that have been washed out and ensuring that the two proposed passing
areas are safe and accessible. From the powerhouse location to the intake
the existing tracks are in varying states of repair and some a short new
section of track will also be required.
Watercourse crossings culverts will be installed in the two tributaries of
Allt
Intake working area a small working area near to the Intake will be
prepared for:
Site notices
2.2 The Method Statements which have been identified for this work are:
Site Establishment Method Statement
Method Statements will be in place prior to any work commencing on this activity
and shall address, as a minimum:
the preparation for and delivery of plant and materials to the area in
question
the establishment of the initial means of access to the site
the type and establishment of a temporary welfare facility (until such
time that the full welfare facilities may be established)
Public Access and Safety
Hazards which will be considered, as a minimum, in the associated Risk Assessment
will include
the safety of road users when offloading plant
the safety of pedestrians
the prevention of debris being deposited on public highway
6 Powerhouse Construction
6.1 Summary of Works/Methods
The powerhouse is sited away from the river and does not involve any de-watering
works.
The powerhouse area is adjacent to the existing access track.
The following is the outline for method for the construction of the powerhouse:
Site preparation
- Removal and storage of vegetation and topsoil - Excavation of foundations for
pipe anchor block, turbine sump and transformer compound, and for powerhouse
wall footings - If required, pumps will be used to keep the working area dry and
this will be discharged to a settlement pit dug several meters away from the burn.
Construction
o Cast foundations and main floor slab
o Build superstructure and roof
o Formalise hard-standing area
Reinstatement and landscaping
Drawings of the proposed powerhouse building are given in Appendix F
6.2 The Method Statements which have been identified for this work are:
Powerhouse Method Statement - Slab Excavation
Powerhouse Method Statement - Slab Construction
Powerhouse Method Statement - Blockwork
Powerhouse Method Statement - Roof
Powerhouse Method Statement - Gantry
Method Statements will be in place prior to any work commencing on this activity
and shall address, as a minimum: