Beruflich Dokumente
Kultur Dokumente
Sl.
No
Description of Material
Source of Quarry
Unit
Initial cost
of material
at quarry
Cement
Local
1 MT
5800
Steel
Guntur
1 MT
42500
40 mm HBG Metal
Boyapalem
1 Cum
20 mm HBG Metal
Boyapalem
10 mm HBG Metal
Cost of Coveyance
M.R in
KM
C.T in
KM
1145
35
35
462.1
50.00
1 Cum
1210
35
35
462.1
50.00
Boyapalem
1 Cum
875
35
35
462.1
50.00
Gundlakamma
1 Cum
462
55
55
609.1
40.00
Pandillapalli
1 Cum
342
10
10
147.1
40.00
Gravel
Dronadula
1 Cum
98
30
30
399.1
22.00
Boyapalem
1 SQM
210.79
35
35
462.1
50
Certificates:
1. Certified that leads noted above are correct to the best of my knowledge.
2. Certified that sufficient quantity of materials are available at sources.
3. Certified that seigniorage charges are provided as per current S.S.R.
4. Certified that the rates adopted in the lead statement are as per SSR 2014-15.
Total lead
Cost of
Add
in KM
Conveyance Seinerage
8
9
charges
IRR-CCDW-2-5Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
10%
LS
B. MACHINERY:
Sl No
1
2
3
4
UNIT :
Quantity
3599.20
49.08
7.36
4.42
2.94
6.54
14.40
16.36
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Description
Unit
1
2
3
4
5
6
7
Rate
in Rs.
5.80
5.80
1740.00
1800.00
1480.00
855.00
75.00
235.08
41.00
Rs:
Amount
in Rs.
20875.36
284.66
12809.88
7950.96
4358.30
5595.12
1079.76
3845.86
384.59
20.50
57204.99
Rate
in Rs.
54.60
74.30
10.40
74.30
411.00
280.70
7.80
19.00
Rs:
Amount
in Rs.
436.80
594.40
5.20
37.15
411.00
280.70
62.40
152.00
1979.65
Rate
in Rs.
174.20
87.40
140.40
125.40
350.00
335.00
Amount
in Rs.
1393.60
43.70
140.40
1003.20
350.00
335.00
280.00
280.00
280.00
280.00
280.00
70.80
Rs:
3080.00
1120.00
840.00
4580.80
280.00
1158.29
14324.99
Rs:
Rs:
Rs:
Rs:
57204.99
1979.65
14324.99
73509.63
10291.34844
83800.98
5122.31
0.50
Description
C. LABOUR:
Sl No
16.36 cum
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Quantity
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Day
Day
Day
Day
Day
sqm
11.00
4.00
3.00
16.36
1.00
16.36
875.60
0.14 122.60
998.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
16.36 cum
Rate per
cum
(A+B+C+D)/16.36
Total
14.00% Rs:
Rs:
Rs.
IRR-CCDW-2-3
Data
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 295 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No
Particulars
Unit
Quantity
1
C. LABOUR:
Sl No
kg
kg
cum
cum
cum
cum
kg
sqm
10%
LS
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Description
Unit
1
2
3
4
5
6
7
15.38 cum
4537.10
46.140
8.305
4.153
1.384
6.152
15.995
15.38
5.80
5.80
1657.10
1722.10
1387.10
1111.10
75.00
235.08
0.50
41.00
Rs:
Amount
in Rs.
26315.18
267.61
13762.22
7151.19
1919.75
6835.49
1199.64
3615.48
361.55
20.50
61448.61
Rate
in Rs.
54.60
74.30
10.40
74.30
411.00
280.70
7.80
19.00
Rs:
Amount
in Rs.
436.80
594.40
5.20
37.15
411.00
280.70
62.40
152.00
1979.65
Amount
in Rs.
1393.60
43.70
140.40
1003.20
335.00
350.00
3080.00
1120.00
840.00
4306.40
280.00
1088.90
108.89
14090.09
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Quantity
Rate
in Rs.
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Rate
in Rs.
174.20
87.40
140.40
125.40
335.00
350.00
Day
Day
Day
Day
Day
sqm
10%
11.00
4.00
3.00
15.38
1.00
15.38
280.00
280.00
280.00
280.00
280.00
70.80
Rs:
916.10
0.14 128.30
1044.40
Total
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per
cum
14.00% Rs:
15.38 cum
Rs:
(A+B+C+D)/15.38
Rs.
Rs:
Rs:
Rs:
Rs:
61448.61
1979.65
14090.09
77518.35
10852.56909
88370.92
5745.83
IRR-CCDW-2-9 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
kg
sqm
25%
LS
B. MACHINERY:
Sl No
1
2
3
4
UNIT :
Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
31.52
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Description
Unit
1
2
3
4
5
6
7
Rate
in Rs.
5.80
5.80
1722.10
1387.10
1111.10
75.00
235.08
41.00
Rs:
Amount
in Rs.
30164.64
457.04
14112.95
6120.99
7879.92
1560.24
7409.63
1852.41
20.50
69578.32
Rate
in Rs.
54.60
74.30
10.40
74.30
411.00
280.70
7.80
19.00
Rs:
Amount
in Rs.
436.80
594.40
5.20
37.15
411.00
280.70
62.40
152.00
1979.65
Amount
in Rs.
1393.60
43.70
140.40
1003.20
350.00
335.00
3080.00
1120.00
1120.00
4412.80
280.00
2231.62
557.90
16068.22
0.50
Description
C. LABOUR:
Sl No
15.76 cum
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Quantity
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Rate
in Rs.
174.20
87.40
140.40
125.40
350.00
335.00
Day
Day
Day
Day
Day
sqm
25%
11.00
4.00
4.00
15.76
1.00
31.52
280.00
280.00
280.00
280.00
280.00
70.80
Rs:
1019.60
0.14 142.70
1162.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per
cum
15.76 cum
(A+B+C+D)/15.76
Total
14.00% Rs:
Rs:
Rs.
Rs:
Rs:
Rs:
Rs:
69578.32
1979.65
16068.22
87626.19
12267.66714
99893.86
6338.44
IRR-CCDW-2-16 Providing and laying insitu vibrated M-25 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 386 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--60:40, FA : 0.40 cum)
DATA:
RATE ANALYSIS
UNIT :
15.76 cum
A. MATERIALS:
Sl No
Particulars
Unit
Quantity
Rate
Amount
in Rs.
in Rs.
1
Cement for mix
kg
6083.36
5.80
35283.49
Cement for incidentals @ 5 kg / cum
kg
78.80
5.80
457.04
2
Coarse aggregate 20-10 mm
cum
8.510
1722.10
14655.07
Coarse aggregate 10 mm below
cum
5.674
1387.10
7870.41
3
Fine aggregate (Un-Screened)
cum
6.304
1111.10
7004.37
4
Super Plasticizer
kg
20.80
75.00
1560.24
5
Use rate of shuttering
sqm
31.52
235.08
7409.63
Scaffolding @ of shuttering
25%
1852.41
6
Sundries
LS
0.50
41.00
20.50
Total cost of Materials
Rs:
76113.15
B. MACHINERY:
Sl No
1
2
3
4
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Description
Unit
C. LABOUR:
Sl No
1
2
3
4
5
6
7
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Quantity
Rate
in Rs.
54.60
74.30
10.40
74.30
411.00
280.70
7.80
19.00
Rs:
Amount
in Rs.
436.80
594.40
5.20
37.15
411.00
280.70
62.40
152.00
1979.65
Amount
in Rs.
1393.60
43.70
140.40
1003.20
350.00
335.00
3080.00
1120.00
1120.00
4412.80
280.00
2231.62
557.90
16068.22
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Rate
in Rs.
174.20
87.40
140.40
125.40
350.00
335.00
Day
Day
Day
Day
Day
sqm
25%
11.00
4.00
4.00
15.76
1.00
31.52
280.00
280.00
280.00
280.00
280.00
70.80
Rs:
1019.60
0.14 142.70
1162.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14.00% Rs:
Total cost for
15.76 cum
Rs:
Rate per
cum
(A+B+C+D)/15.76
Rs.
Rs:
Rs:
Rs:
Rs:
76113.15
1979.65
16068.22
94161.02
13182.54317
107343.57
6811.14
IRR-CCDW-2-16
Note:
Providing and laying insitu vibrated M-30 ( 28 days cube compressive strength not less than
30 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well cap including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 410 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--60:40, FA : 0.40 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
kg
sqm
25%
LS
B. MACHINERY:
Sl No
1
2
3
4
C. LABOUR:
Sl No
1
2
3
4
5
6
7
UNIT :
Quantity
6461.60
78.80
8.510
5.674
6.304
20.80
31.52
Rate
in Rs.
5.80
5.80
1722.10
1387.10
1111.10
75.00
235.08
41.00
Rs:
Amount
in Rs.
37477.28
457.04
14655.07
7870.41
7004.37
1560.24
7409.63
1852.41
20.50
78306.94
Rate
in Rs.
54.60
74.30
10.40
74.30
411.00
280.70
7.80
19.00
Rs:
Amount
in Rs.
436.80
594.40
5.20
37.15
411.00
280.70
62.40
152.00
1979.65
Amount
in Rs.
1393.60
43.70
140.40
1003.20
350.00
335.00
3080.00
1120.00
1120.00
4412.80
280.00
2231.62
557.90
16068.22
0.50
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Description
Unit
15.76 cum
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Quantity
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Rate
in Rs.
174.20
87.40
140.40
125.40
350.00
335.00
Day
Day
Day
Day
Day
sqm
25%
11.00
4.00
4.00
15.76
1.00
31.52
280.00
280.00
280.00
280.00
280.00
70.80
Rs:
1019.60
0.14 142.70
1162.30
Total
D. Add for contractor's profit and overheads on (A+B+C)
14.00% Rs:
Total cost for
15.76 cum
Rs:
Rate per
cum
(A+B+C+D)/15.76
Rs.
Rs:
Rs:
Rs:
Rs:
78306.94
1979.65
16068.22
96354.81
13489.67405
109844.49
6969.83
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
IRRCCDW-2- 20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork,
24
Note:
DATA:
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Requirement of materials :
For 1 cum CC :Coarse aggregates : 0.80 cum
Blending ratio : 65 :35
Fine aggregate : 0.45 cum
Cement content : 330 kg
Super plasticizer : 1.32 kg
Average output of 300/200 ltr mixer : 50 x 13 x 8 / 330
15.76
cum per day
Formwork & scaffolding :
Shuttering at 2.5 sqm / cum of concrete considered for deck slab and kerb.
Use rate of shuttering for 30 uses ( Annexure-A Item-IRR-CCDW-2-3 )
Rs: 297.55 / sqm
Cost of scaffolding materials considered @ :
250 % of shuttering
Labour for shuttering ( Annexure-B Item-IRR-CCDW-2-3)
Rs:
75.30 / sqm
Labour for erecting & dismantling scaffolding @ :
250 % of labour for shuttering
Labour for concreting :
Requirement of labour for concreting same as in item IRR-CCDW-2-4 with 0.5 mazdoor and 1 mason extra.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
kg
sqm
250%
LS
B. MACHINERY:
Sl No
1
2
3
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
Unit
Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
39.40
15.76 cum
Rate
in Rs.
5.80
5.80
1722.10
1387.10
1111.10
80.00
297.55
41.00
Rs:
Amount
in Rs.
30164.64
457.04
14112.95
6120.99
7879.92
1664.26
11723.55
29308.86
41.00
101473.21
Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95
Amount
in Rs.
1518.40
48.05
1092.80
770.00
370.00
3245.00
1180.00
1180.00
4649.20
295.00
2966.82
7417.05
24732.32
1.00
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
2.00
1.00
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
250%
11.00
4.00
4.00
15.76
1.00
39.40
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1569.31
0.14 219.70
1789.01
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14.00% Rs:
Total cost for
15.76 cum
Rs:
Rate per cum
(A+B+C+D)/15.76
Rs.
Rs:
Rs:
Rs:
Rs:
101473.21
1390.95
24732.32
127596.48
17863.50778
145459.99
9229.69
DATA:
and other deleterious matter, dressing of sides and bottom and backfilling with approved material.
Depth upto 3 m
Unit = cum
Taking output = 240 cum
cum
Unit
240.00
A. Materials:
Sl No Description
Unit
Quantity
Rate
Amount
in Rs.
in Rs.
NIL
0.00
0.00
0.00
B. Machinery:
Sl No Description
Unit
Quantity
Hydraulic
excavator 1.0 cum
bucket capacity
hour
Fuel/ Energy
charges
Total in Rs.
hour
6.00
Rate
in Rs.
1706.60
Amount
in Rs.
10239.60
6.00
937.80
5626.80
15866.40
C. Labour:
Sl No Description
Unit
Quantity
1
2
3
day
day
hour
0.32
8.00
6.00
work inspector
Mazdoor
crew for excavator
Total in Rs.
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Rate
in Rs.
370.00
295.00
204.10
Amount
in Rs.
118.40
2360.00
1224.60
3703.00
15.40
0.14 2.20
17.60
Abstract
a) Material
b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14.00% Rs:
Total cost for
240.00 cum
Rs:
Rate per cum
(A+B+C+D)/240.0
Rs.
Rs
Rs
Rs
Rs
0.00
15866.40
3703.00
19569.40
2739.72
22309.12
93.00
IRR-CCDW-2
IRR-CCDW-2-1
Providing, fabricating and placing in position reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with
1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 50 and all lifts.
DATA:
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
Unit
1
2
3
kg
kg
LS
B. MACHINERY:
Sl No
Description
1
UNIT :
Quantity
1050.00
8.00
3.00
Unit
Quantity
Nil
1000.00 kg
Rate
in Rs.
42.00
70.00
41.00
Rs:
Amount
in Rs.
44100.00
560.00
123.00
44783.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
450.00
295.00
Rs:
Amount
in Rs.
370.00
2700.00
3245.00
6315.00
Rs:
Rs:
Rs:
Rs:
44783.00
0.00
6315.00
51098.00
7153.72
58251.72
58.25
0.00
0.00
Unit
1
2
3
Day
Day
Day
work inspector
Bar bender
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Quantity
1.00
6.00
11.00
8 kg
5 percent
6.30
0.14 0.90
7.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
1000.00 kg
Rate per kg
(A+B+C+D)/1000.0
14.00% Rs:
Rs:
Rs.
IRRProviding and filling murrum / gravely soil ( CNS soil ) for foundation or around pipes
CCDW-7- including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by earth
2
masters to achieve density control of not less than 95 percent etc., complete with lead
upto 50 m and all lifts.
DATA:
For foundation filling in pits and around pipes requires collection and rehandling of soil.
Output of 2 mazdoors for rehandling at site per day( loose)
:
Output of 1 mazdoor for levelling & compaction / day ( loose )
:
Cartman with double bullock cart for supplying water
:
1mazdoor for watering and miscellaneous works at site.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
Particulars
gravel
6.00 cum
12.00 cum
0.5 day
UNIT :
Unit
Quantity
cum
12.00
0.00
Description
Unit
Quantity
Nill
0.00
0.00
Description
1
2
3
Unit
Quantity
Day
Day
Day
0.50
0.50
6.00
10.00 cum
Rate
in Rs.
359.87
0.00
Rs:
Rs:
Amount
in Rs.
4318.44
0.00
0.00
4318.44
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
395.00
370.00
295.00
Rs:
Amount
in Rs.
197.50
185.00
1770.00
2152.50
Rs:
Rs:
Rs:
Rs:
4318.44
0.00
2152.50
6470.94
905.93
7376.87
737.70
215.30
0.14 30.10
245.40
ABSTRACT:
A. Cost of Materials including seignorage charges
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
(A+B+C+D)/10.0
10.00 cum
Total
14.00% Rs:
Rs:
Rs.
IRR-CAW-8-1A
Providing and constructing 22.5 cm thick dry rubble stone pitching with pin headers at 2 per
(New Item4 2011-12)
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.207 cum/sqm, Stone Chips : 0.03375cum/sqm, Pin Headers 30cm : 2/sqm)
(For Maintenance works)
DATA:
DATA:
cum
Uncoursed rubble stones at quarry
Nos
Pin header (Through stone) 30 cm
cum
Stone chips at quarry
Total cost of Materials
B. MACHINERY:
Sl No
Description
UNIT :
Quantity
20.70
200.00
3.375
Unit
Quantity
0.00
0.00
Nill
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Description
work inspector
Mason Class II
mazdoor
Unit
Quantity
Day
Day
Day
1.00
5.00
6.00
:
:
:
0.207
200
3.375
:
:
100.00 sqm
5
1
Rate
in Rs.
428.87
23.00
340.00
Rs:
Amount
in Rs.
8877.61
4600.00
1147.50
14625.11
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
370.00
1725.00
1770.00
3865.00
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.
14625.11
0.00
3865.00
18490.11
2588.61526
21078.72
210.79
38.70
0.14 5.40
44.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
Rate per sqm
(A+B+C+D)/100.0
IRR-CCDW-2
IRR-CCDW-2-1
Providing, fabricating and placing in position reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with
1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 50 and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
Unit
1
2
3
kg
kg
LS
B. MACHINERY:
Sl No
Description
1
UNIT :
Unit
Quantity
1050.00
8.00
3.00
Quantity
Nil
0.00
0.00
Unit
Quantity
work inspector
Day
Bar bender
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
6.30
Add contractor's profit and overhead charges
0.14 0.90
labour component/unit qty (including contractor's profit)
7.20
1.00
6.00
11.00
1000.00 kg
Rate
in Rs.
46.50
70.00
41.00
Rs:
Amount
in Rs.
48825.00
560.00
123.00
49508.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
450.00
295.00
Rs:
Amount
in Rs.
370.00
2700.00
3245.00
6315.00
Rs:
Rs:
Rs:
Rs:
49508.00
0.00
6315.00
55823.00
7815.22
63638.22
63.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14.00% Rs:
Total cost for
1000.00 kg
Rs:
Rate per
kg
(A+B+C+D)/1000.0
Rs.