Noi Bai International Airport Terminal 2, Ha Noi, Vietnam
Engineer:
JAC Japanese Airport Consultant
Main Contractor:
TVJV Taisei Vinaconex Joint Venture
Foundation Contractor:
BAUER Vietnam Limited
Scope of Works:
256 nos. of Bored Piles 800, 1200, 1500mm
Construction Period:
From June 2012 to August 2012
Main Equipment:
1nos BG 40 Drilling Rig & 1nos BG 28 Drilling Rig
BAUER Asia Pacific Network
APN_BVN 2012/168
NOI BAI INTERNATIONAL AIRPORT
TERMINATION 2 CONSTRUCTION PROJECT HA NOI, VIETNAM PURPOSE OF WORKS Due to the existing Noi Bai International Airport already surpassing its designed capacity in 2007, the construction of passenger terminal 2 of Noi Bai international airport which is capable to accommodate 10 million international passengers per annum is one of the most important transport infrastructure projects being implemented in order to contribute to the economic and social development of Hanoi and all Vietnam.
Foundation of the building consists of bored piles
with diameter varying from 800 to 1500mm and length varying from 25 to 40m. CONSTRUCTION WORKS & SPECIAL FEATURES
The terminal 2 is a 4-storied international passenger
terminal building with floor area of approximately 139,216 m2, fully equipped with electro-mechanical and other facilities was awarded to Taisei-Vinaconex Joint Venture. Due to the piling package tight construction schedule, the package was divided between two subcontractors. Bauer Vietnam Ltd. has been awarded as specialist subcontractor for more than 50% of foundation works for the main building and the east-wing building consisting of 256 bored piles.
One high performance drilling rigs model BG 40 and
one smaller model BG 28 have been deployed to optimize of the overall performance, whereas the other subcontractor on this Project utilise an assortment of eight different drilling rigs for the works. Bauer with the appropriate equipment and tools, an experienced site team has also been deployed together with well planning and strong logistics, managed to complete our whole works including all variations well ahead of the contract schedule helping the Main Contractor to recover their loss time schedule caused by others.
SOIL / ROCK CONDITION
First 20m below ground level is mainly sandy clay following with eluvium derived from in-situ weathered rock and bed rock underneath. Design of this building adopted a one-column-onepile foundation system which requires a high capacity of pile in both vertical and horizontal. In consideration of that all the piles are designed to socket 6m in bed rock which is up to 20MPa in unconfined compressive strength.