JOB SAFETY ANALYSIS

Construction Right of Way


WORK ACTIVITY: ___________________________________
Each piece of equipment and crew are associated with known specific hazards that cause accidents to reoccur on one project
after another.
P123456
Mhd. Abdul Rahman LOCATION ;____________________
ARAB -D
SITE SUPERVISOR:___________________
PERMIT #:____________
Probability factors.
5

Evaluation Points
40-20High Risk

8
6
4
2
1
No
1

Severity Factors
8: Fatality, Permanent Disability

Probability Factors
5 : Extremely High

Abbreviation
E.P :Evaluation Points

1 9 12 Medium Risk

6: Serious Injury (LD>30 days)

4 : Highly Probable

S : Severity Factor

11-5 Low Risk

4: Major Injury (30>LD>4 days)

3 : Probable

P : Probability Factor

2: Minor Injury (4>LD>1 day)

2 : Rare

T : Total Points

1: Negligible

1 : Very Rare

4-1 Negligible

Activity ( Job Steps )


Arrival of personnel
and equipments on
site

Potential Hazard
Unfamiliar with local
situation and with site
regulation (station)
Incompetent operators
and equipment not in
good condition.
Heat stress

Who/ What Might


Be Harmed
Personnel &
Clients Property

Personnel &
Equipment

Risk E.P.
SxP=T

LD : Lost Workdays

Control/ Recovery Measures


All personnel to be fully briefed on
tasks and responsibilities together
with the use of PPE & Site
induction before start of job. Must
posses H2S training cards.
Operators of equipments shall have
valid license and third party
certified.
All required equipment & vehicle
must be QTIC inspected and copy
of Isthimara shall be kept in the
equipment.
Before operation vehicle and

Target E.P. Responsible/ Action


SxP=T
By
2x1=2
Site supervisor,
And Site Safety
Officer.
BCEC PMV, Client
2x1=2

No

Activity ( Job Steps )

Potential Hazard

Who/ What Might


Be Harmed

Risk E.P.
SxP=T

Control/ Recovery Measures

Target E.P.
SxP=T

equipment must have an approved


entry pass from the client.
Vehicle & equipment insp. must be
done & recorded. Keep fire
extinguisher.

Personnel

Clearing, grubbing,
backfilling and
compaction

Equipment working
under overhead line

Heat stress shelters to be provided


for workers.
Drinking water supply always
available.
Standby vehicle on site for
emergency purpose.
Banksman to be assigned in every
equipment in operation.
Rotating lights and reverse alarm
always operational.

2x1=2

Collision of equipment
or being run over.

Personne &
Clients Property

Breakdown of
equipment and oil/ fuel
spill.

Equipment
& Client Property

Regular checking of equipment with


checklist at first working hour.
Avoid spills and remove
contaminated soil

Personnel Injury and


dust

Personnel

Ensure complete PPE to be worn

2x1=2

Contact with authorized


live overhead line

Personnel
Equipment and
clients property

Maximum height of working


equipment is 3.5 meters.

3x2=6

Equipment might hit the


line post.

No dumping under or near OH line

Page 2 of 3

3x2=6

Responsible/
Action By

Site supervisor,
and Site Safety
Officer

Site supervisor,
and Site Safety
Officer

2x1=2

Site supervisor,
and Site Safety
Officer

No

Activity ( Job Steps )

Potential Hazard

Who/ What Might


Be Harmed

Risk E.P.
SxP=T

Target E.P.
SxP=T

Control/ Recovery Measures


Overhead line clearance certificate
shall be approved with PTW by
Authorized person.

Responsible/
Action By

Site supervisor,
and Site Safety
Officer

Operators and drivers shall aware of


overhead line.
Banksman assigned that equipment
will work with the maximum
awareness the line and posts.

PREPARED BY (HSE)
Name

REVIEWED BY (QP)

----------------------------------------

Name

----------------------------------------

Signature ---------------------------------------

Signature ---------------------------------------

Date

Date

---------------------------------------

Page 3 of 3

---------------------------------------