Beruflich Dokumente
Kultur Dokumente
How to conduct a
plant performance test
Performance testing after initial start-up has value well beyond t he short-term
goal of validating equipment g uarantees-it's your only opportunity to
establ'sh the baseline performance of the overall plant and many of its
I 1 or systems. Corporate bean counters may be interested in short-term
but a good plant engineer unde rstands that a thorough performance test will be useful for ma ny years. Here's your guide to each facet
of a performance test-plus pitfa lls to avoid.
By Tina l. Tob uren, PE. and l arry Jones. McHale & Associates Inc.
ompleting a power plant 's sIan-up
and commissioni ng usually means
pushing the prime contraclor to wrap
up the remaining punch lisl items an d gelting the new operators trained. Staffers are
tired of the long hours they've put in and
are looking forward to sculing into a work
routine.
Just when the job site is beginning to look
like an operating planL a group of engineers
arrives with laptops in hand, commandeers
the only spare desk in the control room. and
begins to un pack boxes of precision instruments. In a fit of controlled confusion, the
engineers install the instruments. find primary no .... elements. and make the required
conneclions. Wires are dragged back to the
eOnlrol room and term inated at a row of neatly arranged laptops. When the test begins.
Anatomy of a test
The type and extent of plant performance
testing activities are typicall y driven by the
project specifications or the turnkey contract.
They also usually are linked to a key progress
payment milestone. although the value of the
tests goes well beyond legalese. 1be typica l
test is designed to \'erify power and heat rate
guarantees that are pegged to an agreed-upon
set of operating condi tions. Sounds simple.
right1 But the behind-theseenes work to
prepare for a test on wh ich perhaps mi llions
of dollars are at stake beyond the contract
guarantees almost cenainly exceeds you r expectations (see box).
Long before arrivi ng on site, the te5tteam
will have:
Gathered s ite information .
Reviewed the plant design for the adequacy and proper placement o f test taps and
for the type and location o f primary now
elements.
Developed plant mathematical models
:lTltll~SI pnx""edurt"s
Met with the plant owner. contractor. and
representatives of major original equipment manufacturers (OEMs) to iron oUI
the myriad details oot covered by COntract
specifications. Experienced owners will
have made sure that the plant operations
staff is included in these meetings.
Tests are nonnally conducted at full- load
operation for a predetermined period of time.
The test team collects the necessary data and
ruliS them through Ihe facility correction
www.pow mog.com
model to obtain preliminary resul ts. Usually withill a day. a preliminary test report
or letter is generated to allow the owner to
declare 'substantial completion" and commence commercial operation. The results ror
fuel sample analysis (andlor ash samples) are
usually available within a couple of weeks.
allowing Ihe final custome r repon 10 be fin
ished and subminoo.
The an and seienceor perfonnance testing
require very specialized expenise and experience that take years to de\elop. The sci-
Performance test
economics are
overpowering
Co nsider a 500-MW fa cility with a heat
rate of 7,000 Btu/kWh. Whe n operating
at baseLoad with an 80% capacity factor, the plant will consu me over 24 million mmBtu per yea r. At a tu el cost of
S8/mm Btu, t hafs nearly SlOO miLlion in
fuel cost s fo r t he year.
If a n instrum entation or controL error ra ises t he heat rate of the facility
by 0.5%, t hat would cost the plant an
additional $1 million each year. If. on
t he other hand, a misreported heat rate
causes the faciLity to be dispatched
0.5"10 Less often, reducing the capacity
factor to 79.5%, t he Losses in revenue
at S50/MWh would amou nt to nearly
S1.1 mittion for the year.
Performa nce t ests can bring the right
people t ogethe r at the facility to identify Losses in performance and to recapt ure or prevent such losses in fa cility
profits.
PERFORMANCE TESTING
cnee of crunching data is defined by industry
standards , but the art rests in the ability \0
spot data inconsistencies , subtle instrument
errors. skewed control systems . and operational miscues. The c"pcrienced tester can
also quickly delennine how tbe plant must
be configured for the tests and can answer
questions such as, Will the steam turbine be
in pressure control or at valves wide open in
sliding-p ressure mode? What control loops
will need 10 be in manual or automatic during testing? and At what le vel should the
boiler or duct bumers be fired?
M id-term exams
There are many reasons to evaluate the performarKe of a plant beyond meeting contract
guarantees. For example. a performance test
might be conducted on an old plant to verify
its output and heat rate prior to an acquisition
~taullC
-.--
"
sitcd 31 sea level. its barometric pressure reference is 14.696 psia. For the same plant at
an altitude of 5.000 feet. the refere nce would
be 12.231 psia. and its guaranteed output
would be much lower.
The relative humidilY reference condition
mayor may not have a significalll bearing
on plant perfonnance. In gas turbine plants
the effect is nOI large (unless the inlet air is
conditioned). but it still must be accounted
for. The effect of humidity. however. is more
pronounced on cooling towers. Very humid
ambient air reduces the rate at which evapo-
FARO
FARO.com
800.736 .0234
----~
THE
MEASURE
OF
~~.""""
SUCCESS
~.,
..
""""_~
~,_'""'"'~
"
. 1PERFORMANCETESTING
ration takes place in the tower. lowering its
cooling capacity. Do wnstream effects arc
an increase in steam turb ine bac kpressure
and a reduction in the turbine -generator's
gross capacity.
The most imponant correction for gas
turbine plant performance tests involves
compressor inlet air temperature. All hough a
site's barometric pressure Iypically varies by
no more than 10% over a year. its tempera tu res may range from 20F to lOOP over the
period. Because air temperature has a direct
effect on air densit)'. temperature variation
changes a unit's available power output. For
a typical heavy-d uty frame gas turbine. a 3degree change in temperature can affect its
capacit)' by 1%. A temperature swing of 30
degrees could raise or lower power output
by as much as 10%. The effect can be even
more pronounced in aeroderivative engines.
ISO-s tandard operating conditions or
site-specific reference conditions are al most impossible to achieve during an ac tual test. Accordingly. plant contractors
and owners often agree on a base operating
condition that is more in line with normal
site atmospheric conditions. For example. a
gas turbine plant built in Florida might be
tested at reference conditions of 14.6 psia.
78F. and 80%. Establishing a realistic set of
General Physics Corporation (Gp) has been hetping power companies find
soIutioos to worl<forte qualifiation issu,,", for over 40 V"ars. GP a n hel p you
eduale your emptoyee'> to make !itlre they IIave the skills an d knowledge they
need to !itlcu'sslully operate and maintain your ptant.
Benefits of GPi Leam "':
21ft 7 Availability
410 .379.3 6 59
www.EnergyWBT.com
ISeplemb.r 20li
PERFORMANCE TESTING [
that it has been calibrated specifically for the
performance test in question followillg National lnstiwle of Standards and Technology
(NIST) procedures.
Another benefit of installing temporary
instrumentation is to verify the readings of
pennanent plant instruments. Plant instrumentation typically lacks NIST-traceable
calibration or has been calibrated by technicians who are more concerned with operability than with accurate perfonnance testing.
1bere's a good reason for the former: Per-
~r2tlOl I PO WE It
..
. 1PERFORMANCE TESTING
installed to independent leSI ports and calibrated separately, there's a gOCKl chnnce the
measurement is accurate. If there's a differ-
put is 460 MW. The plant instrumcm is accurate 10 within I %. and the test instrument
is even more accurate: +/-0.3% . In this case,
the lester prefers to see the two readings well
"
are in compliance with the test procedure because equipment disposition. operating limits.
and load stability affect the results. Data can
then be collected for the time periods defined
in the test pnx:edure and checked for compliance with all test stability criteria. Once data
have been collected and the test has been
deemed complete. the results can be shared
with all interested parties.
Because the short preliminary test may
be the most important part of the process. be
sure to allow sufficient time for it in the test
plan . The preliminary test must be done during steady-state conditions following load
stabilization Of when the unit is operating
at steady state during the emissions testing
program. The preliminary test has three objectives: to verify all data systems, to make
sure manual data takers are reading the correct instruments and meters. and to have the
data pass a "sanity check."
A fter the test data have been collected.
the readings should be entered into the
correction model as soon as possible and
checked for test stabi lity criteria (as dcfined
by the test procedure). At this point, dependin g on the correction methods. the test
director may be able to make a preliminary
analysis of the results. If the numbers are
way out of whack with expected values, a
good director will start looking for explanations-poSSibly, errors in the recorded
data or something in the operational sctup
of the unit itsclf. Though everyone is concerned when a uni t underperfonns, a unit
that performs unexpectedly well may have
problems that have been overlooked. For
exam ple, a unit that corrected test results indicate has a 5% capacity margin may need
10 have its metering checked and rectified.
or it may have been mistuned to leavc it in
an overfired condition.
Although an overtuned gas turbine may
produce more megawatt-hours during initial
operations. the gain comes with a price: increasing degradation of the unit's hot section.
shortening parts life and increasing maintenance costs. The most common mistake in
testing is acceptance of resu lts that are too
good. If results are bad. everyone looks for
thp. pmhlem. If the reslllt~ are ah-nve ]lar.
everyone is happy-especially the plant
ow ner. who seems to have gotten a "super"
machine. However. there's a reason for every excursion beyond expected perfonnance
limits - for better or worse
If all the pretest checks are done properly. the actual perfonnance test should be
uneventful and downright boring. It should
be as simple as veri fying that test parameters
(load , stability. etc.) are being mel. This is
where the really good perfonnance testers
make their work look easy. They appear to