Beruflich Dokumente
Kultur Dokumente
Rail Creep can occur through fasteners during train braking and
accelerating actions as well as due to tempature gradients along the rail. Loss
of toe load of fitting can also cause movement of rail.
Curve Shifting can occur under repeated vehicles lateral loads and high
curving forces.
Track Vertical Settlement can occur under repeated vertical wheel loads
and high impact loads.
Apart from the above, track maintenance operations (such as lining, lifting,
tamping, repairing defective / broken rails, etc.) which alter the longitudinal force state
in the rails also influence the stress free tempature.
Hence the effective rail temperature at which the rail would be stress free, can be
different from the Td at any point of time and in fact, can also vary along the length of
LWR at same time.
The importance of correct knowledge of the stress-free tempature (SFT) of rails
in LWR tracks is demonstrated by the fact that every 10oC variation in tempature causes
LWR force variation of 16 t in 52 kg and 19 t in 60 kg track respectively. The
maximum and minimum tempature in a day varies up to 15oC and 25oC during summer
& winter respectively. Thus the locked up localized stress towards higher / lower side
can result in fractures / buckling of track when compounded with the thermal forces.
This underlines the need for correct assessment of stess-free tempature (SFT) of rail.
The safety of Long Welded Rails (LWR) track is vitally affected by locked up
thermal stresses, which play an important role in the phenomenon of buckling or
fractures and thus have important bearing on safety. At present, the IR do not have any
1
equipment to objectively assess these stresses and therefore de-stressing operations are
carried out based upon the observation of movements at Switch Expansion Joint (SEJ).
Some countries have developed devices to measure stress, in long-welded rails
`in-situ' which makes it possible to monitor and take timely action to avoid rail
fractures. It has been decided to obtain expertise to measure rail stress `in-situ', in the
interest of enhanced safety. This will help in introducing the concept of "Need Based
Destressing" of Long Welded Rails ( LWR) instead of calendar based system. This will
not only save huge costs but also postpone the need to demand longer traffic block at
the specific time of the day.
Methods of measurement of stress-free tempature
Measuring the longitudinal stresses in rail will give an estimation of the
remaining safety margin in a given track section. There are various methods of
measurement of stress in the track.
(1) Conventional methods These methods only allow measurement of the
difference in stress between two states. Such methods can only be used to determine the
absolute stress level if an additional xeroing measurement is carried out. This involves
cutting out a section of rail at the point to be measured and neutralizing the stresses in it.
On IR, two methods have been developed i.e.
(a) Cut & Weld method developed by RDSO
gobs = AE2
(t dcal t obs ) 2
Rmob
tdcal = tobs +
g obs xRmob
AE
It should be portable.
It should be able to give absolute and accurate values.
The measurement should be independent of residual stresses in the rail.
Therefore, realizing the need to determine the general stress level in the LWR
and the difference in the stresses in the various portions of the same LWR, various
Railway Systems in the world made efforts to develop some methods of finding out the
stress level by way of Non-Destructive Instrumentation Device. The developmental
history of these measures is as follows:
(i)
points was measured very very accurately along with the prevailing rail
temperature. The strain thus measured could be converted into stress
level. Similar equipments were subsequently developed and adopted by
some of the European railway systems. This system has limitation that
initial markings had to be done when the rail is stress-free and therefore
it was not possible to determine the stress in the rail without having
access to the zero stress level.
(ii)
Every 200m mark is made on the rail and its position W.r.t ground is
recorded.
The measurements are periodically repeated.
If the distance between two adjacent marks changes, it means the
stress in the rail changes.
Track Segments whose distance between marks are shorter /longer
than before are compression/tension.
The process is time consuming and not accurate.
(iii)
(iv)
In Europe itself during early 90s, heavy equipment was developed where
a on track rail car was used to pick up the rail, which has been released
by removing the clips, and subject it to bending deflection using ram in
the centre. The reactions at the support and load applied at the centre
were measured along with the relative deflection, which could be
analyzed to work out the stress level in the rail accurately. The
equipment was very costly and required blocking of the track as the
equipment was mounted on the rail car and had to be worked like a track
machine.
(v)
(vi)
Procedure of testing
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
(x)
(xi)
(ii)
(iii)
(iv)
With the knowledge of the vertical and longitudinal residual stress, the
thermally induced stress is deduced by simple subtraction.
The measured thermally induced stress can be converted to a temp
difference by using the std rail industry conversion of 2.4 MPa per oC.
So, by dividing the thermally induced stress by the conversion factor and
measuring the actual rail temp, temp it is possible to derive SFT
10
(ii)
(iii)
The process for determining the SFT will permit track maintenance
personnel to monitor changing SFTs in order that they may adjust
them as a planned maintenance activity before they reach a hazardous
level.
The process for determining the SFT can also be used in conjunction
with a SFT adjustment operation in order that the correct amount of
rail to add or remove to attain the desired new SFT.
(iv)
(v)
(vi)
(vii)
(viii)
13
Using Advantechs ADAM data acquisition controller, workers can wireless monitor
railway conditions via the Longitudinal Stress Detector, which can be mounted directly
on the track.
Time consuming.
Not accurate, actual SFT cant be
workout.
Widely used technique in practice today.
14
Tried in USA.
System could not be developed for
commercial application
Against the provision of maintenance
practice of LWR
Time consuming & requires line block
5.MBN Method
_______
15
References:
1. European Rail Research Institutes Report No.ERR/D/173/RP/12.
2. European Rail Research Institutes Report No.ERR/D/202/RP/9.
3. 6th International Heavy Haul Conference (Strategies beyond 2000), 10th April
1997.
4. 8th International Heavy Haul Conference, 2005.
5. Confidential Report dt. 13.9.2005 released by CTEs C.Rly on Non-destructive
Measurement of stresses in LWR.
6. Paper presented by David Bateman, London on Rail Stress & Rail Stress
Management during a Seminar held on 31 March 2004 (Published in Permanent
Way Institution Journal June 2004 Vol. 122).
7. Interim Report No. FRA-OR&D-76-270 dt. July 1976 prepared by D.M. Egle &
D.E. Bray for U.S. Department of Transportation.
8. Various Internet sites.
________
16