Beruflich Dokumente
Kultur Dokumente
FRACTURE PERFORMANCE
PROJECT DESCRIPTION 1
submitted to
Dr. Denis Jelagin
AH2905 - Advanced Pavement Engineering Analysis and Design
October 14, 2014
by
Octavian Babiuc
Ali Taher
Table of Contents
1 Introduction
2 Methods
2.1
Geometry . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.2
Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.2.1
Subgrade . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.2.2
Sub-base . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.2.3
Road base . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.2.4
Bituminouse layer . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.3
Solid Mechanics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.4
2.5
Study scenarios . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
3 Results
14
3.1
14
3.2
Top-down cracking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
3.3
4 Conclusions
20
A first section
21
B second section
21
List of Figures
1
Material definings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
10
MATLAB code . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
11
12
13
14
15
16
17
18
19
20
11
21
11
22
11
23
24
25
26
27
28
29
30
31
14
17
17
33
34
35
Introduction
The goal of this project is to evaluate the effect of temperature on pavement fracture performance. As it is already known, asphalt materials are extremely sensitive to temperature
both due to their visco-elastic nature as well as due to the thermally induced stresses. The
study will be performed on a multilayer pavement system (Figure 1) under different cooling
scenarios.
Although the cooling scenarios are being performed for the duration of just 24 hours, in
time, the potential for low temperature cracking will increase. This is a major distress
in many regions with cold climates and it is believed that the excessive brittleness due
to increase in stiffness and decrease in the ability to relax stress, leads to a buildup of
thermally induced stresses and ultimately cracking of mixtures in pavements. [1]
The cooling scenarios for the project are:
The constant temperature of 2 C during the whole day.
The temperature drops with a constant rate from 2 C to 12 C in 24 hours.
The initial temperature of the pavement system is 2 C. In two hours the temperature
drops to 5 C and during the next 10 hours it reaches to 10 C. The temperature
keeps on being constant for the next 5 hours and after that it drops to 15 C until
the end of the day.
Methods
In order to achieve the goal, a Finite Element program had to be used in order to simulate
the different scenarios, in our case, "COMSOL Multiphysics 4.3b", to create the model and
obtain the required outcomes.
2.1
Geometry
In order to draw the geometry of the pavement system we need to define each layer
(Subgrade, Sub-base, Road Base and Bituminouse) as a rectangle, complying with the
particular size of each of them. The points are being created in order to define the area of
interest when obtaining results.
2.2
Materials
Based on the provided pavement system, all 4 layers have different material proprieties that
define them.
2.2.1
Subgrade
Thermal conductivity: 1.48 W/(m K) - Taken from http: // pubs. usgs. gov/ of/
1988/ 0441/ report. pdf , pg22, as for "Sandstone with air in the pores"
Heat capacity at constant pressure: 920 J/(kg K) - Taken from http: // www.
engineeringtoolbox. com/ specific-heat-solids-d_ 154. html , as for sandstone
2.2.2
Sub-base
2.2.3
Road base
Assumptions:
Note: Excepting Youngs modulus, all other parameters are assumed the same.
2.2.4
Bituminouse layer
Figure 11: MATLAB curve fitting for Prony series (initial value=1000 seconds)
2.3
Solid Mechanics
Roller support
Boundary load
As we have a load of 50 kP a, we can calculate the position at which it must act as follows:
P ressure = Load/Area
50103
800 103 = radius
2
radius = 0.14 m = 14 cm
Reference: Lecture Stress analysis of flexible pavements, Road and Railway Engineering Course
In COMSOL, this is introduced as a Step function (step1) as:
Figure 18: Defining of Long-term elastic proprieties and coefficients for the Generalised
Maxwell model
2.4
As the purpose of this project is to investigate different temperature scenarios, Heat transfer
must be introduced. The Initial values were constant throughout all three scenarios, to a
value of 2 C or 275.15 K.
10
Scenario 1
Scenario 2
For Scenario 2, the temperature in Heat transfer is defined as an Interpolation (int1),
as seen in Figure 21.
11
12
2.5
Study scenarios
The Study has been peformed as a Time-dependent one, over a period of 24 hours, but
also due to the viscoelasticity of the asphalt material.
Scenario 1 and 2 had a Step of 15 minutes (900 seconds),Figure 26a, whereas Scenario
3 had a Step of 5 minutes (300 seconds),Figure 26b, due to the multiple changes that
occurred during the 24 hours interval.
13
Results
The purpose of this project was to examine the effect of all three cooling scenarios on
different fracture modes. The fracture modes are defined as failure criteria in general, but
in our case, we will examine:
Bottom - up cracking (Fatigue cracking)
Top - down cracking (Thermal cracking)
Vertical strain at the top of the subgrade (Rutting)
3.1
Pavement cracking initiates at the bottom of the HMA layer, where the tensile bending
stresses are the greatest, then progresses up to the surface.
Results obtained from COMSOL for all three scenarios:
Scenario 1
14
15
3.2
Top-down cracking
Usually occurs due to a low stiffness on a upper layer caused by high surface temperature,
but it may be also caused by a thick HMA pavement.Throughout all scenarios simulate for
our project, temperatures are decreasing thus stiffness will increase.
Results obtained from COMSOL for all three scenarios:
Scenario 1
16
17
3.3
18
19
Conclusions
The project goal, the effect of temperature on pavement fracture performance, is a topic of
great interest for the reason that it tries to observe the response of a pavement structure
to different temperature cooling scenarios and it provides the knowledge to create a more
reliable asphalt mixture.
COMSOL resulted in the end to test our abilities to learn a new software, of great interest
to todays developing pavement industry.
The results experienced by our model might not be sufficient for some situations, as
encountered in the Rutting chapter in Scenarios 2 and 3 (Figure 34,35), and further
analysis of these kind of specific situations must be engaged, to achieve more detailed plots
that can analyze them. One step in carrying out this, might be to increase the time-span
to a greater extent.
20
References
[1] University of Wisconsin-Madison, "Task 5- Modeling of Asphalt Mixtures Contraction and Expansion Due to Thermal Cycling"// https:
//www.google.se/url?sa=t&rct=j&q=&esrc=s&source=web&cd=4&ved=
0CDUQFjAD&url=http%3A%2F%2Fwww.dot.state.mn.us%2Fmnroad%2Fprojects%
2FLow_Temp_Cracking%2Fpdfs%2FTask%2520Reports%2FT5%2520-%2520Thermal%
2520Modeling%2520(revised%252029mar12).docx&ei=J3stVLHHM-HMyAOvpILgDA&
usg=AFQjCNEE4LV4EQYBZSKnvSOsa-4CSxlfng&sig2=7JHFFWeLPgFb7dyrwGReoQ&
bvm=bv.76477589,d.bGQ&cad=rja
[2] Emmanuel O. Ekwulo and Dennis B. Eme, "Fatigue and rutting strain analysis of flexible pavements designed using CBR methods"// https://www.google.se/url?sa=
t&rct=j&q=&esrc=s&source=web&cd=2&ved=0CCMQFjAB&url=http%3A%2F%2Fwww.
ajol.info%2Findex.php%2Fajest%2Farticle%2Fdownload%2F56271%2F44715&ei=
l0E9VI-1CuroywOFxYK4Cg&usg=AFQjCNGzaQNVdCzHqlUCkB-3Q_EplcjRlg&sig2=
8g33Dd_U_d6aIvd9gszIWg&bvm=bv.77412846,d.bGQ&cad=rja
21