Beruflich Dokumente
Kultur Dokumente
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
1 Proyecto Arquitectnico
glob
1.00
2 Impuestos Municipales
glob
1.00
glob
1.00
650,000
650,000
glob
1.00
1,000,000
1,000,000
glob
1.00
500,000
500,000
glob
1.00
400,000
400,000
7 Pozo artesiano
1.00
100,000
100,000
8 Estudio de Suelos
1.00
100,000
100,000
1.00
15,000
15,000
1.00
300,000
300,000
1.00
75,000
75,000
1.00
16,000
16,000
1.00
6,000
6,000
1.00
9,000
9,000
1.00
7,000
7,000
1.00
5,000
5,000
1.00
15,000
15,000
1.00
11,000
11,000
1.00
7,000
7,000
1.00
10,000
10,000
1.00
16,000
16,000
1.00
5,000
5,000
23 Demolicin revestimientos
1.00
8,000
8,000
24 Desmoche de pilotes
un
1.00
50,000
50,000
1.00
5,000
5,000
1.00
3,000
3,000
1.00
20,000
20,000
1.00
10,000
10,000
1.00
5,000
5,000
1.00
15,000
15,000
1.00
35,000
35,000
1.00
35,000
35,000
9 Clculo Estructural
10 Obrador
11 Vallado perimetral
12 Demolicin techo de tejas
13 Demolicin techo de chapas
14 Demolicin mampostera 0.45m sin recuperacin
15 Demolicin mampostera 0.30m sin recuperacin
16 Demolicin mampostera 0.15m sin recuperacin
17 Demolicin mampostera 0.45m con recuperacin
18 Demolicin mampostera 0.30m con recuperacin
19 Demolicin mampostera 0.15m con recuperacin
20 Demolicin techo de tejas sin recuperacin
21 Demolicin techo de tejas con recuperacin
22 Demolicin contrapiso
26 Replanteo de Obra
27 Excavacin manual (sin acarreo)
28 Relleno manual (sin acarreo)
29 Compactacin manual (pisn)
30 Compactacin mecnica (compactador manual)
31 Excavacin cmara sptica
32 Excavacin pozo absorvente
Trabajos Preliminares
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
Pgina 1 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
EXCAVACION
3
1.00
25,000
25,000
1.00
30,000
30,000
1.00
50,000
50,000
1.00
Kg
210.00
1,100
231,000
Arena lavada
0.42
45,000
18,900
Piedra triturada
ton
0.98
110,000
107,800
0.33
85,000
28,050
1.00
135,000
135,000
1.00
Kg
210.00
1,100
231,000
Arena lavada
0.42
45,000
18,900
Piedra triturada
Kg
0.98
110,000
107,800
0.33
85,000
28,050
1.00
150,000
150,000
1.00
165,000
165,000
1.00
210,000
210,000
1.00
450,000
450,000
1.00
650,000
650,000
1.00
1,000,000
1,000,000
1.00
1,500,000
1,500,000
1.00
2,250,000
2,250,000
1.00
3,500,000
3,500,000
1.00
550,000
550,000
1.00
750,000
750,000
1.00
950,000
950,000
m
m
m
HORMIGON CICLOPEO
1 Base de hormign ciclpeo (70%H + 30%PB)
Cemento
Piedra bruta
Mano de Obra
2 Tubulones (70%H + 30%PB)
Cemento
Piedra bruta
Mano de Obra
m
m
m
520,750
535,750
PILOTES STRAUSS
Fundaciones
Pgina 2 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
1.00
Kg
200.00
1,100
220,000
Arena lavada
0.60
45,000
27,000
Piedra triturada
ton
1.40
110,000
154,000
1.00
250,000
250,000
1.00
Kg
300.00
1,100
330,000
Arena lavada
0.60
45,000
27,000
Piedra triturada
ton
1.40
110,000
154,000
Armaduras
Kg
75.00
5,500
412,500
Alambre de atar
Kg
1.50
11,000
16,500
1.00
400,000
400,000
1.00
Kg
300.00
1,100
330,000
Arena lavada
0.60
45,000
27,000
Piedra triturada
ton
1.40
110,000
154,000
Armaduras
Kg
100.00
5,500
550,000
Alambre de atar
Kg
2.00
11,000
22,000
1.00
400,000
400,000
1.00
Kg
Mano de Obra
2 Zapatas (sin excavacin ni encofrado)
Cemento
Mano de Obra
3 Plateas (sin excavacin ni encofrado)
Cemento
Mano de Obra
4 Cabezales (sin excavacin, encofrado, ni desmoche)
Cemento
m
m
m
m
m
m
651,000
1,340,000
1,483,000
1,597,400
300.00
1,100
330,000
Arena lavada
0.60
45,000
27,000
Piedra triturada
ton
1.40
110,000
154,000
Armaduras
Kg
120.00
5,500
660,000
Alambre de atar
Kg
2.40
11,000
26,400
1.00
400,000
400,000
1.00
Kg
300.00
1,100
330,000
Arena lavada
0.60
45,000
27,000
Piedra triturada
ton
1.40
110,000
154,000
Armaduras
Kg
65.00
5,500
357,500
Alambre de atar
Kg
1.30
11,000
14,300
1.00
400,000
400,000
Mano de Obra
5 Vigas de fundacin (sin excavacin ni encofrado)
Cemento
Mano de Obra
Hormign
m
m
1,282,800
Pgina 3 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
1.00
Kg
300.00
1,100
330,000
Arena lavada
0.60
45,000
27,000
Piedra triturada
ton
1.40
110,000
154,000
Armaduras
Kg
120.00
5,500
660,000
Alambre de atar
Kg
2.40
11,000
26,400
Encofrado
glob
1.00
100,000
100,000
Clavos 2"x11
Kg
2.00
10,000
20,000
1.00
400,000
400,000
1.00
Kg
6 Pilares
Cemento
Mano de Obra
7 Vigas
Cemento
m
m
1,717,400
1,846,000
300.00
1,100
330,000
Arena lavada
0.60
45,000
27,000
Piedra triturada
ton
1.40
110,000
154,000
Armaduras
Kg
125.00
5,500
687,500
Alambre de atar
Kg
2.50
11,000
27,500
Encofrado
glob
1.00
100,000
100,000
Clavos 2"x11
Kg
2.00
10,000
20,000
1.00
500,000
500,000
1.00
Kg
300.00
Arena lavada
0.60
45,000
27,000
Piedra triturada
ton
1.40
110,000
154,000
Armaduras
Kg
75.00
5,500
412,500
Alambre de atar
Kg
1.50
11,000
16,500
Encofrado
glob
1.00
100,000
100,000
Clavos 2"x11
Kg
2.00
11,000
22,000
1.00
400,000
400,000
1.00
Kg
300.00
1,100
330,000
0.60
45,000
27,000
Mano de Obra
8 Losas
Cemento
Mano de Obra
9 Escalera
Cemento
m
m
m
m
1,462,000
1,100
330,000
1,922,800
Arena lavada
Piedra triturada
ton
1.40
110,000
154,000
Armaduras
Kg
65.00
5,500
357,500
Alambre de atar
Kg
1.30
11,000
14,300
Encofrado
glob
1.00
200,000
200,000
Clavos 2"x11
Kg
4.00
10,000
40,000
1.00
800,000
800,000
Mano de Obra
Hormign
Pgina 4 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
1.00
Kg
300.00
1,100
330,000
Arena lavada
0.60
45,000
27,000
Piedra triturada
ton
1.40
110,000
154,000
Armaduras
Kg
100.00
5,500
550,000
Alambre de atar
Kg
2.00
11,000
22,000
Alambre de trinca
Kg
4.00
15,000
60,000
Encofrado
glob
1.00
200,000
200,000
Clavos 2"x11
Kg
4.00
10,000
40,000
1.00
800,000
800,000
10 Pantalla
Cemento
Mano de Obra
Hormign
2,183,000
Pgina 5 de 22
e-constructor
Costeo de Obra
Rubro
1 Cimiento de Piedra Bruta Colocada con arena lavada
Unidad
Cantidad
1.00
P. Unitario
P. Total
297,500
Piedra bruta
1.15
75,000
86,250
Cemento
Kg
45.00
1,100
49,500
Cal viva
Kg
46.00
1,000
46,000
0.35
45,000
15,750
1.00
100,000
100,000
1.00
Piedra bruta
1.15
75,000
86,250
Cemento
Kg
45.00
1,100
49,500
0.30
100,000
30,000
1.00
100,000
100,000
1.00
Kg
30.00
1,100
33,000
Arena lavada
0.20
45,000
9,000
Cal viva
Kg
13.00
1,000
13,000
Ladrillo comn
un
185.00
400
74,000
1.00
30,000
30,000
1.00
Kg
16.00
1,100
17,600
0.10
45,000
4,500
Arena lavada
Mano de Obra
2 Cimiento de Piedra Bruta Colocada con arena gorda
Arena gorda
Mano de Obra
3 Mampostera de nilevacin 0.45m
Cemento
Mano de Obra
4 Mampostera de nilevacin 0.30m
Cemento
m
m
m
m
m
265,750
159,000
102,100
Arena lavada
Cal viva
Kg
7.00
1,000
7,000
Ladrillo comn
un
120.00
400
48,000
Mano de Obra
m2
1.00
25,000
25,000
1.00
Kg
16.00
1,100
17,600
Arena lavada
0.10
45,000
4,500
Cal viva
Kg
7.00
1,000
7,000
Ladrillo comn
un
120.00
400
48,000
1.00
27,500
27,500
1.00
Kg
Mano de Obra
6 Mampostera de elevacin 0.20m (comn)
Cemento
104,600
83,500
10.00
1,100
11,000
Arena lavada
0.10
45,000
4,500
Cal viva
Kg
8.00
1,000
8,000
Ladrillo comn
un
100.00
400
40,000
1.00
20,000
20,000
Mano de Obra
Albailera
Pgina 6 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
1.00
Kg
10.00
1,100
11,000
Arena lavada
0.05
45,000
2,250
Cal viva
Kg
5.00
1,000
5,000
Ladrillo comn
un
60.00
400
24,000
1.00
15,000
15,000
1.00
Kg
3.00
1,100
3,300
Arena lavada
0.01
45,000
450
Cal viva
Kg
1.50
1,000
1,500
Ladrillo comn
un
30.00
400
12,000
1.00
10,000
10,000
1.00
Kg
6.00
1,100
6,600
Arena lavada
0.06
45,000
2,700
Cal viva
Kg
2.50
1,000
2,500
Ladrillo hueco
un
24.00
2,000
48,000
Mano de Obra
1.00
17,500
17,500
1.00
Kg
7.00
1,100
7,700
Arena lavada
0.06
45,000
2,700
Cal viva
Kg
3.00
1,000
3,000
Ladrillo hueco
un
18.00
2,000
36,000
Mano de Obra
1.00
15,000
15,000
1.00
Kg
3.00
1,100
3,300
Arena lavada
0.01
45,000
450
Ladrillo de vidrio
un
25.00
50,000
1,250,000
1.00
45,000
45,000
Mano de Obra
8 Mampostera de elevacin 0.07m
Cemento
Mano de Obra
9 Mampostera de elevacin 0.20m (hueco)
Cemento
11 Ladrillo de vidrio
Cemento
Mano de Obra
Albailera
57,250
27,250
77,300
64,400
1,298,750
Pgina 7 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
1.00
Kg
5.00
1,100
5,500
Arena lavada
0.04
45,000
1,800
Aditivo
Kg
0.50
5,000
2,500
1.00
15,000
15,000
1.00
Kg
1.00
10,000
10,000
1.00
15,000
15,000
1.00
Kg
5.00
5,000
1.00
8,000
1.00
Kg
11.00
1,100
12,100
Arena lavada
0.03
45,000
1,350
Hidrfugo
Kg
0.30
65,000
19,500
1.00
15,000
15,000
1.00
Kg
1.50
10,000
15,000
1.00
10,000
10,000
1.00
Kg
Mano de Obra
13 Aislacin Horizontal (emulsin asfltica)
Emulsin asfltica
Mano de Obra
14 Aislacin Horizontal (asfalto en panes)
Asfalto en panes
Mano de Obra
15 Aislacin Vertical (aditivo hidrfugo)
Cemento
Mano de Obra
16 Aislacin Vertical (emulsin asfltica)
Emulsin asfltica
Mano de Obra
17 Aislacin de Terraza (emulsin asfltica)
Cemento
24,800
25,000
33,000
25,000
8,000
47,950
25,000
80,450
12.00
1,100
13,200
Arena lavada
0.05
45,000
2,250
Asfalto en panes
Kg
10.00
5,000
50,000
1.00
15,000
15,000
1.00
Kg
3.00
10,000
30,000
1.10
5,000
5,500
1.00
10,000
10,000
1.00
1.10
15,000
16,500
1.00
10,000
10,000
1.00
1.10
20,000
22,000
1.00
10,000
10,000
Mano de Obra
18 Aislacin de Terraza (asfalto con trama elstica)
Aditivo
Trama elstica
Mano de Obra
19 Aislacin de Terraza (membrana transitable)
Membrana asfltica 4mm
Mano de Obra
20 Aislacin de Terraza (membrana no transitable)
Membrana asfltica 4mm
Mano de Obra
Albailera
m
m
m
m
m
m
m
m
45,500
26,500
32,000
Pgina 8 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
1.00
Cemento
Kg
3.00
1,100
3,300
Cal viva
Kg
1.50
1,000
1,500
Arena lavada
0.01
45,000
450
2.00
35,000
70,000
Tejas espaolas
un
25.00
1,250
31,250
Tejueln
un
33.00
2,500
82,500
Clavos 2"
Kg
0.25
12,000
3,000
Asfalto
Kg
1.00
8,000
8,000
1.00
60,000
60,000
1.00
2.00
35,000
70,000
Machimbre 1/2"x4"
un
1.05
62,000
65,100
1.75
1,350
2,363
Listn 1"x2"
2.50
2,500
6,250
Tejas francesas
un
15.00
2,500
37,500
Clavos 2"
Kg
0.20
12,000
2,400
Alambre
Kg
0.02
12,000
240
1.00
55,000
55,000
1.00
Mano de Obra
22 Techo de tejas francesas sobre machimbre
Mano de Obra
23 Techo de chapas galvanizadas sobre madera
Chapa galvanizada N 28
m
m
260,000
238,853
87,000
1.00
50,000
50,000
pul /m
0.50
35,000
17,500
pul /m
0.50
3,000
1,500
Kg
0.20
15,000
3,000
1.00
15,000
15,000
1.00
1.00
60,000
60,000
pul /m
0.50
35,000
17,500
Kg
0.03
12,000
360
1.00
15,000
15,000
Albailera
m
m
92,860
Pgina 9 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
1.00
Kg
3.00
1,100
3,300
Arena lavada
0.01
45,000
450
Hidrfugo
Kg
0.10
65,000
6,500
1.00
7,000
7,000
1.00
Kg
2.00
1,100
2,200
Arena lavada
0.02
45,000
900
Cal viva
Kg
4.00
1,000
4,000
1.00
10,000
10,000
1.00
Kg
2.00
1,100
2,200
Arena lavada
0.02
45,000
900
Cal viva
Kg
4.00
1,000
4,000
1.00
15,000
15,000
1.00
Cemento
Kg
4.50
1,100
4,950
Cal viva
Kg
8.00
1,000
8,000
Arena lavada
0.05
45,000
2,250
Cascotes de ladrillo
Kg
0.07
75,000
5,250
1.00
12,500
12,500
1.00
Cemento
Kg
3.50
1,100
3,850
Cal viva
Kg
6.50
1,000
6,500
0.04
45,000
1,800
0.05
75,000
3,750
1.00
12,500
12,500
25 Revoque (azotada)
Cemento
Mano de Obra
26 Revoque (1 capa)
Cemento
Mano de Obra
27 Revoque (2 capas)
Cemento
Mano de Obra
28 Contrapiso de cascotes sobre terreno natural
Mano de Obra
29 Contrapiso de cascotes sobre losa
Arena lavada
Cascotes de ladrillo
Mano de Obra
Albailera
m
m
m
17,250
17,100
22,100
32,950
28,400
Pgina 10 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
1.00
Kg
3.50
1,100
3,850
Arena lavada
0.05
45,000
2,250
Ladrillo comn
un
50.00
400
20,000
un
1.00
35,000
35,000
glob
1.00
50,000
Mano de Obra
111,100
50,000
1.00
Kg
9.00
1,100
9,900
Arena lavada
0.10
45,000
4,500
Ladrillo comn
un
100.00
400
40,000
un
1.00
70,000
70,000
glob
1.00
55,000
55,000
179,400
1.00
Kg
18.00
1,100
19,800
Arena lavada
0.15
45,000
6,750
Ladrillo comn
un
150.00
400
60,000
un
1.00
100,000
100,000
glob
1.00
60,000
60,000
Mano de Obra
1.00
Cemento
Kg
100.00
Cal viva
Kg
246,550
837,500
1,100
110,000
50.00
1,000
50,000
Arena lavada
1.50
45,000
67,500
Ladrillo comn
un
400.00
400
160,000
Mano de Obra
glob
1.00
450,000
450,000
1.00
Kg
1,348,750
150.00
1,100
Arena lavada
0.75
45,000
33,750
Ladrillo comn
un
1,000.00
400
400,000
Mano de Obra
glob
1.00
750,000
750,000
Albailera
165,000
Pgina 11 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
PISO
m
1.00
Kg
12.00
1,100
13,200
0.03
45,000
1,350
1.00
10,000
10,000
1.00
Kg
5.00
1,100
5,500
Arena lavada
0.03
45,000
1,350
Cal viva
Kg
4.50
1,000
4,500
1.05
27,500
28,875
Pastina
Kg
0.20
5,000
1,000
1.00
15,000
15,000
m
m
24,550
56,225
Mano de Obra
3 Piso Cermico
1.00
Kg
5.00
1,100
5,500
Arena lavada
0.03
45,000
1,350
Cal viva
Kg
4.50
1,000
4,500
1.05
65,000
68,250
Pastina
Kg
0.20
5,000
1,000
1.00
25,000
25,000
1.00
Kg
Cemento
Mano de Obra
4 Piso Mosaico Grantico
Cemento
105,600
97,550
7.00
1,100
7,700
Arena lavada
0.03
45,000
1,350
Cal viva
Kg
5.00
1,000
5,000
1.05
45,000
47,250
Pastina
Kg
0.75
5,000
3,750
1.00
17,500
17,500
1.00
15,000
15,000
1.00
Kg
5.00
1,100
5,500
Arena lavada
0.03
45,000
1,350
Cal viva
Kg
m
m
70,975
4.50
1,000
4,500
1.05
50,000
52,500
Pastina
Kg
0.20
5,000
1,000
0.35
17,500
6,125
Mano de Obra
Terminaciones
Pgina 12 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
1.00
Kg
8.50
1,100
9,350
Arena lavada
0.03
45,000
1,350
Cal viva
Kg
4.50
1,000
4,500
1.10
35,000
38,500
1.00
15,000
15,000
1.00
Kg
5.00
1,100
5,500
Arena lavada
0.03
45,000
1,350
Cal viva
Kg
4.50
1,000
4,500
1.05
25,000
26,250
Pastina
Kg
0.20
5,000
1,000
1.00
18,000
18,000
m2
1.00
Kg
0.50
1,100
550
Arena lavada
0.01
45,000
450
Cal viva
Kg
0.35
1,000
350
1.05
10,000
10,500
1.00
7,500
7,500
1.00
Kg
0.50
1,100
550
Arena lavada
0.01
45,000
450
Cal viva
Kg
0.35
1,000
350
Zcalo cermico
1.05
10,000
10,500
1.00
8,500
8,500
1.00
Kg
0.50
1,100
550
Arena lavada
0.01
45,000
450
Cal viva
Kg
0.35
1,000
350
1.05
15,000
15,750
1.00
7,500
7,500
Piedra losa
Mano de Obra
7 Piso tipo Veredita
Cemento
Mano de Obra
m
m
68,700
56,600
ZOCALO
1 Zcalo calcreo
Cemento
Mano de Obra
2 Zcalo cermico
Cemento
Mano de Obra
3 Zcalo granito reconstitudo
Cemento
Mano de Obra
Terminaciones
19,350
20,350
24,600
Pgina 13 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
AZULEJO
m
1.00
Kg
3.50
1,000
3,500
1.10
65,000
71,500
Pastina
Kg
0.20
5,000
1,000
1.00
20,000
20,000
1.00
65,000
65,000
1.00
75,000
75,000
1.00
60,000
60,000
1.00
175,000
175,000
1.00
500,000
500,000
1.00
500,000
500,000
1.00
380,000
380,000
1.00
350,000
350,000
1.00
1,250,000
1,250,000
1.00
1,450,000
1,450,000
m2
1.00
Kg
0.50
200
100
pomo
0.05
6,000
300
lt
1 Azulejo
Adhesivo
Mano de Obra
96,000
CIELORRASO Y MAMPARAS
1 Cielorraso desmontable (yeso acartonado)
2 Cielorraso a junta tomada (yeso acartonado)
3 Cielorraso de PVC
4 Mamparas de yeso acartonado
m
m
m
m
m
m
VIDRIOS
1 Vidrio - Cristal templado fijo incoloro con herrajes
2 Vidrio - Cristal templado fijo color con herrajes
3 Vidrio - Cristal templado incoloro, puerta con herrajes
4 Vidrio - Cristal templado color, puerta con herrajes
m
m
m
PINTURA
7,900
0.50
5,000
2,500
1.00
5,000
5,000
1.00
Lija
un
0.50
1,000
500
Enduido
Kg
1.25
4,000
5,000
1.00
5,000
5,000
1.00
Mano de Obra
2 Enduido interior
Mano de Obra
3 Pintura al ltex interior
Sellador
10,500
11,050
lt
0.05
11,000
550
Kg
0.30
10,000
3,000
Mano de Obra
m2
1.00
7,500
7,500
1.00
lt
0.05
11,000
550
Kg
0.30
20,000
6,000
1.00
7,500
7,500
Terminaciones
14,050
Pgina 14 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
AGUA CORRIENTE
1 Cao PVC 1/2" roscable
1.00
5,000
5,000
1.00
6,000
6,000
1.00
10,000
10,000
un
1.00
1,000
1,000
un
1.00
2,000
2,000
un
1.00
3,000
3,000
un
1.00
3,000
3,000
un
1.00
5,000
5,000
un
1.00
5,000
5,000
un
1.00
3,000
3,000
un
1.00
6,000
6,000
un
1.00
3,000
3,000
un
1.00
7,000
7,000
1 Ducha higinica
un
1.00
250,000
250,000
2 Duchas
un
1.00
45,000
45,000
3 Grifo de mesa
un
1.00
50,000
50,000
un
1.00
150,000
150,000
un
1.00
120,000
120,000
un
1.00
100,000
100,000
un
1.00
120,000
120,000
un
1.00
75,000
75,000
9 Mezclador de mesa
un
1.00
95,000
95,000
10 Mezclador de pared
un
1.00
400,000
400,000
un
1.00
350,000
350,000
un
1.00
450,000
450,000
13 Mezclador monocomando
un
1.00
650,000
650,000
14 Vlvulas de descarga
un
1.00
100,000
100,000
1 Juego de bao
un
1.00
1,000,000
1,000,000
un
1.00
400,000
400,000
un
1.00
650,000
650,000
4 Termocalefn 30lts
un
1.00
400,000
400,000
GRIFERIAS
ARTEFACTOS
Sanitario
Pgina 15 de 22
e-constructor
Costeo de Obra
Rubro
Unidad
Cantidad
P. Unitario
P. Total
5 Termocalefn 50lts
un
1.00
500,000
500,000
6 Termocalefn 80lts
un
1.00
575,000
575,000
7 Termocalefn 100lts
un
1.00
650,000
650,000
8 Baera
un
1.00
1,500,000
1,500,000
9 Hidromasaje
un
1.00
5,000,000
5,000,000
10 Sauna seco
un
1.00
3,000,000
3,000,000
11 Sauna vapor
un
1.00
3,500,000
3,500,000
12 Pileta de cocina
un
1.00
300,000
300,000
13 Pileta de lavar
un
1.00
100,000
100,000
1.00
4,000
4,000
1.00
6,000
6,000
1.00
12,000
12,000
1.00
16,000
16,000
5 Codo 90 40mm
un
1.00
2,000
2,000
6 Codo 45 40mm
un
1.00
2,000
2,000
7 Codo 90 50mm
un
1.00
3,000
3,000
8 Codo 45 50mm
un
1.00
3,000
3,000
9 Codo 90 100mm
un
1.00
10,000
10,000
10 Codo 45 100mm
un
1.00
10,000
10,000
17 Desengrasador PVC
un
1.00
50,000
50,000
un
1.00
50,000
50,000
1.00
20,000
20,000
1.00
30,000
30,000
1.00
35,000
35,000
1.00
35,000
35,000
1.00
37,500
37,500
1.00
40,000
40,000
1.00
45,000
45,000
1.00
50,000
50,000
1.00
55,000
55,000
1.00
45,000
45,000
1.00
50,000
50,000
1.00
60,000
60,000
1.00
30,000
30,000
DESAGE CLOACAL
DESAGE PLUVIAL
Sanitario
Pgina 16 de 22
e-constructor
Costeo de Obra
TRANSFORMADOR
1 Transformador monofsico 5KVA
un
1.00
3,000,000
3,000,000
un
1.00
4,500,000
4,500,000
un
1.00
5,500,000
5,500,000
un
1.00
6,500,000
6,500,000
un
1.00
15,000,000
15,000,000
un
1.00
20,000,000
20,000,000
un
1.00
40,000,000
40,000,000
un
1.00
50,000,000
50,000,000
un
1.00
70,000,000
70,000,000
un
1.00 115,000,000
115,000,000
1 Tablero Elctrico
un
1.00
un
1.00
un
1.00
60,000,000
60,000,000
un
1.00
65,000,000
65,000,000
un
1.00
75,000,000
75,000,000
un
1.00
95,000,000
95,000,000
un
1.00 120,000,000
120,000,000
un
1.00 180,000,000
180,000,000
un
1.00
1 Cable 1mm
1.00
1,000
1,000
2 Cable 2mm
1.00
2,500
2,500
3 Cable 4mm
1.00
3,500
3,500
4 Cable 6mm
1.00
5,000
5,000
5 Cable 10mm
1.00
7,000
7,000
1.00
1,200
1,200
1.00
1,800
1,800
1.00
3,000
3,000
TABLERO ELECTRICO
GRUPO GENERADOR
BANCO CAPACITOR
1 Banco Capacitor
CONDUCTORES
1.00
4,500
4,500
1.00
6,500
6,500
1.00
5,500
5,500
1.00
10,000
10,000
1.00
13,000
13,000
Elctrico
Pgina 17 de 22
e-constructor
Costeo de Obra
ILUMINACION
1 Lmparas de bajo consumo 24W
un
1.00
20,000
20,000
un
1.00
45,000
45,000
un
1.00
85,000
85,000
un
1.00
30,000
30,000
un
1.00
20,000
20,000
un
1.00
40,000
40,000
un
1.00
55,000
55,000
8 Farolas
un
1.00
150,000
150,000
1 Ascensor 400Kg
un
1.00 150,000,000
150,000,000
2 Ascensor 500Kg
un
1.00 200,000,000
200,000,000
3 Ascensor 600Kg
un
1.00
un
1.00 250,000,000
250,000,000
un
1.00 100,000,000
100,000,000
un
1.00
un
1.00
5,000,000
5,000,000
un
1.00
2,000,000
2,000,000
ASCENSOR
ESCALERA MECANICA
1 Escalera mecnica
PARARRAYOS
SOLDADOR
1 Equipo de Soldar
COMPRESOR
1 Compresor 2.5HP 100litros
Elctrico
Pgina 18 de 22
e-constructor
Costeo de Obra
CONTROL DE ACCESO
1
un
1.00
6,000,000
6,000,000
un
1.00
3,500,000
3,500,000
un
1.00
600,000
600,000
un
1.00
350,000
350,000
un
1.00 10,000,000
10,000,000
un
1.00
350,000
350,000
glob
1.00
5,000,000
5,000,000
8 Mano de Obra
glob
1.00
2,500,000
2,500,000
un
1.00
3,500,000
3,500,000
un
1.00
1,000,000
1,000,000
un
1.00 50,000,000
50,000,000
un
1.00
8,000,000
8,000,000
un
1.00
5,000,000
5,000,000
glob
1.00
5,000,000
5,000,000
7 Mano de Obra
glob
1.00
4,000,000
4,000,000
DETECCION DE INTRUSOS
1
un
1.00
6,000,000
6,000,000
un
1.00
1,500,000
1,500,000
un
1.00
50,000
50,000
un
1.00
450,000
450,000
un
1.00
250,000
250,000
un
1.00
500,000
500,000
un
1.00
350,000
350,000
glob
1.00
5,000,000
5,000,000
9 Mano de Obra
glob
1.00
5,000,000
5,000,000
Seales Dbiles
Pgina 19 de 22
e-constructor
Costeo de Obra
TELEFONIA Y DATOS
1 Bocas de red
un
1.00
85,000
85,000
un
1.00
1,000,000
1,000,000
un
1.00
30,000
30,000
un
1.00
35,000
35,000
un
1.00
25,000
25,000
un
1.00
400,000
400,000
7 Line Cord de 3m
un
1.00
20,000
20,000
8 Pach Cord de 1m
un
1.00
20,000
20,000
9 Pacheras
un
1.00
700,000
700,000
un
1.00
175,000
175,000
11 Toma telefnica
un
1.00
85,000
85,000
un
1.00
5,000,000
5,000,000
un
1.00
200,000
200,000
14 Fibra ptica
1.00
100,000
100,000
Seales Dbiles
Pgina 20 de 22
e-constructor
Costeo de Obra
DETECCION DE INCENDIO
1 Pulsador manual
un
1.00
175,000
175,000
2 Alarma audiovisual
un
1.00
400,000
400,000
3 Detector humo/calor
un
1.00
150,000
150,000
4 Detector termovelocimtrico
un
1.00
150,000
150,000
5 Panel de Control
un
1.00
2,500,000
2,500,000
un
1.00
150,000
150,000
7 Iluminacin de emergencia
un
1.00
175,000
175,000
1.00
300,000
300,000
un
1.00
90,000
90,000
un
1.00
90,000
90,000
un
1.00
125,000
125,000
un
1.00
600,000
600,000
un
1.00
350,000
350,000
un
1.00
1,500,000
1,500,000
un
1.00
1,350,000
1,350,000
9 Cajas metlicas
un
1.00
250,000
250,000
10 Mangueras 2 1/2"
1.00
30,000
30,000
un
1.00
650,000
650,000
un
1.00
100,000
100,000
13 Sprinklers (rociadores)
un
1.00
25,000
25,000
un
1.00
80,000
80,000
un
1.00
110,000
110,000
un
1.00
180,000
180,000
un
1.00
220,000
220,000
un
1.00
250,000
250,000
un
1.00
300,000
300,000
un
1.00
740,000
740,000
un
1.00
1,000,000
1,000,000
Incendio
Pgina 21 de 22
e-constructor
Costeo de Obra
AIRE ACONDICIONADO
1 Aire acondicionado 12.000BTU frio
un
1.00
1,450,000
1,450,000
un
1.00
1,600,000
1,600,000
un
1.00
1,850,000
1,850,000
un
1.00
2,200,000
2,200,000
un
1.00
2,500,000
2,500,000
un
1.00
2,650,000
2,650,000
un
1.00
2,750,000
2,750,000
un
1.00
3,000,000
3,000,000
un
1.00
4,000,000
4,000,000
un
1.00
4,500,000
4,500,000
un
1.00
1,750,000
1,750,000
un
1.00
2,500,000
2,500,000
un
1.00
3,500,000
3,500,000
un
1.00
5,800,000
5,800,000
un
1.00
7,000,000
7,000,000
un
1.00
8,000,000
8,000,000
1.00
200,000
200,000
1.00
15,000
15,000
un
1.00
2,000,000
2,000,000
un
1.00
150,000
150,000
un
1.00
185,000
185,000
un
1.00
900,000
900,000
un
1.00
1,050,000
1,050,000
un
1.00
1,350,000
1,350,000
un
1.00
1,750,000
1,750,000
un
1.00
2,000,000
2,000,000
CORTINA DE AIRE
1 Cortina de aire
EXTRACTOR
Climatizacin
Pgina 22 de 22