Beruflich Dokumente
Kultur Dokumente
manual
This manual is intended to serve as a basic guide for the installation of Canams Hambro D500 composite
floor system and must be used in combination with the installation drawings that have been approved and
provided by your Hambro supplier. Please contact the supplier should you come across any contradictions
or ambiguities in these documents.
The execution of the instructions contained in this manual is the responsibility of the user and must be
performed in compliance with current building codes and safety standards.
TABLE OF CONTENTS
OVERVIEW........................................................................................................................................................................................6
HAMBRO D-500 COMPOSITE FLOOR SYSTEM.......................................................................................................................10
INSTALLATION...............................................................................................................................................................................12
HANDLING AND STORAGE.........................................................................................................................................................16
JOIST INSTALLATION..................................................................................................................................................................16
TYPES OF ROLLBARS...................................................................................................................................................................20
ROLLBAR INSTALLATION............................................................................................................................................................26
INSTALLATION OF REUSABLE PLYWOOD FORMS................................................................................................................30
CONCRETING STAGE...................................................................................................................................................................36
SAFETY PRECAUTIONS WHEN POURING CONCRETE.........................................................................................................40
REMOVAL OF PLYWOOD FORMS...............................................................................................................................................42
affa !
tous
CANAM
and safety
lth
is
CANA
t segurida
de
lu
Hea
es
n
o
y
r
e
ev ern!
conc M
overview
11
3
4
10
To watch our
installation
videos:
8
7
OVERVIEW
1.
2.
3.
4.
5.
6.
7.
Note: plywood forms are removed after rotating and removing the Rollbars.
HAMBRO
D-500 COMPOSITE
FLOOR sYSTEM
11
INSTALLATION
INSTALLATION
The joists are placed on the walls or beams and
positioned in compliance with the shop drawings
provided by Canam. The anchorage of joist ends are
also shown on the Canam erection drawings.
13
14
15
HANDLING
AND STORAGE
JOIST
INSTALLATION
STORAGE
DAMAGED JOISTS
Care should be taken at all times to avoid damaging
the joists through careless handling during unloading,
storage and/or installation. Note that damaged joists
may impair the performance and safety of the system.
17
JOIST
INSTALLATION
TYPICAL SPACING
Hambro joists are typically spaced at a distance of
4 ft.-1 in. (1,251 mm). Refer to the installation drawings
for each project.
ICF wall
18
19
TYPES OF
ROLLBARS
STANDARD ROLLBAR
21
EDGE-FORMING ROLLBAR
1ft.-3in. (387mm) - RB13 (grey primer)
22
INTERIOR SUPPORT
ROLLBAR RACK
CL
CL
3mm)
1ft.-9in. (53
8
5mm) - RB
2ft.-1in. (63
2in.
mm)
(51
2in.
(51mm)
9
RB
23
3in
(76mm)
Used with walls made of light structural steel, concrete, wood, masonry or with a beam.
24
4in.
(114mm)
ICF wall
Only used with an insulated concrete wall unless specified otherwise on the installation drawings.
25
ROLLBAR
INSTALLATION
19
27
ROLLBAR INSTALLATION
SPACING
In order to support the forms adequately, the Rollbars should be spaced at the intervals indicated on the installation
drawings. There must be a minimum of one (1) Rollbar at 7 in. (178 mm) from the end of each plywood form. As
indicated on the installation drawings, for each sheet of plywood, there must be at least four (4) interior supports
for a standard joist spacing of 4 ft.-1 in. (1,251 mm).
Important: never use pieces of plywood to complete the forms as this could compromise worksite safety.
Whenever possible, it is recommended that Rollbars be staggered from bay to bay so that only one Rollbar end is
in each slot. This will simplify the stripping procedure. This does not apply to temporary bottom chord bracing or
to the first Rollbar nearest the load-bearing wall or beam.
28
THICKENED SLABS
Hanger plates allow for the addition of an increased
layer of thickness to the existing slab (see the table
below for thickness).
inch
mm
51
76
127
152
Perforated plate
29
INSTALLATION
OF REUSABLE
PLYWOOD FORMS
31
NON-STANDARD SPACING
FORMS BETWEEN TWO JOISTS Indicated by X on the Canam plan.
32
33
34
PRECAUTIONS
1. Before any loads are applied or the forms are put in place, at least three (3) joists must be installed
with all the required Rollbars in order to ensure the structural capacity of the Hambro joists.
2. Full sheets of plywood are recommended. When shorter pieces are used, make sure that they are
adequately supported and do not present a safety risk for workers and construction loads.
3. Bundles of plywood and Rollbar racks should be placed on supporting walls or beams, never on the joist
system. The system is not designed for this purpose and can compromise worksite safety.
4. Do not overload the slab or joists during construction with materials such as palettes of cement blocks,
dry stone walls, sand, etc.
5. No materials whatsoever should cover the top chord so as not to impact the joists composite action.
35
CONCRETE STAGE
CONCRETING STAGE
Important: do not use a laser or a theodolite to level the concrete as an accumulation of concrete could
occur due to the deflection of the joists.
Important: always begin the pour in the middle of the joists and not at the extremities.
During the pour, the forms will camber under the weight of the concrete. If a fixed reference point is used
to measure the thickness of the slab, it will not be reliable because the formwork system itself is not fixed.
The reference used to measure slab thickness should be the forms.
When pouring the concrete, maintain the required slab thickness in all areas.
A light vibration should be applied to the concrete during the pour.
The maximum gross weight of the equipment used to pour and polish the concrete should be 600 lb
(275 kg).
37
6in.
(152mm) min.
45
38
PLACING
When placing the concrete, maintain a minimum depth
of 1 in. (25 mm) above the top chord for a nominal 2 in.
(64 mm) slab. The joists are fabricated with a positive
camber to offset the deflection caused by the weight of
the concrete.
39
40
41
REMOVAL OF
PLYWOOD FORMS
43
44
Normal conditions
Hours after
the pour
or
Compressive
strength
Formwork removal
24 hours*
or
48 hours*
or
* This is for normal conditions of pouring and concrete supplier specifications must be followed.
46
Constant temperature
Removal of Rollbars*
Heating1 after placement and
insulation2
Minimum hours
after placement
or
Compressive
strength
48 hours with
heating
or
72 hours
or
1. Following 72 hours of heating, the concrete must be kept at a minimum temperature of 25F (3C).
2. Protection against the cold (insulation or shelter) should be removed gradually to prevent cracking
due to a sudden change in temperature.
*Never remove the plywood before the heating has been turned off as the wood could stick to the concrete and damage the surface.
47
1 866 506-4000
www.hambro.com
Hambro products are sold in Canada by Canam Group Inc., in the United States by Canam Steel Corporation,
or through their respective agents, distributors or representatives in those countries.
Canam Group Inc., 2003-2013
Revised 09/2013
Printed in Canada 09/2013