Systems
Presenters
!
Martin Eveleigh
! Rolls-Royce North America
! Focal Point for Rolls-Royce Defense
Europe EVMS Implementation
! Based in GEAE Evendale, Cincinnati
! JSF F120 Project Engineer
Jim Henderson
! NAVAIR EVMS Focal Point
! Team Chief for EVMS Validation
Luis C Contreras
! AzTech International - Consultant to
Rolls-Royce during EVMS implementation
2
!
!
!
Program Background
Why Rolls-Royce Sought DoD Validation
Team philosophy/approach
3 Top Reasons for successful implementation
Review Process:
! Pre-Review (before any on-site visits)
! On-Site Reviews
! Post-Review
System Description & Instructions
! How SAP was integrated into the
documentation
SAP Challenges we overcame
5-10 Minutes for Q&A
Contact information for future Q&A
!
!
Did we validate
EVMS or SAP?
Spirit of Implementation
!
!
Not another
#@%&*
audit
!
!
!
!
!
!
!
!
!
!
!
!
!
!
The
contract
required it.
"
To be pro-active
To mitigate risks
Felt that starting implementation prior
to contract award would minimize
impact to initial project planning
The
contract
required it.
Implementation Milestones
!
!
!
!
!
!
!
!
Isnt this
overkill?
11
!
!
!
!
Nobody said
we could do
that!@#
Yeah, right. as
if you could
have even if
you wanted to?
12
Pre-Review Process
!
!
!
13
Stanmore Directory
Set up a folder on the LAN with subfolders for
!
all Project data including:
! MS Project files
! MS Excel files
! WBS Dictionary, SOW
! Purchase Orders
! Training Materials
! System Description/Instructions
Had laptops with the data available to Review
Team and to Project Team (PM, CAMs, PBT).
Electronic System Description
14
15
Review Process
!
!
Had to replace
those #$*&
Zs with Ss!
16
Advanced Visit
Progress Assessment Visit
Initial Compliance Evaluation
! Purchasing/Manufacturing
demonstrated from other programs;
some pending for Production;
mitigated.
17
18
Same old
same old
!
!
Were not
telling you
what to say,
but
!
Do CAMs ever
really use these
Notebooks?
SAP cant
do that!!??
19
20
!
!
!
!
!
Future
programme
required it.
Sometimes
had to beg
for support.
21
!
!
!
!
Paperless hasnt
happened yet
On-going
process
22
24
!
!
!
!
!
!
!
!
M -> J
Tell it like it is
Use the government. DoD Review teams are free consultants
Think: What are the Benefits to OUR Company?
Implementation Team members will not always be there after
implementation, so it is important to spell out as much as you
Free? What about
internal implemention
can.
effort, system design,
Review all standards documents
consulting,
Ask other companies.
Ask other review team experts from the government agencies
It is a big job, but use it to your company's advantage
Respond to all DRs/Issues. Don't necessarily agree, but definitely
Respond.
Neither member can have oversized ego about what's RIGHT
Focus on high value, high impact Control Accounts
Share tools between CAMs
25
!
!
All-expense
paid trip to
Europe!
26
Team Member
Team Assignments
Organization
Gayle Brooks
Lt. Col Paul Waugh
Jim Henderson
Kristen Kehrer
Monique Anneker
Harvey Johnson
Dave Kester
Rocky Galletta
Bill Jackson
Terry Bowd
Lorene Brown
Mike Lowry
Stephen Pears
Judith Yeaman
Bruce Campbell
Bev Deachin
Dennis Chapman
Ed Swain
Barbara Dobbins
Bob Gall
CDR Marion Eggenberger
Co-Review Director
Co-Review Director/Deputy PM
Team Leader
Assistant Team Leader
Organizing Process Leader
Organizing Process
Scheduling Process Leader
Scheduling Process
Work/Budget Authorization Process Leader
Work/Budget Authorization Process
Work/Budget Authorization Process
Accounting/Indirect Mgt Process Leader
Accounting/Indirect Mgt Process
Accounting/Indirect Mgt Process
Managerial Analysis Process Leader
Managerial Analysis Process
Matl Mgt/Change Inc. Process Leader
Matl Mgt/Change Incorporation Process
Matl Mgt/Change Incorporation Process
Subcontract Management Process Leader
Subcontract Management Process
DCMA
JPO
NAVAIR
NAVAIR
NAVAIR
DCMA
NAVAIR
CA MHP
GE
UK DPA SPS
NAVAIR
DCMA
UK DPA SPS
UK DPA SPS
GE
P&W
NAVAIR
GE
GE
P&W
DCMA
27
Beats holding
your thumb to
the sky...
28
Team Preparation:
# Developed review planning schedule
# Reviewed system description
# Worked through Progress Assistance Visit (PAV) issues prior to
Initial Compliance Evaluation (ICE)
# Developed team handbook with review methodology
# Conducted team training
# Cooperation between Government & Industry team was key
Conducted on-site review:
# Documented system description compliance
# Presented story board system traces to review team
# Evaluated compliance with CAM interviews, documentation
verification, and traces
So much for
glamourous
# Prepared evaluation report
European
vacation...
29
!
!
!
!
!
!
!
J -> M
Isnt this
common
sense Project
Management?
System Description:
! Process-oriented
! Includes guidelines and grey areas - for
PMs PMO, to resolve future conflicts
! 90% non-tool-specific
! Addresses management system
characteristics (App. B of EVMIG)
Instructions:
! Roles & Responsibilities
! Step-by-step, more detail, mechanics for
CAMs
! Essential for new CAMs
! More likely to change down the road
! More tool-specific
31
!
!
!
!
!
32
34
35
36
37
Electronic EVMS
DoD Reports
38
!
!
!
!
!
!
!
39
Expert Support
!
!
!
!
Consulting
scope creep...
40
!
!
M->L
SAP (now at Version v4.0b) was implemented as part of the Rolls-Royce IPM before EVMS
requirement came in
All planning, earned value, actual cost collection, and forecasting done at the Activity (work
package) level
Roles - PM, RM, CAM roles required within the tool
One-stop
shopping...
CATS - Cross-Application Time Sheet
Each Activity is automatically a charge number
!
Each Activity can have labor, purchase orders, or manufacturing orders against it
!
CAMs can drill down to see cost details
!
MRP - Material Requirements Planning
Ability to drill down to the manufacturing operations or the purchase order detail
!
Project Systems
WBS down to Control Account levels
!
Activities (Work Packages) linked (cost and schedule integration)
!
Planning & Forecasting: Resource management & Resource Profile Curves
!
Earned Value
!
Aimed to be able to do weekly Earned Value
Most costs accumulated daily/weekly
!
Earned value and forecasting can be done daily/weekly
!
41
One-stop
shopping?!
MRP
Variance
Analysis
Reports
(VARs)
Finance
SAP
Purchasing
Modules
(Among
others)
Project
Systems (PS)
Cost
Performance
Report (CPR)
Formats
Contract Funds
Status Report
(CFSR)
Customer Reporting
Schedule export
SAP
CATS
(Timesheets)
Initial
Planning
(iterations)
L
Earned
Value
Worksheets
Database for
Control Account
& Work Package
Statistics
MS Excel
Legend:
MS Project
MS 42
Access
No CPR?!!!
43
!
!
!
!
!
L -> M
Next release
will do all
thisNOT!
44
Cynics Challenges
!
!
!
!
!
45