Beruflich Dokumente
Kultur Dokumente
Miguel Vega
Hctor G. Sarmiento
Member, IEEE
mvega@iie.org.mx
I. INTRODUCTION
The reliability analysis of a system, portion of a system or
component, can help the engineer understand the reason the
system is failing and its economic consequences, according
to the term Energy Not Supplied (ENS). This term has a cost
associated, so as to accomplish an economic comparison
between what would be spent by not to making an
investment, and the benefit obtained upon improving the
reliability of the system.
II. BACKGROUND
The oil refinery under study has an electrical configuration
consisting of different voltage levels for its supply and
distribution. The system has its own generation at 13.8 kV
with a total capacity of 55 MW. At 6.6 kV the installed total
capacity is 15MW. An interconnection with the utility is also
present, with a capacity of 60 MW. There are links as well
between these three supply systems. Peak demand is 60 MW
.
lematias@iie.org.mx
Luis E. Matas
1.
2.
1095
Bus 6.6kV
Link to
13.8kV
1096
Component
23 kV Bus
13.8 kV Bus
6.6 kV Bus
Reliability data
ri
1
Outages/year
Hrs.
0.0016
0.0008
0.0004
38.0
42.0
60.0
= Outage Frequency
ri = Repair Time
Outages/year
Hrs.
0.043
30.0
0.040
30.0
0.037
60.0
0.04
0.03
0.015
0.012
62.0
173.0
200.0
400.0
1097
TABLE II
RELIABILITY STUDY RESULTS
Reliability Indices
6.6 kV System
[Outages/year]
[Hrs./year]
PNS [kW
per year]
ENS [kWh
per year]
2.0355
20.88
7 304
13.8 kV
System
0.7630
12.17
3 278
160 147
42 653
TABLE IV
ESTIMATED INVESTMENT COST
Concept
Estimated investment
[Thousands of US Dlls.]
Cables
$2 852.5
Transformers
$1 386.0
Busways, load centers
$2 480.0
Basic Engineering
$1 200.0
TOTAL
$7 918.5
From the results above, it can be observed that for the system
at 13.8kV (compared with the 6.6 kV system):
VI. CONCLUSIONS
USDlls/kWh
6.74
(For a 4 hr outage)
Using the above figure, Table III illustrates the total annual
cost for energy not supplied for both systems.
TABLE III
ANNUAL COST FOR ENERGY NOT SUPPLIED
6.6 kV System
13.8 kV System
$1 079 391.00
$287 481.00
Total Cost [US
Dlls]
$791 910.00
Difference in
cost [*]
275%
Difference in
percentage
[*] This is the annual cost for not reconfiguring from 6.6. kV to 13.8 kV.
1098
REFERENCES
[1]. Vega, M., "Evaluacin de confiabilidad de sistemas de
transmisin de energa elctrica" M of Sc. Thesis,
Universidad Nacional Autnoma de Mxico, 1989.
[2]. Vega, M., Anlisis de confiabilidad de sistemas de
distribucin de energa elctrica, B. of Sc. Thesis,
Universidad Nacional Autnoma de Mxico, 1983.
[3]. Allan, R.N., R.Billington, "A Reliability Test System for
Educational Purposes Basic Distribution System Data
and Results", IEEE Trans. on Power Syst., Vol. 6, No.2,
May 1991, pp. 813-820.
[4]. Koval, D.O., Transmission Equipment Reliability Data
from Canadian Electric Association, IEEE Trans. on
Industry Applications, Vol 32, No. 6, Nov/Dec 1996, pp.
1439-1449.
[5]. A.G. Massud, M Th. Shilling, J.P. Hernndez,
Electricity restriction costs, IEE Generation,
Transmission. Distribution, Vol 141, No.4, July 1994,
pp.299-304.
[6]. Yabroff, Irvin, The Short-Term Cost of Electricity
Supply Interruptions", Report DOE/EP-005 from The
National Electric Reliability Study, United States Dept.
of Energy, April 1981, p.337.
[7]. Hung, O. K., "Justifying Upgrade Projects in Existing
Mills", IEEE Publication 0-7803-2418-8-6 / 95, 1995,
p.165.
[8]. Hernandez, F. J.,"Modernization and Expansion of an
Existing Electric Power Plant", IEEE Publication 07803-2642-3 / 95, 1995, p.48.
1099