Beruflich Dokumente
Kultur Dokumente
TWO(2) X 500MW
MONG DUONG 1 THERMAL POWER PLANT
APPROVED
Approved without exception
AC
RT
RJ
REJECTED
Complete redesign required
IC
FOR INFORMATION
Engineer:
Discipline:
Date:
Soumen Mitra
Senior Mec Engineer
27-Jul-12
26-04-12
H.D.KIM
K.T.NAM
J.W.CHOI
REV.
DATE
DESCRIPTION
DSGN
CHKD
APPD
26-04-12
J.A.SEO
M.K.LEE
J.Y.KIM
REV.
DATE
DESCRIPTION
DSGN
CHKD
APPD
PROJECT :
CONSULTANT :
CONTRACTOR :
SUB-CONTRACTOR :
DESIGNED BY
DATE
TITLE :
H.D.KIM
26-04-12
CHECKED BY
DATE
K.T.NAM
26-04-12
APPROVED BY
DATE
PROJECT NUMBER
DOCUMENT NUMBER
REV.
J.W.CHOI
26-04-12
ADB/MD1-TPIP/EPC150911
MD1-0-V-111-09-00008
TABLE OF CONTENTS
I. GENERAL
II. BACKGROUND
IV. BASIC RULES FOR DETERMINING NUMBER AND TYPES OF CHECK VALVES
11
12
13
16
A. Arrangement No. 1
16
B. Arrangement No. 2
17
17
D. Arrangement No. 5
17
17
21
21
22
22
23
LIST OF FIGURES
14
14
15
Figure 4. 3-Way Solenoids in Air Lines to the Spring Side of the Air Piston
15
Arrangement No. 1
19
Arrangement No. 2
19
Arrangement No. 3
20
Arrangement No. 4
20
Arrangement No. 5
20
24
25
25
26
26
I. GENERAL
The following describes Doosans aims and requirements pertaining to the extraction system
and should answer the majority of questions that arise on this subject. The enclosed typical data
form (ATT. #1) will aid in the study of a particular extraction system and overspeed situation. It
will also help determine the requirement for and the proper location of check valves in the
extraction system. Form (ATT. #1) issued for the specific unit must be returned to Doosan
completely filled in for the review of the overspeed potential by the responsible engineering
section. This document, together with DST00132A, Water Induction in Large Steam Turbines
Design Recommendations, should be used in designing the extraction system and controls.
II. BACKGROUND
A wellknown fact among consultants and power companies is that excessive overspeed of a
turbinegenerator shaft can be disastrous. A lesser known fact is that the energy contained in
the feedwater heaters of a steam turbinegenerator power cycle is often sufficient to contribute
significantly to the magnitude of the turbinegenerator rotating speed upon an electrical load
rejection or tripout and must be prevented from doing so by some means, the most common of
which is by the use of check valves. This energy is in the steam contained in the piping from the
turbine to the feedwater heaters and in the heater shells, in the water contained in the feedwater
heaters, as well as in the metal parts.
After a load rejection, the steam admission valves will close, causing the pressure of the steam
already in the turbine to decay. This decay allows the steam in the extraction piping and heater
shell to flow back into the turbine giving its energy to the rotor. This will cause the heater
pressure to decay so that the water which was saturated at the heater pressure under normal
operating conditions will become superheated momentarily, flash into steam, and flow through
the turbine giving up its energy to the rotor. The heat of the metal components provides some of
the necessary latent heat of vaporization.
In applications where steam volumes and water volumes are large, check valves in the
extraction piping are considered necessary to protect the turbine from this energy. The number
of check valves recommended by Doosan depends upon the steam and water volumes and
include the free swing and power assisted types. Two power assisted valves in series (with
proper maintenance and testing) are considered to afford the maximum protection necessary.
Doosan steam turbine design rules and code requirements specify that the turbine controls will
be capable of preventing the turbine speed from rising above a certain maximum value after a
full load rejection or trip. Under this condition, the speed will rise due to the delays in getting
the steam admission valves closed and due to the energy contained in the bottled up volumes of
steam within the turbine. Part of the latter is the extraction system volume. The amount of speed
increase contributed by the extraction system must be held below a certain maximum value by
4
example, the vendor may recommend locating the valve in a straight run of pipe 10 pipe
diameters downstream from any elbow in the pipe and 5 pipe diameters upstream from
the next elbow.
B. SPECIFICATIONS FOR THE FREE SWING PORTION OF THE CHECK VALVE
1. The free swing portion of the check valve must be such that it will freely close with no
flow in the extraction line.
2. The pivot shaft should be a single shaft.
3. On check valves with a circular disc attached to a swing arm there should be a means of
preventing rotation of the disc.
4. On check valves with separate check valve discs and swing arms, there should be two
different positive means of assuring the disc will not come off the swing arm. Just
pinning the nut to the disc threads is not satisfactory. It is preferred that the disc and
swing arm assemblies be secured by the valve vendor such that field removal can only
take place by pulling the pivot shaft and removing the whole assembly rather than by
allowing internal removal of the disc off the swing arm.
5. Field tests have shown that on a turbine load rejection small diameter high pressure
check valves stroke from full open to closed position in 0.1 seconds. As the valves
increase in diameter and the steam pressures decrease, the stroke times increase to
approximately 0.6 seconds. The check valves should be capable of these repeated
closures without sustaining permanent deformation that would prevent shutoff of steam
on reverse flow.
6. Disc to seat sealing shall be accomplished with metal to metal seals. There shall be no
seal ring screwed into the disc, unless there are two provisions for locking the screws in
place, for example, bottoming screw torqued and staked secured in place. There shall be
no screwed in seats, unless they are seal welded in place.
7. The disc must be designed such that it will cause minimum pressure drop when open.
8. The use of a counterweight on a lever, external to the valve body, to balance the weight
of the disc for the purpose of reducing pressure drop is permissible, but only if the
following conditions are met.
a. The lever should be short enough so that it is impossible to develop more than 50% of
6
the torque required to open the valve under no flow conditions no matter where the
weight is positioned on the lever.
b. The weight should be secured positively on the lever. For example, the weight could
be pinned in place on the lever, then the pin should be staked.
c. The shaft seal should meet the criteria set forth in the next items. This will probably
lead to applications where external counterweighting would not be permitted.
9. Shaft sealing has a significant impact on the reliability of the check valve to perform
satisfactorily. Based on field experience the following restrictions are placed on the
type of shaft sealing.
a. To avoid a potential water source of water induction to the turbine, and to prevent
quenching and distortion of the valve, water sealing the shaft is not permitted.
b. To avoid binding of the free swing check valve disc due to overtightening of packing
material, the valve must be designed with shaft seals such that it is not possible to
overtighten packing to restrain free swing motion.
a. Hardened steel bushings with gasketed end caps where the shaft does not protrude
through the valve body
b. Hardened steel bushings with an intermediate steam leak off to the turbine steam seal
system, with no soft packings
d. Soft packing, but with the lost motion device internal to the valve so that the packing
does not restrict free swing motion. This implies that any counterweighting required
must be internal to the valve.
a. The plates should not open to an angle of greater than 85 perpendicular to the flow,
so that re-verse flow will force the plates closed.
b. There should be 1 /2 in. (40 mm) dia. hole drilled through one plate to ensure positive
drainage.
c. The spring should be selected so that it is stressed below its endurance limit.
C. SPECIFICATIONS FOR THE POWER ASSISTED PORTION OF THE CHECK
VALVE
1. The power assisted portion of the check valve shall consist of an actuator designed such that,
on tripping the air system by the turbine air relay dump valve (ARDV), a spring will cause the
actuator to close the check valves.
2. Upon supplying air to the cylinder, the air should compress the spring and allow the check
valve to open. It must not restrict the free swing motion of the check valve disc in the closed
direction.
3. To help assure a fast response when the air system is tripped, the air cylinder and spring are to
be sized so that with the cylinder connected to the valve and with no steam flow:
a. Approximately 30 psig [206.9 kPa (gauge)] [2.1 kg/cm (gauge)] air pressure is required
to lift
the piston from its closed end stop.
b. Approximately 60 psig [413.7 kPa (gauge)] [4.3 kg/cm (gauge)] air pressure is required
to hold the piston against its open end stop. [Assuming air supply pressure to be in the 60
2
to 100 psig(413.7 to 689.5 kPa (gauge)] [4.3 to 7.1 kg/cm (gauge)] range.]
4. To help assure an adequate force level to overcome valve friction, the air cylinder and spring
are to be sized so that:
a. With the cylinder in the closed position, there must be enough spring force to exceed, by a
factor of at least four, the force required to overcome the combined normal friction levels
of the air piston, linkage and valve disc.
b. With the power assist actuator hooked up to the valve, with the check valve disc free to
move, with full steam flow down the extraction line, and with normal friction levels in the
valve and actuator, there will be enough spring force to close the disc to the point where
the disc will have closed off 10% of the cross sectional flow area. If the 10% flow point is
not known, it is accept-able to size the spring to shift the disc from 100% open to 90%
open position of angular travel against the above conditions of full resistance force. At the
90% position reverse steam flow is to be a positive closing force on the disc.
8
5. The power assist actuator should have a stroke such that it would move the check valve to the
3
point where the check valve disc would have closed off at least /4 of the cross sectional flow
area.
6. The power assist actuator should be designed with a convenient means of local daily testing
that the free swing portion of the check valve is still free to move. The testing feature should
be located such that the operator testing the valve can be sure that the valve moves freely
through stroke. Because rod end seals in the top of conventional air closing cylinders tend to
develop excessive leakage with time, testing force margin can be lost. To overcome this
maintenance problem, the heater high level solenoid can be used to accomplish the daily check
valve test. This option is shown in figure 3.
D. SPECIFICATIONS FOR THE PERFORMANCE OF THE AIR SYSTEM
1. The extraction air piping from the turbine air relay dump valve (ARDV) to the individual
power assist actuator must be designed so that the air in the cylinder will depressurize
rapidly. With full rated air pressure in the system and check valve discs in the closed
position, this rate of decay should be fast enough for the air pistons to go through full stroke
in the check valve closing direction within two seconds of tripping the air relay dump valve.
Careful attention to the size and routing of all the air piping is required to minimize the
volume of air contained in the system and yet maximize the response time of the critical air
pistons. In general the following has been used successfully in the field. The main manifold
run from a single ARDV at the turbine end standard down to the first or second tee for the
closing cylinders has worked well when sized to 1 in. (27 mm) inside diameter. Note that for
two ARDVs tied together the main header flow area could be doubled. The individual runs
1
to single air closing cylinders have worked well with the equivalent of /2 in. (13 mm)
tubing. Sub manifolding lines were sized in between the main header and individual runs.
Minimizing the number of elbows is important. Because of the variety of field installations
the above information is only intended as a guide. The architect engineer and customer are
responsible for determining their optimum station layout which will meet the two sec-ond
timing requirement.
It is common practice to provide check valves of the power assisted type even when it has
been deter-mined only a free swing check valve is required for adequate overspeed
protection. The extra air piping and volume involved can make it very difficult for those
valves requiring power assist for overspeed reasons to have a satisfactory response time. The
following two subsections describe possible alternatives for arranging the critical and non
critical power assists. Subsection a. is for a single air relay dump valve (ARDV) and
9
an ARDV with critical positive assist check valves must not pose any problems in restricting
flow on tripping the air system from the ARDV. See Figure 3 for the arrangement. Thus the
solenoid valve must be of the direct acting type, and must have been selected for fast dumping
of the cylinder through the cylinder to inlet port direction. Fast dumping through the cylinder
to vent connection is not as important as through the cylinder to inlet connection. This is
because the cylinder to vent connection is used on heater level as a protection against water
induction. Water from a leaking feed-water heater is a relatively slow process. Flow rates for
such an event have been given in ASME TDP1 for use in timing when shutoff valves have to
1
the Doosan.
Items 16 and 17 are to be filled in to show what is being done to meet the individual extraction
requirements.
Items 18 through 26 should be filled in for each different check valve that is used in the
extraction system. Note these items are not under the column headings of items 1 through 17.
The information requested is to assist in assuring that the reliability and performance of the
check valves will be satisfactory. They are grouped in four major areas.
Items 18, 19, and 20 relate to general information about the check valves.
Items 21 and 22 relate to the free swing performance of the check valve.
Items 23, 24, 25 and 26 relate to solenoid valve restriction of flow. Additional sheets may be
needed to fill in the data for all types of valves.
To eliminate late changes and corresponding higher costs the form should be returned to the
Doosan by the date shown on the top of ATT. #1 in partial satisfaction of schedule item ATT.
#1. It is appreciated the final data (to meet partial satisfaction of schedule item ATT. #1), might
not be obtained by this date, but good estimates would indicate whether a problem exists.
VI. OVERSPEED PROTECTION AGAINST EXTRACTION SYSTEM AUXILIARY
STEAM SUPPLIES
Should the unit undergo a load rejection, it is subsequently free to accelerate in speed at a rate
directly proportional to any energy input to it (minus rotation losses) and inversely
proportional to the inertia of the rotors. From the worst case point of view, it must be assumed
that no auxiliary load remains on the generator.
The form of energy input, which we are concerned with here, is due to externally unlimited or
auxiliary sup-plies of steam which enter a feedwater heater, an extraction pipe, a branch of an
extraction pipe or any auxiliary turbine or vessel equipment associated with an extraction pipe.
Interconnections between extractions on the same unit may also come under the above
category depending upon whether or not they constitute a by-pass path around normal
protective devices (i.e. main stop valves, control valves, combined valves, etc.). If such an
auxiliary supply, upon a worst case failure of regulators, reducers, various types of valves, etc.,
could have an open backflow path through the extraction piping to the main turbine wheels
and to the con-denser at full vacuum, the location of that supply must then receive special
consideration. Typically, because of the low condenser pressure, sonic flow generally would
exist somewhere in the backflow path. If the power of the resulting backflow can overcome
rotation losses, the unit will accelerate towards an unsafe speed as determined by the available
power then being equal to the losses at that speed. Any such source of supply is then defined
as being externally unlimited.
13
14
The regulators, reducers or valves mentioned above, which in an emergency would require
manual operator action, are not acceptable as turbine protective devices. Two (2) power
assisted check valves (PACV) must be situated in series in some way between the auxiliary
supply and the turbine extraction wheel space. Both PACVs must be positively closed by
action of the turbine emergency trip system through the extraction relay dump valve. This is
consistent with the two in series valves in the more common turbine flow paths (main
stop/control valves, crossover administration stop/control valves, speed matching valves and
15
16
B. ARRANGEMENT NO. 2
For plant cycles in which the BFP turbine primary supply branches from an extraction
pipe which also supplies a deaerator, it would not be necessary to install two additional
PACVs. These will already be provided in the extraction pipe to protect the main turbine
from the overspeed hazard presented by the large amount of water in the deaerator. The
requirement here is that the BFP turbine primary supply should branch from the
extraction pipe at some point between the PACVs and the deaerator. In this way the
same PACVs will afford the required protection of the main turbine against either the
deaerator or the BFP turbine auxiliary supply. However, for the reasons outlined under
Arrangement No. 1, the BFP turbine manufacturer may require the FSCV. Again, the two
PACVs also provide the required protection against any other process systems.
C. ARRANGEMENT NO. 3 AND 4
These arrangements are simply generalizations of 1 and 2, respectively, just discussed. It
is recognized that there may be several other types of BFP turbine cycles and designs.
There are also a number of other plant process systems which might take their primary
supply from a main turbine extraction pipe, but also require an auxiliary source of steam
into the same branch. Discounting any auxiliary supplies of steam for the moment, the
volume of a process system, such as might be in a plant heating network, could become
so large as to constitute a nearly unlimited source of steam. All such volumes should be
taken into account by the customer when filling out Form ATT. #1, shown in this bulletin.
D. ARRANGEMENT NO. 5
Upon occasion, the volume of steam and water in a closed feedwater heater will require
only a simple FSCV, or possibly no valve at all, for protection of the main turbine. In
determining and approving protective FSCV or PACV(s) requirements, for heaters and
deaerators, the Doosan will use the data supplied on Form ATT. #1. Since such
determinations could result in some liberties in choosing the numbers and sizes of FSCV
or PACVs, the customer should complete and return the Form ATT. #1 at the earliest
possible date. The PACV is generally the more costly valve with size and it is desirable to
have the optimum arrangement of valves in an extraction system, from the standpoint of
normal flow head losses, and still meet the main turbine protective requirements. Form
ATT. #1 also provides space in which to describe the auxiliary steam supplies we have
mentioned.
The following list gives the possible energy sources which could result in excessive
overspeed if a load rejection occurred.
A. The deaerator and feedwater steam and water storage
B. Evaporator vapor combined with boiler feed pump turbine exhaust, or others
C. Pegging lines or startup steam connection from the boiler
D. Interconnection from the cold reheat line with some lower extraction
E. Interconnection from an extraction stage of another turbine
18
19
turbine rotor if reverse flow occurs. In some cases the piping may restrict the flow to such an
extent that the excessive overspeed will never be reached even though the total energy storage
is very large.
IX. PRESSURIZATION OF FEEDWATER HEATERS
On some fossil units, for example oncethru boilers of the Bensen or Universal design, it has
been deter-mined that there may be a severe overspeed problem even during the startup phases.
Consequently, it is a requirement to have two (2) PACVs between any heater receiving
pressurizing steam or pressurizzing water and the turbine. Also, it is a requirement to have two
(2) PACVs between the turbine and any heaters receiving pressurizing energy through
cascaded drains of higher point heaters.
Nuclear units are considerably more complicated in the feedwater cycle than fossil units.
Pressurizing feed-water heaters on nuclear units makes the opportunity greater for equipment
failure, control system failure and operator failure to cause excessive turbine overspeed or
water induction as compared to fossil units. Doosan Large Steam Turbine Department
recommends against pressurizing feedwater heaters on nu-clear units.
X. PROBLEMS OF LOWPRESSURE (LP) HEATER APPLICATION
Experience has shown that it is permissible, from an overspeed protection point of view, to
eliminate check valve protection in the last one or two LP stage heaters. This requires: first, the
proper location of the check valves of the other extraction lines and second, actual steam and
water volume reduction in the LP heaters by changing pipe routing, relocating heaters,
maintaining a lower water level in the heater, etc. or by the addition of a baffle plate below the
LP heater tube bundle but above the heater water volume to restrict the rate of flashing and
back flow.
In many cases, the LP heaters have been drained completely dry with the water level
maintained in separate drain receivers, standpipes, etc. A heater water level control adjusted to
hold the amount of saturated water storage at a minimum in the heater shell itself has been
possible in the majority of cases where it is necessary to do so. Such arrangements in heater
design and drain system have become increasingly important with the increasing popularity of
LP heaters located in the condenser neck where it is difficult to provide check valves in the
extraction lines.
Figures 5 through 8 show some typical methods of water volume reduction in heaters. They do
not cover all the possible methods or means of accomplishing this reduction but are
representative of some in use today.
Some gains can be made by considering the case shown in Figure 9, where there are X number
of extraction lines coming from the number Z extraction stage of LPA shell going to heater YA
21
and there are X number of extraction lines coming from the number Z extraction stage of LPB
shell going to heater YB. If these steam extraction lines or heaters are not intertied, they may
be treated as separate extractions to separate heaters. We suggest that the data requested on
DST00173A be provided for each separate heater and extraction such as YA & YB in this
example.
XI. WET EXTRACTIONSNUCLEAR UNITS
It should be recognized that the wet extraction steam associated with saturated steam cycles will
introduce variable quantities of saturated water in the extraction piping system.
The extraction lines, therefore, must be adequately pitched and drained to prevent or minimize the
accumulation of water in the extraction piping.
Where feedwater heaters are located such that the extraction line does not continuously pitch
downward or a check or isolation valve is not present between the turbine connection and the heater
shell, special attention must be given to providing adequate drainage. This could be accomplished by
use of a drain pot with a level control, high level alarm and a bypass drain dumping directly to the
condenser.
When a check or isolation valve is located in an extraction line, the extraction piping between the
turbine connection and the valve must be adequately drained. This is done to prevent accumulation of
water when the valve is closed.
For full details of the extraction drain recommendations see the Turbine Steam Drain
Recommendations.
XII. WATER INDUCTION
The introduction of water into any part of the turbine can cause serious damage to the shells, rotors,
buckets and thrust bearings. The problem has reached serious proportions. The Doosan has revised
and reissued design recommendations to prevent water induction in large steam turbines. These
recommendations are outlined in DST00132. These recommendations closely follow the
Recommended Practices for Prevention of Water Damage to Steam Turbines Used for Electric
Power Generation, issued by the American Society of Mechanical Engineers, ASME, Turbine Water
Damage prevention Committee.
Design of an extraction system consistent with the safety and reliability required of a large steam
turbine must be undertaken by reviewing the above two publications along with this publication. This
publication is now used only to consider the extraction system from an overspeed viewpoint and to
transmit the Doosans requirements to protect the unit from overspeed.
22
23
24
25
26
NOTE: APPROVAL AND/OR COMMENTS OF THE SUBJECT DATA WILL BE RECEIVED BY LETTER
FROM Doosan REVISION AND REISSUANCE OF THIS FORM DOES NOT IMPLY APPROVAL.
27
28
STATION
TB.NO.
REVISION #
DATE
EXTRACTION STAGE NO./ HEATER NO.
1. VOLUME OF PIPING FROM TURBINE TO CHECK VALVES (M3 ) OR FROM TURBINE TO
HEATER PLUS HEATER STEAM VOLUME (M3 ) IF THERE ARE NO CHECK VALVES.
2. VOLUME OF PIPING FROM CHECK VALVE TO HEATER PLUS HEATER STEAM
VOLUME. ITEM 2 IS NOT TO BE ENTERED IF THERE ARE NO CHECK VALVES.
3. VOLUME OF SATURATED WATER IN HEATER SHELL OUTSIDE OF SUB COOLING
SECTION OR IN THE STORAGE TANK OF A DEAERATOR (M3 ) IF THERE ARE CHECK
VALVES.
4. VOLUME OF SATURATED WATER IN HEATER SHELL OUTSIDE OF SUB COOLING
SECTION (M3 ). ITEM 4 IS NOT TO BE ENTERED IF THERE ARE CHECK VALVES.
5. VOLUME OF WATER IN HEATER SUB COOLING SECTION OR IN SEPARATE DRAIN
COOLER, OR IN SEPARATE DRAIN TANK (M3 ).
6. FLOW AREA (CM2 ) OF OPENING BETWEEN SHELL AND SUBCOOLING SECTION, OR
PIPE SIZE BETWEEN HEATER SHELL AND DRAIN COOLER, OR PIPE SIZE BETWEEN
HEATER SHELL AND SEPARATE DRAIN TANK IF THERE ARE NO CHECK VALVES.
7. AUXILIARY STEAM SUPPLY TO HEATER, IF ANY. GIVE MAXIMUM CAPACITY
(KG/HR) PRES SURE, TEMPERATURE AND SOURCE. DESCRIBE SOURCE SO THAT IT
WILL BE KNOWN WHETHER OR NOT THIS SUPPLY WILL BE SHUT OFF UPON CLOSING
OF THE THROTTLE STEAM TO THE TURBINE. ALSO, INCLUDE ANY
INTERCONNECTION BETWEEN TWO EXTRACTION STAGES AS IN AUXILIARY STEAM
SUPPLY TO THE LOWER STAGE.
8. AVAILABLE ENERGY OF STEAM, KILOJOULES/M.3
9. AVAILABLE ENERGY OF WATER, KILOJOULES/M.3
10. TOTAL AVAILABLE ENERGY OF STEAM UNRESTRAINED BY CHECK VALVES
KILOJOULES (#1) X (#8)
11. TOTAL AVAILABLE ENERGY OF STEAM RESTRAINED BY CHECK VALVES
KILOJOULES (#2) X (#8)
12 TOTAL AVAILABLE ENERGY OF STEAM UNRESTRAINED BY CHECK VALVES
KILOJOULES (#4) X (#9)
13. TOTAL AVAILABLE ENERGY OF WATER RESTRAINED BY CHECK VALVES
KILOJOULES (#3) X (#9)
14. TOTAL AVAILABLE ENERGY OF STEAM AND WATER, KILOJOULES (#10) + (#11) +
(#12) + (#13)
15. TOTAL AVAILABLE ENERGY OF STEAM AND WATER UNRESTRAINED BY CHECK
VALVES, KILOJOULES (#10) + (#12)
LIMITATIONS INDICATES PRELIMINARY DATA SUBJECT TO CHANGE
IF: TOTAL AVAILABLE ENERGY PER EXTRACTION LINE <_____________ KJ, NO CHECK VALVE NECESSARY
IF: TOTAL AVAILABLE ENERGY PER EXTRACTION LINE >_____________ KJ, BUT <_________KJ, NEED ONE (1) FSCV
IF: TOTAL AVAILABLE ENERGY PER EXTRACTION LINE >_____________ KJ, BUT <_________KJ, NEED ONE (1) PACV
IF: TOTAL AVAILABLE ENERGY PER EXTRACTION LINE >_____________ KJ, NEED TWO (2) PACV
TOTAL AMOUNT OF UNTRSTRAINED ENERGY MUST NOT EXCEED_____________ KJ, REFER TO DST 00132A FOR ALTERNATES:
(SUM TOTAL OF ALL AMOUNTS ENTERED IN LINE 15)
NOTE USE OF BAFFLES EFFECTIVELY REDUCES THE VOLUME OF
WATER ENTERED IN ITEM 4 & USED IN ITEMS 12 & 15. IT DOES NOT
ELIMINATE THE WATER.
16. NUMBER OF CHECK VALVES IN SERIES PER EXTRACTION LINE.
17. STATE TYPE OF CHECK VALVE, PACV OR FSCV. IF PACV, STATE WHETHER
CONTROLLED DIRECTLY BY ARDV OR HEATER HIGH LEVEL OR BOTH. STATE BAFFLE
AREA PER HEATER IF USED.
NOTE: APPROVAL AND/OR COMMENTS OF THE SUBJECT DATA WILL BE RECEIVED BY LETTER
FROM Doosan REVISION AND REISSUANCE OF THIS FORM DOES NOT IMPLY APPROVAL.
REVISION __________________ DATE ___________
29