Beruflich Dokumente
Kultur Dokumente
(d)
(e)
(f)
P&DB
EPCT
CONS 13.1 continues by listing the broad extent to which the Engineer may
instruct Variations. Under sub-paragraph (a), Variations may involve changes in
quantities, but a change in the quantity of an item in the Bill of Quantities does not
necessarily constitute a Variation. For example, the final volume of general
218
excavation is typically not exactly identical to the Bill quantity for this work, without
there having been any Variation. See also CONS 12.3(a).
CONS 13.1(d) empowers the Engineer to instruct omissions, to which CONS 12.4
refers, unless the work is to be carried out by others. A similar provision and
restriction are contained in the first paragraph of P&DB/EPCT 13.1.
CONS 13.1(f) empowers the Engineer to instruct "changes to the sequence or
timing of the execution of the Works". However, "changes to the timing of the
execution" only empowers the Engineer to instruct changes to the timing of
execution operations, not to the timing of completion. In other words, the Engineer
is not empowered to instruct the Contractor to complete major parts (or all) of the
Works or any Section before the relevant Time for Completion expires.
Acceleration to complete within the Time for Completion is covered in Sub-Clause
8.6. Acceleration to complete prior to the Time for Completion is covered in the
first sentence of Sub-Clause 13.2. This "Time for Completion" is defined in SubClause 1.1.3.3 as including extensions of time due under Sub-Clause 8.4. If the
Engineer (under CONS or P&DB) or Employer (under EPCT) fails to determine
extensions of time in accordance with Sub-Clauses 8.4 and 20.1:
-