Beruflich Dokumente
Kultur Dokumente
http://eprints.qut.edu.au/
I. INTRODUCTION
(a)
The aim is to test this UPS in real time framework for different network conditions. The network is torn along the network tearing line as shown in Fig. 2. The portion of network
which is above the tearing line is simulated by a computer
which is referred here as the supply side. A VSC based current
amplifier is connected to the UPS at PCC' (see Fig. 3), which
amplifies the current signal of RTS and mimics the supply
side network for the UPS. It is to be noted the load is simulated in the RTS and hence cannot consume any physical
power supplied by the UPS (see in Fig. 3). Therefore, the amplifier is used such that the real power can flow from the UPS
to the amplifier. The current amplifier is designed with power
regeneration capability so that it can supply the power back to
the UPS. The VSC based amplifier tracks this reference current to mimic the supply side. Thus the current if* from the
computer simulation is set as the reference for the amplifier.
The DC buses of the amplifier and the UPS are connected
such that the amplifier can send the power back towards the
UPS. Therefore the DG only supplies the losses in the physical
circuit. Also the PCC' voltage is measured with the help of
voltage sensor and fed in to RTS through an ADC.
(1)
Then from Fig. 2, we get the following expression for the active and reactive power entering the PCC from the source
Ps =
Qs =
Fig. 4. UPS structure used in which three separate VSCs are supplied from a
common dc storage capacitor.
Vt
2
R + X2
Vt
R2 + X 2
(2)
(3)
(4)
S1
vcf
S3
= K ps es + Kis es dt + K ds
des
dt
(5)
B. Mode-2 Control
In this mode, a fixed amount of power is drawn from the
UPS and the source supplies the balance amount of load requirement. Hence the control loop is given by
= K pu eu + Kiu eu dt + K du
deu
dt
(6)
S2
S4
The zonal scheme is shown in Fig. 7 for a sinusoidal reference voltage with zones and hysteresis band. The controller is
assumed to be in Zone-1 when the error is large and it is in
Zone-2, when the error is small (within the hysteresis band).
In Zone-1, the control decision is made based on filter inductor current. When the error reduces as a result of the control
action of Zone-1, the controller switches to Zone-2, where the
decision will be made depending on filter capacitor voltage.
However, in both the zones, all three states (+1, -1 and 0) of
converter are used based upon the reference voltage. In + 1
state, the converter output becomes + Vdc, which is achieved
by turning on the switches S1 and S4 and turning off the
switches S2 and S3 of Fig. 6. Similarly in 1 state, the converter output becomes Vdc that can be achieved by turning on
the switches S2 and S3 and turning off the switches S1 and S4.
Usually the 0-state is defined when output voltage of converter
is 0 V which is achieved by closing the pair S1-S2 or S3- S4.
if i f i f + h
elseif i f i f h
then
then
(7)
u = 1
u =1
(8)
Real Power
Load
Source
UPS
3.5
3
2.5
Power (MW)
1
(vt u vdc )
Lf 1
2
1.5
1
0.5
0
-0.5
0
0.05
0.1
Time (s)
0.15
0.2
0.25
(a)
Error in Real Power
0.12
0.1
0.08
Error (MW)
dt
0.06
0.04
0.02
0
0
0.05
0.1
Time (s)
0.15
0.2
0.25
(b)
0.4
0.3
0.2
Current (kA)
di f
0.1
0
-0.1
-0.2
-0.3
-0.4
0
0.05
Time (s)
0.1
0.15
(c)
Power (MW)
0
0
0.1
Time (s)
0.2
0.25
(d)
Fig. 8. Performance of UPS in torn network.
Load
Source
UPS
4.5
4
Power (MW)
3.5
3
2.5
(a)
2
0.5
1.5
0.14
0.16
0.18
0.2
Time (s)
0.22
0.24
0.3
0.26
0.2
Current (kA)
(a)
Error in Real Power
0.1
0.1
0
-0.1
-0.2
-0.3
0.09
Error (MW)
Actual
Reference
0.4
-0.4
0.08
-0.5
0.16
0.18
0.2
0.22
0.24
Time (s)
0.07
0.26
0.28
0.3
(b)
0.06
0.05
3.5
0.2
Time (s)
0.25
0.3
(b)
Fig. 9 Performance of UPS during load change in torn network
Power (MW)
0.15
2.5
Torn Network
Actual Network
2
1.5
1
0.5
0
0.15
0.2
0.25
Time (s)
0.3
0.35
0.4
(c)
Fig. 10. Performance evolution during sag.
Real Power
4.5
Load
Source
UPS
4
3.5
3
2.5
2
1.5
1
0.2
0.25
0.3
0.35
0.4
0.45
0.5
0.55
Time (s)
(a)
Real Power
4
3.5
Torn Network
Actual Network
Power (MW)
0.04
2.5
2
1.5
1
0.5
0
0.2
0.25
0.3
0.35
Time (s)
0.4
(b)
Fig. 11. Performance evolution during Mode-2 operation.
0.45
0.5
........ Reference
_____ Torn network
2.5
Power (MW)
2
UPS Power
1.5
Source Power
1
Mode Change
0.5
0
0.15
0.2
0.25
0.3
Time (s)
0.35
(a)
UPS Power
4
Torn Network
Actual Network (Reference)
3.5
Phase A Voltage
10
CB Opens
2.5
Voltage (kV)
Power (MW)
Torn Network
Actual
1.5
1
2
0
-2
-4
0.5
-6
0
0.15
0.2
0.25
0.3
Time (s)
0.35
-8
-10
(b)
Fault Occurence
0.13
0.15
0.4
0.19
0.21
(a)
Actual
Reference
0.3
0.17
Time (s)
Torn N/W
Actual
0.5
0.1
Current (kA)
Current (kA)
0.2
0
-0.1
-0.2
-0.5
-0.3
-1
-0.4
0.16
0.18
0.2
0.22
0.24
Time (s)
0.26
0.28
0.3
0.32
(c)
Fig. 13. UPS performance during utility feeder change.
-1.5
0.15
0.16
0.17
Time (s)
(b)
Fig. 15 Fault evolution using torn network
0.18
0.19
0.2
R. Kuffel et al, RTDS a fully digital power system simulator operating in real-time, Digital Power System Simulators, ICDS95, 1995.
[2] G. Sybille and P. Giroux, Simulation of FACTS controllers using the
MATLAB power system blockset and Hypersim real-time simulator,
IEE PES Panel Session on Digital Simulations of FACTS and Custom
Power Controllers, Winter Meeting, New York, 2002.
[3] C. A. Rabbath, M. Abdoune and J. Belanger, Effective real-time simulations of event-based systems, Proceedings of the 2000 Winter Simulation Conference, 2000.
[4] C. Zhang, V. K. Vijapurapu, A. K. Srivastava, N. N. Schulz and J.
Bastos, Hardware-in-the-Loop Simulation of Distance Relay Using
RTDS, Summer Computer Simulation Conference, San Diego, California, pp. 149-154, 2007.
[5] S. Goyal, A. Ghosh and G. Ledwich, Active Power Flow Control in a
Distribution System Using Discontinuous Voltage Controller, Electrical Power Systems Research, 2008.
[6] G. Kron, Tensor Analysis of Networks, John Wiley, N.Y., 1939.
[7] B. Han, B. Bae and Y. Jeong, Load simulator with power recovery
capability based on voltage source converter-inverter set, Proc. IEE
Electric Power Application, Vol. 153, No. 6, pp. 891-897, 2006.
[8] L. S. Czamecki, G. Chen, H. Ginn and J. Hu, Phantom Load: A Simulator of Non-Periodic Currents, IEEE PES Summer Meeting, Seattle,
USA, pp. 988-993, 2000.
[9] I. Ando, I. Takahashi, Y. Tanaka and M. Ikehara, Electric Load Controlled by Computer Simulator having Power Regeneration Ability,
Power Conversion Conference, Nagaoka, Vol. 2, pp. 925-930, 1997.
[10] S. Goyal, A. Ghosh and G. Ledwich, A Hybrid Discontinuous Voltage
Controller for DSTATCOM Applications, IEEE PES General Meeting,
USA, 2008.
[11] A. Ghosh and G. Ledwich, "Load compensating DSTATCOM in weak
AC Systems," IEEE Transaction on Power Delivery, vol. 18, pp. 13021309, October 2003