G+7 Storeyed+3Basements
Plinth area:32,000 sq.m
Solar PV System
930KWp Capacity
PROJECT TEAM
User organisation
Execution Agency
Architectural and
Structural Planning
Consultants
Green Building
MEP Services
Interior Design
Construction agencies
1.Main Composite Contract
2. Solar Power
3.Automated Parking
MoEF
CPWD
CPWD
M/s DPAP
M/s Spectral Services
M/s Kothari
M/s Swadeshi Civil Infra structure
M/s Swadeshi Civil Infra structure
M/s Simplex Projects
details
Plot area
Plinth Area
Project
Completion Cost
9565 sqm
31400 sqm
Rs 195 Cr
(Tentative)
4
930 KW Capacity
6000 sqm
330 cars
UNIQUE FEATURES
FIRST
FIRST
in GOVERNMENT SECTOR
targeted for both ratings
of Green
building
5STAR GRIHA
LEED India PLATINUM
LARGEST Roof top
Solar Power system
8
in any multistoreyed Building
(930KWp)
ACHIEVEMENTS
Overall Environmental
Protection
GREEN
BUILDING
COMPOSITE CONTRACT
Services Included (All inclusive)
1.Main structure and finishing works
2.Central Air Conditioning
3.Sub station
4.Lifts
5.Fire Fighting & Fire Alarm
6.IBMS
7.DG Sets
8.UPS
9.CCTV system
10.Internal EI
CHRONOLOGY OF EVENTS
12
28.01.2011
31.10.2013
31.12.2013
2Y 11M
Sl No
STATUTORY APPROVALS
Approval
Concept
stage
Completion
Stage
04.01.2011
----------
----------
21.12.2010
28.10.2013
AAI
24.05.2010
----------
DUAC
06.01.2011
11.12.2013
ASI
19.04.2010
----------
NDMC
13.01.2011
31.01.2014
(expected)
----------
STATUTORY APPROVALS
Sl No Approval
Concept
stage
Completion
Stage
Electric Load
Sanction
------------
Oct 2013
10
Energisation of HT
panels
-----------
Nov2013
11
Substation by CEA
-----------
Oct 2013
12
Nov 2013
13
14
31.12.2013
24.01.2014
W
N
E&M Services
REGULAR
1.Central Air Conditioning(HVAC)
2.Lifts
3.Fire Fighting & Fire Alarm
4.IBMS
5.DG Sets
6.UPS
7.CCTV system
8.Audio Visual System
9.Internal EI
SPECIAL
1.Fully Automated robotic Parking for 330 cars
ENERGY SCENARIO
(Average Annual)
Power Requirement (Base
Case)
22.0
lakh KWh
Power Requirement(Design
Case)
13.6
lakh KWh
Percentage savings
40% (approx)
14.3 lakh KWh
0.7
lakh KWh
(Surplus)
22
ENERGY EFFICIENCY
ECBC 2007
ACTUAL
5 W/sqm
HVAC load
20 sqm/Tr
40 sqm/Tr
Total
100W/sqm
40 W/sqm
23
OPTIMIZED BUILDING
ENVELOPE
1)PROPER ORIENTATION
2)INSULATED WALLS AND
ROOF
3)GLASS TRANMITTING
LIGHT BUT NOT HEAT
OPTIMIZED DAY
LIGHTING
1)ENERGY EFFICIENT
LED LIGHTS
2)SENSORS
OPTIMIZED ENERGY
SYSTEMS I/C HVAC
2)GEOTHERMAL HEAT
EXCHANGE SYSTEM
3)REGENRATIVE LIFTS
4)ENERGY EFFICIENT
EQUIPMENT
28
Suppl
y Air
Induc
ed Air
There are 180 vertical bores at the Depth of 80 meter all along the
Building Premises. Minimum 3 meter distance is maintained between
any two bores.
Each bore is lowered with HDPE pipe U-loop (32mm outer Dia.) and
grouted with Bentonite Slurry.
Each U-Loop is connected to MS Header Pipe(100mm Dia.)which
finally joins the Condenser Water Line in Plant Room.
Condenser hot water is sent at 100F (37.8 C) & back at 900 F (32.2
C).
One U-Loop has 0.9 TR Heat Rejection capacity, so all together 160
TR of Heat rejection is obtained without using a cooling tower.
: 14 lakh KWh
Per Year
Area required for locating Solar panels : 6000 m2
Area available over terraces
: 2200 m2
Creation of this additional space(6000 minus 2200 m2)
in a multistoreyed building with restricted plot & roof areas
where no structure including surface parking is provided around
the building, was a big Constraint
,32
started on 19.11.2013
SOLAR PV SYSTEM
TOTAL AREA
TOTAL AREA OF PANELS
ANNUAL ENERGY Generation
930KWp CAPACITY
6000 M2
4650 M2
14.3 lakh units
34
36
37
Flyash (Reuse) :
AAC BLOCKS
FALG BRICKS
FLYASH
40%
Granite
(Lakha Red)
Dholpur Stone
Calcium Silicate
Tiles
Terrazo Tiles
Crazy Marble
Polymer
Thermosetti
ng Resin
(Phenol
Formal
Dehyde)
BAMBOO
MAT
Woven sheet
using
Bam0.boo
slivers 0.6 to
0.8mm thick
& 5mm wide
JUTE / COIR
MAT
Jute / Coir
Thread
woven into
coarse cloth
45
SALIENT FEATURE
LIFT WELL
SHUTTLE BAY
SHUTTLE BAY
55