Sie sind auf Seite 1von 38

ROAD AND HARDSTANDING

Item

Description

Unit

Qty.

Rate

ROAD AND HARDSTANDING


Excavate commencing from existing platform level, get out, part
return, fill in and ram deposit, spread in making up levels where
directed within site and remainder load and cart away
To reduce levels
A

average 550mm deep (Provisional)

m3

2,132

m2

3,877

m2

3,877

m2

3,877

m2

3,877

Trim, levelling and grading sub-grade; rolling to the required


chamber and gradient
B

at road sub-grade level


imported fill materials; spreading, laying to gradients and chambers;
compacting in layers by mechanical means
Granular sub-base

50mm thick
Crusher run

375mm thick
Approved bituminous tack coat spread on top premix road

generally
Premix surfacing
Premix 'Asphaltic concrete' surfacing compound wearing/ binder
course; spread, levelled and rolled to the required chambers and
gradient

75mm thick binder course (ACBC 28)

m2

3,877

50mm thick wearing course (ACWC 14)

m2

3,877

To Collection

RM

Item

ROAD AND HARDSTANDING


Unit
Qty.
Rate

Description
ROAD AND HARDSTANDING (Cont'd)
Road kerb
Cast in-situ concrete Grade 20 kerb including all necessary bend,
curves and intersection; finished fair on all exposed surfaces bedded
jointed in Grade 15 concrete haunching of 450mm width x 325mm
high including all necessary excavation, concrete & formwork etc, all
as detailed in Engineer's Drawing No.:PL/SJKC/101018/RD/DT/01

610mm x 150mm x 300mm high

722

EXTRA OVER for cast in-situ concrete kerb with 290mm x


205mm oulet opening including all necessary formwork and
reinforcement

No

111

722

227

Prepare and apply one sealer coat and two finishing coat of acrylic
pint to concrete kerb
C

610mm x 300mm x 300mm high


Glazed wire scupper pipe bedded and jointed in 150mm thick
concrete haunching semi surround to road side drain (In 111 No.)

225mm diameter
Road Marking (Provisional)
Preparing; applying two coats of hot applied thermoplastic road
marking paint; on concrete / premix surfaces areas; all detailed in
Engineer's Drawing No. PL/SJKC/101018/RD/DT/04

Straight ahead directional arrow

No

25

Right turn arrow sign

No

Straight and Left turn arrow sign

No

Left and Right turn arrow sign

No

150mm wide road edge line marking

722

100mm wide centre line marking

518

Double line marking each line 100mm wide

147

To Collection

RM

Item

Description

Unit

ROAD AND HARDSTANDING


Qty.
Rate

ROAD AND HARDSTANDING (Cont'd)


Stop lines
A

200mm wide

17

100mm wide

11

189

83mm X 360mm x 12 Gauge galvanised steel guardrail as described


to profile fixed on and including 178mm x 76mm G. I. channel
section to 360mm length and 178mm x 76mm G. I. channel section
2.18m length embedded in 400mm diameter x 915mm high Garde
20/40 concrete at 1.9m centres, including all fixing screws, bolts and
nuts, flat plate washers and all incidental excavation, laid in straight
or curve on plan, all detailde in Engineer's drawings No.:
PL/SJKC/101018/RD/DT/06

Supply and instal road signages as described comprising 75mm


diameter galvanised iron post painted to local authority's
requirements embedded in Grade 15 mass concrete, all as detailed
in Engineer's Drawings No.: PL/SJKC/101018/RD/DT/04
(Provisional)
D

Stop Sign (RP.1)

No

Yield Sign (RP.13)

No

Chevron Sign (WD.39a)

No

Left and Right Bends Sign (WD.10)

No

Chevron Sign (WD.44)

No

Speed Limit (RP.7)

No

Making good
Allow for reinstatement of the public road and making good all works
disturbed after completion of the road works, to comply the
Authorities' requirement
K

Generally

Item

To Collection

Item

Description

Unit

RM

ROAD AND HARDSTANDING


Qty.
Rate

ROAD AND HARDSTANDING (Cont'd)


Slope Protection by Close Turfing (Provisional)
A

Approved 75mm thick coarse clean sand blanket with 50mm thick
approved black vegetable soil, spread, levelled, well rolled and
compacted to receive turfing (measured separately)

m2

3,000

Close turfing to flat or sloping surfaces with approved good grade


cow grass with an approximate turf size of 225mm x 225mm as
described nailing with and including 10mm diameter 300mm long
hardwood laid on 50mm thick approved semi compacted black
vegetable soil (measured separately) and including watering, rolling,
weeding and tending until firmly established, replacing badly ground
areas as directed and preparation works consisting of levelling and
trimming surfaces

m2

3,000

Allow for labour, plant, materials and everything else necessary to


provide 12 months of full time intensive maintenance of all planted
turfing within boundary including watering, weeding on continous
basis, fertilising on monthly intervals using compound fertiliser,
mowing at 3 weeks intervals and top dressing to level the ground on
continous basis. Contractor shall replace any wilted grass at his own
cost

item

Allow for all other works not listed above but shown on the drawing
or referred to in the Specification or Preambles or which are
necessary to ensure completion of the works in this bill (item to be
specified)

To Collection

Item

Description

Unit

RM

ROAD AND HARDSTANDING


Qty.
Rate

ROAD AND HARDSTANDING (Cont'd)


COLLECTION

Page No. 1/1

Page No. 1/2

Page No. 1/3

Page No. 1/4

To Final Summary

Item

Description

RM

STORM WATER DRAINAGE SYSTEM


Unit
Qty.
Rate

STORM WATER DRAINAGE SYSTEM


Precast concrete box culvert with cover
Precast concrete box culvert G40; collar joints; jointing in cement
mortar (1:2); with and including 200mm thick hardcore, excavation,
getting out; part returning and compacting; removing surplus
excavated materials from site, as detailed in Engineer's Drawing No.:
PL/SJKC/101018/RD/DT/02
A

900mm x 1200mm depth laid in trench

12

Reinforced concrete drain


Construct reinforced concrete drain consist of 150mm thick wall and
base with 2 layer of BRC A8; complete with 50mm thick lean
concrete, 200mm x 150 mm concrete beam on top at 4m centre to
centre and 50mm diameter PVC pipe with 10mm sized aggregate
wrapped with filter cloth at 4m centre to centre at both side of walls;
with and including excavation, getting out; part returning and
compacting; removing surplus excavated materials from site, as
detailed in Engineer's Drawing No.: PL/SJKC/101018/RD/DT/04
750mm x 750mm depth internally
B

not exceeding 1000mm deep

156

exceeding 1000mm but not exceeding 1500mm deep

89

cascasing drain of size


D

750mm / 1050mm x 1050mm depth internally

63

1200mm / 1500mm x 1200mm depth internally

147

No

Sump
Reinforced concrete sump; construct of 150mm thick wall and base
with Y10-150 c/c both way; with and including 50mm thick lean
concrete, formwork, excavating pits, part returning and compacting;
removing surplus excavated materials from site and building in ends
of drains and culvert; as detailed in Engineer's Drawing No.:
PL/SJKC/101018/RD/DT/03
1500mm x 1500mm internally
F

not exceeding 1500mm deep to invert

To Collection

Item

Description

RM

STORM WATER DRAINAGE SYSTEM


Unit
Qty.
Rate

STORM WATER DRAINAGE SYSTEM (Cont'd)


Mild steel sump grating
Sump cover gratings complete with hinges; all welded together;
painting with two coats biuminous paint; placing in position; as
detailed in Engineering's Drawing No.: PL/SJKC/101018/RD/DT/02
A

1500mm x 1500mm wide

No

No

item

item

Trash screen
Trash screen consisting of top & side member 50mm x 12mm thk.
Galvanised m.s flat, bottom member 75mm x 12mm thk. Galvanised
m.s flat and verical member consisting of T12 diameter galvanised
m.s bar welded to galvanised m.s flat at 50mm c/c with 250mm high
x 150mm width x 100mm thk. 1:3:6 concrete mix stopper at both
ends : as detailed in Engineer's Drawing No.
PL/SJKC/101018/RD/DT/05
B

overall size 1500mm x 600mm high

Allow for new drainage connection to the existing main drain / sump;
including all necessary fitting, excavation, backfilling, etc; making
good all work disturbed; all as per Engineer's specification
Testing

Allow for testing, cleaning and disinfecting the whole Storm


water Drainage System to the satisfaction of the Engineer
and/or Local Authorities and make good all defects
..

Allow for all other works not listed above but shown on the drawings
or referred to in the Specification or Preambles or which are
necessary to ensure completion of the works in this bill (item to be
specified)
.
.
.

To Collection

Item

Description

RM

STORM WATER DRAINAGE SYSTEM


Unit
Qty.
Rate

STORM WATER DRAINAGE SYSTEM (Cont'd)


COLLECTION

Page No. 2/1

Page No. 2/2

To Final Summary

Item

Description

RM

RETAINING STRUCTURE (CH 225.00 TO CH 275.00)


Unit
Qty.
Rate

RETAINING STRUCTURE (CH 225.00 TO CH 275.00)


PILING WORKS (PROVISIONAL
Notes:
1

This Bill is to be read in conjunction with the foregoing General


Conditions, Preliminaries and Specifications

The words "as described" where used in tis Bill mean as described
in the above documents

The quantities given for piling works are Provisional and Payment
sall be made based on site measurement of actual work done

The Contractor may carry out his own soil investigation in addition to
the information that may be given. All cost in connection there with
shall be deemed to be included in the piling rates
Payable length for piles shall be as follows

(a) Driving of piles shall be measured and paid for in linear metre
measured from the toe of the pile when pitched to the toe of the
pile when driven
(b) The supply of piles shall be measured and paid for in linear
metre measured from the toe of the pile when pitched to the toe of
the pile when driven
Piling Equipment
Provide all necessary plant, equipment and tools; including
transporting to the site, assembling, dismantling and removing from
site after conmpletion of the works
A

hydraulic hammer system

item

item

item

handling and moving piling plant and equipment about the site;
including all necessary temporary work in conection therewith
B

hydraulic hammer system


Piling records
submit piling records in triplicate duly signed by the Contractor and
the Engineer's representative and delivered to the Engineer as work
proceeds

reinforced concrete piling system

To Collection

Item

Description

RM

RETAINING STRUCTURE (CH 225.00 TO CH 275.00)


Unit
Qty.
Rate

RETAINING STRUCTURE (Cont'd)


Reinforced Concrete Piling; Grade 45
Supplying and delivering to site reinforced concrete pile
A

150mm x150mm; initial pile in 6.00m length

No

125

150mm x150mm; extension pile in 6.00m length

No

125

150mm x150mm; extension pile in 3.00m length

No

250

Unloading, transporting, handling and pitching for driving


D

150mm x150mm; initial pile in 6.00m length

No

125

150mm x150mm; extension pile in 6.00m length

No

125

150mm x150mm; extension pile in 3.00m length

No

250

2,250

No

375

No

125

No

Drive by hydraulic hammer vertical Precast Reinforced Concrete


Sirim approved piles singly orin cluster
G

150mm x 150mm pile


Mild steel connection plates; butt welding plates

extension joints; to 150mm x 150mm R.C. Pile


Cutting off pile head to specified depths; include for out-of-sequence
working and returning at a later stage to complete operation and
preparing reinforcement for connection and removing surplus
lengths from site

150mm x 150mm pile


Pile Dynamic Load Test (PDA)
Supply all necessary equipment to conduct dynamic load tests using
pile driver analyser (PDA) on selected 200mm x200mm piles to
determine pile integrity and load carrying capacity including
mobilisation and demobilisation of all equipment and submission of 3
sets of reports to the S.O.

150mm x 150mm pile

To Collection

Item

Description

RM

RETAINING STRUCTURE (CH 225.00 TO CH 275.00)


Unit
Qty.
Rate

RETAINING STRUCTURE (Cont'd)


Excavate; commencing from finished ground levels; get out, part
return, fill in and ram deposit, sread in making levels where directed
within site and remainder load and cart away
Retaining walls base
A

not exceeding 1.50m deep

m3

379

1.51m - 3.00m deep

m3

253

m2

319

m2

208

m2

208

m3

65

m2

334

Imported fill materials; spreading, leveling and compacting in layer;


20mm diameter aggregate
Back of retaining walls
C

1000mm thick
Hardcore bed consisting of hard, dry broken brick or stone, spread
and levelled and well consolidated
150mm thick

retaining wall base


Concrete Grade 15 spread and levelled as described
Blindings; 50mm thick

retaining base
Vibrated reinforced concrete Grade C30 as descibed
Retaining wall base

generally
Retaining walls

225mm thick

To Collection

Item

Description

RM

RETAINING STRUCTURE (CH 225.00 TO CH 275.00)


Unit
Qty.
Rate

RETAINING STRUCTURE (Cont'd)


High tensile steel bar reinforcement
Retaining wall bases
A

16mm diameter bar

kg

5,979

10mm diameter bar

kg

2,083

Retaining walls
C

16mm diameter bar

kg

12,681

10mm diameter bar

kg

2,074

Sawn formwork as described


Sides; vertically
E

edge of base; 300mm high

300

retaining walls

m2

668

No

130

Weep hole
To supply and install 75mm diameter weep hole comlete with
300mm x 300mm x 300mm agregate wrapped with 1 layer of
geotextile; all detailed in Enginner's Drawing No.:
PL/SJKC/101018/EW/DT/04
G

225mm long
Allow for all other works not listed above but shown on the drawings
or referred to in the Specifications or Preambles or which are
necessary to ensure completion of the works in this bill (items to be
specified)
.
.
.

To Collection

Item

Description

RM

RETAINING STRUCTURE (CH 225.00 TO CH 275.00)


Unit
Qty.
Rate

RETAINING STRUCTURE (Cont'd)


COLLECTION

Page No. 3/1

Page No. 3/2

Page No. 3/3

Page No. 3/4

To Collection

Item

Description

RM

RETAINING STRUCTURE (CH 0.00 TO CH 25.00)


Unit
Qty.
Rate

RETAINING STRUCTURE (CH 0.00 TO CH 25.00)


PILING WORKS (PROVISIONAL
Notes:
1

This Bill is to be read in conjunction with the foregoing General


Conditions, Preliminaries and Specifications

The words "as described" where used in tis Bill mean as described
in the above documents

The quantities given for piling works are Provisional and Payment
sall be made based on site measurement of actual work done

The Contractor may carry out his own soil investigation in addition to
the information that may be given. All cost in connection there with
shall be deemed to be included in the piling rates
Payable length for piles shall be as follows

(a) Driving of piles shall be measured and paid for in linear metre
measured from the toe of the pile when pitched to the toe of the
pile when driven
(b) The supply of piles shall be measured and paid for in linear
metre measured from the toe of the pile when pitched to the toe of
the pile when driven
Piling Equipment
Provide all necessary plant, equipment and tools; including
transporting to the site, assembling, dismantling and removing from
site after conmpletion of the works
A

hydraulic hammer system

item

item

item

handling and moving piling plant and equipment about the site;
including all necessary temporary work in conection therewith
B

hydraulic hammer system


Piling records
submit piling records in triplicate duly signed by the Contractor and
the Engineer's representative and delivered to the Engineer as work
proceeds

reinforced concrete piling system

To Collection

Item

Description

RM

RETAINING STRUCTURE (CH 0.00 TO CH 25.00)


Unit
Qty.
Rate

RETAINING STRUCTURE (Cont'd)


Reinforced Concrete Piling; Grade 45
Supplying and delivering to site reinforced concrete pile
A

240mm x 240mm; initial pile in 6.00m length

No

78

240mm x 240mm; extension pile in 6.00m length

No

78

240mm x 240mm; extension pile in 3.00m length

No

156

Unloading, transporting, handling and pitching for driving


D

240mm x 240mm; initial pile in 6.00m length

No

78

240mm x 240mm; extension pile in 6.00m length

No

78

240mm x 240mm; extension pile in 3.00m length

No

156

Drive by hydraulic hammer vertical Precast Reinforced Concrete


Sirim approved piles singly orin cluster
G

240mm x 240mm pile

1,404

No

234

No

78

No

Mild steel connection plates; butt welding plates


H

extension joints; to 240mm x 240mm R.C. Pile


Cutting off pile head to specified depths; include for out-of-sequence
working and returning at a later stage to complete operation and
preparing reinforcement for connection and removing surplus
lengths from site

240mm x 240mm pile


Pile Dynamic Load Test (PDA)
Supply all necessary equipment to conduct dynamic load tests using
pile driver analyser (PDA) on selected 200mm x200mm piles to
determine pile integrity and load carrying capacity including
mobilisation and demobilisation of all equipment and submission of 3
sets of reports to the S.O.

240mm x 240mm pile

To Collection

Item

Description

RM

RETAINING STRUCTURE (CH 0.00 TO CH 25.00)


Unit
Qty.
Rate

RETAINING STRUCTURE (Cont'd)


Excavate; commencing from finished ground levels; get out, part
return, fill in and ram deposit, sread in making levels where directed
within site and remainder load and cart away
Retaining walls base
A

not exceeding 1.50m deep

m3

569

1.51m - 3.00m deep

m3

2,788

m2

583

m2

358

m2

358

m3

288

m2

583

Imported fill materials; spreading, leveling and compacting in layer;


20mm diameter aggregate
Back of retaining walls
C

1000mm thick
Hardcore bed consisting of hard, dry broken brick or stone, spread
and levelled and well consolidated
150mm thick

retaining wall base


Concrete Grade 15 spread and levelled as described
Blindings; 50mm thick

retaining base
Vibrated reinforced concrete Grade C30 as descibed
Retaining wall base

generally
Retaining walls

225mm thick

To Collection

Item

Description

RM

RETAINING STRUCTURE (CH 0.00 TO CH 25.00)


Unit
Qty.
Rate

RETAINING STRUCTURE (Cont'd)


High tensile steel bar reinforcement
Retaining wall bases
A

32mm diameter bar

kg

24,363

25mm diameter bar

kg

7,432

16mm diameter bar

kg

7,507

Retaining walls
D

32mm diameter bar

kg

37,549

25mm diameter bar

kg

11,543

16mm diameter bar

kg

9,517

10mm diameter bar

kg

380

Sawn formwork as described


Sides; vertically
H

edge of base; 300mm high

143

retaining walls

m2

1,289

No

99

Weep hole
To supply and install 75mm diameter weep hole comlete with
300mm x 300mm x 300mm agregate wrapped with 1 layer of
geotextile; all detailed in Enginner's Drawing No.:
PL/SJKC/10108/EW/DT/04
K

225mm long
Allow for all other works not listed above but shown on the drawings
or referred to in the Specifications or Preambles or which are
necessary to ensure completion of the works in this bill (items to be
specified)
.
.
.

To Collection

Item

Description

RM

RETAINING STRUCTURE (CH 0.00 TO CH 25.00)


Unit
Qty.
Rate

RETAINING STRUCTURE (Cont'd)


COLLECTION

Page No. 4/1

Page No. 4/2

Page No. 4/3

Page No. 4/4

To Final Summary

RM

1/1
ROAD AND HARDSTANDING
Amount

1/2
ROAD AND HARDSTANDING
Amount

1/3
ROAD AND HARDSTANDING
Amount

1/4
ROAD AND HARDSTANDING
Amount

1/5
ROAD AND HARDSTANDING
Amount

2/1
ORM WATER DRAINAGE SYSTEM
Amount

2/2
ORM WATER DRAINAGE SYSTEM
Amount

2/3
ORM WATER DRAINAGE SYSTEM
Amount

3/1
CTURE (CH 225.00 TO CH 275.00)
Amount

3/2
CTURE (CH 225.00 TO CH 275.00)
Amount

3/3
CTURE (CH 225.00 TO CH 275.00)
Amount

3/4
CTURE (CH 225.00 TO CH 275.00)
Amount

3/5
CTURE (CH 225.00 TO CH 275.00)
Amount

4/1
RUCTURE (CH 0.00 TO CH 25.00)
Amount

4/2
RUCTURE (CH 0.00 TO CH 25.00)
Amount

4/3
RUCTURE (CH 0.00 TO CH 25.00)
Amount

4/4
RUCTURE (CH 0.00 TO CH 25.00)
Amount

4/5
RUCTURE (CH 0.00 TO CH 25.00)
Amount

Das könnte Ihnen auch gefallen