Beruflich Dokumente
Kultur Dokumente
CLASSIFICATION OF
PART 4 CHAPTER 3
CONTENTS
Sec. 1
Sec. 2
Sec. 3
PAGE
A. General
This sub section has been expanded and introduces the concept
of system approval (as opposed to component approval). Particular attention has been given to system integration.
B. Design
The expanded design sub section has been added to better explain
and present the approval exercise in DNV. The main changes relate to the test requirements. Cycle-based testing including frequent start and stop sequences represents the improvement in
DNV's expertise towards gas turbine in-service operation for
new engines.
C. Inspection and testing
Production verification process and extent of manufacturing survey arrangement have been added.
D. Workshop testing
Cyclic loading has been introduced in the certification test requirements. Less stringent than type testing, certification testing
focuses on the operating profile each specific engine is intended
for.
E. Control, alarms, safety functions and indication
The list of control and alarms has been expanded and amended.
Furthermore the concept of availability, in addition to safety, has
been highlighted. Specific fire safety requirements have been introduced and strengthened.
F. Arrangement
Main changes
General
A200 and A300 have been expanded to cover the extent and
specification of required documentation.
B100 and B1602 have been extended to cover type testing for
highly rated engines.
In B200 bedplates and frame boxes have been considered with
regard to fatigue (welding).
In B500 requirements regarding power transmitting parts have
been added.
In B1200 requirements for turbochargers have been expanded
and amended.
In B1300 requirements regarding the auxiliary blower capacity
has been included for 2-stroke engines.
In B1400 requirements concerning vibration dampers have been
included and extended.
In C201 an opening for reduced certification of parts for smaller
engines in MSAs has been introduced.
In items C200 and C300 the certification requirements for tie
rods and piston rods have been removed and the certification requirements for bolts, piston crowns, connecting rod, crosshead
and gear wheels have been reduced. The certification requirements for cylinder liners, bedplates and frameboxes have been
increased. Certification of turbochargers, when supplying cylinder groups of less than 2500 kW, have been reduced from NV to
Covering both quay and sea trials, this sub section is designed to
verify system integration and control system behaviour. The general test requirements are the same as those defined in B.
If any person suffers loss or damage which is proved to have been caused by any negligent act or omission of Det Norske Veritas, then Det Norske Veritas shall pay compensation to such person
for his proved direct loss or damage. However, the compensation shall not exceed an amount equal to ten times the fee charged for the service in question, provided that the maximum compensation shall never exceed USD 2 million.
In this provision "Det Norske Veritas" shall mean the Foundation Det Norske Veritas as well as all its subsidiaries, directors, officers, employees, agents and any other acting on behalf of Det
Norske Veritas.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Contents Page 3
CONTENTS
SEC. 1 DIESEL ENGINES .............................................. 5
A. General...................................................................................5
A
A
A
A
A
100
200
300
400
500
Application........................................................................5
Documentation of the engine ............................................5
Additional documentation of propulsion engines .............7
Documentation of arrangement.........................................7
Documentation of vibration ..............................................7
B. Design .....................................................................................8
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
1600
1700
1800
General ..............................................................................8
Structural components ......................................................9
Safety valves and crankcase ventilation............................9
Bolt connections................................................................9
Power transmitting parts ...................................................9
Hydraulic valve operation...............................................10
Fuel oil system ................................................................10
Charge air system and cooler..........................................10
Starting air system...........................................................10
Lubrication ......................................................................10
Fire protection .................................................................10
Turbocharger...................................................................10
Auxiliary blower .............................................................11
Vibration dampers...........................................................11
Type testing.....................................................................11
Type testing data collection ............................................12
Type testing program ......................................................12
Type testing of engines for high speed, light craft and
naval surface craft ...........................................................13
100
200
300
400
General ............................................................................14
Certification of parts .......................................................14
Testing and inspection of parts .......................................14
Inspection during assembly.............................................16
100
200
300
400
500
Application......................................................................16
General engine tests ........................................................16
Testing of propulsion engines.........................................16
Testing of engines for auxiliary generating sets .............17
Opening up after testing..................................................17
100
200
300
400
500
600
General ............................................................................17
Speed governing..............................................................17
Overspeed protection ......................................................17
Instrumentation and alarms for propulsion engines........17
Speed governing of diesel generator sets........................18
Instrumentation and alarms on auxiliary engines ...........18
F. Arrangement........................................................................19
F
F
F
F
F
F
100
200
300
400
500
600
G. Vibration ..............................................................................20
G
G
G
G
G
G
100
200
300
400
500
600
H. Installation Inspections.......................................................24
H
H
H
H
H
100
200
300
400
500
Application......................................................................24
Assembling of engines supplied in sections ...................24
Alignment and foundation ..............................................24
Resiliently mounted engines ...........................................24
Fuel, lubrication and cooling systems.............................24
100
Application......................................................................25
I
I
I
I
I
I
I
I
200
300
400
500
600
700
800
900
400
500
600
700
800
Application......................................................................27
Documentation................................................................27
Additional documentation for gas fuel arrangement (e.g.
for mobile offshore units) ............................................... 28
Documentation of vibration analysis (core and system).29
Documentation of arrangement.......................................30
Documentation of production verification...................... 31
Documentation of control systems..................................31
Documentation of fire safety ..........................................31
B. Design .................................................................................. 31
B
B
B
B
B
B
B
B
B
B
100
200
300
400
500
600
700
800
900
1000
General ............................................................................31
Structural components .................................................... 32
Component design requirements.....................................32
Engine testing and type testing .......................................39
General requirements for engine test .............................. 39
Engine test data collection .............................................. 40
Power measurement ........................................................40
Type testing, general....................................................... 40
Type testing program ......................................................41
Boroscope inspection and tear-down after testing ..........43
General ............................................................................43
Certification of parts ....................................................... 43
Production verification.................................................... 43
100
200
300
400
500
Application......................................................................43
Certification testing......................................................... 44
Certification testing of propulsion engines .....................44
Certification testing of engines for generating sets.........44
Boroscope inspection ......................................................45
100
200
300
400
500
F. Arrangement....................................................................... 46
F
F
F
F
F
F
F
F
100
200
300
400
500
600
700
800
F 900
G. Vibration ............................................................................. 49
G 100
G 200
G 300
General ............................................................................49
Analysis...........................................................................49
Tests and measurements ................................................. 49
H. Installation Inspections...................................................... 49
H
H
H
H
100
200
300
400
Application......................................................................49
Assembly of gas turbines supplied in modules...............49
Alignment and foundation .............................................. 49
Inlet and outlet passages ................................................. 50
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Contents Page 4
H 500
H 600
H 700
H 800
B 200
B 300
C. Arrangement ....................................................................... 52
C 100
C 200
I. Shipboard Testing............................................................... 50
I
I
I
100
200
300
Quay trial.........................................................................50
Sea trial ...........................................................................50
Boroscope inspection ......................................................51
Application......................................................................52
Documentation ................................................................52
General ............................................................................52
Design .............................................................................53
100
200
300
400
General ............................................................................53
Propulsion steam turbines ...............................................53
Auxiliary steam turbines .................................................53
Monitoring ......................................................................53
F. Testing On Board................................................................ 54
F 100
F 200
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 5
SECTION 1
DIESEL ENGINES
A. General
A 100 Application
101 This section covers requirements applicable to diesel engines above 200 kW subject to certification, see Ch.2 Sec.1
and Sec.2, as well as the engine installation and shipboard testing. For diesel engines with power less than 200 kW, IMO and
SOLAS requirements will still apply, see B800 and B1200. Installations intended for running on crude oil or gas will be especially considered, see Pt.6 Ch.13.
102 The rules in B to E apply to the diesel engine, its components and its internal systems. The rules in F to I apply to the
installation of the engine, the engine and its system dynamics
(which is influenced by the engine), and the shipboard testing.
103 The diesel engine is to be delivered with a NV certificate
that is based on the component certification in C and the workshop testing in D.
104 Fig.1 shows the certification process for a diesel engine
where the manufacturer is a licensee or producer of own design.
A licensee can apply for type approval or case by case approval
when a design assessment has been issued and a type test has
been carried out. This principle also applies for turbochargers
and torsional vibration dampers produced under licence.
A licensee does not have to carry out a new type test for engines, turbochargers and dampers produced under license
when the licenser has already carried out a type test.
A 200 Documentation of the engine
201 Drawings, data, specifications, calculations and other information are to be submitted as applicable according to Table
A1 (except for items covered by a type approval) where:
A
I
UR
NDT
=
=
=
=
*)
Fig. 1
Flow chart showing the certification process for diesel engines
for approval
for information
upon request
non-destructive testing.
Table A1 Documentation
Component
Drawings
Material
specification
Calculations
I
I
A
UR
UR
Engine block
Main and crankpin bearings
Thrust bearing and structure 1)
I
I
A
I
I
A
Tie rod
Crankcase safety valve arrangement
Cylinder head
I
A
I
Miscellaneous
Reference to
design
requirements
See B200
See B200
See B200
See 301
See 302
Welding procedure specification, see 204
A
See B300
NDT specification if cast for crosshead engines
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 6
Material
specification
Calculations
Cylinder liner
Piston complete
Piston rod
Crosshead complete including guides
Connecting rod
Connecting rod bolts
Crankshaft
I
I
I
A
A
A
I
I
I
A
A
A
UR
UR
Crankshaft bolts
UR
Thrust shaft
Torsional vibration damper
Axial vibration damper
Camshaft drive assembly
Gear wheels for camshaft drive
Camshaft
Cams and cam rollers
High pressure parts for fuel oil injection system
Electronic injection system
Fuel oil system 3)
Shielding of fuel pipes
Hydraulic system for valve lift
Exhaust valve
Inlet valve
Turbocharger
Auxiliary blower arrangement
Exhaust pipes, shielding
Starting air system 3)
Charge air system 3)
Lubrication oil system 3)
Cooling water system 3)
Safety and control system including
alarm list
Speed governing system
Monitoring system
Maintenance and Operation manual 5)
A
A
I
I
I
I
I
A
I (of bolts if
applicable)
A
A
A2)
A
A
A
I
I
TA
A
A
A
A
A
I
A
Miscellaneous
NDT specification if propulsion
engine
NDT specification upon request
NDT specification upon request
Alignment specification
NDT specification
NDT specification
allowable deflections
alignment specification
See B509
See B508
See B400
See B502 to B506
See B400 and
B507
See B1400
See B1400
I
I
I
I
See B700
Shielding
I
I
TA
Reference to
design
requirements
See B1300
See B700
See B700
See B601
See B1200
See B1300
See B1100
See B900
See B800
See B1000
See B300 and E
A4)
A
I
See E
See E
Including maintenance schedule for
the complete engine
1)
Applicable when the engine thrust bearing is the main thrust bearing for the complete shafting system (taking propeller thrust).
2)
3)
4)
5)
This applies for design assessments, type approvals and case-by-case approvals if no design assessment or type approval is issued.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 7
f)
c) Axial vibration calculations. This applies only when requested by the Society.
Guidance note:
Requests for axial vibration calculations are normally made
when:
1)
2)
302 For engines with integrated main thrust bearing the maximum permissible wear is to be submitted for information unless given in the maintenance manual.
303 Engines driving generators in diesel electric propulsion
systems are defined as propulsion engines.
A 400
Documentation of arrangement
401 The following plans and specifications are to be submitted (normally by the yard):
a) Engine fastening arrangement with bolts, pre-stress,
epoxy (including calculations) or metallic chocks (see
F200), if applicable.
b) Top stay arrangement, if applicable, including reaction
forces (see F205).
c) Resilient mounts (to be type approved, see F300), if applicable.
d) For resiliently mounted engines, arrangement of exhaust
piping and all flexible piping. This also applies to diesel
generator sets mounted on a frame that is resiliently
mounted.
e) Frame (skid) for engines and generators mounted on a
frame that is resiliently mounted.
d) Engine vibration calculations. This applies to all resiliently mounted engines except to engine-generator sets where
the engine and generator are rigidly mounted on a common frame and the frame is resiliently mounted.
502
The conclusion is to be based on a comparison between calculated dynamic response and the permissible values for all the
sensitive parts in the plant.
503 In all kinds of torsional vibration calculations the variation of essential data such as dynamic characteristics of elastic
couplings and dampers is to be considered, see Ch.2 Sec.3
A101. Especially rubber couplings and certain types of vibration dampers have wide tolerances of stiffness and damping. It
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 8
is normally not required to perform calculations with all combinations of these extreme data, but as a minimum the influence of such wide tolerances is to be qualitatively considered
and also addressed in the conclusions.
For couplings having stiffness with strong dependency on vibratory torque and mean torque and temperature (as a consequence of power loss) it may be required to carry out either
iterative direct calculations or simulation calculation where
these dependencies are included.
504 In vibration calculations the source of all essential data
is to be listed. For data that cannot be given as constant parameters (see for example 503), the assumed parameter dependency and tolerance range is to be specified.
505 In connection with torsional vibration calculations the
following may be requested:
type of speed governor
position of speed sensor.
506 Measurements and analysis of camshaft and gear drive
vibration may be required if service experience with this or
similar engine types indicate excessive vibration. If the type
test engine has a considerably lower number of cylinders than
the maximum number for that engine type, this test requirement may be postponed to the sea trial testing of the first engine with the high number of cylinders.
Guidance note:
It is desirable to minimise the extent of documentation of vibration as given in 500 for the actual plants.
This can be achieved by e.g.:
a)
System type approval, see Ch.2 Sec.2. For example: 1) Resiliently mounted engines where standard mounts are used
and all connections (including the drive coupling) are made
so flexible that they have no influence on the vibration, may
be covered by a system type approval. 2) Engines which use
a limited number of elastic couplings, generators, gearboxes, shafting lengths, propellers, water jets etc. may be suitable for system type approval.
b)
Including the crankshaft vibration in the engines type approval. For engines where the crankshaft stresses are practically independent of the driven system, i.e. engines that are
generally fitted with an elastic coupling, it is advised to have
both axial (if necessary) and torsional vibration included in
the type approval. Thus, this part of the torsional vibration
need not be submitted for the actual applications. Such torsional vibration calculations are to be made with the maximum relevant engine load in the whole actual speed range.
Misfiring (no fuel injection) of one cylinder is also to be
considered. For this purpose, the worst cylinder is to be selected, see G301 d).
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
B. Design
B 100
General
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 9
the engine has been case by case approved and has proven
reliability in service, for example more than 2500 running
hours.
Guidance note:
The net gas volume is equal to the volume confined by the crankcase minus the volume of moving parts such as crankshaft, connection rod and cross head.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
B 200
Structural components
201 Bedplates, framebox, columns and crankcases with integrated parts as crankcase doors are defined as structural components.
202 All welds in bedplates, frameboxes and columns are to
be designed to avoid fatigue cracking due to the stresses in operation. Full penetration welds are to be applied in the most fatigue exposed areas. Such areas are in particular those near the
main and thrust bearings.
203 If partial penetration welds are applied in the most fatigue exposed areas, the weld dimensions including the maximum nose (root gap) is to be clearly defined. In addition, it is
to be documented that the stated nose is acceptable.
Documentation of this may be based on relevant tests, service
experience or by means of fracture mechanics calculations
where the nominal stresses are found by e.g. finite element calculations.
The threshold value for crack propagation is to be taken as 2
(MPam), unless another value can be documented.
B 300
301
Separate spaces that are not in open connection to the crankcase such as
gear and chain case etc.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 10
802 In 2-stroke engines, charge air spaces in open connection to the cylinders are to be fitted with:
903 The pipes and valves, including the non-return valve, are
to be designed to withstand the possible back pressure if a
starting valve remains open.
B 1000 Lubrication
1001 The lubrication oil pump intakes are to be arranged to
ensure that no air suction takes place under the worst operating
conditions such as maximum list, roll, pitching etc. as defined
in Ch.1 Sec.3 B.
B 1100 Fire protection
1101 All exposed surfaces are to be kept below the maximum permissible temperature given in Ch.1 Sec.3.
Surfaces that reach higher temperatures are to be insulated or
equivalently protected so that flammable fluids hitting the surface cannot be ignited.
B 1200 Turbocharger
1201 Turbochargers are to be type approved (see also A104)
based on:
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 11
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 12
been informed about the nature and extent of investigations carried out during the pre-production stages.
engine r.p.m.
torque
maximum combustion pressure for each cylinder
compression pressure
mean indicated pressure for each cylinder
lubrication oil pressure and temperature
cooling water pressure and temperatures
exhaust gas temperature before and after turbine and,
where required (see E400 and E600), from each cylinder.
To be measured also if installed due to manufacturers minimum sensor delivery
exhaust gas pressure before turbine
r.p.m. of turbocharger (applicable when the turbocharger
serves a group of cylinders > 1 000 kW)
charging air pressure
charging air temperature before and after cooler
jacket cooling temperature
piston cooling temperature (in case of separate cooling
medium).
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 13
Fig. 2
Load points
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 14
General
Certification of parts
201 Engine parts, semi-products or materials are to be documented according to Table C1 and 300 if not otherwise agreed.
This applies independent of being supplied by subcontractors
or produced by the engine manufacturer. In 300 the inspection
and testing mentioned in Table C1 are described in more detail.
The extent in Table C1 may be reduced according to an agreement with the manufacturer. This agreement should preferably
be arranged in connection with type approval of the engine,
and be settled in a MSA.
Guidance note:
Spare parts for ships in operation:
For general principles, see Ch.2 Sec.2 A102 (Guidance note).
In addition the following requirements should apply for diesel
engines:
To item 2:
The actual part should be produced by a manufacturer authorised by the engine designer or the designer's licensee.
305 Crankshaft bolts (between crankshaft parts) and connecting rod bolts are to be tested, inspected and documented
with regard to:
chemical composition of the material
mechanical properties
crack detection.
306 Crankshafts are to be tested, inspected and documented
with regard to:
To item 3:
If the part is produced by a manufacturer not authorised by
the engine designer or the designer's licensee, DNV may
carry out inspections according to Table C1 and issue a report confirming this. However, this inspection report will
not cover design approval and testing as a part of the engine.
It is the operator's responsibility to evaluate and take the
necessary precautions to see that the parts are fit for their intended use.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
C 300
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 15
All
NV when
> 2500 kW
W when
< 2500 kW
Crack
detection 1)
NV 2)
NV 2)
Hydraulic
testing
Dimensional
inspection
Other
See 302
See 302
W
TR
See 303
See 304
See 303
See 303
See 305
W
W
W
NV
W
NV
W
W
W 3)
W
See 309
See 309
W4)
W6)
See 310
W (water
side)
See 311
TR
TR 2)
Rotating
parts: NV
when
> 2500 kW,
W when
< 2500 kW
NV
TR 2)
See 306
See 307
See 307
See 308
See 312
W
NV if caseby-case approved
See 313
See 314
2)
3)
If cast.
4)
5)
6)
Of complete piston.
312 Fuel oil piping (high pressure, return pipes and low pressure) is to be tested, inspected and documented with regard to:
Ultrasonic
testing
W
For common rail systems the above requirements are also valid
for the control oil side.
313 Turbochargers supplying groups of cylinders in excess
of 1000 kW are to be tested, inspected and documented with
regard to:
chemical composition of the material of rotating parts 1)
mechanical properties of the material of a representative
specimen for the rotating parts1) or, in special cases, documentation of heat treatment (temperature time diagrams)
NDT of rotating parts 1) (upon request)
crack detection
dimensional inspection of rotating parts 1) (before assembly)
dynamic balancing of rotating parts 1) separately as well as
complete rotating assembly
overspeed test 2) of all compressor wheels with a duration
of 3 minutes at 20% above the maximum speed at room
temperature, or 10% above the maximum speed at maximum permissible temperature
compressor chart.
In addition, the following test to be carried out:
Running test for each unit during 20 minutes at maximum
speed and ambient temperature.
If the turbocharger can be tested on the engine for which it is
intended for, the running test can be replaced by a test run of
20 minutes at an overload corresponding to 110% of maximum
continuous rating for the applicable engine.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 16
1)
2)
If each forged compressor wheel is individually controlled by an approved non-destructive method, the overspeed test may be waived except
for the wheel of the type test unit. For wheels without a bore, the overspeed test may be omitted.
D. Workshop Testing
D 100 Application
101 All relevant equipment for safety of personnel is to be
operational during the workshop testing.
102 Each engine to be certified shall be tested in the workshop. The purpose of the workshop testing is to verify the design premises such as performance, safety (against fire),
adherence to maximum pressure, functionality, product quality
and further to establish reference values or base lines for later
reference in the operational phase.
103 For case by case approved engines the workshop testing
may be extended up to the full type testing if found necessary
by the Society.
104 The engine manufacturer is to compile all results in a test
protocol that is to be signed by the attending surveyor and submit it to the Society for later reference.
105 After the required workshop testing, engines are to be
blocked for output beyond the approved maximum rating, i.e.
either the maximum continuous rating or the specified overload permitted for intermittent use. The setting of the blocking
is to be made as applicable for the intended fuel. i.e. if an engine is intended for running on heavy fuel oil during the sea trial, the blocking after a workshop test on light diesel oil is to be
set in accordance with the theoretical correlation between
these fuel oils. If the sea trial full load testing will be made on
light diesel oil, and the service is intended for heavy fuel oil,
the blocking is to be made after the sea trial testing.
D 200 General engine tests
201 All measurements at the various ratings are to be made
at steady operating conditions unless otherwise stated.
202 The following external particulars are to be recorded:
203 The measured maximum pressures, exhaust temperatures, charge air pressure and compression pressures are to be
corrected to ISO conditions. This is to enable comparisons
with approved values and measurements in the operation
phase.
204 As a minimum the engine is to be run for 30 minutes at
its maximum continuous rating.
205 Unless otherwise approved, the maximum pressure is to
be recorded for each cylinder at maximum continuous rating.
It shall not exceed the maximum permissible value nor vary
more than permitted by the engine designer, alternatively 3%
of the maximum permissible value where no design specification applies.
206 During testing, the engine is to be checked visually for
leakage of fuel and lubrication oils.
207 The turbocharger system is to be checked with fuel shut
off (misfiring) in one cylinder when running at the maximum
permissible load for misfiring condition. There is not to be any
continuous surging. See B1205. This test may be waived if
successfully tested on identical engine and turbocharger.
208 The safety systems to the extent as integrated in the engine design, is to be tested (e.g. a mechanical overspeed trip
device).
D 300 Testing of propulsion engines
301 The testing described in 300 apply to propulsion engines
in addition to 200.
302 The engine is to be tested at the following power levels
(given in percentage of MCR):
50%, 75%, 90%, 100% and 110%, according to the following
(whichever is applicable):
a) The propeller curve based on the propeller law
This applies if driving a fixed pitch propeller, water jet or controllable pitch propeller with variable r.p.m. and pitch limited
(or permitted) to nominal value.
Or:
b) The modified propeller curve
This applies if driving a controllable pitch propeller that
is intended to use a higher pitch than the nominal when
running at reduced r.p.m. In this case, the load point with
lowest r.p.m. at 100% of maximum continuous rated
torque is to be added
has a combinator pitch control using reduced pitch at lower speeds. In this case the pitch limitations have to be stated on a signboard for the purpose of manual operation.
Or:
c) At constant speed
This applies if driving a controllable pitch propeller with constant speed or a generator for propulsion.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 17
The operating time per load point depends on the engine size
(achievement of steady state condition) and on the time for collection of the operating values. Normally, an operating time of
0.5 to 1 hour can be assumed per load point.
303 For HS, LC and NSC the test point at 110% of maximum
continuous rating is replaced with a test point 10% (of the maximum continuous power) above the specified overload permitted for intermittent use.
304 At the power levels specified in 302 the following data
is to be recorded:
501 If nothing else is specified in a manufacturing survey arrangement, the requirements in 502 to 505 apply.
502
General
Speed governing
201 All engines are to be fitted with a speed governor so adjusted that the engine speed cannot continuously exceed the
rated speed by more than 10%.
E 300
Overspeed protection
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 18
sion. Instrumentation and alarms are required according to Table E1 if not otherwise approved.
Table E1 Instrumentation and alarms for propulsion engines
Valid
for
engine
type 1)
System
Item
Engine
R.p.m.
C, T
R.p.m. 3)
C, T
C, T
Turbocharger
Scavenge air
Exhaust gas
Fuel oil
Double and
shielded pipes
Cylinder cooling medium
Piston cooling
medium
Lubrication of
bearings
Crankcase explosive conditions 7)
Main thrust
bearing
Chain tension
Indication
Alarm at
level 1
C, T
C, T
Local
Remote
Remote
Local
Remote
Local
Remote
Remote
Remote
C, T
Remote
Large deviation
C, T
Remote
Low
C, T
Receiver temperature
C, T
High
If separate, forced
lubrication
Low
High
High
High
X
X
X
Remote
Low 6)
C, T
Remote
High
C, T
C, T
Crankcase protection 8)
C, T
Local
Remote
Local
Remote
Local
Remote
Local
Remote
Local
Remote
Low 6)
Low
High
Low 6)
X and
shutdown
Local
Remote
High
Remote
High
Local
Remote
2)
Action means either slow down (r.p.m. reduction) or load reduction (e.g. pitch reduction), whichever is relevant.
Applicable when the turbocharger serves a group of cylinders > 1000 kW.
4)
Low
1)
3)
Fire detection
Leakage
C, T
Position feeler
Engine overspeed protection
Action 2)
with
Comments
alarm at
level 2
If applicable
Slow down or shutdown
5)
6)
7)
8)
For trunk engines: a) Oil mist concentration or b) Temperature monitoring of main- and crank bearings or c) Oil splash temperature deviation or d) Crank
case pressure combined with metal particle detection (shunt to filter)
For crosshead engines: a) Oil mist concentration or b) Temperature monitoring of main-, crank- and crosshead bearings, plus pressure monitoring of crankcase. Pressure monitoring in each crankcase compartment if separated. Metal particle detector (shunt to filter) may be accepted as alternative to pressure
monitoring.
9)
If individual stop valves are fitted for the cylinder jackets. Otherwise main outlet.
E 500
E 600
501 For requirements concerning the speed governing of diesel generator sets, see Ch.2 Sec.6.
601 Instrumentation and alarms for auxiliary engines are required according to Table E2 if not otherwise approved.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 19
Item
Engine
R.p.m.
Turbocharger
R.p.m. 2)
Exhaust gas temperature before turbine 3)
Exhaust temperature each cylinder 4)
Exhaust temperature each cylinder, deviation from
average 4)
Leakage, all double and shielded pipes for fuel and
valve operation
Cooling water outlet temperature
Exhaust gas
Double and
shielded pipes
Indication
Local
Remote
Remote
Remote
Remote
Remote
Alarm at
level 1
High
High
High
Large deviation
Leakage
Remote
High
Remote
Low
Local
Remote
Local Remote
Low
X
Automatic start of
standby pump, if
available
High
Local Remote
Low
Crankcase protection 6)
Local
Remote
High
Remote
Action 1) with
alarm at level Comments
2
Automatic start of
X
standby pump, if
and shutdown
available
X
X
Slow-down or shutdown
1)
Action means either automatic slow down (r.p.m. reduction, when not driving a generator) or load reduction, whichever is relevant.
2)
Applicable when the turbocharger serves a group of cylinders > 1000 kW.
3)
4)
5)
6)
Either a) Oil mist concentration or b) Temperature monitoring of main- and crank bearings or c) Oil splash temperature deviation or d) Crank case pressure
combined with metal particle detection (shunt to filter).
F. Arrangement
F 100
101 Direct coupled engines are to be aligned so that the internal bearing reactions within the engine comply with the engine specification.
102 For engines driving generators with one bearing, the
common frame is to have a stiffness that fulfils the requirement
in 101 with regard to bearing reactions. Documentation is to be
submitted upon request.
103 For direct coupled propulsion engines the alignment
specification (see Ch.4 Sec.1 A402) may be required substantiated by shaft alignment calculations, see Ch.4 Sec.1 F400.
104 For engines with elastic couplings the alignment is to be
within the permissible values for the couplings under all relevant driving conditions. This is particularly important for resiliently mounted engines, see 300.
105 For engine plants with elastic coupling, universal joints,
spline connections, tooth couplings, etc. the reaction forces under all relevant driving conditions are to be considered. These
forces are to be within the limits specified by the engine manufacturer.
F 200
Rigid mounting
202 Metallic chocks are to be at least 20 mm thick. The accuracy of the fit between chocks and bedplate and foundation,
respectively, is to be better than 0.1 mm. Shims or combinations of shims and chocks are not acceptable.
203 The pre-tensioning of the holding down bolts is to be
specified with regard to tightening as well as the method. The
friction forces are to prevent dynamic movements between
bedplate and chocks and epoxy.
204 Side and end stoppers are normally required. They are
regarded as safety devices in case of relative movement between engine and foundation caused by loosened bolts. End
stoppers may be waived if fitted bolts or equivalent solutions
are used.
205 The securing of the engine top stays to the hull structure
is to be designed to avoid cracks at the fastening points.
F 300 Resilient mounting
301 All connections to the engine such as couplings, exhaust
pipes, fuel pipes, lubrication oil and cooling water connections
are to be designed for the maximum possible engine movements as limited by dual characteristic mounts or stoppers. For
determination of dynamic movements, see G600.
302 The elastic mounts are to be able to support the mass of
the engine, the reaction forces due to engine torque, the maximum environmental conditions as list and trim (see Ch.1 Sec.3
B200), and the dynamic loads (see G600) without exceeding
the approved specification.
303 The static positions of the engine on the elastic mounts
are to be calculated under consideration of the static loads given in 302.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 20
Exhaust pipes
401 Where exhaust pipes are led overboard near the water
line, means are to be provided to avoid the possibility of water
entering the engine.
402 Exhaust pipes from several engines are not to be connected, but are to have separate outlets, unless precautions are
taken to prevent the return of exhaust gases to a stopped engine.
F 500
501
(mean torque T). In such cases the mean torque used in various
fatigue criteria is to be replaced with the average torque.
502 The lubricating oil drain pipes from the engine sump to
the system tank are to be submerged at their outlet ends during
all operating conditions as defined in Ch.1. Drain pipes from
different engines are to be laid independently of each other in
order to avoid intercommunication between crankcases.
F 600
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
G. Vibration
G 100
101
n0
n
T0
T
Tv
v
102
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 21
e) The normal operation, i.e. engines with a certain imbalance between the cylinders, is considered as a combination
of the ideal and the misfiring condition as:
TV = (TVmisfiring TVideal) z/24 + TVideal
z
= number of cylinders in the engine
f)
302
h) Propeller excitation can be taken as a percentage of the actual mean torque according to Table G1 unless other values are substantiated by the propeller manufacturer.
Table G1 Propeller excitation
Number of Blade frequency (%)
blades
3
8
4
6
5
4
6
4
i)
j)
Double blade
frequency (%)
2
2
1.5
1.5
Other excitation sources as water jet impeller pulses, universal joints (second order) etc. may have to be taken into
account in special cases.
The results of the forced torsional vibration calculations
are to be presented as relevant for the various components
in the system, see 303. If any result is close to the acceptance limit and there are uncertainties in the calculations,
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 22
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 23
Axial vibration
Note that the following is not always required, see also A501 c.
a) For engines with elastic coupling, the axial vibration, calculations may be restricted to the engine itself. For directcoupled engines, the whole plant is to be included.
b) As a minimum, the calculations are to include the natural
frequencies and mode shapes of the relevant vibration
modes. Coupled torsional and axial vibration may also be
required.
c) If the lowest vibration mode (with the node in the thrust
bearing) is of significance to the conclusion, the calculations are to be made with various thrust bearing stiffness
in order to see the influence of an estimation error.
d) If major critical resonance occurs near or in the operational speed range and no damper is foreseen, forced axial vibration calculations and measurements (see 200) will be
required.
502
Acceptance criteria
Engine vibration
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 24
602
Acceptance criteria
H. Installation Inspections
H 100 Application
101 The paragraphs in H apply to installation inspections of
diesel engines including the engine fastening, shaft connections and all piping to the engine. The alignment of intermediate shafts and elastic couplings is specified in Ch.4 Sec.1.
102 Unless otherwise stated, a surveyor is to attend the inspections given in H.
H 200 Assembling of engines supplied in sections
201 Crosshead engines
a) The bedplate alignment is to be carried out under stable
conditions. All welding in the engine room that may influence the alignment is to be finished. The temperatures are
to be stable.
b) The crankshaft deflections are to be checked as per manufacturers specifications.
c) The piston, piston rod and crosshead alignment are to be
recorded. These records are to be reviewed by the surveyor
and compared with the corresponding workshop records.
The results are to be within the designers tolerances.
c) Side and end stoppers and top stays (if applicable) are to
be checked according to the arrangement drawing. See
also F204 and F205.
d) The tightening of the holding down bolts is to be checked
versus approved specification.
H 400 Resiliently mounted engines
401 Resilient mounts
a) The engine mounts are to be checked as follows:
mounts are to be type approved
load distribution between mounts of same type (approximately equal deflection)
distance to stoppers (or second level if dual characteristic mounts) as approved.
The distance or clearance to the stoppers should be checked after some sink in of the rubber, e.g. one or two weeks after fully
loaded. Some further sink in should also be considered.
402 Engine connections
a) The coupling alignment should be checked after the sink
in of the rubber mounts. Alternatively, the adjustment may
be made under the assumption of a sink in based on experienced values.
b) All flexible pipes and hoses are to be:
type approved (for fuel and lubrication oil)
arranged so that in case of leakage no flammable fluid
can get in contact with hot surfaces
arranged to allow for the maximum possible engine
movements (i.e. reaching the stoppers) without restricting the engine movement. See guidance in Fig.1.
Fig. 3
Recommended arrangements of hoses and pipes
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 25
I. Shipboard Testing
I 100
I 400
Application
101 The paragraphs in I apply to all shipboard testing of diesel engines including vibration that are influenced by the diesel
engines.
I 500
I 200
201 The functioning of water drain from the charge air system is to be checked.
202 The functioning of the cylinder lubricators (when applicable) are to be randomly checked.
203 For the jacket cooling and the piston cooling (when applicable) medium temperatures are to be checked versus engine specifications.
204 The engine is to be checked for any leakage of fuel oil,
hydraulic oil or lubrication oil.
205 The suitability of the engine to burn residual or other
special fuels is to be demonstrated, if the machinery installation is arranged to burn such fuels.
206 If the sea trial full load testing is made on light diesel,
and the service is intended for heavy fuel, the mechanical
blocking of the fuel rack is to be made after sea trial testing.
The blocking is to limit the engine output to the approved value.
207 For engines to be run on heavy fuel, the maximum pressure is to be recorded for each cylinder at maximum continuous rating. It shall not exceed the maximum permissible value
nor vary more than permitted by the engine designer, alternatively 3% of the maximum permissible value where no design
specification applies.
208 Starting tests are to be made in order to document the required starting air energy capacity, see Ch.6 Sec.5.
209 The control, alarm and safety functions are to be tested,
see Table E1 and E2, except items integrated in the engine and
verified during the workshop test.
210 The temperature of hot surfaces is to be checked during
full load testing. Where surface temperatures exceed 220C,
insulation of oil non-absorbent material covered by sheet metal
is to be fitted. It is advised to use thermographic analyses for
documentation.
I 300
Axial vibration
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.1 Page 26
I 800
Engine vibration
801 For resiliently mounted engines the engine movements
are to be observed during the misfiring tests of the engine (torsional vibration), especially at full load. The engine is not to
reach contact with the stoppers, see F304. None of the engine
connections such as exhaust pipe compensators, cooling water
bellows, lubrication oil pipes, etc. are to restrict the engine
movements.
I 900
Opening up after testing
901 Unless otherwise approved, the following apply for all
kinds of engines:
a) One crankpin bearing is to be checked. In the case of serrations, a thorough check for fretting is to be carried out
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 27
SECTION 2
GAS TURBINES
A. General
A 100 Application
101 This section covers requirements applicable to gas turbines subject to certification, see Ch.2 Sec.1, as well as the engine installation and shipboard testing. These requirements
apply to conventional gas turbines used as propulsion engines
and driving auxiliaries, and are aimed at manufacturers, packagers, yards and operators.
102 The rules in this section apply to all gas turbines operating on liquid and or gaseous fuel. However, gas turbines operating on only liquid fuel do not need to comply with the
requirements specific to gaseous fuel operation (see F800 and
F900).
103 The rules apply for gas turbine packages.
104 The rules apply for mobile offshore units.
105 The rules apply for ships and high speed, light craft and
naval surface craft.
106 Subject to approval are the gas turbine with foundation,
ductwork, fuel and lubrication oil systems, other supporting
systems, control and monitoring systems and heat recovery
systems (if applicable).
107 Normally, gas turbines intended for propulsion, power
generation or any major functions such as gas compression,
water injection, etc, on DNV classed objects are to be type approved. This applies to engines of existing or modified designs, where documented service experiences is available for
the specific application, operating profile, and rating.
Novel, or new designs may receive a preliminary (time limited) design approval so as to allow initial operation. It is required that the manufacturer documents 2 500 hours of inservice experience of one unit, without major fault findings,
before the type approval certificate will be issued. The in-service experience should be relevant for the application that type
approval is applied for, with respect to working profile, and
rating. It is also a condition for type approval that the manufacturer has satisfied the following criteria:
Fig. 1
Type approval and certification process for the first engine
a) The engine has been thoroughly tested during the development phase.
b) The engine test program has been designed to cover uncertainties in the design analysis.
108 Fig.1 shows the type approval and certification processes for a gas turbine (first engine).
Fig.2 presents the certification process for subsequent type approved engines.
It is assumed that the following is in place:
type approval certificate
manufacturer survey arrangement (MSA) (see Ch.2 Sec.2
C100).
109 Where the rule requirements defined herein are not explicitly complied with, or documented, the Society will, upon
request, evaluate alternative and or equivalent solutions in accordance with Pt.1 Ch.1 Sec.1 B200.
Guidance note:
This implies e.g. that during the design assessment credit may be
given for extensive relevant operational experience, approval by
other recognised bodies such as CAA, FAA, etc.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
Fig. 2
Certification process for subsequent engines
A 200
Documentation
201 Drawings, data, specifications, calculations and other information are to be submitted as applicable according to Table
A1. Plans, analysis and particulars as listed below, as well as
in 400, 500 and 600, are to be submitted for all gas turbines.
Additional documentation for mobile offshore units is listed in
300. In addition, the Society might require complementary information when faced with unconventional designs, modifications, upgrading, and change in application, change in working
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 28
202 The drawings are to have clear references to the applicable material specification. When calculations are required see
201, these are to substantiate the requirements given in these
rules. In the case when NDT specifications are required, the acceptance criteria are to be included in the documentation.
203 When considering components that are of welded construction, and for repair welding, full details of seams are to be
given and relevant welding procedure specifications are to be
referred to on the drawings. In addition, the following are to be
specified:
filler metal particulars
heat treatment after welding
NDT with acceptance levels.
204 For the purpose of these rules, the following definitions
apply:
a) Maximum continuous output rating. The maximum power
level at which the engine has passed the engine type testing specified in B800.
b) Start-stop stress cycle consists of a mission cycle or an
equivalent representation of engine usage. It includes
starting the engine, accelerating to maximum rated power,
decelerating, and stopping.
c) Time between overhaul. This is the period which the engine is expected to run prior to removal for overhaul, assuming normal recommended shipboard maintenance
procedures have been followed, limiting pressures, temperatures and power ratings have not been exceeded and
lubricating (when applicable) and fuel oils specified in the
type approval certificate have been used.
d) Overhaul is normally to be accomplished at the engine
manufacturer's plant or at an OEM's approved plant. It
shall include disassembly, examination, cleaning and repair of the gas turbine engine and accessories.
e) OEM is original equipment manufacturer.
f)
205 When the design assessment conflicts with confidentiality and or proprietary issues, the review of the relevant documentation may be performed by the Society at the
manufacturer's premises, upon agreement between both parties.
a) Description of installation.
b) Arrangement of engine room installation.
A 300 Additional documentation for gas fuel arrangement (e.g. for mobile offshore units)
301 The following plans and particulars are to be submitted
for approval:
f)
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 29
g) Enclosures with details of flame detectors smoke detectors, gas detectors, and their locations. Enclosure drawings
and information including duration the enclosure can contain a fire (A-0, A-60 etc.).
Table A1 Documentation
Plans, analysis, particulars, specifications Drawings and
and components
specifications
General technical specifications
A
General arrangement of gas turbine
A
Section rotor assembly, including bearings
A
and shaft design
Section showing blade, and blade fastening
A
Seals with sealing arrangement
A
Blades
A
Impellers
A
Casing
A
Diffuser
A
Variable guide vanes, inlet guide vanes,
I
variable stator vanes
Bleed valves
I
Bearing, rolling element
A
Bearing, hydrodynamic
A
Bearing, thrust
A
Bearing housings
I
Tie rod
A
Rotors
A
Disks
A
Shafts
A
Combustor and flame tube
A
Burners
I
Turbine nozzles
A
Turbine internal air cooling system
A
Starting systems
A
1)
Turbine mounted piping
Lubricating oil system
I
Turbine fuel system
I
Fuel metering valves
UR
Fuel specification
I
Control system
A
Monitoring and instrumentation system
A
Safety system
A
Performance
I
FMEA
I
Fire prevention
A
Maintenance manuals
I
Operating manual
I
Test procedures
A
1)
A:
I:
UR:
Material
specification
Calculations
Miscellaneous
I
B302/B303
A
A
A
A
A
A
B303
B303
B304
B305
B306
B307
I
I
I
UR
A
A
A
I
UR
I
A
A
A
A
A
I
A
I
A
A
A
I
UR
I
I
B308
I
UR
B309
B310
B311
B312
B313
B314
B315
B316
B317
B318
B319
B320
B321
B322
B323
B324
B325
B326
B327
B328
B329
B330
B331
B332
B333
B334
B335
B336
1)
UR
UR
I
A
objectives
description of the method
conditions
assumptions
conclusion.
The conclusion is to be based on a comparison between calculated dynamic response and the permissible values for all the
sensitive parts in the engine or system.
403 In all vibration calculations the variation of essential
data such as dynamic characteristics of flexible couplings,
bearings, and foundations, are to be considered.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 30
gear induced excitation, such as mesh frequency, unbalance, and pitch line run-out
control system induced excitations
starting device excitation.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 31
i)
j)
The heat rejection curve of the turbine (heat rejection versus time for shutdown from full load) or equivalent shall
normally be provided.
Drawings indicating temperature profile on the skin and
casing of the gas turbine from intake to exhaust (maximum). This shall include bleed air piping, with the maximum temperature.
B. Design
B 100 General
101 For general design principles for machinery, see Ch.2
Sec.3. Special attention is to be given to A100.
102 The design and construction is to enable the gas turbine
to meet the general requirements, with regard to environmental
conditions, functional capability and to reliability and availability as given in 103.
The engine must be capable of withstanding environmentally
induced acceleration loads during operations. The manufacturer is to provide a two-dimensional design envelope made up of
what may be sustained during normal operation and what may
be experienced occasionally (e.g., storm conditions). The engine must not suffer unreasonable distortion (or stress) if these
loads are applied repeatedly. See also A408.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 32
108 Previously approved engines with an upgraded or modified design or up-rated operational parameters can be granted
approval with a reduced documentation scope, provided that
the engine:
Guidance note:
Example of design envelope diagram:
Structural components
See F200.
B 300
2)
Trip speed.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 33
302
General arrangement
compressor rotor
high pressure turbine rotor
power turbine rotor
bearings
seals
combustion chamber
blades
disks
guide vanes
shafts.
In the case that assembly drawings are not available as described, then sub-level drawings that give the same details will
be considered.
304 Blades
Blade documentation shall as a minimum contain the data required in this section.
Blade strength with respect to radial forces, gas pressure,
thermal loads, and creep
Blade strength with respect to centrifugal forces and gas pressure is to be documented by finite element analysis (FEM) or
equivalent methods. Analyses are to take into consideration
geometric stress raisers e.g. blade neck, fir-tree blade and disk
interface.
Blades fitted with interference are to document local pressure,
and analyses are to include combined stress.
Thermally loaded areas are to take into consideration local
hot spots; e.g. areas where boundary layers due to the rotating disk may form insulation against forced cooling air or the
blocking of cooling air due to other reasons. In the case of
blades with internal cooling passages, calculations are to include analysis at thinnest cross section, and thickest cross-section, and the consequence of loss of cooling medium (FMEA).
Normally only the following blades are required to be documented as representative of the different stages as applicable:
Documentation is to include dimensions, material specification, heat treatment specifications, cooling and coating. However, documentation of cooling and coating is only to indicate
presence, if applicable. Particulars, such as cooling hole patterns or coating composition, are not required. The stages
where cooled and coated blades are used shall be specified.
Vibration analysis
A sectional representation, incorporating the listed components, is preferred included in one drawing. However, if this is
not possible, several drawings may be used to give the same
general information. The drawings are to include the material
of the main components, and need have only overall dimensions such as casing dimensions, inlet diameter, compressor
rotor length, turbine rotor length, bearing spans etc. Production
drawings are not required.
In case the materials are manufacturer specific, the material
properties, as chemical composition, yield strength, elongation, fatigue properties etc. (relevant to the design review) are
to be supplied upon request.
first flexural
second flexural
first torsional
first edgewise.
Impellers
Impellers for radial compressors or turbines shall have documented evidence of its design (see 304). 3-D finite element
analysis or equivalent methods calculating the von Mises
stress of the complete impeller is required to be submitted for
assessment. Segments of the impeller, which take into consideration the impeller body, vanes, and the vane root, are also acceptable.
The analysis shall take into consideration the gas force, and its
distribution along the impeller vanes, as well as radial and thermal loads.
The analysis shall also predict the expected thrust forces at full
load.
Vibration models shall be such that they will depict the correct
mode shapes and frequencies (within uncertainty limits of verified measured frequency). This model shall then be used for
the stress calculations mentioned above.
Experimental or other means of correlating the calculated frequency and modes of vibration of the impeller should be submitted upon request. This is to prove that the model used is
accurate. This proof of correlation could be from other impellers, but using the same method and tools of computation. The
calculated frequency should be within the uncertainty limits of
the measured frequency.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 34
306 Casing
The gas turbine casing design shall be supported by an analysis, covering the most severe conditions of temperature and
pressure during operation. Overall buckling strength shall be
documented combining following loads:
The hoop-stress values seen in the design shall not exceed the
allowable values as required by international standards such as
ASME codes (Section VIII Division 1, the revision is that
which coincides with the validity of these rules).
Bolted flange design
Bolt pre-load calculations are to be submitted for information,
including thermal effects and fatigue considerations (Goodman diagram).
Containment and rotor failure
All the sections of the casing exposed to rotating parts, including power turbine casing, shall be capable of containing a projectile such as blades or parts thereof (minimum one blade for
axial units, in the case of a centrifugal impeller the parts from
one blade root failure), without catching fire and without failure of its mounting attachments.
Containment calculations or other methods are required to
document that casing integrity is maintained.
Such blade and impeller loss is not to result in consequential
loss of other components such as disk or rotor which will in
turn result in hazardous conditions for the vessel or its occupants. See also 314, 316 and 317.
Inspection openings
The design is to have features that permit boroscope inspection
or equivalent of the first stage in the compressor and the last
stage in the power turbine.
The engine is to accommodate features that permit inspection
of the combustors, and the compressor and turbine stages, such
as holes for boroscope inspection. Inspection procedures are to
be described in the operating instructions.
307 Diffusers
The following design documentation for diffusers shall be submitted for approval:
main drawings, describing major dimensions and materials.
Diffuser design shall upon request be supported by aerodynamic calculations. This includes:
wall angles
diffuser chart - area ratio vs. non-dimensional length
(straight walled conical diffuser only)
reaction forces on diffuser wall.
Guidance note:
The internal flow quality is assessed through the diffuser design
review and used for further study such as for instance, combustion process consideration.
Diffuser efficiency, defined as follows:
2 ( p2 p1 )
- 100%
= -------------------------------------------2
2
1 [ 1 1/ AR ]
AR
tension
bending moment
shear
torque.
p1,2
Bleed valves shall be documented through drawings, indicating their position, and size.
The maximum and minimum flow rates of the valves shall be
specified in the documentation. The associated power loss of
the turbine shall also be documented.
The operation of the bleed valve shall not result in the poor performance of the compressor, e.g. reduce stall margins. The corresponding compressor map for open and closed conditions
(0% and 100%) is to be submitted for information.
Care shall be taken to see that bleed valve is always in a controlled position. That is, the valve position shall not be allowed
to roll off the required position dictated by the control system.
In the event that the bleed air is used for other purposes such as
anti-icing, system diagrams showing expected maximum and
minimum air flow through the system are to be provided for information. The maximum temperature of the gas shall also be
documented.
When bleed valves are controlled by the fuel system (or shaft
speed), a diagram showing actuators and actuating media is to
be submitted for information.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 35
310
rotor mass
vibration loads
misalignment
pre-loading
combined thrust and radial loads
blade-out loads
loads due to gyroscopic effects, if relevant.
Hydrodynamic bearings
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 36
Disks
T m ax T 3
TTQ = -----------------------T3 T2
Tmax
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 37
i)
Life calculations for high pressure turbine nozzle(s) shall consider the elements listed above and take into account the effects
of both loss of coating and cooling (independently), and is to
be submitted for information.
aerodynamics
gas flow at geometric boundaries
profile loss
annulus loss
secondary flow loss
tip clearance loss.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 38
redundancy in technical design and physical arrangement of the hydraulic fluid supply system
starting logic and set points
disengaging speed.
The starting system shall be capable of performing at least 6
consecutive starts.
The start system shall have its own protective system to ensure
that failure to reach ignition speed, shall not cause damage to
the starting system.
The start system shall be protected such that a stuck rotor does
not damage the start system.
In pressurised systems there shall be provision for safe relief of
pressure in the event that the pressure goes above the design
limit.
The start system shall be designed such that a single component failure does not lead to a failure to achieve propulsion
power, see Pt.4 Ch.1 Sec.3 B300 or Rules for Classification of
HS, LC and NSC Pt.4 Ch.1 Sec.3 B300.
323 Turbine mounted piping
Included in the term piping is fuel piping, lubricating oil piping, hydraulic piping, instrument and control air piping, starting system piping, and other piping determined to be subject to
these rules.
Piping is to be designed and tested in compliance with Ch.6.
Note that normally all fuel piping covered by 326 shall be class
I as defined by Ch.6. This also applies to HS, LC and NSC applications.
Piping is to be designed to withstand all expected vibration and
environmental loads, including normal, engine induced, vibration loads.
324 Lubricating oil system
The following lubricating oil system documentation shall be
submitted for information:
drawing of the lubricating oil system for the gas turbine
piping and instrumentation diagrams (or equivalent) and
instrumentation listing
drawings shall indicate maximum and minimum pressure
and temperature in the system, e.g. before bearings, relief
valve setting, etc.
type of lubricating oil
approved list of lubricants
maximum permissible amount by volume of water in the
oil
oil filtration requirement, according to NAS 1638 or ISO
4406 (or equivalent).
The lubricating oil system is to be designed and tested in compliance with Ch.6. Gas turbine lubricating oil systems are in
addition to comply with the following:
gas turbines are to have a separate lubrication oil system
the system is to include sufficient filtering, heat exchanger
capacity, magnetic chip detectors located as necessary,
and water separator arrangements, if necessary. Location
of these components is to be indicated on the drawings listed in above
any shutdown of the gas turbine, either due to a normal
shutdown, shutdown due to turbine trip (except due to fire
detection), or due to a blackout of the vessel, is not to result in damage to any turbine bearings.
Heat balance calculations for the lubricating oil system is to be
submitted upon request. The heat balance is to be considered at
cooler inlet temperature of 32C, an ambient air temperature of
40C or conditions specified by the specifications for the vessel or project, whichever is more demanding.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 39
a) Compressor characteristics.
b) Overall gas turbine performance curves. These are normally to be based on the overall efficiency (t) and the
quasidimensionless massflow group mT05/p05 as function of the pressure ratio p05/p 06 This shall be presented for
various values of the quasidimensionless speed group N/
T05, where 5 and 6 denote turbine inlet and outlet conditions (see Fig.3). Equivalent performance curves are also
acceptable.
c) The expected performance of new engine.
d) The expected performance of used engine (approximately
30 000 hours).
e) The expected recoverable performance of a used engine
(after a complete overhaul).
f) The normal performance or power loss as a function of
running time. The turbine in this case is assumed to be running within design specification or contract specifications.
For type approval, the design specification shall be assumed, for product certificates the contract specifications
shall be consider as the running conditions.
Fig. 3
Station numbering, basic cycle
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 40
Power measurement
The following methods may be applied.
Mechanical
a) Torque measurements based on absorption dynamometers.
b) Shaft torque meters.
The method used and the expected errors are to be submitted
to the Society. Should there be discussions over methods and
materials used (e.g. difference in Poissons ratio between calibrated shaft and actual shaft), the Societys decision will be final.
Thermodynamic
This method may be used when it is not possible to use direct
shaft torque measurements. That is, in the case that a gas generator is being tested alone. However, a new test will normally
be required based on shaft torque when the power turbine is
coupled to the gas generator.
This method can normally not be used alone during a type test
for a unit consisting of both gas generator and power turbine,
but may (based on proven accuracy) be used during a certification test for the gas generator.
B 800
803 The complete type testing program is subject to approval. The tests are to be witnessed by a surveyor, however, the
precise extent shall be agreed in each case.
Table B2 Engine and system data acquisition
CertifiType
Quay
Parameter
cation
test
trial
test
1)
X
X
X 5)
Power (thermodynamic)
Gas generator, and power turbine
X
X
X
speed 2)
Shaft torque at drive end (power turX
X
bine output)
Electrical power at drive end (generX
ator set only)
Compressor inlet pressure and temX
X
X
perature 1)
Compressor discharge pressure and
X
X
X
temperature 1)
X
X
X
Turbine inlet temperature 1) 6)
Gas generator exit pressure and temX
X
X
perature 1)
Gas generator exit gas temperature
X
X
X
spread
Power turbine exhaust pressure and
X
X
X
temperature 1)
Lubrication oil temperature and
X
X
X
pressure 4)
Fuel temperature and pressure, at
X
X
X
the fuel inlet
Hydraulic fluid pressure
X
Coolant temperature and pressure 4)
Temperature of external surfaces of
X
the engine
7)
Bearing metal temperatures
X
X
X
Intake pressure loss
X
X
Exhaust pressure loss
X
X
Vibration levels
X
X
X
Position of variable stator vanes, or
X
X
bleed valve opening, as applicable
Sea
trial
X 5)
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
1)
2)
3)
4)
5)
6)
7)
804 Type testing is normally valid for only one specific type
of engine, and does not cover a range of design variations. The
maximum speeds of the spools, firing temperature, turbine inlet temperature, exhaust temperatures, mass flow rate, etc. are
fixed for a given type of turbine, and will be specified on the
type approval certificate.
805 Type testing shall preferably be made with the type of
fuel oil for which the engine is intended, or equivalent. If this
is not possible then there shall be prior agreement with Society
as to the fuel used for the test, and its consequences to the results of the test. For engines intended for running on heavy fuel
oil, the test verification of the engines suitability for this may
be postponed to the sea trial.
806 If no special turbine application considerations apply
(such as e.g. fitness for purpose testing, significant application
limitations, or extensive relevant operational experience), the
type test program is to be arranged as outlined in 900. If special
considerations apply, the test program will be agreed between
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 41
Temperature:
15 C
Humidity:
60% relative
Barometric pressure: 1.013 bar (760 mmHg).
809 Control settings of the gas turbine, such as alarm and
shutdown shall be agreed upon with the Society. Set points that
shall be used in the test that are inappropriate in relation to
those used in normal running require written agreement.
810 Variation in control parameters (compressor discharge
temperature, turbine inlet temperature, etc,) during data acquisition shall normally not exceed 1% (or the manufacturers
specification.). Shaft power shall not vary more than 3% (or
that agreed upon in the contract specification).
811 If during the test, the observed data is obviously inconsistent with expected data or out of specifications of the manufacturer, all possible effort shall be made to rectify the
inconsistency during the testing. This shall be done in a mutually agreed upon manner between the manufacturer and the Society. Failure to reach an agreement shall result in a retest.
Even if the inconsistency is rectified during the test, a re-test or
test extension may be required by the Society.
812 When measured test parameters do not conform with design specification (e.g. high temperature spread), then formal
changes in the design specification need to be documented before acceptance shall be given for the test. If not the test shall
be considered as failed.
813 Test data shall be recorded only after steady state conditions have been reached by the gas turbine, for the specific test
point. Steady state is achieved when all key control parameters
of the gas turbine have reached a steady state for that specific
test condition. Variation within expected limits under testing
conditions are however permitted, see 810.
814 For turbines driving electric generators, load shedding
from 100% to 20%, load increase from 20% to 100% and other
load variations due to power demand, are not to result in a transient variation in r.p.m. greater than 10%. The permanent
speed variation is not to be more than 1% of the rated speed.
The rates at which load is shed from 100% to 20% and load is
increased from 20% to 100% (and other load variations)
should be established by agreement between the Society, engine manufacturer, and engine packager.
If feasible, complete generator sets should perform an instantaneous load shed test from 100% to 0%, without tripping.
This, however, may be postponed until the certification test, if
preferable. See D402.
B 900
901
Fig. 4
Example of type test schedule
902 Functional tests and collection of operating values including test hours are to be documented. The relevant results
are to be presented to attending surveyor during the type test.
903 Component inspections after completion of the test program shall be conducted or witnessed by attending surveyor,
see 1000.
904 The engine designer is to compile results in a type test
report, which is to be submitted for approval. If deviation from
design specifications exists, this shall be agreed upon between
the engine designer and the Society.
For emergency operating situation, the following tests may be
performed:
quick start
override functions.
The Society will not allow the engines to run at these points unless there is a design basis that clearly indicates integrity of the
components for a sufficient period of time, not less than 500
hours.
905 Start test
Seven starts must be made, of which 3 starts must be preceded
by at least a two-hour engine shutdown. There must be at least
one false engine start, pausing for the manufacturer's specified
minimum fuel drainage time, before attempting a normal start.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 42
Performance test
The performance test is to be carried out in a manner equivalent to standards recognised by the Society, e.g. ISO 2314 Gas
turbines acceptance tests or ANSI and ASME PTC 22 Gas turbine power plant, performance test codes. In the case of conflict between the standards and these rules, these rules prevail.
The type test engine must be subjected to an endurance test that
includes a total of at least 15 hours of operation. The 3-hour
test sequence (or "run", as defined below) must be conducted
5 times to complete the required 15 hours of operation.
A leak check is to be performed prior to all runs.
The engine is to be operated according to the power and speed
diagram, according to the application (e.g. propulsion drive,
the curve shall be the propeller and waterjet curve). The data to
be measured and recorded when testing the engine at the various load points, and is to include all major parameters for the
engine operation (see also 600). The operating time per load
point depends on the engine size (achievement of steady state
condition) and on the time for collection of the operating values. Normally, an operating time of 10 minutes can be assumed
per part load point.
The test sequence is to include:
one hour and thirty minutes total at successive part loads
corresponding to at least 9 approximately equal speed and
time increments between maximum continuous engine rotational speed and minimum idle rotational speed, according to nominal propeller curve
one hour and thirty minutes at rated maximum continuous
power, i.e. 100% output at 100% torque and 100% speed.
For high speed, light craft and naval surface craft application,
further testing may be required under certain circumstances,
and will be mutually agreed upon between the Society and the
manufacturer.
Engine and control system is to demonstrate trouble free running without load for a minimum of 20 minutes, before testing
at load conditions.
918 For dual fuel installations, the performance test is to be
carried out using the least favourable fuel. Gas turbines intended for dual fuel service are to demonstrate the capability to
change from one fuel to the other, e.g. liquid to gas, and vice
versa, while at load specified in operating manual, without detrimental change in operational parameters.
919 Any deviations to the engine internals, e.g. blades, disks,
combustors, bearings, etc. from that submitted to the Society
during the design review, are to be presented to the Society's
approval centre in due time before the actual test. The deviations are to be recorded in the test report. Additional testing
and measurements may be required by the Society should there
be significant changes to critical components e.g. blades,
disks, combustors, bearings, etc.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 43
blades
impellers
disks
shafts
inter-stage coupling
tie bolts
combustors
nozzles
gas generator casing
power turbine casing
gas generator rotor assembly
power turbine rotor assembly.
302 A manufacturing survey arrangement (MSA) is to be established based on a product audit covering the following aspects:
General
D. Workshop Testing
D 100 Application
101 This sub section covers procedures and requirements for
certification testing of complete gas turbines. General considerations and requirements pertaining to certification testing are
found in B400, B500, B600, B700 and B1000.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 44
D 200
Certification testing
D 300
207 The certification test shall include testing found necessary by the Society to demonstrate:
208 Prior to the start of the certification test, the engine and
the control and monitoring system are to demonstrate trouble
free running at no load for 20 minutes.
The operating time per load point depends on the time for
collection of the operating values. Normally, an operating
time of 10 minutes can be assumed per load point. The actual time may be determined by the attending surveyor.
303 For plants with water jets that may experience air ingestion, the speed control system is to be checked with a sudden
load shed from the maximum continuous power to 20%. The
engine overspeed is not to trigger the overspeed protection
function (no trip).
D 400
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 45
D 500
Boroscope inspection
501 Boroscope inspection is to be conducted following certification testing. See B1000 for particulars and requirements.
E 100
Parameter
value
High
High-High
High
High-High
Alarm
Step to
idle
Alarm
Alarm
Step to
idle
Alarm
Alarm
Shutdown
Alarm
Alarm
Step to
idle
Alarm
Alarm
Alarm
Alarm
Deviation
Alarm
High
Shutdown
Indicated
surge
Alarm
High
High-High
Low
Low-Low
High
Control systems for gas turbines are to be certified in accordance with Ch.9 before being installed on board or being
hooked up to the turbine.
Low
Low-Low
High
High
High-High
103 The control system is to be equipped with an uninterruptible power supply designed to function even under blackout conditions. Total loss of control system power shall lead to
a controlled turbine shutdown.
Shutdown
Alarm
High
ShutHigh High
down
Flame out
Inlet guide vanes, bleed valves, variable stator vanes actual position not in synchronisation with command value, as applicable
Bearing temperature
Hydrodynamic bearing, radial displacement, gap value 2)
Action
Alarm
High
High-High
Alarm
Step to
idle
Alarm
High
High
High-High
Alarm
Alarm
Shutdown
High
Alarm
High
High-High
High
High-High
Low
Low
High
Alarm
Step to
idle
Alarm
Shutdown
Alarm
Alarm
Alarm
3)
Alarm
Alarm
Step to
idle
Alarm
1)
2)
3)
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 46
109 For gas turbines driving main or emergency electric generators, see Ch.2 Sec.6.
Guidance note:
Note that the time requirement to re-establishment of steady
state speed after load shed in Ch.2 Sec.6 A104 (5 s), is not applicable to gas turbines, but is subject to a case by case evaluation
taking generator package design into account.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
F. Arrangement
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 47
202 Preferably, the gas turbine casing shall not absorb deflections in vessel structure. This might however be accepted
if it can be shown by calculations that casing deflections are
within acceptable limits as specified by the gas turbine manufacturer.
203 The foundation system is normally to be designed with
a minimum separation margin of 20% to dominant frequencies
of the gas turbine and adjacent equipment. Calculations to be
submitted upon request.
F 300 Rigid mounting
301 For mounting on epoxy resin, the surface pressure due to
mass and bolt tension is to be within approved values for the
applicable epoxy resin. Calculation of surface pressure due to
peak loads can be required in special cases. The thickness of
502 The inlet ducting and components in way of inlet airflow, such as filters, silencers and anti-icing devices are to be
constructed and mounted to minimise the risk of loose parts
entering the gas turbine.
503 Icing at air intake is to be prevented by suitable means.
504 When considered necessary, the air intake system is to
incorporate an effective filtration system preventing harmful
particles, including sea salt and harbour dust, from entering the
compressor inlet. Maximum allowable salt content in the air
entering the compressor inlet is 0.01 wppm. Pressure drop
across filter to be monitored in accordance with Table E1.
505 Air intakes are to be placed such that the ingestion of
spray due to ship motion and weather is kept within acceptable
limits. The air inlet ducts are to incorporate a system for drainage of water.
506 Air intakes and exhaust outlet are to be so arranged that
re-ingestion of combustion gases are avoided.
507 The flow path of the inlet air is to be as straight and clean
as possible, with a minimum of obstacles, sharp corners and
duct curving. This is to minimise the creation of vortex flow,
pressure drops and uneven air distribution in the compressor
inlet. Inlet airflow analyses or model tests may be required in
special cases.
508 Pressure losses in air intake and exhaust ducting are not
to exceed the specifications of the gas turbine manufacturer.
509 Multi-engine installations are to have separate inlets and
outlets for each gas turbine and are to be arranged to prevent
induced circulation through a stopped engine.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 48
802 The ventilation pipe and duct is to terminate at a ventilated hood or casing arranged to cover the areas occupied by
flanges, valves etc. and the piping at the gas or crude oil control
unit. The hood or casing is to be installed or mounted to permit
ventilation air to sweep across the control unit and be discharged at the top of the hood or casing (enclosure). The duct
and hood are to be fitted with gas-tight inspection openings in
way of connections of pipes.
803 Gas supply lines are not to pass through the accommodation or control station spaces. Gas lines may pass through or
extend into other spaces if the lines are enclosed in a mechanically exhaust-ventilated gas-tight pipe or duct. The air space
between outer and inner walls is to be provided with separate
mechanical ventilation with a capacity of a minimum of 30 air
changes per hour. The ventilation is to take place at a pressure
below that of the outside room.
804 There is to be an interlock between ventilation and gas
supply with control logic documented, such that then ventilation between outer and inner walls will always be in operation
when there is gas in the supply line. In or immediately inside
the duct outlet, continuous gas detection is to be provided.
F 900 Special requirements for arrangement of fuel
supply in mobile offshore units
901 The gas may be taken directly from the oil production facilities. The complete system for treatment of gas including
pressure vessel, compressors, water separator, filters, pressure
control valves etc., is to be located in hazardous area and separated from the engine and boiler room by gas-tight bulkheads.
902 A double block and bleed system arranged by two
three-way valves in series is to be fitted on the gas supply line.
The block and bleed system is to shut off the gas supply and
vent the gas piping to a safe location in the open air. One
block and bleed valve may be accepted for short supply lines
located in hazardous area.
903 The block and bleed valves are to be arranged for both
automatic and manual operation. The manual operation is to be
carried out from the control hood of gas turbine and from a location outside the engine room.
904 Means for gas-freeing of the complete piping system are
to be provided. Warning and notice plate is to be provided,
which clearly indicates that gas-freeing is not to take place
through a recently extinguished combustion chamber.
905 The switch-over from gas operation to oil operation, or
vice versa, is to be possible during normal running condition.
906 A separate and independent supply line is to be arranged
for each gas turbine.
907 The minimum nominal wall thickness of the pipes for
fuel in non-hazardous areas is to be designed for a pressure of
at least 50% higher than normal working pressure but not less
than 6.3 mm.
908 Full penetration butt-welded joints are normally to be
used for enclosed fuel pipes in non-hazardous areas. Detachable pipe connections are to be limited to those that are necessary for the installation purpose only.
909 Exposed (i.e. not enclosed in a gas tight pipe or duct)
fuel pipes may be accepted in non-hazardous areas after special consideration in each case, provided compliance with the
following minimum criteria:
a) 10% non-destructive testing of welded connections is to be
carried out.
b) Strength of pipes(wall thickness w.r.t. diameter) and the
arrangement (support etc.) are such that the piping is able
to withstand the maximum possible combined load from
internal and external forces it may be exposed to.
c) Clearly identifiable colour code is to be used for the pipes.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 49
G. Vibration
G 100
General
H 200
Analysis
The evaluation shall consist of a combination of analytical calculations and test measurements.
G 200
102 In general the installation shall be in accordance with approved drawings and specifications fulfilling the requirements
in F.
301
Alignment of engines
G 300
301 Requirements for measurement verification of actual vibration behaviour for core engine and system are located as
shown in Table G2.
Table G2 Vibration measurement requirements for core engine
and system
Test type Measurements
Reference to
test requirements
Verification of core engine lateral critiB912, B913,
Type test cal speeds and vibration levels during
B914, B916
mechanical running test
Certifica- Verification of core engine vibration
D211, D212
tion test
levels
Verification of core engine and system
Quay test vibration levels
I107
Verification of core engine and system
Sea trial
I203, I209
vibration levels
303
H. Installation Inspections
H 100
Fig. 5
Recommended arrangements of hoses and pipes
Application
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 50
I. Shipboard Testing
I 100
Quay trial
101 The testing described in 100 applies to all gas turbines in
addition to installation inspections as described in H. General
considerations and requirements pertaining to the shipboard
testing are found in B400, B500, B600, B700 and B1000.
102 The test purpose is to verify system integration, control
system behaviour and the functioning of auxiliary systems.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.2 Page 51
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.3 Page 52
SECTION 3
STEAM TURBINES
A. General
A 100 Application
101 The rules in this section apply to steam turbines used as
propulsion engines and for driving auxiliaries.
102 Subject to approval is the steam turbine itself with foundation, integrated steam and drain piping, lubricating oil systems, other support systems, and the control and monitoring
systems.
A 200 Documentation
201 The following drawings and specifications are to be submitted:
303 The control and monitoring systems are to be tested according to Ch.9 Sec.1.
304 Vibration levels are to be recorded for speeds varying
from idle to 110% of rated speed. At each speed setting at
which vibration levels are to be measured the running is to be
of such length of time that steady state conditions are ensured.
305 After the test a lubricating oil sample is to be tested for
traces of metallic particles, and a visual inspection of internal
parts is to be carried out to the extent as requested by the surveyor.
306 For turbines driving electric generators the capability of
supplying 110% of its rated power for a period of 15 minutes
is to be demonstrated.
C. Arrangement
B. Certification and Testing
B 100 General
101 The turbine is to be delivered with a NV certificate.
102 The manufacturer is to have in operation a certified quality system. Should the manufacturer not be in possession of a
valid quality system certificate, an assessment of the quality
system elements which are in operation at the manufacturer's
works is to be made. Based on this assessment a survey arrangement with the manufacturer may be established.
B 200 Testing of components
201 Mechanical properties and chemical composition of
power transmitting parts, as well as parts subject to pressure,
are to be proved and documented through the manufacturer's
quality system.
202 The materials of parts mentioned in 201 are to be free
from defects which may lead to damages. This is to be proved
and documented as above. Accepted methods may be:
ultrasonic testing (rotors and blades)
magnetic particle testing (or dye penetrant)
hydraulic pressure testing (integrated valves and piping 2
times design pressure, otherwise 1.5 times, but not less
than 2 bar).
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.3 Page 53
Design
General
101 The requirements in this item are additional to those given in Ch.9.
102 Automatic or semiautomatic control systems are to provide controlled load changes to avoid thermal shocks and other
unacceptable transients.
103 Arrangement is to be provided for shutting off the steam
to the propulsion turbines by suitable hand trip gear situated at
the manoeuvring stand and at the turbine itself. Hand tripping
for auxiliary turbines is to be arranged in the vicinity of the turbine overspeed protective device. (The hand trip gear is understood to be any device which is operated manually irrespective
of the way the action is performed, i.e. mechanically or by
means of external power).
Failure
Low
Lower
Low
High
Low
High
High
Required monitoring
(Stated by an x)
Automatic
Alarm shutdown of
turbine
x
x
x
x
x
x
x
Comments
Each separate
system
In system tank
High
High
x
x
x
x
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2001
Pt.4 Ch.3 Sec.3 Page 54
Failure
Low
Lower
High
Low
Required monitoring
(Stated by an x)
Automatic
Alarm
shutdown
of turbine
x
x
x
x
Comments
In system tank
See 300
x
x
x
High
F. Testing On Board
F 100 Testing before sea trial
101 Turbines driving electrical generators are subject to tests
according to the requirements in E300.
F 200 Sea trial
201 During sea trials, the turbine is to be tested according to
an approved test programme. Upon completion of the sea tri-