012
Qtr 2
Qtr 3
Qtr 4
12/1
3/1
12/1
Task
Progress
Summary
External Tasks
Split
Milestone
Project Summary
External Milestone
Page 1
Deadline
Qtr 1
2013
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2014
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2
Qtr 2
Task Name
MCA-M Approval
Duration
3 wks
Start
Mon 10/11/10
Finish
Fri 10/29/10
2 wks
Mon 11/1/10
Fri 11/12/10
2 wks
Wed 12/1/10
Tue 12/14/10
16 wks
Wed 12/15/10
Tue 4/5/11
46
MCC Approval
47
48
Bidding Period
49
Evaluation of Bids
6 wks
Wed 4/6/11
Tue 5/17/11
50
MCA-M Approval
2 wks
Wed 5/18/11
Tue 5/31/11
51
MCC Approval
1 wk
Wed 6/1/11
Tue 6/7/11
52
3 wks
Wed 6/8/11
Tue 6/28/11
53
54
Notice to Proceed
BP#1 Rehab Work - Prut River
2 wks
Wed 6/29/11
Tue 7/12/11
715 days
Wed 7/13/11
Tue 4/8/14
55
Mobilization
8 wks
Wed 7/13/11
Tue 9/6/11
56
Tetcani
73 wks
Wed 9/7/11
Tue 1/29/13
57
Blindesti
37 wks
Wed 1/30/13
Tue 10/15/13
58
Grozesti
45 wks
Wed 9/7/11
Tue 7/17/12
59
Carpenenii de Sus
90 wks
Wed 5/23/12
Tue 2/11/14
60
Leova Sud
37 wks
Wed 9/7/11
Tue 5/22/12
61
Chircani-Zirnesti
91 wks
Wed 9/7/11
Tue 6/4/13
62
Cahul
69 wks
Wed 7/18/12
Tue 11/12/13
63
64
8 wks
Wed 2/12/14
Tue 4/8/14
700 days
Wed 7/13/11
Tue 3/18/14
65
Mobilization
8 wks
Wed 7/13/11
Tue 9/6/11
66
Jora de Jos
45 wks
Wed 9/7/11
Tue 7/17/12
67
Lopatna
20 wks
Wed 7/18/12
Tue 12/4/12
68
Cosnita
50 wks
Wed 12/5/12
Tue 11/19/13
69
Criuleni
37 wks
Wed 9/7/11
Tue 5/22/12
70
Serpeni
50 wks
Wed 5/23/12
Tue 5/7/13
71
Puhaceni
45 wks
Wed 9/7/11
Tue 7/17/12
72
Roscani
37 wks
Wed 5/8/13
Tue 1/21/14
73
Talmaza
77 wks
Wed 7/18/12
Tue 1/7/14
74
75
76
Mobilization
77
Suvorov
78
79
80
81
Compact Completion
8 wks
Wed 1/22/14
Tue 3/18/14
705 days
Wed 7/13/11
Tue 3/25/14
8 wks
Wed 7/13/11
Tue 9/6/11
125 wks
Wed 9/7/11
Tue 1/28/14
8 wks
Wed 1/29/14
Tue 3/25/14
98 wks
Wed 5/23/12
Tue 4/8/14
144 wks
Wed 5/23/12
Tue 2/24/15
0 days
Fri 2/27/15
Fri 2/27/15
2009
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2010
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2011
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2012
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2013
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2014
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2
Qtr 2
2/27
Task
Progress
Summary
External Tasks
Split
Milestone
Project Summary
External Milestone
Page 2
Deadline
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
11-1
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
11-2
December 2009
2014
2020
2025
Tetcani
3.32
5.89
12.54
Blindeti
1.99
3.84
7.98
Grozeti
1.85
3.60
7.68
Crpinenii de Sus
3.55
5.59
9.14
Leova Sud
1.55
3.20
6.84
Chircani-Zrneti
0.83
1.50
3.07
Cahul
1.11
1.92
3.71
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
11-3
December 2009
2014
2020
2025
Jora de Jos
1.94
3.83
8.14
Lopatna
1.23
2.28
4.80
Conia
0.93
1.87
3.96
Criuleni
0.93
1.63
3.34
erpeni
1.83
3.61
7.59
Puhceni
0.88
1.61
3.34
Roscani
1.52
2.94
6.28
Talmaza
0.83
1.50
3.06
Suvorov
2.28
4.82
10.33
1.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
11-4
December 2009
23.44
7.28
17.15
35.90
14.53
39.24
16.47
19.28
5.36
20.28
4.85
11.51
6.54
9.83
16.08
276.07
This varies from 4.85 million MDL in Criuleni to over 276 million MDL in Suvorov.
Despite that FIRR show these systems to be sustainable in the long run, the sustainability
in the short term would be a concern if the WUO do not have another source of revenue
to overcome these losses on a yearly basis during these initial years.
In looking at a potential funding source, it can be assumed that the current subsidies will
continue (at minimum, the energy component) in the near future even under the
decentralized (WUO) management. In which case, the percentage of energy subsidy
required to offset the identified shortfall is illustrated in Figure 11-1.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
11-5
December 2009
As illustrated in Figure 11-1, the level of subsidy in terms of percentage of the energy
cost would vary from system ranging from 12% at Chircani-Zrneti to approximately
44% at Tetcani. The total subsidy over the period for each of the CIS would equal the
shortfall identified in Table 11.3.
Since the working assumption of the FIRR analysis is from the perspective of the WUO
supplying water to farmers, a realistic sensitivity at this level of the study would be to test
the results on the WUO if there is a decrease in water demand from that estimated for the
above analysis. Given current practices in Moldova, this is a situation that is very likely
to occur in the future.
A sensitivity analysis was run to determine the impacts to the base assumptions should
the actual water consumed be 50% less than the estimated volume (based on MCC
identified assumption of % HVA and % area irrigated as discussed in Section 9.4). There
is a potential for this to occur due to a myriad of factors, including high rainfall, farmers
decision not to irrigate, farmers not being prepared to switch to HVA or to irrigate at all,
which could all result in less water being consumed, meaning less revenue being realized
by the WUO, which would put it at risk of not meeting the fixed costs (albeit a small
component of the unit cost of water). The shortfall at each CIS under such a scenario is
presented in Table 11-4.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
11-6
December 2009
44.46
15.15
18.04
63.23
14.42
87.1
83.1
21.23
10.45
23.13
15.98
18.81
14.7
11.04
48.88
245.76
Comparing Table 11-3 and Table 11-4 shows that in the case of Leova Sud and Suvorov
shortfall decreased or remains unchanged.
To maintain consistency with our earlier analysis, the energy subsidy required to offset
this shortfall is illustrated in Figure 11-2.
Figure 11-2
% Energy Subsidy Required to Offset Shortfall in Table 11-4
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
11-7
December 2009
Under this scenario, the energy subsidy required would increase from a low of 32% at
Chircani-Zrneti to 106% at Tetcani. Again, it should be noticed that these percentages
are relative. For example, although the total shortfall in Suvorov declined from 276
million MDL to 246 million MDL with a 50% decrease in water consumption, the %
energy subsidy required increased marginally from 33 to 54%.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
11-8
December 2009
11.4 Conclusions
As discussed previously, the financial sustainability only looked at O&M budgets and
tariffs under the assumption that operation and management is satisfied if all costs are
met through the levy of fees for water delivered. While the FIRR for each CIS is low,
they realistically reflect the working assumptions. The following should be taken into
account while considering the financial sustainability:
As discussed in Section 9.4, energy cost is the dominant component of the unit
water cost. Subsidizing this cost at levels illustrated in Figure 11-1 and 11-2
would be of significant benefit to the WUO in the near future (through 2025 based
on current assumptions) for offsetting potential shortfalls.
WUOs might have to be granted an infant industry protection to cover shortfalls
in recovering tariffs while farmers are in a transition period to HVA. This
protection could be in the form of creating reserve accounts, guarantee on loans,
or at a minimum maintaining energy subsidies at levels identified in Figures 11-1
and 11-2.
As discussed in Section 8.0, there are risks associated with the WUO not having
the capacity and capability to take on the roles and duties of managing the CIS
within the allotted time period (2010-20014), thus impacting financial cost
recovery and potentially pushing back scheduled HVA production.
Part of the task of ensuring WUO financial sustainability should be providing
guidance on standardized accounting practices such that the O&M budget, tariff
and, if applicable, transparent subsidy process.
Further, a mechanism need to be established to addresses the current practices of
estimating water at each CIS at the beginning of each season. The current practice
allows farmers the opportunity to overestimate water requirements resulting in
lower water tariff. This mechanism needs to consider a range of options such as
submitting either a surcharge or remittance at the end of the growing season
assuming a fixed tariff, or establishing a variable tariff which is adjusted during
the growing season as a function of actual water used.
A willingness and ability to pay analysis needs to be coupled with this financial
analysis in order to look at farmer generated revenue versus tariff which will
provide a more realistic and complete picture.
Energy management should have top priority and best practices instituted with a
goal toward reducing energy costs across the board for the rehabilitated irrigation
systems.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
11-9
December 2009
1,258
Blindeti
521
Grozeti
1,018
Crpinenii de Sus
1,815
Leova Sud
963
Chircani-Zrneti
4,417
Masivul Cahul
1,930
Jora de Jos
1,165
Lopatna
506
Conia
2,800
Criuleni
677
erpeni
1,107
Puhceni
856
Rocani
682
Masivul Talmaza
Masivul Suvorov
Total
2,468
13,394
35,577
12.2 Conclusions
Based on the technical, institutional and financial assessment of proposed rehabilitation
of the 16 CIS, the following can be concluded:
The rehabilitation of the 16 CIS under consideration will provide the necessary
infrastructure to support irrigation in an area covering 35,577 ha, which will be
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report - Final
12-1
December 2009
capable of delivering the required water to support HVA, as per USUs crops
water demand recommendation.
The cost of rehabilitating the 16 CIS is significant. Based on discussions with
MCC, it is likely that not all 16 CIS would be selected for rehabilitation. Once
MCC identifies its investment plan, the implementation plan and schedule
identified in Section 10.0 will have to be revised accordingly.
If planned and coordinated properly, these projects can be rehabilitated within the
MCC prescribed five-year period.
A more detailed and accurate cost estimate would only be available at the end of
the detailed design of the rehabilitation works. A design based cost estimate
should provide MCC with an assessment of the adequacy of its proposed funding
levels and with the opportunity to develop/revise its investment plans in keeping
with its budget limitations.
Cost escalation based on future inflation and currency exchange trends also need
to be monitored to periodically assess the adequacy of the MCC investment to
meet its desired objectives. This will help identify potential shortfalls ahead of
time, and an opportunity for the Government of Moldova to seek supplemental
funding from other sources to ensure the completion of the MCC objectives in
Moldova.
AM would be the implementing entity for the MCC funded rehabilitation
program. However, technical assistance would be required to assist AM with its
responsibilities to ensure that the projects are implemented on time and on budget.
Although there are not inherent fatal flaws to any of the CIS under consideration,
several major risks were identified with the assumptions and the process
associated with the proposed IMT program as proposed in Section 8, which would
have near term sustainability impacts on the MCC investment, if the process and
the establishment of the WUO are not adequately incorporated or brought up to
capacity.
Based on current MCC plans of tying the IMT process with the rehabilitation
works, delays in the registration of the WUO would have an impact on the
construction schedule and risk the project not being completed on time and on
budget. To mitigate this risk, it would be critical for the IMT Consultant and the
Design Engineer to coordinate periodically so the IMT process informs the
rehabilitation schedule and the Design Engineer can develop the priority of
construction accordingly.
Assessment of the current financial practices in the irrigation sector identified the
following;
Energy subsidies are supposed to cover up to 100% of the energy cost.
However, there are still shortfalls in the payment to cover energy cost that
cannot be reconciled. The second subsidy (irrigation service subsidy)
provided by AM supposedly covers approximately 50% of the fixed cost.
However, based on the discussion in Section 9.2, the subsidies seem to be
me significantly higher.
The revenues collected by STI from irrigation are a small fraction
compared to the state financing that goes to sustain irrigation operation.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report - Final
12-2
December 2009
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report - Final
12-3
December 2009
References
13.0 References
Apele Moldovei. 1997, Rehabilitation and Institutional Development of the Irrigation
Sector-Final Report. AM, Chisinau (Sep. 1997).
Brlund, K. and Snoy, B., 2005, Transboundary Diagnostic Study for the Dniester River
Basin, OSCE/UNECE Project, Geneva, Switzerland. (file: Final Report_eng.pdf).
Clarke, R., and King, J., 2004. "The Atlas of Water" Earth scan, Myriad Editions, Ltd.,
Brighton, U.K. www.earthscan.co.uk, 127 pages.
Corobov, R., 2008, Regional Climate and Environmental Change: Moldovas Case
Study, PowerPoint presentation at the NATO Advance Workshop. Odessa, UA., August
23-28. Regional aspects of climate-terrestrial hydrologic interactions in EE. Retrieved
October 17,2008, from
http://neespi.org/web-content/meetings/Odessa_2008/Day_3_4_Corobov.pdf.
Cazac, V., 2008, Present River Water Resources of the Republic of Moldova and Their
Possible Evolution as a Result of Forthcoming Climate Warming, December 22, 2008.
Cazac, V., 2008, Catastrophic floods in Moldova in the summer of 2008, WMO
MeteoWorld, from
http://www.wmo.int/pages/publications/meteoworld/archive/oct08/moldova_en.html.
Dumitru, D., 2005, Prut River Basin. Opportunities For Transboundary Cooperation For
Local Authorities In Implementation Of The Prut River Basin Management Plan,
Regional Center for Strategic Environmental Studies ECOS, Republic of Moldova.
Eoearth.org from http://www.eoearth.org/article/Water_profile_of_Moldova
FAO, 2003, Aqua stats. Food and Agric. Organization of the United Nations, Rome,
Italy. www.fao.org/ag/agl/aglw/aquastat/main/
Fipps, G., 2003, Irrigation Water Quality Standards and Salinity Management Strategies,
Texas Cooperative Extension from http://lubbock.tamu.edu/irrigate/documents/2074410B1667.pdf.
IPCC, 2000, Special Report on Emissions Scenarios, Intergovernmental Panel on Climate
Change.
Keith, John, and Gary Merkley, 2008, Institutional assessment, recommendations on
alternative water service and delivery arrangements, and identification of specific legal
and policy reforms to achieve sustainability and improved performance in the irrigated
agricultural sector, Republic of Moldova. International Irrigation Center, USU, Logan,
UT. (November).
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
13-1
References
Lalikin N.V., Sirodoev I. G., 2004, A few approaches to estimation of influences of
change and changeability of climate on water resources / In the book: Climate of
Moldova in the XXI-st century. Chisinau 2004, p. 176-212.
Loboda, Nataliya S., Glushkov, Alexander V., and Khokhlov, Valeriy N., 2005, Using
Meteorological Data for Reconstruction of Annual Runoff Series Over an Ungauged
Area: Empirical Orthogonal Function Approach to MoldovaSouthwest Ukraine Region,
Atmospheric Research 77 100 113.
Merkley, Gary Hill, Robert W., Gherciu, Viorel, Drost, Daniel, and Caron, 2009,
Irrigation Engineering, Hydrologic, and Agronomic Assessment Report-Republic of
Moldova, Submitted to the Millennium Challenge Corporation, Washington, D.C.,
Prepared by International Irrigation Center Utah State University, Logan, Utah.
Merkley, Gary, Raymond Rifenburg, Viorel Gherciu, John Keith, Oleg Uica, and
Stephen Hodgson, 2009, Irrigation Management Transfer (IMT) Program Design,
Republic of Moldova. International Irrigation Center, USU, Logan, UT.
Ministry of Ecology and Natural Resources-National Institute of Ecology, 2003, Republic
of Moldova State of the Environment Report 2003.
Ministry of Environment and Territorial Development, 2000, First National
Communication of the Republic Of Moldova Under the United Nations Framework
Convention on Climate Change.
Moraru, C. and Anderson, J., 2005, A Comparative Assessment of the Ground water
Quality of the Republic of Moldova and the Memphis, TN Area of the United States of
America, Council of International Exchange of Scholars, University of Memphis Ground
water Institute, and Academy of Sciences, Institute of Geophysics and Geology, Republic
of Moldova.
Munteanu, V, and Rusu, M, 2001,Monitoring of the Surface Waters in Republic of
Moldova and Integration in Eurowaternet, National Institute of Ecology, 3 Academiei Str.
Chisinau, MD-2028, Republic of Moldova, Proceedings Mtm-Iii - Monitoring in the
Republic of Moldova.
PA Consultants, 2004, USAID Agricultural Irrigation Assessment in Moldova Final
Report Volume 1 - Main Reports Phase I: Assessment Report - Phase II:
Recommendations for an Irrigation Strategy, November 2004.
Potop, V. and Soukup, J., 2008, Spatiotemporal Characteristics of Dryness and Drought
in the Republic of Moldova, Theor Appl Climatol, DOI 10.1007/s00704-008-0041-5.
Retrieved April 13, 2009, from www.springerlink.com/index/247p704k71v50t14.pdf.
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
13-2
References
Srodoev I. G. and Knight C. G., 2007, Vulnerability to Water Scarcity in Moldova:
Identification of the Regions. Buletinul Academiei de tiine a Moldovei. tiinele vieii3
(303): 159-166.
Srodoev I.G., and Knight C.G., 2008, Vulnerability to Water Scarcity in Moldova:
Likely Threats for Future Development. Present Environment and Sustainable
Development 2: 7-15 [Romania]
Skogerboe G and Merkley G. P., 1996, Irrigation Maintenance and Operations Learning
Process, Gaylord. Water Resources Publications, LLC
Tafi, Jana, 2005, Institutional Arrangements and the Water Data Centre Case study of the
Republic of Moldova, IWG-Env, International Work Session on Water Statistics, Vienna,
June 20-22 2005.
USAID, CNFA, Agro-Info and Apele Moldovei, 2008, Organization of Water Users for
Irrigation Purposes, Chisinau, Moldova.
UNDP/GEF Danube Regional Project, undated, Support to the development of the Prut
River Basin Management Plan.
Utica, Oleg, and Stephen Hodgson. 2009. The legal framework for WUOs and irrigation
management transfer (IMT).
World Bank, 2001, Agricultural Strategy for Moldova. Washington, DC.
Zubcov, Elena, 2009, personal communication, Consiliul National Pentru Acreditare si
Atestare
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report Final
December 2009
13-3
Appendices
Appendix A
Historic Flow Data for Prut and Nistru Rivers
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
Appendix A
Prut River - Ungheni - Flow in m3/sec
Year
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
1971
1972
1973
1974
1975
1976
1977
1978
1979
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
May
51
15
12
10
82
36
15
13
20
33
52
48
38
34
65
35
46
26
47
27
101
157
42
38
40
44
29
28
35
65
19
35
46
43
34
79
93
61
88
67
40
88
118
40
42
51
33
56
18
19
13
56
122
27
25
23
49
77
43
65
41
39
25
127
30
45
60
125
102
37
40
32
51
26
49
31
48
27
42
43
42
35
121
79
49
136
76
40
128
94
71
54
43
33
70
59
63
30
147
116
173
110
96
162
117
109
139
36
89
93
97
173
47
43
193
86
38
48
61
53
31
40
26
29
18
44
50
46
40
109
66
49
224
72
43
134
89
82
91
81
37
81
303
232
120
120
167
190
139
303
196
94
111
168
34
152
166
238
134
323
254
133
73
38
42
56
81
36
116
33
32
18
103
144
68
72
222
66
81
222
117
87
132
136
92
107
286
48
117
124
92
95
220
73
146
77
100
392
149
105
161
70
138
107
227
152
177
167
283
175
44
175
109
54
39
98
142
32
57
97
141
65
135
253
135
248
185
114
86
124
109
67
145
175
80
48
33
14
40
157
10
56
32
21
43
136
13
82
43
30
70
224
18
131
73
33
117
323
18
133
89
47
124
392
32
June
91
94
44
35
179
71
163
36
286
294
75
51
241
131
350
148
138
161
159
295
92
132
84
167
163
61
54
270
99
41
173
129
116
113
103
92
122
251
105
51
129
121
43
50
121
356
126
July
August
32
133
25
120
114
74
95
46
355
117
236
94
151
299
200
57
156
214
110
346
182
132
101
127
186
55
57
108
115
39
194
120
74
65
118
53
87
237
127
77
141
72
48
33
100
192
67
September
25
56
23
77
64
69
43
91
91
59
66
124
95
135
146
115
69
109
220
308
131
156
190
135
160
54
58
117
61
37
284
65
70
48
54
40
114
116
116
59
108
137
95
131
211
132
40
17
28
15
85
35
54
28
87
48
43
97
118
50
65
83
134
77
190
122
129
76
98
95
65
84
55
36
107
121
25
128
51
62
40
53
88
112
87
70
44
136
102
35
72
140
105
89
15
21
16
102
23
26
26
89
32
40
60
96
41
121
66
163
58
133
107
122
73
71
63
62
38
39
27
115
68
21
76
54
57
43
49
103
71
56
68
44
119
72
29
58
65
47
99
15
25
22
62
24
41
23
48
27
47
54
94
39
154
46
75
54
53
49
122
163
53
49
80
42
33
30
56
49
23
69
51
51
38
44
61
61
132
70
39
86
110
34
46
52
41
74
14
22
16
73
68
32
14
25
41
39
92
76
27
83
39
63
38
50
45
139
157
49
41
35
46
32
29
37
52
20
54
51
45
34
44
103
70
104
69
34
97
98
35
54
46
37
70
104
59
38
95
308
23
78
49
26
77
190
15
65
40
21
60
163
15
58
39
23
49
163
15
54
34
17
45
157
14
203
126
67
200
492
39
173
106
56
162
437
40
149
101
59
128
422
38
144
92
45
121
421
37
Average
49
75
48
69
94
73
78
66
119
123
97
89
101
100
118
98
110
119
121
168
142
107
69
85
85
51
37
95
69
34
93
70
75
54
65
110
90
122
123
66
93
110
72
66
98
129
66
Discharge
(mil m3)
1533
2360
1521
2168
2976
2319
2475
2069
3742
3869
3073
2811
3194
3165
3716
3104
3483
3747
3816
5286
4495
3372
2162
2670
2672
1608
1183
3001
2189
1083
2935
2217
2368
1693
2051
3483
2828
3866
3891
2086
2924
3466
2272
2095
3088
4067
2093
Flow (m3/sec)
Average
75Percentile
95percentile
Median
Max
Min
136
79
42
121
356
35
125
69
34
114
355
25
Discharge in Million m3
Average
75Percentile
95percentile
Median
Max
Min
129
88
36
107
421
28
136
79
50
106
332
32
219
116
79
187
600
48
340 357
188 239
86 125
303 332
837 1050
47
87
353
206
109
314
923
92
335
186
92
305
951
66
280
158
101
253
824
62
Page1
Appendix A
Prut River -Sirauti - Flow in m3/sec
Year
January
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
35
29
31
24
43
37
37
62
61
44
26
21
62
19,4
11,4
26,5
24,8
February
26
13
39
23
25
32
29
71
54
40
70
22
91
13
60
21
23
March
40
33
67
50
68
80
39
67
52
210
74
91
123
96
81
89
115
April
48
49
106
131
66
108
44
106
158
208
162
69
143
93
60
121
245
May
55
238
80
107
81
125
161
148
242
120
43
47
81
58
64
120
125
June
53
160
162
58
148
108
57
125
238
111
28
178
80
28
31
98
319
36
214
70
60
56
85
40
75
196
108
77
120
53
97
46
46
132
27
188
46
44
33
42
46
109
65
78
33
71
159
64
146
268
99
26
95
44
96
30
57
170
120
54
80
40
128
63
23
45
61
43
27
75
44
46
33
42
93
75
75
54
25
38
71
30
40
55
27
42
73
86
31
26
75
68
50
97
43
21
48
70
44
43
31
28
33
32
41
41
28
53
73
65
38
53
21
47
22
22
43
40
21
89
44
32
65
268
27
69
43
25
57
170
23
50
33
26
44
93
25
51
31
25
44
97
21
40
28
21
40
73
21
239
117
86
174
718
73
179
112
66
149
441
59
134
87
70
118
248
67
133
81
65
113
251
55
106
74
55
106
196
55
37
100
68
59
53
70
72
89
111
96
52
73
85
52
60
86
107
Discharge
(mil m3)
1177
3152
2144
1871
1674
2218
2257
2822
3498
3020
1626
2315
2676
1625
1891
2722
3376
Flow (m3/sec)
Average
75Percentile
95percentile
Median
Max
Min
39
29
23
37
62
21
38
23
13
29
91
13
81
52
38
74
210
33
113
66
47
106
245
44
111
64
46
107
242
43
117
57
28
108
319
28
89
53
39
75
214
36
Discharge in Million m3
Average
75Percentile
95percentile
Median
Max
Min
105
78
61
98
167
57
94
55
33
72
222
32
216
139
102
197
562
88
292
172
122
275
635
114
298
170
123
287
648
114
302
148
72
280
827
72
238
141
105
201
573
97
Page2
Appendix A
Nistru River - Hrusca - Flow in m3/sec
Anul
Martie
Aprilie
Mai
149
96.3
173
231
160
97.7
132
361
144
140
131
300
106
287
357
239
94.5
105
360
121
132
189
186
166
184
233
186
200
281
326
305
297
245
176
297
301
136
220
250
277
210
108
201
345
165
172
251
192
156
521
166
456
225
459
240
195
87.6
136
265
167
161
136
149
161
219
240
271
158
205
267
295
353
375
173
503
217
270
263
283
449
635
320
630
443
403
409
174
319
321
459
692
894
165
759
456
283
219
228
268
170
343
127
134
149
155
216
203
174
206
175
265
313
338
273
386
438
246
378
240
232
443
1130
646
289
271
447
146
538
1030
470
378
599
1070
439
500
499
350
303
174
126
441
237
332
302
350
368
253
398
656
328
554
687
696
360
400
362
371
496
937
276
184
337
903
389
238
348
219
442
459
344
598
363
504
580
572
342
333
460
192
152
219
785
159
266
258
275
245
391
550
524
551
511
390
374
328
295
200
600
390
203
Average
75Percentile
95percentile
Median
Max
Min
209
139
98
188
361
95
247
166
135
218
521
88
331
205
148
278
894
127
466
322
173
399
1130
126
Average
75Percentile
95percentile
Median
Max
Min
561
372
261
502
967
253
602
405
329
532
1272
214
886
550
397
745
2394
340
1209
834
447
1034
2929
327
1968
1969
1970
1971
1972
1973
1974
1975
1976
1977
1978
1979
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Ianuarie Februarie
Iunie
Iulie
136
134
1210
650
743
433
216
490
218
204
555
453
629
937
796
366
512
182
311
389
422
555
222
265
875
1010
343
378
294
524
332
311
365
475
450
294
219
187
351
187
534
327
474
282
184
179
350
343
311
241
233
263
322
191
300
289
266
230
496
333
780
832
365
391
209
268
456
611
325
261
156
183
147
155
419
215
748
399
252
246
Flow (m3/sec)
387
413
367
255
247
226
183
156
178
356
347
303
903
1210
1010
152
136
134
Discharge in Million m3
1036
1071
982
682
641
606
489
403
476
952
898
810
2419
3136
2705
407
353
359
August
Septembrie
Octombrie
445
225
235
179
227
270
365
456
223
236
213
410
791
495
261
301
191
139
232
217
194
243
180
549
176
284
162
184
289
476
387
301
226
529
368
160
512
484
464
225
530
178
209
251
327
137
212
265
425
244
402
180
382
294
189
134
111
153
276
170
375
370
157
188
175
501
179
214
592
319
284
289
192
459
248
171
217
241
317
463
422
125
173
179
230
135
404
226
330
178
327
141
467
288
166
150
120
148
181
160
236
207
189
349
212
267
190
231
435
461
426
241
200
331
396
162
220
253
209
253
Noiembrie Decembrie
209
120
219
207
279
144
694
160
199
150
191
203
474
396
154
127
103
165
106
133
237
214
168
368
557
334
187
247
266
223
550
253
188
371
340
154
279
205
286
310
126
157
221
337
222
109
322
120
210
108
246
221
534
306
179
104
98
248
116
129
180
214
184
225
290
222
185
186
268
338
276
319
195
293
266
135
271
187
199
298
313
216
162
252
791
139
276
180
137
246
592
111
250
177
135
223
467
120
254
164
119
212
694
103
221
174
108
218
534
98
837
579
434
675
2119
372
714
466
355
638
1534
288
671
473
360
597
1251
321
659
424
309
548
1799
267
592
465
289
583
1430
262
Media
302
388
399
296
245
273
374
353
349
296
360
355
550
419
324
251
212
236
215
174
282
290
183
285
261
286
215
248
354
356
459
360
294
367
343
228
252
330
394
290
Page3
Appendix A
Nistru River - Bender - Flow in m3/sec
Year
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
1971
1972
1973
1974
1975
1976
1977
1978
1979
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
January February
March
April
May
185
384
302
329
562
227
554
216
448
1030
398
273
328
192
485
522
401
647
407
577
673
595
345
322
433
172
138
243
816
126
267
238
262
204
347
602
547
593
617
398
371
316
330
249
642
447
189
267
54.7
116
98.1
176
237
127
129
136
161
234
217
113
146
379
165
124
136
343
130
366
467
238
118
116
373
127
141
181
178
130
150
226
166
131
167
228
330
311
260
178
291
306
190
213
180
212
249
126
189
59.3
234
601
216
254
180
260
449
194
202
259
235
164
580
171
498
252
515
291
232
105
186
315
157
168
140
142
159
183
215
154
128
228
262
274
407
401
178
553
290
201
219
192
390
292
326
344
107
702
790
980
622
465
655
485
362
433
182
334
480
570
836
1020
252
819
521
250
254
260
346
196
346
120
126
134
168
208
165
143
178
178
271
994
328
222
374
533
258
398
224
244
276
941
867
930
612
444
647
521
1450
764
355
277
563
160
534
1130
507
427
732
1210
536
501
503
430
361
176
143
494
198
352
205
285
303
183
300
636
272
533
776
743
330
395
401
356
486
1030
224
Average
75Percentile
95percentile
Median
Max
Min
201
131
114
178
467
54.7
257
175
127
219
601
59.3
394
215
128
328
1020
107
521
302
178
486
1450
143
Average
75Percentile
95percentile
Median
Max
Min
539
350
305
477
1251
147
626
426
309
535
1467
145
1054
576
344
879
2732
287
1351
781
462
1260
3758
371
June
July
248
130
388
429
156
123
147
233
511
484
233
373
557
308
161
132
1320
870
927
467
249
590
227
234
572
496
606
938
862
414
535
197
316
413
515
600
244
283
965
909
325
412
279
578
287
318
365
494
507
407
173
158
357
167
571
299
437
326
144
122
272
332
228
180
184
162
214
122
194
217
236
162
460
269
732
1070
324
345
192
218
342
649
250
185
173
179
167
165
407
192
696
323
174
166
Flow (m3/sec)
403
392
358
256
221
180
176
158
125
371
316
308
1030
1320
1070
126
144
122
Discharge in Million m3
1080
1016
960
684
572
481
471
408
335
994
819
825
2759
3421
2866
337
373
327
August
September
October
November
December Average
110
291
90
193
338
365
174
415
276
299
206
249
291
444
471
242
246
287
413
1000
484
251
314
210
157
164
195
183
201
117
566
112
242
121
126
200
537
421
254
213
531
285
174
398
330
280
167
95.9
118
97.4
212
308
425
142
598
205
237
281
337
156
211
322
432
247
415
216
424
326
200
147
138
165
244
155
321
400
110
165
112
426
128
153
518
274
267
265
178
372
196
173
237
242
233
352
75.2
103
102
265
153
182
136
476
157
198
203
269
137
407
229
409
227
363
160
494
284
175
146
141
158
168
146
230
206
138
255
135
208
138
163
435
420
449
225
183
304
345
177
200
194
185
214
78.1
118
110
179
121
375
134
234
146
239
223
313
151
757
223
244
162
222
230
538
446
155
183
121
182
112
144
221
201
141
326
470
294
141
173
283
233
610
223
179
311
320
176
233
207
208
233
75.4
142
124
342
413
300
115
176
192
241
370
289
129
381
146
259
112
254
242
569
406
180
118
111
281
114
138
182
209
153
211
271
200
150
148
275
359
282
327
192
318
211
169
265
180
187
257
290
188
114
251
1000
90
255
161
111
237
598
95.9
229
155
113
198
494
75.2
241
153
114
221
757
78.1
229
149
113
209
569
75.4
777
504
304
672
2678
241
660
416
287
614
1550
249
614
415
302
530
1323
201
624
397
295
573
1962
202
613
399
302
560
1524
202
173
285
218
258
385
379
341
328
487
457
337
270
298
390
386
398
325
406
399
610
466
349
257
234
268
210
172
283
286
154
252
211
244
157
185
327
337
486
422
290
342
310
257
243
309
349
235
Discharge
(mil m3)
5474
8996
6891
8138
12134
11971
10756
10346
15371
14406
10632
8523
9391
12315
12186
12568
10269
12815
12591
19250
14706
11027
8102
7387
8450
6614
5425
8939
9033
4863
7947
6659
7705
4960
5846
10309
10622
15337
13328
9165
10798
9785
8102
7676
9757
11006
7421
Page4
Appendices
Appendix B
Water Quality Data for Prut and Nistru Rivers
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
Appendix B
Nistru River and the lake Dubasari, 2008
Location
Date
SO4
--
HCO3
--
Cl
++
Mg
++
Na
Mineralization
(mg/l)
Water hardness
(mg-ecv/l)
r.Nistru, Valcinet
r.Nistru, Soroca
rez.Dubsari, Erjovo
rez.Dubsari, Goieni
rez.Dubsari, Cocieri
r.Nistru, Vadul-lui-Voda
r.Nistru, Varnita
r.Nistru, Sucleia
r.Nistru, Palanca
13.02.2008
23.02.2008
23.02.2008
23.02.2008
23.02.2008
23.02.2008
01.03.2008
22.02.2008
01.03.2008
72,4
65
69,5
72,8
69,1
106,2
93
92,2
95,5
189,2
190,7
201,4
201,4
195,3
210,6
204,5
213,7
207,5
26,2
27,7
29,4
29,4
27,7
29,4
30,8
30,8
32,3
64,1
64,1
68,1
68,1
72,1
70,1
70,1
70,1
67,1
9,6
12
14,4
14,4
9,6
12
14,4
18
19,8
26.8
34.5
16.1
18.6
18.2
34.4
25.1
24.6
25.7
6.,0
14,7
8.4
10.2
7.3
15.4
11.4
7.7
7.3
395,3
408,7
407,3
414,9
399,3
478,1
449,3
457,1
455,2
4
4.3
4.6
4.5
4.4
4.4
4.7
5
5
r.Nistru, Naslavcea
r.Nistru, Valcinet
r.Nistru, Soroca
r.Nistru, Camenca
rez.Dubsari, Erjovo
rez.Dubsari, Goieni
rez.Dubsari, Cocieri
r.Nistru, Vadul-lui-Voda
r.Nistru, Varnita
r.Nistru, Sucleia
r.Nistru, Palanca
19.05.2008
19.05.2008
19.05.2008
20.05.2008
20.05.2008
20.05.2008
20.05.2008
21.05.2008
21.05.2008
21.05.2008
21.05.2008
69,54
93,82
68,31
74,48
68,72
76,54
65,43
96,29
88,88
84,36
90,94
180
186,1
180
207,5
183,1
192,2
155,6
189,2
198,3
192,2
207,5
41,83
43,25
47,86
44,67
46,44
47,86
44,67
44,67
46,44
47,86
51,05
70,14
70,14
70,14
70,14
74,15
65,13
62,12
54,13
62,12
71,14
64,13
9
8,4
6
10,8
9
14,4
7,2
12,6
26,4
17,4
10,8
22.9
34.8
29.9
31.2
29.8
28.3
25.4
37.1
19.2
21.7
50.4
33,25
50.5
13.4
14.0
2.4
12.7
11.4
16.5
8.5
10.2
15.3
403,8
477,2
415, 6
452,8
413,7
437,1
371,8
450,8
449,1
444,5
490,2
4,25
4,2
4
4,4
4,45
4,45
3,7
4,25
5,3
5
4,1
r.Nistru, Naslavcea
r.Nistru, Valcinet
r.Nistru, Soroca
r.Nistru, Camenca
rez.Dubsari, Erjovo
rez.Dubsari, Goieni
rez.Dubsari, Cocieri
r.Nistru, Vadul-lui-Voda
r.Nistru, Varnita
r.Nistru, Sucleia
r.Nistru, Palanca
18.07.2008
18.07.2008
18.07.2008
19.07.2008
20.07.2008
20.07.2008
20.07.2008
22.07.2008
22.07.2008
22.07.2008
22.07.2008
49,97
51,44
48,56
51,4
52,67
56,38
53,91
62,38
64,19
71,19
69,54
166,28
167,81
183,06
170,86
173,81
180,01
158,65
169,33
173,81
176,96
189,16
20,84
20,84
25,18
22,58
22,58
24,32
22,58
24,32
26,92
28,66
29,53
59,12
60,12
58,12
54,11
56,11
54,11
40,08
52,1
52,1
54,11
56,11
9,12
8,51
9,73
12,16
12,16
15,81
18,24
12,16
15,81
14,59
17,02
1.3
2.1
5.5
14.2
13.6
14.2
14.8
19.7
18.8
22.2
20.4
307,1
311,72
332,4
331,36
336,83
350,78
329,71
349,19
359,96
377,74
390,94
3,7
3,7
3,7
3,7
3,8
4
3,5
3,6
3,9
3,9
4,2
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
1
0.5
0.9
2.2
6.0
5.9
20,15
11.4
9.2
8.3
10.0
9.2
++
178,49
23,45
62,12
9,73
11.6
r.Nistru, Valcinet
11.11.2008
45,68
178,49
23,01
62,12
10,94
9.1
r.Nistru, Soroca
11.11.2008
52,67
195,26
26,92
68,14
10,94
13.2
r.Nistru, Camenca
12.11.2008
105,34
216,62
24,75
68,14
15,81
30.1
rez.Dubsari, Erjovo
12.11.2008
41,56
195,26
24,32
65,13
11,55
9.8
rez.Dubsari, Goieni
12.11.2008
48,15
216,62
27,36
64,13
17,02
12.9
rez.Dubsari, Cocieri
12.11.2008
31,69
180,1
23,88
64,13
8,51
6.5
r.Nistru, Vadul-lui-Voda
13.11.2008
51,03
198,32
27,79
62,12
14,59
13.6
r.Nistru, Varnita
13.11.2008
99,17
196,78
25,18
60,12
14,59
31.0
r.Nistru, Sucleia
13.11.2008
91,77
208,99
26,92
65,13
12,77
31.2
r.Nistru, Palanca
13.11.2008
98,35
210,52
26,05
61,12
16,42
31.3
r.Nistru, Olanesti
r.Nistru, Rascaieti
r.Nistru, Valcinet
r.Nistru, Soroca
r.Nistru, Sucleia
rez.Dubsari, Erjovo
rez.Dubsari, Goieni
rez.Dubsari, Cocieri
r.Nistru, Dubasari
r.Nistru, Vadul-lui-Voda
12.02.2008
12.02.2008
13.02.2008
23.02.2008
22.02.2008
23.02.2008
23.02.2008
23.02.2008
23.02.2008
23.02.2008
1,9
1,6
1,5
3
2,8
2,5
2,6
2,4
2
(mg/l)
13,43
13,49
13,54
13,8
13,57
14,39
15,04
14,8
14,23
14,14
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
2
O2
%
96,2
95,9
96
97,8
100,1
105,6
109,5
108
103,3
101,6
Na
46,91
O2
Mg
++
11.11.2008
t,C
Cl
r.Nistru, Naslavcea
Date
HCO3
--
Date
Location
SO4
--
Location
Mineral
Suspension
(mg/l)
0,4
2,4
1,6
3
0,4
2,8
0,4
0,4
1,8
5,6
Mineralization
(mg/l)
5.2
4.2
5.6
13.4
4.2
5.2
3.2
6.2
14
13.8
14.7
Organic
Suspension
(mg/l)
0,2
1,2
2,4
1,2
2
1,2
0,2
0,2
0,2
1
Water
hardness
(mg-ecv/l)
337,45
3,9
333,49
372,68
4,3
474,11
4,7
351,82
4,2
391,28
4,6
317,81
3,9
373,6
4,3
440,84
4,2
450,58
4,3
458,46
4,4
Suspension
Total
(mg/l)
0,6
3,6
4
4,2
2,4
4
0,6
0,6
2
6,6
r.Nistru, Varnita
r.Nistru, Palanca
r.Nistru, Naslavcea
r.Nistru, Valcinet
r.Nistru, Soroca
r.Nistru, Camenca
Location
01.03.2008
01.03.2008
19.05.2008
19.05.2008
19.05.2008
20.05.2008
Date
4
5,8
11,2
12,4
16,9
17
t,C
13,36
13,56
11,36
15,31
15,38
11,62
101
107,2
101,6
140,5
154,6
117
O2
O2
5
1,8
0,8
1,2
1,6
3,6
1,4
0,6
4,8
5,6
4,8
4,4
6,4
2,4
5,6
6,8
6,4
8
Organic
Suspension
(mg/l)
1,6
1,6
3,6
2,6
1,4
1,4
5,2
Suspension
Total
(mg/l)
14,4
2,4
8
6,6
8
8,8
8,8
rez.Dubsari, Erjovo
rez.Dubsari, Goieni
rez.Dubsari, Cocieri
r.Nistru, Vadul-lui-Voda
r.Nistru, Varnita
r.Nistru, Sucleia
r.Nistru, Palanca
20.05.2008
20.05.2008
20.05.2008
21.05.2008
21.05.2008
21.05.2008
21.05.2008
17,8
19,8
21
18,3
17
18,1
18,9
(mg/l)
11,11
12,5
16,44
10,68
9,31
9,58
8,62
%
113,6
132,6
178,1
110,3
93,8
98,6
89,9
Mineral
Suspension
(mg/l)
12,8
0,8
4,4
4
6,6
7,4
3,6
r.Nistru, Naslavcea
r.Nistru, Valcinet
r.Nistru, Soroca
r.Nistru, Camenca
rez.Dubsari, Erjovo
rez.Dubsari, Goieni
rez.Dubsari, Cocieri
r.Nistru, Vadul-lui-Voda
r.Nistru, Varnita
r.Nistru, Sucleia
r.Nistru, Palanca
18.07.2008
18.07.2008
18.07.2008
19.07.2008
20.07.2008
20.07.2008
20.07.2008
22.07.2008
22.07.2008
22.07.2008
22.07.2008
14,2
16,8
20,6
21,5
22
22,5
22,8
22,4
25,2
25,5
26,3
7,73
13,15
8,8
12,03
9,57
8,36
10,61
8,57
7,39
7,02
7,25
73,6
131,8
94,7
131,7
105,6
93,1
118,7
6,52
86,1
82,2
85,9
0,4
0,2
1,2
2,4
4,8
4,4
0,8
1,6
2
1,2
7,6
0,4
0,2
1,4
5,2
5,2
1,2
2
2
7,2
6,8
1
0,8
0,4
2,6
7,6
10
5,6
2,8
3,6
9,2
8
8,6
r.Nistru, Naslavcea
r.Nistru, Valcinet
r.Nistru, Soroca
11.11.2008
11.11.2008
11.11.2008
10,5
9,8
7,9
8,01
9,89
11,12
70,6
85,9
92,4
0,4
0,4
3,2
0,4
0,4
1,2
0,8
0,8
4,4
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
3
r.Nistru, Camenca
rez.Dubsari, Erjovo
rez.Dubsari, Goieni
rez.Dubsari, Cocieri
r.Nistru, Vadul-lui-Voda
r.Nistru, Varnita
r.Nistru, Sucleia
r.Nistru, Palanca
12.11.2008
12.11.2008
12.11.2008
12.11.2008
13.11.2008
13.11.2008
13.11.2008
13.11.2008
7,2
7,8
9,8
11,2
10
9,4
9,4
9,1
12,17
12,03
11,25
11,55
10,12
10,48
10,37
8,66
99,5
99,8
97,6
103,3
88,3
90,1
89,1
74
1,8
2
3,2
2
3,4
1,4
1,2
2
0,2
0,1
0,4
0,4
0,6
0,2
1,6
0,2
2
2,1
3,6
2,4
4
1,6
2,8
2,2
Date
SO4
--
HCO3
--
Cl
++
Mg
++
Na
Mineralization
(mg/l)
16.05.2008
16.05.2008
17.05.2008
17.05.2008
18.05.2008
57,61
49,38
49,38
55,96
77,77
180,01
155,6
155,6
158,65
180,01
18,57
14,77
18,99
19,41
20,68
59,12
50,1
52,1
52,1
53,11
10,34
9,73
8,51
8,51
12,16
15.2
12.3
14.2
17.5
18.4
6.5
5.4
6.3
7.7
9.1
347,2
297,1
305,1
319,9
381,2
rez.Costesti-Stanc,sect.superior (Badrajii
Noi)
rez.Costesti-Stanc,sect.mediu (Cucunesti)
rez.Costesti-Stanc,sect.inferior
r.Prut, Brneti
r.Prut, Sculeni
r.Prut, Sculeni
r.Prut, Leueni
r.Prut, Leovo
25.07.2008
25.07.2008
26.07.2008
26.07.2008
27.07.2008
24.08.2008
24.08.2008
21.08.2008
73,25
65,84
55,96
66,66
68,31
83,12
92,18
100,82
178,48
161,7
158,65
161,7
172,38
154,08
173,91
201,37
20,26
21,09
19,41
19,41
20,26
14,56
18,84
23,98
64,13
56,11
52,1
53,11
54,11
46,09
48,09
53,11
9,12
8,51
10,34
10,34
12,16
9,73
13,38
15,2
6.4
19.2
14.9
18.8
18.9
27.7
31.0
37.6
3.6
8.6
6.7
8.4
8.9
11.6
14.1
6.7
354,4
341,1
318.0
338,5
355,1
346,8
391,4
448,7
r.Prut, Calia-Prut
r.Prut, Cahul
r.Prut, Djiurdjiuleti
13.09.2008
14.09.2008
25.09.2008
92,99
91,35
92,99
199,84
201,37
202,13
17,55
18,41
19,69
49,09
51,1
53,11
13,38
13,98
13,98
37.2
34.9
34.2
16.6
15.7
15.8
426,6
426,7
431,9
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
4
rez.Costesti-Stanc,sect.superior (Badrajii
Noi)
rez.Costesti-Stanc,sect.inferior
r.Prut, Brneti
r.Prut, Sculeni
Location
24.10.2008
25.10.2008
25.10.2008
25.10.2008
79,83
77,36
80,65
119,34
213,57
175,43
186,11
222,72
28,97
20,75
21,73
23,01
Date
t,C
O2
O2
(mg/l)
76,15
62,12
64,13
60,12
12,77
9,73
12,16
17,63
Mineral
Suspension
(mg/l)
19.5
20.4
24.2
40.2
8.7
8.7
4.3
18.1
Organic
Suspension
(mg/l)
Suspension
Total
(mg/l)
rez.Costesti-Stanc,sect.superior (Badrajii
Noi)
rez.Costesti-Stanc,sect.mediu (Cucunesti)
rez.Costesti-Stanc,sect.inferior
r.Prut, Brneti
r.Prut, Sculeni
16.05.2008
16.05.2008
17.05.2008
17.05.2008
18.05.2008
15,4
15,4
13,2
12,4
14,8
10,97
11,02
10,8
10,43
10,19
107
107,5
100,8
95,7
98,2
20
5,2
0,4
1,2
34,6
4,4
1
0,8
0,4
3
24,4
6,2
1,2
1,6
37,6
rez.Costesti-Stanc,sect.superior (Badrajii
Noi)
rez.Costesti-Stanc,sect.mediu (Cucunesti)
rez.Costesti-Stanc,sect.inferior
r.Prut, Brneti
r.Prut, Sculeni
r.Prut, Sculeni
r.Prut, Leueni
r.Prut, Leovo
25.07.2008
25.07.2008
26.07.2008
26.07.2008
27.07.2008
24.08.2008
24.08.2008
21.08.2008
27
28,8
26,4
21,2
24,8
21,3
21,8
22
10,55
12,05
9
6,36
8,34
6,82
5,62
7,59
126,35
148,39
106,76
69,21
96,42
74,3
61,8
83,8
22,4
6,4
1,2
0,8
26,8
136,4
296,4
4,8
1,6
0,8
2,8
1,6
15,6
37,6
27,2
8
2
3,6
28,4
152
334
13.09.2008
14.09.2008
25.09.2008
25,4
21,5
16
5,98
6,83
8,1
69,9
74,4
79,9
20
124,4
68,4
4,4
16,8
11,2
24,4
141,2
79,6
24.10.2008
25.10.2008
25.10.2008
25.10.2008
12
13,2
13,2
13,4
11,53
9,62
10,19
10,19
104,9
89,7
95,1
95,5
71,2
0,4
1,2
12,4
9
0,3
0,5
0,6
80,2
0,7
1,7
13
r.Prut, Calia-Prut
r.Prut, Cahul
r.Prut, Djiurdjiuleti
rez.Costesti-Stanc,sect.superior (Badrajii
Noi)
rez.Costesti-Stanc,sect.inferior
r.Prut, Brneti
r.Prut, Sculeni
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
5
439,5
374,5
393,3
501,1
Appendices
Appendix C
Historic Water Use Data for Prut and Nistru River Basins
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
APPENDIX C
Industry
244.83
244.83
245.1
234.89
240.72
240.67
220.95
209.09
198.9
171.86
75.72
61.68
54.12
50.13
49.38
53.45
55.12
58.99
158.8
116.96
107.77
108.58
81.89
61.62
60.2
48.67
56.3
53.27
16.81
15.99
16.09
15.92
14.23
12.38
12.19
10.68
Central
Irrigation
Systems
599.35
269.4
465.73
361.36
472.72
291.98
206.66
99.68
64.92
61.21
11.25
5.54
7.66
10.59
6.21
5.72
5.86
17.77
Agriculture
Fish
Farming
86.05
78.79
73.52
70.85
63.67
56.4
54.79
43.88
43.04
36.12
28.84
17.02
16.84
16.57
16.82
16.13
16.75
16.87
45.7
45.05
39.79
29.54
29.23
32.97
33.89
28.87
28.7
2.59
0.73
0.39
0.85
0.44
0.42
0.64
0.65
1.14
Agriculture
Fish
Farming
27.94
26.58
25.53
22.87
20.95
18.54
15.87
14
13.69
12.97
12.77
7.61
7.58
7.64
7.66
7.58
7.66
7.84
27.56
26.99
23.09
18.12
17.66
13.33
9.48
5.59
5.88
3.61
4.81
0.16
0.18
0.17
0.14
0.16
0.15
0.16
1200
FishFarming
1000
Agriculture
800
CentralIrrigation
Systems
Industry
600
400
200
0
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Drinking
Water
WaterUsage(milm3)
NISTRURIVERBASIN
18.83
17.6
16.8
16.33
15.81
14.74
12.78
11.61
10.68
9.08
6.26
4.95
3.93
3.58
3.35
3.43
3.4
3.8
13.77
13.57
12.36
11.43
8.55
6.54
5.8
5.18
5.15
3.07
2.65
2.06
2.11
2.07
2.18
2.43
2.46
2.09
Central
Irrigation
Systems
232.26
73.87
134.89
84.99
112.54
84.65
41.99
20.69
19.72
11.71
2.13
1.05
2.28
5.14
4.6
3.36
3.6
8.72
350
300
FishFarming
250
Agriculture
200
150
CentralIrrigation
Systems
100
50
0
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Industry
waterUsage(milm3)
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Drinking
Water
PRUTRIVERBASIN
6.94
7.47
6.63
6.98
6.13
5.51
4.97
4.46
4.32
3.75
3.65
2.91
2.16
2.09
1.99
2.68
2.03
2.01
3.64
4.2
2.75
2.86
2.3
1.76
1.42
1.25
0.86
0.76
0.69
0.46
0.35
0.39
0.45
0.54
0.34
0.39
Central
Irrigation
Systems
66.2
44.32
56.43
34.84
36.18
25.66
25.57
8.05
7.25
7.2
0.99
0.06
0.93
3.5
1.81
2.13
2
3.73
Agriculture
Fish
Farming
20.63
20.03
19.42
16.38
15.75
11.92
9.77
8.95
8.76
9.02
8.31
4.66
4.42
4.36
4.34
4.95
4.4
4.53
0
0
0
0
0
0
1.5
1.5
1.49
0.49
0.5
0.75
0.9
0.72
0.72
0.4
0.55
0.72
120
100
80
FishFarming
Agriculture
CentralIrrigationSystems
60
Industry
40
DrinkingWater
20
0
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Industry
WaterUsuage(milm3)
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Drinking
Water
INTERBASIN
Appendices
Appendix D
Future Water Use Estimates for Prut and Nistru River
Basins
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
APPENDIX D
Hectares
1000
m3/hectare
521
1930
1815
4417
1018
963
1258
3.36
3.89
3.67
4.49
4.44
4.44
3.48
Total
April
May
June
July
August
156
671
594
1770
403
382
391
4,368
323
1387
1228
3659
834
789
809
9,027
312
1342
1188
3541
807
763
783
8,736
323
1387
1228
3659
834
789
809
9,027
323
1387
1228
3659
834
789
809
9,027
Sept
Total
312
1342
1188
3541
807
763
783
8,736
1749
7516
6653
19828
4519
4274
4384
48,922
Industrial Requirements
Domestic Requirements
Agricultural Use
Fish Farming
Irrigation (other schemes)
Total Demand
Return Water
Net Demand
May
June
July
Aug
Sept
Total
0.17
0.08
1.44
0.01
1.17
2.88
-0.75
2.13
0.17
0.08
1.44
0.01
1.17
2.88
-0.75
2.13
0.17
0.08
1.44
0.01
1.17
2.88
-0.75
2.13
0.17
0.08
1.44
0.01
1.17
2.88
-0.75
2.13
0.17
0.08
1.44
0.01
1.17
2.88
-0.75
2.13
0.96
0.46
7.85
0.06
6.39
15.72
-4.13
11.59
April
May
June
July
Aug
Sept
Total
170.04
21.80
74.12
4.59
0.95
68.58
356.53
43.60
156.46
9.48
2.13
144.86
353.42
43.60
154.91
9.17
2.13
143.61
334.97
43.60
145.69
9.48
2.13
134.08
279.56
43.60
117.98
9.48
2.13
106.37
202.91
43.60
79.66
9.17
2.13
68.36
1697.44
239.80
728.82
51.37
11.59
665.86
% of
Available
Flow
7.05%
April
May
June
July
Aug
Sept
Total
94.09
21.80
36.14
4.59
0.95
30.61
238.51
43.60
97.46
9.48
2.13
85.85
205.68
43.60
81.04
9.17
2.13
69.74
186.01
43.60
71.21
9.48
2.13
59.60
157.76
43.60
57.08
9.48
2.13
45.47
125.97
43.60
41.19
9.17
2.13
29.88
1008.02
239.80
384.11
51.37
11.59
321.15
% of
Available
Flow
13.37%
April
May
June
July
Aug
Sept
Total
139.44
21.80
58.82
4.59
0.95
53.28
292.35
43.60
124.38
9.48
2.13
112.77
289.81
43.60
123.10
9.17
2.13
111.80
274.68
43.60
115.54
9.48
2.13
103.93
229.24
43.60
92.82
9.48
2.13
81.21
166.39
43.60
61.39
9.17
2.13
50.09
1391.90
239.80
576.05
51.37
11.59
513.09
% of
Available
Flow
8.92%
April
May
June
July
Aug
Sept
Total
77.15
21.80
27.68
4.59
0.95
22.14
195.58
43.60
75.99
9.48
2.13
64.38
168.65
43.60
62.53
9.17
2.13
51.23
152.53
43.60
54.47
9.48
2.13
42.86
129.36
43.60
42.88
9.48
2.13
31.27
103.30
43.60
29.85
9.17
2.13
18.55
826.58
239.80
293.39
51.37
11.59
230.43
% of
Available
Flow
17.51%
Total
Extracted
(1000 m3)1
1,836
7,891
6,986
20,819
4,745
4,488
4,603
51,368
APPENDIX D
Hectares
1000
3
m /hectare
2800
677
1165
506
856
682
1107
13394
2468
3.61
3.97
4.07
4.34
4.30
4.65
3.57
4.00
3.84
Total
1. Total Extracted is assumed to be an additional 5% of the Total Water Required
April 15 -30
2.21
7.16
3.01
0.28
5.08
17.74
-8.43
9.31
Industrial Requirements
Domestic Requirements
Agricultural Use
Fish Farming
Irrigation (other schemes)
Total Demand
Return Water
Net Demand
May
4.44
14.32
6.62
0.56
11.22
37.16
-16.88
20.28
April
May
June
July
902
240
423
196
329
283
352
4785
846
8,356
1864
496
875
405
680
585
728
9888
1748
17,270
1804
480
847
392
658
566
705
9569
1692
16,713
1864
496
875
405
680
585
728
9888
1748
17,270
Sept
4.44
14.32
6.62
0.56
11.22
37.16
-16.88
20.28
August
1864
496
875
405
680
585
728
9888
1748
17,270
Sept
1804
480
847
392
658
566
705
9569
1692
16,713
Total
24.41
78.76
36.11
3.08
61.18
203.54
-92.85
110.69
3
Average Flow Conditions (mil m )
April
May
June
July
Aug
Sept
Total
604.32
148.33
228.00
8.77
9.31
209.92
1036.07
296.70
369.69
18.13
20.28
331.28
910.18
296.70
306.74
17.55
20.28
268.91
888.83
296.70
296.07
18.13
20.28
257.66
800.15
296.70
251.72
18.13
20.28
213.31
630.62
296.70
166.96
17.55
20.28
129.14
4870.18
1631.83
1619.17
98.27
110.69
1410.22
% of
Available
Flow
6.07%
April
May
June
July
Aug
Sept
Total
416.99
148.33
134.33
8.77
9.31
116.25
682.32
296.70
192.81
18.13
20.28
154.40
640.87
296.70
172.09
17.55
20.28
134.26
605.99
296.70
154.64
18.13
20.28
116.23
578.53
296.70
140.92
18.13
20.28
102.51
465.91
296.70
84.61
17.55
20.28
46.78
3390.62
1631.83
879.39
98.27
110.69
670.44
% of
Available
Flow
11.17%
April
May
June
July
Aug
Sept
Total
495.55
148.33
173.61
8.77
9.31
155.53
849.58
296.70
276.44
18.13
20.28
238.03
746.34
296.70
224.82
17.55
20.28
187.00
728.84
296.70
216.07
18.13
20.28
177.66
656.12
296.70
179.71
18.13
20.28
141.30
517.11
296.70
110.21
17.55
20.28
72.38
3993.54
1631.83
1180.86
98.27
110.69
971.90
% of
Available
Flow
8.32%
3
Drought Conditions (mil m )
April
May
June
July
Aug
Sept
Total
341.93
148.33
96.80
8.77
9.31
78.72
559.50
296.70
131.40
18.13
20.28
92.99
525.52
296.70
114.41
17.55
20.28
76.58
496.91
296.70
100.11
18.13
20.28
61.70
474.40
296.70
88.85
18.13
20.28
50.44
382.05
296.70
42.67
17.55
20.28
4.85
2780.31
1631.83
574.24
98.27
110.69
365.28
% of
Available
Flow
17.11%
Total
10,103
2,688
4,743
2,197
3,683
3,168
3,947
53,588
9,474
93,590
Total
Extracted
(1000 m3)1
10,608
2,822
4,980
2,307
3,867
3,327
4,145
56,267
9,948
98,270
Appendices
Appendix E
Assumptions for Basis of Design for Proposed
Rehabilitation
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
APPENDIX E
2020
% Traditional
% HVA
% Traditional
0.66
0.62
0.68
0.70
0.65
0.70
0.78
0.71
0.68
0.76
0.74
0.74
0.65
0.64
0.62
0.83
0.34
0.38
0.32
0.30
0.35
0.30
0.22
0.29
0.32
0.24
0.26
0.26
0.35
0.36
0.38
0.17
0.78
0.72
0.80
0.83
0.79
0.86
0.99
0.89
0.82
0.95
0.88
1.00
0.78
0.74
0.72
0.93
0.67
0.64
0.69
0.71
0.66
0.71
0.78
0.71
0.68
0.76
0.74
0.73
0.65
0.65
0.64
0.83
0.33
0.36
0.31
0.29
0.34
0.29
0.22
0.29
0.32
0.24
0.26
0.27
0.35
0.35
0.36
0.17
83%
66%
78%
68%
68%
70%
62%
71%
76%
65%
70%
65%
74%
74%
62%
64%
17%
34%
22%
32%
32%
30%
38%
29%
24%
35%
30%
35%
26%
26%
38%
36%
93%
78%
99%
80%
82%
83%
72%
89%
95%
79%
86%
78%
88%
100%
72%
74%
83%
67%
78%
69%
68%
71%
64%
71%
76%
66%
71%
65%
74%
73%
64%
65%
% Traditional
% HVA
0.42
0.33
0.47
0.51
0.42
0.56
0.76
0.58
0.49
0.69
0.60
0.73
0.42
0.36
0.36
0.78
0.58
0.67
0.53
0.49
0.58
0.44
0.24
0.42
0.51
0.31
0.40
0.27
0.58
0.64
0.64
0.22
0.65
0.60
0.68
0.70
0.66
0.74
0.86
0.76
0.69
0.82
0.76
0.87
0.66
0.61
0.61
0.92
78%
42%
76%
47%
49%
51%
33%
58%
69%
42%
56%
42%
60%
73%
36%
36%
22%
58%
24%
53%
51%
49%
67%
42%
31%
58%
44%
58%
40%
27%
64%
64%
92%
65%
86%
68%
69%
70%
60%
76%
82%
66%
74%
66%
76%
87%
61%
61%
% HVA
Blindesti
Cahul
Carpinenii de Sus
Chircani-Zirnesti
Cosnita
Criuleni
Grozesti
Jora de Jos
Leova Sud
Lopatna
Pugaceni
Roscani
Serpeni
Suvorov
Talmaz
Tetcani
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
Tetcani
Blindesti
Grozesti
Carpinenii de Sus
Leova Sud
Chircani-Zirnesti
Cahul
Jora de Jos
Lopatna
Cosnita
Criuleni
Serpeni
Pugaceni
Roscani
Talmaz
Suvorov
45%
45%
45%
45%
45%
45%
45%
45%
45%
45%
45%
45%
45%
45%
45%
45%
2025
Total %
Irrigated
Total %
Irrigated
% of Total Area
Irrigated
Page 1
APPENDIX E
CerealandOilSeed
Scheme
Blindeti
Masivul Cahul
Crpinenii de Sus
Chircani-Zrneti
Conia
Criuleni
Grozeti
Jora de Jos
Leova Sud
Lopatna
Pugceni
Rocani
erpeni
Masivul Suvorov
Masivul Talmaz
Tetcani
Site
Ratio
0.97
0.99
1.02
0.99
1.01
1.01
0.98
1.00
0.98
0.99
1.01
1.02
1.02
0.98
0.99
0.97
Daily
HVA(m3/ha)
1,636
1,894
1,734
1,894
1,604
1,604
1,664
1,590
1,881
1,567
1,601
1,608
1,608
1,867
1,889
1,830
3,681
4,790
3,902
4,790
3,928
3,928
3,746
3,893
4,756
3,893
4,889
3,936
3,936
4,780
4,722
3,184
Monthly
84
98
89
98
89
89
85
89
97
87
89
90
90
97
98
87
2,194
2,578
2,326
2,578
2,242
2,242
2,233
2,221
2,560
2,190
2,236
2,247
2,247
2,543
2,572
2,163
2014
Vegetative
4,614
5,758
4,891
5,758
4,899
4,899
4,695
4,855
5,717
4,788
4,889
4,908
4,908
5,746
5,676
3,864
4,075
5,113
4,364
5,285
4,338
4,467
4,463
4,449
5,226
4,510
4,889
4,649
4,346
5,123
5,061
3,713
2020
(m3/ha)
4,298
5,387
4,571
5,468
4,561
4,610
4,485
4,577
5,411
4,570
4,889
4,651
4,569
5,398
5,316
3,746
2025
4,303
5,408
4,582
5,478
4,567
4,617
4,484
4,574
5,412
4,571
4,889
4,646
4,572
5,407
5,332
3,747
Page 2
Appendix E
Code
1-1
CIS System
Area
Irrigated (Ha)
Proposed
Water
Demand
(m3/s) 1
1258
1.22
SP-1
313
0.30
SP-1
tr SP-2
PS ID #
Tetcani
Requested
Design
Discharge
(lps/Ha)
Original
(BOD)
Design
Discharge
(lps/Ha)
0.97
1.05
Pressure at
Minimum
Hydrants
Pressure at
Number of
Potential
Discharge of
based on
Hydrants based
Watering
Existing
Suitable OnWatering
MCC-MCAon
Equipment
Pump
Farm Watering
Equipment
AM
Manufacturer's
Operating at Capcity (l/s)
Equipment
(lps)
Recommend
Recommendatio
a Time
ation (Bar)
n (Bar)
Existing
Required
Pump Head
Capacity (l/s)
(m)
SP-2
3-2
Blindeti
Source: Prut
AIPRE:
Ugheni
SR-3
SP-4
SP-7
3-6
Grozeti
Source: Prut
Ugheni
SP-11
SPR-12
NSG-1
NSP-1
NSP-2
445
0.43
0.97
500
521
0.49
0.51
0.97
tr SP-4
180
0.17
0.97
80
120
141
0.08
0.12
0.97
0.97
0.14
0.97
1018
tr SPR-12
tr SPR-16*
398
240
1.00
NSP-7
NSP-2
5-4
Leova Sud
Source: Prut
Hnceti
S-28
S-28
S-2
6-6
Chircani-Zrneti
Source: Prut
S-5
4
0.91
0.24
0.98
0.88
0.14
0.98
0.82
1815
1.85
NSP-2
4
to NSP-7
648
567
320
tr NSP-4
963
tr B-1
tr S-2, S-3
363
0.29
1.02
0.66
0.58
0.33
1.02
1.02
1.02
0.97
280
0.27
0.98
320
0.31
4417
4.37
1.96
0.98
0.99
1980
SPP-3A
449
AIPRE: Cahul
0.52
0.40
1.21
1.21
1.91
0.44
0
0.99
0.99
0.62
0.69
0.99
1.05
SPP-2
675
0.67
0.99
806
0.80
0.99
0.94
1165
1.17
0.24
1.00
0.94
Source: Nistru
SPP-1
235
AIPRE:Orhei
SPP-2
tr SP-1
100
259
0.10
0.26
SPP-1
1.00
1.00
0.66
0.56
tr SP-2
SP-2
11-7 Lopatna
Source: Nistru
AIPRE: Orhei
12-3 Conia
Dubasari
SPP
80
0.08
1.00
278
213
0.28
1.00
0.21
0.50
1.00
506
tr SP
358
0.35
0.99
0.15
0.99
SP
SP-1
SP-2
SP-3
S-1
148
2800
986
353
tr S-1
620
2.24
1.00
0.36
0.63
4
0.32
1.01
1.01
1.01
0.65
0.27
1.01
1.51
Nistru
NSP-1
677
459
0.68
0.46
1.01
0.79
AIPRE:
Chiinu
NSP-2
0.12
1.01
0.10
1.13
1.01
NS-3
Source:
Nistru
AIPRE:
Chiinu
AIPRE:
Chiinu
1.67
tr S-12
0.68
1.02
0.84
670
S-14
to S14
437
856
0.45
0.86
1.02
0.80
S-17
438
0.44
1.01
0.92
4
S-18
418
0.42
682
0.70
1.01
0.72
S-20
tr S-22
4
AIPRE:
Chiinu
S-22
AIPRE:
tefan-Voda
682
2,468
ONS-1
0.70
1.02
1.41
880
90
920
90
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
1.02
Estimated
Volume per
Year (m3) at
2014
70%
1,202,048
3,713
522,960
70%
207,524
1,578,906
70%
552,838
3,713
743,506
70%
292,149
3,713
835,400
70%
120,253
2,101,866
20.00
22
330
105
440
101
0.99
20.00
24
440
57
480
37
0.96
380
63
520
62
360
92
260
88
Capacity Ok
Pump
Efficiency
(%)
Estimated
Volume per
Year (m3) at
2020
4,335,169
3,746
Estimated
Water
Annual
Consumption
Energy
per Year
Consumption
(KWh) at 2020
(m3/ha) at
2025
2,479,263
1,078,623
428,025
3,256,546
1,140,247
3,746
1,533,506
602,568
3,746
1,723,040
248,026
Estimated
Volume per
Year (m3) at
2025
4,383,778
3747
Annual
Energy
Consumptio
n (KWh) at
2025
432,824
3,293,060
1,153,032
3747
1,550,700
609,324
3747
1,742,360
250,807
955,368
70%
230,442
1,455,591
351,100
1,748,653
421,788
478,601
70%
163,853
729,192
249,646
876,005
299,908
20.00
180
90
180
90
1.00
Capacity Ok
4075
330,070
70%
115,571
4,298
502,891
176,082
4303
604,141
211,534
20.00
20.00
20.00
4
6
7
90
105
500
50
120
95
80
120
140
50
120
90
1.00
1.00
0.99
Capacity Ok
Capacity Ok
4075
4075
4075
146,698
220,046
258,555
70%
70%
70%
28,536
102,729
90,530
4,298
4,298
4,298
223,507
335,261
393,931
43,477
156,518
137,931
4303
4303
4303
268,507
402,761
473,244
52,231
188,030
165,702
70%
1,352,189
20.00
20.00
20.00
20
12
12
420
360
Change pumps
4463
4463
4463
799,327
482,006
482,006
70%
70%
73,134
178,146
4,485
4,485
4,485
1,535,241
925,774
925,774
140,465
342,159
4484
4484
4484
1,766,829
1,065,425
1,065,425
161,654
393,773
20.00
120
Capacity Ok
4463
281,170
70%
29,535
4,485
540,035
56,726
4484
621,498
65,283
3,563,916
70%
1,192,409
70%
1,247,870
139
1018
Not part of the assessment
Fed by Gravity
65
240
87
240
36
Capacity Ok
Change pumps
170
Fed by Gravity
Change pumps
2,044,510
39
95
1.00
1.00
140
27
1.00
1840
86
1840
90
3,563,916
880
1,741,704
20.00
14
230
61
280
59
1.00
20.00
34
550
92
680
85
1.05
Capacity Ok
Existing pump curves proves to
provide capacity
20.00
20.00
28
16
415
255
89
65
560
320
960
68
52
15
0.99
1.00
1560
128
960
123
20.00
18
360
81
0.99
New Pumps
5226
20.00
14
280
55
1.00
New Pumps
5226
20.00
16
320
43
1.00
New pumps
5226
1.00
5285
Capacity Ok
Change pumps
New PS
3,926,823
5,641,565
5,641,565
2,597,105
4,519,177
1,887,545
6,652,973
1,975,338
6,652,973
2,757,062
Drainage
Pump Flow
(l/s)
Volume per
Annual
Annual
Annual
Drainage
year (m3) 2014
Volume per
Volume per
Energy
Energy
Energy
Pump Head (assume 25%
Consumption year (m3) 2020 Consumption year (m3) 2025 Consumptio
(m)
of the Irrigation
2014
2020
n 2025
water)
2,507,062
1,090,717
2,988,874
2,225,940
2,329,472
3,251,343
4364
549,805
70%
126,200
4,571
870,324
199,771
4582
1,026,354
235,585
4364
1,272,406
70%
420,769
4,571
2,014,178
666,064
4582
2,375,276
785,475
4364
4364
1,113,356
628,349
1,822,212
70%
70%
70%
294,539
127,117
106,338
4,571
4,571
1,762,406
994,656
2,884,502
466,245
201,222
173,202
4582
4582
2,078,367
1,172,976
3,401,630
549,833
237,297
198,508
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
39
660
57
35
200
57
25
20.00
20.00
28
93
670
750
57
54
20.00
23
880
57
2,264,610
70%
1,083,672
3,595,178
1,720,381
4,273,871
2,045,153
853,638
70%
269,004
5,411
1,355,192
427,056
5412
1,611,023
507,675
658,454
70%
140,892
5,411
1,045,327
223,673
5412
1,242,662
265,898
752,518
70%
125,888
5,411
1,194,659
199,854
5412
1,420,186
237,582
4,708,717
70%
1,172,416
5,468
7,578,094
1,886,858
5408
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
60
700
75
57
560
1860
69
78
0.99
Change pumps
New pumps and PS.
5285
5285
2,897,764
2,897,764
70%
70%
777,878
879,340
5,468
5,468
4,663,589
4,663,589
1,251,897
1,415,188
5408
5408
460
45
1.02
Capacity Ok
5113
1,033,014
70%
180,850
5,387
1,451,240
254,069
5408
1,748,442
306,100
8,888,238
5,469,857
5,469,857
2,213,069
32
700
10
640
67
0.95
Change pumps
5113
1,552,973
70%
404,798
5,387
2,181,708
568,684
5408
2,628,504
685,145
42
1200
54
840
70
1.04
5113
1,854,364
70%
505,001
5,387
2,605,121
709,456
5408
3,138,628
854,746
20.00
12
220
75
240
70
1.02
Capacity Ok
4449
4,577
817,368
222,595
4574
630
60
950
70
3,234,689
880,907
20.00
20.00
5
14
110
360
95
90
100
280
85
78
500
195
500
195
Change pumps
1.00
1.08
Capacity Ok
Capacity Ok
Capacity Ok because have
basin
4449
4449
470,463
70%
128,122
1,861,832
70%
507,035
200,197
518,510
70%
70%
66,203
157,344
1,143,125
70%
867,217
4,577
4,577
347,816
900,843
115,019
273,365
1,986,029
1,506,675
4574
4574
956,645
260,524
3,785,872
1,031,011
407,083
1,054,345
134,617
319,946
2,324,444
1,763,409
20.00
120
92
80
70
1.00
Capacity Ok
4449
160,158
70%
43,616
4,577
278,253
75,777
4574
325,666
88,689
20.00
14
140
53
280
50
1.01
4449
556,548
70%
108,261
4,577
966,928
188,089
4574
1,131,691
220,139
20.00
11
210
44
210
44
0.99
Change pumps
Capacity Ok
4449
426,420
70%
72,994
4,577
740,848
126,818
4574
867,087
148,428
468
110
506
108
70%
431,439
1,896,063
796,665
20.00
18
Fed by Gravity
4510
726,489
4571
1,554,705
20.00
1.00
Capacity Ok
4510
300,336
70%
4338
4338
49
18
180
50
148
39
1,026,826
Capacity Ok
Gravity Fed
57
98
14
85
980
360
1200
620
69
97
14
81
0.99
1.02
Change pumps
2,197,432
1,341,483
45,569
4,570
554,580
84,145
4571
642,727
97,519
70%
70%
70%
70%
516,684
260,043
127,375
381,396
4,561
4,561
796,697
400,972
196,405
588,090
4567
4567
954,985
480,637
235,427
704,932
20.00
31
1.00
Capacity Ok
4338
1,924,761
689,088
2,338,604
1,210,296
4,561
2,967,870
1,062,534
3,605,992
1,866,206
4567
3,557,527
1,273,638
4,322,432
2,236,985
20.00
29
460
155
580
180
1.00
Change pumps
4338
1,128,308
70%
790,132
4,561
1,739,786
1,218,337
4567
2,085,447
1,460,397
395
50
260
66
0.99
Capacity Ok
4338
513,400
70%
131,825
4,561
791,633
203,267
4567
948,915
243,652
Change pumps
4467
922,751
70%
251,294
4,610
1,565,943
426,455
4617
1,822,409
496,299
4467
245,263
70%
71,564
4,610
416,220
121,446
4617
484,388
141,336
4467
192,994
192,994
70%
70%
37,542
42,047
4,610
327,517
327,517
63,709
71,355
4617
381,157
381,157
74,144
83,041
3,947,341
1,382,122
20.00
23
360
62
460
70
1.00
20.00
180
50
140
75
1.15
20.00
360
160
50
70
100
100
50
56
1.04
700
70
1110
90
20.00
34
560
70
670
79
70
20.00
22
40
350
85
440
440
20.00
22
420
65
20.00
21
300
45
Change pumps
Capacity Ok
Capacity Ok
Change pumps
1.00
Change pumps
70
80
1.01
Change pumps
Change pumps
438
82
1.00
420
81
1.00
Change pumps
2,165,159
70%
758,109
4346
1,310,440
70%
402,757
3,338,402
1,168,908
4,569
2,020,532
621,001
4346
854,720
854,720
70%
70%
232,767
266,019
4,569
1,317,870
1,317,870
4889
963,622
70%
307,411
4,889
4889
919,621
70%
289,797
4,889
70%
471,798
70%
444,045
70%
28,841
13
500
22
2,626,061
178,790
4,226,318
287,740
4,956,988
337,486
539
57
3000
20
1,110,088
166,271
1,559,517
233,588
1,878,894
281,425
1,405,242
72,894
2,000,894
103,792
2,368,466
122,858
923,291
4,570
880
440
1100
660
Capacity Ok
Change pumps
800
1,468,332
1,659,854
20.00
20.00
780
500
20.00
20.00
20.00
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
20.00
Capacity Ok
4572
2,389,086
734,274
358,897
410,168
4572
1,558,255
1,558,255
424,361
484,984
1,627,450
519,183
4889
1,884,416
601,160
1,553,138
489,434
4889
1,798,370
566,713
Masivul
Suvorov
801
0.79
0.99
1202
465
1.19
0.46
0.99
0.99
13,394
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
780
92
680
85
960
92
680
80
2800
5.5
460
1,426,717
Capacity Ok
2,759,645
912,581
3,168,272
1,047,709
4
20.00
34
1.00
Capacity Ok
4649
1,426,717
4,651
2,759,645
858,900
4646
3,168,272
986,079
330
10
48,611
40
10
2.44
tr NS-2
1.42
T-2
T-2
NS-2
17-3
147
102
Remarks
Estimated
Annual
Water
Energy
Consumption
Consumptio
per Year
n (KWh) at
(m3/ha) at
2014
2020
Estimated
Water
Consumption
per Year
(m3/ha) at
2014
Change pumps
14-13 Rocani
Source:
Nistru
1.48
S-12
14-11 Puhceni
Source:
Nistru
122
tr NS-3
96
1107
S-10
578
263
14-6 erpeni
1240
320
660
4
0.83
SP-4
14-2 Criuleni
105
Capacity
Provided
(lps/ha)
0.94
0.98
1219
1219
1930
SP-1
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
0.76
S-6
S-1
330
to NSP-1
Masivul - Cahul
Source: Prut
0.98
0.98
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
16
1.14
240
140
AIPRE: Cahul
6-9
4
1.50
20.00
0.81
tr SP-7
280
NSP-4
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
Required
Head (m)
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
1,059,056
Capacity ok
20.00
40
800
90
800
90
1.00
20.00
20.00
60
23
1200
660
90
70
1200
460
69
50
1.00
0.99
Capacity ok
Capacity ok
Capacity ok
1,507,967
1,784,986
5061
1,824,310
70%
638,764
5,316
2,597,595
909,522
5332
3,074,783
1,076,605
330
10
5061
5061
2,737,603
1,059,056
70%
170%
734,884
84,828
5,316
5,316
3,898,014
1,507,967
1,046,386
120,784
5332
5332
4,614,093
1,784,986
1,238,610
142,973
40
1000
10
20
400
20
13.13
GNS
tr NSP
6200
80
7100
80
19,574,204
70%
6,092,189
27,953,665
8,700,176
33,967,471
10,571,886
NSP
tr PNS-1
6200
80
7100
80
19,574,204
70%
6,092,189
27,953,665
8,700,176
33,967,471
10,571,886
PNS-1
PNS-1
1827
430
tr PNS-2
1.79
0.42
2260
82
5123
5123
70%
70%
70%
1,343,780
316,270
1,280,517
6,015,471
1,415,792
6,812,265
1,919,034
451,661
1,828,689
5407
5407
69
4,212,258
991,391
4,770,204
5,398
5398
1725
7,309,608
1,720,378
8,277,821
2,331,885
548,829
2,222,104
2.03
0.92
2.16
0.16
0.20
0.33
0.98
0.98
0.98
0.98
0.98
0.98
2070
940
2200
180
200
340
79
81
69
41
62
1.00
1.00
1.00
1.13
1.00
1.00
Change pumps
Change pumps
4,770,204
2,164,921
5,086,065
366,584
461,112
783,890
1,466,099
682,223
1,365,307
58,473
111,224
5398
5398
5398
5398
5398
5398
6,812,265
3,091,695
7,263,343
523,514
658,508
1,119,464
2,093,717
974,274
1,949,777
83,505
158,837
5407
5407
5407
5407
5407
5407
8,277,821
3,756,826
8,825,941
636,140
800,176
1,360,299
2,544,148
1,183,874
2,369,242
101,470
193,009
Fed by Gravity
5123
5123
5123
5123
5123
5123
70%
70%
70%
70%
70%
PNS-7
2069
939
2206
159
200
340
PNS-7
320
0.31
0.98
320
42
1.00
Capacity Ok
5123
5398
5407
4840
80
Source:
Nistru
AIPRE:
tefan-Voda
PNS-1
PNS-2
PNS-3
PNS-4
PNS-5
PNS-6
0.98
0.98
1.07
4
0.71
0.76
1.13
1.48
1.36
0.67
Reel Hose,
Hand-moving
laterals and/or
Drip irrigation
equipment
20.00
20.00
90
0
2200
1500
85
85
51
20.00
20.00
20.00
20.00
20.00
20.00
104
47
110
9
10
17
1620
710
2100
880
500
395
80
73
80
57
84
20.00
16
300
55
GNS-1
NSP-1
S-1
S-2
S-3
tr S-2
770
1380
tr S-3
1940
S-3
814
S-2
S-2
0.75
1.35
0.98
0.98
1.90
0.98
0.80
0.98
0.93
0.79
1.00
Capacity OK
Change pumps
Capacity Ok
Capacity Ok
Capacity Ok
737,779
70%
120,552
11,306,466
70%
3,518,975
70%
70%
70%
70%
70%
70%
3,518,975
3,958,847
283,172
854,091
988,097
1,392,090
5398
5398
70%
525,694
90
57
66
40
90
4840
4840
800
1300
2740
1940
80
90
41
69
40
80
1.04
0.94
97
2200
720
1290
1650
1470
1.00
Change pumps
5123
11,306,466
11,306,466
1,775,281
3,181,673
6,349,512
4,472,786
40
600
68
800
72
0.98
Change pumps
5123
1,876,726
20.00
20.00
40
65
20.00
20.00
Change pumps
Change pumps
5123
5123
1,053,613
172,159
16,146,616
5,025,402
1,280,282
209,196
19,620,316
6,106,541
5,025,402
5,653,577
404,394
1,219,715
1,411,089
1,988,026
5407
5407
5398
16,146,616
16,146,616
2,535,256
4,543,705
9,067,655
6,387,528
5407
19,620,316
19,620,316
3,080,678
5,521,214
11,018,424
7,761,707
6,106,541
6,869,858
491,393
1,482,119
1,714,663
2,415,720
5398
2,680,128
750,736
5407
3,256,716
912,245
Page 3
Appendices
Appendix F
Apele Moldovei Organizational Chart
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
GENERAL DIRECTOR
PROJECT
IMPLEMENTATION UNIT
DEPUTY DIRECTOR
ECONOMICALFINANCIAL AND
PLANNING
UNIT
WATER MANAGEMENT
DEPARTMENT
DUNAREA
-PRUT
BASIN
UNIT
NISTRU
BASIN
UNIT
LAND
IMPROVEMENT
UNIT
(HYDRO
WATER
USE
UNIT
INVESTMENTS,
CONSTRUCTIONS
AND NEW
TECHNOLOGIES
UNIT
SECRETARIAT,
PR & HUMAN
RESOURCES
UNIT
AIPRE BENDER
AIPRE BRICENI
AIPRE UNGHENI
AIPRE CAHUL
AIPRE VULCANESTI
AIPRE CHISINAU
AIPRE DROCHIA
ACVAPROIECT
AIPRE DUBASARI
AIPRE HINCESTI
COMPUTING CENTER
AIPRE ORHEI
LEGAL
CONSULTANT
COLLEGE
WATER SUPPLY
AND SANITATION
SYSTEMS
DEVELOPMENT
UNIT
WATER SUPPLY
AND SANITATION
SYSTEMS
EXPLOATATION
UNIT
STATE INTER-RAYONAL
ENTERPRISE ACVA-NORD
INTER-RAYONAL UNIT FOR THE
EXPLOITATION OF THE SOROCABALTIAQUEDUCT
STATE ENTERPRISE UNIT FOR
REPAIRING THE ARTESAIN-WELL
FROM CHISINAU
STATE ENTERPRISE PRODUCTION
AND TRAINING CENTER CHISINAU
Appendices
Appendix H
Soil Salinity Evaluation Report
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
By
Noemi Sabillon and Mohammed Shaban
Prepared for
Table of Contents
Section
Page
INTRODUCTION................................................................................................................................. 1
BACKGROUND ................................................................................................................................... 1
FIELD MEASUREMENTS OF SOIL SALINITY ............................................................................ 1
OTHER FIELD SIGNS OF SOIL SALINITY................................................................................... 2
WATER TABLE EFFECT ON IRRIGATED LAND ....................................................................... 2
RESULTS .............................................................................................................................................. 3
Soil Salinity ..................................................................................................................................... 3
Water Salinity ................................................................................................................................. 8
CONCLUSIONS AND RECOMMENDATIONS ............................................................................ 10
ANNEX 1:
ANNEX 2:
LIST OF TABLES
Table 1. Evaluated CIS areas and ECsw testing density..................................................................... 3
Table 3. ECsw Summary of measured Soil salinity status by CIS .................................................... 3
Table 4. Summary of equivalent ECe measured Soil salinity status by CIS ................................... 4
Table 5. Crop tolerance to salinity, ECe ............................................................................................. 8
Table 6. Field measured Electrical conductivity of different sources of water within evaluated
CIS. ......................................................................................................................................................... 9
LIST OF FIGURES
Figure 1. Surveyed CIS: Crpinenii de Sus, Cahul, Chircani-Zrneti, Talmaza, and Suvor. ..... 2
Figure 2. Spatial distribution of measured points: Crpinenii de Sus ............................................. 4
Figure 3. Spatial distribution of measured points: Cahul ................................................................. 5
Figure 4. Spatial distribution of measured points: Chircani-Zirnesti.............................................. 6
Figure 5. Spatial distribution of measured points: Talmaza............................................................. 1
Figure 6. Spatial distribution of measured points: Suvorov ............................................................. 1
Figure 8. Reeds in Chircani-Zirnesti ................................................................................................... 2
Figure 9. Algae and soil surface crusting ............................................................................................ 2
Figure 10. Drainage canal water levels ............................................................................................... 3
Figure 11. Waterlogged areas in the lowlands of Talmaza ............................................................... 3
Figure 12. Field salinity measurements: Chircani-Zrneti .............................................................. 4
Figure 14. Field salinity measurements: Crpinenii de Sus .............................................................. 6
Figure 15. Field salinity measurements: Masivul Talmaza ............................................................... 7
Contents - ii
Contents - iii
I.
Introduction
Crop production is often reduced because of a combination of factors such as climate,
crop and soil conditions. Within the soil, among other physical (and chemical)
characteristics, soil salinity could become a limiting factor for reaching potential crop
yields. Salinity content may affect the availability of water and nutrients to plants.
When soluble salts are in excess, and the crop is salt sensitive, its water intake
capacity is reduced as function of the salt content in the soil solution. Even if there is
water in the rootzone, the plant will not take water and will wilt. Salts content in the
soil can be originated in situ from decomposing (weathering1) of the soil parent
material or can be brought into the soil by fertilizers, salty water tables rise, or by the
irrigation water. All water contains salts, with time salts build-up within the soil
profile or at the soil surface if leaching and drainage is not provided. Crops ability to
withstand soil salinity content varies from crop to crop; however, most are susceptible
to increased amount of salts in the rootzone. Periodic monitoring of soil and
irrigation water is necessary in order to assess the salinity status of the soil, and to
implement a salinity management program when necessary. This type of assessment
even though it is required by law in Moldova, has not been done for at least 10 years
mostly because of the lack of funds. To determine the risk to sustained irrigated
agriculture on the potential rehabilitated CIS, MWH determined that it was necessary
to conduct a rapid assessment of the soil salinity and drainage systems in the
following CIS: Crpinenii de Sus, Cahul, Chircani-Zrneti, Talmaza, and Suvorov.
These systems were selected for the assessment for the reason outlined in the section
below.
The methodological approach and the required tasks and activities are described in the
Scope of Work (SoW), which is attached as Annex 1.
II.
Background
Previous studies2 have shown that there are signs of drainage and soil salinity hazards
in five of the sixteen CIS pre-selected to be considered for rehabilitation under the
Feasibility Study, Environmental and Social Impact Assessment - Moldova (CIS)
project. These signs consist of water logging (surface ponding of water), and white
blemish coloring on the soil surface of cropped lands. The five CIS under
consideration are Crpinenii de Sus, Cahul, Chircani-Zrneti, Talmaza, and Suvorov.
To assess the salinity status of those irrigation systems, MWH carried out a field
study of these areas using electrical conductivity meters that measure the resistance to
electrical current transmission directly in the field. These meters provide
reconnaissance level results of the potential salinity problems on the previously
identified CIS. Crop yields can be affected by the amount and type of salts (common
are the Chlorides of Calcium, Sodium, Magnesium, Potassium) in the soil or in the
soil water. High content of salts impact the nutrients (and water) intake by crops,
details are explained in sections below.
III.
the disintegration and decomposition of rocks and minerals by natural processes such as the action of frost or percolating ground
water
2
Irrigation Engineering, Hydrologic, and Agronomic Assessment Report Republic of Moldova, USU report February, 2009 Section
V.4.2 Soil Erosion and Salinization
Page - 1
The soil salinity was measured using the Field Scout EC 110 Meter by inserting the
probe in the soil at two different depths: at 30 cm and up to 60cm.
The Field Scout EC 110 Meter tester used for the reconnaissance of the soil salinity
measures the soil-water-salinity (ECsw). The standard parameter used to determine
salinity problems is the salinity measured on a saturated extract3 of the soil, ECe.
There is at least twice the volume of water in a saturated soil paste compared to the
amount of water at field conditions, therefore as a general rule of thumb, ECe is
considered to be half of the ECsw. In terms of water content, most of the areas
surveyed were close to field conditions4, meaning that the relation between ECe and
ECsw holds. The exception was in the lowlands of Talmaza where saturated or
waterlogged conditions were found.
The testing sites were chosen at random and geo-referenced with a GPS. The five
CIS are shown in Figure 1.
Figure 1. Surveyed CIS: Crpinenii de Sus, Cahul, Chircani-Zrneti, Talmaza,
and Suvorov.
Figures 2 through 6 show the spatial distribution of measured sites by CIS evaluated:
Carpineni de Sus, Cahul, Chircani-Zirnesti, Talmaza, and Suvorov.
The original proposed testing density was of 1 site per 100 ha; however, a change of
strategy was made in order to have the two teams working together in each of the
evaluated CIS, instead of taking measurements each team in a different CIS as per the
3
The saturated soil extract is the water extracted by pressure means from a volume of soil, which has been added distilled water
to saturation, the salinity content of this water extract is then measured as ECe.
4
Contrary to the saturated soil paste, soil at Field condition or at field capacity has much less water because it has been
naturally drained after saturation events like rainfalls, inundations or irrigations.
Page - 2
original proposed work plan. This change of the field implementation plan and the
active involvement of the ACVAProiect Scientists allowed an increase in sampling
density to about 1 site per 25ha, therefore providing a better coverage. In the cases of
Carpinenii de Sus, where the relief is more undulating, and for Talmaza where
waterlogged areas are commonly present, the density was purposely further increased
to a density of about 1 site per 21 ha in Carpinenii de Sus and 1 site per 18 ha in
Talmaza (Table 1).
Page - 3
Page - 4
Page - 5
Page - 6
Page - 1
Page - 1
IV.
V.
S/cm = microsimen per centimeter, is the mesure of electric conductivity, in this case is through the soil and the more salts in the
soil the higher the conductivity. More details at: www.horiba.com/process-environmental/features/water-
quality/the-story-of-conductivity/.../what-is-conductivity/
MWH Americas, Inc.
Page - 2
In Talmaza, the CIS with waterlogged areas, most of the land close to the T2/T3
pumping stations is saturated and/or with water ponded at the surface (Figure 10).
Some drainage canals have water at the level of the soil surface (Figure 11).
The elevation of the water table was measured by Mr. Michael Teske, the Drainage
Expert, in some observation wells that are still operating in the Circani-Zirnesti and
Cahul areas. Most of the points measured show that the water table is at a depth of
about 2 m below the soil surface. This could be an indication of a rising water table.
In irrigation systems, it is always recommended to keep water below from the root
environment, at a depth of at least 2 m below the soil surface, georeferenced data in
Annex 2.
VI.
Results
a. Soil Salinity
Table 3 shows the summary of the results of ECsw by CIS. The details of the field
measured soil salinity of the tested areas are included in annex 2. Table 4 shows
the same measurements of ECsw adjusted to the approximated equivalent of ECe,
as explained in sections III and table 2 in section IV above
Table 3. ECsw Summary of measured Soil salinity status by CIS
CIS
Chircani-Zrneti
Masivul Cahul
Crpinenii de Sus
Masivul Talmaza
Masivul Suvorov
Maximum salinity,
ECsw
(S/cm)
0-30 cm 30-60 cm
3,040
4,100
1,595
1,800
999
806
1,953
2,061
808
743
Minimum salinity,
ECsw
(S/cm)
0-30 cm 30-60 cm
338
349
344
502
313
316
394
342
787
690
Average salinity,
ECsw
(S/cm)
0-30 cm 30-60 cm
1,050
1,209
1,061
1,074
566
556
1,285
1,404
798
717
Page - 3
CIS
Chircani-Zrneti
Masivul Cahul
Crpinenii de Sus
Masivul Talmaza
Masivul Suvorov
Maximum salinity,
ECe (S/cm)
Minimum salinity,
ECe (S/cm)
0-30 cm 30-60 cm
1520
2050
797.5
900
499.5
403
976.5
1030.5
404
371.5
0-30 cm
169
172
156.5
197
393.5
30-60 cm
174.5
251
158
171
345
Average salinity,
ECe (S/cm)
0-30
cm
30-60 cm
525
604.5
530.5
537
283
278
642.5
702
399
358.5
4000
3500
ECsw , uS/cm
3000
2500
2000
1500
1000
500
5
CZ
_
CZ 9
_1
CZ 3
_1
CZ 7
_2
CZ 1
_2
CZ 5
_3
CZ 0
_3
CZ 4
_3
CZ 8
_4
CZ 2
_4
CZ 6
_5
CZ 0
_5
CZ 4
_5
CZ 8
_6
CZ 2
_6
CZ 6
_7
CZ 0
_7
CZ 4
_7
CZ 8
_8
CZ 2
_8
CZ 6
_9
CZ 0
_9
CZ 4
_
CZ 98
_1
CZ 02
_1
CZ 06
_1
CZ 10
_1
CZ 14
_1
CZ 18
_1
CZ 22
_1
CZ 26
_1
CZ 30
_1
CZ 34
_1
CZ 38
_1
42
CZ
_
CZ
_
Page - 4
Cahul. Figure 13 depicts the data for Cahul (also Prut River), the points in this case
are aligned around the value of 1,000 S/cm; the maximum and high values are also
in the low range of soil salinity risk for crops.
1800
1600
ECsw , uS/cm
1400
1200
1000
800
600
400
200
Ca
hu
Ca l_1
hu
Ca l_3
hu
Ca l_5
hu
Ca l_7
h
Ca ul_
hu 9
Ca l_1
hu 1
Ca l_1
hu 3
Ca l_1
hu 5
Ca l_1
hu 7
Ca l_1
hu 9
Ca l_2
hu 1
Ca l_2
hu 3
Ca l_2
hu 5
Ca l_2
hu 7
Ca l_3
hu 0
Ca l_3
hu 2
Ca l_3
hu 4
Ca l_3
hu 6
Ca l_3
hu 8
Ca l_4
hu 0
Ca l_4
hu 2
Ca l_4
hu 4
Ca l_4
hu 7
Ca l_4
hu 9
Ca l_5
hu 1
Ca l_5
hu 3
Ca l_5
hu 5
Ca l_5
hu 7
Ca l_5
hu 9
Ca l_6
hu 1
Ca l_6
hu 3
Ca l_6
hu 5
l_
67
Conclusion for Cahul. Similar results were encountered for Chircani. Measurements
of salinity currently indicate a low risk condition. There are indications that lack of
proper drainage could create a salinity problem over time in the future. As such it is
recommended that the drainage system be rehabilitated and be maintained as a
properly functioning system. It is also recommended that there be an annual
monitoring program established to monitor groundwater tables, electro-conductivity
and specific salts as necessary to conduct SAR calculations
Page - 5
Carpinenii De Sus. The values for Carpinenii De Sus in the Prut River are presented
in Figure 14, in this CIS all the values are in the very low ranking of salinity content
risk. Again a similar pattern is seen to the two previous systems. In fact, the
electroconductivity measurements were the lowest of the measured systems.
Note that there is not an engineered drainage system present in the Carpinenii CIS.
The concern about salinity here was attributed to drawing irrigation water from the
lake which has been known to be a bit saline. Note also, that the recommendation
rehabilitation schem for Carpinenii is to re-design so that the system pumps draw
directly from the river rather than from the Lake Minjir.
Figure 14. Field salinity measurements: Crpinenii de Sus
1200
0-30 cm
30-60 cm
1000
EC sw , uS/cm
800
600
400
200
C_
8
C_
11
C_
14
C_
17
C_
20
C_
23
C_
26
C_
29
C_
32
C_
35
C_
38
C_
41
C_
44
C_
47
C_
50
C_
53
C_
56
C_
59
C_
62
C_
65
C_
68
C_
71
C_
74
C_
77
C_
80
C_
83
C_
86
C_
5
C_
2
Talmaza. Figure 15 shows the values for Talmaza which on average are around the
value of 1,400 S/cm; the recorded maximum and high values are also in the low
salinity risk classification. The high values shown in the graphs could be attributed to
drainage problems of water stagnation and salt concentration due to evaporation of
that ponded water.
In Talmaza, on the Nistru River, a rising shallow water table has brought salts to the
soil surface, Figure 15. Still this area is not considered a saline soil (same condition
as in Chircani-Zirnesti); however, the raising of soil surface water evaporation each
MWH Americas, Inc.
Page - 6
summer will increase the salt content very rapidly. The reason why these soils do not
show degradation due to salt accumulation has been frequent flooding in the area and
the relative low load of salts in the irrigation water6 (in addition to minimal irrigation
taking place). In contradiction, those floods, the elevation of the fields with respect to
the Nistru average water elevation, and the current inadequate drainage conditions,
are the causes for the high water table.
Figure 15. Field salinity measurements: Masivul Talmaza
2500
0-30 cm
30-60 cm
EC sw , uS/cm
2000
1500
1000
500
T_
1
T_
4
T_
7
T_
10
T_
13
T_
16
T_
19
T_
22
T_
25
T_
28
T_
31
T_
34
T_
37
T_
40
T_
43
T_
48
T_
51
T_
54
T_
57
T_
60
T_
63
T_
66
T_
69
T_
72
T_
75
T_
79
T_
82
T_
85
T_
88
T_
91
T_
94
Conclusion for Talmaza. Similar results were encountered as the other CIS except
somewhat higher in terms of electro-conductivity and more spatial variability.
Measurements of electroconductivity currently still indicate a low risk for salinity
condition. There are indications however that lack of proper drainage could create a
salinity problem over time in the future. As such it is recommended that the drainage
system be rehabilitated and be maintained as a properly functioning system. It is also
recommended that there be an annual monitoring program established to monitor
groundwater tables, electro-conductivity and specific salts as necessary to conduct
SAR calculations
Chemistry of Salinity
The ions generally associated with salinity are Ca, Mg, K, Na, NO3, SO4, Cl-, HCO3,
and CO3. To determine the salinity hazard, the ECe of the soil is compared with the
tolerance or sensitivity of the crop to be grown. In general, crop yields are impacted
as follows::
6
DRAFT Moldova - CIS Feasibility Study & Environmental and Social Assessment. Water Availability Assessment Report by Phillip E.
Brown
Page - 7
The ECe is less than 2 dS/m (or 2,000 S/cm, very low), most crop yields are
not affected; The ECe is between 2 and 4 dS/m or between 2,000 S/cm and
4,000 S/cm (low), some crop yields are affected;
The ECe is between 4 and 8 dS/m or between 4,000 S/cm and 8,000 S/cm,
(moderate), many crop yields are affected;
The ECe is between 8 and 16 dS/m or between 8,000 S/cm and 16,000 S/cm,
(high), only tolerant crops are not affected;
The ECe is greater than 16 dS/m or 16,000 S/cm (very high), even very
tolerant crop yields are affected.
The majority of the conductivity points measured in the field indicate a very low
salinity risk for crops. However, this condition would change if excess water
containing dissolved salt is allowed to evaporate from the soil surface. Water must
naturally percolate through the soil profile and should be removed from the cropped
fields by drainage. When water evaporates the salts are left behind and the salinity
content of the soil increases.
For a soil to be classified as saline, the measured ECe should be greater than 4 dS/m
or 4,000 S/cm. Where the soil moisture is close to field capacity or field conditions
(see footnote 4, page 2), the measured salinity will correspond approximately to an
ECsw of 8 dS/m or 8,000 S/cm.
Crops being grown in the potential affected areas are included in Table 5. With the
exception of wheat and sunflower that are moderately tolerant to salts, the other crops
are salt sensitive. Information on yield reduction is not documented, but currently
farmers are being able to grow the crops, which is a good indication that the soils are
still productive.
Table 5. Crop tolerance to salinity, ECe
Crop
ECe (dS/m) for a Yield potential of
100 %
90%
75%
Corn (forage) (Zea mays)
1.8
3.2
5.2
Alfalfa (Medicago sativa)
2.0
3.4
5.4
Wheat (Triticum aestivum)
6.0
7.4
9.5
Grape (Vitus sp.)
1.5
2.5
Bean (Phaseolus vulgaris)
1.0
1.5
2.3
Potato (Solanum tuberosum)
1.7
2.5
3.8
Sunflower (Helianthus annuus) Moderately Tolerant
Source: Crop Tolerance and Yield Potential of Selected Crops as influenced by irrigation water salinity
(ECw) or soil salinity (ECe). FAO Irrigation and Drainage Paper 29 Rev.1 Water quality for
Agriculture. 1989.
b. Water Salinity
Twenty one water samples were collected in the field and the salt content was
measured using a different probe on the same meter as used for the soil salinity
measurements (Table 5). In Carpinenii only the water from Lake Minjir was
MWH Americas, Inc.
Page - 8
measured. In general surface river waters have the lowest salt content and have no
restriction for their use, but salt is still added to the soil when they are used for
irrigation and insufficient drainage is provided; i.e during the growing season,
irrigating 1 ha of land with 10000 m3 of water with a ECw of 406 S/cm,
corresponding to a salt concentration of 0.26 g/l (0.26 kg/m3), will bring 2600 kg of
salt per ha per year. According to the Guidelines for Water Quality for Agriculture
(FAO, 1989), in order for irrigation water not to affect the availability of water to
crops, the electric conductivity (ECw) should be less than 3.0 dS/m (3000 S/cm), or
the Total Dissolved Solids (TDS) content less than 2000 mg/l. Water with ECw
greater than 3000 S/cm should not be used for irrigation unless appropriate irrigation
and drainage management programs are implemented.
Waypoint
ECw,
S/cm
CIS/ ID
GPS coordinates
SPP-3
Cahul
406
River
SPP-3
Cahul
1100
Drainage pond
60
Cahul_SPP-3
1450
Drainage canal
68
Cahul_SPP-3
1451
Drainage canal
80
Cahul_SPP-1
864
Drainage canal
85
Cahul_SPP-2
2390
Drainage canal
86
Cahul_SPP-2
1923
Drainage canal
94
Cahul_SPP-2
2300
Drainage canal
98
Cahul_SPP-2
1228
Drainage canal
101
Chircani-Zirnesti_S-5
4370
Drainage canal
Chircani-Zirnesti
1674
Drainage pond
102
Chircani-Zirnesti_S5
4360
Drainage canal
103
Chircani-Zirnesti_S5
4420
Drainage canal
104
Chircani-Zirnesti_S5
2770
Drainage canal
142
Chircani_S-1
1972
Drainage canal
163
Chircani-Zirnesti
1620
Drainage canal
Nistru
Talmaza
562
River
D2
Talmaza
688
Drainage pond
230
Talmaza_T-2
3970
238
Talmaza_T-2
883
Drainage canal
Surface
waterlogged
10
Carpinenii_NSP-7
1161
Lake Minjir
SPD-4
Source
The highest salt concentrations were recorded in water in the drainage canals within
the Chircani-Zirnesti CIS. Most of the drainage water is stagnant, some even with
algae, which is a clear indication of slow or no movement at all. If this water is not
removed, the salt concentration will keep increasing as water evaporates and more
water is added. Unless the drainage system is rehabilitated the water table will keep
on rising bringing the salts to the root zone.
MWH Americas, Inc.
Page - 9
VII.
Page - 10
drainage systems and monitoring and maintaining thes drainage systems. Those
costs all described in the companion report Drainage Evaluation
Recommendations
Set up monitoring programs for:
soil parameters (including Na, k, mg, and pH, and ECe)
drainage water salinity and water table fluctuation
The cost for these recommendations is included in the companion report Drainage
Evaluation
Page - 11
Annex 1.
16-38
2.44
2.90
1.52
2.29
1.68
2.13
2.39
2.29
2.49
1.68
0.61
3.53
Clogged with soil 1 m from top of
well casing pipe
Annex 1- 1
Annex 2:
CIS
C_2
537
565
C_3
570
481
C_4
519
422
C_5
479
431
C_6
466
425
C_7
450
463
C_8
463
480
C_9
326
457
C_10
408
452
C_11
486
499
C_12
313
739
C_13
999
806
C_14
545
497
C_15
591
494
C_16
500
516
Uncultivated, plowed
C_17
557
586
Grape
C_18
537
544
C_19
493
541
C_20
408
515
C_21
477
512
C_22
606
535
Uncultivated, plowed
C_23
539
430
C_24
573
543
C_25
528
554
C_26
614
606
C_27
580
614
C_28
591
550
Uncultivated, plowed
C_29
531
340
Uncultivated, plowed
C_30
546
606
Unplowed, trees
C_31
524
486
Uncultivated, plowed
C_32
528
528
C_33
460
464
Uncultivated, plowed
C_34
606
674
Unplowed, trees
C_35
550
471
Uncultivated, plowed
C_36
456
516
C_37
576
696
C_38
603
561
Grass
GPS Coordinates
30-60
0-30 cm cm
ID
Observation
Annex 2- 1
546
629
Unplowed, trees
C_40
535
550
Unplowed, weeds
C_41
490
520
Unplowed, weeds
C_42
486
576
Uncultivated, plowed
C_43
513
475
Uncultivated, plowed
C_44
423
554
Uncultivated, plowed
C_45
629
539
Uncultivated, plowed
C_46
322
341
C_47
355
316
C_48
623
484
C_49
540
549
C_50
682
620
C_51
469
560
C_52
675
620
Uncultivated, plowed
C_53
683
804
Uncultivated, plowed
C_54
601
531
C_55
647
575
Uncultivated, plowed
C_56
636
562
Uncultivated, plowed
C_57
607
605
Uncultivated, plowed
C_58
593
577
Uncultivated, plowed
C_59
618
600
C_60
559
573
Lavender
C_61
417
504
Lavender
C_62
544
538
C_63
549
536
Lavender
C_64
541
500
Lavender
C_65
504
529
C_66
476
560
C_67
534
513
C_68
565
546
C_69
798
715
C_70
798
681
Unplowed, weeds
C_71
779
745
Uncultivated, plowed
C_72
685
723
C_73
715
629
C_74
524
580
C_75
606
614
C_76
501
629
Uncultivated, plowed
Wheat, initial growth stage, near level
slope
Wheat, initial growth stage, near level
slope
Wheat, initial growth stage, near level
slope
Wheat, initial growth stage, near level
slope
Annex 2- 2
Annex 2- 3
ID
CIS
GPS Coordinates
Cl_1
Cahul_SPP-3
1352
Cl _2
Cahul_SPP-3
992
Cl _3
Cahul_SPP-3
810
Observation
Wheat, initial growth stage, near level
1009 slope
Wheat, initial growth stage, near level
755 slope, soil sampled
Wheat, initial growth stage, near level
1320 slope, DW sampled
Cl _4
Cahul_SPP-3
1080
1049
Cl_5
Cahul_SPP-3
698
502
Cl_6
Cahul_SPP-3
1396
1304
Cl_7
Cahul_SPP-3
1124
1288
Cl_8
Cahul_SPP-3
1097
1751
Cl_9
Cahul_SPP-3
1250
1063
Cl_10
Cahul_SPP-3
1049
1112
Cl_11
Cahul_SPP-3
1086
1007
Cl_12
Cahul_SPP-3
989
914
Cl_13
Cahul_SPP-3
1056
1090
Cl_14
Cahul_SPP-3
1022
1090
Cl_15
Cahul_SPP-3
1056
1094
Cl_16
Cahul_SPP-3
1022
805
Unplowed, weeds
Cl_17
Cahul_SPP-3
1049
1034
Unplowed, weeds
Cl_18
Cahul_SPP-3
974
977
Unplowed, weeds
Cl_19
Cahul_SPP-3
842
1142
Cl_20
Cahul_SPP-3
771
606
Cl_21
Cahul_SPP-3
989
1064
Cl_22
Cahul_SPP-3
1034
1086
Uncultivated, plowed
Cl_23
Cahul_SPP-3
1052
1067
Uncultivated, plowed
Cl_24
Cahul_SPP-3
1026
1056
Uncultivated, plowed
Cl_25
Cahul_SPP-3
996
794
Cl_26
Cahul_SPP-3
1004
1041
Cl_27
Cahul_SPP-3
921
1049
Cl_29
Cahul_SPP-3
1022
1052
Cl_30
Cahul_SPP-3
1022
580
Cl_31
Cahul_SPP-3
1015
857
Cl_32
Cahul_SPP-1
682
866
Alfalfa, re-growth
Cl_33
Cahul_SPP-1
805
1205
Cl_34
Cahul_SPP-1
658
825
Cl_35
Cahul_SPP-1
951
1022
Cl_36
Cahul_SPP-1
1191
994
Uncultivated, plowed
Cl_37
Cahul_SPP-1
1014
1213
Uncultivated, plowed
Cl_38
Cahul_SPP-1
1480
1800
Uncultivated, plowed
Cl_39
Cahul_SPP-1
1375
1250
Alfalfa, re-growth
Cl_40
Cahul_SPP-1
1424
1350
Unplowed, weeds
Annex 2- 4
Cahul_SPP-1
1460
1395
Cl_42
Cahul_SPP-1
1091
1577
Unplowed, weeds
Wheat, initial growth stage, corn last
crop
Cl_43
Cahul_SPP-1
1034
1086
Cl_44
Cahul_SPP-1
1090
1086
Cl_45
Cahul_SPP-1
947
1124
Cl_47
Cahul_SPP-1
1052
929
Unplowed, weeds
Cl_48
Cahul_SPP-1
955
794
Cl_49
Cahul_SPP-1
1045
1094
Cl_50
Cahul_SPP-1
1026
1034
Cl_51
Cahul_SPP-1
1015
1064
Cl_52
Cahul_SPP-2
706
527
Cl_53
Cahul_SPP-2
1419
1274
Alfalfa, re-growth
Cl_54
Cahul_SPP-2
1284
1129
Uncultivated, plowed
Cl_55
Cahul_SPP-2
1165
1361
Cl_56
Cahul_SPP-2
1595
1569
Cl_57
Cahul_SPP-2
885
1314
Uncultivated, plowed
Cl_58
Cahul_SPP-2
1368
1340
Cl_59
Cahul_SPP-2
1361
1559
Cl_60
Cahul_SPP-2
1041
1052
Cl_61
Cahul_SPP-2
1180
962
Unplowed, weeds
Cl_62
Cahul_SPP-2
1112
925
Uncultivated, plowed
Cl_63
Cahul_SPP-2
1082
1045
Cl_64
Cahul_SPP-2
344
1064
Cl_65
Cahul_SPP-2
1154
685
Uncultivated, plowed
Cl_66
Cahul_SPP-2
1120
917
Cl_67
Cahul_SPP-2
1030
854
ID
CIS
ChircaniZirnesti_S-5
ChircaniZirnesti_S-5
ChircaniZirnesti_S-5
ChircaniZirnesti_S-5
ChircaniZirnesti_S-5
ChircaniZirnesti_S-5
ChircaniZirnesti_S-5
ChircaniZirnesti_S-5
GPS Coordinates
CZ_1
CZ_2
CZ_3
CZ_4
CZ_5
CZ_6
CZ_7
CZ_8
30-60
0-30 cm cm
3040
Observation
Salt surface accumulation,
3610 waterlogged
642
4100
Grass
1294
2670
Alfalfa, re-growth
1396
1086
1101
1569
559
606
901
1157
1317
1931
Annex 2- 6
Annex 2- 7
1079
1011
Unplowed, weeds
CZ_85
741
1094
Unplowed, weeds
CZ_86
1127
1004
Unplowed, weeds
CZ_87
1082
1127
Unplowed, weeds
CZ_88
1150
1075
CZ_89
970
1139
CZ_90
816
1139
CZ_91
1131
831
CZ_92
1154
1124
CZ_93
1041
970
CZ_94
1131
1112
CZ_95
1090
1131
Unplowed, weeds
CZ_96
404
636
Unplowed, weeds
CZ_97
1000
966
Unplowed, weeds
CZ_98
1052
985
Alfalfa, re-growth
Annex 2- 8
1041
1101
Alfalfa, re-growth
CZ_100
1034
1026
Unplowed, weeds
CZ_101
1097
1097
Unplowed, weeds
CZ_102
1071
1097
CZ_103
1041
1067
Unplowed, weeds
CZ_104
1022
1082
CZ_105
921
738
Uncultivated, plowed
CZ_106
1045
1116
CZ_107
857
891
CZ_108
1067
550
CZ_109
981
1086
CZ_110
974
1082
CZ_111
1041
899
CZ_112
1030
809
Unplowed, weeds
CZ_113
1007
1030
CZ_114
902
1101
Unplowed, weeds
CZ_115
902
1004
Uncultivated, plowed
CZ_116
981
1067
Uncultivated, plowed
CZ_117
1056
1056
Unplowed, weeds
CZ_118
947
1082
Unplowed, weeds
CZ_119
850
1094
Unplowed, weeds
CZ_120
1019
1064
Unplowed, weeds
CZ_121
1015
1037
Alfalfa, re-growth
CZ_122
906
1004
CZ_123
842
1079
CZ_124
805
1007
CZ_125
977
1041
CZ_126
891
1026
Unplowed, weeds
CZ_127
977
1071
Unplowed, weeds
CZ_128
1082
1026
Uncultivated, plowed
CZ_129
1034
1060
Uncultivated, plowed
CZ_130
1000
989
CZ_131
Chircani-Zirnesti
ChircaniZirnesti_S-6
ChircaniZirnesti_S-6
ChircaniZirnesti_S-6
ChircaniZirnesti_S-6
ChircaniZirnesti_S-6
ChircaniZirnesti_S-6
1011
1090
Unplowed, weeds
1335
1393
Uncultivated, plowed
1325
1570
824
1661
Unplowed, weeds
748
2720
1251
1415
Alfalfa, re-growth
1286
1615
Alfalfa, re-growth
CZ_132
CZ_133
CZ_134
CZ_135
CZ_136
CZ_137
Annex 2- 9
Annex 2- 10
ID
CIS
GPS Coordinates
T_1
Talmaza_NS-2
944
1045
Uncultivated, plowed
T_2
Talmaza_NS-2
1060
1178
Uncultivated, plowed
T_3
Talmaza_NS-2
826
681
T_4
Talmaza_NS-2
993
1057
T_5
Talmaza_NS-2
903
1075
Uncultivated, plowed
T_6
Talmaza_NS-2
1022
1359
T_7
Talmaza_NS-2
426
993
T_8
Talmaza_NS-2
596
667
T_9
Talmaza_NS-2
746
915
Uncultivated, plowed
Wheat, initial growth stage,
sunflower last crop
T_10
Talmaza_NS-2
958
1231
Uncultivated, plowed
T_11
Talmaza_NS-2
1149
1360
Uncultivated, plowed
T_12
Talmaza_NS-2
1146
1113
Uncultivated, plowed
T_13
Talmaza_NS-2
1280
1188
T_14
Talmaza_NS-2
1348
1316
T_15
Talmaza_NS-2
1212
1159
T_16
Talmaza_NS-2
667
884
Potato
T_17
Talmaza_NS-2
1362
1229
T_18
Talmaza_NS-2
1506
1699
Unplowed, weeds
T_19
Talmaza_NS-2
1711
1965
T_20
Talmaza_NS-2
1675
2061
T_21
Talmaza_NS-2
1892
1904
Uncultivated, plowed
T_22
Talmaza_NS-2
1555
1880
Uncultivated, plowed
T_23
Talmaza_NS-2
1760
1904
Uncultivated, plowed
T_24
Talmaza_NS-2
1687
1941
Uncultivated, plowed
T_25
Talmaza_NS-2
1326
1627
T_26
Talmaza_NS-2
1543
1121
T_27
Talmaza_NS-2
1748
1904
T_28
Talmaza_NS-2
952
2025
T_29
Talmaza_NS-2
1736
1880
T_30
Talmaza_NS-2
1675
1844
T_31
Talmaza_T-2
600
511
T_32
Talmaza_T-2
566
918
Unplowed, grass
Uncultivated, sunflower previous
crop
T_33
Talmaza_T-2
1001
1236
T_34
Talmaza_T-2
1029
1364
T_35
Talmaza_T-2
394
342
T_36
Talmaza_T-2
1259
1137
T_37
Talmaza_T-2
1287
1011
T_38
Talmaza_T-2
1308
1461
Observation
Talmaza_T-2
1276
1281
T_40
Talmaza_T-2
912
1136
T_41
Talmaza_T-2
1213
1239
T_42
Talmaza_T-2
1169
1018
T_43
Talmaza_T-2
1235
955
T_44
Talmaza_T-2
1502
1434
T_47
Talmaza_T-2
1540
1558
T_48
Talmaza_T-2
1421
1688
T_49
Talmaza_T-2
1420
1465
T_50
Talmaza_T-2
1466
1683
T_51
Talmaza_T-2
1490
1368
T_52
Talmaza_T-2
1616
1939
T_53
Talmaza_T-2
1480
1515
T_54
Talmaza_T-2
1506
1760
T_55
Talmaza_T-2
1285
1306
T_56
Talmaza_T-2
1348
1320
T_57
Talmaza_T-2
801
706
T_58
Talmaza_T-2
1022
916
T_59
Talmaza_T-2
1349
1513
T_60
Talmaza_T-2
1596
1476
T_61
Talmaza_T-2
1491
1292
T_62
Talmaza_T-2
1420
1540
T_63
Talmaza_T-2
1485
1402
T_64
Talmaza_T-2
1495
1525
T_65
Talmaza_T-2
1411
1425
T_66
Talmaza_T-2
760
1113
T_67
Talmaza_T-2
1345
1460
T_68
Talmaza_T-2
1024
1350
T_69
Talmaza_T-2
1362
1470
T_70
Talmaza_T-2
1603
1760
T_71
Talmaza_T-2
1446
1494
T_72
Talmaza_T-2
1458
1531
T_73
Talmaza_T-2
1181
1591
T_74
Talmaza_T-2
1482
1832
T_75
Talmaza_T-2
1603
1808
Annex 2- 12
Talmaza_T-2
1603
1760
T_80
Talmaza_T-2
613
626
Unplowed, weeds
T_81
Talmaza_T-2
1289
1748
Unplowed, weeds
T_82
Talmaza_T-2
1675
1651
T_83
Talmaza_T-2
1760
1989
T_84
Talmaza_T-2
988
759
Trees
T_85
Talmaza_T-2
1627
1772
Uncultivated, plowed
T_86
Talmaza_T-2
1953
1362
Unplowed, weeds
T_87
Talmaza_T-2
1699
1977
Unplowed, weeds
T_88
Talmaza_T-2
1470
1844
Unplowed, weeds
T_89
Talmaza_T-2
1784
1989
Unplowed, weeds
T_90
Talmaza_T-2
1253
1302
Uncultivated, plowed
T_91
Talmaza_T-2
1808
1929
T_92
Talmaza_T-2
1736
1868
Uncultivated, plowed
Uncultivated, sunflower previous
crop
T_93
Talmaza_T-2
916
952
Unplowed, weeds
T_94
Talmaza_T-2
711
674
Unplowed, weeds
T_95
Talmaza_T-2
700
1338
S_1
Zuvorov
787
743
S_2
Zuvorov
808
690
Unplowed, weeds
Wheat, initial growth stage, corn last
crop
Wheat, initial growth stage, corn last
crop
Annex 2- 13
Appendices
Appendix I
Drainage Systems Evaluation Report
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
DRAINAGE EVALUATION:
CAHUL, CHIRCANI-ZRNETI,
SUVOROV, and TALMAZA
APPENDIX I
Introduction
Majority of the CISs under the MCC consideration are relatively well drained and
do not require or include engineered drainage systems. There are four CIS,
however, that do include engineered drainage systems. These CIS include:
Cahul,
Chircani-Zrneti,
Suvorov,
Talmaza
Periodic assessments of salinity (and by inference the drainage status) are
required by law in Moldova. The maintenance of these drainage systems have
been neglected over the last 10 to 15 years due to lack of maintenance funds for
cleaning and maintaining these systems. Due to inadequate drainage, there were
reports of salinity concerns in the soil. During MWH team field visits, anecdotal
observations were made of ponded water, water logged soils and other
indications of poor drainage. Adequate drainage (whether natural or engineered)
is essential for long-term sustainability of robust crop production to control
salinity, water logging of soils and standing water.
To determine the current status of the salinity and drainage to sustain irrigated
agriculture on the potential rehabilitated CIS, MWH and MCC determined it
necessary to conduct a rapid assessment of the soil salinity and drainage
systems in the following four CIS: Chircani-Zrneti, Cahul, Talmaza, and
Suvorov.
The cost of rehabilitating to correct salinity and drainage deficiencies can be
substantial. It was therefore important to obtain a gauge of the magnitude of the
cost involved in correcting salinity problems (if found) and drainage deficiencies
(if found) in these four CIS.
Relationship with Salinity Assessment Report
This report is a companion piece to the Soil Salinity Assessment Report
(presented as Appendix H). The activities summarized in the soil salinity report
involved an extensive sampling of soils and water to gather current data on
electro-conductivity (an indicator of salinity). Note that the major conclusion of
that activity are as follows:
1. No Current Salinity Problems. Current soil-water salinity as measured
indicates that the salinity risk is quite low.
2. Poor Drainage Could Cause Salinity Problems in Future. However,
drainage water canals were observed with elevated levels of electroconductivity. While there is not a need to remediate for current salinity
2|P age
APPENDIX I
problems, poor drainage, over time, could result in salinity problems as
well as potentially sodicity problems. Such problems could jeopardize the
investments in the CIS rehabilitation over the long run.
In short, the engineered drainage systems must be rehabilitated to good working
condition and maintained in good condition over time in order to ensure the
viability of the investment in the CIS rehabilitation.
Assessment of Drainage Systems - Methodology
The following section presents the results of the rapid assessment of the four
systems that contain engineered drainage systems. The time and budget
considerations limited the physical inspection of the entire drainage system within
each CIS. Instead, the MWH team visited and carefully evaluated typical sections
of the drainage system at each CIS. The selection of the typical sections was
developed in conjunction with AcvaProjects (MWH team member) experience,
discussions with Apele Moldovei staff on site, and examination of network maps.
Based on these inputs, typical sampling was extrapolated for system wide
estimates for remediation measures and costs. In addition to the one time capital
costs needed for rehabilitation, it is recommended that an allocation of
maintenance funding be made to perform proper on-going maintenance of these
systems. An estimate has been made of this on-going maintenance costs on a
system by system basis.
This report attempts to make an assessment on a system by system basis to
allow decision makers to pick-and choose individual CIS systems that may be
selected for further development.
It should be noted that the field observation part of this work was conducted in
early April in order to meet the MCC deadline for end of May decision making. As
such, irrigation was not yet in full operation during field visits. For this reason,
additional information should be gathered including (1) checking whether the
open drains have free outflow (brief submergence of the outlets is normally
acceptable), (2) checking if drains are discharging during and shortly after rain or
irrigation, (3) monitoring water levels in the collector and secondary canals, (4)
inspecting the field surfaces for wet spots, which would be signs of potential
water-logging, a few days after rain or irrigation, (5) checking the depth of the
water table in the monitoring wells.
Components of Drainage Rehabilitation General Terms
The rehabilitation of drainage systems can be an extensive process depending
on how far one wants to proceed with the rehabilitation. The components for
possible rehabilitation in the CIS systems examined were as follows:
Earthen Surface Canals. The surface canals are the backbone of the drainage
3|P age
APPENDIX I
system in the CIS observed. These canals were designed to convey away
excess drainage water and run-off to keep relatively poorly drained soils from
becoming water logged and susceptible to salinity. The problems typically
encountered without proper routine maintenance is the accumulation of sediment
in the canals as well as the deterioration of the side slopes of the canals. Both of
these developments significantly impact the hydraulic capacity of the systems.
When the capacity is diminished, the system ceases to function properly.
Sub-Surface Drainage Pipes. In some irrigation systems, sub-surface piping is
designed in the presence of heavy soils to convey drainage water to the canals.
Despite an extensive search for records at various locations, no records or maps
could be found of sub-surface pipes in the selected CIS. During the field visits, no
evidence of subsurface pipes was observed. Also, no evidence of clean out
manholes was observed.
Monitoring Wells. There exist some monitoring wells in the CIS. These are
useful for routine monitoring of the groundwater levels in the fields needed to
track the potential for water logging and adequacy of the drainage system. Based
on field observations, some of these wells are not non-functional and need to be
restored.
Bridges. There are many bridges in the area that provide access across the
canals. Field observation indicate that pre-cast concrete decks, beams and
columns are all in various states of deterioration with spauling edges observed at
many locations. Reinforcement steel is exposed on many structural members.
The supporting columns are plumb and appear to be well founded. No differential
settlement was noted. The bridge decks are generally level side to side and end
to end. Sink holes have developed at the majority of the bridges at points where
the adjacent land meets the bridge deck. Since more frequent and heavy
equipment travel is envisioned in the future, associated with high value
agriculture (HVA), structural analysis is required to assure integrity of every
bridge structure. Cleaning of exposed reinforcing steel and patching could add
years of service to these members, but assuring structural integrity must be the
first priority. Repairs of bridges were identified and a rough estimate of a unit
cost for minor rehabilitation of the bridges was established and extrapolated over
the number of bridges.
Dikes. In selected areas adjacent to rivers, dikes have been constructed to
protect from river flooding. The dikes in question were built after the Costesti
Stanca dam was built on the Prut River and the Dubasari Dam along the Nistru
Dam. The failure of the dam might cause overtopping of downstream dikes. The
need to examine the adequacy of the dikes was discussed with Apele Moldovei.
Since the area at risk in case of dam failure is much larger than the area of the
present project, the proposed study should be a separate project on dikes and
dams safety in Moldova.
4|P age
APPENDIX I
Pumping Stations. Drainage water is evacuated via pumping stations.
Rehabilitating the pump stations and operating the drainage pump stations is
likely a major cost of the rehabilitation of the drainage systems.
Drainage Assessment in the Chircani-Zrneti CIS
Earthen Surface Canals. The earthen drainage canals total 69.24 km in this
CIS. There are 13.84 km of collector canals and 55.42 km of secondary canals.
The drainage system covers about 100 % of the irrigated area. The canals have
an average sediment accumulation of approximately 0.5m to 0.8m in the
collectors canals (b=3,h=4) and a lesser amount, up to 0.5m, in the secondary
canals (b=2,h=3) for those measured. Tall reed growth is pervasive in all canals
and is also growing on the banks of the canals in some areas. Water was
standing about two meters down from the top of the canal banks when inspected
on April 6, 2009. The original cross-section (side slopes and embankment) of the
canals, that is visible, is uniform although some minor sloughing is seen rarely.
Recommended Action
Remedial Cleaning. Clean the sediment and reed growth in the canals
immediately. The estimate of the current volume of sediment in the
canals is approximately 1.9 cubic meters/meter for the collectors and
about 1.4 cubic meters/meter for the secondary canals. Minimal
reshaping of the canal embankments needs to be done at this time.
Annual Inspection / Periodic Cleaning. The drainage system should be
inspected once a year and provisions for sediment cleaning and bank
maintenance should be made on an approximate five year cycle. Weed
control should be done on a more frequent basis. A budget should be
established for this purpose.
Sub-Surface Drainage Pipes. There are no maps or records of sub-surface
drainage piping. During field inspection, there was no visual evidence of such
piping. Interviews with knowledgeable people also provided no indication of the
existence of such a system.
Recommended Action
Monitoring the Need. It is presumed that there is no existence of a sub-surface
piping system. Monitoring wells should be observed on an annual basis to
determine whether the surface canal drainage system is sufficient to serve the
area without the necessity for subsurface pipe system.
Monitoring Wells. There were 12 monitoring wells that were observed in this
CIS. The majority are operable. The problem is that the number of wells and
spacing are not sufficient. If true observations are to be made in a systematic
fashion, then additional monitoring wells need to be installed.
5|P age
APPENDIX I
Recommended Action
Restore Monitoring Wells. Construct approximately 55 new wells. These should
be read on a routine basis to monitor the effectiveness of the drainage system in
the CIS.
Bridges. There are 18 bridges in this CIS that provide access across the canals.
The bridge decks are approximately 0.2m thick and 7.3m wide. These bridges
are all in various states of deterioration with spaulling edges present at many
locations. Reinforcement steel is exposed on many structural members.
However, the bridges seem to be in reliable structural condition. There is a
problem with the erosion of the approaches up to the bridges from the farm
roads. There exist so-called sink holes at the entrances creating difficulty in
mounting the bridge. These need correcting and will only get worse with time.
Recommended Action
Patching. Cleaning of exposed reinforcing steel and patching could add years of
service to these members. For purposes of the budget estimate, MWH has
established a unit cost for rehabilitation action on a typical bridge and multiplied it
by the number of bridges. During final design it is recommended that each bridge
be looked at on a unit by unit basis.
Correct the Approaches. The approaches to the bridges have eroded away over
time. It would be useful to restore these approaches to allow better entry onto the
bridges and less wear and tear to the both the bridge and the vehicles. This is a
minor cost that will afford significant benefits
Dikes. There are some dikes along the Prut River associated with this CIS.
However, there is no recent flooding reported in the area. The dikes in question
were built after the CostestiStanca dam was built on the Prut River. The failure
of the dam might cause overtopping of downstream dikes. Therefore, a study of
dikes adequacy is required in case of dam failure.
Recommended Action
The need to examine the adequacy of the dikes was discussed with Apele
Moldovei. Since the area at risk in case of dam failure is much larger than the
area of the present project, the proposed study should be a separate project on
dikes and dams safety in Moldova.
Drainage Assessment in the Masivul Cahul
Earthen Surface Canals. The earthen drainage canals total 96.8 km in this CIS.
There are 38.5 km of collector canals and 58.2 km of secondary canals. The
drainage system covers about 35 % of the irrigated area, primarily in the lower
level area in the area adjacent to the river. The canals have an average sediment
accumulation of approximately 0.5m to 0.8m in the collectors canals (b=3,h=4)
6|P age
APPENDIX I
and a lesser amount, up to 0.5m, in the secondary canals (b=2,h=3) for those
measured. Tall reed growth is pervasive in all canals and are also growing on
the banks of the canals in some areas. Water was standing about two meters
down from the top of the canal banks when inspected on April 7, 2009. The
original cross-section (side slopes and embankment) of the canals, that is visible,
is uniform although some minor sloughing is seen rarely.
Recommended Action
Remedial Cleaning. Clean the sediment and reed growth in the canals
immediately. The estimate of the current volume of sediment in the canals is
approximately 1.9 cubic meters/meter for the collectors and about 1.4 cubic
meters/meter for the secondary canals. Minimal reshaping of the canal
embankments needs to be done at this time.
Annual Inspection / Periodic Cleaning. The drainage system should be inspected
once a year and provisions for sediment cleaning and bank maintenance should
be made on an approximate five year cycle. Weed control should be done on a
more frequent basis. A budget should be established for this purpose.
Sub-Surface Drainage Pipes. There are no maps or records of sub-surface
drainage piping. During field inspection, there was no visual evidence of such
piping. Interviews with knowledgeable people also provided no indication of the
existence of such a system.
Recommended Action
Monitoring the Need. It is presumed that there is no existence of a sub-surface
piping system. Monitoring wells should be observed on an annual basis to
determine whether the surface canal drainage system is sufficient to serve the
area without the necessity for subsurface pipe system.
Monitoring Wells. There were 12 monitoring wells that were observed in this
CIS. The majority are operable. The problem is that the number of wells and
spacing are not sufficient. If true observations are to be made in a systematic
fashion, then additional monitoring wells need to be installed. .
Recommended Action
Restore Monitoring Wells. Construct approximately 31 new wells. These should
be read on a routine basis to monitor the effectiveness of the drainage system in
the CIS.
Bridges. There are 28 bridges in this CIS that provide access across the canals.
The bridge decks are approximately 0.2m thick and 7.3m wide. These bridges
are all in various states of deterioration with spaulling edges present at many
locations. Reinforcement steel is exposed on many structural members.
However, the bridges seem to be in reliable structural condition. There is a
problem with the erosion of the approaches up to the bridges from the farm
7|P age
APPENDIX I
roads. There exist so-called sink holes at the entrances creating difficulty in
mounting the bridge. These need to be corrected or will only get worse with time.
Recommended Action
Patching. Cleaning of exposed reinforcing steel and patching could add years of
service to these members. During final design it is recommended that each
bridge be looked at on a unit by unit basis.
Correct the Approaches. The approaches to the bridges have eroded away over
time. It would be useful to restore these approaches to allow better entry onto the
bridges and less wear and tear to both the bridge and the vehicles. This is a
minor cost that will afford significant benefits
Dikes. There are some dikes along the Prut River associated with this CIS.
However, there is no recent flooding reported in the area.
Recommended Action
Examination of Adequacy of Dike. For reasons discussed in the case of ChircaniZrneti, the associated costs for the proposed study for dikes adequacy or for
dikes rehabilitation are not included in the cost estimates for this CIS
rehabilitation.
Drainage Assessment in the Talmaza
Earthen Surface Canals. The earthen drainage canals total 48.0 km in this CIS.
The drainage system covers about 100 % of the irrigated area. The canals have
an average sediment accumulation of approximately 0.2m to 0.5m in the canals
(b=2,h=2 and b=3, h=3). Reed growth in the canals is not as pervasive as at the
other systems, but there are many trees growing on the side slopes and in the
canals, as well as on the embankments. It is estimated that there are
approximately 15 trees per kilometer of canal length. The trees are estimated to
be from 15 cm to 50 cm in diameter. Water is at the top of and in some sections
overflowing the canal banks when inspected on April 8, 2009. The canal side
slopes are not clearly visible, but the cross-section appears to be round.
Slouching of the embankment towards the center of the canals has diminished
capacity.
Recommended Action
Remedial Cleaning. Clean the sediment and reed growth in the canals
immediately. The estimate of the current volume of sediment in the canals is
approximately 1.9 cubic meters/meter for the canals. Trees need to be cut and
significant reshaping of the canal embankments needs to be done at this time.
Annual Inspection / Periodic Cleaning. The drainage system should be inspected
once a year and provisions for sediment cleaning and bank maintenance should
8|P age
APPENDIX I
be made on an approximate five year cycle. Weed control should be done on a
more frequent basis. A budget should be established for this purpose.
APPENDIX I
adequacy or for dikes rehabilitation are not included in the cost estimates for this
CIS rehabilitation.
Drainage Assessment in the Suvorov
Upon inspection of the Suvorov CIS, it was discovered that the drainage system
comprised only 12 hectares of the massive Suvorov system (less than 1%).
Although there is no as-built information regarding the drainage piping, the local
operator states that there is 63mm diameter drainage piping spaced 14m to 17m
apart, but does not know the length. He also indicated that the piping never
worked. Any pipe that had an outlet into the drainage canals has been removed
during sediment cleaning through the years.
In conclusion, the drainage system in Suvorov, upon field investigation, became
a non issue because of its insignificant size. It was dropped from further
consideration.
10 | P a g e
Appendices
Appendix J
Historic Electricity Tariffs in Moldova
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
Tarifele de livrare a energiei electrice consumatorilor n 1997-2008 (bani/kWh) Electric Energy tariffs for 1997 - 2008 (bani/KWh)
Jun97
Sep98
Dec98
Jun99
Mar00
Sep01
Aug02
Jul03
REDNordiNordVes
24.00
25.50
42.00
50.00
57.00
65.00
63.00
70.00
REDUnionFenosa
24.00
25.50
42.00
50.00
65.00
68.00
72.00
80.00
Source:REPORTofANRE:ActivitateaANREinanul2008publishedonwebsitehttp://www.anre.md/press/index.php?vers=1
16%
Dec04
70.00
78.00
Dec05
70.00
78.00
Dec06
70.00
78.00
REDNordiNord
Vest
REDUnionFenosa
120.00
80.00
60.00
40.00
20.00
01/06/2008
01/02/2008
01/10/2007
01/06/2007
01/02/2007
01/10/2006
01/06/2006
01/02/2006
01/10/2005
01/06/2005
01/02/2005
01/10/2004
01/06/2004
01/02/2004
01/10/2003
01/06/2003
01/02/2003
01/10/2002
01/06/2002
01/02/2002
01/10/2001
01/06/2001
01/02/2001
01/10/2000
01/06/2000
01/02/2000
01/10/1999
01/06/1999
01/02/1999
01/10/1998
01/06/1998
01/02/1998
01/10/1997
0.00
01/06/1997
8%
MDbani
7%
Aug08
120.00
110.00
100.00
19%
Jan08
108.00
98.00
140.00
15%
31%
Aug07
101.00
96.00
ElectricEnergyTariffs19972008
REDNordi REDUnion
NordVest Fenosa
Averageannualrate
increasebetween
1997and2008
Averageannual
Increasebetween
2006&2008
Averageannual
increasebetween
1998&2006
Jul03
70.00
78.00
Appendices
Appendix K
Inventory of Missing/Vandalized Electrical Components
at Each CIS
Feasibility Studies for the 16 CIS in Moldova Proposed for MCC Funding
Main Report -Final
December 2009
APPENDIXK
InventoryofMissing/VandalizedElectricalComponentsatEachCIS
ITEM
ACTION
SUB-COMPONENT
QTY.
UNITS
NSG-1
Power
Supply
Add new
Add new
Add new
Replace
0.2
3
1
6
1
1
1
km
Ea
Ea
Ea
Ea
Ea
Lot
2
3
2
3
2
1
2
km
Ea
Ea
Ea
Ea
Ea
Lot
3
2
1
3
1
1
1
km
Ea
Ea
Ea
Ea
Ea
Lot
3
3
1
6
1
1
1
1
1
km
Ea
Ea
Ea
Ea
Ea
Ea
Lot
Lot
NSP-1
Power
Supply
NSP-2
Power
Supply
NSP-4
Power
Supply
S-1
Power
Supply
Page1of5
5
3
2
3
1
1
1
1
km
Ea
Ea
Ea
Ea
Ea
Ea
Lot
APPENDIXK
ITEM
ACTION
SUB-COMPONENT
QTY.
UNITS
0.1
2
6
1
1
1
km
Ea
Ea
Ea
Ea
Lot
0.1
2
6
1
1
1
km
Ea
Ea
Ea
Ea
Lot
0.8
2
1
3
1
1
1
1
km
Ea
Ea
Ea
Ea
Ea
Ea
Lot
S-6
Power
Supply
Replace
Replace
SPD-5A
Power
Supply
S-5
Power
Supply
Upgrade Main
Power
Transformer
from 400 kVA to
Main Power Transformer 10 kV/0.4 kV, 1000 kVA
1,000 kVA
Ea
SP-2
Power
Supply
Upgrade Main
Power
Transformer
Ea
Ea
AuxiliaryPowerTransformer6310/0,4V
Ea
Ea
Ea
1
1
1
Ea
AuxiliaryPowerTransformer6310/0,4V
Ea
Ea
Ea
1
1
1
NSP
Power
Supply
Replace
NSG
Power
Supply
Replace
Page2of5
APPENDIXK
ITEM
ACTION
SUB-COMPONENT
QTY.
UNITS
NS-2
Power
Supply
Replace
0.15
2
1
3
1
1
1
km
Ea
Ea
Ea
Ea
Ea
Lot
1.5
2
km
Ea
Ea
Ea
Ea
Ea
Lot
D-1
Power
Supply
Replace
6
1
1
1
D-2
Power
Supply
Replace
2
2
6
1
1
1
km
Ea
Ea
Ea
Ea
Ea
Lot
GNS-1
6 kV Overhead Line, 70 mm2, concrete poles
6 kV Disconnect Switch, 300 A
6 kV Circuit Breaker
Power
Supply
Add new
0.2
1
1
0.5
2
6
1
1
1
km
Ea
Ea
km
Ea
Ea
Ea
Ea
Lot
0.05
1
1
0.2
2
6
1
1
1
km
Ea
Ea
km
Ea
Ea
Ea
Ea
Lot
NSP-1
6 kV Overhead Line, 70 mm2, concrete poles
6 kV Disconnect Switch, 300 A
6 kV Circuit Breaker
Power
Supply
Add new
Page3of5
APPENDIXK
ITEM
ACTION
SUB-COMPONENT
QTY.
UNITS
PNS-2
Power
Supply
1
1
1
km
Ea
Ea
Ea
Ea
Ea
Ea
Lot
PNS-3
km
Power
Supply
Upgrade Main
Power
Transformer
from 1000 kVA
to 2,500 kVA
10 kV Disconnect Switch
10 kV Circuit Breaker
10 kV Power Fuses
Main Power Transformer 10 kV/6 kV, 2500 kVA
Auxiliary Power Transformer
0.4 kV Circuit Breaker
Connection to Switchgear (Bus or Cable)
Ea
Ea
Ea
Ea
Ea
Ea
Lot or m
S-10
km
Power
Supply
10 kV Disconnect Switch
Upgrade Main 10 kV Circuit Breaker
Power Xfmr 10 kV Power Fuses
from 1000 kVA Main Power Transformer, 10 kV/6 kV, 1600 KVA
to 1600 KVA Auxiliary Power Transformer
0.4 kV Circuit Breaker
Connection to Switchgear (Bus or Cable)
Ea
Ea
Ea
Ea
Ea
Ea
Lot or m
S-12
Power
Supply
Page4of5
1
1
1
km
Ea
Ea
Ea
Ea
Ea
Ea
Lot
APPENDIXK
ITEM
ACTION
SUB-COMPONENT
QTY.
UNITS
SP-18
Power
Supply
Replace
km
10 kV Disconnect Switch
10 kV Circuit Breaker
10 kV Power Fuses
Main Power Transformer, 630 kVA
Auxiliary Power Transformer
0.4 kV Circuit Breaker
Connection to Switchgear (Bus or Cable)
Ea
Ea
Ea
Ea
Ea
Ea
Lot
3
1
SP
Power
Supply
Replace
0.1
1
3
1
1
1
km
Ea
Ea
Ea
Ea
Ea
Ea
Lot
S-2
Power
Supply
Replace
3
2
2
1
1
1
1
km
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Lot
SP-11
km
Power
Supply
Upgrade Main
Power
Transformer
from 2500 kVA
to 5,000 kVA
35 kV Disconnect Switch
35 kV Circuit Breaker
35 kV Power Fuses
Main Power Transformer 35 kV/10 kV, 5000 kVA
Auxiliary Power Transformer
0.4 kV Circuit Breaker
Connection to Switchgear (Bus or Cable)
Page5of5
Ea
Ea
Ea
Ea
Ea
Ea
Lot or m