OWNER
CONSTRUCTION MANAGER
CONSULTANT
GENERAL CONTRACTOR (GC)
SUBCONTRACTORS (SUBS)
CWM COORDINATOR :
TELEPHONE:
preparing the site for the construction of the new tower. The following phases will involve the
construction of all three structures. Though the potential environmental impacts of the later phases
must be considered, the first phase is considered to be the most disruptive to the environment.
Generally Construction waste will arise on a Project mainly from: (Excavation/ Demolition /Unavoidable
construction work/Material surpluses/Damaged materials)
The work generally will consist of The construction of 5.970 m 2 of.
Construction Estimated time will take :
3.5 years
The main waste categories as of its material types and streams are as follow:
1-Construction Targeted Recyclables (Packaging/metals/plastics/and glass)
2-Construction Reinforcements Steel Rebars
3-Construction Hardcore Waste ABCs
4-Construction Non- recyclables
5-Construction Workforce trash and waste
6-Construction Hazardous Waste
7-Construction Job Site offices waste (Paper/metals/plastics/glass/Kitchen&general waste)
Site Description
The project site is located in the Sharq district of Kuwait City, Kuwait. The site is bound to the north
by Al-Hilali Street and to the East by Jaber Al-Mubarak Street. The surrounding area is highly
urbanized with several skyscrapers in proximity to the site. The site was previously cleared and
prepped for another construction project that did not follow through.
LEED Caculation
No
3
Concrete
Steel Rebars.
Structural metal/steel.
Plaster board/gypsum.
Wood
Asphalt.
Paving.
GRC
Glass.
Plastics
Packaging
Office paper
Organic Waste/Kitchen
Mixed Construction Waste
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
Yes
Yes
Yes
Yes/Recycled
Yes/Salvaged
Yes/Recycled
Yes/Recycled
Yes/Recycled
Yes/Recycled
Yes/Recycled
Yes/Recycled
Yes/Recycled
Yes/Recycled
Yes/Recycled
Yes/ Recycled
No/ Municipal waste company
No/ Landfill
(Verified in Rev02)
Estimated Quantity
-
Disposal Method
Excavation hole was an
existing condition when
ACTC start duties.
4
Handling Procedure
Keep separated in designated
areas on site. Reuse in site
landfilling, and to Landfill.
Material
Estimated Quantity
Plywood, Squares
Disposal Method
Reuse at NBK Site, Land
filling, cut and fill works
Reuse at NBK Site, landfill
Concrete Casting
Concrete Masonry Units
4,400 TONS
Metals
16.7 TONS
GRC
73.75 TONS
Salvaged Sold
Recycle at
MRC Metal recycling Co.
Recycle at
EPIC
Paint
REV 2
Insulation
Flooring
Carpet and pad
REV 2
REV 2
BP5
Glass
8 TONS
Plastics
5.3 TONS
Cardboard
9 TONS JANGO
Handling Procedure
Reuse or recycle at
Environmental Depot; Cost
= $0.21/lb latex, $0.37/lb oil
Reuse, landfill
Reuse, landfill
Reuse or recycle with
carpet manufacturer
Keep separated in designated
Recycle at
areas on site. Place in
MRC Metal recycling Co.
Glass/Plastic /Meta/
(MRF)
Cardboard containers
Keep separated in designated
Polyethylene pipes to be
areas on site. Place in
returned
Glass/Plastic /Meta/
Recycle at
Cardboard containers
MRC Metal recycling Co.
Glass/Plastic /Meta/
Cardboard containers
Recycle at
Keep separated in designated
areas on site. Place in
MRC Metal recycling Co.
Glass/Plastic bottles/Metal
Cans/Mixed Paper/
Cardboard container
Material
Office paper
Estimated Quantity
#
Disposal Method
Recycled at
MRC Metal recycling Co.
Handling Procedure
Keep separated in designated
areas on site. Place in
Glass/Plastic bottles/Metal
Cans/Mixed Paper/
Cardboard container
TOTAL
Waste reduction will be achieved through building design, and reuse and recycling efforts will be
maintained throughout the construction process.
After assuring the full coverage of all wasting types in terms a separate and weighed collection,
and with all possible supporting tools (Containers/weighing tools/ site personnel/and awareness)
,then Waste Calculation results will be under a continuous verification every month to reach
more compliance with the LEED goal of maximum diverting from land fill, all non-recyclables will
be more worked out more and more to explore ways of reusing, salvaging, or recycling.
Evaluation Plan:
Ahamdiah Contracting Co. as the GC developed, Signage addressing the recycling on site , it
will be more developed to incorporate progress to date for achieving the projects waste
recycling goal of 75% or more by weight of the total project waste stream.
Waste General Foreman has a Construction Forms as a waste log, to record every waste
diversion from site, in terms of its weight, every material type has a separate form for logging.
All will be compiled together in the end of the month for Waste calculation results.
3. Polyethylene pipes longs, are being chosen to minimize the cutting to the most possible, all
remaining cutting will be weighed and returned to the supplier.
4. Steel rebars where considered in design so to assure the lowest waste estimates.
5. All wooden members used in excavation will be used future projects of ACTC so it will be
returned to stores.
6. All segregated materials containers will be expected to be reused again in construction,
specially steel reinforcements cuttings.
7. In the first phases of the project land clearing are being used in land filling , as a p art of the cut
and fill works, for the land grading to stabilize site slopes, required for LEED ESC Plan.
o metal cans
The Construction Waste Reduction Plan is already implemented and executed as follows and
as on the chart:
o Salvageable materials will be diverted from disposal where feasible.
o There will be a designated area on the construction site reserved for a row of
dumpsters each specifically labeled for respective materials to be received.
o Before proceeding with any removal of construction materials from the
construction site, Recycling Coordinators will inspect containers for compliance .
o Wood cutting will occur in centralized locations to maximize reuse and make
collection easier.
o Hazardous waste will be managed by a licensed hazardous waste vendor.
ACTC will conduct a pre-award meeting for subcontractors. Subcontractors under consideration
will be required to attend the meeting to review project goals and requirements with the project
team. Attendance will be a prerequisite for award of subcontracts. A sign-off will be required by
subcontractors attending the meeting that the project goals are understood. This document will
be an attachment to every subcontract. Copies of the attachment will be posted prominently at
the jobsite.
Safety team
Concrete foreman
Truck driver 1 concrete
Truck driver 2 mixed waste
Store keeper
Movable crane driver
Pop cat Driver
Attached site conference Site personnel signatures for LEED waste management plan introduction
and highlight on waste segregation.
All recycling containers are clearly labeled. Containers are located in close proximity to excavation
hole in which recyclables/salvageable materials will be placed.
Lists of acceptable/unacceptable materials will be posted throughout the site.
All subcontractors will be informed in writing of the importance of non-contamination with other
materials or trash.
Recycling coordinator and his team shall inspect the containers on a weekly basis to insure that no
contamination is occurring and precautions shall also be taken to deter any contamination by the
public.
A jobsite Graphics boards, will be mounted for acceptable and non-acceptable items for
recycling, and also in a ways of (Does and Donts)
A jobsite Graphics boards, will be mounted for Hazardous waste Storage areas, and all
safety requirements for any ignitable materials.
Motivation Plan:
The project team will develop and publish a project mission statement that can be distributed to
the subcontractors, attached to subcontracts, and posted at the jobsite.
= KD255
10
6,389.45 tons
Recycling Calculation:
If all construction waste was disposed in landfill: 6,389.45 tons
Total of recycled construction waste (diverted from land landfill) : 5,713.25 tons
Percent of Recycling (Diversion from Landfill) = 89.42 %
Diversion/Recycling Hauler
or Location
Diversion/Recycling
Quaintly
Units
(tons)
Concrete *0
EPIC
4400
tons
GRC
EPIC
73.75
tons
Paving
EPIC
tons
Flooring
EPIC
tons
Asphalt
EPIC
tons
1200
tons
Diversion/Recycling
Materials Description
Steel Rebars
11
Structural Steel/Metals
MRC
16.7
tons
Glass
MRC
tons
Plastics
MRC
5.3
tons
Packaging / Paper *1
MRC
9.5
tons
Hazardous Waste *2
tons
*0
*1
5,713.25 tons
Landfill
Materials Description
Landfill
or Location
Hauler
Municipal/Kitchen Waste *4
Tanzifico Company
Hazardous Waste
Landfill
Quantity
675
tons
46.1 + #
tons
tons
676.2
tons
6,389.45 tons
89.42 %
The derived waste value is only as from the construction field only as per feedback from subcontractors BMB/Jangho , Still
Office Paper is under more verification and study for next month plan, offices waste plan.
*2 Hazardous waste as (Sealants, paint, coating, and adhesives) including the two grades of hazardous if toxic or ignitable;
all have been planned to be handled by authorized haz vendor, handling procedures will include separate methods for solid,
and liquids waste, in addition to the proper ways of storage as instructed in the all materials data of each material. More
information and numbers/values at Rev02
*3
Estimates of General construction waste, is only representing those materials which came out of construction field
building components , an estimate of 16 tons / month, Basis of estimating is to give logic values, that will turned to exact at
following months #
*4
The counted number of organic/municipal waste is based yet only on site workforce personnel as 300 in day, 100 night, as
100 gram/person/day gives in total 40 kg/day and 1.2 tons/month and finally gives 46.1 tons in the 3.5 years, taking in
consideration that values for office staffs as personal trash or kitchen waste needs to be added. In rev02 #
12
Diversion/Recycling
Hauler or Location
Diversion/Recycling
Quantity
Units
(tons)
Concrete *
EPIC
4400
tons
GRC
EPIC
73.75
tons
Paving
EPIC
tons
Flooring
EPIC
tons
Asphalt
EPIC
tons
1200
tons
Structural Steel/Metals
MRC
16.7
tons
Glass
MRC
tons
Plastics
MRC
5.3
tons
Packaging / Paper
MRC
9.5
tons
Hazardous Waste
tons
Diversion/Recycling
Materials Description
Steel Rebars
5,713.25 tons
Landfill
Materials Description
Landfill
or Location
Hauler
Municipal/Kitchen Waste
Tanzifico Company
Hazardous Waste
Landfill
Quantity
Units
(tons)
675
tons
46.1 + #
tons
tons
676.2
6,389.45 tons
89.42 %
tons
**
** The table always under development in terms of perusing more to the exact numbers than the logic
numbers, and this will happen from covering (weighing) all the categories of waste, recyclables vs nonrecyclables. Especially the general construction waste, and the offices waste. More will be in Rev01.
13
14
Who