Sie sind auf Seite 1von 852

Oracle Corporation

Oracle Value Chain


Planning Profile
Options
Revised: 2013-01-27

For Oracle Internal and licensed customer use only.


This report is compiled from the Profile Options Database created and maintained by the
VCP Support Team and contains knowledge gathered from the Documentation, Notes,
Bugs, and other internal sources. We do not guarantee this data to be without flaw and
offer no warranty to its fitness for use.
We will update and maintain this document when possible to present the best available
information.
(c) Oracle Corporation 2010

Table of Contents
Advanced Planning and Scheduling Profile Options....................................................................19
BOM: Hour UOM...................................................................................................................20
CRP:Spread discrete requirements......................................................................................21
CSD: Default Repair Order...................................................................................................22
CSD: Default Repair Organization........................................................................................23
CSD: Default Repair Type.....................................................................................................24
CSD: Default Service Request Severity for Internal Repair Order........................................25
CSD: Default Service Request Type for Internal Repair Order.............................................26
CSD: Repair Mode for Depot Repair Orders.........................................................................27
CSD: Repair Type Internal Repair Order..............................................................................28
CSP: Repair Supplier Organization's Defective Subinventory..............................................29
CSP: Repair Supplier Organization's Usable Subinventory..................................................30
GMP: APS Installation Level.................................................................................................31
INV:Capable to Promise........................................................................................................33
MO: Operating Unit...............................................................................................................34
MRP: 2-Cuttoff Date Offset Months......................................................................................35
MRP: Calculate MATO Demand...........................................................................................36
MRP: Calculate Plan Performance.......................................................................................37
MRP: Calculate Supply Demand...........................................................................................38
MRP: Category Set for Backlog Form...................................................................................39
MRP: Compute Standard Mandatory Components for ATO Models....................................40
MRP: Cutoff History Days.....................................................................................................42
MRP: Disable Project Validation...........................................................................................43
MRP: Explode Demand Through Phantom Component.......................................................45
MRP: Firm Internal Req Transferred to OE...........................................................................46
MRP: Hash Area Size (Bytes)...............................................................................................47
MRP: Ignore Alternate BOM/Routing....................................................................................48
MRP: Ignore Zero Quantity Demands in Calculating First Bucket for Statistical Forecasting
49
MRP: Net All Purchase Orders Prior To Requisitions...........................................................50
MRP: Old Sales Orders Cutoff Days.....................................................................................51
MRP: Persist ATP Results....................................................................................................52
MRP: Plan Revenue Discount Percent.................................................................................53
MRP: Plan Revenue Price List..............................................................................................54
MRP: Planning Manager Run First Time..............................................................................55
MRP: RHX Check Profile......................................................................................................56
MRP: Round Source Entries.................................................................................................57
MRP: Sort Area Size (Bytes).................................................................................................58
MRP: Update Requested Completion Date when Releasing Reschedules..........................59
MRP: Use Alternate SQL for Daily Cleanup..........................................................................60
MRP: Use Progress Bar for Backlog Workbench..................................................................61
MRP: i2 Batch Client Timeout...............................................................................................62
MRP: i2 Calc Cumulative Yield.............................................................................................63
MRP: i2 Check if FP installed................................................................................................64

MRP: i2 Data Load Timeout..................................................................................................65


MRP: i2 Date Constant.........................................................................................................66
MRP: i2 Debug Mode............................................................................................................67
MRP: i2 Factory Planner Exec Dir Attr Number....................................................................68
MRP: i2 Factory Planner User Attribute Number..................................................................69
MRP: i2 Job Change Attribute Number.................................................................................70
MRP: i2 Log Directory...........................................................................................................71
MRP: i2 Net Change Dir........................................................................................................72
MRP: i2 RHYTHM Aggregate Resource Attribute Number...................................................73
MRP: i2 RHYTHM BC Delimiter............................................................................................74
MRP: i2 RHYTHM BOM Attribute Consumed attribute number............................................75
MRP: i2 RHYTHM BOM Attribute Produced attribute number..............................................76
MRP: i2 RHYTHM Batch Client Filter....................................................................................77
MRP: i2 RHYTHM Cooldown Time Attribute Number...........................................................78
MRP: i2 RHYTHM Delimiter..................................................................................................79
MRP: i2 RHYTHM Enable Attribute Base Planning..............................................................80
MRP: i2 RHYTHM Estimated Queue Time Attribute Number...............................................81
MRP: i2 RHYTHM Factory Planner Data Dir Attribute Number............................................82
MRP: i2 RHYTHM Factory Planner Host Attribute Number..................................................83
MRP: i2 RHYTHM Factory Planner Port Attribute Number...................................................84
MRP: i2 RHYTHM Inventory Attribute Alias Separator.........................................................85
MRP: i2 RHYTHM Minimum Queue Time Attribute Number................................................86
MRP: i2 RHYTHM OE Attribute Consumed attribute number...............................................87
MRP: i2 RHYTHM Offloadable To Attribute Number............................................................88
MRP: i2 RHYTHM Offloadable from Attribute Number.........................................................89
MRP: i2 RHYTHM PO Attribute Alias attribute number........................................................90
MRP: i2 RHYTHM Part Buffer Style Attribute Number..........................................................91
MRP: i2 RHYTHM Resource Type Attribute Number...........................................................92
MRP: i2 RHYTHM released as firm manufacturing order.....................................................93
MRP: i2 RhythmLink Data Directory.....................................................................................94
MRP: i2 RhythmLink Executable Directory...........................................................................95
MRP: i2 RhythmLink Host.....................................................................................................96
MRP: i2 RhythmLink Port Number........................................................................................97
MRP: i2 RhythmLink User.....................................................................................................98
MRP: i2 Start Factory Planner Client....................................................................................99
MRP: i2 Start RhythmLink Client.........................................................................................100
MRP: i2 WIP Job Load Timeout..........................................................................................101
MRP:ATP Assignment Set..................................................................................................102
MRP:ATP Database Link....................................................................................................103
MRP:Activate OLP..............................................................................................................104
MRP:Allow Safety Stock Pegging.......................................................................................105
MRP:Backlog Progress Timeout.........................................................................................106
MRP:Calculate Excess Exceptions on Time Fence............................................................107
MRP:Combine Sugg Rep Schedules..................................................................................108
MRP:Complete Supply Chain ATP.....................................................................................109
MRP:Compute Sales Order Changes.................................................................................110
MRP:Consume Fcst Set Summary.....................................................................................111
MRP:Consume Forecast.....................................................................................................112
MRP:Consume MDS...........................................................................................................113
MRP:Consume MPS...........................................................................................................114

MRP:Create Time fence......................................................................................................115


MRP:Cutoff Date Offset Months..........................................................................................116
MRP:Debug Mode...............................................................................................................117
MRP:Default Criteria Set.....................................................................................................118
MRP:Default DRP Plan Name............................................................................................119
MRP:Default Forecast Date................................................................................................120
MRP:Default Forecast Name..............................................................................................121
MRP:Default Plan Name.....................................................................................................122
MRP:Default Schedule Name.............................................................................................123
MRP:Default Sourcing Assignment Set..............................................................................124
MRP:Demand Time Fence Days........................................................................................125
MRP:Derive PO supply date from need by date.................................................................126
MRP:Enhanced Exception..................................................................................................127
MRP:Environment variable to set path for MRP files..........................................................128
MRP:Firm Planned Order Time Fence................................................................................129
MRP:Include Schd Rcpts in Use-up....................................................................................130
MRP:Include Substitute Components.................................................................................131
MRP:Interface Table History Days......................................................................................132
MRP:MPS Relief Batch Size...............................................................................................133
MRP:MPS Relief Direction..................................................................................................134
MRP:Maintain Original Schedule Version...........................................................................135
MRP:Perform Planning Manager Functions in Loads.........................................................136
MRP:Planner Batch Size.....................................................................................................137
MRP:Planner Workers........................................................................................................138
MRP:Planning Manager Batch Size....................................................................................139
MRP:Planning Manager Max Workers................................................................................140
MRP:Purchasing By Revision.............................................................................................141
MRP:Purge Batch Size.......................................................................................................142
MRP:Recommend action within PTF..................................................................................143
MRP:Repetitive Past Due Supply Days..............................................................................144
MRP:Requisition Load Group Option..................................................................................145
MRP:Retain Dates Within Calendar Boundary...................................................................147
MRP:Snapshot Pause for Lock (Minutes)...........................................................................148
MRP:Snapshot Substitute Parts..........................................................................................149
MRP:Snapshot Workers......................................................................................................150
MRP:Sourcing Rule Category Set.......................................................................................151
MRP:Time Fence Warning..................................................................................................152
MRP:Trace Mode................................................................................................................153
MRP:Use Direct Load Option..............................................................................................154
MRP:Use Ship Arrived Flag................................................................................................155
MRP_NEW_PLANNER_BACK_COMPATIBILITY..............................................................156
MSC : Consider all supplies for VMI replenishment calculation..........................................158
MSC : Consume Highest Revision Forecast.......................................................................159
MSC : Publish Supply Commit based on pegging information............................................160
MSC : VMI Requisitions Need By Date at RTF end............................................................161
MSC: 64-bit Planner Platform.............................................................................................162
MSC: APCC - Enable Cumulative Measures in Archive.....................................................163
MSC: APCC Archive SCRM Measures...............................................................................165
MSC: APCC Calendar Code...............................................................................................167
MSC: APCC Category Set 1...............................................................................................168

MSC: APCC Category Set 2...............................................................................................169


MSC: APCC Category Set 3...............................................................................................170
MSC: APCC Category set for detailed pegging analysis....................................................171
MSC: APCC Currency Code...............................................................................................172
MSC: APCC Gather Fact Tables Statistics.........................................................................173
MSC: APCC Gather Intermediate Tables Statistics............................................................174
MSC: APCC Gather Plan Tables Statistics.........................................................................175
MSC: APCC Instance..........................................................................................................176
MSC: APCC Period Set name............................................................................................177
MSC: APCC SNO Item Simulation Set...............................................................................178
MSC: APCC WebLogic Console Password........................................................................180
MSC: APCC WebLogic Console Username.......................................................................181
MSC: APCC WebLogic Password......................................................................................182
MSC: APCC WebLogic Username......................................................................................183
MSC: APCC Webcenter Admin URL..................................................................................184
MSC: APCC Webcenter Enabled........................................................................................185
MSC: APCC Webcenter Group Space Template................................................................186
MSC: APCC Webcenter Spaces Member Role..................................................................187
MSC: APCC Webcenter Spaces Port.................................................................................188
MSC: APCC Webcenter Spaces Recipient Key Alias.........................................................189
MSC: APCC Webcenter Spaces Saml Issuer Name..........................................................190
MSC: APCC Webcenter URL..............................................................................................191
MSC: APCC to APS database link name............................................................................192
MSC: ASCP Planning URL.................................................................................................193
MSC: ATP Allocation Method..............................................................................................194
MSC: ATP Capacity Allocation............................................................................................195
MSC: ATP Debug Mode......................................................................................................196
MSC: ATP Enforces Lead Time for ATO Model..................................................................197
MSC: ATP Infinite Time Fence Pad....................................................................................198
MSC: ATP Synchronization Downtime (minutes)................................................................199
MSC: ATP Web Service Responsibility...............................................................................200
MSC: ATP Web Service User.............................................................................................201
MSC: AVOID RE-SOURCING SALES ORDERS...............................................................202
MSC: Action Allowed on ATP 24x7 Plan While Running....................................................203
MSC: Aggregate Resource Name Flexfield Attribute..........................................................204
MSC: Align Component Demand Date with Pegging Date.................................................205
MSC: Allocated ATP Forward Consumption Method..........................................................206
MSC: Allocation Assignment Category Set.........................................................................207
MSC: Allow Release of Planned Orders from Demand Schedule Plan..............................208
MSC: Allow release of replenishments above suggested quantity.....................................209
MSC: Analytics Currency Code...........................................................................................210
MSC: Anchor date for calculating operation yields.............................................................211
MSC: Anchor date for calculating remaining shelf life.........................................................212
MSC: Apply Lot Modifiers in Weekly/Period Buckets..........................................................213
MSC: Apply Order Modifier To Start Quantity.....................................................................214
MSC: Apply Safety Stock Change interval to non MRP Planned Safety Stock..................215
MSC: Apply shortage and excess tolerance to planned orders..........................................216
MSC: Auto-Release Compression Days Tolerance............................................................217
MSC: Automatically Recalculate Operation Time...............................................................219
MSC: Avoid Re-Sourcing Sales Orders..............................................................................220

MSC: BPEL Demantra Password.......................................................................................221


MSC: BPEL Demantra Username.......................................................................................222
MSC: BPEL Domain Name.................................................................................................223
MSC: BPEL End Point URI.................................................................................................224
MSC: BPEL Process Version..............................................................................................225
MSC: Batch Size for Self Service Loads.............................................................................226
MSC: Batchable Flag..........................................................................................................227
MSC: Batching Window......................................................................................................228
MSC: Buy Order Processing Lead Time Calendar.............................................................229
MSC: CP Debug Level........................................................................................................230
MSC: Calendar Reference for Bucketing............................................................................231
MSC: Cancel Oustanding Sales Order Quantities..............................................................232
MSC: Category Set for Jobs without an Item Reference....................................................233
MSC: Category Set for Liability Analysis.............................................................................234
MSC: Category for Jobs without an Item Reference...........................................................235
MSC: Category set for CP Horizontal View.........................................................................236
MSC: Category set for Strategic Planning..........................................................................237
MSC: Category set for serviceable items............................................................................238
MSC: Choice of item for which to create supplies in substitute relationship.......................239
MSC: Circular sourcing surplus days..................................................................................240
MSC: Class Hierarchy.........................................................................................................241
MSC: Closest Quantity Pegging..........................................................................................242
MSC: Collaborative Planning Default Calendar..................................................................243
MSC: Collect CMRO Work Order Demand for PS..............................................................244
MSC: Collect Item, Material and Resource Costs...............................................................245
MSC: Collect PS SNO Data................................................................................................246
MSC: Collection Time Window for Install Base under Contracts history.............................247
MSC: Collection Window for Trading Partner Changes (Days)..........................................248
MSC: Collections Snapshot Threshold...............................................................................249
MSC: Compute Project Exception.......................................................................................250
MSC: Configuration.............................................................................................................251
MSC: Consolidate Interplant Demands...............................................................................252
MSC: Consume Forecast Inside Demand Time Fence.......................................................253
MSC: Consume forecast with no demand class.................................................................254
MSC: Consume forecasts using Internal Sales Orders.......................................................255
MSC: Cost Type..................................................................................................................257
MSC: Cost of Using a BOM/ Routing Flexfield Attribute.....................................................258
MSC: Create Resource Requirements for all Operations...................................................259
MSC: Currency Conversion Type.......................................................................................260
MSC: Custom allocation......................................................................................................261
MSC: DPP Allow Quantity Reduction Only When Supply is Excess on Internal Requisition,
Requisition and PO.............................................................................................................262
MSC: DPP Debug Level......................................................................................................263
MSC: DPP Demand Priority Details viewing buckets..........................................................264
MSC: DPP Discrete Job Cutoff Window (Days)..................................................................265
MSC: DPP Related Exception Additional Offset Days........................................................266
MSC: DRP Multitasking Group ID's per Process................................................................267
MSC: DRP Multitasking Max Concurrent Processes..........................................................268
MSC: Daily Allocation to Maintain Safety Stock Level........................................................269
MSC: Day UOM..................................................................................................................270

MSC: Days of Resource Availability before sysdate...........................................................271


MSC: Debug Level..............................................................................................................272
MSC: Debug Module...........................................................................................................273
MSC: Default Category Set for Rapid Planning..................................................................274
MSC: Default Project for Supplies Pegged to Excess.........................................................275
MSC: Default Time Stamp for Make Planned Order Release.............................................276
MSC: Default Workbench Height........................................................................................277
MSC: Default Workbench Width.........................................................................................278
MSC: Degree of Parallelism for Index Creation..................................................................279
MSC: Demand Priority Flexfield Attribute............................................................................280
MSC: Demand Satisfied Percent Threshold for Pegging....................................................281
MSC: Display Order Rescheduling Supplies.......................................................................282
MSC: Display Supplier Item in Collaborative Planning.......................................................283
MSC: Display Warning Message When Rescheduling Recommendation Not Suggested by
the Plan...............................................................................................................................284
MSC: Distribution Planning Ship Date................................................................................285
MSC: Distribution Planning Use Firm Supplies and Minimize Excess Supplies.................286
MSC: E1 APS FC URL........................................................................................................288
MSC: E1 APS ODI URL......................................................................................................289
MSC: E1 Concatenation Character.....................................................................................290
MSC: E1APS_BATCH_SIZE..............................................................................................291
MSC: E1APS_DEM_END_DATE_IN_MONTHS................................................................292
MSC: E1APS_DEM_START_DATE_IN_MONTHS............................................................293
MSC: E1APS_DEM_WF_TIME_OUT.................................................................................294
MSC: E1APS_NO_OF_WORKERS....................................................................................295
MSC: E1APS_TIME_OUT..................................................................................................296
MSC: E1APS_WS_TIME_OUT...........................................................................................297
MSC: E1_DBLINK...............................................................................................................298
MSC: EBS source instance for OTM...................................................................................299
MSC: ENFORCE CRITERIA REQUIREMENT BEFORE EXECUTING QUERY................300
MSC: Enable 64 bit snapshot..............................................................................................301
MSC: Enable ATP Summary Mode.....................................................................................302
MSC: Enable ATP Workflow...............................................................................................303
MSC: Enable ATP for Phantom Components.....................................................................304
MSC: Enable Advanced Constraints...................................................................................305
MSC: Enable Allocated ATP...............................................................................................306
MSC: Enable DRP Multitasking..........................................................................................307
MSC: Enable Diagnostic ATP.............................................................................................308
MSC: Enable Enhanced Sourcing.......................................................................................309
MSC: Enable Group Based Netting....................................................................................310
MSC: Enable Java Debug...................................................................................................311
MSC: Enable Large Plan Copy...........................................................................................312
MSC: Enable Model and End Item dimensions in APCC....................................................313
MSC: Enable Priority Pegging.............................................................................................314
MSC: Enable Release of Defective Planned Transfers......................................................315
MSC: Enforce Hard Links....................................................................................................316
MSC: Enhanced Project Netting.........................................................................................317
MSC: Excess and Safety Stock by Demand Class.............................................................318
MSC: Fast Refresh of Region Site Map..............................................................................319
MSC: File Flush Limit..........................................................................................................320

MSC: Firm Internal Requisition Time Fence.......................................................................321


MSC: Firm Intransit and PO in Receiving Supplies.............................................................322
MSC: Fixed Date for Install Base under Contracts History (DD-MON-YYYY)....................323
MSC: Flush All Items for Simulation....................................................................................324
MSC: Forecast Priority Flexfield Attribute...........................................................................325
MSC: Forecast Spreading Calendar...................................................................................326
MSC: Forecast Spreading Calendar...................................................................................327
MSC: Future Days for Currency Conversion.......................................................................329
MSC: Gateway URL to External Application.......................................................................330
MSC: Generate Exceptions in CP.......................................................................................331
MSC: Generate Notifications for Transportation Updates...................................................332
MSC: HP Maximum Displayed Item Count.........................................................................333
MSC: High Volume Items....................................................................................................334
MSC: History Days for Currency Conversion......................................................................335
MSC: Horizon for APCC Collected data - Backward days..................................................336
MSC: Horizon for APCC Collected data - Forward days.....................................................337
MSC: Horizontal Plan Demand Bucketing Preference........................................................338
MSC: Horizontal Plan Extension Program..........................................................................339
MSC: Hour UOM.................................................................................................................340
MSC: Hybrid Allocated ATP................................................................................................341
MSC: INTER PLANT DEM PRIORITY................................................................................342
MSC: IO UI Performance tuning.........................................................................................343
MSC: IO UI Period Set Name.............................................................................................344
MSC: Ignore ATP Check for Configured Item from Sales Order in ODS-ATP....................345
MSC: Ignore CMRO and EAM Workorders in ASCP..........................................................346
MSC: Ignore PTF during CTP.............................................................................................347
MSC: Ignore Routings Without Any Date Effective Operations..........................................348
MSC: Ignore Safety Stock Inside Lead Time......................................................................349
MSC: Include Firm Planned Orders In Firm Allocation Window..........................................350
MSC: Include Manufacturing Calendar in ATP Sales Order Ship Date Calculations..........351
MSC: Include Safety Stocks in Priority Based Pegging......................................................352
MSC: Inflate WIP Resource Requirements.........................................................................353
MSC: Inventory Rebalancing Surplus Inventory Basis........................................................355
MSC: JInitiator Version.......................................................................................................356
MSC: Launch Analyze Plan Partition..................................................................................357
MSC: Launch System Sql Loader.......................................................................................358
MSC: Launch Workflow-Enabled Exception Message Notifications...................................359
MSC: Level for Calculating Liability.....................................................................................360
MSC: Limit Gantt Chart Orders View Hierarchy..................................................................361
MSC: MPS Auto-Firm Planned Orders...............................................................................362
MSC: Map Server Host.......................................................................................................363
MSC: Map Server Port........................................................................................................364
MSC: Max display decimals for Currency...........................................................................365
MSC: Max display decimals for Quantity............................................................................366
MSC: Max display decimals for Quantity (aggregates).......................................................367
MSC: Max display decimals for Ratios/Percentages..........................................................368
MSC: Max display decimals for Time..................................................................................369
MSC: Max display decimals for Time (aggregates)............................................................370
MSC: Maximum Capacity....................................................................................................371
MSC: Maximum Percentage variation in safety stock values.............................................372

MSC: Maximum number of planned orders per demand....................................................373


MSC: Maximum number of planned orders per demand(1)................................................374
MSC: Minimize Project Cross Peg within Window..............................................................375
MSC: Minimize changes to chronological sequence of supplies while rescheduling..........376
MSC: Minimum Capacity.....................................................................................................377
MSC: Minimum Percentage variation in safety stock values..............................................378
MSC: Minimum Supply/Demand Percent for Pegging........................................................379
MSC: Move Past Due To Sysdate......................................................................................380
MSC: Net Change Temp Dir...............................................................................................381
MSC: New Forecast Auto Plan...........................................................................................382
MSC: New Material and Resource Plan Fetch Size............................................................383
MSC: New Planner Backward Compatibility.......................................................................384
MSC: New Supply Commit Auto Plan.................................................................................386
MSC: Number of Workers for Self Service Loads...............................................................387
MSC: OTHER with zero allocation percent is valid demand class......................................388
MSC: OTM Punchout URI...................................................................................................389
MSC: OTM Responsibility...................................................................................................390
MSC: OTM User..................................................................................................................391
MSC: Operator Company Name.........................................................................................392
MSC: Oracle Rapid Planning URL......................................................................................393
MSC: Order Number-CA Mandatory for CVMI....................................................................394
MSC: Order Type for Consigned VMI.................................................................................395
MSC: Organization containing generic BOM for forecast explosion...................................396
MSC: Overwrite all Order Forecast records........................................................................397
MSC: Overwrite all supplier capacity records.....................................................................398
MSC: PS - Snapshot Base Package...................................................................................399
MSC: PS - Snapshot Beginning Inventory Package...........................................................400
MSC: PS - Snapshot Calendar Package............................................................................401
MSC: PS - Snapshot Customer Package...........................................................................402
MSC: PS - Snapshot Distribution Package.........................................................................403
MSC: PS - Snapshot Enterprise Forecast Package............................................................404
MSC: PS - Snapshot Inventory Safety Targets Package....................................................405
MSC: PS - Snapshot Manufacturing Package....................................................................406
MSC: PS - Snapshot Purchase Orders Package................................................................407
MSC: PS - Snapshot Reservation Package........................................................................408
MSC: PS - Snapshot Sales Orders Package......................................................................409
MSC: PS - Snapshot Supplier Package..............................................................................410
MSC: PS - Snapshot Transfer Orders Package..................................................................411
MSC: PS - Snapshot Work Orders Package.......................................................................412
MSC: PS - Visit Display Format in PS UI............................................................................413
MSC: PS Adjust Post Horizon Demand Qty........................................................................414
MSC: PS Allow WO Purchased Item Offloading.................................................................415
MSC: PS Consistent Resource Assignment.......................................................................416
MSC: PS Currency Symbol.................................................................................................417
MSC: PS Enable CRO Scheduling.....................................................................................418
MSC: PS Enable RMO Scheduling.....................................................................................419
MSC: PS Filter Active Items................................................................................................420
MSC: PS Firm Past Due WO..............................................................................................421
MSC: PS Import On-Hold Work Orders..............................................................................422
MSC: PS Resource Constraint Horizon..............................................................................423

MSC: PS Run Application Script.........................................................................................424


MSC: PS Run Connector Script..........................................................................................425
MSC: PS/SNO API Version.................................................................................................426
MSC: PS/SNO Alignment Date...........................................................................................427
MSC: PS/SNO App Server URL.........................................................................................428
MSC: PS/SNO Client Install Path........................................................................................429
MSC: PS/SNO Compress Xml Files...................................................................................430
MSC: PS/SNO Data Store Path..........................................................................................431
MSC: PS/SNO Debug Mode...............................................................................................432
MSC: PS/SNO Download XML Files...................................................................................433
MSC: PS/SNO Include Negative Inventory Demands.........................................................434
MSC: PS/SNO Past Due Supplies Window........................................................................436
MSC: PS/SNO Use DB for Integration Data.......................................................................437
MSC: Pass List Price to OM in DRP Release.....................................................................438
MSC: Peg Firm Supply First................................................................................................439
MSC: Peg Firm Work Orders Within Assigned Projects and Tasks....................................440
MSC: Peg to maximize supply usage.................................................................................441
MSC: Perform ATP check for Internal Sales Orders...........................................................442
MSC: Plan Name for CMRO...............................................................................................443
MSC: Plan co-products.......................................................................................................444
MSC: Plan for order at risk calculation................................................................................445
MSC: Planning Currency.....................................................................................................446
MSC: Pre-Flush...................................................................................................................447
MSC: Prefer Consumption within Forecast Bucket.............................................................448
MSC: Priority for Substitute Items Flexfield Attribute..........................................................449
MSC: Priority of Alternate Resources for an Operation Flexfield Attribute..........................450
MSC: Production Plan for Transportation updates..............................................................451
MSC: Project Task Collection Window Days......................................................................452
MSC: Provide Warning For Dates Entered on Non-work Days...........................................453
MSC: Provide Warning when Sales Order Quantity is Changed........................................454
MSC: Purchase Order Dock Date Calculation Preference..................................................455
MSC: Purge Exception Days...............................................................................................456
MSC: Purge Staging and Entity Key Translation Tables.....................................................457
MSC: Rapid Planning Group Planned Orders.....................................................................458
MSC: Rapid Planning Safety Stock Lead Time Method......................................................459
MSC: Rapid Planning Scripts Home...................................................................................460
MSC: Rapid Planning UI Refresh Timeout..........................................................................461
MSC: Rapid Planning WebLogic Server Home...................................................................462
MSC: Read Profiles From DB.............................................................................................463
MSC: Recalculate Demand Priorities after Spreading........................................................464
MSC: Refresh Site to Region Mappings Event...................................................................465
MSC: Refresh Snapshots Pending Timeout.......................................................................466
MSC: Region Instance........................................................................................................467
MSC: Release WIP Dtls if Order Date different then BOM Revision Date..........................468
MSC: Released Only By User.............................................................................................470
MSC: Resource Group for a Line Flexfield Attribute...........................................................471
MSC: Resource Type for an Operation Flexfield Attribute..................................................472
MSC: Respect Minimum Remaining Shelf Life Days..........................................................473
MSC: Retain Time for Non-ATPable Items.........................................................................474
MSC: Return Best Source in Global ATP............................................................................475

MSC: SCEM Engine Launch Events...................................................................................476


MSC: SNO - Snapshot Base Package................................................................................477
MSC: SNO - Snapshot Beginning Inventory Package........................................................478
MSC: SNO - Snapshot Calendar Package.........................................................................479
MSC: SNO - Snapshot Customer Package........................................................................480
MSC: SNO - Snapshot Demand Package..........................................................................481
MSC: SNO - Snapshot Distribution Package......................................................................482
MSC: SNO - Snapshot Enterprise Forecast Package.........................................................483
MSC: SNO - Snapshot Fixed Production Package.............................................................484
MSC: SNO - Snapshot Inventory Safety Targets Package.................................................485
MSC: SNO - Snapshot Manufacturing Package.................................................................486
MSC: SNO - Snapshot Manufacturing Package(1).............................................................487
MSC: SNO - Snapshot Purchase Orders Package.............................................................488
MSC: SNO - Snapshot Sales Orders Package...................................................................489
MSC: SNO - Snapshot Supplier Package...........................................................................490
MSC: SNO - Snapshot Transfer Orders Package...............................................................491
MSC: SNO - Snapshot Work Orders Package....................................................................492
MSC: SNO Connector Precision.........................................................................................493
MSC: SNO Currency Precision...........................................................................................494
MSC: SNO Decimal Precision.............................................................................................495
MSC: SNO Optimization Type............................................................................................496
MSC: SNO Publish On Client..............................................................................................497
MSC: SNO Run Application Script......................................................................................498
MSC: SNO Run Connector Script.......................................................................................499
MSC: SNO Transportation Capacity By..............................................................................500
MSC: Safety Stock Project..................................................................................................501
MSC: Safety stock change interval (Days)..........................................................................502
MSC: Sales Orders Offset Days.........................................................................................503
MSC: Scope of Analyze Plan Partition................................................................................504
MSC: Search Criteria Warning............................................................................................505
MSC: Selection order for Firm Supplies in backward allocation window............................506
MSC: Self Service Loads Delimiter.....................................................................................507
MSC: Service Level Category Set.......................................................................................508
MSC: Service Planning Enabled.........................................................................................509
MSC: Service Planning Item Safety Stock Level Value......................................................510
MSC: Share Plan Partitions................................................................................................511
MSC: Shelf Life Override of Order Modifiers for Transfer Orders.......................................512
MSC: Simultaneous Resource Sequence Flexfield Attribute..............................................513
MSC: Smoothing method to calculate Safety stock within Change interval........................514
MSC: Source Instance ID....................................................................................................515
MSC: Source Setup Required.............................................................................................516
MSC: Sourcing History Start Date Offset(in months)..........................................................517
MSC: Sourcing Rule Category Set......................................................................................518
MSC: Sourcing Variance Tolerance....................................................................................519
MSC: Split Planned Order to perform safety stock pegging................................................520
MSC: Split Planned Orders for Scheduling Flexibility.........................................................521
MSC: Supplier Capacity Accumulation(multiplier)...............................................................523
MSC: Supplier Capacity Consumption by Purchase Orders...............................................524
MSC: Suppress Exception for Selection of Alternates........................................................526
MSC: Temp Index Extent Size(Bytes).................................................................................527

MSC: Temp Table Extent Size(Bytes)................................................................................528


MSC: Unit of Measure.........................................................................................................529
MSC: Update Requested Completion Date when Releasing Reschedules........................530
MSC: Update Use Up Date.................................................................................................531
MSC: Use Enhanced Forward ATP....................................................................................532
MSC: Use FIFO Pegging....................................................................................................533
MSC: Use Optimization Phase Supply Due Dates for Pegging..........................................534
MSC: Use Shipping/Receiving Calendar............................................................................535
MSC: Use attribute based netting.......................................................................................536
MSC: VMI Default Query.....................................................................................................537
MSC: Value of N for all top/bottom-N reports in Dashboards.............................................538
MSC: Vertical view default query........................................................................................539
MSC: Wait Time to Obtain Lock on Table/Partition for Snapshot Delete Worker (in sec)..540
MSC: Write MBP Flat Files.................................................................................................541
MSC:ATP Assignment Set..................................................................................................542
MSC:Coll Error Debug Mode..............................................................................................543
MSC:Coll Performance Debug Mode..................................................................................545
MSC:Collect Completed Jobs.............................................................................................546
MSC:Collect Routing...........................................................................................................547
MSC:Compute IB Aggregation during Collection................................................................548
MSC:Criticality Category Set...............................................................................................550
MSC:Prevent Loops when pegging Non-Standard Jobs.....................................................551
MSC:Release only orders pegging fully to on hand............................................................552
MSC:Retain Released Data................................................................................................554
MSC:SRP PHASE2 ENABLED...........................................................................................555
MSC:Select Sourcing Rules In ATP Based On...................................................................556
MSC_USE_HASH_KEY......................................................................................................557
MSD: AW Tablespace.........................................................................................................558
MSD: Calculate Planning Percentages...............................................................................559
MSD: Category Set Name...................................................................................................560
MSD: Client Debugging.......................................................................................................561
MSD: Conversion Type.......................................................................................................562
MSD: Currency Code..........................................................................................................563
MSD: Customer Attribute....................................................................................................564
MSD: Default DP Scenario..................................................................................................565
MSD: Enabled Organization for Item Collections................................................................566
MSD: Excess and Obsolescence, Liability Category Set Name.........................................567
MSD: Include all internal sites within scope of LOB scoped demand plan.........................568
MSD: MAXVALUECOUNT for edges in XWDEVKIT..........................................................569
MSD: Master Org................................................................................................................570
MSD: OLAP Directory Alias................................................................................................571
MSD: OLAP Initial Page Pool..............................................................................................572
MSD: OLAP Maximum Page Pool......................................................................................573
MSD: OLAP Workflow Page Pool.......................................................................................574
MSD: One Step Collection..................................................................................................575
MSD: Two-Level Planning...................................................................................................576
MSD: Use Classic Even Allocation.....................................................................................577
MSD: Use Classic Worksheet.............................................................................................578
MSD: Worksheet Automatic resize.....................................................................................579
MSD:View Scope measures are editable............................................................................580

MSD_DEM: Calculate Planning Percentage.......................................................................581


MSD_DEM: Category Set Name.........................................................................................582
MSD_DEM: Conversion Type.............................................................................................583
MSD_DEM: Currency Code................................................................................................584
MSD_DEM: Customer Attribute..........................................................................................585
MSD_DEM: Data Profile for Price Lists...............................................................................586
MSD_DEM: Debug Mode....................................................................................................587
MSD_DEM: Enable Supply Plan Download for work orders...............................................588
MSD_DEM: Explode Demand Method................................................................................589
MSD_DEM: Fiscal Calendar...............................................................................................590
MSD_DEM: Host URL.........................................................................................................591
MSD_DEM: Include Dependent Demand...........................................................................592
MSD_DEM: Include organization in CMR Data Load.........................................................593
MSD_DEM: Master Org......................................................................................................594
MSD_DEM: Maximum seeded units available for price lists...............................................595
MSD_DEM: Schema...........................................................................................................596
MSD_DEM: Simulation Set Name......................................................................................597
MSD_DEM: Source Instance for Global Forecast...............................................................598
MSD_DEM: Truncate Staging Table...................................................................................599
MSD_DEM: Two-Level Planning.........................................................................................600
MSD_DEM: UOM for fleet flight hours................................................................................601
MSD_DEM: Use new Site code format...............................................................................602
MSD_DEM: Version............................................................................................................603
MSD_SPF: History basis for Failure Rate computation......................................................604
MSD_SPF: Organization containing generic BOM for Service Parts Forecasting..............605
MSO: Activity Selection Window (in Days)..........................................................................606
MSO: Additional Demand Slices for Shared Supply Rescheduling....................................607
MSO: Allow Partial Demand Completion............................................................................608
MSO: Allow Schedule Gaps for Shared Supplies...............................................................609
MSO: Allow Simultaneous Resource To End At Different Time..........................................611
MSO: Allow Simultaneous Resources to End at Different Times........................................612
MSO: Allow early builds to consume existing supplies of phased-out components and
sources................................................................................................................................613
MSO: Alternate Process Penalty.........................................................................................614
MSO: Alternate Resource Penalty......................................................................................615
MSO: Alternate Resource Selection Method......................................................................616
MSO: Alternate Source Penalty..........................................................................................617
MSO: Apply Windows for Firm Scheduling.........................................................................618
MSO: Avoid non working days for Buy/Transfer order dates..............................................619
MSO: Barrier Optimizer Algorithm Choice..........................................................................620
MSO: Batching Precision....................................................................................................621
MSO: Big M Value for SCO.................................................................................................622
MSO: CPLEX Crash Parameter..........................................................................................623
MSO: CPLEX Refactor Rate...............................................................................................624
MSO: CPLEX Scaling Factor..............................................................................................625
MSO: CPLEX messages to screen indicator......................................................................626
MSO: Calculate Constraint Exceptions...............................................................................627
MSO: Capacity Units Recalculation Threshold...................................................................628
MSO: Check Redundant Constraints..................................................................................629
MSO: Choice of supply for substitution...............................................................................630

MSO: Component offset logic for optimization....................................................................631


MSO: Consume Existing Purchase Order Supplies in First-In-First-Out Sequence During
Component Substitution......................................................................................................632
MSO: Continuous transfer across organizations.................................................................634
MSO: Convergent Supplies Consumption Pattern..............................................................635
MSO: Convergent Supplies Consumption Pattern for Inter-Org and Supplier Sourced orders
............................................................................................................................................636
MSO: Convergent Supplies Consumption Pattern for Intra-Org Sourced orders................637
MSO: Cost Roll-up incremental factor.................................................................................639
MSO: Create Aggregate Supply for Unsatisfied Demands within Planning Time Fence....640
MSO: DS Scheduling Window............................................................................................642
MSO: Default Forecast Priority...........................................................................................643
MSO: Default Idle Time Tolerance (Hours).........................................................................644
MSO: Default Resource Sequencing Window (in Days).....................................................645
MSO: Default Sales Order Priority......................................................................................646
MSO: Default Timestamp Safety Stocks.............................................................................647
MSO: Default Timestamp for Forecasts..............................................................................648
MSO: Default Timestamp for Sales Orders.........................................................................649
MSO: Default Value for Maximum Acceptable Days Early.................................................650
MSO: Delay Fulfillment of Small Demands.........................................................................651
MSO: Demand Size Tolerance Before Splitting Planned Orders........................................652
MSO: Demand Type Priority...............................................................................................653
MSO: Demand Window Size...............................................................................................654
MSO: Disable Inference of Item Substitution Relationship.................................................655
MSO: Divergent Supply Feeding Pattern............................................................................656
MSO: Divergent Supply Feeding Pattern for Inter-Org and Supplier Sourced orders.........657
MSO: Divergent Supply Feeding Pattern for Intra-Org Sourced orders..............................658
MSO: Dual Simplex Parameter...........................................................................................659
MSO: EDD Demand Cutoff Priority.....................................................................................660
MSO: EDD Scheduling Window Control.............................................................................661
MSO: Enable Advanced Sequencing..................................................................................662
MSO: Enable Cost Rollup for Optimization.........................................................................663
MSO: Enable Decision Rules..............................................................................................664
MSO: Enable Hard Links Globally.......................................................................................665
MSO: Enable Rounding of Fractional Supplies For Service Planning................................666
MSO: Enable sourcing split for end item substitution..........................................................667
MSO: Enforce Minimum Transfer Quantities......................................................................668
MSO: Enforce Resource Sequence Contiguity...................................................................669
MSO: Firm Purchase Orders Within Time Fence................................................................670
MSO: Firm Requisitions Within Time Fence.......................................................................671
MSO: Firm Supply Allocation Window (Backward days).....................................................672
MSO: Firm Supply Allocation Window (Forward days).......................................................673
MSO: Firm Work Orders/Operations Within Time Fence....................................................674
MSO: Floating Point Precision............................................................................................675
MSO: Floating Point Precision for Increments of Shift Start/End Times Within a Planning
Bucket.................................................................................................................................676
MSO: Floating Point Precision for Order Q.........................................................................677
MSO: Floating Point Precision for Planning Bucket Efficiency............................................678
MSO: Floating Point Precision for Transportation Capacities (Volume).............................679
MSO: Floating Point Precision for Transportation Capacities (Weight)..............................680

MSO: Floating Point Precision for Usage in Routings.........................................................681


MSO: Generate Compression Days Exception...................................................................682
MSO: Generate Compression/Firming Exceptions for Orders in Progress.........................683
MSO: Generate Reduced Model.........................................................................................684
MSO: Generate Shared Supply Exceptions........................................................................685
MSO: Global Batchable Flag...............................................................................................686
MSO: Global Chargeable Flag............................................................................................687
MSO: Global Time Limit......................................................................................................688
MSO: HLS flat files path......................................................................................................689
MSO: Hard link scheduling window.....................................................................................690
MSO: Hard link scheduling window expansion factor.........................................................691
MSO: Heuristic type............................................................................................................692
MSO: Incremental Planned Orders.....................................................................................693
MSO: Internal Demand Aggregation Within Optimization...................................................694
MSO: Inventory Carrying Costs Percentage.......................................................................695
MSO: JIT Selector Window Size.........................................................................................696
MSO: LP Constraint Batch Size..........................................................................................697
MSO: LP Markowitz Coefficient..........................................................................................698
MSO: LP Optimization Algorithm........................................................................................699
MSO: Late Demands Exceptions Tolerance Minutes.........................................................700
MSO: Lead Time Control....................................................................................................701
MSO: List Size for Pricing Candidates................................................................................703
MSO: Lookahead days to net co-product/by-product supplies before creating planned
orders..................................................................................................................................704
MSO: Max Gap Tolerence on SDS.....................................................................................705
MSO: Maximium Number of Prepones...............................................................................706
MSO: Maximize Search of Availability Intervals..................................................................707
MSO: Maximize Use of Unfirm PurchOrd/WorkOrd in Optimization...................................708
MSO: Maximum Activity Duration.......................................................................................709
MSO: Maximum Allowable Days Late.................................................................................710
MSO: Maximum Allowable Days Late before Forecast Expiration......................................711
MSO: Maximum Alternate Combinations............................................................................712
MSO: Maximum Demands Per Group for Advanced Sequencing......................................713
MSO: Maximum Demands per Group.................................................................................714
MSO: Maximum Demands per Slice...................................................................................715
MSO: Maximum Inventory Level % of Safety Stock............................................................716
MSO: Maximum Lead Time Factor.....................................................................................717
MSO: Maximum Number of Demands in a Hard Linked Demand Set................................718
MSO: Maximum Number of Pull for Operation....................................................................719
MSO: Maximum Number of Pushes for Operation..............................................................720
MSO: Maximum Operations Per Slice................................................................................721
MSO: Maximum Resource Over-capacity...........................................................................722
MSO: Maximum Simplex Iterations.....................................................................................723
MSO: Maximum number of pulls/push for hard linked operations......................................724
MSO: Minimize Supply Duration.........................................................................................725
MSO: Minimum Processing Lead Time Adjustment Factor................................................726
MSO: Multiplier To Derive Supply Allocation Window.........................................................727
MSO: Net All Firm Supplies Before Creating Planned Order..............................................728
MSO: Network routing cycle time coefficient.......................................................................730
MSO: Network routing fixed time window...........................................................................731

MSO: Nfl Backward Compression Pct................................................................................732


MSO: Nfl Forward Compression Pct...................................................................................733
MSO: Number of Backtracks Allowed.................................................................................734
MSO: Number of Decomposition Groups Per Process.......................................................735
MSO: Number of Demand Groups for Optimization............................................................736
MSO: Number of Iterations for Local Search......................................................................737
MSO: Number of LP Phases for Safety Stock Calculation..................................................738
MSO: Number of Processes to use in Decomposition........................................................739
MSO: Number of Threads for Optimization.........................................................................740
MSO: Number of processes for Inline Forecast..................................................................741
MSO: Optimization Advanced Start....................................................................................742
MSO: Optimization Daily Aggregation Buckets...................................................................743
MSO: Optimization Weekly Aggregation Buckets...............................................................744
MSO: Optimization debug level...........................................................................................745
MSO: Order Modifier Max Searching Depth.......................................................................747
MSO: Overlap Activities by MTQ........................................................................................748
MSO: Peg By-product Supplies..........................................................................................749
MSO: Penalty Basis for Changeovers.................................................................................750
MSO: Penalty Cost Factor for Exceeding Item Material Capacity Flexfield Attribute..........751
MSO: Penalty Cost Factor for Exceeding Material Capacity...............................................752
MSO: Penalty Cost Factor for Exceeding Material Capacity Flexfield Attribute..................753
MSO: Penalty Cost Factor for Exceeding Org Material Capacity Flexfield Attribute...........754
MSO: Penalty Cost Factor for Exceeding Org Resource Capacity Flexfield Attribute........755
MSO: Penalty Cost Factor for Exceeding Org Transportation Capacity Flexfield Attribute756
MSO: Penalty Cost Factor for Exceeding Resource Capacity............................................757
MSO: Penalty Cost Factor for Exceeding Resource Capacity Flexfield Attribute...............758
MSO: Penalty Cost Factor for Exceeding Transportation Capacity Flexfield Attribute.......759
MSO: Penalty Cost Factor for Late Demands.....................................................................760
MSO: Penalty Cost Factor for Late Forecasts Flexfield Attribute........................................761
MSO: Penalty Cost Factor for Late Item Demands Flexfield Attribute................................762
MSO: Penalty Cost Factor for Late Org Demands Flexfield Attribute.................................763
MSO: Penalty Cost Factor for Late Sales Orders Flexfield Attribute..................................764
MSO: Penalty Increase Tolerance Percentage in Local Search.........................................765
MSO: Penalty multiplier outside unconstrained..................................................................766
MSO: Percent Complete Before Resequencing..................................................................767
MSO: Postpone Use of Alternates to Latest Possible Time................................................768
MSO: Preemption Slack Ratio............................................................................................769
MSO: Preprocessing Aggregator Fill...................................................................................770
MSO: Preprocessing Aggregator Limit................................................................................771
MSO: Preprocessing Flag for LP Matrix..............................................................................772
MSO: Preprocessor LP Compression.................................................................................773
MSO: Primal Simplex Parameter........................................................................................774
MSO: Primal/Dual Preprocessing Reduction......................................................................775
MSO: Pull push base..........................................................................................................776
MSO: Pull push offset.........................................................................................................777
MSO: Queue Time Factor...................................................................................................778
MSO: Re-computation percentage for sequence generation..............................................779
MSO: Reschedule Jobs Out to Reduce Inventory Carrying Costs......................................780
MSO: Reschedule Shared Supply to Influence Batching....................................................781
MSO: Resource Adjustment Factor For Improved Offloading to Alternates.......................782

MSO: Resource Batching Strategy.....................................................................................783


MSO: Resource Group for the Line Flexfield Attribute........................................................784
MSO: Respect Activity Contiguity Flag for Process Supplies.............................................785
MSO: Respect EDD Scheduling windows for Lead Times..................................................786
MSO: SCO Dual Variables Tolerance.................................................................................787
MSO: SCO Reduced Cost Tolerance.................................................................................788
MSO: SCO TRIANGULATION............................................................................................789
MSO: STL Buffer Size.........................................................................................................790
MSO: Schedule Across Breaks...........................................................................................791
MSO: Schedule All Firm Planned Orders First....................................................................792
MSO: Schedule Simultaneous Resources Across Breaks..................................................793
MSO: Schedule window width.............................................................................................795
MSO: Scheduler Time Step................................................................................................796
MSO: Scheduling Activity Selection Window......................................................................797
MSO: Scheduling Window UOM.........................................................................................798
MSO: Setup Pattern Calculation Window...........................................................................799
MSO: Simplex Feasibility Tolerance...................................................................................800
MSO: Simplex Optimality Tolerance...................................................................................801
MSO: Simplex Perturbation Constant.................................................................................802
MSO: Simplex Perturbation Limit........................................................................................803
MSO: Simplex Perturbation Parameter...............................................................................804
MSO: Simplex Presolve Limit..............................................................................................805
MSO: Simplex Singularity Repair Limit...............................................................................806
MSO: Skip Firm SDS Activities During Justify....................................................................807
MSO: Slack Hours For Batch Resource..............................................................................808
MSO: Solve Dual Problem..................................................................................................809
MSO: Sourcing Allocation Window.....................................................................................810
MSO: Split Planned Orders for Assigned Units...................................................................811
MSO: Split Supplies for SPP Release.................................................................................812
MSO: Spread Resource Consumption Within Optimization................................................813
MSO: Substitute Item Penalty.............................................................................................814
MSO: Supplies used for satisfying transient safety stock...................................................815
MSO: Supply Reschedule Window Size for Safety Stock Pegging.....................................816
MSO: Supply Window Size.................................................................................................817
MSO: Synchronize Chargeable Resources to Respect Hard Links....................................818
MSO: Target Inventory Level % of Safety Stock.................................................................819
MSO: Transfer Quantity Threshold for Enforceing Hard Links............................................820
MSO: UOM for converting Changeover Time to Penalty....................................................821
MSO: Upper Limit for Maximum Time Offset for Hard Links...............................................822
MSO: Use Breaks in Calculation of Unconstrained Scheduling Windows..........................823
MSO: Use Collections Start Time.......................................................................................824
MSO: Use Customer Site in End Item Substitution Rule....................................................825
MSO: Use Decomposition in Optimization..........................................................................826
MSO: Use Discrete Job Resource Usage to Consume Resource Capacity.......................827
MSO: Use Effectivity Date to Infer End Item Substitution Priority.......................................828
MSO: Use Existing Supplies in Alternate BOM/Subs. Comp..............................................829
MSO: Use Item Shelf Life Days in Scheduling Buy/Transfer Orders..................................830
MSO: Use JIT dates from high level scheduling results......................................................831
MSO: Use Of Assigned Units In Scheduling.......................................................................832
MSO: Use Optimization and Decision Rules for Simulation................................................833

MSO: Use SCO Time Aggregation.....................................................................................834


MSO: Use Safety Lead Time..............................................................................................835
MSO: Use Sequencing Template........................................................................................836
MSO: Use Shift Definitions When Scheduling Lead Times.................................................837
MSO: Use Up Existing Supply of Primary Components Before Substitute.........................838
MSO: Write Inline forecasting flat files................................................................................839
MSR: Budget Category Set.................................................................................................840
MSR: Budget Enditem Favor Factor...................................................................................841
MSR: Budget Heuristic........................................................................................................842
MSR: Enable Cycle Stock Adjustment................................................................................843
MSR: Postponement Factor................................................................................................844
MSR: Probability Distribution Type.....................................................................................845
MSR: Safety Stock Holding Strategy..................................................................................846
MSR: Warehouse Capacity Granularity..............................................................................847
MSR: Warehouse Category Set..........................................................................................848
POR: Sync up Need by date on IR with OM.......................................................................849
WIP:Discrete Job Prefix......................................................................................................850
WSM: Create Job Level BOM and Routing Copies............................................................851

Advanced Planning and Scheduling Profile Options


BOM: Hour UOM
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

BOM
BOM:HOUR_UOM_CODE
Hour UOM used by leadtime calculations Usuallly set to HR for hours and then any conversions are entered as
required in Inventory application.

Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

CRP:Spread discrete requirements


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

CRP
CRP_SPREAD_LOAD
Spread discrete requirements that span multiple days
Not used for collections, but used in ASCP for resource horizontal plan

Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

CSD: Default Repair Order


Profile Code
Profile Option Name
Description

CSD
CSD_DEFAULT_REPAIR_ORDER
For SPP - Service Parts Planning
Set on EBS Source in a distributed environment
Default Repair Order

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

CSD: Default Repair Organization


Profile Code
Profile Option Name
Description

CSD
CSD_DEFAULT_REPAIR_ORG
For SPP - Service Parts Planning
Set on EBS Source in a distributed environment
Default repair owning organization

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

CSD: Default Repair Type


Profile Code
Profile Option Name
Description

CSD
CSD_DEFAULT_REPAIR_TYPE
For SPP - Service Parts Planning
Set on EBS Source in a distributed environment
Default repair type for new repair orders

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

CSD: Default Service Request Severity for Internal


Repair Order
Profile Code
Profile Option Name
Description

CSD
CSD_IRO_DEFAULT_SR_SEVERITY
For SPP - Service Parts Planning
Set on EBS Source in a distributed environment
Default service request severity for internal repair orders

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

CSD: Default Service Request Type for Internal


Repair Order
Profile Code
Profile Option Name
Description

CSD
CSD_IRO_DEFAULT_SR_TYPE
For SPP - Service Parts Planning
Set on EBS Source in a distributed environment
Default Service Request Type for internal repair orders

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

CSD: Repair Mode for Depot Repair Orders


Profile Code
Profile Option Name
Description

CSD
CSD_REPAIR_MODE
For SPP - Service Parts Planning
Set on EBS Source in a distributed environment
Repair Mode for Depot Repair Processes - Site Level

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

CSD: Repair Type Internal Repair Order


Profile Code
Profile Option Name
Description

CSD
CSD_IRO_REPAIR_TYPE
For SPP - Service Parts Planning
Set on EBS Source in a distributed environment
Repair Type for creation of internal repair orders

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

CSP: Repair Supplier Organization's Defective


Subinventory
Profile Code
Profile Option Name
Description

CSP
CSP_REPAIR_SUP_ORG_DEFECT_SUBINV
For SPP - Service Parts Planning
Set on EBS Source in a distributed environment
This profile value used in Repair PO Execution as Defective Subinventory

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

CSP: Repair Supplier Organization's Usable


Subinventory
Profile Code
Profile Option Name
Description

CSP
CSP_REPAIR_SUP_ORG_USABLE_SUBINV
For SPP - Service Parts Planning
Set on EBS Source in a distributed environment
This profile value used in Repair PO Execution as Usable Subinventory

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

GMP: APS Installation Level


Profile Code
Profile Option Name
Description

GMP
GMP_APS_CONFIG_LEVEL

What is the APS Installation Level.


available profile settings
1 - Not Installed
2 - Upgrade from MRP
3 - Full Installation
Profile affects following screens :
ASCP instances form :
If profile is set to 1 or 2 on source or destination,
then show following message :
" Currently installed/licensed options of Advanced
Supply Chain Planning product do not allow
Distributed Instances"
Plan options screen :
If MSO is not licensed show message :
" Currently installed/licensed options of Advanced
Supply Chain Planning product do not allow
Constrained Plans. Please consult the
implementation guide and upgrade notes for
details"
If the profile option is set to 1 (Not Installed) then
restrict to single instance and single organization
Following message is displayed :
" Currently installed/licensed options of Advanced
Supply Chain Planning product do not allow Multiorg Planning. Please consult the implementation
guide and upgrade notes for details"
If the profile is set to 2 (upgrade from MRP) then

restrict to single instance and multi organization


Following message is displayed
" Currently installed/licensed options of Advanced
Supply Chain Planning product do not allow MultiInstance Planning. Please consult the
implementation guide and upgrade notes for
details"
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5346351
-1
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

INV:Capable to Promise
Profile Code
Profile Option Name
Description

INV
INV_CTP
Valid values are
ATP based on collected data
ATP/CTP based on planning output
Other values may appear, but are not longer used by the code.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MO: Operating Unit


Profile Code
Profile Option Name
Description

MO:
ORG_ID

MO: Operating Unit


The MO:Operating Unit profile option must be set
to the appropriate value at either the Responsibility
or User level.
This profile option is used to distinguish which
Operating Unit will be used by the users that login
into Oracle Applications.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: 2-Cuttoff Date Offset Months


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_CUTOFF_DATE_OFFSET_2
Do NOT Use
custom profile for secondary offset - not used except in DEV supported test
instances.

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Calculate MATO Demand


Profile Code
Profile Option Name
Description

MRP
MRP_CALC_MATO_DEMAND
This profile option is used by ASCP to support forecast consumption
processes
for Multi-level ATO models. Set to Yes if these processes are utilized.
This was used only until 11.5.9. From 11.5.10 this profile is not used.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3125951
3125891
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Calculate Plan Performance


Profile Code
Profile Option Name
Description

MRP
MRP_CALCULATE_PLAN_PERFORMANCE
Not used in Oracle Advanced Planning
This profile is used to decide upon whether the request Calculate Plan
performance Indicators needs to be run at the end of MRP Launch or not.
This was an optional program used to gather info from MRP and load into
tables used by the old Business Intelligence programs. More information is
available in Note: 783088.1

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Calculate Supply Demand


Profile Code
Profile Option Name
Description

MRP
MRP_ATP_CALC_SD
Calculate Supply Demand details for ATP.
When you drill to ATP Details on the ATP inquiry or Sales order Availability
window (and other applications like iStore, Quoting, etc), the ATP Details and
Pegging are displayed.
In the pegging screen, you can right-click on lines showing Green or Red
icon, then you will have access to other information like
Supply/Demand, Horizontal Plan, etc.
These details are only available when this profile is set to Yes. Otherwise you
will get an error message to setup the profile.
PERFORMANCE NOTE:
This is used for ATP debugging and can effect performance, especially on
large orders or ATO models.
This should usually be setup at the User Level as required.

Note Reference(s)
368229.1
565918.1
436771.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Global Order Promising Implementation and User's Guide


-1
-1
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MRP: Category Set for Backlog Form


Profile Code
Profile Option Name
Description

MRP
MRP_BALWB_CATEGORY_SET
Category Set for Order Backlog Workbench Form accessed from the Order
Management Responsibility / Scheduling
Suggest that this would be the same as used for preferences when viewing
data in the Collections Workbench (View Collected Data)
Use this profile option to indicate which items belonging to this category set
appear in the Backlog Scheduling Workbench tree navigator.
If no value is entered, no items appear in the Backlog Scheduling Workbench
tree navigator. You can update this profile at the site level.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Global Order Promising Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MRP: Compute Standard Mandatory Components


for ATO Models
Profile Code
Profile Option Name
Description

MRP
MRP_EXPLODE_ATO
Determines whether to call the CTO API to calculate the dependent demand
for ATO items during the Refresh Snapshots process.
This will cause performance to be slower when Yes.
Setting this to Yes would be normal if ATO Models are present in the system.
Collections code will default this profile to Yes if it is NULL. Set this profile in
the EBS Source instance when you have distributed installation.
Note: Refresh Collection Snapshots will finish with warning when:

CTO BOM not found for the item

CTO_API was exploding the BOM and returns a warning


from the CTO code.

We print the following for CTO BOM not found - this is a setup violation since the requirement for CTO is to configure and create the [STAR] item
using CTO Auto-Create or by progressing the sales order.
Warning: Item_ID = 781553, ORG_ID=5002 ; No BOM found for configured
item in ship-from org.
You may safely disregard this warning if the configured item is transferred
across orgs, and the warning points to an org in which no assembly of the
configured item takes place. If you are using ODS based ATP, please check
that you have the BOM in shipping org. If you are using PDS based ATP,
please check that item attribute ""Create Configured Item, BOM"" equals
""Based on Model"" and BOM exists in ship-from org.
DOCUMENTATION BUG: The documentation has this profile
backwards.
Default Value - No
Note Reference(s)
179522.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No

Global Order Promising

No

MRP: Cutoff History Days


Profile Code
Profile Option Name
Description

MRP
MRP_CUTOFF_HISTORY_DAYS
Not used by Advanced Supply Chain Planning
Note 303809.1 has more information about this

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Disable Project Validation


Profile Code
Profile Option Name
Description

MRP
MRP_DISABLE_PROJECT_VALIDATION

Special profile for Seiban project numbers. Used


for release of planned orders from the ASCP
workbench.
Profile set in EBS Source in distributed installation.
Valid values are:

Yes - project validation won't be executed.


No - the project validation will be executed.

Default Value - No when NULL


11.5.10 Patch 6903209
One off patch released by DEV.
Also included in 1st APS Source Side UI patch
7427625 and all Source Side rollups since October
2008
Bug 6903209
One off patch released for 11.5.10
12.0.6
bypass code included in
$MRP_TOP/patch/115/MRPRLWFB.pls
120.1.12000000.6
BUT - the profile is not created, and must be
created manually - see below
12.1.1 and above
bypass code included in
$MRP_TOP/patch/115/MRPRLWFB.pls
120.1.12010000.2 and above
BUT - the profile is not created, and must be
created manually - see below
Maunual Profile Creation details
Application - Master Scheduling/MRP
Hierarchy Type - Security
Hierarchy Type Access Level
Visible and Updatable at the following levels

Site, Application, Responsibility, User


SQL validation:
SQL="select lookup_code, meaning
\"MRP:DisableProjectValidation\"
into :profile_option_value, :visible_option_value
from fnd_lookups
where lookup_type = 'YES_NO'"
Column="\"MRP:DisableProjectValidation\"(*)"

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6865274
-1
Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MRP: Explode Demand Through Phantom


Component
Profile Code
Profile Option Name
Description

MRP
MRP_EXPL_DEM_THROUGH_PHANTOM
Not used in Oracle Advanced Planning.
This is used by MRP to decide whether demand needs to be exploded
through Phantom components or not.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Firm Internal Req Transferred to OE


Profile Code
Profile Option Name
Description

MRP
MRP_FIRM_OE_XFERRED_INTERNAL_REQ
Valid values are:

Yes - all internal requisitions transferred to Oracle Order


Management are treated as firm supplies by Oracle
Advanced Supply Chain Planning
No - Oracle Advanced Supply Chain Planning may generate
reschedule recommendations for these internal requisitions.

Rescheduled recommendations cannot be released to purchasing for internal


requisitions. To reschedule recommendations, cancel the internal requisition
in the source instance and create a new requisition with the new date.
Default Value - Yes
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
Yes
No
No
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No

MRP: Hash Area Size (Bytes)


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_HASH_AREA_SIZE
Used in 11.5.9 and below for Data Collections.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Ignore Alternate BOM/Routing


Profile Code
Profile Option Name
Description

MRP
MRP_IGNORE_ALTERNATES
Not Used in Oracle Advanced Planning, only for Oracle MRP.
Ref Bug 3824520

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Ignore Zero Quantity Demands in Calculating


First Bucket for Statistical Forecasting
Profile Code
Profile Option Name
Description

MRP
MRP_IGNORE_ZERO_QTY_DEMANDS
Not used in Oracle Advanced Planning.
This is for standard MRP Forecasting functionality - program INCFIF

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Net All Purchase Orders Prior To Requisitions


Profile Code
Profile Option Name
Description

MRP
MRP_FIRM_REQS_WITHIN_TF
Use this profile to specify whether or not the planning engine should net all
existing supplies prior to netting purchase requisitions.

Yes - Net purchase orders, then net purchase requisitions.


This may result in purchase requisitions with schedule dates
earlier than purchase orders being canceled or rescheduled
out.
No - Net purchase orders and purchase requisitions
together. Note: If the plan planning mode is Constrained
(Without Detailed Scheduling), the planning engine does not
use this profile option.

Default - No
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Old Sales Orders Cutoff Days


Profile Code
Profile Option Name
Description

MRP
MRP_OLD_SO_CUTOFF_DAYS
Only For MRP, it controls the number of days from sysdate backwards that
the Planning Manager goes to pick up sales orders. For example the value
365 will let the Planning Manager see sales orders up to 365 days old.
Choose a value that will capture all open sales orders.
The Planning Manager will pick up closed sales orders as well, these are
used for forecast consumption in MRP functionality.
A NULL value will pick up ALL sales orders.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Persist ATP Results


Profile Code
Profile Option Name
Description

MRP
MRP_ATP_PERSIST
Profile added in 11.5.9.
This is to fulfill customer specific requirement for reporting on the
MRP_ATP_SCHEDULE_TEMP and MRP_ATP_DETAILS_TEMP tables
data.
Default is NO and should be left as NO
Bug details:
Commit ATP results data (mrp_atp_details_temp and
mrp_atp_schedule_temp) into database instead of removing data as is done
in types of ATP requests.
Customer is using these tables to generate a report.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5102683
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MRP: Plan Revenue Discount Percent


Profile Code
Profile Option Name
Description

MRP
MRP_BIS_AV_DISCOUNT
Specifies the average discount percent applied to all items in a plan. This
value is a key performance indicator used to calculate performance in a plan
for Business Intelligence reports. Valid values are:

Integers between 0 and 100.

Optional - Average Discount to be applied when calculating Revenue of a


plan as part of Plan Performance Indicators Set on EBS Source and APS
Destination in a distributed installation.
Default Value - NULL
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Plan Revenue Price List


Profile Code
Profile Option Name
Description

MRP
MRP_BIS_PRICE_LIST
Lookup for Price List in Order Management Optional - Price List used to
calculate revenue of a plan as part of Plan Performance Indicators- from
SO_PRICE_LISTS. Valid values are:

Numeric

This value is a key performance indicator used to calculate performance in a


plan for Business Intelligence reports. Set in EBS Source in a distributed
installation.
Default Value - NULL
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Planning Manager Run First Time


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_PLNG_MGR_FIRST_TIME
Not used by Oracle Advanced Planning.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: RHX Check Profile


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_RHX_CHECK_PROFILE_FP
Not used by Oracle Advanced Planning.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Round Source Entries


Profile Code
Profile Option Name
Description

MRP
MRP_ROUND_SOURCE_ENTRIES
Not used in Oracle Advanced Planning.
Used by MRP to decide whether to round forecast or sales order quantities
when loading the forecast or MDS.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Sort Area Size (Bytes)


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_SORT_AREA_SIZE
Used for Data Collections in 11.5.9 and below.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Update Requested Completion Date when


Releasing Reschedules
Profile Code
Profile Option Name
Description

MRP
MRP_UPD_REQ_DATE_REL
Not used in Oracle Advanced Supply Planning.
Exists in release code for MRP Planning in MRP_REL_PLAN_PUB
File $MRP_TOP/patch/115/sql/MRPPRELB.pls
See profile for Advanced Supply Chain Planning - MSC: Update Requested
Completion Date when Releasing Reschedules

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Use Alternate SQL for Daily Cleanup


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_ALTERNATE_SQL
Not used for Advanced Planning. This is for the planning manager Once-ADay Task Worker operations. Ref Bug 3958467

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: Use Progress Bar for Backlog Workbench


Profile Code
Profile Option Name
Description

MRP
MRP_ATP_PROGRESS_BAR
MRP: Use Progress Bar for Backlog Workbench
This is the display bar which is present when you schedule orders in the
Order Backlog Workbench.
PERFORMANCE ALERT:
This should be set to No if you are processing many orders OR IF you find
that the Backlog Workbench appears to hang while scheduling orders.

Note Reference(s)
742648.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MRP: i2 Batch Client Timeout


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_BC_TIMEOUT
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 Calc Cumulative Yield


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_ENABLE_CUMUL_YIELD
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 Check if FP installed


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_CHECK_FOR_FP
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 Data Load Timeout


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_DATA_LOAD_TIMEOUT
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 Date Constant


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_DATE_CONSTANT
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 Debug Mode


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_DEBUG
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 Factory Planner Exec Dir Attr Number


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_FP_EDIR_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 Factory Planner User Attribute Number


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_FP_USER_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 Job Change Attribute Number


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_JC_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 Log Directory


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_LOG_DIR
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 Net Change Dir


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_FP_NET_DIR
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Aggregate Resource Attribute


Number
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_AGG_RES_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM BC Delimiter


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_BC_DELIMITER
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM BOM Attribute Consumed


attribute number
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_BOM_AC_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM BOM Attribute Produced attribute


number
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_BOM_AP_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Batch Client Filter


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_BCL_FILTER
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Cooldown Time Attribute Number


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_RES_CDT_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Delimiter


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_DELIMITER
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Enable Attribute Base Planning


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_ENABLE_ABP
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Estimated Queue Time Attribute


Number
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_RES_EQT_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Factory Planner Data Dir Attribute


Number
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_FP_DD_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Factory Planner Host Attribute


Number
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_FP_HOST_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Factory Planner Port Attribute


Number
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_FP_PORT_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Inventory Attribute Alias


Separator
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_INV_AA_SEP
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Minimum Queue Time Attribute


Number
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_RES_MQT_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM OE Attribute Consumed attribute


number
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_OE_AC_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Offloadable To Attribute Number


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_RES_OFFTO_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Offloadable from Attribute


Number
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_RES_OFFFROM_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM PO Attribute Alias attribute


number
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_PO_AA_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Part Buffer Style Attribute Number


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_BUF_STYLE_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM Resource Type Attribute Number


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_RES_TYP_ATTR_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RHYTHM released as firm manufacturing


order
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_RELEASED_AS_FIRM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RhythmLink Data Directory


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_RL_DATA_DIR
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RhythmLink Executable Directory


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_RL_EXEC_DIR
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RhythmLink Host


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_RL_HOST
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RhythmLink Port Number


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_RL_PORT_NUM
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 RhythmLink User


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_RL_USER
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 Start Factory Planner Client


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_START_FP_CLIENT
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 Start RhythmLink Client


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_START_RL_CLIENT
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP: i2 WIP Job Load Timeout


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_I2_P_JOB_LOAD_TIMEOUT
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:ATP Assignment Set


Profile Code
Profile Option Name
Description

MRP
MRP_ATP_ASSIGN_SET
ATP Assignment Set to be used when scheduling Orders for ATP based on
Collected Data.
Required for ATP Based on Collected data to have sourcing information and
provide correct results.
This assignment set will default into the ATP Inquiry when accessed form the
Order Management application.
In a distributed installation, this would be setup on the EBS Source instance
(not required on the APS Destination instance - see MSC: ATP Assignment
Set)

Note Reference(s)
147243.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4567833
-1
-1
-1
Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MRP:ATP Database Link


Profile Code
Profile Option Name
Description

MRP
MRP_ATP_DATABASE_LINK
Determines whether distributed Order Promising is used. This profile is
obsolete in 11.5.10 and later releases.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3049003
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MRP:Activate OLP
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP-OLP
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Allow Safety Stock Pegging


Profile Code
Profile Option Name
Description
Note Reference(s)

MRP
MRP_ALLOW_SS_PEGGING
This is a MRP Profile. Not used in advanced Supply Chain Planning

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5924044
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Backlog Progress Timeout


Profile Code
Profile Option Name
Description

MRP
MRP_BALWB_TIMEOUT
Used to help the performance of the Order Backlog workbench.
Timeout in minutes.
Should be set to 10
Change to other values only at the direction of Development for debugging
an issue with the back log workbench

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MRP:Calculate Excess Exceptions on Time Fence


Profile Code
Profile Option Name
Description

MRP
MRP_CALC_EXCESS_EXCEPT
Indicates whether excess exceptions are calculated at the time fence or up to
the time fence

Yes: The planning engine issuesexceptions only at the time


fence date.

No: The planning engine issues individual exception.

Valid values: yes/no


Default value: yes
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Combine Sugg Rep Schedules


Profile Code
Profile Option Name
Description

MRP
MRP_COMBINE_REP_SCHEDULE
Combines repetitive schedules, if scheduled back-to-back for the same
quantity. Used only by unconstrained plans
Valid values: yes/no
Default value: yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Complete Supply Chain ATP


Profile Code
Profile Option Name
Description

MRP
MRP_COMPLETE_SCATP
Not used by Advanced Supply Chain Planning.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2655891
2941520
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Compute Sales Order Changes


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_COMPUTE_SO_CHANGES
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Consume Fcst Set Summary


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_CONSUME_FC_SET_SUMMARY
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Consume Forecast
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_FORECAST_CONSUMPTION
Not used in Oracle Advanced Planning.

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Consume MDS
Profile Code
Profile Option Name
Description

MRP
MRP_MDS_CONSUMPTION
If set to yes, planning manager needs to be running when loading MDS in the
ASCP plan

Note Reference(s)

790125.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Consume MPS
Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_MPS_CONSUMPTION
If set to yes, planning manager needs to be running on the source to collect
WIP/PO supplies.
790125.1

4890962
-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Create Time fence


Profile Code
Profile Option Name
Description

MRP
MRP_FIRM_ORDER_TF
Instructs the planning engine to create a natural time fence on firm work
orders, purchase orders, flow schedules and shipments. Valid values are:

Yes - create a natural time fence based on firm work orders,


purchase orders, flow schedules, and shipments

No - the planning engine does not create a time fence

The planning engine honors the item attribute Planning Time Fence
regardless of the value of this profile option.
Note Reference(s)

399888.1
422361.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
-1
-1
-1
-1
-1
-1
-1
-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Cutoff Date Offset Months


Profile Code
Profile Option Name
Description

MRP
MRP_CUTOFF_DATE_OFFSET
Determines how many months of resource availability should be computed
for resources and simulation sets. No resource availability is calculated
beyond this horizon. For constrained plans beyond this horizon, resource
capacity is viewed as infinite. Set this value to your plan horizon
Valid values: Integer >= 0
Default value: 6

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4736046
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Debug Mode
Profile Code
Profile Option Name
Description

MRP
MRP_DEBUG
Enable debug messages.
Note:
Has high impact across many applications.
This profile should only be set at USER Level unless otherwise instructed by
support.
Setting at the Site Level can have impact on WIP, BOM, OM, MRP, ASCP
applications.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Yes
No
Yes
Yes
No
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No
No
Yes
No
No
No
No
Yes

MRP:Default Criteria Set


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_DEFAULT_CRITERIA_SET
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Default DRP Plan Name


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_DEFAULT_DRP_NAME
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Default Forecast Date


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_DEFAULT_FORECAST_DATE
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Default Forecast Name


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_DEFAULT_FORECAST
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Default Plan Name


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_DEFAULT_PLAN
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Default Schedule Name


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_DEFAULT_SCHEDULE
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Default Sourcing Assignment Set


Profile Code
Profile Option Name
Description

MRP
MRP_DEFAULT_ASSIGNMENT_SET
Not used by Oracle Advanced Planning.
Used in Oracle Purchasing to determine the sourcing assignment set to
assign sources to requisitions.

Note Reference(s)
209633.1
763822.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7362528
Oracle Global Order Promising Implementation and User's Guide
-1
-1
Oracle Master Scheduling/MRP and Oracle Supply Chain Planning User's
Guide
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MRP:Demand Time Fence Days


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_DEMAND_TF
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Derive PO supply date from need by date


Profile Code
Profile Option Name
Description

MRP
MRP_CALC_SUPDT_FROM_NBDT

Not used in ASCP


Used in Inventory Supply Demand form - Ref Bug
7260101
Check the value of the profile MRP:Derive PO
supply date from need by date
If this set to No, set it to Yes.
Then, we derive the PO due date as need by date
+ post processing lead time.
This calculation is done during the supply/demand
inquiry.
If this is not set, then the date displayed in the
supply/demand inquiry is the
expected_delivery_date in mtl_supply.
If you change the value in the profile option, then
you must also bounce the INV Remote Procedure
Manager for the change to be effective.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7260101
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Enhanced Exception
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_ENHANCED_EXCEPTION
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Environment variable to set path for MRP files


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_FILES_PATH_ENV_VAR
Specifies appropriate path for the MRP files. If this profile option is not used,
files are written to the $APPLOUT directory.

Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Firm Planned Order Time Fence


Profile Code
Profile Option Name
Description

MRP
MRP_FIRM_PO_TF
Instructs the planning engine to create a natural time fence for an item at the
completion date of the latest firm planned order. Valid values are:

Yes - firm planned orders create a natural time fence.

No - planning engine does not create a time fence at a firm


planned order

If the overwrite option in the plan is set to overwrite all, then all firm planned
orders are deleted
Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3642086
2553205
-1
-1
-1
-1
-1
-1
-1
-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Include Schd Rcpts in Use-up


Profile Code
Profile Option Name
Description

MRP
MRP_SCH_RCP_USEUP
If this profile option is set to Yes, it includes scheduled receipts when
computing the engineering change order use-up date.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5087357
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Include Substitute Components


Profile Code
Profile Option Name
Description

MRP
MRP_ATP_SUB_COMP
Indicates whether to include substitute components in the Oracle Global
Order Promising calculation.
Users can update at the site level.
This setting is only applicable when ATP is based on Planning output.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3162334
1555350
-1
-1
Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MRP:Interface Table History Days


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_INTERFACE_HISTORY_DAYS
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:MPS Relief Batch Size


Profile Code
Profile Option Name
Description

MRP
MRP_MPS_RELIEF_BATCH
Not used in Oracle Advanced Planning.
This is for standard MRP processing of MPS Relief.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:MPS Relief Direction


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_MPS_RELIEF_DIRECTION_CONTROL
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Maintain Original Schedule Version


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_ORIGINAL_SCHEDULE_VERSION
Not used in Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Perform Planning Manager Functions in Loads


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_PLANNING_MANAGER_IN_LOADS
Not used by Oracle Advanced Planning

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Planner Batch Size


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_PLANNER_BATCH_SIZE
Not used by Oracle Advanced Planning. This profile is used by the MRP
planning manager. This impacts ASCP only in the sense that it affects how
the planning manager runs.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Planner Workers
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_PLANNER_WORKERS
Not used by Oracle Advanced Planning. This profile is used by the MRP
Planning Manager.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Planning Manager Batch Size


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_SCHED_MGR_BATCH_SIZE
Not used by Oracle Advanced Planning.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Planning Manager Max Workers


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_SCHED_MGR_MAX_WORKERS
Not used by Oracle Advanced Planning.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Purchasing By Revision
Profile Code
Profile Option Name
Description

MRP
MRP_PURCHASING_BY_REVISION
When releasing planned orders, we check if profile is set.
IF NULL, then we check if item has Revision Control checked and if Yes,
then we set revision control Yes
When profile Yes (or NULL and item revision control - Yes), then we update
revision of item based on effectivity date of revisions defined for the item
Set on EBS Source in a distributed environment

Note Reference(s)
238838.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3939138
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Purge Batch Size


Profile Code
Profile Option Name
Description
Note Reference(s)

MRP
MRP_PURGE_BATCH_SIZE
Used by Oracle Advanced Supply Chain Planning collections and Snapshot
.111955.1

Bug Reference(s)
Document References(s)

4590579
-1
-1

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No

MRP:Recommend action within PTF


Profile Code
Profile Option Name
Description

MRP
MRP_REC_ACTION_IN_PTF
Affects exceptions and recommendations. It instructs the planning engine, in
unconstrained plans, to generate recommendations for scheduled receipts
earlier than Planning Time Fence Date.
This profile is not used for MSO (constrained planning), looks at planning
time fence control.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2980511
-1
-1
Yes
No
No
Yes
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Repetitive Past Due Supply Days


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_REP_PAST_DUE_SUPPLY
Not used by Oracle Advanced Planning.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Requisition Load Group Option


Profile Code
Profile Option Name
Description

MRP
MRP_LOAD_REQ_GROUP_BY

This profile is used when the Auto-Release


Planned Orders process is run as part of an Plan
run.
The Auto-Release Planned Orders will launch
when the Production Flag is checked on the Plan
Names form.
Additional Item setups are required for orders to be
eligible for release during this process.
Set in APS Destination instance.
The profile is NOT used when releasing planned
orders from the workbench.
Instead, the Planner workbench /Tools/Preferences - the Plan Preferences - Other
tab - Req Group By
This has a lookup to choose the options for how
you group lines being released to PO application to
create requisitions.
Indicates group by option used when loading
requisitions
Valid values are
DB Value [number] - Application Displayed
Value - Description
1 - All on One - (creates one purchase requisition
for all recommended orders)
2 - Item (creates one purchase requisition for each
item; within each requisition, creates one line for
each planned order),
3 - Buyer - (creates one purchase requisition for
each buyer; within each requisition, creates one
line for each planned order),
4 - Planner - (creates one purchase requisition for
each planner; within each requisition, creates one

line for each planned order),


5 - Vendor - (creates one purchase requisition for
each vendor; within each requisition, creates one
line for each planned order),
6 - Category - (creates one purchase requisition
for each item category; within each requisition,
creates one line for each planned order,
7 - One each (creates a purchase requisition for each planned order).

8 - Location - PO Req Import process chooses


deliver to location to group the lines.
Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

779922.1

-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
Yes
Yes
No
No
No
No
Yes
No
No
No
No
No
No

MRP:Retain Dates Within Calendar Boundary


Profile Code
Profile Option Name
Description

MRP
MRP_RETAIN_DATES_WTIN_CAL_BOUNDARY
Determines whether to pull dates outside the calendar boundary into
calendar horizon.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4874810
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Snapshot Pause for Lock (Minutes)


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_SNAPSHOT_PAUSE_FOR_LOCK
Not used by Oracle Advanced Planning.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Snapshot Substitute Parts


Profile Code
Profile Option Name
Description
Note Reference(s)

MRP
MRP_SNAP_SUBSTITUTES
Not used in Oracle Advanced Planning.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6436732
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Snapshot Workers
Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_SNAPSHOT_WORKERS
Determines number of workers launched by the snapshot monitor. When set
to 0, the Snapshot runs as a single- threaded process. Snapshot workers
collect data on bills of material, work in process, on- hand quantities,
purchasing, firm planned orders, routings, and work-in-process job resource
requirements.
111955.1
824317.1
130995.1

-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Sourcing Rule Category Set


Profile Code
Profile Option Name
Description

MRP
MRP_SRA_CATEGORY_SET
Not used in Advanced Supply Chain Planning
Indicates the category set used when Oracle Supply Chain Planning or
Oracle Purchasing creates sourcing assignments at category-org or category
level.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Time Fence Warning


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_MPS_TIME_FENCE_WARNING
Not used in Oracle Advanced Planning.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Trace Mode
Profile Code
Profile Option Name
Description

MRP
MRP_TRACE
Enable trace option for MRP, ASCP, other processes.
This should only be used with suggestion of support since this reaches to
many different applications.
Should only be set at User Level to avoid tracing many application
processes.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
Yes
No
No
No
Yes
Yes
Yes
No
No
No
No
No
No
No
Yes

MRP:Use Direct Load Option


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MRP
MRP_DIRECT_LOAD
Valid values are:

Yes - SQL Loader is called directly to load rows into the


database during planning.

No

Default Value - No
307443.1

-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
Yes
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MRP:Use Ship Arrived Flag


Profile Code
Profile Option Name
Description

MRP
MRP_SHIP_ARRIVE_FLAG
Determines whether sales orders are automatically viewed as arrived at a
customer site after transit lead-time has expired. Used when a customer is
modeled as an organization

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MRP_NEW_PLANNER_BACK_COMPATIBILITY
Profile Code
Profile Option Name
Description

MRP
MRP_NEW_PLANNER_BACK_COMPATIBILITY

Per bug 9848641:


There have been changes back and forth with this
profile in combination with MSC: New Planner
Backward Compatibility.
1. MRP profile will remain the same. It will decided
whether an item should be treated as phantom or
not.
2. MSC on the other hand will now decide whether
the new algorithm would be used or the old one.
Yes would mean old and No would mean new.
Yes - Phantoms will be treated as regular items
and planned orders will be created.
No - Phantoms will be exploded, and not appear in
the plan.
Default - Null - which is No

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized

9848641
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
-1
Yes
No
No
Yes
Yes
Yes
Yes
Yes
No
No
No
Yes
Yes
Yes
Yes

Disable Constraints Not Optimized


Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
Yes
No
No
No
No
No
No
No

MSC : Consider all supplies for VMI replenishment


calculation
Profile Code
Profile Option Name
Description

MSC
MSC_VMI_ALL_SUPPLY
When profile is set as yes the VMI engine considers all manually created
PO/PR/ASN/Shipments as supply and account them in replenishment
calculation

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5949512
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC : Consume Highest Revision Forecast


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_CONSUME_HIGHEST_REV_FCST
Lower revision SOs consume against forecast of only the Highest revision

-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC : Publish Supply Commit based on pegging


information
Profile Code
Profile Option Name
Description

MSC
MSC_PUBLISH_SUPPLY_COMMIT
Enables or disables detailed publish of supply commits as a single supply
commit record or multiple supply commit records if there are multiple
supplies to meet the demand. Valid values are:

Yes
No

Default Value - No
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC : VMI Requisitions Need By Date at RTF end


Profile Code
Profile Option Name
Description

MSC
MSC_VMI_REQUISTION_AT_RTF_END
When set to yes, this profile option ignores the release time fence.
This enhancement impacts only the need-by date on the requisition that is
created, when a replenishment is released from VMI
Added the code to ignore RTF if the profile "VMI Requisitions Need By Date
at RTF end" is set to No. The default value of this profile is "Yes".
Set on APS Destination in a distributed environment

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6001195
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: 64-bit Planner Platform


Profile Code
Profile Option Name
Description

MSC
MSC_PLANNER_PLATFORM
Set to the supported 64-bit platforms. Valid values are:

Sun 64-bit - 1
HP 64-bit - 2
AIX 64-bit - 3
Linux 64-bit - 4
HP Itanium 64-bit - 5

Note Reference(s)
254810.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6836990
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: APCC - Enable Cumulative Measures in


Archive
Profile Code
Profile Option Name
Description

MSC
MSC_APCC_ENABLE_CUM

When a plan is published from ASCP to APCC, all


fact tables are loaded irrespective of customer
needs.
The profile provides user the ability to load data of
selected facts/measures where possible.
It has Yes/No values, and defaults to Yes.
To disable cumulative measures, user needs to
explicitly set it to No.
When the profile "MSC: APCC - Enable Cumulative
Measures in Archive" is set to No
the following tables are not populated during
archive:
- MSC_DEMANDS_CUM_F
- MSC_RESOURCES_CUM_F

Note Reference(s)

Bug Reference(s)

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning

10252796
12612608
12617301
-1
-1
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
Yes
No
No

MSC: APCC Archive SCRM Measures


Profile Code
Profile Option Name
Description

MSC
MSC_APCC_ENABLE_SCRM

This is about performance problems in


msc_phub_cost_pkg due to source_count
section. It has to process msc_item_sourcing, and
has to densify by
multiplying weeks in horizon. This makes data
volume large, and results in
performance problems.
But source_count measures are mostly used for
SNO plans, while performance
problem in this bug happened on ASCP plans.
Confirmed with PM, we should
allow user to turn it off by setting a profile option.
We introduced new profile option "MSC: APCC
Archive SCRM Measures"
(MSC_APCC_ENABLE_SCRM, Yes(default)|No),
when set to No, source_count is
skipped. Following presentation columns are not
populated:
"- Excess, Obselescence And Risk
Management"."Count of Sources"
"- Excess, Obselescence And Risk
Management"."Count of Sources in IO Plan"
"- Sourcing Effectiveness"."Count of Items Single
Sourced"
Values:
with profile options "MSC: APCC Archive SCRM
Measures" set to "Yes'and "No" and also with
blank.
Blank and yes will have same result as the default
value is blank.
When profile set to "Yes" the count of sources and
Count of Items single
sourced are populated and when "No" the Count of
Sources and Count of Items
single sourced are not populated. Hence

performance could be improved by


switching off the profile.
Note Reference(s)

Bug Reference(s)

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

12820986
12845928
12820986
10252796
13638350
-1
-1
-1
-1
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Calendar Code


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_HUB_CAL_CODE
Used in the dashboard to code manufacturing calendar.

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: APCC Category Set 1


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_HUB_CAT_SET_ID_1
Used to filter the category set name. Only 3 category sets are supported, and
dashboards will use this profile in the dashboards.
844667.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Category Set 2


Profile Code
Profile Option Name
Description

MSC
MSC_HUB_CAT_SET_ID_2
This profile works in conjunction with MSC: APCC Category Set 1 and MSC:
APCC Category Set 3. These profiles govern which category set the
analytical layer when displaying the item-category hierarchy uses.
It precomputes the data for all three hierarchies, but displays the data using
only the MSC: APCC Category Set 1 value. Therefore, if the user wants to
view using the value in MSC: APCC Category Set 2, the values in these two
profiles must be switched. The user can then see the results using the new
category set, which is now in the MSC: APCC Category Set 1 profile.
There is no need to rerun the plan or republish it to APCC, however, if user
decides to use a completely new category set, which is not currently in these
three profiles, then the
profile values must be updated, and the plans must be rerun, or republished,
to APCC for the change to take effect.

Note Reference(s)

This is a site level profile


759571.1

844667.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6836737
-1
-1
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Category Set 3


Profile Code
Profile Option Name
Description

MSC
MSC_HUB_CAT_SET_ID_3
This profile works in conjunction with MSC: APCC Category Set 1 and MSC:
APCC Category Set 2. These profiles govern which category set the
analytical layer when displaying the item-category hierarchy uses.
It precomputes the data for all three hierarchies, but displays the data using
only the MSC: APCC Category Set 1 value. Therefore, if the user wants to
view using the value in MSC: APCC Category Set 3, the values in these two
profiles must be switched.
The user can then see the results using the new category set, which is now
in the MSC: APCC Category Set 1 profile.
There is no need to rerun the plan or republish it to APCC, however, if user
decides to use a completely new category set, which is not currently in these
three profiles, then the
profile values must be updated, and the plans must be rerun, or republished,
to APCC for the change to take effect.
This is a site level profile.

Note Reference(s)
844667.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Category set for detailed pegging


analysis
Profile Code
Profile Option Name
Description

MSC
MSC_APCC_PEGGING_CAT_SET
Category set for detailed pegging analysis. APCC archives pegging
information for ASCP items of this catetory set.

Note Reference(s)
1225973.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

10013480
12746734
-1
-1
-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Currency Code


Profile Code
Profile Option Name
Description

MSC
MSC_HUB_CUR_CODE_RPT
The analytical layer to convert the values in functional currency to a common
reporting currency uses this. This profile is used as the reporting currency for
APCC.
Please note that if this profile is changed the plan must be republished to
APCC repository to see the data in the new currency.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

This is a site level profile.


759571.1
844667.1

-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Gather Fact Tables Statistics


Profile Code
Profile Option Name
Description

MSC
MSC_APCC_GATHER_FACT_STATS
Profile is used for gathering table stats on fact tables such as
MSC_SUPPLIES_F, MSC_ITEMS_F, etc.
Valid Values

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

13967788
-1
-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

Yes
No (default)

MSC: APCC Gather Intermediate Tables Statistics


Profile Code
Profile Option Name
Description

MSC
MSC_APCC_GATHER_ST_STATS
Profile is used for gathering table statistics on staging tables such as
MSC_ST_SUPPLIES_F, MSC_ST_ITEMS_F, etc.
Valid Values

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

13967788
-1
-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

Yes
No (default)

MSC: APCC Gather Plan Tables Statistics


Profile Code
Profile Option Name
Description

MSC
MSC_APCC_GATHER_PDS_STATS
Profile is used for gathering table statistics on staging tables such as
MSC_ST_SUPPLIES_F, MSC_ST_ITEMS_F, etc.
Valid Values

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

13967788
-1
-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

Yes
No (default)

MSC: APCC Instance


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_APCC_TARGET_DBLINK
Name of the database link in the 11.5.10 server to the 12.1 APCC instance. It
is used by the archive plan summary to push the plan summary for 11.5.10
Planning Server to the APCC Server.
This profile options is set up on the APS 11.5.10 instance only.
844667.1

8665145
8597162
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Period Set name


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_HUB_PERIOD_SET_NAME
The analytical layer and the dashboards that display time in the hierarchy of
days, fiscal periods, quarters, and year use this.
This is a site level profile.
759571.1
844667.1

-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC SNO Item Simulation Set


Profile Code
Profile Option Name

MSC
MSC_APCC_SNO_ITEM_SIMULATION_SET

Description

Bug 9274349: APCC


SUPPORT SNO ITEM
SIMULATION SET
FOR EXCESS AND
OBSOLESCENCE
FACTS.
temporary solution for simulation sets for sno in apcc

It'll wort like this:- user sets the profile option before publishing SNO
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9274349
9612415
-1
-1
No
No
No
No
No
No
No
No
No
No
No
Yes
Yes
No
No

MSC: APCC WebLogic Console Password


Profile Code
Profile Option Name
Description

MSC
MSC_WC_WEBLOGIC_PASSWORD

Note Reference(s)

1081051.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC: APCC WebLogic Console Password

-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

Webcenter

MSC: APCC WebLogic Console Username


Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_WC_WEBLOGIC_USERNAME
Set it to WebLogic admin user. For example, weblogic. This user should be
the admin user for WebLogic.
1081051.1

-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC WebLogic Password


Profile Code
Profile Option Name
Description

MSC
MSC_WS_WEBLOGIC_PASSWORD

Note Reference(s)

1081051.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC: APCC WebLogic Password

-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

Soa server

MSC: APCC WebLogic Username


Profile Code
Profile Option Name
Description

MSC
MSC_WS_WEBLOGIC_USERNAME

Note Reference(s)

1081051.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC: APCC WebLogic Username

-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

Soa server

MSC: APCC Webcenter Admin URL


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_WC_ADMIN_URL

No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Webcenter Enabled


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_WC_ENABLED
7
MSC_WC_URL
MSC: APCC Webcenter URL
Webcenter URL
For example,
http://rws60018rems.us.oracle.com/webcenter/wcAuthentication/?login=true
&success_url=/spaces
Replace your host and keep the other things same. Then, you skip the
Webcenter welcome/login screen when navigating from e-Business Suite to
Webcenter.
1226033.1

-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Webcenter Group Space Template


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_WC_SPACES_TEMPLATE
3
MSC_WC_SPACES_TEMPLATE
MSC: APCC Webcenter Group Space Template
Webcenter Group Space Template Name
For example,
1226033.1

-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Webcenter Spaces Member Role


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_WC_SPACES_MEMBERROLE
2
MSC_WC_SPACES_MEMBERROLE
MSC: APCC Webcenter Spaces Member Role
Viewer Or Participant
Members added to the webcenter group space can be either viewers or
participants.
1226033.1

-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Webcenter Spaces Port


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_WC_SPACES_PORT
6
MSC_WC_SPACES_PORT
MSC: APCC Webcenter Spaces Port
Webcenter Spaces managed server Port
For example, 8877
1226033.1
1081051.1

-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Webcenter Spaces Recipient Key Alias


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_WC_SPACES_RECIPIENTKEYALIAS
4
MSC_WC_SPACES_RECIPIENTKEYALIAS
MSC: APCC Webcenter Spaces Recipient Key Alias
Recipient Key Alias
For example,
1226033.1

-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Webcenter Spaces Saml Issuer Name


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_WC_SPACES_SAMLISSUERNAME
5
MSC_WC_SPACES_SAMLISSUERNAME
MSC: APCC Webcenter Spaces Saml Issuer Name
Saml issuer name of Webcenter
For example, www.oracle.com
1226033.1

-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC Webcenter URL


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_WC_URL
7
MSC_WC_URL
MSC: APCC Webcenter URL
Webcenter URL
For example,
http://rws60018rems.us.oracle.com/webcenter/wcAuthentication/?login=true
&success_url=/spaces
Replace your host and keep the other things same. Then, you skip the
Webcenter welcome/login screen when navigating from e-Business Suite
1226033.1

-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: APCC to APS database link name


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_APCC_BACK_TO_SELF_DBLINK
new profile option "MSC: APCC to APS database link name" (MSC_APCC_BACK_T

Bug Reference(s)

8856448
8665145
-1
-1

Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: ASCP Planning URL


Profile Code
Profile Option Name
Description

MSC
MSC_ASCP_WEBLOGIC_URL

ASCP Weblogic Server URL


This profile is available in VCP 12.1.3.8 and later.
The profile is used for the ASCP Usability
Enhancements for the deployment of the ASCP
application to weblogic.

Note Reference(s)
1493554.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Planning Command Center User's Guide


-1
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: ATP Allocation Method


Profile Code
Profile Option Name
Description

MSC
MSC_ALLOCATION_METHOD
For ATP based on Planning Output only

Note Reference(s)

This site-level profile determines the allocation method used by ATP.


This is a site level profile.
Values are:
User-Defined Allocation Percentage
Demand Priority
334286.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: ATP Capacity Allocation


Profile Code
Profile Option Name
Description

MSC
MSC_CAP_ALLOCATION
Set it to No.
You should only set it to Yes with specific instruction from Oracle
Applications development

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Global Order Promising Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: ATP Debug Mode


Profile Code
Profile Option Name
Description

MSC
MSC_ATP_DEBUG
Used to create debug files for ATP.
Files are named session-[number] -- [number] is assigned by a sequence.
In a distributed installation, files are created on both the EBS Source
instance and APS Destination instance.
Both files are required for Support and DEV to investigate an ATP issue.
Note 122372.1 is key guide to producing and providing these files to support.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Values are:
+ Debug Only: ATP generates a log file for an ATP request.
+ Debug and Database Trace: ATP generates a log file and a database trace
file.
+ Database Trace Only: ATP generates a database trace file.
+ None: ATP does not generate a log file or a database trace file. (Default)
954333.1
122372.1

-1
-1
Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: ATP Enforces Lead Time for ATO Model


Profile Code
Profile Option Name
Description

MSC
MSC_ENFORCE_MODEL_LT
Used for ATP based on Collected Data
Indicates whether ATP enforces lead time for ATO models or not.
+ Yes - Enforces lead time for ATO models.
+ No - Does not enforce lead time for ATO models.

Note Reference(s)

1177424.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Global Order Promising Implementation and User's Guide


Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: ATP Infinite Time Fence Pad


Profile Code
Profile Option Name
Description

MSC
MSC_ATP_INFINITE_TF_PAD
Add Offset Days to Infinite Supply Fence
Per Note 227406.1 for 11.5.9
Results displayed by Oracle Advanced Supply Chain Planning
and
ATP mismatch when considering the Infinite Supply Fence Date to
satisfy demands. Oracle Advanced Supply Chain Planning considers
Delivery
Calendar, but ATP does not.
A new profile option MSC: ATP Infinite Time Fence Pad has
been
created to offset the Supply Fence Date with the number of days
set
by user. ATP adds this number to the Infinite Supply Fence Date.
Thus, the Oracle Advanced Supply Chain Planning matches the ATP output.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Note: Once in 11.5.10 and using MSC: Use Shipping/Receiving Calendars,


this profile should be obsolete for functional purposes.
227406.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: ATP Synchronization Downtime (minutes)


Profile Code
Profile Option Name
Description

MSC
MSC_ATP_SYNC_DOWNTIME
Used for ATP 24x7 plan run.
Determines the approximate ATP downtime (in minutes) to cover the time
required to synchronize and to switch over to the
refreshed plan during the plan synchronization process. Oracle Global Order
Promising internally translates this value into
the number of orders to process.
You should set the value for this profile based on the sales order volume
during the ATP 24x7 plan run.
This profile option also determines the duration of the extended
synchronization process.
This process is executed for the duration of the ATP downtime or 10 minutes
(default), whichever is larger.
Note:
ATP Post Plan Processing is where this is executed and it reports in the log
file how much downtime was used.
Actual downtime is usually very small and default value of 10 mins should not
require any changes.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Global Order Promising Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: ATP Web Service Responsibility


Profile Code
Profile Option Name
Description

MSC
MSC_WS_ATP_FNDRESP
Responsibility used when ATP web service is invoked.
Not used yet

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6625571
-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
Yes

MSC: ATP Web Service User


Profile Code
Profile Option Name
Description

MSC
MSC_WS_ATP_FNDUSER
User used when ATP web service is invoked
Not Used yet.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6625571
-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
Yes

MSC: AVOID RE-SOURCING SALES ORDERS


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC: AVOID RE-SOURCING SALES ORDERS
Ignore this profile, it is duplicate and needs to be removed.
See instead - MSC: Avoid Re-Sourcing Sales Orders
MSC_AVOID_RESOURCING_SALES_ORDERS
352277.1

6134419
12846307
-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Action Allowed on ATP 24x7 Plan While


Running
Profile Code
Profile Option Name
Description

MSC
MSC_ALLOWED_ACTION_24X7
Profile to control whether 24X7ATP plan can be viewed and updated while
the plan is running.
Determines whether manual updates are allowed to the original plan when
the plan copy is running.
Values are:
Yes: The ATP plan appears in the Workbench window while it is running.
You can make changes to the plan. However, the changes will not appear in
the refreshed plan.
No: The ATP plan appears only in the View Plan window.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Aggregate Resource Name Flexfield Attribute


Profile Code
Profile Option Name
Description

MSC
MSC_AGGREG_RES_NAME
This profile option stores the name of the flexfield column that contains the
value in the corresponding table. See 'Flexfield Attributes, page A-1 for more
information.

Set in EBS Source in a distributed installation.

Created by Create Planning Flexfields concurrent request.


Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Align Component Demand Date with Pegging


Date
Profile Code
Profile Option Name
Description

MSC
MSC_ALIGN_COMP_DMD_WITH_PEG
Per Bug 6512739The work orders are scheduled out further than planned
order--"cross scheduling", because the assembly level, the pegging window
is very large, causing some early component supplies are pegged (via multihop) to late high priority demand. The scheduler's right justification pushes
the work orders out.
.
Introduce a profile MSC: Align Component Demand Date with Pegging Date.

Yes - the component demand will be pushed out in the first


place, so it has less chance to grab the work orders

First introduced in 11.5.9 - Bug 5903195


Forward ported to 11.5.10 and included in ASCP Engine/UI RUP #33
Forward ported to R12 in Bug 6266579 and present in CU3 patch 6731645
and included in 12.0.6 Fixed in base release of 12.1.1
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6512739
6266579
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Allocated ATP Forward Consumption Method


Profile Code
Profile Option Name
Description

MSC
MSC_ATP_FORWARD_CONSUME_METHOD
Determines the type of forward consumption that Oracle Global Order
Promising can perform to accommodate the shortage faced by a demand
class.
Values are:
+ Reduce future supply from lowest priority:
Use the available supply from the lowest priority demand to account for the
shortage of a demand class. If every demand class is at same priority,
reduce the future supply to cover the shortage for a demand class.
+ Reduce available supply from any priority:
A promised demand is the most important demand that you need to meet.
Oracle Global Order Promising starts the
adjustments from the higher priority demand class. That is, Oracle Global
Order Promising reduces the availability
of a lower priority demand class before a higher priority demand class to
account for shortages from a previous period.
Thus, it reduces the available supply to account for the shortage from lower
priority demand classes.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Global Order Promising Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Allocation Assignment Category Set


Profile Code
Profile Option Name
Description

MSC
MSC_ALLOC_CATEGORY_SET
The Assign Allocation Rule form and the Sourcing assignment form both use
the MSC: Sourcing Category Set to determine the valid category set. Use
this profile option if you want the allocation rule category set to be different
from the sourcing
assignments category set.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3128505
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Allow Release of Planned Orders from


Demand Schedule Plan
Profile Code
Profile Option Name
Description

MSC
MSC_DRP_RELEASE_FROM_MRP
This profile option provides increased flexibility for releasing planned orders
and applies to manual release from the workbench and also for the AutoRelease Planned Orders process that runs during plan run.
Valid values are:

Yes - You can release demand schedule MPP or MPP


planned orders from the lower level plan

No - You cannot release demand schedule MPP or MPP


planned orders from the lower level plan

Set on APS Destination in a distributed environment


Note Reference(s)
795033.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5852065
-1
-1
-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Allow release of replenishments above


suggested quantity
Profile Code
Profile Option Name
Description

MSC
MSC_VMI_RELEASE_ABOVE_MAX
When set to yes, this will allow users to replenish more than the suggested
quantity.
Used in Collaborative Planning for release of VMI Orders
Set on APS Destination in a distributed environment

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3389269
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Analytics Currency Code


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_ANALYTICS_CURRENCY_CODE
No Documentation available for this profile.

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Anchor date for calculating operation yields


Profile Code
Profile Option Name
Description

MSC
MSC_OPERATION_YIELD_TYPE
Use this profile option to instruct the planning engine on which effectivity date
to use when it generates resource requirements of operations with yields.
This profile option applies to discrete jobs and Oracle ShopFloor
Management (OSFM) routings with primary network scheduling method.

(1) - Operation start date: Use the operation start date to


check for operation effectivity and select yield value.
(2) - Order start date: Use the order start date to check for
operation effectivity and select yield value.

The planning engine uses lead-time percent to calculate the operation start
date; it assumes that the lead-time percent of an operation that is effective in
the future is the same as the lead-time percent of the operation it replaces. If
an operation's effectivity ends within a time bucket, the planning engine
assumes that its effectivity ends on the first day of the time bucket.
Note: The code will internally set this profile as Order Start Date if it is not
setup.
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3161454
-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Anchor date for calculating remaining shelf


life
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_USE_SHIP_DAYS_FOR_MRSL
Specifies arrival date or ship date as the anchor date to use when calculating
the remaining shelf life
760046.1

-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Apply Lot Modifiers in Weekly/Period Buckets


Profile Code
Profile Option Name
Description

MSC
MSC_APPLY_LOT_MODIFIER
Determines whether order modifiers are considered when creating planned
orders for weekly or period time buckets. Valid values are:

Yes - considers order modifiers in these calculations


No - does not consider order modifiers in these calculations

Default Value - NULL (Yes)


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No

MSC: Apply Order Modifier To Start Quantity


Profile Code
Profile Option Name
Description

MSC
MSC_APPLY_OM_TO_START_QTY
Use this profile option to specify whether order modifiers are applied to start
quantities for discrete or lot based jobs. This behavior only applies to routings
that have operation yield. In this case the start quantity may be different
from the expected supply quantity. Valid values are:

Yes - The planning engine inflates the order start quantity by


the routing operation yield and then applies order modifiers.
No - The planning engine applies the order modifiers to the
end quantity

Default Value - No
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
Yes
No
No
No
Yes
No
Yes
No
No
No
No
No
No
No
No

MSC: Apply Safety Stock Change interval to non


MRP Planned Safety Stock
Profile Code
Profile Option Name
Description

MSC
MSC_SS_SMOOTH_NON_MRP
Use this profile option to specify the safety stock to which the smoothing
within time interval applies: Valid values are:

Yes - Smoothing applies to all types of safety stock


No - Smoothing applies only to MRP planned safety stock

Note Reference(s)
276707.1
759329.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Apply shortage and excess tolerance to


planned orders
Profile Code
Profile Option Name
Description

MSC
MSC_APPLY_TOL_PLAN_ORD
Introduced in ASCP Egnine/UI rollup #33
Valid values are:

Yes - The shortage tolerance and excess percentages are


applied to all supplies including planned orders. This is the
default value.
No - The shortage tolerance and excess percentages are
applied only to firm existing supplies (such as Onhand, WIP).

Introduced in ASCP Engine/UI rollup #33.


11-May-2010 - Not front ported to any R12.x release.
Default Value - Yes
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7461501
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Auto-Release Compression Days Tolerance


Profile Code
Profile Option Name
Description

MSC
MSC_AUTO_REL_COMP_TOLERANCE
Allows orders to be auto-released provided their compression is not more
than the value specified
Set on APS Destination in a distributed environment
In the Planner workbench you can use /Folder/Show Field to show
Compression field to see how much compression - if any - is calculated for a
planned order.
Remember that Auto-Release will release orders based on the Suggested
Order Date for the planned order
(NOT the Suggested Due Date) - this field is also available via /folder/Show
field
Suggested Due Date - date order to be available in inventory
Suggested Dock Date - Due Date - Post processing Lead Time
Suggested Start Date - Dock Date - Processing LT
Suggested Order Date - Start Date - Pre-processing LT
Example:
Assume the profile = NULL
Item/Org setup has Release time fence days User define - 15,
Leadtime is 10 days (working days).
New planned order created due on working day 1 though 9 will not be
released since the lead time is being compressed.
The Sugg Order Date will show the anchor date of the plan and Compression
Days field will be greater than 0.
But any planned order that with Compression Days 0 and Sugg Order Date =
to the anchor date of the plan run out to working day 15 will be released
Set the profile to 10. Now in the above example, the planned order will be
released on working day 1 through 9 since you're allowed up to 10
compression days for Autorelease to release the planned order.
The Production Flag must be checked in the Plan Names form for
Autorelease to run during the plan run.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
Yes
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No

Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No

MSC: Automatically Recalculate Operation Time


Profile Code
Profile Option Name
Description

MSC
MSC_RECALCULATE_OP_TIME
Enables automatic re-calculation of "New Date" (due date) of make orders
when order is firmed and the "New Start Date" is updated by the user. This
takes into account Fixed and Variable Lead Times and working days. This is
done only in the case of unconstrained plans and has certain limitations.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6142627
9359714
-1
-1
Yes
No
No
Yes
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Avoid Re-Sourcing Sales Orders


Profile Code
Profile Option Name
Description

MSC
MSC_AVOID_RESOURCING_SALES_ORDERS
Possible values: Yes or No - Default = Yes (If null, then Yes)
Yes - To maintain backward compatibility. Planning logic will avoid sourcing
sales orders.
This will disable the following functionalities: plan by arrival date, change ship
methods, and change source org for sales order lines.
No - With this setting, you can plan by arrival date, change ship methods,
and change source org provided you have set up the correct sourcing rules.
Introduced because ASCP planning was resourcing FIRM sales orders and
changing the ship method that was chosen on the sales order.
This is not forward ported to 12.1 or 12.2
Fixed in 11.5.10 and 12.0.6

Note Reference(s)
352277.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6134419
12846307
-1
-1
-1
Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: BPEL Demantra Password


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SCN_DEMANTRA_PASSWORD
Required for launching Demantra nodes in BPEL, default value is soa.
759571.1

-1
No
No
No
No
No
No
No
No
No
No
Yes
No
Yes
No
No

MSC: BPEL Demantra Username


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SCN_DEMANTRA_USERNAME
Required for launching Demantra nodes in BPEL, default value is soa.
759571.1

-1
No
No
No
No
No
No
No
No
No
No
Yes
No
Yes
No
No

MSC: BPEL Domain Name


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SCN_BPEL_DOMAIN
Required for launching BPEL. To deploy custom BPEL processes, you must
deploy the processes to the domain that is specified in the profile option
MSC:BPEL
759571.1

-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: BPEL End Point URI


Profile Code
Profile Option Name
Description

MSC
MSC_SCN_SERVICE_ENDPOINT
Required for launching BPEL, typically:

Note Reference(s)

http://[m/c name]:port
759571.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: BPEL Process Version


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SCN_BPEL_VERSION
Deployed BPEL process flows version number.
759571.1

-1
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: Batch Size for Self Service Loads


Profile Code
Profile Option Name
Description

MSC
MSC_SELF_SERVICE_LOADS_BATCH_SIZE
For large data loads using Legacy Self Service Loads, set to a higher value
in combination with profile MSC: Number of Workers for Self Service Loads
to achieve best fit for performance and data size being loaded. Valid values
are:

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Integer

Default Value - 1000


352277.1

-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Batchable Flag


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_BATCHABLE_FLAG
No longer used in ASCP

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Batching Window


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_BATCHING_WINDOW
Not used in Oracle Advanced Planning.

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Buy Order Processing Lead Time Calendar


Profile Code
Profile Option Name
Description

MSC
MSC_BUY_ORDER_PROCESSING_LEAD_TIME_CALENDAR
Use this profile option to instruct the planning engine what calendar to use
when it offsets processing lead-time for buy orders. Valid values are:

Supplier Capacity Calendar - The planning engine offsets


processing lead-time for buy orders using the Approved
Supplier List Supplier Capacity Calendar. The Approved
Supplier List Supplier Capacity Calendar is the successor to
the Approved Supplier List supplier delivery calendar.
Org Manufacturing Calendar - The planning engine offsets
processing lead-time for buy orders using the organization
manufacturing calendar.

This profile was introduced to offer backward compatibility to the way


processing Lead-time was calculated in 11.5.9. The equivalent of the 11.5.9
functionalty is to use Org Manufacturing calendar.
Notes:
Ref Note 566206.1 for more information.ATP does not currently use this
profile. an ASL must be assigned to the item with the Supplier Capacity
Calendar same as the Org calendar to get ATP to offer the same
functionality as ASCP planning
Default Value - Supplier Capacity Calendar
Note Reference(s)
566206.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
Yes
No
No
Yes
No
No
No
No
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
Yes
No

MSC: CP Debug Level


Profile Code
Profile Option Name
Description

MSC
MSC_CP_DEBUG
Controls the level of detail in the concurrent program log messages for
Oracle Collaborative Planning. Valid values are:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

295564.1

-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

Off - No debug messages generated


On - Short debug messages generated
High - Detailed debug messages generated.

MSC: Calendar Reference for Bucketing


Profile Code
Profile Option Name
Description

MSC
MSC_BKT_REFERENCE_CALENDAR

Calendar used for bucketing KPI's.


If the profile option MSC:Calendar Reference for
Bucketing is null, then the plan owning organization
calendar is used for the plan bucketing. If this
profile points at a valid calendar, then the plan will
use that calendar for bucketing
Also known to cause plan failures, Signal 11 errors
when this not setup.
No formal documentation on the profile

Note Reference(s)

452630.1
372199.1
603981.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
-1
Yes
No
No
Yes
No
No
No
No
Yes
No
Yes
No
No
No
No
No
No
No
No

MSC: Cancel Oustanding Sales Order Quantities


Profile Code
Profile Option Name
Description

MSC
MSC_FILL_OR_KILL_ENABLED
Valid values are:

No - then the DRP engine behavior is not affected and does


not exhibit 'Fill or Kill'.
Yes - then for any sales orders with open quantities after the
Latest Acceptable Date, the quantities are canceled and the
demands are not carried forward. The cancellation is
effective as of the Latest Acceptable Date (which is
considered by DRP as the end of the allocation bucket).

Note that the only order modifier that is considered when determining partial
allocations to sales orders is the Round Order Quantities item attribute for
the shipping organization.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: Category Set for Jobs without an Item


Reference
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_NO_ACTIVITY_ITEM_CATEGORY_SET
No information available for this profile in user guides.

No
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Category Set for Liability Analysis


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_CATEGORY_SET_NAME
Not used in Oracle Advanced Planning.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5481643
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Category for Jobs without an Item Reference


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_NO_ACTIVITY_ITEM_CATEGORY
No Information available in user guides.

No
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Category set for CP Horizontal View


Profile Code
Profile Option Name
Description

MSC
MSCX_CP_HZ_CATEGORY_SET
Indicates a category set that you want to query in the Oracle Collaborative
Planning horizontal view. Using this profile option, you can restrict queries to
specific categories based on your requirement.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2422506
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Category set for Strategic Planning


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_STRATEGIC_PLANNING_CATEGORY_SET
Information about this profile is not available in user guides.
365112.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Category set for serviceable items


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SERVICE_ITEMS_CATSET
Category set to hold the serviceable Items. This profile is used to designate
the category set to which all Serviceable (FRU) items have been assigned.
1225993.1

-1
No
No
No
No
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSC: Choice of item for which to create supplies in


substitute relationship
Profile Code
Profile Option Name
Description

MSC
MSC_ITEM_CHOICE_FOR_SUBSTITUTE
Determines the item for which Oracle Global Order Promising and Oracle
Advanced Supply Chain Planning creates planned supplies when item
substitution relationships are specified.
Choices are:
Demanded Item (default), (701)
Highest Level Item, (702)
Follow Item Attributes (703)
When set to Follow Item Attribute and the item attribute Create Supply for all
the substitute items in the substitution chain is No, no supplies are created.
When you have a substitution chain A --> B --> C, and this profile option is
set to Highest Level Item, it is expected that Oracle Advanced Planning
creates supply for item C. Item C must be enabled in the organization where
you are trying to create supply. If item C is not enabled in the organization,
Oracle Advanced Planning creates supply for item B (the next highest level
item in the substitution chain) and does not create supply for item C.
Oracle Global Order Promising currently supports only the No Substitution or
Full Substitution options. It does not support partial substitution. Therefore, a
request is not fulfilled by using a partial quantity from the requested item and
a partial quantity from a substituted item.

Note Reference(s)
382638.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6528915
-1
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Circular sourcing surplus days


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_CIRC_SRC_DAYS
This profile is no longer used.

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Class Hierarchy


Profile Code
Profile Option Name
Description

MSC
MSC_CLASS_HIERARCHY
This profile determines the type of hierarchy that will be used. This profile
has two values:
+ Demand Class: single level. (1)
+ Customer Class: three levels; customer class, customer, and site (2)

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Closest Quantity Pegging


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_CLOSEST_QTY_PEGGING
This profile was removed in 11.5.9

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Collaborative Planning Default Calendar


Profile Code
Profile Option Name
Description

MSC
MSC_X_DEFAULT_CALENDAR
When multiple customer sites display together, Oracle Collaborative Planning
uses the default system calendar (profile option MSC: Collaborative Planning
Default Calendar).

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4446794
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Collect CMRO Work Order Demand for PS


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_CMRO_WO_DEMAND_PS
Collect CMRO Work Order demands into msc_demands for PS
Set profile to Yes if using the CMRO integration
1157809.1

-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Collect Item, Material and Resource Costs


Profile Code
Profile Option Name
Description

MSC
MSC_COLLECT_COSTS_FOR_ITEM
This profile option indicates whether data collection should include cost
information.
Specifying No may improve data collections performance.
Only required if using Cost Based Optmization type plan where Optimization
flag is checked in the plan options.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
Yes
No
Yes
Yes
Yes
No
No
No
No
Yes
Yes
No
Yes
No
No
No

MSC: Collect PS SNO Data


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_COLLECT_PS_SNO_DATA

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Collection Time Window for Install Base


under Contracts history
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_COLL_TIME_WINDOW_IBUC_HISTORY
Profile for Collection Time Window for Install Base under Contracts history
This profile option specifies the time window for which IB under Contract
history is to be collected.
1225993.1

-1
No
No
No
No
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSC: Collection Window for Trading Partner


Changes (Days)
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_COLLECTION_WINDOW_FOR_TP_CHANGES
Used by Oracle Advanced Supply Chain Planning collections. Specifies the
number of days backwards that changes in customer names, customer sites,
vendors, and vendor sites are collected.
If null, then all changes are collected. Used when collections for the trading
partners entity is run in complete mode.
405295

-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Collections Snapshot Threshold


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SNAPSHOT_THRESHOLD
In Refresh Snapshots request, we checks the number of rows in table and
number of rows in the MLOG
If ratio exceeds the threshold, then we will launch Complete Refresh of the
SnapshotWe do not recommend setting this profile unless directed by DEV
We will perform a complete refresh when a large number of rows exist in the
MLOG, since this would be faster than referencing the MLOG table for a fast
refresh
This profile would usually be triggered when a large data load was performed
to load data into setup tables.
Valid values: Integer 0 - 100
NULL is default - seen as 40
179522.1

-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Compute Project Exception


Profile Code
Profile Option Name
Description

MSC
MSC_PROJECT_TASK_EXCEPTION
This profile option determines whether to generate project specific
exceptions when running a project based plan. Valid values are:

Yes: Enable the generation of project specific exceptions.


No: Disable the generation of project specific exceptions.

Default Value - Yes


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Configuration
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_X_CONFIGURATION
Ensure that the value of the profile option MSC: Configuration is set to APS &
CP. This enables collaboration between Oracle Advanced Supply Chain
Planning and Oracle Collaborative Planning used to enable ASCP - CP
interaction

Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Consolidate Interplant Demands


Profile Code
Profile Option Name
Description

MSC
MSC_CONSOL_INTERPLANT_DEM
This profile option is not documented in the User Guide. (see Note 555016.1
)
Consolidates inter-plant demand into a single inter-plant supply, thus
reducing the number of inter-plant orders. Valid values are:

By End Pegged Demand - Retain current behavior of


creating a demand for each end pegged demand.
Interorganization Demand lines are shown for each
individual demand

By Demand Schedule Supply -On a given day aggregate the


dependent demands from one supply
Interorganization Demand are aggregated into a single
demand.

Default Value - By End Pegged Demand


Example:
Plan 1 shows in planner workbench - Planned order demand 03-DEC-2012
qty = 96
-- if you drill into the pegging for this demand you will see many smaller
demand making up this single qty of 96
Plan 2 has Plan 1 as demand Schedule and has Inter Plant box is checked
In Plan 2 we see many lines of Interorganization Demand for 03-DEC that
add up to 96 (profile is using default End Pegged Demand)
If we change the profile to By Demand Schedule Supply - then we only see
the single Interorganization Demand line for 96
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7457980
-1
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: Consume Forecast Inside Demand Time


Fence
Profile Code
Profile Option Name
Description

MSC
MSC_CONSUME_FORECAST_DTF
Valid values are:

No - demand time fence control is implemented prior to


forecast consumption. Forecast entries in the demand time
fence are dropped as demand statements and not used for
consumption.
Yes - forecast consumption occurs prior to enforcing demand
time fence control. The forecast entries within the demand
time fence are used for consumption but not as demand.
After consumption, demand quantity for all the forecast
entries within the demand time fence is zero.

If you are using forecast spreading:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

565926.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

For a periodic forecast entry that falls in weekly planning


buckets within the demand time fence, the forecast
spreading process spreads the entries into daily entries.
If the daily entry is within the demand time fence, the process
ignores the value that you set and uses the value Yes in
processing.
If the daily entry is outside the demand time fence, the
process ignores this profile option and consumes against the
entry.

MSC: Consume forecast with no demand class


Profile Code
Profile Option Name
Description

MSC
MSC_CONSUME_NULL_DC
This profile option instructs the forecast consumption process in about the
order it should use to consume forecast entries when some of them have a
demand class and others do not have a demand class. Valid values are:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

Within Each Bucket - The forecast consumption process


starts by consuming forecast entries for the day on the sales
order; it consumes entries with matching demand class first,
then entries with no demand class. Then, it consumes
forecast entries within the backward and forward
consumption days; for each day, it uses matching demand
class first, then no demand class.
Within Each Bucket - After Consuming Demand Class
Specific Forecast: The forecast consumption process starts
by consuming forecast entries for the day on the sales order
with matching demand class only. Then, it consumes
forecast entries within the backward and forward
consumption days with matching demand class only. If there
is a remaining sales order quantity, it repeats the process
against forecast entries with no demand class, first on the
day on the sales order, then within the backward and forward
consumption days.

MSC: Consume forecasts using Internal Sales


Orders
Profile Code
Profile Option Name
Description

MSC
MSC_CONSUME_INT_SALES_ORDERS
Only used when INV: Inventory Capable to Promise - ATP/CTP based on
Planning Data
Valid values are:
* Yes - Perform ATP check on Internal Sales Orders (1 - default)
* No - Do Not perform ATP check on Internal Sales Orders (2)
* Only If Destination Organization on ISO is not part of Plan -(3)
From Note 558908.1
1. The profile was added in bug 5440895. This profile works in tandem with
the profile option MSC: Perform ATP Check for Internal Sales Orders. see
the table in the note to understand the profile values and how they are used.
2. If you have a centralized instance, set the profile value as required. If
you are a decentralized/distributed installation with both APS Destination and
EBS Source, set this on the APS destination and EBS source.
Notes:

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization

1. Bug 6434413 Some Orgs do use an Internal sales order and need
consumptions, but other orgs do NOT want consumption, so fixes had to be
made so that profile value can be set for different orgs at different settings
(by Responsibility) and have the value honored. Set in EBS source
2. For Bug 6434413 - fix is released on ATP RUP #22 and above (See
Note 252108.1 for list of patches. Patch 6434413 should not be applied
instead of a rollup patch.
3. In R12.0.4, this fix is included ATP CU4, and also in base release of
12.0.6
558908.1

6434413
-1
-1
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

Advanced Planning Command Center


Manufacturing Operations Center
Global Order Promising

No
No
Yes

MSC: Cost Type


Profile Code
Profile Option Name
Description

MSC
MSC_COST_TYPE
Use this profile option on the source instance (execution system) to specify
the cost type that collections should use when collecting the item costs. You
should perform a cost rollup for the specified cost type before collecting data.
If this profile option is null, collections
uses the:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

Frozen cost type for standard costed organizations


Average cost type specified for average costed organizations

MSC: Cost of Using a BOM/ Routing Flexfield


Attribute
Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_ALT_BOM_COST
Not used by Oracle Advanced Planning.

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Create Resource Requirements for all


Operations
Profile Code
Profile Option Name
Description

MSC
MSC_CREATE_DUMMY_RES_REQS
If an operation has no resources with Schedule = Yes, when this profile
option is set to:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

Yes - The planning engine creates a dummy resource


requirement for the operation
No - The planning engine does not create a dummy resource
requirement for the operation; the operation does not have
any resource requirements

MSC: Currency Conversion Type


Profile Code
Profile Option Name
Description

MSC
MSC_CURRENCY_CONVERSION_TYPE
Use this profile option on the destination instance to specify currency
conversion type. If you change the value, the next time you run collections,
the collections process purges the data with the previous currency
conversion type and replaces it with data with the new currency conversion
type.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Custom allocation


Profile Code
Profile Option Name
Description

MSC
MSC_USE_CUSTOM_ALLOCATION
To improve performance for customer allocated ATP used only in following
cases.
Only end item allocation. no component allocation. that is, the item cannot
be a component of other bom.
No ctp (so we don't deal with planned order demand allocation and CTP
suggested supply/demand allocation).

Note Reference(s)
555016.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6456520
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: DPP Allow Quantity Reduction Only When


Supply is Excess on Internal Requisition,
Requisition and PO
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_DRP_FIRM_REQS_QTY
Per Bug 9546158The profile option "MSC: DPP Allow Quantity Reduction Only

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: DPP Debug Level


Profile Code
Profile Option Name
Description

MSC
MSC_DRP_DEBUG_LEVEL
Debug Level for Distribution Planning
Was renamed from MSC: Distribution Planning Debug Level" to "MSC: DPP
Debug Level" in 12.0 Engine CU10 patch and in EBS 12.1.3
Should be set only with guidance of Support or Development.

0 - No Debug 1 - Informational Message 2 - Logic and Data Debug 3 - Logic


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9262606
-1
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: DPP Demand Priority Details viewing buckets


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_DRP_DMD_PRIORITY_BK
No documentation found on this profile.

Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: DPP Discrete Job Cutoff Window (Days)


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_DRP_DISCRETE_JOB_CUTOFF_WINDOW
Use this profile option to control the number of days from plan start date that
discrete jobs are considered. Valid values are:

Null: -All discrete jobs are considered by the distribution plan.

0 - No discrete jobs are considered by the distribution plan.

Integer >=0 - All discrete jobs with completion dates from


plan launch date + {integer value} are considered by the
distribution plan. New planned orders for discrete jobs can
be created both inside and outside the job cutoff window.

Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: DPP Related Exception Additional Offset Days


Profile Code
Profile Option Name
Description

MSC
MSC_DRP_REL_EXP_OFFSET_DAYS

The profile is used to specify the number of days to


extend the lead time window calculation for related
exceptions in the source organization. Therefore,
the calculation is "Start date - max LT - profile
option days"
This profile option is added to account for the fact
that UI does not consider shipping / receiving /
manufacturing / intransit calendars in its window
calculation.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: DRP Multitasking Group ID's per Process


Profile Code
Profile Option Name
Description

MSC
MSC_DRP_GROUPIDS_PER_PROCESS
Use this profile option to specify how many Group IDs an unconstrained
demand and supply netting and allocation child process should process. In
this phase, a child process loads data based on internal group IDs and will
load all the org-items belonging to those group ID's. This option specifies the
length of the list of group ID's.
This profile option does not control the Load Consolidation processes.
This profile option does not apply with operating system Microsoft Windows.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8523019
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: DRP Multitasking Max Concurrent Processes


Profile Code
Profile Option Name
Description

MSC
MSC_DRP_MAX_CONCURRENT_PROCESSES
Use this profile option to specify the maximum number of DPP processes
that are allowed to run in parallel. For example, if your machine has 4
CPU's,you might choose to run a maximum of one concurrent process on
each CPU; in this case, set the value to 4.
This profile option does not apply with operating system Microsoft Windows.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8523019
-1
-1
-1
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: Daily Allocation to Maintain Safety Stock


Level
Profile Code
Profile Option Name
Description

MSC
MSC_DAILY_ALLOCATION_SS
Indicates whether or not the safety stock level that you specify needs to be
maintained.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Day UOM


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC:DAY_UOM_CODE
Supports the unit of measure conversion required for Oracle Advanced
Supply Chain Planning resource batching calculations. Batching Window is
considered in days, but users can specify the batching window in a unit of
measure other than days. The profile option establishes a standard for the
Day unit of measure.

Users must specify a unit of measure that represents the


value Day using this profile option.

Users must also set up a unit of measure conversion


between the unit of measure used for resources and the Day
unit of measure specified here.

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Days of Resource Availability before sysdate


Profile Code
Profile Option Name
Description

MSC
MSC_RES_AVAIL_BEFORE_SYSDAT
Calculate Resource Availability for X days before sysdate. If a high number,
then resource availability calculation during ODS Load could take a longer
time. This can be used to collect resource availability in the past. Then this
can be used in Planning to calculate completion time of operations in
progress. You should collect resource availability in the past that will cover
the earliest operation start date currently running in the system. Valid values
are:

Integer / NULL = 1

This profile is not supported in 12.1.1 and above


Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5044955
5043399
-1
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Debug Level


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_DEBUG_LEVEL

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Debug Module


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_DEBUG_MODULE

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Default Category Set for Rapid Planning


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_RP_DEFAULT_CAT_SET
This is category set that is used in the UI when no more specific set is
available. It is used in particular for plan input. For plans, category set is a
parameters in the plan options
1276896.1

-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Default Project for Supplies Pegged to Excess


Profile Code
Profile Option Name
Description

MSC
MSC_DEF_PROJ_SUP_EXCESS
This is a profile to support pegging of excess supplies to a default project.
This was however modified to be supported only for buy items and items with
no components.Refer bug# 5217328 mentioned below'
Default Value: blank.
Valid Values: Restricted to those setup in Oracle Projects (see Oracle
Projects User Guide).

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5217328
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Default Time Stamp for Make Planned Order


Release
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_PO_DEFAULT_TIME_STAMP
The profile allows you to set the timestamp to 23:59:59 for discrete jobs in
case of an unconstrained plan.
1448762.1

-1
No
No
No
Yes
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Default Workbench Height


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_DEFAULT_WORKBENCH_HEIGHT
Specify the default workbench height. Can be defined at the site level.

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Default Workbench Width


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_DEFAULT_WORKBENCH_WIDTH
Specify the default workbench width. Can be defined at the site level.

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Degree of Parallelism for Index Creation


Profile Code
Profile Option Name
Description

MSC
MSC_INDEX_PARALLEL_THREADS

Controls the use of parallel workers in data


collections. Specifies how many parallel workers to
use when creating indexes.
If the profile is set to null, then the DOP (degree of
parallelism) is being calculated by the database
based on the number of cpu and the initialization
parameter PARALLEL_THREADS_PER_CPU.
If you set the profile to 1 then it will not use any
parallel slaves, as such performance will be slower
in collections

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4460213
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Demand Priority Flexfield Attribute


Profile Code
Profile Option Name
Description

MSC
MRP_DMD_PRIORITY_FLEX_NUM
Stores the value of the attribute column that controls the demand priority.
See 'Flexfield Attributes, page A-1 for more information. Set in EBS Source
in a Distrubuted installation.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Oracle Advanced Supply Chain Planning Implementation and User's Guide
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Demand Satisfied Percent Threshold for


Pegging
Profile Code
Profile Option Name
Description

MSC
MSC_DEMAND_SA_PER_THRESHHOLD
Set this profile option to instruct the planning engine to stop pegging supplies
to a demand which is over satisfaction percentage. Oracle recommends
setting the value greater than 99.9.
Even if you set this profile option below 100.0, the planning engine still
satisfies 100% of the demand.

Note Reference(s)
739561.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Display Order Rescheduling Supplies


Profile Code
Profile Option Name
Description

MSC
MSC_DISP_RESCH_SUPPLIES
Yes: Planner Workbench displays Order Rescheduling Supply and Order
Rescheduling Demand inserted by available to promise when it unschedules
a sales order for a configured item
Values are:
+ Yes: Displays the rescheduling supplies details in the Planner Workbench.
+ No: he rescheduling supplies details are hidden from the Planner
Workbench
This profile is provided for debugging and analysis only. Therefore, you
should set this profile to No in a production environment.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Global Order Promising Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Display Supplier Item in Collaborative


Planning
Profile Code
Profile Option Name
Description

MSC
MSC_DIS_SUP_ITEM_CP_HZ
This setting is to display the Supplier Item value in the Horizontal Plan in
Collaborative Planning. Valid values are:

Yes - display the Supplier Item value in the Horizontal Plan in


Collaborative Planning

No - do not display the Supplier Item value in the Horizontal


Plan in Collaborative Planning

After the profile change, allow 60-90 seconds for the profile change to take
place.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3969852
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Display Warning Message When


Rescheduling Recommendation Not Suggested by
the Plan
Profile Code
Profile Option Name
Description

MSC
MSC_REL_SHOW_WARN
This profile option specifies whether or not the Planner Workbench should
display a warning message when you release rescheduled orders that the
planning engine has not recommended. Valid values are:

Yes - Use this value if you want the Planner Workbench to


prompt you for confirmation when you release rescheduled
orders that the planning engine does not recommend.
No - Use this value if you do not want the Planner
Workbench to display the message prompting to prompt you
for confirmation when you release the rescheduled orders
that the planning engine does not recommend.

Set on APS Destination in a distributed environment


Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3016969
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Distribution Planning Ship Date


Profile Code
Profile Option Name
Description

MSC
MSC_DIST_PLAN_SHIP_DATE
Use this profile option to schedule a trip for departure based on the earliest
and latest possible ship dates of the trip. Valid values are:

Ship full trips early or ship latest(Target) - Utilized trips ship


on the earliest possible ship date or in time to prevent
inventory levels from dropping below target.

Ship full trips early or ship latest (SS) -Utilized trips ship on
the earliest possible ship date or in time to prevent inventory
levels from dropping below safety stock.

Latest possible ship date (Target) -Trips ship just in time to


prevent inventory levels from dropping below target.

Latest possible ship date (SS) - : Trips ship just in time to


prevent inventory levels from dropping below safety stock

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
-1
-1
-1
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: Distribution Planning Use Firm Supplies and


Minimize Excess Supplies
Profile Code
Profile Option Name
Description

MSC
MSC_DRP_USE_FIRM_SUPPLIES
DPP uses for netting the firm supplies from entire horizon (not only within
current allocation bucket)
First released in 12.0.4/12.0.6 ASCP Engine/UI CU8 patch.
Forward ported in 12.1.3.1
Description from DRP FAQ Note 761820.1:

Why do sometimes I don't see


my future firm supplies netted
with current demand and I see a
new planned order created by
DRP?
In DRP, we do netting of supply
and demand within an allocation
bucket.
So if allocation bucket is say
weekly then supplies of 2nd week
onwards won't be used to meet the
demand of 1st week.
This is current functionality.
To make this functionality more
flexible, in R12 CU8 we have
provided one profile where based
on the business requirement, user
can select whether to net supplies
of next buckets to meet demands
of current buckets. The profile
name is "MSC: Distribution
Planning Use Firm Supplies and
Minimize Excess Supplies".
If profile value is Yes the
Unconstrained Netting phase will
use first all firm supplies within

entire horizon. Only if there is no


more firm supply than new
unconstrained supply will get
generated and dependent demand
gets pushed down to sourcing.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9176212
-1
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: E1 APS FC URL


Profile Code
Profile Option Name
Description

MSC
MSC_E1APS_FCURL
URL for the webservice used to Launch ODI scenarios from collections
program
Format: String
Where Used: JDE-VCP Collections

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: E1 APS ODI URL


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_E1APS_ODIURL
URL for the webservice used to Launch ODI scenarios from collections
program
Format: String
Where Used: JDE-VCP Collections

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: E1 Concatenation Character


Profile Code
Profile Option Name
Description

MSC
MSC_E1_CONCAT_CHAR
Delimiter character in the generated flat files from JDE
Default: +
Format: Character
Where Used: JDE-VCP Collections.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: E1APS_BATCH_SIZE
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_E1APS_BATCH_SIZE
Transaction batch size used in Legacy Collections
Default: 1000
Format: Integer
Where Used: JDE-VCP Collections

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: E1APS_DEM_END_DATE_IN_MONTHS
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_E1APS_DEM_END_DATE_IN_MONTHS
End date offset in months from the current date used for Demantra Price List
collections
Format: Integer
Where Used: JDE-VCP Collections

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: E1APS_DEM_START_DATE_IN_MONTHS
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_E1APS_DEM_START_DATE_IN_MONTHS
Start date offset in months from the current date used for Demantra Price List
collections
Format: Integer
Where Used: JDE-VCP Collections

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: E1APS_DEM_WF_TIME_OUT
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_E1APS_DEM_WF_TIME_OUT
Timeout value for Demantra Workflow in seconds
Format: Integer
Where Used: JDE-VCP Collections

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: E1APS_NO_OF_WORKERS
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_E1APS_NO_OF_WORKERS
Number of workers for Legacy Collections concurrent program
Default: 3
Format: Integer
Where Used: JDE-VCP Collections

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: E1APS_TIME_OUT
Profile Code
Profile Option Name
Description

MSC
MSC_E1APS_TIME_OUT
Timeout value in minutes for Legacy collections preprocessor and ODS Load
programs
Default: 180
Format: Integer
Where Used: JDE-VCP Collections

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: E1APS_WS_TIME_OUT
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_E1APS_WS_TIME_OUT
Timeout value in seconds for ODI webservice
Format: Integer
Where Used: JDE-VCP Collections

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: E1_DBLINK
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_E1_DBLINK
Database link to ODI Work repository from the apps schema
Format: String
Where Used: JDE-VCP Collections

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: EBS source instance for OTM


Profile Code
Profile Option Name
Description

MSC
MSC_EBS_INSTANCE_FOR_OTM
A string such as TST. Default to same instance as APS self instance. Now
APS-OTM integration only support single EBS source instance.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: ENFORCE CRITERIA REQUIREMENT BEFORE


EXECUTING QUERY
Profile Code
Profile Option Name
Description

MSC
MSC_PQUERY_EXEC_WITH_CRITERIA
Use this profile option to specify if a query requestor needs to specify criteria
before executing a query. Valid values are:

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes - This ensures that the query performs more efficiently.


No

867822.1

-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Enable 64 bit snapshot


Profile Code
Profile Option Name
Description

MSC
MSC_ENABLE_64BIT_SNAPSHOT
When using 64 bit planning, you can also run the Memory Base Snapshot in
64 bit mode.
This does not make the plan run faster. This is for extremely large data
models the exceed the requirements of 32 bit snapshot. Most customers
using 64 bit planning will not need 64 bit snapshot. Valid vaules are:

Enabled - 1

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Disabled - 0

Default Value - Disabled


254810.1

-1
-1
Yes
No
No
Yes
Yes
No
No
No
Yes
No
Yes
Yes
Yes
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Enable ATP Summary Mode


Profile Code
Profile Option Name
Description

MSC
MSC_ENABLE_ATP_SUMMARY
This profile determines whether we launch program - Load ATP Summary
Based on Collected Data - MSCCLCNC
This will summarize data for sales orders and supply / demand data and can
improve ATP scheduling performance.
This is a site level profile. Valid values are:

Yes - Enable ATP Summary Mode

No - Disable ATP Summary Mode.

You may only set this profile to Yes when Oracle Global Order Promising is
on the same instance as other ERP application (i.e. You have a centralized
instance setup)

Note Reference(s)

ATP will use the detailed information in several cases even if you have this
set to Yes
ATP in the Order Backlog Workbench is based on the detail supply demand
tables, regardless of the profile setting for MSC:
Enable ATP Summary Mode.
ATP for ATO models is always based on detailed information.
457840.1
563617.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Oracle Global Order Promising Implementation and User's Guide
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Enable ATP Workflow


Profile Code
Profile Option Name
Description

MSC
MSC_ALLOCATED_ATP_WORKFLOW
The profile MSC: Enable ATP Workflow is a site level profile option and it
cannot be set at the responsibility level.
Controls the notification sent to planner if we cannot meet the request, or
stealing is involved when allocated ATP is used or when override happens
under ATP based on planning output.
If end item substitution is used, then we send notification to customer
contacts and sales representative.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Also used for ATP Override functionality.


419271.1

-1
Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Enable ATP for Phantom Components


Profile Code
Profile Option Name
Description

MSC
MSC_ENABLE_PHANT_COMP
Enable ATP for Phantom Components
Yes / No
When set to No, it skips the Phantom components and ignores Phantom lead
times and moves directly to the next level in the BOM.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

11797513
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Enable Advanced Constraints


Profile Code
Profile Option Name
Description

MSC
MSC_ENABLE_NEW_CONSTRAINTS
Use this profile option to control the values that display for plan option
Constraints Mode (on the Constraints tab). Valid values are:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

Yes: All values for plan option Constraints Mode display


No: All values for plan option Constraints Mode display
except Constrained (Without Detailed Scheduling)

MSC: Enable Allocated ATP


Profile Code
Profile Option Name
Description

MSC
MSC_ALLOCATED_ATP
Enable Allocated ATP is only available for ATP based on Planning Output
Update at the Site level only.
This should be set to NO for ATP based on Collected Data
-- there have been issues in the past where this profile was Yes and
ATP based on Collected Data has issues

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes / No (default)
212788.1
218010.1
339599.1
154293.1
333936.1
251920.1

-1
-1
-1
-1
-1
-1
Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Enable DRP Multitasking


Profile Code
Profile Option Name
Description

MSC
MSC_DRP_MULTITASKING
Use this profile option to specify whether the planning engine should use
high volume distribution planning. You can set at the user and site levels.
Valid values are:

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8523019
-1
-1
-1
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

Yes - All DPP plans run by this user or at this site are run in
high volume mode. This value does not apply with operating
system Microsoft Windows.
No - DPP plans run by this user or at this site are not run in
high volume mode

MSC: Enable Diagnostic ATP


Profile Code
Profile Option Name
Description

MSC
MSC_DIAGNOSTIC_ATP
Use this profile to enable diagnostics within the ATP Inquiry form.

Note Reference(s)

Open the ATP inquiry screen and then go to /Tools and check on Enable
Diagnostic ATP
Then when you perform ATP inquiry for the item, additional information on
the constraints causing lateness will be available.
Example on the GOP Users Guide provides more information.
303067.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6001023
-1
-1
Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Enable Enhanced Sourcing


Profile Code
Profile Option Name
Description

MSC
MSC_ENHANCE_SOURCING
Enables enhanced sourcing logic that considers historical allocations and
allows the splitting of planned orders to achieve target sourcing percentages.

Rank 2 buy sources are considered if supplier capacity is exhausted for rank
1 sources. This profile option duplicates the functionality of the decision rule
Use Alternate Sources parameter for buy items but not for transfers from
other organizations. When the decision rules are enabled, the planning
engine does not consider this profile option.
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Enable Group Based Netting


Profile Code
Profile Option Name
Description

MSC
MSC_ENABLE_GROUP_BASED_NETTING
Use this profile option to control whether the planning engine uses group
based netting features. Valid values are:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes - provides the most recent netting logic

Oracle recommends that you set the value to Yes and use the latest netting
features. This profile option is for backward compatibility. In R12 this profile
has to be set to Yes.
421097.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Enable Java Debug


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_JAVA_DEBUG
When setting this profile to Yes, debug messages are written to the java
console.
396037.1

-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
Yes
Yes
No

MSC: Enable Large Plan Copy


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_ENBL_COPY_LARGE_PLAN
User Defined profile for key code required by DEV for certain file functions in
mslflt.ppc

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Enable Model and End Item dimensions in


APCC
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_APCC_END_ITEM_ENABLED
Enabled flag, indicating whether APCC will archive pegging information at
End Item granularity.

No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: Enable Priority Pegging


Profile Code
Profile Option Name
Description

MSC
MSC_ENABLE_PRIORITY_PEGGING
This is not a visible profile.
This is actually a parameter on the options form for the plan options.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Enable Release of Defective Planned


Transfers
Profile Code
Profile Option Name
Description

MSC
MSC_ENABLE_REL_DFCT_PLAN_TRNSFRS
To Control Release of Defective Planned Transfers
May be customer specific and change in 12.2 - Per bug 9187165

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9187165
-1
No
No
No
No
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSC: Enforce Hard Links


Profile Code
Profile Option Name
Description

MSC
MSO_ENFORCE_HARD_LINKS
This profile option specifies whether time offsets are hard constraints or soft
constraints. Valid values are:

Yes - the planning engine can violate resource and material


capacities to satisfy minimum and maximum time offsets. If
capacity is exceeded, exception messages start the cause
as "Hard Link Constraint".

No - the planning engine cannot violate resource and


material capacities to satisfy the minimum and maximum
time offsets. In this case, the planning engine can violate
hard links and generate a "Hard Link Violation" exception
message.

Default Value - Yes


Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7453287
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Oracle Advanced Supply Chain Planning Implementation and User's Guide
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Enhanced Project Netting


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_ENHANCED_PROJECT_NETTING
The new schedule date on on-hand and expired-lots is calculated incorrectly,
when flushing to MSLD_SUPPLIES.dat. The new shcedule date now is
calculated using date from call to get_curr_date() instead of arguments>curr_date as done previously

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Excess and Safety Stock by Demand Class


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_EXCESS_SUPPLY_BY_DC
Controls the allocation of supply or demand that pegs to excess or safety
stock in the case of allocated ATP using the demand-priority based method.
Values are:
+ Yes:
If such supply or demand has a demand class, and if the demand class
exists on the allocation rule, then allocate the supply or demand to the
demand class. If the supply or demand does not have a demand class or if
the demand class does not exist on the allocation rule, then allocate the
supply or demand to OTHER.
+ No:
Allocate such supply or demand to OTHER.
250289.1

-1
Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Fast Refresh of Region Site Map


Profile Code
Profile Option Name
Description

MSC
MSC_FAST_REGION_SITE_MAP
This effects Region to site mapping of suppliers which is launched during the
Refresh Collections snapshots.
No - default - standard functionality
Yes - will launch and cursor to specifically select only newly changed records
for region to site mapping of supplies.
Introduced in VCP 12.1.3.4

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

10417975
-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: File Flush Limit


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_FILE_FLUSH_LIMIT
Use this profile option to control Planner concurrent process write to
database, if the number of records exceed this value, the process uses
SQL*Loader or array insert.
725858.1

-1
Yes
No
No
Yes
No
No
No
No
Yes
Yes
Yes
Yes
No
No
No
No
No
Yes
Yes
No
Yes
No
No
No

MSC: Firm Internal Requisition Time Fence


Profile Code
Profile Option Name
Description

MSC
MSC_FIRM_PURCH_REQ_TF
This profile option creates a natural time fence for an item if a firm internal
requisition exists. The natural time fence is the date of the latest firm internal
requisition. Valid values are:

Yes: Use this to create a natural time fence for a firm internal
requisition.
No: Use this if you do not want to create a natural time fence
for a firm internal requisition.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: Firm Intransit and PO in Receiving Supplies


Profile Code
Profile Option Name
Description

MSC
MSC_FIRM_INTRANSIT_PO_IN_RECEIVING
This profile option applies to unconstrained plans only and instructs the
planning engine whether it should consider intransit and purchase order in
receiving supplies as firm or it should issue reschedule recommendations for
them. Valid values are:

Yes - the planning engine considers intransit and purchase


order in receiving supplies as firm.

No - the planning engine generates reschedule


recommendations for these types of supplies. Use this
setting if you expedite shipments that are en route from a
supplier to a receiving organization or if you want to expedite
the movement of materials in receiving to the shop floor. For
example, you might offload a package from a ship at a port
and then fly the package to the receiving organization.

These recommendations are informational only and cannot be released from


the Planner Workbench.
This is a user level profile option.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4593891
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Fixed Date for Install Base under Contracts


History (DD-MON-YYYY)
Profile Code
Profile Option Name
Description

MSC
MSC_FIXED_DATE_IBUC_HISTORY
Profile for defining the date for the Fixed date instances
This is only applicable for testing instances where fixed date is being used in
the system for testing stability.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9979825
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Flush All Items for Simulation


Profile Code
Profile Option Name
Description

MSC
MSC_FLUSH_ALL_ITEMS_ONLINE
Profile option used to identify items to calculate safety stock as part of the
batch replan. Valid values are:

Yes - flush the item data during simulation/batch replan to


calculate the safety stocks and not miss any data.

No - only the items changed for simulation or batch replan


are taken into account and recalculated

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5920518
9361980
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Forecast Priority Flexfield Attribute


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_FCST_PRIORITY_FLEX_NUM
Stores the value of the attribute column that will control the forecast priority.
See 'Flexfield Attributes, page A-1 for more information.
794086.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Forecast Spreading Calendar


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_FCST_SPREADING_CALENDAR
Obsolete

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Forecast Spreading Calendar


Profile Code
Profile Option Name
Description

MSC
MSC_FORECAST_SPREAD_CAL

MSC: Forecast Spreading Calendar will use the


calendar for spreading the forecast based on
either:
Org Manufacturing Calendar
Org Shipping Calendar
It should be noted that the bucketing of the forecast
is always based on the shipping calendar.
This is the design, since you cannot ship when the
org is closed for shipping, then forecast will be
bucketed so that it will be ready to ship.
For instance, using the example below - if you
enter a sales order with day 6 as requested ship
date, and we cannot ship on Day 6, then we will
back up the ship date to Day 5
So the sales order demand would fall on Day 5, so
we plan the forecast in the same manner, so you
can produce when the demand from sales order
will fall on the calendar.
Example:
Mfg calendar 7 days on
shipping calendar 5 on / 2 off
Forecast qty per week = 700
Spread Forecast qty / Forecast Bucketing
Day 1 100
100
Day 2 100
100
Day 3 100
100
Day 4 100
100
Day 5 100
300
Day 6 100
Day 7 100
Note: Introduced in 11.5.10 in Rollup #34

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile

7420122
-1
-1
Yes

12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
Yes
Yes
Yes
Yes
Yes
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
No

MSC: Future Days for Currency Conversion


Profile Code
Profile Option Name
Description

MSC
MSC_FUTURE_DAYS_FOR_CURR_CONV
Use this profile option to instruct the collections process how many future
days of currency conversion rates to collect, starting from today.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Gateway URL to External Application


Profile Code
Profile Option Name
Description

MSC
MSC_GATEWAY_URL_EXTERNAL
This profile is obsolete and needs to be removed from the applications. This
is documented in bug 2937850

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2937850
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Generate Exceptions in CP


Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_WS_OTM_GEN_EXC_CP
Control whether the order later or earlier exceptions will be generated in
Collaborate Planning.
733189.1
761773.1

-1
-1
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Generate Notifications for Transportation


Updates
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_GEN_NOTIFICATION_FOR_OTM
Use this profile option to specify whether the process that passes estimated
arrival time updates from Oracle Transportation Management should create
workflow notifications.
Valid values are:

Yes - Create workflow notifications

No - Do not create workflow notifications

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: HP Maximum Displayed Item Count


Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_HP_ITEM_LIMIT
Controls the number of items that can be viewed in the Horizontal Plan.
734926.1

-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: High Volume Items


Profile Code
Profile Option Name
Description

MSC
MSC_HIGH_VOL_ITEMS
This snapshot profile controls plan weed out logic. Since snapshot on 64-bit
machines could run out of memory if the number of planned items is high.
Valid values:

Yes: Snapshot bypasses the weed out logic and directly


inserts items from operational data store to planning data
store. If item planning type is All Planned Items, the snapshot
inserts all items into the planing data store. If the items have
demand schedules only, snapshot only inserts the items in
demands schedules into the planning data store.

No: The snapshot uses weed out logic.

Note Reference(s)

749602.1
404046.1
387368.1

Bug Reference(s)

7696320
5203445
-1
-1
-1
-1
-1

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: History Days for Currency Conversion


Profile Code
Profile Option Name
Description

MSC
MSC_HISTORY_DAYS_FOR_CURR_CONV
Use this profile option to instruct the collections process how many past days
of currency conversion rates to collect, starting from today.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Horizon for APCC Collected data - Backward


days
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_APCC_COLL_HORIZON_DAYS_BACK
no info

No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: Horizon for APCC Collected data - Forward


days
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_APCC_COLL_HORIZON_DAYS
cant find much of anything on this.

No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: Horizontal Plan Demand Bucketing


Preference
Profile Code
Profile Option Name
Description

MSC
MSC_HP_DMD_BKT_PRF
This profile controls how Oracle Global Order Promising treats demand due
date when calculating availability.
Valid values are:
Plan Recommended Date - Oracle Global Order Promising treats the
demand due as the date recommended by Oracle Advanced Supply Chain
Planning. (Material Available Date of the Sales Order demand in
Supply/Demand view of the ASCP Plan)
Demand Due Date, Oracle Global Order Promising treats the demand due as
the Schedule Ship Date. (Suggested Due Date in Supply/Demand view of
ASCP plan.)
So using Demand Due Date will have ATP Hiorizontal Plan and ASCP
Horizontal Plan show demand in the same buckets.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Global Order Promising Implementation and User's Guide


Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Horizontal Plan Extension Program


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_HP_EXTENSION_PROGRAM
Use this profile option when you are using a custom row in the Planner
Workbench Horizontal Plan. Specify the name of the PL/SQL program unit
with no parameters that specifies that information to display in the custom
row.
743420.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Hour UOM


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC:HOUR_UOM_CODE
Specifies unit of measure. Can be defined at the site level.

Yes
No
No
Yes
Yes
No
No
No
No
No
Yes
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSC: Hybrid Allocated ATP


Profile Code
Profile Option Name
Description

MSC
MSC_HYBRID_ALLOC_ATP

MSC: Hybrid Allocated ATP


This is the profile option to support Hybrid
Allocated ATP
The profile provides ability for the system to check
if any allocation rule exists for items.
"MSC: Enable Allocated ATP" set to 'Yes',
Allocated ATP will be performed to ALL
items irrespective of checking if any allocation rule
exists for items.
Set the new profile "MSC: Hybrid Allocated ATP" to
'Yes' and "MSC: Enable Allocated ATP" set to
'Yes', Allocated ATP will
be performed ONLY for items which are having
allocation rules.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: INTER PLANT DEM PRIORITY


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_INTERPLANT_DEM_PRI
Hidden. Used for coding.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7457980
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: IO UI Performance tuning


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_IO_UI_PERF_TUNE
Not available in user guide and no information on this profile.

-1
Yes
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No

MSC: IO UI Period Set Name


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_IO_UI_PERSETNAME
Introduced in Patch 9724753 for 12.1.1 CU4
Included in VCP 12.1.3.1 and above.
The period_set_name used in financial calendar is
different than the one being supported.
Currently only 'Accounting' is supported and defaulted by
the code.
This profile will allow setting of a different calendar, otherwise Accounting
calendar will be defaulted.
1133108.1

9724753
9892129
-1
-1
-1
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No

MSC: Ignore ATP Check for Configured Item from


Sales Order in ODS-ATP
Profile Code
Profile Option Name
Description

MSC
MSC_IGNORE_ATP_CHECK
Valid values are:
Yes - and using "ATP Based on collected Data" then when there is a
configuration existing for the Sales order, we treat the model as non atpable.
No - no alterations on existing demand will be done
Default Value - No
Only available in 11.5.10 at this time (Jun 2011)

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6355057
6475340
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Ignore CMRO and EAM Workorders in ASCP


Profile Code
Profile Option Name
Description

MSC
MSC_ASCP_IGNORE_CMRO_EAM_WO
This profile exists in 12.1.3.6 and later
if profile: "MSC: Ignore CMRO and EAM Workorders in ASCP" is set as Yes,

- If profile is set to Yes, depending on net_wip


setting in the plan option Continue with old
behavior
- If profile is set to No and net_wip is No - Only
Eam/cmro orders are dealt with.
- If profile is set to No and net_wip to Yes, code
deals with all except eam/cmro orders. New code
deals with eam/cmro orders alone.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

12686233
-1
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Ignore PTF during CTP


Profile Code
Profile Option Name
Description

MSC
MSC_CTP_IGNORE_PTF
Valid values are:
* Yes - set the Planning Time Fence to sysdate. So Planning Time Fence
is not considered while doing ATP.
* No
Default Value - No
Introduced to help customers who are running UNconstrained plan and using
ATP based on Planning output.
For GOP, for make order, the start date will respect Planning Time Fence .
For transfer order, the ship date will respect Planning Time Fence. For buy
order, the dock date will respect Planning Time Fence.
This it is consistent with the constrained plan, and it is by design.
However, for an unconstrained plan, due date will respect Planning Time
Fence.
So if GOP is done on a unconstrained plan, this could lead to confusion.

Note Reference(s)

Bug Reference(s)

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Only available in 11.5.10 - front port to R12.x has not occurred yet.
464095.1

6113215
6241549
624154
-1
-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Ignore Routings Without Any Date Effective


Operations
Profile Code
Profile Option Name
Description

MSC
MSC_IGNORE_RTG_WITHOUT_DT_EFF_OPER
Ignore Routings Without Any Date Effective Operations
Introduced in bug 9387109
released in ASCP Engine/UI Rollup #41 - 9550751
A new profile MSC: Ignore Routings Without Any Date Effective Operations
is introduced and a code change was made to ignore the operations with
routings with effectivity date in the past.
Bug notes:
Set the Profile "MSC: Ignore Routings Without Any Date
Effective Operations" to 'NO'.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Create an item with primary bom, primary routing, and an


alternate routing.
Alternate routing is with all operations disabled.
-- This will be treated as item with no operations.
1312424.1

9387109
-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSC: Ignore Safety Stock Inside Lead Time


Profile Code
Profile Option Name
Description

MSC
MSC_IGNORE_SS_IN_LEAD_TIME

Note Reference(s)

1264886.1
1323113.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

When the profile is set to yes then make of safety


stock quantity to zero inside time fence.

-1
-1
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Include Firm Planned Orders In Firm


Allocation Window
Profile Code
Profile Option Name
Description

MSC
MSC_INCLUDE_FPO_IN_FAW
For priority pegging, controls the point at which demands peg to firm planned
orders.
Valid values are:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6623090
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

Yes - Firm planned orders are included in the firm allocation


window (along with scheduled receipts). They are eligible for
pegging during the first phase of priority pegging.
No - Firm planned orders are not included in the firm
allocation window (along with scheduled receipts). They are
eligible for pegging during the second phase priority pegging.

MSC: Include Manufacturing Calendar in ATP Sales


Order Ship Date Calculations
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_INCLUDE_MFG_CAL
This profile was obsoleted in 11.5.10. The functionality of MSC: Use
Shipping/Receiving Calendars replaces this in 11.5.10 and above.
For 11.5.9 and lower, this determines whether ATP uses 24x7 calendar
instead of Org Manufacturing calendar for shipping dates (No for 24x7, Yes
for Org Calendar)
555016.1

-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Include Safety Stocks in Priority Based


Pegging
Profile Code
Profile Option Name
Description

MSC
MSC_INCLUDE_SS_IN_PRIORITY
Controls whether to exclude non-transient safety stock levels from the
priority-based pegging logic. Valid values are:

Yes - The planning engine does not give preference to nontransient safety stock levels in priority-based pegging. It pegs
the demands and the safety stock levels, at the same time,
to the supplies.
No - The planning engine gives preference to non-transient
safety stock levels in priority-based pegging. It first pegs
them to non-firm planned orders. Then, it pegs the demands
to the other supplies.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4011546
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Inflate WIP Resource Requirements


Profile Code
Profile Option Name
Description

MSC
MSC_INFLATE_WIP
Determines whether or not the planning engine should inflate the Work in
Process resource requirements based on resource efficiency and utilization
during collections from Oracle Work in Process. Valid values are:

Yes - Planning engine inflates the resource requirements for


the firm, unfirm, and non-standard discrete jobs considering
the resource efficiency and utilization.
No - The planning engine does not consider resource
efficiency and utilization to inflate the resource requirements
for the collected discrete jobs.

Note that this profile option is used in conjunction with shop floor scheduling
products such as Oracle Manufacturing Scheduling. It is assumed that the
discrete jobs are not released from the planning engine. If the jobs are
rescheduled and released by the planning engine, the resource requirements
are deflated. This could result in data inconsistency as the resource
requirements are deflated on release whereas Oracle Manufacturing and
Scheduling might have calculated resource requirements based on the
inflated values. The planning engine always sends the original resource
requirements upon release. If the resource requirements are already inflated
in the source from Oracle Manufacturing Scheduling, set this profile option to
No to avoid double inflation of the resource requirements. Otherwise, set it to
Yes so that the planning engine inflates the resource requirements.
Default Value - No
Set on APS Destination in a distributed environment
Note Reference(s)
373892.1
858515.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization

2490553
-1
-1
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

Advanced Planning Command Center


Manufacturing Operations Center
Global Order Promising

No
No
No

MSC: Inventory Rebalancing Surplus Inventory


Basis
Profile Code
Profile Option Name
Description

MSC
MSC_CIRC_SRC_SURP_INV_BASIS
This profile can be set at the Site, Responsibility, or User. This profile
relates to Distribution Planning. Use this option to specify whether inventory
rebalancing considers target or safety stock inventory levels. Valid values
are:

Target - Surplus inventory is defined as the quantity of


projected available balance greater than target inventory
level. Target inventory demands are considered by inventory
rebalancing.

Safety Stock - Surplus inventory is defined as the quantity of


projected available balance greater than safety stock
inventory level. Target inventory level demands are ignored
by inventory rebalancing.

Note Reference(s)

397199.1

Bug Reference(s)

7366907
7426019
-1
-1
-1
-1

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSC: JInitiator Version


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_JINI_VERSION
No documentation or bugs found for this profile.

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Launch Analyze Plan Partition


Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_LAUNCH_ANALYZE_PART
Launches the concurrent request Analyze Plan Partition.
250161.1
298355.1

-1
-1
-1
Yes
No
No
Yes
Yes
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Launch System Sql Loader


Profile Code
Profile Option Name
Description

MSC
MSC_LAUNCH_SYSTEM_SQLLDR
Valid values are:

Yes - will launch sqlldr by system call.

No - will call fdpldr() function as earlier.

This profile option is specifically used when MRP_DIRECT_LOAD is set to


Yes.
Note Reference(s)
555016.1
307443.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5722157
-1
-1
-1
Yes
No
No
Yes
Yes
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Launch Workflow-Enabled Exception


Message Notifications
Profile Code
Profile Option Name
Description

MSC
MSC_LAUNCH_EXCEPTION_NOTIFICATION
Determines if Oracle Collaborative Planning sends notification messages
when it generates exceptions

Note Reference(s)
564868.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2474996
-1
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Level for Calculating Liability


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_LIABILITY_CALC_LEVEL
This profile is not used.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5481643
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Limit Gantt Chart Orders View Hierarchy


Profile Code
Profile Option Name
Description

MSC
MSC_GANTT_ORDER_HIERARCHY
When you enter the ordersview of the ASCP Ganttchart from the context of
a supply, you should (optionally) see in the left hand pane tree only the
supply and those supplies that end peg to that supply. You should not see
any of the supplies between the context supply and the end pegged demand.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3621869
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: MPS Auto-Firm Planned Orders


Profile Code
Profile Option Name
Description

MSC
MSC_MPS_AUTO_FIRM_PO
This profile option specifies how the planning engine deals with master
production schedule firm planned orders. You can use this profile option to
specify whether or not the planning engine should treat all planned orders in
the master production schedule as firm:
Valid values are:

Yes - When running batch replan using an MPS plan, all


planned orders are treated as firm without regard to planning
time fence

No - When running batch replan, only planned orders inside


the PTF are firm.

If an MPS is a demand schedule for another plan,


this has no impact as planned orders from the MPS
are always treated as firm.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

This profile option applies only to master production schedule plans. You can
set it at the site and user levels.
259322.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Map Server Host


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_MAPSERVER_HOST
Not Used.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4573393
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Map Server Port


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_MAPSERVER_PORT
Not Used.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4573393
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Max display decimals for Currency


Profile Code
Profile Option Name
Description

MSC
MSC_RP_DEC_CURR

Note Reference(s)

1276896.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

This profile is to control the decimal places for


Currency units. The default value for this profile is
2. This profile can be enabled only at the site and
responsibility level. Users will not be able to set
them at user level.

-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Max display decimals for Quantity


Profile Code
Profile Option Name
Description

MSC
MSC_RP_DEC_QTY

Note Reference(s)

1276896.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

This profile is to control the decimal places for


Quantity units (order quantity, exception quantity,
etc.). The default value for this profile is 2. This
profile can be enabled only at the site and
responsibility level. Users will not be able to set
them at user level.

-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Max display decimals for Quantity


(aggregates)
Profile Code
Profile Option Name
Description

MSC
MSC_RP_DEC_QTY_AGG

This profile is to control the decimal places for


aggregate Quantity units. The default value for this
profile is 0. This profile can be enabled only at the
site and responsibility level. Users will not be able
to set them at user level.
Applies to quantities in the Material Plan and all
Hours measures shown in the Resource Plan.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

1276896.1

-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Max display decimals for Ratios/Percentages


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_RP_DEC_RATIO
This profile is to control the decimal places for ratio measures (utilization %,
fill rate %, load ratio, etc.) in the resource plan. The default value for this
profile is 2. This profile can be enabled only at the site and responsibility
level. Users will not be able to set them at user level.
1276896.1

-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Max display decimals for Time


Profile Code
Profile Option Name
Description

MSC
MSC_RP_DEC_TIME

This profile is to control the decimal places for Time


(hours, days, etc.). The default value for this profile
is 2. This profile can be enabled only at the site and
responsibility level. Users will not be able to set
them at user level.
This is useful when the lead time calculation is not
in the integer value in terms of days and Hours.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

1276896.1

-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Max display decimals for Time (aggregates)


Profile Code
Profile Option Name
Description

MSC
MSC_RP_DEC_TIME_AGG

Used to control the decimal places displayed for


time (hours, days, etc.)
Applies to the Hours measures shown in the
Resource Plan

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

10193934
-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Maximum Capacity


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_MAX_CAPACITY
Not Used

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4573393
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Maximum Percentage variation in safety stock


values
Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_SS_MAX_VARIATION
The safety stock is not allowed to deviate by more than this value between
two adjacent time intervals. Null allows any deviation.
759329.1
376451.1
276707.1
559867.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Maximum number of planned orders per


demand
Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC: MAXIMUM NUMBER OF PLANNED ORDERS PER DEMAND
The maximum number of planned orders that the planning engine can create
to satisfy one demand.
399364.1
434809.1

-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Maximum number of planned orders per


demand(1)
Profile Code
Profile Option Name
Description

MSC
MSC_MAX_PLANNED_ORDERS_PER_DEMAND
This profile is obsolete.
This profile was introduced in basically to plug abnormal demand supply
situation in plans.
Suppose there is a demand line of 1000 and by mistake some one has setup
an order modifier (FOQ/MOQ) of 1 then 1 demand would generate 1000
work orders. In actual business the order sizes may be 50 or 100, so 1000
work order/demand is really not an ideal profile of supply /demand.
To check these kind of data maintenance issues this profile was introduced
where one has a rough idea on the maximum number of work orders one
demand might generate and can set this as an internal checkpoint.
I believe this profile has been removed later as in some
business/Semiconductors work orders can really run into very huge
number/demand and it is difficult to guess the value for this. Plans at our end
were tripping on this profile.
I do not see this profile any more in planners log 11.5.10-Rollup 4 onwards.
This is correct, just to add this logic is not applicable to DRP Plans and will
get invoked only for Fixed Order Quantity order modifiers.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Minimize Project Cross Peg within Window


Profile Code
Profile Option Name
Description

MSC
MSC_MINIMIZE_CROSS_PEG
Values: Yes/No
Default: Yes Used in conjunction with profile option MSC: Use attribute
based netting in priority pegging. Valid values are:

Yes - The planning engine tries to minimize cross pegging


within the Supply/Demand window.
No - The planning engine does not attend to the amount of
cross pegging

Default Value - Yes


Note Reference(s)

417736.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Minimize changes to chronological sequence


of supplies while rescheduling
Profile Code
Profile Option Name
Description

MSC
MSC_MINIMIZE_WORKORDER_CROSSOVER
Valid values are:

Yes - to minimize the rescheduling of work orders in


progress during rescheduling operations during Memory
Based Planner.

No

Default Value - No

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Available in 12.1.1 and upwards as well


376038.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Minimum Capacity


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_MIN_CAPACITY
Not Used.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4573393
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Minimum Percentage variation in safety stock


values
Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SS_MIN_VARIATION
The safety stock is held constant across time intervals if the deviation is
within
this percentage. Zero ignores all deviations.
376451.1
276707.1
759329.1
559867.1

-1
-1
-1
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Minimum Supply/Demand Percent for Pegging


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_MIN_SUP_DEM_PER_PEG

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Move Past Due To Sysdate


Profile Code
Profile Option Name
Description

MSC
MSC_MOVE_PAST_DUE_TO_SYSDATE

When the Arrival date is given and we


offset it with the Lead times if the
dates go behind Sysdate that is Past
Due then we move it to the Sysdate

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5618929
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Net Change Temp Dir


Profile Code
Profile Option Name
Description

MSC
MSC_OA_TEMP_DIR
Stores the location of image cache used in the Plan Comparison Report.
Indicate the location in the following format: [directory]@[subdir] where
[directory]
This must match the absolute path of the OA_MEDIA environment variable
and [subdir] is the name of a subdirectory under the OA_MEDIA directory.
The subdirectory must have write permissions for all.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: New Forecast Auto Plan


Profile Code
Profile Option Name
Description

MSC
MSC_DEFAULT_UNCONST_PLAN
The plan launched in Oracle Advanced Supply Chain Planning when Oracle
Collaborative Planning receives a supplier's forecast. Oracle recommends
that this plan be an unconstrained plan.
Set the profile to an unconstrained supply chain plan. When the demand plan
scenario mentioned in the profile option MSD: Default DP Scenario is
published, the unconstrained supply chain plan specified in the profile option
MSC: New Forecast Auto Plan starts running.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Yes
No
No
Yes
No
No
No
No
No
Yes
No
No
No
Yes
No
No
No
No
No

MSC: New Material and Resource Plan Fetch Size


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_HP_FETCH_SIZE
Page fetch size of ASCP material and resource horizontal plan screen.
1462359.1

Bug Reference(s)
Document References(s)

14251869
-1
-1

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: New Planner Backward Compatibility


Profile Code
Profile Option Name
Description

MSC
MSC_NEW_PLANNER_BACK_COMPATIBILITY

Based on latest information available in Bug


9848641
And Per bug 12352866, this needs to be set to
YES in 12.1.3 to avoid a performance issue in
constrained plans.

Yes - uses the new algorithm for planning phantom items.


When you also set
MRP_NEW_PLANNER_BACKWARD_COMPATIBILITY =
Yes, then Phantoms will be planned as regular items.
When you also set
MRP_NEW_PLANNER_BACKWARD_COMPATIBILITY =
No or NULL, then Phantoms will NOT be planned as regular
items.

No - Uses the old algorithm for planning phantom items.


When you also set
MRP_NEW_PLANNER_BACKWARD_COMPATIBILITY =
Yes, then Phantoms will be planned as regular items.
When you also set
MRP_NEW_PLANNER_BACKWARD_COMPATIBILITY =
No or NULL, then Phantoms will NOT be planned as regular
items.

Most all customers should use Yes.


If case of certain plan errors when working with byproducts and profile = Yes, then you need to set
profile = No
The failure will occur when by-product is also a
component of the BOM as shown below
Ex: Assembly A
/
\
Phantom B
Phantom C -> By-product
C
|
comp C
This setup will result in a A->C->A
loop.
This was seen in bug where plan failed
with the following message:
### Error: found loop between FROM
operation : with sequence number 10

supply id 1018430492 item id 1181059


TO operation : with sequence number 1
supply id 1018430492 item id 1181059
org Id = 86
This could occur in two conditions :
A. There is a loop in network routing
- if so, please check the set-up and
fix the routing
B. There are by/co-products of
assembly which are also a component of
an item forming this assembly
If so, try to change the profile
option MSO: Peg By-product Supplies to
FALSE APP-MRP-22064: An internal error has
occurred (hls_failure, 1)
Note Reference(s)
433492.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9848641
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
-1
Yes
No
No
Yes
Yes
Yes
Yes
Yes
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
No

MSC: New Supply Commit Auto Plan


Profile Code
Profile Option Name
Description

MSC
MSC_DEFAULT_CONST_PLAN
The profile controls the plan that is launched in Oracle Advanced Supply
Chain Planning when Oracle Collaborative Planning receives a supplier's
supply commits. Oracle recommends that this plan be a constrained plan.
Valid values are:

Specify the name of the plan that you want to launch


automatically in the profile option MSC: New Supply Commit
Auto Plan. It is recommended that you specify a constrained
plan.

Set the profile option MSC: SCEM Engine Launch Events to All to
automatically start Supply Chain Event Manager (SCEM) when a supplier
loads an order forecast or when you publish an order forecast from the
planning server. If you set the profile option to Publish, Supply Chain Event
Manager starts only when plans are published from Oracle Advanced Supply
Chain Planning. If you set the profile option to Load, Supply Chain Event
Manager starts only when data is loaded using flat files.
Ensure that the value of the profile option MSC: Configuration is set to APS &
CP.
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
Yes
No
No
Yes
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Number of Workers for Self Service Loads


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SELF_SERVICE_LOADS_WORKERS_NUM
Used in conjunction with profile MSC Batch Size for Self Service Loads to
help size loading for large data loads using Self Service Collections. Oracle
does not suggest using a value larger than 10. You may need to increase
Standard Manager workshifts (processes) to accommodate a larger number.
Valid values: Integer
Default value = 3
352277.1

-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: OTHER with zero allocation percent is valid


demand class
Profile Code
Profile Option Name
Description

MSC
MSC_ZERO_ALLOC_PERC
Set this profile, if you want to consider others with zero allocation percent as
valid demand class
When set to Yes, demand classes with 0% allocation are considered as valid
demand classes for allocated ATP calculations.
When set to No, demand classes with 0% allocations are not considered as
valid demand classes for allocated ATP calculations

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6156478
-1
Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: OTM Punchout URI


Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_OTM_PUNCHOUT_URI
Used by punchout. URL to OTM such as:
http://otm-it1-55-oas.us.oracle.com/
733189.1
761773.1

-1
-1
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: OTM Responsibility


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_WS_OTM_RESPID
Responsibility like supply chain planner
761773.1

-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: OTM User


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_WS_OTM_USERID
Userid, like MFG, this profile and next one will be used for notification
workflow
761773.1

-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Operator Company Name


Profile Code
Profile Option Name
Description

MSC
MSC_X_COMPANY_NAME
Used by Oracle Collaborative planning. This profile option will be defaulted
with value of "My Company". User can update the company name. This
company name will get reflected in next collection run

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2297044
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Oracle Rapid Planning URL


Profile Code
Profile Option Name
Description

MSC
MSC_RP_HOST_URL

Rapid Planning External Server URL


The port number provided in the profile value
should be same as the port number for the UI
Domain that is defined in Creating the UI Domain
from the Oracle Rapid Planning Installation Guide,
Release 12.1.3.3

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

1276882.1

-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Order Number-CA Mandatory for CVMI


Profile Code
Profile Option Name
Description

MSC
MSC_X_CVMI_CA_MAND
Determines whether the order number is mandatory for a consumption
advice, while the customer enters the consumption advice record.

If the profile option is set to Yes, the user must enter order
number for the consumption advice.
If set to No, the key date for sales orders and ASN is
considered as part of deletion key.

Valid values: Yes/No


Default = No
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Collaborative Planning Implementation and User's Guide


Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Order Type for Consigned VMI


Profile Code
Profile Option Name
Description

MSC
MSC_X_VMI_OM_ORDER_TYPE
This indicates the order type that Oracle Collaborative Planning uses when
creating a sales order for consigned VMI. This order type should encompass
billing and inventory reduction functions without any shipping being
performed
Set on APS Destination in a distributed environment

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6518881
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Organization containing generic BOM for


forecast explosion
Profile Code
Profile Option Name
Description

MSC
MSC_ORG_FOR_BOM_EXPLOSION
Used by collections to identify and populate the bill of material validation
organization.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Overwrite all Order Forecast records


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_X_OVERWRITE_OF
If the profile "MSC: Overwrite order forecast" is Yes, we delete all the Order
forecast for that item,cust/cust_site, supp/supp_site , order type combination;
and then load the new Order forecast.
461898.1

3754801
-1
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Overwrite all supplier capacity records


Profile Code
Profile Option Name
Description

MSC
MSC_X_OVERWRITE_SC
Indicates whether or not the previous records regarding supplier capacity
need to be maintained. You can set this profile option to replace all previous
supplier capacity values with the latest supplier capacity to which the supplier
commits.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3103879
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Base Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_BASE_PKG
Valid value are:

Yes - Base Package is used for creating a model in


Production Scheduling.

No - Base Package is not used for creating a model in


Production Scheduling.

Default Value - Yes


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Beginning Inventory Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_BGN_INVNTRY_PKG
Valid value are:

Yes - Beginning Inventory Package is used for creating a


model in Production Scheduling.

No - Beginning Inventory Package is not used for creating a


model in Production Scheduling.

Default Value - Yes


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Calendar Package


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SCP_PS_CALENDAR_PKG
Valid values are:

Yes - Calendar Package is used for creating a model in


Production Scheduling.

No - Calendar Package is not used for creating a model in


Production Scheduling.

Default Value - Yes


415381.1

-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Customer Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_CUSTOMER_PKG

Valid value are:


Yes - Customer Package is used for creating a
model in Production Scheduling.
No - Customer Package is not used for creating a
model in Production Scheduling.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Distribution Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_DSTRBTN_PKG

Valid value are:


Yes - Distribution Package is used for creating a
model in Production Scheduling.
No - Distribution Package is not used for creating a
model in Production Scheduling.
Default Value - Yes
At this time this package is not used by the PS
model creation process.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Enterprise Forecast Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_FORECAST_PKG

Valid value are:


Yes - Enterprise Forecast Package is used for
creating a model in Production Scheduling.
No - Enterprise Forecast Package is not used for
creating a model in Production Scheduling.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Inventory Safety Targets


Package
Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_IST_PKG

Valid value are:


Yes - Safety Stock Targets Package is used for
creating a model in Production Scheduling.
No - Safety Stock Targets Package is not used for
creating a model in Production Scheduling.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Planning Command Center User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Manufacturing Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_MFG_PKG

Valid value are:


Yes - Manufacturing Package is used for creating a
model in Production Scheduling.
No - Manufacturing Package is not used for
creating a model in Production Scheduling.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Planning Command Center User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Purchase Orders Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_PO_PKG

Valid value are:


Yes - Purchase Orders Package is used for
creating a model in Production Scheduling.
No - Purchase Orders Package is not used for
creating a model in Production Scheduling.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Reservation Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_RESERVATION_PKG

MSC: PS - Snapshot Reservation Package


This profile brings in reservations for PS plans
(similar to how you enable all the other data
packages).
Only meaningful for 12.1.3.6+ (which is not
released yet)

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

1386168.1

-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Sales Orders Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_SO_PKG

Valid value are:


Yes - Sales Orders Package is used for creating a
model in Production Scheduling.
No - Sales Orders Package is not used for creating
a model in Production Scheduling.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Supplier Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_SUPPLIER_PKG

Valid value are:


Yes - Supplier Package is used for creating a
model in Production Scheduling.
No - Supplier Package is not used for creating a
model in Production Scheduling.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Transfer Orders Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_TO_PKG

Valid value are:


Yes - Transfer Orders Package is used for creating
a model in Production Scheduling.
No - Transfer Orders Package is not used for
creating a model in Production Scheduling.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Snapshot Work Orders Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_WO_PKG

Valid value are:


Yes - Work Orders Package is used for creating a
model in Production Scheduling.
No - Work Orders Package is not used for creating
a model in Production Scheduling.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS - Visit Display Format in PS UI


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SCP_PS_VISIT_DISP_FORMAT

Allows the user to specify the display for CMRO


Visits in the Production Scheduling client.
Allowable vaues are: "Name" or "Code" or
"Name:Code"
Applicable to 12.1.3+

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS Adjust Post Horizon Demand Qty


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_ADJUST_POST_HORIZON_DEM_QTY

MSC: PS Adjust Post Horizon Demand Qty


This profile allows PS solver to "net-out" demands
that are not fulfilled until after the end of the
scheduling horizon.
When profile "MSC: PS Adjust Post Horizon
Demand Qty" to yes,
then PS uses the Work Orders that are on end of
horizon to meet demand.

Note Reference(s)
1386168.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

12939774
-1
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS Allow WO Purchased Item Offloading


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SCP_PS_ALLOW_WO_PURCHASED_ITEM_OFFLOADING
MSC: PS Allow WO Purchased Item Offloading

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS Consistent Resource Assignment


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_CONSISTENT_RESOURCE_ASSIGNMENT
Whether the Production Scheduling functionality 'Consistent Resource
Assignment' should be used. If activated, where a routing has alternates on
multiple operation steps with the same resources, then the solver will try to
use the same resource across the routing.
There are three available options:
+ No - This functionality is not activated
+ Yes - The functionality is activated for all routings

Note Reference(s)
883676.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5332948
7316625
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS Currency Symbol


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_CURRENCY_SYMBOL
The currency symbol used by PS for measurement of costs and calculation
of key performance indicators.
Set this in the APS destination for a distributed installation

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS Enable CRO Scheduling


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_ENABLE_CRO

If CRO option is licensed along with Production


Scheduling application, the profile option "MSC: PS
Enable CRO Scheduling" must be set to "Yes".
RMO and CRO are synonymous.
Made obsolete in R12.1.3

Note Reference(s)
973027.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7037527
-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS Enable RMO Scheduling


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_ENABLE_RMO

Note Reference(s)

454651.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Obsolete with v2 integration (11.5.10/12.1)

-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS Filter Active Items


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_FILTER_ACTIVE_ITEMS

Introduced in Patch 9921057


This profile option will filter out any items which do
not have any active demand within the PS horizon.
This can be dependent or independent. This works
with or without an ASCP plan reference. If an
ASCP plan is referenced, the active demand from
planned orders is also studied.
Not applicable after 12.1.3.7.

Note Reference(s)

Bug Reference(s)

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9609494
9921057
9444710
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS Firm Past Due WO


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_FIRM_PAST_DUE_WO
This option if enabled will firm all work order operations which commence
prior to the beginning of the schedule horizon. This also considers the
schedule start date offset.
This is based on the operation start dates.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7489790
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS Import On-Hold Work Orders


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_IMPORT_ON_HOLD_WO

We bring in the On hold workorders into PS. This is


controlled by a Profile option.
The On hold workorders will be extracted into PS if
the profile option is set to 'Yes'. The default value
will also be set to 'Yes'.
The On hold workorders will not be brought into PS
if the profile option is set to 'No'.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

13862916
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS Resource Constraint Horizon


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_RESOURCE_CONSTRAINT_HORIZON
Introduced in bug 10160770
This flag (set in number of days) is used to set the capacity constraint

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

10160770
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS Run Application Script


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_APP_SCRIPT

Specifies the name of the batch script that starts


Production Scheduling.
Default Value - runPS.bat
Obsolete in PS V2 integration (11.5.10/R12.1)

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5136451
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS Run Connector Script


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PS_CONNECTOR_SCRIPT

Specifies the batch script that starts the Production


Scheduling Connector.
Default Value - runPSConnector.bat
Obsolete in v2 integration (11.5.10/R12.1)

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: PS/SNO API Version


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SCP_API_VERSION
The API version used when generating the XML packages for Strategic
Network Optimization and/or Production Scheduling. This must be
configured as specified for the current version of the software being used.
Typically, this value should not be changed unless the guidance of Oracle
Support.
552381.1
973027.1

-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: PS/SNO Alignment Date


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_ALIGNMENT_DATE
The date/time that determines the start of the period start date within
Strategic Network Optimization. For example, if set to a Monday all full SNO
periods will commence on a Monday. If the plan start date does not align
with this, the first period may be a partial period. If your plan start date falls
on a Wednesdy while the alignment date is a Monday will result in the first
period being Wednesday - Sunday (5 days).

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6012870
5646419
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: PS/SNO App Server URL


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_APP_SERVER_URL
The fully qualified URL (including port number) for the application server.
This is required for the Production Scheduling and Strategic Network
Optimization client release process

Note Reference(s)
760103.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7037527
-1
-1
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: PS/SNO Client Install Path


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SCP_CLIENT_PATH
This is the install path on the client. The system installs the software in a 'scp'
directory under this path.
PS and SNO are installed automatically the first time they are accessed by
the E-Business Suite.

Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: PS/SNO Compress Xml Files


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_ZIP_PACKAGES

This flag indicates whether the extracted


files/model files are stored in compressed format or
not. Typically this should be set to Yes to
mazimize data download speed to the client.
If integration extensions are being developed then
you may not want to store these in compressed
format.
Valid values are:

Yes

No

Default Value - Yes


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

415381.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: PS/SNO Data Store Path


Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SCP_DATA_STORE_PATH
Where model/publish and temporary files are stored on the server.
602712.1
868904.1

-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: PS/SNO Debug Mode


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_DEBUG_MODE

This flag determines the level of logging appearing


in the integration log files. This flag is typically
only set upon request from Oracle support when
investigating issues. Setting this flag to Yes will
have peformance implications.
Valid values are:

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No

Default Value - No
868904.1
809199.1
405083.1

-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: PS/SNO Download XML Files


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_DOWNLOAD_XML_FILES

Setting this flag causes the intermediate integration


data files to be downloaded to the client. This
causes significantly more data to be transfered and
is typically done for debugging model construction
issues. When set to No, only the final model file
will be downloaded to the client
Valid values are:

Yes - if users want to download the xml files to the client


machine for debugging purpose.
No

Default Value - No.


Note Reference(s)
733189.1

Bug Reference(s)

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7293823
8762862
8945618
-1
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: PS/SNO Include Negative Inventory Demands


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_INCLUDE_NEGATIVE_INVENTORY_DEMANDS

MSC: PS/SNO Include Negative Inventory


Demands
This profile has been introduced to extract negative
beginning inventory.
If there is negative on-hand inventory then an
artificial demand will be created for this negative
quantity so that the projected inventory balances
are accurate.
For example, if Item A has -10 on hand a demand
of 10 will be created. This profile option controls the
creation of these artificial demands.
The profile controls the extraction of negative
demand.
Values:
The default value is Yes.
If this set to "No" then negative demands will not be
extracted.

Note Reference(s)

1386168.1

Bug Reference(s)
Document References(s)

12848085
-1
-1

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
Yes
No

Manufacturing Operations Center


Global Order Promising

No
No

MSC: PS/SNO Past Due Supplies Window


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_PAST_DUE_SUPPLIES_WINDOW

This value specifies the amount of time in the past


to look for supply.
Not applicable after 12.1.3.7 so will be removed
from the ldt file, however, customers who have this
profile in their DB would continue to see them but
can safely ignore.
From bug 9909547 which introduced this profile
A new profile option "MSC: Past Due Supplies
Window" has been added.
The past due supplies will be extracted based on
the user's input.
If the value in this profile option is 10 then
integration will bring the supplies 10 days before
the horizon start.
Older past due supplies will be ignored.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9909547
-1
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: PS/SNO Use DB for Integration Data


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SCP_USE_DB_FOR_DATA
In an distribution env, the application server and concurrent program server
may run on different machine. In this case the application server may not
have access to the file system which concurrent program server could
access. In this case you will need to use the database option to access the
data across servers.
454651.1

-1
Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: Pass List Price to OM in DRP Release


Profile Code
Profile Option Name
Description

MSC
MSC_DRP_PASS_LIST_PRICE_OM
This is discussed in Bug 7284253 MSC CREATES ISO WITH STATUS OF
'ENTERED' INSTEAD OF 'BOOKED':
If profile MSC: Pass List Price to OM in DRP Release is set to Y, DRP
release will create the internal sales order in 'Booked' state.
Only in 11.5.10, not reported in any R12.x release.

Note Reference(s)
943244.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7497020
-1
-1
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: Peg Firm Supply First


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_PEG_FIRM_SUPPLY_FIRST
Does not appear in the documentation.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Peg Firm Work Orders Within Assigned


Projects and Tasks
Profile Code
Profile Option Name
Description

MSC
MSC_FIRM_JOB_RESV_TASK
When set to yes, reservation level for firm work orders will be set at Task
level
This is designed to work with MSC: Enable Attribute Netting = No
Note that in 12.1 we recommend that customers use MSC: Enable Attribute
Netting = Yes to use the new netting engine, unless they have specific
business requirement for using old netting engine (No)
Per Enhancement 8482143
When pegging firm work orders for hard pegged items, in
old attribute netting, peg the firm work orders to
demands having same project/task as itself.
Otherwise peg it to excess.
This is independent of the reservation level.
Introduced in ASCP Engine/UI RUP #37 for 11.5.10
- Per bug 9087339, further fix was made.
- Ported to 12.1.3.1 and 12.0.6 ASCP Engine/UI CU10 patch

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8482143
-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSC: Peg to maximize supply usage


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_PEG_TO_MAX_SUPPLY_USAGE
Does not appear to exist in the documentation

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Perform ATP check for Internal Sales Orders


Profile Code
Profile Option Name
Description

MSC
MSC_ATP_CHECK_INT_SALES_ORDERS
Only used when INV: Inventory Capable to Promise - ATP/CTP based on
Planning Data From Note 558908.1
1. The profile was added in bug 5440895. This profile works in tandem
with the profile option MSC: Consume forecasts using Internal Sales Orders.
So, If profile MSC: Perform ATP Check for Internal Sales Orders is set with a
value, it is used. Otherwise, the value of the previous profile is used.
2. If you have a centralized instance, set the profile value as required. If
you are a decentralized/distributed installation with both APS Destination and
ERP Source, set this on the APS destination and ERP source.
3. Profile option values and meanings:
* Yes - Perform ATP check on Internal Sales Orders
* No - Do Not perform ATP check on Internal Sales Orders
Notes:
1. Bug 6434413 Service Orgs do NOT use an External sales order, so fixes
had to be made so that scheduling would be correct for service orgs that
generate Internal Reqs directly
2. For Bug 6434413 - fix is released on ATP RUP #22 and above (See
Note 252108.1 for list of patches. Patch 6434413 should not be applied
instead of a rollup patch.
3. In R12.0.4, this fix for bug 6434413 is not yet released - 16-APR-2008

Note Reference(s)
558908.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Plan Name for CMRO


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
AHL_MSC_RES_CPCTY_PLAN
12.1.3.7, we introduced a new enhancement to publish resource availability
to cMRO. In order to do that, we need to provide the ASCP plan name for
this profile.

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Plan co-products


Profile Code
Profile Option Name
Description

MSC
MSC_PLAN_COPRODUCTS
Indicate whether co-products are planned and whether supplies are created
for the co-products. Valid values are:

Yes
No

Can be defined at the site level.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

If the plan planning mode is Constrained (Without Detailed Scheduling), the


planning engine only uses this profile option if its value is Yes.
305575.1

-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Plan for order at risk calculation


Profile Code
Profile Option Name
Description

MSC
MSC_PLAN_FOR_ORDER_AT_RISK

Indicates a plan that Oracle Collaborative Planning


uses to derive the pegging information for each
order that you upload.
See also Note.276003.1 for the description of
Enhanced Flagging of Potentially Late Orders.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Yes
No
No
Yes
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Planning Currency


Profile Code
Profile Option Name
Description

MSC
MSC_PLANNING_CURRENCY
In 11.5.10, this profile option is used to specify the planning currency.
This profile option can be defined at the site level.
In 12.1.x, this profile is not used.
Default Value - US Dollar

Note Reference(s)
147221.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4573393
-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Pre-Flush
Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_PRE_FLUSH
Not used per bug 4573393

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4573393
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Prefer Consumption within Forecast Bucket


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_PREF_FOR_BUCKET
Valid values are:

Yes - this profile will take effect when the plan options are
"Spread Forecast" and "Consumption by bucket" is
unchecked. In that case, we would consume the forecasts in
the following fashion: Spread the forecasts first. First round
of consumption begins by walking backwards for the number
of backward days mentioned from the date of the sales
order, considering any forecast entry as eligible only if the
sales order falls in the same bucket as the forecast. Once we
find no more entries backwards we walk forwards for the
forward number of days mentioned checking for eligible
forecasts as mentioned above. Now, if we still need forecast
entries, we start walking backwards this time trying to
consume all the forecast entries within the backward time
fence. After this we go forward in the same fashion if
required.

No - old behavior

Default Value - No
395804.1
804214.1

-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Priority for Substitute Items Flexfield Attribute


Profile Code
Profile Option Name
Description

MSC
MSC_BOM_SUBST_PRIORITY
This profile option stores the name of the flexfield column that contains the
value in the corresponding table. Set this profile option at the site level only
See 'Flexfield Attributes, page A-1 for more information.
Set in EBS Source in a distributed installation. Created by Create Planning
Flexfields process.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Oracle Advanced Supply Chain Planning Implementation and User's Guide
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Priority of Alternate Resources for an


Operation Flexfield Attribute
Profile Code
Profile Option Name
Description

MSC
MSC_ALT_RES_PRIORITY
This profile option stores the name of the flexfield column that contains the
value in the corresponding table. See 'Flexfield Attributes, page A-1 for more
information.

Set in EBS Source in a distributed installation.

Created by Create Planning Flexfields concurrent program

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Production Plan for Transportation updates


Profile Code
Profile Option Name
Description

MSC
MSC_PROD_PLAN_ID_FOR_OTM_UPDATES
Use this profile option to indicate the production plans that receive estimated
arrival time updates from Oracle Transportation Management. Valid values
are:

Null: Do not pass updates to any plan


All Production Plans: Pass updates to all plans with
Production flag selected
[specific plan name]: Pass updates only to the plan that is
specified

Default Value - NULL


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Project Task Collection Window Days


Profile Code
Profile Option Name
Description

MSC
MSC_COLLECTION_WINDOW_FOR_PROJ_TASKS
Controls which projects/tasks are collected after the collection engine deletes
all of the previously collected records for the instance.
Valid values are:
+ Null: Collects all of the records from the source.
+ Integer: Collects all of the records from the source from projects whose end
date is within the number of days in the past specified in the profile option
value.
The collections process never collects tasks whose projects are completed.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
Yes
No
Yes
Yes
Yes
No
No
No
No
Yes
Yes
No
No
No
No
No

MSC: Provide Warning For Dates Entered on Nonwork Days


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_VALIDATE_NON_WORK_DATE
Warning is displayed in the workbench if a non-working day is entered

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4639108
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Provide Warning when Sales Order Quantity


is Changed
Profile Code
Profile Option Name
Description

MSC
MSC_SO_QTY_CHANGED_WARN
The New Quantity field on a sales order is user editable. The user can raise
or lower the sales order quantity by firming the sales order. Valid values are:

Yes - As the user tabs out of the New Quantity field, if the
quantity is changed then a warning is given as " Sales orders
with changed quantities cannot be released. The user must
update the sales order directly in the source instance." In
addition, the action for the sales order is set to None when
the quantity is changed.
No - supresses the warning

Default = Yes
Set on APS Destination in a distributed environment
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4479258
-1
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: Purchase Order Dock Date Calculation


Preference
Profile Code
Profile Option Name
Description

MSC
MSC_PO_DOCK_DATE_CALC_PREF
This profile option specifies the purchase order line date that the planning
engine uses as the material arrival (dock) date. Valid values are:

Promise Date: If the Promise Date is not available, the


planning engine uses Need by Date so that unacknowledged
purchase orders consume supplier capacity. (1)

Need By Date: Existing purchase orders do not consume


supplier capacity. (2)

This is a site level profile option.


Use the same setting of this profile option for running both collections and
plans.
Default Value - Promise Date
Note Reference(s)
413816.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Purge Exception Days


Profile Code
Profile Option Name
Description

MSC
MSC_PURGE_EXCEPTION_DAYS
Information about this profile is not available in user guide.

Note Reference(s)

All exceptions generated/updated by the number of days before (set by this


profile value) will be deleted.
555016.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Purge Staging and Entity Key Translation


Tables
Profile Code
Profile Option Name
Description

MSC
MSC_PURGE_ST_CONTROL
Controls both truncation of the staging table during data collection process
and deletion of the link ID tables. Valid values are:

Yes - conserve disk space when running data collections for


single instances, or as separate processes for multiple
instances. Set this profile to Yes when you have only 1
source instance connected to the planning server. This
allows the MSC_ST_ tables to be truncated rather than
deleted from. This helps conserve space and improve
performance

No - When running data collections for multiple instances


simultaneously, set to avoid data loss. It should be set to
No if you have multiple source instances connected to the
planning server to avoid data loss as a truncation would get
rid of all the data in the table.

Note Reference(s)
405295.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4717843
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Rapid Planning Group Planned Orders


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_RP_GROUP_PLANNED_ORDERS
Determines if planned orders of the same type are grouped. Purchase and t

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

10130815
-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Rapid Planning Safety Stock Lead Time


Method
Profile Code
Profile Option Name
Description

MSC
MSC_RP_SAFETY_STOCK_METHOD

Safety Stock Lead Time Method Values


This profile provides the following options:

Do not compute Safety Stock (currently exists)


Use Safety Stock Percent (currently exists)
Use Safety Stock Quantity (this is the enhancement)

In 12.1.3.6, this profile is not used. A new profile


has been introduced MSC: Safety Stock Planning
Method which has valuesa. Do not plan Safety Stock
b. Use Safety Stock Quantities
c. Use Safety Stock Lead Time from Safety Stock
Percent
To calculate safety stock using quantity, this plan
options must be set to Use Safety Stock Quantity.
Use Safety Stock Lead Time from Safety Stock
Percent (this option replaces Use Safety Stock
Percent option that was in RP 12.1.3.3.)
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

1276896.1

-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Rapid Planning Scripts Home


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_RP_SCRIPTS_HOME

This profile should point to the directory where all


the WLST_scripts will be kept.
1276882.1

-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Rapid Planning UI Refresh Timeout


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_RP_UI_TIMEOUT
Timeout value is in millisecond. Example value 5000
1276882.1

-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Rapid Planning WebLogic Server Home


Profile Code
Profile Option Name
Description

MSC
MSC_RP_WLS_HOME

Note Reference(s)

1276882.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Installation path to the WLS Home directory

-1
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Read Profiles From DB


Profile Code
Profile Option Name
Description

MSC
MSC_READ_PROFILES_FROM_DB
No During planning flat files are created that hold profile values. At times, it is
better to have profiles read from the database instead of the flat files. This
can espeically true for on-line or batch replan when profiles are changed.
Valid values are:

Yes

No

Default Value - No
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9406133
-1
Yes
No
No
Yes
Yes
No
No
No
Yes
No
Yes
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSC: Recalculate Demand Priorities after Spreading


Profile Code
Profile Option Name
Description

MSC
MSC_RECALC_DMD_PRI_SPREADING
MSC: Recalculate Demand Priorities after Spreading
Default = No
When plan option Spread Forecast is checked and profile = Yes, then after
we spread the forecast, we recalculate the demand priority of sales orders
and forecasts.
First released in ASCP Engine/UI Rollup #35 for 11.5.10
Not ported to R12.x
Ported to 12.1 and released in 12.1.2.1 and above.

Note Reference(s)

Bug Reference(s)

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8301504
8839391
8311261
-1
-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Refresh Site to Region Mappings Event


Profile Code
Profile Option Name
Description

MSC
MSC_REFRESH_REGION_SITE
Valid values are:

Yes - Collection of Sourcing Rules / Existing behavior mapping during collection if sourcing rules parameter is set
to Yes

No - Running of Refresh Collection Snapshots Request /


Mapping will be performed only during standalone refresh
snapshot and not during a complete refresh of data
collections.

With the alternate value selected, the collected data might not reflect the
exact region site mapping based if the standalone Refresh Collection
Snapshots is run.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Default Value - Yes


427338.1

5717270
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Refresh Snapshots Pending Timeout


Profile Code
Profile Option Name
Description

MSC
MSC_REF_SNAP_PENDING_TIMEOUT
Sets the time that the Planning Data Pull concurrent process waits for
concurrent process Refresh Snapshots on the source before it times out.
This time out only applies if concurrent process Refresh Snapshots is at
status Pending/Inactive which occurs if another version of concurrent
process Refresh Snapshots is running. Valid values are:

Integer in minutes

Default Value - 10
Note Reference(s)
468903.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Region Instance


Profile Code
Profile Option Name
Description

MSC
MSC_HUB_REGION_INSTANCE

This profile needs to be set when data is being


collected from multiple sources. APCC only reports
from the instance which is defined in this profile.
The profile is depreciated after patch
10309327:R12.MSC.B - APCC TO SUPPORT
REGIONS FROM MULTIPLE INSTANCES

Note Reference(s)
844667.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6899253
6850493
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: Release WIP Dtls if Order Date different then


BOM Revision Date
Profile Code
Profile Option Name
Description

MSC
MSC_RELEASE_DTLS_REVDATE
Oracle Work in Process uses the details effective on the job start date. Valid
values are:

Yes - then planning engine releases the WIP details even if


the Suggested Start Date is different than BOM Revision
Date.
No - the planning engine does not release the WIP details if
the new WIP Start Date is different than BOM Revision Date.

Set on APS Destination in a distributed environment


If all conditions are met to release the WIP details when releasing a planned
orders (Ref Note 1346745.1)
Then we evaluate the order as per the following example:
Check the fixed and variable LT of the item and offset the start date:
Answer: Planned order with Suggested due Date of Day 60 and offset makes
start date Day 50
If the planed order has been compressed, or the planning engine has used
an alternate routing (also possible that Alternate BOM is used)
Then is it possible that the start date in workbench is not Day 50 but [different
day]
If [different day], then check the profile, If Yes, then release the details, IF
No, then do not release the details and just release the header row to WIP
and let WIP Mass Load compute the components and resources and dates
for these based on the BOM and Routing for the item.
then we will not release details unless the profile is set to Yes.
Note Reference(s)
958034.1
1346745.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center

2682123
-1
-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No

Manufacturing Operations Center


Global Order Promising

No
No

MSC: Released Only By User


Profile Code
Profile Option Name
Description

MSC
MSC_RELEASED_BY_USER_ONLY
Use this profile option to specify whether to restrict implementation of
planned orders and recommendations to the current user. Valid values are:

Yes - Only implement planned orders and recommendations


that this user marked

No - Implement planned orders and recommendations that


any user marked

Set on APS Destination in a distributed environment


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8326980
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Resource Group for a Line Flexfield Attribute


Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_LINE_RES_GROUP
This profile option stores the name of the flexfield column that contains the
value in the corresponding table.
147242.1
763878.1

-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Resource Type for an Operation Flexfield


Attribute
Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_RESOURCE_TYPE
This profile is no longer being used.
147242.1

Bug Reference(s)
Document References(s)

2954572
-1
-1

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Respect Minimum Remaining Shelf Life Days


Profile Code
Profile Option Name
Description

MSC
MSC_RESPECT_SHELF_LIFE_DAYS

Details added to recent ASCP Guide - E13358-08


(page A-53)
This profile option enables ASCP to plan supplies
with respect to the shelf life enhancements
described in this design including the minimum
remaining shelf life days. Valid values are:

Yes - ASCP plans supplies with respect to minimum


remaining shelf life days. This is the recommended setting.
No - ASCP plans supplies without enforcing minimum
remaining shelf life days - This is the default value.

Safety Stock will NOT be generated for any item


when this profile is set to Yes and the user has
input a value in the Org Item Attributes - Inventory
tab for field = Shelf life Days
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7424037
-1
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Retain Time for Non-ATPable Items


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_RETAIN_TIME_NON_ATP_ITEM
Valid values are:
Yes - ATP returns same time stamp as passed to ATP from the Request
Date and Time, for all single lines for nonatpable
items or for all sets containing only non-atpable items. If a set contains mix of
atpaple and non atpable items, then ATP continues to return 23:59:00 as the
new timestamp.
No
259601.1
9237457
551293.1
9237457
-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Return Best Source in Global ATP


Profile Code
Profile Option Name
Description

MSC
MSC_BEST_SOURCE_GLOBAL_ATP
No Information available in User guides (115.5.10 or R12.1.1)
This profile in only available in 11.5.10
Not ported to R12 or 12.1
Basic Functionality:
This Feature will result in ATP taking more time to find the Best Source.
- Original Behaviour:
---------------------------Suppose the Rank1 source gives you a Date within the 'Latest Acceptable
Date'. ATP will stop there and won't go through all the sources.
- New Behaviour with profile option set to YES:
-------------------------------------------------------------If this profile is set to YES, ATP will go through all the Sources until it finds
the best Available Date. So this feature is strictly monitored by the above
profile option.
So, if the profile MSC: Return best source in Global ATP is set as Yes, the
Best possible source from all the global Sources defined for the item will be
used.
If the profile is set to NO or NULL, the original Behavior is retained. Default
value of this profile is NO.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

NOTE:
This feature is not supported for Ship set and Arrival Set. If the profile is set
to yes the original behavior is retained for ship sets and arrival sets.
960369.1
734925.1

5982134
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: SCEM Engine Launch Events


Profile Code
Profile Option Name
Description

MSC
MSC_X_AUTO_SCEM_MODE
Launch the Supply Chain Event Manager when data is loaded,published, or
both.
Set the profile option MSC: SCEM Engine Launch Events to All to
automatically
start Supply Chain Event Manager (SCEM) when a supplier loads an order
forecast
or when you publish an order forecast from the planning server. If you set the
profile option to Publish, Supply Chain Event Manager starts only when plans
are
published from Oracle Advanced Supply Chain Planning. If you set the profile
option to Load, Supply Chain Event Manager starts only when data is loaded
using
flat files.

Note Reference(s)
295564.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2949437
2546115
-1
-1
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: SNO - Snapshot Base Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_BASE_PKG

Valid value are:


Yes - Base Package is used for creating a SNO
model.
No - Base Package is not used for creating a SNO
model.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Beginning Inventory Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_BGN_INVNTRY_PKG
Specifies whether the Beginning Inventory Package is used for creating a
model in Strategic Network Optimization. Valid values are:

Yes

No

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Calendar Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_CALENDAR_PKG

Valid value are:


Yes - Calendar Package is used for creating a
SNO model.
No - Calendar Package is not used for creating a
SNO model.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Customer Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_CUSTOMER_PKG

Valid value are:


Yes - Customer Package is used for creating a
SNO model.
No - Customer Package is not used for creating a
SNO model.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Demand Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_DEMAND_PKG

Valid value are:


Yes - Demand Package is used for creating a SNO
model.
No - Demand Package is not used for creating a
SNO model.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Distribution Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_DSTRBTN_PKG

Valid value are:


Yes - Distribution Package is used for creating a
SNO model.
No - Distribution Package is not used for creating a
SNO model.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Enterprise Forecast Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_FORECAST_PKG

Valid value are:


Yes - Forecast Package is used for creating a SNO
model.
No - Forecast Package is not used for creating a
SNO model.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Fixed Production Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_FP_PKG

Valid value are:


Yes - Fixed Production Package is used for
creating a SNO model.
No - Fixed Production Package is not used for
creating a SNO model.
Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Inventory Safety Targets


Package
Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_IST_PKG
Specifies whether the Inventory Safety Targets Package is used for creating
a model in Strategic Network Optimization. Valid values are:

Yes
No

Default Value - Yes


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Manufacturing Package


Profile Code
Profile Option Name
Description

MSC
MSC_SNO_SCP_MFG_PKG
Specifies whether the Manufacturing Package is used for creating a model in
Strategic Network Optimization. Note: We have two profiles:
MSC: SNO - Snapshot Manufacturing Package
MSC: SNO - Snapshot Manufacturing Package (1)
Valid values: Yes/No
Default value: Yes

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Manufacturing Package(1)


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_MFG_PKG
Specifies whether the Manufacturing Package is used for creating a model in
Strategic Network Optimization. Valid values are:

Yes
No

Default Value - Yes


Note: We have two profiles:
MSC: SNO - Snapshot Manufacturing Package
MSC: SNO - Snapshot Manufacturing Package (1)
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: SNO - Snapshot Purchase Orders Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_PO_PKG
Specifies whether the Purchase Orders Package is used for creating a model
in Strategic Network Optimization. Valid values are:

Yes
No

Default Value - Yes


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Sales Orders Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_SO_PKG
Specifies whether the Sales Order Package is used for creating a model in
Strategic Network Optimization. Valid values are:

Yes
No

Default Value - Yes


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Supplier Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_SUPPLIER_PKG
Specifies whether the Supplier Package is used for creating a model in
Strategic Network Optimization. Valid values are:

Yes
No

Default Value - Yes


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Transfer Orders Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_TO_PKG
Specifies whether the Transfer Orders Package is used for creating a model
in Strategic Network Optimization. Valid values are:

Yes
No

Default Value - Yes


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO - Snapshot Work Orders Package


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_WO_PKG
Specifies whether the Work Orders Package is used for creating a model in
Strategic Network Optimization. Valid values are:

Yes
No

Default Value - No
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO Connector Precision


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_CONNECTOR_PRECISION
8 Specifies the precision value of the SNO connector. Valid values are:

Integer

Change only on advise from Oracle Development.


Default Value - 8
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5157640
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO Currency Precision


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_CURRENCY_PRECISION

The precision used when displaying currency


values in SNO.
For the most accurate calculations, a precision of 9
is recommended. Valid values are:

Numeric

Default Value - 2
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO Decimal Precision


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_PRECISION
Specifies the number of decimal places shown for data in properties
windows. Valid values are:

Integer

Within SNO, the number of decimal places is called the display precision.
Changing the display precision does not change the actual data values
saved in a model. The display precision can affect results when you match
data. For example, if the display precision is 2, a Machine node Utilization
field with a value of 133.333333 displays 133.33. If you try to match Machine
nodes with a Utilization field value of 133.33, the Machine node in this
example is not matched because its actual value is 133.333333.
Default Value - 2
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO Optimization Type


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_OPTIMIZATION_TYPE
Whether the model is a Cost or Profit based model. In cost based models,
the Selling Price is not part of the optimization. Valid values are:

Cost: The item list price is not considered.


Profit: The item list price is considered.

Default Value - Cost


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO Publish On Client


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_PUBLISH_ON_CLIENT

This flag causes released results to be stored on


the client side for diagnostic purposes. It slows
down the whole release process so it is
recommended to be used under the guidance of
Oracle support.
Valid values are:

Yes
No - prevents the local save of the files in CSV for
debugging, This can save space and improve performance
on large models.

Default Value - Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7233633
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: SNO Run Application Script


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_APP_SCRIPT
Specifies the name of the batch script that starts SNO.
Default Value - runSNO.bat
OBSOLETE -- in R12.1.2

Note Reference(s)
961419.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7037527
6010199
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO Run Connector Script


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_CONNECTOR_SCRIPT

Specifies the batch script that starts the SNO


Connector.
Do not change without advise from Oracle
Development.
Default Value - runSNOConnector.bat
Obsolete in v2 integration (11.5.10/R12.1)

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: SNO Transportation Capacity By


Profile Code
Profile Option Name
Description

MSC
MSC_SCP_SNO_TRANSPORT_CAPACITY
Needs to be Weight as capacity constraints are not stored by volume in EBS.
Default Value - Weight

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No

MSC: Safety Stock Project


Profile Code
Profile Option Name
Description

MSC
MSC_SAFETY_STOCK_PROJECT
Specifies the default project charged for all safety stock demands.
Oracle Advanced Supply Chain Planning assigns the project specified for all
safety stock demands which originate from non-MRP planned safety stock.
When safety stock requirements are specified in Oracle Inventory for specific
projects, the profile option value is not honored.
The list of values for this profile option is restricted to projects specified in
Oracle Projects. This profile option is enabled at project/seiban level, not at
the task level.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Safety stock change interval (Days)


Profile Code
Profile Option Name
Description

MSC
MSC_SS_INTERVAL_DAYS
Use this profile option to specify the time interval used for smoothing within
the time interval functionality. You can instruct the planing engine to keep
safety stock levels relatively constant within a time interval. You specify:

The number of days in the time interval: Set profile option


MSC: Safety stock change interval (Days)

The method that the planning engine should use to calculate


the constant value: Set profile option MSC: Smoothing
method to calculate Safety stock within Change interval

Note Reference(s)

276707.1
559867.1
376451.1

759329.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
-1
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Sales Orders Offset Days


Profile Code
Profile Option Name
Description

MSC
MSC_SO_OFFSET_DAYS
Completed sales orders are collected within the offset duration. For example,
if Sales Orders Offset Days is set to 90, all the sales orders completed in the
past 90 days are also collected. Valid values are:

Integer > 0

Can be defined at the site level.


A Null value means all closed sales orders are collected.
Does not apply to complex maintenance repair and overhaul where the
material scheduled for a visit or task is collected as a sales order in Oracle
Advanced Supply Chain Planning.
Default Value - null
Note Reference(s)
277863.1
217116.1
780735.1
365770.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Scope of Analyze Plan Partition


Profile Code
Profile Option Name
Description

MSC
MSC_ANALYZE_PARTITION_SCOPE
This profile option specifies the partitions that concurrent process Analyze
Plan Partitions should analyze. Valid values are:

All Partitions (1)

Plan Partition Only (2)

Normally, we recommend the default setting for this profile, unless you run
several plans each cycle and the profile MSC: Launch Analyze Plan Partition
is set to No. Then you should set All Partitions and launch this request after
running all ASCP plans in your planning cycle. Using this strategy can have
positive performance impact if all plans are run together and then users start
working in the plans.
Default Value - Plan Partition Only
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Yes
No
No
Yes
No
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Search Criteria Warning


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_ALLOW_SEARCH_CRITERIA_WARNING
No information currently available on this profile.

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Selection order for Firm Supplies in backward


allocation window
Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SUPPLY_SELECTION_ORDER_BACKWARD_WINDOW
Closest Supply (1), Earliest Supply (2)
Site level default: Closest Supply (1) If profile is set to Earliest Supply, then
we would walk forward instead of the existing backward way. If this profile is
set to Closest Supply, then we will peg it to the closest firm supply.
This would mean that the loop for backward phase present in mslflp.ppc,
should be able to move in both the directions based on profile option.
391548.1

5525679
-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Self Service Loads Delimiter


Profile Code
Profile Option Name
Description

MSC
MSC_SELF_SERVICE_LOADS_DELIMITER
~/, (tilde or Comma) - default = ~ (tilde) Delimiter used to parse the data files
loaded using self service loads, for example, the loading of spreadsheet
forecast data to Oracle Demand Planning. Valid values are:

~
,

Default Value - ~
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: Service Level Category Set


Profile Code
Profile Option Name
Description

MSC
MSC_SERVICE_LEVEL_CATEGORY_SET
Not much information is available about this profile in user guides.
As per IO user guide:
As part of the setup it is necessary to specify the value of the profile option
MSC:
Service Level Category Set. Only categories from this category set are
available
when assigning target service levels and fulfillment lead times at a category
level
during the setup of specific item or category level service levels and
fulfillment lead
times.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
Yes
No
No
No
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Service Planning Enabled


Profile Code
Profile Option Name
Description

MSC
MSC_SRP_ENABLED
If using Service Parts Planning, then set to Yes to collect data for SPP (aka
SRP). Valid values are:

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No

Default Value - No
760095.1
566096.1

-1
-1
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Service Planning Item Safety Stock Level


Value
Profile Code
Profile Option Name
Description

MSC
MSO_SS_PLAN_LEVEL
This profile determines how safety stock targets for different revisions in a
supersession chain are considered in SPP.
Valid Values.

Item - SPP will consider the safety stock level for each item
(for which safety stock is prescribed)
Prime (Default) - the safety stock for the entire prime will be
considered as the safety stock level and the existing supply
for the various members of the prime will be considered
while trying to maintain the safety stock level.

Example:
Consider this supersession session chain: A3 -] A4 [-] A5 [-] A6 -] A7 [-] A8
Assume safety stock for each item = 100 units for a give period.
If the profile option = 'Item', then consider the safety stock level for each item
to be 100 units and use only native supply to maintain this level. There will be
no substitution recommended by planning and safety stock violation
exceptions will be raised for each item.
If the profile = 'Prime', then planning determines that A3, A6 and A8 are the
primes in this supersession chain then planning will use the following levels:
SS target for A3=100 units, and planning will only use supply of A3 to
maintain this level. SS target for A6=300 units, and planning will use supplies
of A4, A5 and A6 to maintain this level. SS target for A8=200 units, and
planning will use supplies of A7 and A8 to maintain this level.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Share Plan Partitions


Profile Code
Profile Option Name
Description

MSC
MSC_SHARE_PARTITIONS
Yes: The number of plan partitions parameter to the concurrent program
mentioned becomes irrelevant; only one partition is created for a plan (you
can enter 1)

Note Reference(s)
137293.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
Yes
No
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No
Yes
No
No
No
No
No
No

MSC: Shelf Life Override of Order Modifiers for


Transfer Orders
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_OVERRIDE_OM_FOR_TRANSFER
Instructs Oracle Advanced Supply Chain Planning whether to maximize the
number of demands satisfied with respect to minimum remaining shelf life.
760046.1

-1
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Simultaneous Resource Sequence Flexfield


Attribute
Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SIMUL_RES_SEQ
This profile option stores the name of the flexfield column that contains the
value in the corresponding table. This setup is only performed during
application install.
153919.1
136734.1
130995.1

-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Smoothing method to calculate Safety stock


within Change interval
Profile Code
Profile Option Name
Description

MSC
MSC_SS_SMOOTHING_METHOD
Specifies the mathematical construct used to calculate safety stock for a time
interval using values within the time interval. Available values include:

Minimum
Average (Default)

Maximum

Note Reference(s)

376451.1
276707.1

Bug Reference(s)

5370377
4520265
-1
-1
-1
-1
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC: Source Instance ID


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_SR_INSTANCE_ID
This profile option is no longer used as of August 2003.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2937850
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Source Setup Required


Profile Code
Profile Option Name
Description

MSC
MSC_SOURCE_SETUP
Internal profile used by the software during collections configuration. Do not
manually update.
When the Default Value of a profile option states that it is automatically
calculated, this means that the Planning Engine determines the default value
of that particular profile option. If you must change these profile option
values, do so only after consulting Oracle Development and Oracle Support.
Valid values are:

11i

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

apsinfo_us
837670.1
211121.1
860349.1
580205.1

-1
-1
-1
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

Y - for Yes

N - for No

Yes
No

12+

MSC: Sourcing History Start Date Offset(in months)


Profile Code
Profile Option Name
Description

Note Reference(s)

MSC
MSC_START_SOURCING_HISTORY
Offsets the starting date of sourcing history calculations and is used with
collections parameters Purge Sourcing History = Yes and Recalculate
Sourcing History = Yes.
399468.1
305327.1
780883.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6959481
-1
-1
-1
-1
Yes
No
No
Yes
No
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Sourcing Rule Category Set


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SRA_CATEGORY_SET
Determines the category set used in Oracle Advanced Supply Chain
Planning in the assignment set form. If this is not set, the user cannot assign
sourcing rules and bills of distribution at the Category- Instance-Organization
and Category-Instance level.
205167.1
783204.1
306913.1

-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Sourcing Variance Tolerance


Profile Code
Profile Option Name
Description

MSC
MSC_SOURCING_TOLERANCE
Used when Enforce Sourcing Constraints is enabled for a plan. This
percentage value establishes a threshold for triggering exception messages
if sourcing allocations are violated.
Exceptions are generated if the difference between the user-specified
sourcing allocation percentages and the plan-derived allocation percentages
is greater than the Sourcing Variance Tolerance. The profile option is entered
as a number and converted to a percentage.
If the user enters 0.5 it becomes 50%.
Valid values are:

Integer between 0 and 1

Default Value - 0.05 (5%)


Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Split Planned Order to perform safety stock


pegging
Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_VIOLATE_ORDER_MODIFIER_SS
Use this profile option to instruct the planning engine how to split a planned
order that pegs to customer demand when pulling it in to meet transient
safety stock.
Values:
1 - No
2 - Yes but do not violate order modifier
3 - Yes
276707.1

3829477
-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Split Planned Orders for Scheduling


Flexibility
Profile Code
Profile Option Name
Description

MSC
MSC_SPLIT_SUPPLY
For constrained plan with decision rules and optimized plans, it determines
whether the planning engine consolidates planned orders that were split
during optimization processing prior to scheduling them. For unconstrained
plans, set it to No. Valid values are:

Yes - Do not consolidate planned orders prior to scheduling.


The planning engine splits them into multiple planned orders
whose quantities generally satisfy one planning time bucket's
worth of capacity against the resources or suppliers used in
the planned order. During scheduling, the planning engine
has more flexibility to place smaller quantities into available
time slots. You cannot specify the size of the durations and
the planning engine does not guarantee that each planned
order in the final plan output spans exactly one planning
bucket.

No - Consolidate orders when possible prior to scheduling.


Use this value if you tend to have long production runs per
routing that cross multiple planning buckets. The planning
engine creates a single planned order. If the plan planning
mode is Constrained (Without Detailed Scheduling), the
planning engine only uses this profile option if its value is No.

Note Reference(s)
298806.1
787982.1
562872.1
787458.1
947399.1
958872.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
-1
-1
-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No

Manufacturing Operations Center


Global Order Promising

No
No

MSC: Supplier Capacity Accumulation(multiplier)


Profile Code
Profile Option Name
Description

MSC
MSC_SUPP_CAP_ACCUM_MLTPLR
This profile option is a multiplier to ASL lead-time. The planning engine uses
it to derive the date when capacity accumulation begins for a supplier. If
profile option MSC: Purchase Order Dock Date Calculation Preference is
Promise Date, Oracle suggests that you set this profile option to 0 so that
suppliers accumulates capacity withintheir lead-time.
This is a site level profile option.
It specifies the date that the planning engine begins supplier capacity
accumulation. You enter it as a multiplier of the Approved Supplier List
Processing Lead-time. To begin accumulation at the Approved Supplier List
Processing Lead-time, enter 1 (the default). To begin accumulation at the
plan start date, enter 0. To begin accumulation at a multiple of the Approved
Supplier List Processing Lead-time, enter another whole number.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8344302
8847552
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Supplier Capacity Consumption by Purchase


Orders
Profile Code
Profile Option Name
Description

MSC
MSO_ALWAYS_CONSUME_CAPACITY_FOR_PO

MSC: Supplier Capacity Consumption by Purchase


Orders
Required capacity for purchase orders will be
correctly shown based on the setting of the profile
option
MSC: Supplier Capacity Consumption by
Purchase Orders.
The following behavior is expected:
Values:
Yes: all purchase orders should be considered
No: no purchase orders are considered
Unacknowledged Only: only purchase orders
without a promised date are considered
Purchase Orders Outside Lead time only: only
purchase orders scheduled outside lead time are
considered

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra

11790310
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No

Strategic Network Optimization


Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No

MSC: Suppress Exception for Selection of


Alternates
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_SUPPRESS_ALT_EXCEPTION
Controls whether the planning engine generates exceptions related to
alternate bills of material and routings. If the profile option is No, it does not
generate those exceptions.
Valid values: Yes/No
Default value: No

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Temp Index Extent Size(Bytes)


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_TEMP_IND_NXTEXT
Not Used
343996.1

-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Temp Table Extent Size(Bytes)


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_TEMP_TAB_NXTEXT
Not used
343996.1

-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Unit of Measure


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_UNIT_OF_MEASURE
Not Used

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Update Requested Completion Date when


Releasing Reschedules
Profile Code
Profile Option Name
Description

MSC
MSC_UPD_REQ_DATE_REL
Marked as N/A in the Users Guide for all information. Exists in the code for
releasing from Planner Workbench in the Source side code
MRP_AP_REL_PLAN_PUB and defaults to No
The file is $MRP_TOP/patch/115/sql/MRPRELPB.pls
Code review points to this not being used anywhere, even though the value
is determined during the release process.
Introduced in 11.5.9 and exists in 11.5.10
Bug 8603036 logged to get this ported into R12

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3938565
8603036
-1
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Update Use Up Date


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_UPDATE_USE_UP_DATE
This is an internal profile
747628.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Use Enhanced Forward ATP


Profile Code
Profile Option Name
Description

MSC
MSC_ENHANCED_FORWARD_ATP
Use Enhanced Forward ATP -which can combine sources in Supply Chain
ATP.
This works only for ATP based on Planning Data and is not available for ATP
based on Collected Data
12.1.3 Documentation updated with example of this functionality:
See Oracle Global Order Promising Implementation and User's Guide
Release 12.1
Part No. E13378-07 May 2010
pg 4-14 - Enhanced Forward ATP
This example applies to 11.5.10 with latest GOP Rollup patch
R12.0.6 with ATP CU patch 6
12.1.3
CAUTION: This can have significant performance impact as we do multiple
iterations to arrive at an answer for ATP.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8443590
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC: Use FIFO Pegging


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_USE_FIFO_PEGGING
If this profile option is Yes, the planning engine uses FIFO pegging. Not used
in constrained plans without detailed scheduling
368676.1

-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Use Optimization Phase Supply Due Dates for


Pegging
Profile Code
Profile Option Name
Description

MSC
MSC_USE_SCO_DATE
When set to yes, Pegging uses the optimization recommended supply date
for planned orders and scheduled receipts

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6009093
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSC: Use Shipping/Receiving Calendar


Profile Code
Profile Option Name
Description

Note Reference(s)

MSC
MSC_USE_SHIP_REC_CAL
Enables the collection and use of shipping, receiving and transit calendars in
ASCP, GOP, Rapid Planning
Works for both ATP based on Collected Data and ATP based on Planning
Data
Determines whether shipping/receiving/carrier calendars are used for order
promising.
Values are:
+ Yes: Uses the shipping, receiving, and carrier calendars to schedule ship
and arrival dates.
+ No: Uses only the organization's manufacturing calendar to schedule ship
dates at each level.
- EXCEPT for Processing Lead Time for Buy Items which will use 24x7
calendar
845365.1
390531

730061.1
436771.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

845365.1
-1
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Oracle Global Order Promising Implementation and User's Guide
-1
-1
Yes
No
No
Yes
No
No
No
No
Yes
No
No
No
Yes
No
No
No
No
No
Yes

MSC: Use attribute based netting


Profile Code
Profile Option Name
Description

MSC
MSC_USE_ATTR_BASED_NETTING
Use this profile option to control netting in a project manufacturing
environment.

Yes: Planning nets at the reservation level. It respects


pegging level and creates planned orders based on hard
pegging level. It does not respect order modifiers if the
reservation level and hard pegging level are not the same.
With this approach, you can enable priority pegging can be
enabled.

Note Reference(s)
420752.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

No: The planning engine uses customary netting in a project


manufacturing environment.

MSC: VMI Default Query


Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSCX_SCE_DEFAULT_QUERY
Displays default results in the Oracle Collaborative Planning Horizontal View

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5058121
-1
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Value of N for all top/bottom-N reports in


Dashboards
Profile Code
Profile Option Name
Description
Note Reference(s)

MSC
MSC_HUB_TOP_BOTTOM_N_VALUE
It holds the value of N for all top/bottom-N reports in Dashboards.
759571.1
844667.1

Bug Reference(s)
Document References(s)

6755107
-1
-1
-1

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No

MSC: Vertical view default query


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSCX_VERTICAL_VIEW_DEFAULT_QUERY
Used by Oracle Collaborative Planning to determine whether default results
are displayed for the vertical view

Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No

MSC: Wait Time to Obtain Lock on Table/Partition


for Snapshot Delete Worker (in sec)
Profile Code
Profile Option Name
Description

MSC
MSC_LOCK_WAIT_TIME
Time (in seconds) the Snapshot Delete Worker waits to obtain a lock on a
table/partition before aborting.
Releasing plan recommendations through Workbench and running Purge
Plan can cause locks on the table/partition preventing the Snapshot Delete
Worker from obtaining a lock.
If the timer expires, the program prints the following message in the log file:
Unable to obtain a lock on table.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC: Write MBP Flat Files


Profile Code
Profile Option Name
Description

MSC
MSC_WRITE_TO_FLAT_FILES
Profile provide controls whether to flush the Planner concurrent process data
files and setup data files during the plan run. If Yes, the process writes all the
files to the $APPLCSF/out/data
directory.

Note Reference(s)
336724.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
Yes
No
No
Yes
Yes
No
No
No
Yes
No
Yes
Yes
Yes
No
No
No
No
Yes
No
No
No
No
No
No

MSC:ATP Assignment Set


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_ATP_ASSIGN_SET
ATP Assignment Set used for ATP Based on Planning Output
This should be the same assignment set assigned to the ASCP - ATP
enabled plan to provide consistent results.
This will default into the ATP Inquiry form when accessed from Advanced
Supply Chain Planner responsibility.
812964.1
760117.1
290251.1
1059017.1
986625.1

-1
-1
-1
-1
-1
-1
Oracle Global Order Promising Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC:Coll Error Debug Mode


Profile Code
Profile Option Name
Description

MSC
MSC_COLL_ERR_DEBUG

Added in R12.x for debug messages for Data


Collections - Planning Data Pull and ODS Load
and other collections processes.
MRP: Debug mode is still debug profile used for
Refresh Collections Snapshots, but all other
processes now use this profile to set debug level.
Level settings may vary by release:
On (Minimal)
Medium
-- CAUTION - levels below may cause performance
issues. Should usually be set only with DEV
recommendation.
High
High (Verbose)
Dev
List of values available as in 12.1.3.4:
OFF
LOW (Default)
MEDIUM
HIGH
DEV

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning

5514401
5578510
-1
-1
-1
-1
No
No
No
No
No
No
No
No
No
No

Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No

MSC:Coll Performance Debug Mode


Profile Code
Profile Option Name
Description

MSC
MSC_COLL_PERF_DEBUG
Introduced in R12. Helps by adding messaging about performance in the log
files. Valid values are:

Off

Medium

High (Verbose)

CAUTION: Should not be used with MSC:Coll Error Debug Mode set to
Medium or higher unless directed by DEV.
Best to set this profile and have MSC: Coll Error Debug Mode = OFF when
working a pure performance issue
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6722040
5514401
-1
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC:Collect Completed Jobs


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_COLLECT_COMPLETED_JOBS
This profile is used to prevent the collection of remaining requirements for
jobs that are completed when set to No. Jobs may still have requirements for
components that were not issued to the job.
This profile was Introduced in 11.5.10 Collections Rollup #13 and is only
used for Complete or Targeted Refresh of Data Collections
404975.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC:Collect Routing
Profile Code
Profile Option Name
Description

MSC
MSC_COLLECT_ROUTING
Use this profile to instruct the targeted collections process how to collect bill
of material and routing data. Valid values are:

Yes - Collect bill of material and routing data

No: Collect bill of material data but do not collect routing data

This profile option is overridden by profile option


INV: Capable To Promise is ATP/CTP based on
Planning Output.
Do NOT set no if running any Plans in VCP
Applications.
Useful when ATP based collected data is being
used and having very large BOM Routing tables
and it can help performance.
Currently only available in 11.5.10 starting in Data
Collections Rollup #25.
Bugs to Front port to R12 and R12.1 are pending
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6658721
-1
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC:Compute IB Aggregation during Collection


Profile Code
Profile Option Name
Description

MSC
MSC_COMPUTE_IB_AGGREGATE

MSC:Compute IB Aggregation during Collection


Initiallly the Aggregate Information Collection was
made part of Refresh Collection Process.
We have made it a standalone program which can
be run independently of the Refresh Collection
Snapshot process based on value of the profile
option MSC:Compute IB Aggregation during
Collection.
By default ,the Install base aggregation will be
computed during Collection process,
and if the profile option is set to No, then the
Installbase Aggregation can be computed by
running the concurrent program
"Compute Installbase Aggregate Under
Contracts".
To imrove performance we have paralleilized the
computation by introducing concurrent programs
"Installbase Worker" ,
however this program can only be invoked by the
parent program "Compute Installbase Aggregate
Under Contracts".
If this profile option is set to No, then the
concurrent program "Compute Aggre Installbase
under Contract" will not be called during
collections.
So, when the data pull parameter "Install Base
Under Contracts" is set to Yes, we will collect over
the install base under contracts information already
computed at that time.
The user can run the concurrent program
"Compute Aggre Installbase under Contract",

before the collection run so that the collection run


timings are reduced.
Note Reference(s)

Bug Reference(s)

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

12648806
11792946
11932063
11727030
11930028
-1
-1
-1
-1
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC:Criticality Category Set


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_CRIT_CATEGORY_SET
Category Set To Define Criticality

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSC:Prevent Loops when pegging Non-Standard


Jobs
Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSC
MSC_PREVENT_NSJOB_LOOP
Discrete job demands remain unpegged in case of job demands generated
due to Loops in BOM. Valid values are:

Yes - If there exists a non standard job demand for a top


level item in the supply chain bill and the non-standard job
also exists as a valid supply in the plan, ASCP will make the
pessimistic assumption that this could cause a fatal loop in
the pegging and essentially ignore this demand for pegging
purposes. This default setting is recommended strongly to
prevent plan failures due to pegging loops.

No - In the above case, ASCP makes the optimistic


assumption that loops will not exist after pegging and
proceeds to peg supply of the top level item to the nonstandard job demand. This setting should not to be used
unless the user is completely certain that loops will not be
caused based on their pegging related plan and profile
option settings

Default Value - Yes


Available 12.1.1 and upwards
365112.1

4575602
-1
-1
Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC:Release only orders pegging fully to on hand


Profile Code
Profile Option Name
Description

MSC
MSC_REL_ONLY_ONHAND_SUPPLY

Enhancement Bug 4417550 was logged to help


further control how orders can be released.
This is first released in 11.5.10 in ASCP Engine/UI
Rollup # 8 - Ref Note 252108.1 for more
information on the rollup patches for APS Suite
The implementation is described as follows:
1. Implement the functionality at
the Responsibility Level.
-- This is enabled at Site,
Application and Responsibility level
only
-- This is NOT available to set at
the User level
2. This is check ONLY for planned
orders for Make Items - that will
release as WIP jobs or OPM
batches
3. The check is ONLY for first level
of pegging for Buy From or
Transfer From type pegging lines.
Warning:This will not check the
pegging of any Sub-Assemblies
that are in the pegging tree to see
if they components of the Subassembly are pegging to on hand.
4. The message is a Warning and
can be ignored by the user and
order may still be released
Set on APS Destination in a distributed
environment
Currently not supported for Auto-Release planned

orders process, which is launched during planning


Enhancement 6855650 has been logged for this
profile to be enabled for the Auto-Release Planned
orders process.

Note Reference(s)
560587.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6855650
-1
-1
Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC:Retain Released Data


Profile Code
Profile Option Name
Description

MSC
MSC_RETAIN_RELEASED_DATA

When set to Yes, then the data that is inserted into


the MSC%Interface tables during release from the
workbench (Or when Auto-Release Planned
Orders is run) is retained in these tables. ( Also can
effect release from PS application)
Default = No
Primarily used for debugging purposes.
Tables effected:
MSC_SO_RELEASE_INTERFACE
MSC_PO_RESCHEDULE_INTERFACE
MSC_WIP_JOB_SCHEDULE_INTERFACE
MSC_WIP_JOB_DTLS_INTERFACE
MSC_PURCHASE_ORDER_INTERFACE
MSC_SALES_ORDER_INTERFACE
MSC_PO_REQUISITIONS_INTERFACE
This profile is used for release process in E1-VCP
integration

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

12592939
-1
No
No
No
Yes
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSC:SRP PHASE2 ENABLED


Profile Code
Profile Option Name
Description

MSC
MSC_SRP_PH2_ENABLED
Profile for SRP phase2 enable
Special profile to Service Parts Planning and Install Base Under Contracts
integration.
In case of using new Install Base functionality in 12.1.3.3 in Data Collections,
this profile should be set to Yes.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9791058
11785629
-1
-1
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSC:Select Sourcing Rules In ATP Based On


Profile Code
Profile Option Name
Description

MSC
MSC_SOURCING_DATE
From Documentation bug 8423266 logged to get this added to the
documentation.
Available in the latest Users Guide

1 - Sysdate - current default functionality


Sourcing rule effectivity date is based on system date
2 - Request Date - this will check for sourcing effectivity based on the
Request Date or Planning Time Fence Date (whichever is greater)
Example:
Item has 5 days leadtime and ZERO on hand
Item sourced from supplier A on right now
Item sourcing will change on Day 10 to Supplier B
So sourcing rule is setup with supplier A sourcing disabled on Day 9
Sourcing shows supplier B with sourcing starts on Day 10
So Customer A calls today and requests item to ship on Day 20,
SO -- best solution is to use profile with setting Request Date, since you
would need to order the product on Day 14 to arrive on Day 19, then ship on
Day 20.
Supplier B would be chosen for this order.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8423266
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes

MSC_USE_HASH_KEY
Profile Code
Profile Option Name
Description

MSC
MSC_USE_HASH_KEY
This is an internal profile. Should be set to Yes always

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3575822
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSD: AW Tablespace
Profile Code
Profile Option Name
Description

MSD
MSD_TABLESPACE
This profile controls where analytic workspaces are created and stored. New
plans are created in the specified tablespace; existing plans remain in the
tablespace specified at the time of their creation. Changing the tablespace
profile has no effect on existing data.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3900222
-1
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Calculate Planning Percentages


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_PLANNING_PERCENTAGE
This profile option controls the behavior of the planning percentage
calculations. For example, it controls whether the planning percentages can
be calculated from the sales history of options. This profile can prevent
expensive calculations when the user does not want to calculate planning
percentages and just wants to use the existing planning percentages
specified in the enterprise resource planning source to explode the forecast.
556091.1

2930793
-1
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Category Set Name


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_CATEGORY_SET_NAME
This profile option is used to select one category set during the data
collection process. If the user value is left blank, then all categories will be
selected for data collection. Valid values are limited to valid category set
names.
344626.1

4058454
-1
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Client Debugging


Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_CLIENT_DEBUGGING
Used for debugging ODP
789091.1
301936.1

-1
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Conversion Type


Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_CONVERSION_TYPE
This profile option determines what conversion rates are collected from the
General Ledger rates table
419412.1

7530857
-1
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Currency Code


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_CURRENCY_CODE
This profile option designates the base currency used in Oracle Demand
Planning. All revenues are calculated and displayed in this base currency
577726.1

-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Customer Attribute


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_CUSTOMER_ATTRIBUTE
This is a source profile option used to selectively bring the customer names
into Oracle Demand Planning to improve the system performance
217042.1

-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Default DP Scenario


Profile Code
Profile Option Name
Description

MSD
MSD_DEFAULT_DP_SCENARIO
This profile option specifies a demand scenario, which appears as a demand
schedule in the Plan Options window. When you publish the demand
scenario specified in this option, the planning engine launches the
unconstrained plan specified in the profile option MSC: New Forecast Auto
Plan

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2710122
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Enabled Organization for Item Collections


Profile Code
Profile Option Name
Description

MSD
MSD_ITEM_ORG
This profile option allows users to collect relationships for Items in Master
Organization only or All Organizations. This profile option specifies how
Oracle Demand Planning collects Product Family and Product Category
relationships

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4157588
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Excess and Obsolescence, Liability Category


Set Name
Profile Code
Profile Option Name
Description
Note Reference(s)

MSD
MSD_EOL_CATEGORY_SET_NAME
This profile is not used.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5202797
-1
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Include all internal sites within scope of LOB


scoped demand plan
Profile Code
Profile Option Name
Description

MSD
MSD_ISO_CHECK
New Site level profile option named - MSD: Include all internal sites within
scope of LOB scoped demand plan
In R12, we enhanced ODP to support ISOs (Internal Sales Orders). Now the
demand plan
stripping code has been modified to use this profile to decide whether to use
the ISO
enhancement or not.
Value - Yes. (11i Behavior)
All the internal sites are included into the plan even when its org is
inside
the scope of the plan.
Essentially no distinction between internal sites and external sites.
No. (R12 Behavior) Filter out the Internal sites from the plan if its org is already in the
scope of the plan.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD: MAXVALUECOUNT for edges in XWDEVKIT


Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_EDGEMAXVALCOUNT
Used for setting the maximum number of values allowed on an edge for
XWDEVKIT. Used in the ODP Worksheet
359953.1

4725583
-1
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Master Org


Profile Code
Profile Option Name
Description

MSD
MSD_MASTER_ORG
This profile option is used to select a master organization, if there are
multiple master organizations. The item attributes pertaining to the selected
master organization are used by Oracle Demand Planning

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2779954
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: OLAP Directory Alias


Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_DIR_ALIAS
Use this profile to specify the database directory alias used to store the log
files created during the demand plan build process.
470483.1

3826884
-1
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: OLAP Initial Page Pool


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_USER_INIT_PAGEPOOL
This profile specifies an initial minimum memory for planning and manager
sessions and can be optimized for individual users. A value of 4 to 6MB is
generally adequate. The default value is olap_page_pool_size.
363491.1

-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: OLAP Maximum Page Pool


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_USER_MAX_PAGEPOOL
Not used - obsolete
Note.416107.1

-1
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD: OLAP Workflow Page Pool


Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MAX_WF_MAX_PAGEPOOL
This profile specifies the memory footprint for workflow initiated Oracle
Demand Planning sessions. The default value is 64MB.
363491.1
285489.1
286729.1

-1
-1
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: One Step Collection


Profile Code
Profile Option Name
Description
Note Reference(s)

MSD
MSD_ONE_STEP_COLLECTION
This profile option controls the number of steps in the data collection process
332545.1

Bug Reference(s)
Document References(s)

2930793
-1
-1

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Two-Level Planning


Profile Code
Profile Option Name
Description

MSD
MSD_TWO_LEVEL_PLANNING
This profile allows you to forecast demand at product family level on the
basis of sales histories of member items. You can collect all the product
family members and their sales histories regardless of the forecast control as
long as the product family forecast control is 'Consume' or 'Consume &
Derive' and the planning method for product family as well as members is not
set to 'Not Planned'. This is achieved by setting the profile value to: Collect
all family members and their sales histories. The default profile value,
Exclude family members with forecast control 'None' enforces the existing
behavior that is, only 'Consume' or 'Consume & Derive' product family
members are collected.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3009964
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Use Classic Even Allocation


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_USE_EVEN_ALLOC
This profile allows you to determine the allocation method used when an
allocation basis does not exist. You can allocate evenly down the time
dimension and use "first" allocation for other dimensions when an allocation
basis is not available. Demand Planning uses the First Child allocation
method by default, unless you enable the MSD: Use Classic Even Allocation
profile.
436673.1

4577092
-1
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Use Classic Worksheet


Profile Code
Profile Option Name
Description

MSD
MSD_USE_CLASSIC_WORKSHEET
To force recalculations between worksheet edits, enable the MSD: Classic
Worksheet profile option. This option enforces consistency across hierarchy
levels, but may decrease performance. in 11.5.10 default is classic, in R12
default is simple. Not applicable to planning percentages worksheet

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6137940
-1
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD: Worksheet Automatic resize


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_WKS_AUTO_RESIZE
Defines whether the worksheet should be automatically resized when you fill
cells

No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD:View Scope measures are editable


Profile Code
Profile Option Name
Description

MSD
VIEW_SCOPE_MEAS_EDITABLE
The measures not included in the Assignment scope, but included in the
View scope, can be viewed but not edited. Valid values are:

Y - Yes, the default behaviour

N - No

Default Value - Y
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6367799
-1
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSD_DEM: Calculate Planning Percentage


Profile Code
Profile Option Name
Description

MSD
MSD_DEM_PLANNING_PERCENTAGE
Controls the planning percentage calculation for options and option classes.
Use this profile option to specify upon what entities to calculate planning
percentages. This occurs when system parameter
CTO_PLANNING_PERCENTAGE_CHOICE instructs Oracle Demantra to
calculate planning percentages.
Do not change the setting of this profile option after the initial download or
invalid combinations may result:
+ The typical reason for changing this value is to correct a setup error.
+ In that case, delete the invalid combinations and re-download. See
Implementation Considerations.
The default is Null. Valid vales are:
+ Yes for Consume & Derive Options and Option Classes: Include the sales
history of options and option classes
+ Yes for Consume & Derive Options only: Include the sales history of
options to model and removes option classes. Use it for assemble to order
situations.
+ Yes for all the Options and Option Classes: Include the sales history of
options and option classes including optional components of forecastable
product families that have Forecast Control None.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Note: It is recommended to set this parameter to Yes, for All Options and
Option Classes before running shipping and booking history for Configure to
Order
975066.1

-1
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Category Set Name


Profile Code
Profile Option Name
Description
Note Reference(s)

MSD
MSD_DEM_CATEGORY_SET_NAME
This profile defines the Item to Category rollups in each instance.
549565.1

Bug Reference(s)
Document References(s)

8235032
-1
-1

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Conversion Type


Profile Code
Profile Option Name
Description

MSD
MSD_DEM_CONVERSION_TYPE
This profile determines which currency conversion rates are collected from
the General Ledger tables Source side profile

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5969081
-1
Yes
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Currency Code


Profile Code
Profile Option Name
Description

MSD
MSD_DEM_CURRENCY_CODE
This profile designates the Demand Management base currency. Destination
side profile

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5959651
-1
Yes
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Customer Attribute


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_DEM_CUSTOMER_ATTRIBUTE
This is a source profile option used to selectively bring the customer names
into Demand Management to improve system performance. Source side
profile
726444.1

6926188
-1
-1
Yes
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Data Profile for Price Lists


Profile Code
Profile Option Name
Description

MSD
MSD_DEM_PRICE_LIST_PROFILE
Set this profile to import integration data profile for price lists. Destination
side profile

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6450646
-1
Yes
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Debug Mode


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_DEM_DEBUG_MODE
When set to 'Yes', this profile is used to print debug information to the output
file of the concurrent request. Destination side profile
741464.1

-1
Yes
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Enable Supply Plan Download for work


orders
Profile Code
Profile Option Name
Description

MSD
MSD_DEM_ENABLE_SUPPLY_PLAN_WO
As of 1/15/12 - This is a new profile options added in 12.1.3.6 for Integration
of CMRO and EAM with Demantra.
Important - This feature is under CA and is meant for a specific customer
only. For all other customers, they should not use these profiles till the
feature is made GA.
Profile to determine whether supply plan download will bring in data by work
order attributes or not
The profile will be used as a switch between the existing SOP integration
design and the new design to bring in data striped by work order attributes.
Possible Values a. No - Existing SOP Integration
b. Yes - New SOP Integration with support for work orders
Default Value - No.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
Yes
Yes
No
No
No
No

MSD_DEM: Explode Demand Method


Profile Code
Profile Option Name
Description

MSD
MSD_DEM_EXPLODE_DEMAND_METHOD
This profile option applies to Demantra integration with Service Parts
Planning.
This profile option specifies which historical data is used to determine the
failure rate.
The options are Field Service or Depot Repair & Field Service.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Fiscal Calendar


Profile Code
Profile Option Name
Description

MSD
MSD_DEM_FISCAL_CALENDAR
All the fiscal calendars chosen in the calendar setup list will be available
in the List Of Values for this profile.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6278515
-1
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Host URL


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_DEM_HOST_URL
Set this profile to the Oracle Demantra Application Server Host Name, Port
Number and Application Name. This profile is used to invoke Oracle
Demantra URLs from the E-Business Suite applications. Destination profile
431301.1

6497910
-1
-1
Yes
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Include Dependent Demand


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_DEM_INCLUDE_DEPENDENT_DEMAND
Use this profile option to specify whether the collections process should
include configure to order structures, demand, and history. Valid values are:
+ Yes: Include configure to order structures, demand, and history
+ No: Do not include configure to order structures, demand, and history. This
is the default
975066.1

-1
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Include organization in CMR Data Load


Profile Code
Profile Option Name
Description

MSD
MSD_DEM_INCLUDE_ORG_CMRO_DATA
This is a new profile options added in 12.1.3.6 for Integration of CMRO and
EAM with Demantra.
As of 1/15/12 - Important - This feature is under CA and is meant for a
specific customer only. For all other customers, they should not use these
profiles till the feature is made GA.
In 12.2 as well as 12.1.3.6, even though the code is available, it is
hidden/disabled in UI out of the box.
A new planning side profile to specify whether organization should be a
dimension for the data loaded to SPF GL or not.
Possible Values a. No
b. Yes
Default Value - No.
Profile to determine whether to include organization in cMRO data load or
not.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
Yes
Yes
No
No
No
No

MSD_DEM: Master Org


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_DEM_MASTER_ORG
This profile defines the Product Family to which an Item rolls up. Source side
profile

Yes
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Maximum seeded units available for


price lists
Profile Code
Profile Option Name
Description

MSD
MSD_DEM_MAX_PRL
This profile determines the number of slots available for price lists in Oracle
Demantra. Destination side profile

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5879252
-1
Yes
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Schema
Profile Code
Profile Option Name
Description

MSD
MSD_DEM_SCHEMA
Set this profile value to the database schema name where the Oracle
Demantra schema has been installed. Destination side profile

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8361879
-1
Yes
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Simulation Set Name


Profile Code
Profile Option Name
Description

MSD
MSD_DEM_SIMULATION_SET_NAME
This is a new profile options added in 12.1.3.6 for Integration of CMRO and
EAM with Demantra.
Important This feature is under CA and is meant for a specific customer only. For all
other customers, they should not use these
profiles till the feature is made GA.
In 12.2 as well as 12.1.3.6, even though the code is available, it is
hidden/disabled in UI out of the box.
A new planning side profile to specify the simulation set from which repair
cost of items will be collected into Demantra.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
Yes
Yes
No
No
No
No

MSD_DEM: Source Instance for Global Forecast


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_DEM_SR_INSTANCE_FOR_GLOBAL_FCST
'MSD_DEM: Source Instance for Global Forecast' was created to allow user
to specify the instance where global forecast will be uploaded into ASCP.
850484.1

-1
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Truncate Staging Table


Profile Code
Profile Option Name
Description

MSD
MSD_DEM_TRUNCATE_STG_TABLE
The profile should be set to No, if both Demantra and SRP are used
together.
No additional information available - logged documentation bug 12685689

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Two-Level Planning


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_DEM_TWO_LEVEL_PLANNING
This profile enables demand forecasts at the Product Family level on the
basis of sales histories of member items. Destination side profile.

Yes
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: UOM for fleet flight hours


Profile Code
Profile Option Name
Description

MSD
MSD_DEM_FLEET_FLIGHT_HOURS_UOM
This is a new profile options added in 12.1.3.6 for Integration of CMRO and
EAM with Demantra.
Important This feature is under CA and is meant for a specific customer only. For all
other customers, they should not use these
profiles till the feature is made GA.
In 12.2 as well as 12.1.3.6, even though the code is available, it is
hidden/disabled in UI out of the box.
A new source side profile to specify the UOM/counter that will be used to
identify the entry for fleet flight hours in the AHL_FLEET_UTILITZATION
(Product CMRO, Entity - Fleet Utilization Data) table.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
Yes
Yes
No
No
No
No
No
Yes
Yes
No
No
No
No

MSD_DEM: Use new Site code format


Profile Code
Profile Option Name
Description

MSD
MSD_DEM_SITE_CODE_FORMAT
Determines whether new Site code format is used or not.

Note Reference(s)

Created Doc bug 12685703


1312493.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_DEM: Version
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_DEM_VERSION
Created documentation bug 12685733 .
1061331.1

-1
No
No
No
No
No
No
No
No
No
No
Yes
No
No
No
No

MSD_SPF: History basis for Failure Rate


computation
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_SPF_FAILURE_RATE_HIST_BASIS
This profile is used to specify the history data that should be used for failure
rate computation
1225993.1

-1
No
No
No
No
No
No
No
Yes
Yes
No
No
No
No
No
No
Yes
No
No
No
No

MSD_SPF: Organization containing generic BOM for


Service Parts Forecasting
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSD
MSD_SPF_MASTER_ORG
This profile is used to specify the master organization for service
organizations which will have the generic BOM definition
This is for Service Parts Planning forecasting and explosion.
Similar to profile used for ASCP planning - MSC: Organization containing
generic BOM for forecast explosion - which is used for ASCP planning.
1225993.1

-1
No
No
No
No
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Activity Selection Window (in Days)


Profile Code
Profile Option Name
Description

MSO
MSO_SDS_SELECTOR_WINDOW
This profile option specifies the number of days over which the
planning engine groups activities that are candidates for scheduling.
The larger the number, the greater the chance of finding an activity
that can be scheduled with another activity of the same setup type.
Making this number too large might result in demand priorities
not being fully respected while scheduling.
Valid values are any number. The profile option is used in Days.
Default value: 7

Note Reference(s)
415276.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8538729
-1
-1
No
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Additional Demand Slices for Shared Supply


Rescheduling
Profile Code
Profile Option Name
Description

MSO
MSO_MAX_NUMBER_OF_RESCHEDULES
Controls the maximum number of slices to which supply can be rescheduled.
VAlid values are:

Between -1 and maximum number of slices.

Controls the maximum number of slices to which supply can be rescheduled.


Supply is not rescheduled after this maximum even when demand will be
delayed. Possible values include:

-1 - Reschedule to last slice

0 - Does not reschedule.

For example, if a supply pegs to demand in slice 2, 3, 4, 5, and 6, and the


parameter value is 2, supply will reschedule if needed in slice 3 and 4
(rescheduled 2 times, in slice 3 and 4) and will not reschedule in slice 5 and
6.
If the plan planning mode is Constrained (Without Detailed Scheduling), the
planning engine does not use this profile option.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Default Value - 0
739561.1
952924.1
726610.1
747739.1

-1
-1
-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Allow Partial Demand Completion


Profile Code
Profile Option Name
Description

MSO
MSO_PARTIAL_DEMAND_COMPLETION
Enables supply orders to individually schedule for partial satisfaction of a
demand when demand is split across several supply orders. Valid values
include:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

All End Demands - Enable Partial Demand Satisfaction for all


independent demands (forecasts,sales orders, and MDS
entries).
Sales Orders: Enable Partial Demand Satisfaction for all
Sales Order demand only.
None: Schedules all supplies to coincide with completion
date (latest supply date) to meet demand.

This functionality can be enabled for all independent demands or only for
Sales Orders.
If the plan planning mode is Constrained (Without Detailed Scheduling), the
planning engine only uses this profile option if its value is All End Demands.
Default Value - None
458693.1

-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Allow Schedule Gaps for Shared Supplies


Profile Code
Profile Option Name
Description

MSO
MSO_ENHANCED_RIGHT_JUSTIFY
This profile option controls the scheduling of shared supplies (scheduled
receipts, firm planned orders, and planned orders with multiple demands
pegged to them). Valid values are:

Yes - When scheduling shared supplies, the shared supply is


moved to the right (moving the schedule date later) during
the final scheduling step (to coincide with the start time of
downstream supplies) if it would make one of the pegged
demands late or later. The shared supply schedule is always
right justified if it does not make any pegged demands late or
later. When a lower-level shared supply is scheduled for the
highest priority demand pegged to it, there may be a gap
between the shared supply end date and the start date of the
next downstream supply. By not right justifying it, it is more
likely to be on time for the lower priority demands in later
demand slices which are also pegged to it. Before selecting
Yes, consider the setting for MSO: Additional Demand Slices
for Shared Supply Rescheduling. If this profile is not 0,
shared supplies may be rescheduled and this profile option
does not need to be Yes. For example, Demand A with
priority 100 and Demand B with priority 500 are in different
slices. If the shared supply is late for Demand B, it may still
be rescheduled to be on time depending on available
capacity and the number of additional demand slices in
which it is scheduled. If MSO: Additional Demand Slices is 0
and this profile option is Yes, the planning engine does not
right justify the shared supply due date; the shared supply
might still be on time for demand B even though it is not
rescheduled in a later slice.

No - When scheduling shared supplies and moving them to


the right (moving the schedule date later), the planning
engine does not consider demands in other slices that are
not yet unscheduled but pegged to this supply. This yields a
schedule with fewer gaps but at the expense of potentially
more late demands.

This is a user level profile option.


Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No

Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No

MSO: Allow Simultaneous Resource To End At


Different Time
Profile Code
Profile Option Name
Description

MSO
MSO_SIMULTANEOUS_RESOURCE_OVERLAP_MODE

Yes/No - Default = No
When scheduling simulateous resources, value of
Yes can allow these resources to finish at different
times. This can cause different resource
consumption. Yes may be required when resources
are available with different shift times in order to
get reasonable plan results.
No documentation on this profile.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

837834.1

-1
No
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Allow Simultaneous Resources to End at


Different Times
Profile Code
Profile Option Name
Description

MSO
MSO_ALLOW_SIM_RES_TO_END_DIFF_TIMES
This profile is NOT USED. We have two profiles with same name
MSO_SIMULTANEOUS_RESOURCE_OVERLAP_MODE - MSO: Allow
Simultaneous Resource To End At Different Time
MSO_ALLOW_SIM_RES_TO_END_DIFF_TIMES - MSO: Allow
Simultaneous Resources to End at Different Times
-- this profile has 's' at end of name - Times vs Time
-- this is description from application - Relaxes the constraint the the principal
and simultaneous resources should start and end at the same time
Available in 12.1.1 and upwards

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4566790
-1
No
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Allow early builds to consume existing


supplies of phased-out components and sources
Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SCO_USE_EXIST_PHASEOUT_SUPP
Allow early builds to consume existing supplies of phased-out components
and sources
1462299.1

7678394
-1
-1
No
No
No
Yes
No
No
Yes
Yes
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No
No
No
No
No

MSO: Alternate Process Penalty


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_ALT_PROCESS_PENALTY
Specifies weight for alternate process objective in optimization. Valid values
are:

Integer > 0

This is an internal value.


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Alternate Resource Penalty


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SCO_ALT_RESOURCE_PENALTY
Specifies weight for alternate resource objective in optimization. Valid values
are:

Integer > 0

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Alternate Resource Selection Method


Profile Code
Profile Option Name
Description

MSO
MSO_SDS_ALTRES_SELECTION
Valid values: (1) Rank of Alternate (2) Setup Type Match

If Rank of Alternate, ASCP will prefer to load the primary


resource if it is available even if it means incurring a setup
that could have been avoided by going to the alternate.

If Setup Type Match, ASCP will prefer the alternate that is


the best option from a setup minimization perspective. If all
alternates are equal from a setup perspective, then ASCP
chooses the alternate based on rank.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Alternate Source Penalty


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SCO_ALT_SOURCE_PENALTY
Specifies weight for alternate source objective in optimization. Valid values
are:

Integer > 0

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Apply Windows for Firm Scheduling


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_APPLY_WINDOW_IN_FORWARD_SCHEDULE
Currently not used by HLS

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Avoid non working days for Buy/Transfer


order dates
Profile Code
Profile Option Name
Description

MSO
MSO_AVOID_NON_WRKNG_DAY_BUY_AND_TFR
This profile option applies only when profile option MSO: Use Shift definitions
when scheduling lead-times is No. Valid vales are:

Yes - The planning engine avoids placing the ship, dock, due
dates of buy and transfer orders on non-workdays according
to the appropriate calendar.
No: The planning engine does not schedule buy and transfer
orders with regard to the appropriate calendar.

This profile option does not govern the placement of order dates. If profile
option MSO: Use Shift definitions when scheduling lead-times is Yes, the
planning engine assumes accurate shift timing.
Note Reference(s)
853822.1
1331154.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Barrier Optimizer Algorithm Choice


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_BARALG
This profile indicates which starting point algorithm the planning engine when
it uses the barrier algorithm to solve an optimization problem. It applies only
when multiple threads are used in optimization.
Values: 0, 1, 2, or 3 Default value: Null (interpreted as 0)

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3511063
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Batching Precision


Profile Code
Profile Option Name
Description

MSO
MSO_BATCHING_TYPE
Documentation bug 9669424 has been created to include this profile option
in the ASCP User Guide.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8899964
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Big M Value for SCO


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SCO_BIG_M
No longer used in ASCP

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: CPLEX Crash Parameter


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_CRAIND
Determines how objective coefficients are used to select basis.
Values: -1, 0, and 1
Default value: See 'Automatic Calculations, page A-1 of the R12.1 ASCP
User Guide.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: CPLEX Refactor Rate


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_REINV
Specifies the value of the parameter to control the refactor rate.
Values: Integer > 0.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3964120
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: CPLEX Scaling Factor


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_SCAIND
Contains the scaling factor in the Planning Engine.
Values are -1, 0, 1.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: CPLEX messages to screen indicator


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_SCRIND
Used for Debugging issues for Supply Chain Optimized Plans
Which means plans that have Decision Rules OR Optimization set. Usually
specified by Development when additional information in the log file is
required for debugging purposes. Valid values: zero = Off and 1 = On
Available in 12.1.1 and upwards

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7424573
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Calculate Constraint Exceptions


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_CALCULATE_CONSTRAINT_EXCEPTIONS
Determines whether constraint exceptions are calculated for plans with
Enforce Capacity Constraints selected. The planning engine issues an
"Order lead time constraint exception" when the lead-time of an order is the
cause for a demand being satisfied late or a "Requirement lead time
constraint exception" when the lead time of a resource requirement is the
cause for a demand satisfied late or a "Material constraint exception" when a
demand due date needs to be pushed out due to either a "Lead time
violation" or a "Supplier capacity constraint" and if profile option MSO:
Calculate Constraint Exceptions is Yes. Values are Yes or No.
214041.1

-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
No
No
No
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Capacity Units Recalculation Threshold


Profile Code
Profile Option Name
Description

MSO
MSO_RESOURCE_CONSUMPTION_PERCENTAGE
Valid values are:

Any Value between 0 and 1

The planning engine schedules supplies in two phases:

Backward schedule - From demand due date to see if


demand can be met on time.

Forward schedule: If the backward schedule results in a late


demand, the forward schedule from the plan start date meet
demands with minimum lateness.

At the end of the forward schedule phase, the planning engine adjusts the
schedule to remove gaps between supplies (right justification). It may move
a supply to occur at a time where there are more resource units available
that there were in its previously scheduled time.
If this profile option is 1, the planning engine considers assigning more
resource units to the supply. For example, this profile option is 0.5. The
planning engine considers changing the number of resource units if the
current capacity units value is less than 0.5 * Max assigned units on the
routing for the item.
If this profile option is 0, the planning engine does not consider assigning
more resource units.
This is a user level profile option.
If the plan planning mode is Constrained (Without Detailed Scheduling),
the planning engine does not use this profile option.
Default Value - 0
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8745009
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Check Redundant Constraints


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_DEPIND
Specifies location and removal of redundant constraints.
Values: 0 and 1
Default value: See 'Automatic Calculations, page A-1 of the R12.1 ASCP
User Guide.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Choice of supply for substitution


Profile Code
Profile Option Name
Description

MSO
MSO_SUPPLY_FOR_SUBSTITUTE
Determines which supplies are considered by the Planning Engine for
substitution.
Determines which supplies are considered by the Planning Engine for
substitution.
Valid values are:
All Supplies (1)
Oracle Advanced Supply Chain Planning takes supplies belonging to
substitute items even when there is demand for substitute items. Demand
priorities drive the allocation.
Excess supplies (2)
Oracle Advanced Supply Chain Planning takes supplies belonging to
substitute items only if it finds that the supply
from the substitute item is in excess. Oracle Advanced Planning performs
regular netting logic within the Substitution Window
and find that excess can be offered for substitution. The native demand
satisfaction has priority only within the Substitution Window. After the
Substitution Window demand priorities drive the substitution.
Oracle Order Promising does not honor this profile option. Oracle Order
Promising always honors native demand satisfaction logic

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

B31553-02
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Component offset logic for optimization


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_COMP_OFFSET_LOGIC
Introduced in 11.5.10 - ASCP Engine/UI rollup #12
Works in tandem with MSO: Postpone Use of Alternates to Latest Possible
Time = Yes

1: Component requirement date is put one day before


assembly start date.

2: Component requirement date is put on the same date as


assembly start date

3: if assembly lead time =0, same result as 2. if assembly


lead time >0, same result as 1

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5018283
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
Yes
Yes
No
Yes
No
Yes
No
No
No
No
No
No
No

MSO: Consume Existing Purchase Order Supplies


in First-In-First-Out Sequence During Component
Substitution
Profile Code
Profile Option Name
Description

MSO
MSO_SCHEDULE_PO_IN_FIFO

Consume Existing Purchase Order Supplies in


First-In-First-Out Sequence During Component
Substitution
Introduced on top of EBS 12.1.2 in one-off patch
9238752 (included in VCP 12.1.2.1)
In base release of EBS 12.1.3
Bug 8238752 notes the following:
For enabling the Consume PO supplies
in FIFO sequence feature the following
profiles needs to be set.
1.MSO: Component offset logic for
optimization = 2
2.MSO: Schedule PO in FIFO = Yes
3.MSC: Use Optimization Phase Supply
Due Dates for Pegging - Yes
4.MSO: Additional Demand Slices for
Shared Supply Rescheduling -1
5.MSO: Net All Firm Supplies Before
Creating Planned Order - All Supply
Types
This enhancement was done for a
particular customer. They also used
some customization scripts for this
solution to work.
Default Value=No

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning

9238752
-1
No
No
No
Yes
No
No
Yes
Yes
No

Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No

MSO: Continuous transfer across organizations


Profile Code
Profile Option Name
Description

MSO
MSO_MTQ_ACROSS_ORGS
Allows you to model continuous or non-continuous transfers across
organizations. Valid values are:

Yes - Allows continuous transfers across organizations.

No: Allows discrete, incremental or non-continuous transfers


across organizations.

This feature can also be set at the item/organization level using the
Continuous Inter-Org Transfers item attribute. The value specified for the
item attribute overrides the profile option setting. If the plan planning mode
is Constrained (Without Detailed Scheduling), the planning engine does
not use this profile option.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7436622
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Convergent Supplies Consumption Pattern


Profile Code
Profile Option Name
Description

MSO
MSO_DEMAND_SPLIT
Allows you to fulfill a demand in series or in parallel from multiple supplies
from suppliers and/or other organizations. Valid values are:

Series - Demand is satisfied in series from multiple supplies.

Parallel - Demand is satisfied in parallel from multiple


supplies.

Default Value - Parallel


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Convergent Supplies Consumption Pattern


for Inter-Org and Supplier Sourced orders
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_INTER_ORG_DEMAND_SPLIT
Allows you to fulfill a demand in series or in parallel from multiple supplies
from suppliers and/or other organizations.
Valid Values are:

Series - Demand is satisfied in series from multiple supplies.

Parallel - This is the default value.Demand is satisfied in


parallel from multiple supplies.

Default Value: Parallel


For supplier sourced orders, use profile option MSO: Convergent Supplies
Consumption Pattern for Inter-Org and Supplier Sourced Orders.
If the plan planning mode is Constrained (Without Detailed Scheduling), the
planning engine does not use this profile option.
726610.1

-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Convergent Supplies Consumption Pattern


for Intra-Org Sourced orders
Profile Code
Profile Option Name
Description

MSO
MSO_INTRA_ORG_DEMAND_SPLIT
Allows you to satisfy a demand in series or in parallel from multiple supplies
in the same organization.
Values are:

Series - Demand is satisfied in series from multiple supplies.

Parallel - This is the default value. Demand is satisfied in


parallel from multiple supplies.

If a component is fed by orders from multiple


organizations, the value of profile option
MSO:Convergent Supplies Consumption Pattern
for Inter-Org and Supplier Sourced orders
overrides the value of this profile option.
If the plan planning mode is Constrained (Without
Detailed Scheduling), the planning engine does not
use this profile option.
Defaut value: Parallel
Note Reference(s)

726610.1

Bug Reference(s)

9310030
9147919
-1
-1
-1
-1

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center

Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No

Global Order Promising

No

MSO: Cost Roll-up incremental factor


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_COST_ROLLUP_INCR_FACTOR
ASCP Userguide Profile Name: MSO: Incremental factor of internal cost
roll up
This profile option controls the cost increments used by the internal cost roll
up in Oracle Advanced Supply Chain Planning. The cost calculation is:
SUM across all components for the assembly [K * Cost of a component *
(Usage of the component for the assembly + 0.01)].
K is the value that you set in this profile option.
Oracle recommends a minimum value of 1.
Valid values are:

Number

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Default Value - 1
555016.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Create Aggregate Supply for Unsatisfied


Demands within Planning Time Fence
Profile Code
Profile Option Name
Description

MSO
MSO_AGG_SUP_FOR_DMD_IN_PTF

Introduced in ASCP Engine/UI rollup #33 for


11.5.10
Front ported to R12 in CU5 patch 7270650
Fixed in VCP Cum patch 12.1.3.1 and above
The Memory Based Planner (MBP) used to create
supplies for unsatisfied demands inside PTF on
respective dates after considering the FDS. Later
on those supplies were moved to PTF date,
resulting in more than one supply on PTF date.
This would be wrong for some set up. So, we made
the code changes to create single supply for
unsatisfied demands in PTF.
This is now controlled by this profile.

Yes, then one supply is created for unsatisfied demands on


the PTF date if all of the following conditions are satisfied:

Plan is not constrained with


Decision Rules
Plan is not optimized.

No, more than one supply may be created for unsatisfied


demands on the PTF date.

Available in 12.1.1 and upwards


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning

7294117
-1
Yes
No
No
Yes
No
Yes
No
No
No
No
No
No

Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No

MSO: DS Scheduling Window


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_DETAILED_SCHEDULING_WINDOW
This was introduced in R12 for DS. It is not being used.

No
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Default Forecast Priority


Profile Code
Profile Option Name
Description

MSO
MSO_DEFAULT_FORECAST_PRIORITY
Contains default priority value for forecasts and is used by the Scheduling
Engine to determine when to schedule the forecast. Can be defined at the
site level. Valid values are:

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Integer > 0.

Default Value - 100000.


147220.1
296941.1

-1
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Default Idle Time Tolerance (Hours)


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_IDLE_TIME_TOLERANCE
No Documentation on this profile.

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Default Resource Sequencing Window (in


Days)
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SETUP_CYCLE_FOR_HLS_SDS
After the planning engine select an unscheduled activity from the activity
selection window specified by MSO: Activity Selection Window (Days), this
profile option specifies the number of days from the pegged demand date
over which the planning engine can look for another activity of the same
setup type to schedule the activity with and achieve a good sequence on the
resource. This profile option
number can be overridden by resource level settings made in the
Departments: Resources screen in the source system. The large this
number, the longer
the time spent by the resource on a setup type before changing over to
the next setup type.
Valid values: any number
Default value: 7 (days)
415276.1

-1
No
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Default Sales Order Priority


Profile Code
Profile Option Name
Description

MSO
MSO_DEFAULT_SO_PRIORITY
Contains default priority value for sales orders. Used by the Scheduling
Engine to determine when to schedule a sales order. Can be defined at the
site level. Valid values are:

Integer > 0.

Default Value - 10000.


Note Reference(s)
296941.1
147220.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Default Timestamp Safety Stocks


Profile Code
Profile Option Name
Description

MSO
MSO_DEFAULT_TIMESTAMP_SFTSTCK
The planning engine uses this profile option value to determine when safety
stock supplies are due. The timestamp value applies to the safety stock
requirements from Oracle Inventory, Oracle Inventory Optimization, Oracle
Material Requirements Planning, and Oracle Advanced Supply Chain
Planning. Valid values are:

Beginning of Day - Supplies must be available at 00:00.Set


this option if you want to use timestamps that match safety
stock requirements from Oracle Inventory Optimization.
End of Day: Supplies must be available at 23:59.Set this
option if you want to use timestamps that match safety stock
requirements from Oracle Inventory or Oracle Material
Requirements Planning.

Default Value - Beginning of Day


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No

MSO: Default Timestamp for Forecasts


Profile Code
Profile Option Name
Description

MSO
MSO_DEF_TIME_FCST
Determines the forecast timestamps that ASCP uses to plan. The timestamp
denotes the time by which supplies to meet the demand must be available to
be considered on time
E - End of Day (23:59)
B - Beginning of Day (00:00)
R - Retain Timestamp of Salesorders

Note Reference(s)

1331154.1
Bug Reference(s)

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6273866
3198606
7460229
3573179
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
-1
-1
-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
Yes
No
No
No
No
No

MSO: Default Timestamp for Sales Orders


Profile Code
Profile Option Name
Description

MSO
MSO_DEF_TIME_SO
This profile option determines the sales order line timestamps that Oracle
Advanced Supply Chain Planning uses to plan.
The timestamp denotes the time by which supplies to meet the demand must
be available to be considered on time: Values are:

B - Beginning of Day: Supplies must be available at 00:00.


E - End of Day: Supplies must be available at 23:59.
R - Retain Sales Order Timestamps: Supplies must be
available at the timestamp on the sales order line.

The sales order demand due timestamp does not affect forecast
consumption because forecast consumption is done in daily buckets.
This profile option does not apply to forecasts.
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4120214
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Default Value for Maximum Acceptable Days


Early
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_DEFAULT_MAX_EARLY_DAYS
No information on this profile

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Delay Fulfillment of Small Demands


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_RESPECT_SUPPLY_TOLERANCES
Use this profile option to enable the planning engine to delay fulfilling a small
demand until it has a later larger demand. Valid values are:

Yes - set the item attribute Unsatified Demand Factor on


each item whose small demands you want delayed.

No

Default Value - No
1068297.1
749448.1

-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Demand Size Tolerance Before Splitting


Planned Orders
Profile Code
Profile Option Name
Description

MSO
MSO_SPLIT_PO_THRESHOLD
Creates a threshold percentage that causes Planned Orders to split prior to
scheduling (if the remaining unallocated quantity of a planned order is
greater than the remaining unallocated quantity of the pegged demand). Not
used if order modifiers exist for an item and not used in a project planning
environment. Valid values are:

Positive decimal quantities (.5 is interpreted as 50%).

If the plan planning mode is Constrained (Without Detailed Scheduling), the


planning engine does not use this profile option.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Default Value - NULL


739561.1
1068297.1

-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Demand Type Priority


Profile Code
Profile Option Name
Description

MSO
MSO_DEMAND_TYPE_PRIORITY
Appears to be unused according to the Oracle Advanced Supply Chain
Planning Implementation and Users Guide

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4573393
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Demand Window Size


Profile Code
Profile Option Name
Description

MSO
MSO_DEMAND_WIN
During priority pegging, demands are sorted based on the demand priority
within the demand window. After these demands are fully pegged, Oracle
Advanced Supply Chain Planning sorts all demands in the next window by
priority. This is stated as the number of calendar days including nonworkdays. With a value of 10, the first demand window is between the start
date of the plan or the first demand date +10 days. Valid values are:

Integer >= 0

Default Value - NULL (1)


Note Reference(s)

Bug Reference(s)

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8264328
2764894
8264323
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Disable Inference of Item Substitution


Relationship
Profile Code
Profile Option Name
Description

MSO
MSO_NO_INFER_IN_ITEMSUBST
Use this profile option to instruct the planning engine whether to infer end
item substitution relationships. Valid values are:

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes - Do not infer item substitution relationships


No/Null - Do infer item substitution relationships

Default Value - Null


1068297.1

6901454
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Divergent Supply Feeding Pattern


Profile Code
Profile Option Name
Description
Note Reference(s)

MSO
MSO_SUPPLY_SPLIT
Not used.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4573393
-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Divergent Supply Feeding Pattern for InterOrg and Supplier Sourced orders
Profile Code
Profile Option Name
Description

MSO
MSO_INTER_ORG_SUPPLY_SPLIT
Allows you to fulfill multiple downstream demands in parallel or in series by a
supply from another internal organization.
Values are:

Series With MTQ Only - This is the default value. A supply


always feeds multiple demands in series when a
corresponding MTQ has been specified.

Series - Supply feeds multiple demands in series.

If the plan planning mode is Constrained (Without


Detailed Scheduling), the planning engine does not
use this profile option.
Default Value: Series With MTQ Only
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Divergent Supply Feeding Pattern for IntraOrg Sourced orders


Profile Code
Profile Option Name
Description

MSO
MSO_INTRA_ORG_SUPPLY_SPLIT
Allows you to fulfill multiple downstream demands in parallel or in series by a
supply in the same organization.
Values are:

Series With MTQ Only - This is the default value. A supply


always feeds Multiple demands in series when a
corresponding MTQ has been specified.

Series - Supply feeds multiple demands in series.

If the plan planning mode is Constrained (Without Detailed Scheduling), the


planning engine does not use this profile option.
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8675345
9147919
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Dual Simplex Parameter


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_DPRIIND
Gradient parameter for dual simplex.
Values: 0, 1, 2, 3, and 4
Default value: See 'Automatic Calculations, page A-1 of the R12.1 ASCP
User Guide.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: EDD Demand Cutoff Priority


Profile Code
Profile Option Name
Description

MSO
MSO_EDD_DEMAND_CUTOFF_PRIORITY
For an (ECC) plan, we can Enforce Due Dates (EDD) for some sales order
demand based on priority
So if you have sales order priorities, and want all priority 1 and 2 to be
planned as EDD, then set the profile value = 3
This will override constraints, and plan these orders as EDD.
This can cause overloads in resources and also for supplier capacity. This is
a hidden profile in 11.5.10, but can be defined manually in Application
Developer
In R12, this is seeded profile.
This is available in 12.1.1 and upwards as well.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4572101
-1
Yes
No
No
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: EDD Scheduling Window Control


Profile Code
Profile Option Name
Description

MSO
MSO_EDD_SCHEDULING_WINDOW_CONTROL
This profile option is applicable to constrained plans with enforce demand
due dates. The planning engine calculates an actual scheduling window for
each resource activity and supply. Valid values are:

Number between 0 and 1

The actual window is defined by the dates:

Latest Possible completion time (LPCT) - Determined by the


start time of downstream activities that have already been
scheduled.

Earliest Allowable Completion Time (EACT) - Calculated by


the planning engine which accounts for the unscheduled
upstream activities and how much time those activities need.

If this profile option is the default value, the planning engine uses the
calculated EACT. If this profile option is lower than the default value, the
planning engine uses an earlier EACT than the calculated EACT which gives
the activity a larger scheduling window. If this profile option is higher than the
default value, the planning engine uses a later EACT than the calculated
EACT which gives the activity a smaller scheduling window. This is a user
level profile option.
Default Value - 0.5
Note Reference(s)
259322.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Enable Advanced Sequencing


Profile Code
Profile Option Name
Description

MSO
MSO_GLOBAL_SDS_FLAG

Valid values: Yes/No


Default value: No
The planning modes Constrained (Without Detailed
Scheduling) and Constrained (With Detailed
Scheduling) are available when the value of this
profile option is set to Yes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5233140
-1
No
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Enable Cost Rollup for Optimization


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_COST_ROLLUP
This profile specifies where the optimization engine looks for costs during
cost-based optimization.
Valid values are:

No: Use user-provided costs from the source system


Yes: Use costs from the internal cost rollup

Default value = NULL (No)


Will be used if the Optimization Flag is checked in
Plan Options.
When Yes, it is possible that internal cost rollup
may take some time and impact performance.
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
Yes
No
Yes
No
No
No
No
No
No
No

MSO: Enable Decision Rules


Profile Code
Profile Option Name
Description

MSO
MSO_ENABLE_DECISION_RULES
The profile option enables User Defined Decision Rules. Valid values are:

Yes - Use the user-defined decision rules.

No - User defined decision rules are not allowed.

The Plan Options tab, Decision Rules, is disabled. If you select No, you can
duplicate the functionality of the decision rule Use Alternate Sources
parameter for buy items but not for transfers from other organizations; set
profile option MSC: Enable Enhanced Sourcing to Yes.
Default Value - No
Note Reference(s)

214041.1
225876.1

267399.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Oracle Advanced Supply Chain Planning Implementation and User's Guide
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Enable Hard Links Globally


Profile Code
Profile Option Name
Description

MSO
MSO_GLOBAL_HARD_LINK_FLAG
Valid values are:

Yes - hard links in the code are not disabled

No - disable the hard links in the code.

Default Value - Yes


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5067925

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Enable Rounding of Fractional Supplies For


Service Planning
Profile Code
Profile Option Name
Description

MSO
MSO_ENABLE_ROUNDING_OF_FRACTIONAL_SUPPLIES_FOR_SRP

Enables rounding of fractional supplies and


demands and allocated qty after 1-to-1 splitting
based on pegging for SPP
Valid values are:
Y - By rounding the orders we are going to update
the data from the pegging, supplies and demands
table. Rounding is process that round up to the
nearest integer the fractional order quantities.
N - If the profile is not specified the order quantities
are NOT rounded up (default behavior)

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6834025
-1
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Enable sourcing split for end item


substitution
Profile Code
Profile Option Name
Description

MSO
MSO_SRC_SPLIT_FOR_SUBS

When using End Item Substitution, for Rank 1


sourcing rules with split sourcing %, this profile
must be set to enforce the sourcing split.
Valid values: Yes/No
Default value: No
Not supported on Rank 2 of the sourcing rule.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6430766
9486069
-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
Yes
Yes
Yes
Yes
No
Yes
No
No
No
No
No
No
No

MSO: Enforce Minimum Transfer Quantities


Profile Code
Profile Option Name
Description

MSO
MSO_GLOBAL_MTQ_FLAG

Valid values : Yes/No


Default value = Yes
If set to Yes : The downstream process starts after
a minimum quantity from the upstream process has
been completed. The material transfer is
continuous after the Minimum Transfer Quantity is
completed.
No documentation on this profile. However, you
can find information about "Minimum Transfer
Quantity" (MTQ) in ASCP guide (Page 6-79)
This is linked to MTQ setups for resources and
routings.
This should be No, unless you have specific MTQ
setups that must be enforced.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6650688
9409110
-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Enforce Resource Sequence Contiguity


Profile Code
Profile Option Name
Description

MSO
MSO_ENFORCE_RESOURCE_SEQUENCE_CONTIGUITY
Controls contiguity constraints between resource activities within an
operation. Valid values are:

Yes - Resource activities within the same operation are


scheduled contiguously in time. The end of the preceding
activity exactly lines up with the start of the current activity
and the end of the current activity exactly lines up with the
start of the next (if there is MTQ specified, the activities may
also overlap).

No: The contiguity constraint is relaxed and in certain cases,


the chances of obtaining feasible schedules improved.

Default Value - No
Note Reference(s)
562872.1
259322.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Firm Purchase Orders Within Time Fence


Profile Code
Profile Option Name
Description

MSO
MSO_FIRM_PURCHASE_ORDER_WITHIN_PTF
Indicates whether or not the planning engine should firm those purchase
orders that are within the time fence. Valid values are:

Note Reference(s)

Yes - Firms purchase orders that are within the time fence.
No - The planning engine does not reschedule the non-firm
purchase orders that have dock dates within the Planning
Time Fence. The planning engine does not reschedule or
cancel recommendations even if there are conditions for
reschedules and cancellations.

370386.1
365112.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Firm Requisitions Within Time Fence


Profile Code
Profile Option Name
Description

MSO
MSO_FIRM_REQ_WITHIN_PTF
Indicates whether or not the planning engine should firm those requisitions
that are within the time fence. The valid values are:

Yes: Firms requisitions that are within the time fence.

Note Reference(s)

The planning engine does not reschedule or cancel recommendations even if


there are conditions for reschedules and cancellations.
The planning engine uses the start date of the receiving organization as the
reference for internal requisitions. Default : No
555016.1
1079681.1
1068297.1
365112.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No: The planning engine does not reschedule the non-firm


purchase requisitions that have dock dates within the
Planning Time Fence.

8709703
-1
-1
-1
-1
-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Firm Supply Allocation Window (Backward


days)
Profile Code
Profile Option Name
Description

MSO
MSO_FIRM_SUPPLY_ALLOC_WIN
The allocation of firm supplies to demands is based on demand priorities
within the Firm Supply Allocation window. Set this window using system
level profile options. This window is derived dynamically for each demand; it
starts with the demand due date and goes backwards to the window size.
This is stated as the number of calendar days including non-workdays. Valid
values are:

Integer > 0

Default Value - 1
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4688250
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Firm Supply Allocation Window (Forward


days)
Profile Code
Profile Option Name
Description

MSO
MSC_FIRM_SUPPLY_FWD_FENCE
The allocation of firm supplies to demands is based on demand priorities
within the Firm Supply Allocation window. Set this window using system level
profile options.
This window is derived dynamically for each demand; it starts with the
demand due date
and moves forwards to the window size. This pegs demands to firm supplies
that are scheduled after the demand date. After searching backward, it
searches forward by
the number of days set by this profile option, pegging the supply with the
nearest (earliest) schedule to the unallocated demand quantity. This can
cause supplies to
be late for the demand due date. This is stated as the number of calendar
days including non-workdays.
To use this feature, set profile option MSO: Net All Firm Supplies Before
Creating Planned Orders to Yes.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Firm Work Orders/Operations Within Time


Fence
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SCHEDULE_FIRMED_BEFORE_PTF
Used for both constrained and unconstrained plans. Valid values are

Yes - all operations of an order with start dates in the


Planning Time Fence are treated as firm. Any operation with
a start date outside of the Planning Time Fence is not
considered firm and can be moved.

No - operations with start dates in the Planning Time Fence


can be rescheduled out.

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Floating Point Precision


Profile Code
Profile Option Name
Description

MSO
MSO_FLOATING_POINT_PRECISION

There is a documentation bug : The documentation


says that this profile is replaced by profile MSO:
Floating Point Precision for Order Quantities - but
this does not exist.
This (Floating Point Precision) is the correct profile
name - Refer to the documentation for MSO:
Floating Point Precision for Order Quantities and
use this profile instead.
Number > 0
Default = 100
Internal multiplier for order quantities.
Can change the value depending on precision
desired.
Verify that the product of the floating point precision
and the number does not exceed the maximum
integer size handled by
the machine.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Floating Point Precision for Increments of


Shift Start/End Times Within a Planning Bucket
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_HLS_SHIFT_INC_PRECISION
Could not find in the User guide.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Floating Point Precision for Order Q


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_HLS_ORDER_QUANTITY_PRECISION
Not used. Replaced by profile option MSO: Floating Point Precision for Order
Quantities

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Floating Point Precision for Planning Bucket


Efficiency
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_HLS_GRANULAR_PRECISION
This has been changed to MSO:HLS Granularity Precision.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Floating Point Precision for Transportation


Capacities (Volume)
Profile Code
Profile Option Name
Description

MSO
MSO_HLS_TRANS_VOLUME_PRECISION
Internal multiplier for transportation lane capacities by volume, by day. Can
change the value depending on precision desired. Verify that the product of
the floating point precision and the number does not exceed the maximum
integer size handled by the machine. See 'Floating Point Precision, page A-2
of ASCP User guide for more information.
Valid Values: Number>0
Default Value: 100
If the plan planning mode is Constrained (Without Detailed Scheduling), the
planning engine does not use this profile option.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Floating Point Precision for Transportation


Capacities (Weight)
Profile Code
Profile Option Name
Description

MSO
MSO_HLS_TRANS_WEIGHT_PRECISION
Internal multiplier for transportation lane capacities by weight, by day. Can
change the value depending on precision desired.
Verify that the product of the floating point precision and the number does not
exceed the maximum integer size handled by
the machine. See 'Floating Point Precision, page A-2 of ASCP User guide for
more information.
Valid Values: Number>0
Default Value: 100
If the plan planning mode is Constrained (Without Detailed Scheduling), the
planning engine does not use this profile option.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5173359
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Floating Point Precision for Usage in


Routings
Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_HLS_USAGE_PRECISION
Internal multiplier for order quantities. Can change the value depending on
precision desired. Verify that the product of the floating point precision and
the number does not exceed the maximum integer size handled by the
machine. See 'Floating Point
Precision, page A-2 of ASCP User guide for more information.
Valid Values: Number>0
Default Value: 100
If the plan planning mode is Constrained (Without Detailed Scheduling), the
planning engine does not use this profile option.
560505.1
579204.1
224112.1

-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Generate Compression Days Exception


Profile Code
Profile Option Name
Description

MSO
MSO_GENERATE_COMPRESSION_EXCEPTION
Use this profile option to control issuance of exception message Orders with
compression days. Valid values are:

Yes - Issue the exception message


No - Do not issue the exception message

The planning engine issues exception message Orders with insufficient leadtime when it schedules orders for less time than their assembly's lead-time.
If the reason for that scheduling is that the planning engine would schedule
the order in the past, it also issues exception message Orders with
compression days.
To avoid seeing both these exceptions for the same order, select No for this
profile option.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Generate Compression/Firming Exceptions


for Orders in Progress
Profile Code
Profile Option Name
Description

MSO
MSO_GENERATE_COMPRESSION_FIRMING_EXCEPTIONS
When set to No, the planning engine does not issue the following exception
messages for firm orders whose start date is in the past (after applying the
lead time offset to the due date). Valid values are:

Order with Insufficient Lead Time


Order is Firmed Early

The planning engine assumes that these orders are in progress and on time:
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Generate Reduced Model


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_ENABLE_REDUCED_MODEL

Generate Reduced Model in Optimization


Description: Generate Reduced Model in
Optimization
Application: Constraint Based Optimization
Values = Yes / No
Default value: No
With this profile set to no, the return fcst are used
now.
This profile is available from VCP 12.1.3.5 PATCH:
12695590:R12.SCP_PF.B

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
Yes
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No

MSO: Generate Shared Supply Exceptions


Profile Code
Profile Option Name
Description

MSO
MSO_GENERATE_SHARED_SUPPLY_EXCEPTIONS
MSO: Generate Shared Supply Exceptions
Values: Yes/No

No: The planning engine schedules demands in slices; each


slice contains a set of demands in a time period. Sometimes,
a supply is pegged to two demands (shared supply) that are
each in different slices. If these two slices are separated by
more slices than the value of profile option MSO: Additional
Demand Slices for Shared Supply Rescheduling, the
planning engine does not reschedule the shared supply in
the earlier slice when it schedules the demand in the later
slice. It is possible that the demand in the later slice is
satisfied late because the planning engine did not reschedule
in (earlier date) the supply in the earlier slice.

Yes: The planning engine issues a Shared Supply


Scheduled Late exception message when this occurs. If this
profile option is No, the planning engine does not generate
the exception message. This is a user level profile option.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Global Batchable Flag


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_BATCHABLE_FLAG
Enables resource batching functionality for order scheduling.

B31553-02
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Global Chargeable Flag


Profile Code
Profile Option Name
Description

MSO
MSO_CHARGEABLE_FLAG
This profile option controls whether Oracle Advanced Supply Chain Planning
schedules resource charges.

Yes: the planning engine schedules charges for chargeable


resources.
No, chargeable resources are considered as item basis an
no individual charges are scheduled.

Material flows and resource loads are not influenced by charge quantities.
Valid values: yes/no
Default value: no
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Oracle Advanced Supply Chain Planning Implementation and User's Guide
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Global Time Limit


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_TILIM
Parameter used to set global time limit for halting optimization.
Values: Number > 0.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: HLS flat files path


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_HLS_FLAT_FILES_PATH
Specifies the directory to store the Planning Engine debugging data files.
Valid Values: Text
Default Value: Null

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Hard link scheduling window


Profile Code
Profile Option Name
Description

MSO
MSO_HARD_LINK_SCHEDULING_WINDOW

This profile option specifies the time window within


which ASCP tries to schedule a set of operations
linked together through hard links.If scheduling is
unsuccessful,overloads are created.
This is a hidden profile option used by
development. This defines the scheduling window
within which the system schedules the hard-linked
operation set. Increasing the window gives room to
schedule operations with hard links without
overloading. Based on the number of operations
per hard linked operation set,increasing this value
can have a performance impact.
Valid Values : Integer Default value 30

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Hard link scheduling window expansion


factor
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_HARD_LINK_SCHEDULE_WINDOW_FACTOR
This hidden profile option used by development is used to limit the
propagation for the hard linked operation set.
Normally, we limit the propagation by a factor of (This profile option value *
Minimum duration of hard linked operation set).
Valid Values: Integer
Default Value: 10

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Heuristic type


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_HEURISTIC_TYPE
Determines which heuristic to use.
The look-ahead heuristic reserves time for lower priorities so the schedule
begins with the tasks of higher priorities.
This is a site level profile option.
Valid Value: Look Ahead
Default Value Look Ahead

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Incremental Planned Orders


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SUPPLIER_DEMAND_SPLIT
No documentation found.

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Internal Demand Aggregation Within


Optimization
Profile Code
Profile Option Name
Description

MSO
MSO_SCO_INT_DMD_AGGR
This profile specifies how the optimization engine should prioritize
independent demands.
Valid values are:

Yes: Prioritize by date. This value improves optimization


engine performance.

No: Prioritize by demand priority

Bug 9587814 shows that cusotmer had plan using


12gb of memory and by setting this profile = Yes,
the plan only used 5gb of memory
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9587814
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
Yes
Yes
No
Yes
Yes
Yes
No
No
No
No
No
No
No
No
No
No

MSO: Inventory Carrying Costs Percentage


Profile Code
Profile Option Name
Description

MSO
MSO_CARRYING_COST_PCT
Specifies inventory carrying costs percentage for all items in the plan. Can be
defined at the site level. You can update this value. The inventory carrying
cost is a percent
(if the user enters 10, the value is 10%). A percentage between 0 and 100.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6863019
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: JIT Selector Window Size


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SELECTOR_JIT_WINDOW_SIZE
No information on this profile

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: LP Constraint Batch Size


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_CONSTRAINT_BATCH_SIZE
Not used.

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: LP Markowitz Coefficient


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_EPMRK
Sets the Markowitz Coefficient.
Values: Number between 0.0001 and 0.99999
Default value: See 'Automatic Calculations, page A-1 of the R12.1 ASCP
User Guide.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: LP Optimization Algorithm


Profile Code
Profile Option Name
Description

MSO
MSO_LP_ALGORITHM
Determines which optimization algorithm is used. Can be defined at the site
level. This is Automatic Calculations.
When the Default Value of a profile option states that it is automatically
calculated, this means that the Planning Engine
determines the default value of that particular profile option.
Valid Values:

0: Primal simplex

1:Dual simplex

2: Hybrid barrier primal

3: Hybrid barrier dual

Default Value:0
If you must change these profile option values, do
so only after consulting Oracle Development and
Oracle Support.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
Yes
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Late Demands Exceptions Tolerance Minutes


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_LATE_DMD_EXC_TOL_MIN
This profile option is used by constrained plans. Sets the value in minutes for
a window during which the planning engine does not issue exception
messages for late demands. Use it particularly in cases where demands are
only a few minutes
or a few hours late.
The value that you enter is used based on a 24 hour, 7 day per week
calendar. For example, enter 1440 minutes (24 hours) for this profile option.
A demand due at 15:00 on Tuesday does not cause late demand exception
or diagnosis information
as long as the supplies are complete by l5:00 on Wednesday.

Yes
No
No
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Lead Time Control


Profile Code
Profile Option Name
Description

MSO
MSO_LEAD_TIME_CONTROL

Violate Minimum Processing Times to Meet


Demand Due Date: The planning engine meets
the demand due date even if it compresses
operations and supplies beyond their minimum
durations (from item lead-times and routing
usages).
-- This setting can violate the Planning Time Fence
settings for an item.
-- It can also violate a Natural Time Fence created
by using profile MRP: Create Time Fence = Yes
Do Not Violate Minimum Processing Times: The
planning engine respects the minimum durations of
operations and supplies (from item lead-times and
routing usages) even if it satisfies demands late.
Default Value: Violate minimum Processing Times
to Meet Demand Due Date
This, sometimes, used with plan option - Enforce
Purchasing Lead-times Constraint and can change
planning engine behavior.
In 11.5.10, this profile is only for EDD - Enforce
Demand Due Dates plan
In 12.0.4 and above, this profile works for BOTH
EDD and ECC - Enforce Capacity Constraints
plans.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning

399888.1
850591.1
443357.1

-1
-1
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes

All Plan Types


Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
Yes
Yes
No
No
No
Yes
No
Yes
Yes
No
Yes
No
No
No
No
No
No
No

MSO: List Size for Pricing Candidates


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_PRICELIM
Parameter to set the list size for pricing candidates.
Values: Integer > 0.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Lookahead days to net co-product/by-product


supplies before creating planned orders
Profile Code
Profile Option Name
Description

MSO
MSO_CO_LOOKAHEAD_WINDOW
Profile no longer used in the application.
Will be removed from UI in a future release.
Was originally available in 11.5.8 and removed in 11.5.10.
accidentally included in R12

Note Reference(s)
111.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5462273
3631110
-1
-1
-1
No
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Max Gap Tolerence on SDS


Profile Code
Profile Option Name
Description

MSO
MSO_MAX_GAP_TOLERANCE_ON_SDS
Per bug 8538729 this profile is not currently used.

**Begin PM Update
This profile was introduced in R1 for DS. Not used anymore
**End PM Update
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximium Number of Prepones


Profile Code
Profile Option Name
Description

MSO
MSO_MAXIMUM_PREPONES
Scalability factor for the Scheduling Engine. The Scheduling Engine attempts
to schedule the operations in different orders to find a solution. Limits the
number of times the Scheduling Engine attempts to schedule an operation.If
there are many components for some items or many small supplies
answering a demand, the number of orders is larger; reduce this parameter.
Valid values are:

Integer > 0

Can be defined at the site level.


This profile is automatically calculated,this means
that the Planning Engine determines the default
value of this profile option.
If the plan planning mode is Constrained (Without
Detailed Scheduling), the planning engine does not
use this profile option.
Default Value - 10
If you must change these profile option values, do
so only after consulting Oracle Development and
Oracle Support.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximize Search of Availability Intervals


Profile Code
Profile Option Name
Description

MSO
MSO_MAXIMIZE_SEARCH_OF_AVAILABILITY_INTERVALS
Enhances the capability of the scheduling engine to accurately identify
pockets of available time where resource activities can be feasibly
scheduled. Valid values are:

Yes - Maintains a detailed picture of the Resource Profile


while scheduling. Resource Profile refers to the time varying
picture of requirements and availability. The maintenance of
this detailed picture causes the planning engine to miss
fewer valid slots for scheduling activities than otherwise.

No - Detailed Resource Profile is not maintained.

Default Value: Yes

If you need to change the default value of this profile in your installation, it is
recommended that you consult with Oracle Development before doing so.
You can set this option if you receive the Requirement causes resource
overload exceptions in the Planner Workbench in Enforce Capacity
Constraints Plans.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

If the plan planning mode is Constrained (Without Detailed Scheduling), the


planning engine does not use this profile option.
841308.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximize Use of Unfirm PurchOrd/WorkOrd in


Optimization
Profile Code
Profile Option Name
Description

MSO
MSO_SCO_MAXIMIZE_POWO
Optimization phase of the engine has the capability to evaluate the use of
new planned orders versus using partial supplies from scheduled receipts.

If you set it to 0 (Zero) engine may create new planned


orders while scheduled receipts exist. Ex: you have demand
of 10 units and you have a W/O or PO of 100 units, engine
will create new supply for 10 units versus using 10 units ut of
100 units of scheduled receipts and carrying the 90 units.
This decision might be taken as it is cheaper to produce than
to carry extra inventory.

Note Reference(s)
567317.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4006732
-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
Yes
No
Yes
No
No
No
No
No
No
No

If you set it to 1, the engine will use existing supplies and


decide to carry the un used portion of the supplies from W/O
or a PO. Continuing the example, Engine will use 10 units of
supply out of 100 and decide to carry the rest of the 90 units
instead of creating new supplies. This might not be cost
effective.

MSO: Maximum Activity Duration


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_HLS_ACTIVITY_DURATION_MAX
Defines the Planning Engine maximum activity duration in days.All
requirements should be less in duration than this. If null, the planning horizon
duration is used.
If the plan planning mode is Constrained (Without Detailed Scheduling), the
planning engine does not use this profile option.
Valid Values: Number>0
Default Value: by Automatic Calculations
179406.1
1327805.1

-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Allowable Days Late


Profile Code
Profile Option Name
Description

MSO
MSO_MAX_DAYS_LATE
Limits the number of days by which a demand or unfirmed scheduled receipt
can be moved out when optimization is turned on. This value is used only to
improve performance and reduce the size of the plan for the optimization
component of the Planning Engine. Scheduling moves demands and
unfirmed scheduled receipts out as long as necessary. Valid values are:

Integer > 0

Can be defined at the site level.


Note: Set this to a number as large as the typical planning horizon to avoid
unusual results.
Default Value - 300
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Allowable Days Late before


Forecast Expiration
Profile Code
Profile Option Name
Description

MSO
MSO_MAX_FCST_LATE_DAYS
Oracle Advanced Supply Chain Planning uses this profile option when
planning supplies for forecast scenarios from Oracle Demand Planning,
master demand schedule forecasts, and manual master demand schedule
entries. When a forecast or master demand schedule entry cannot be
completely satisfied within the allowable days late, the planning engine does
not plan supplies for the quantity that is late by this many days. The profile
option does not apply to sales orders. Valid values are:

Interger > 0

Default Value - Null


Note Reference(s)
859179.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8801111
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Alternate Combinations


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_ALT_COMBINATIONS
Does not appear in any manual,

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Demands Per Group for Advanced


Sequencing
Profile Code
Profile Option Name
Description

MSO
MSO_NUMBER_OF_DEMAND_PER_GROUP_FOR_SDS
The profile option specifies the number of demands that are grouped
together for scheduling. The larger this number, the greater the chances of
obtaining good sequences on the resources. Making this number too large
might result in demand priorities not being fully respected while scheduling.
Valid values are:

Any number

Default Value - 1
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Demands per Group


Profile Code
Profile Option Name
Description

MSO
MSO_DEMANDS_PER_GROUP
Determines the maximum number of demands that can be grouped together
for scheduling. Within a group, the default heuristic can try different orders
among the demands. Valid values are:

Integer > 0, smaller than the size of a slice

Default Value - 5
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2829066
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Demands per Slice


Profile Code
Profile Option Name
Description

MSO
MSO_DEMANDS_PER_SLICE
Determines the number of demands in a slice. Enables the Scheduling
Engine to resolve interactions of demands within a slice. Supplies shared
between demands are scheduled better when the demands are in the same
slice. However, slices that are too large slow down the Scheduling Engine
use more memory. Valid values are:

Integer >= 0

Default Value - 100


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Inventory Level % of Safety Stock


Profile Code
Profile Option Name
Description

MSO
MSO_MAX_INV_LEVEL
Use this option to specify maximum inventory levels. If no other method of
calculation is defined for an item-organization maximum inventory level, the
levels are based on the specified percentage of the safety stock level. Valid
values are:

Percentage between 0 and 100

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
MSO: Target Inventory Level % of Safety Stock
Yes
No
No
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Lead Time Factor


Profile Code
Profile Option Name
Description

MSO
MSO_MAX_LEAD_TIME_FACTOR
As per Bug#2953151 not used any more.

Note Reference(s)

This is used by the scheduling engine. This is the fraction of the overall
horizon length, within which the backward pass restricts looking for resources
to fit the schedule. If this cannot be scheduled within this fraction of the
overall horizon length, it is forward scheduled.
The value is specified as a number between 0 to 1. This profile option can be
defined at the site level. You can update this value.
The default value is 1
167239.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Number of Demands in a Hard


Linked Demand Set
Profile Code
Profile Option Name
Description

MSO
MSO_MAX_DEMANDS_PER_HLK_DEMAND_SET
Value specified in number of demands. Default value is 1, indicating no
upper limit. This is a hidden profile option.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6818322
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Number of Pull for Operation


Profile Code
Profile Option Name
Description

MSO
MSO_MAX_PULL_OPERATION
When an operation cannot be scheduled on a certain day, the scheduling
engine attempts to schedule it on an earlier date (for backward scheduling).
This profile option controls how many days are tried in this manner. Many
days result in lower performance. Valid values are:

Integer > 0

Can be defined at the site level.


This profile is automatically calculated, this means
that the Planning Engine determines the default
value of this profile option.
Default Value - 8
If you must change these profile option values, do
so only after consulting Oracle Development and
Oracle Support.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Number of Pushes for Operation


Profile Code
Profile Option Name
Description

MSO
MSO_MAX_PUSH_OPERATION
When you are running constrained plans with the Enforce Capacity
Constraints plan option checked,this profile option controls the number of
attempts made to schedule a resource activity feasibly. Valid values are:

-1 - Continues the search for available capacity till the end of


the planning horizon.

Integer > 0 - The number that you specify here determines


the number of attempts that the planning engine makes to
schedule the activity. For example, if you set the profile
option to 5, the planning engine makes 5 attempts to
schedule the activity feasibly, and after that schedules the
activity with an overload. The spot chosen to schedule the
activity with overload is the initial spot that was tried.

If the plan planning mode is Constrained (Without Detailed Scheduling), the


planning engine does not use this profile option.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Operations Per Slice


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_HLS_MAX_OPERATIONS_PER_SLICE
Determines the number of operations which can be scheduled in a slice.
Limits the problem size in a slice and can be a limiting factor in determining
the number of demands that can be scheduled in a slice.
Oracle recommends that you use a large value such as the default value.
If the plan planning mode is Constrained (Without Detailed Scheduling), the
planning engine does not use this profile option.
Valid Values: Integer>0
Default Value: 3000 operations
747739.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Resource Over-capacity


Profile Code
Profile Option Name
Description

MSO
MSO_MAX_EXCESS_RESOURCE_UNITS
Assigns resource slacks when it does not find the resource available and it is
forced to use slacks. The Scheduling Engine initiate the resource slack from
0 to maximum assigned units and will jump to this number if no solution is
possible. This limits the number of tries to assign the resource slack. Valid
values are:

Number > 0

Can be defined at the site level.


This is automatic Calculated profile. When the Default Value of a profile
option states that it is automatically calculated, this means that the Planning
Engine determines the default value of that particular profile option.
Default Value - 5
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum Simplex Iterations


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_ITLIM
Parameter to set the maximum number of simplex iterations.
Values: Integer > 0

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Maximum number of pulls/push for hard


linked operations
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_MAX_PUSH_PULL_FOR_HARD_LINKS
This hidden profile option is not used.

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Minimize Supply Duration


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_MIN_SUPPLY_LEAD_TIME_BY_LEFT_JUSTIFY
Valid Values:
1. Yes
2. No
This is a profile to compress supply durations. It was introduced in R12.
Default value: Yes
This is used during HLS scheduling of jobs and supplies.

No
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Minimum Processing Lead Time Adjustment


Factor
Profile Code
Profile Option Name
Description
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_MIN_PROC_LEAD_TIME_ADJ_FACTOR
Not available in user guide.
564241.1

-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Multiplier To Derive Supply Allocation


Window
Profile Code
Profile Option Name
Description

MSO
MSO_FIRM_SUPPLY_MULTIPLIER
You can set the Firm Supply Allocation window using the profile option MSC:
Firm Supply Allocation Window or you can use the manufacturing lead-time
and the profile option MSC: Multiplier to Derive Firm Supply Allocation
Window.
If you specify any value for the latter profile option, the information you enter
for MSC: Firm Supply Allocation Window is ignored. If the product of this
multiplier and cumulative manufacturing lead-time is a fractional quantity, the
number is rounded up to the next integer. Formulas for the item-specific firm
supply allocation window:

Make item: Cumulative manufacturing lead-time * MSO:


Multiplier to derive supply allocation window.

Buy item: Processing lead-time * MSO: Multiplier to derive


supply allocation window.

Valid Value: Number >= 0.


Default Value: Null.
Note Reference(s)
1068297.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Net All Firm Supplies Before Creating


Planned Order
Profile Code
Profile Option Name
Description

Note Reference(s)

MSO
MSO_FIRM_B4_PO
Nets all firmed supply available in any future period before creating new
planned orders.
The profile option treats firmed planned orders the same as real supplies.
The values are:

0 - No: Does not net firm supplies before creating planned


orders.

1 - All Supply Types: Net all firm supplies before creating


planned orders. This includes work orders, purchase orders,
transfer supplies and firm planned orders for these supplies.

2 - Only for Work Orders: Net only firm discrete jobs before
creating planned orders.

3 - Only for Purchase and Transfer Supplies: Net all firm


purchased and transfer supplies before creating planned
orders.

4 - All Supply Types Including by-product/co-product


supplies: Nets all firm supplies (including by-product and coproduct supplies) before creating planned orders. The
planning engine does not reschedule by-product and coproduct supplies, they follow the scheduling of the supply
that generates them. This choice allows these supplies to be
netted for earlier demands. This may cause late demands,
but may reduce overall inventory.

Default: No
370386.1

749448.1

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning

-1
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
-1
-1
Yes
No
No
Yes
Yes
Yes
Yes
Yes
No

Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No

MSO: Network routing cycle time coefficient


Profile Code
Profile Option Name
Description

MSO
MSO_NFL_CYCLE_TIME_COEFFICIENT
Used by the Scheduling Engine to calculate the window of time allocated to
schedule a network flow. This is used in conjunction with NFL Fixed Time
Window. The window of time is (Coefficient *Cycle time) + Fixed time
window. Valid values are:

Number > 0

Defined at the site level.


Profile is applicable when OSFM Network Scheduling Method is set to
Optimized.
Default Value:0
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Network routing fixed time window


Profile Code
Profile Option Name
Description

MSO
MSO_NFL_FIXED_TIME_WINDOW
Used by the Scheduling Engine to calculate the window of time allocated to
schedule a network flow. This is used in conjunction with NFL Fixed Time
Window. The window of time is (Coefficient *Cycle time) + Fixed time
window.
Valid values are:

Number > 0

Profile is applicable when OSFM Network Scheduling Method is set to


Optimized.
Defined at the site level.
Default Value - 0
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Nfl Backward Compression Pct


Profile Code
Profile Option Name
Description

MSO
MSO_NFL_BACKWARD_COMPRESSION_PCT
Defines the percentage of the actual resources capacity that the network flow
takes into account. A value under 100 percent tends to offload more
activities to alternate resources. Can be defined at the site level. Valid
values are:

Between 10 and 100%

Profile is applicable when OSFM Network Scheduling Method is set to


Optimized.
Default Value - 100%
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Nfl Forward Compression Pct


Profile Code
Profile Option Name
Description

MSO
MSO_NFL_FORWARD_COMPRESSION_PCT
Defines the percentage of the actual resources capacity that the network flow
takes into account. Use in forward phase to force the system to use
alternates and limit the tardiness of activities. Valid values are:

Between 10 and 100%

Can be defined at the site level.


Profile is applicable when OSFM Network Scheduling Method is set to
Optimized.
Default Value - 100%
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Number of Backtracks Allowed


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_MAX_BACKTRACKS
As per Bug 2953151, this is not used

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Number of Decomposition Groups Per


Process
Profile Code
Profile Option Name
Description

MSO
MSO_SCO_DECOMP_GROUPS

MSO: Number of Decomposition Groups Per


Process
Set to the number of decomposition groups in each
process in multi-process solve mode
Product: Constrained based optimization
Internal name: MSO_SCO_DECOMP_GROUPS
User name: MSO: Number of Decomposition
Groups Per Process
Description: Set to the number of decomposition
groups in each process in multi-process solve
mode

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Number of Demand Groups for Optimization


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_MAX_DEMAND_GROUPS
You can use this profile option only for constrained plans that have decision
rules enabled. In the case of cost-based optimization, the planning engine
considers the demand lateness penalty cost instead of demand priorities.
Use this profile option to instruct the planning engine how to group demand
into demand groups by priority ranges. For example, the demand priority
values are from 1 to 100 and you set this profile option to 5. The planning
engine assigns demands to five demand groups. Each group includes a
range of 20 priorities - 1 to 20, 21 to 40, 41 to 60, 61 to 80, 81 to 100.
The planning engine searches for supplies that satisfy all demands having
priorities in the same range. It satisfies demands in the higher priority range
first. For multiple demands in the same priority range, the planning engine
satisfies demands based on individual demand priorities.
Valid values: Integer > 0
Default value = 50

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
Yes
No
Yes
No
No
No
No
No
No
No

MSO: Number of Iterations for Local Search


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_NUMBER_OF_LOCAL_SEARCH_ITERATIONS
Introduced for Detailed scheduling in R12. Not used

No
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Number of LP Phases for Safety Stock


Calculation
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SCO_MRP_SS_LOGIC
Set only with guidance from Oracle Development

Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Number of Processes to use in


Decomposition
Profile Code
Profile Option Name
Description

MSO
MSO_DECOMPOSITION_TOTAL_PROCESSES
Number of Processes to use in Decomposition. This is applicable for Service
Parts Planning and Distribution Planning
Used to help in performance of a specific stage of the planning engine.
Default is 2
This should be changed only with Support or DEV recommendation.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

12409853
-1
No
No
No
No
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Number of Threads for Optimization


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_NUM_THREADS
This profile option applies to 64-bit platforms only.

Values greater than 1 invoke running optimized plans in a


multi-threaded mode. This enables various optimization
problems to be solved in parallel so that run time may be
reduced.

However, multi-threading increases the CPU usage and memory


consumption. You can control the load on CPU by specifying the number of
threads that you want to run in parallel.
Valid value: Integer >0
Default value: null
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
Yes
No
Yes
No
No
No
No
No
No
No

MSO: Number of processes for Inline Forecast


Profile Code
Profile Option Name
Description

MSO
MSO_NUM_OF_PROCS
Number of processes for Inline Forecast. For Multiprocess run for inline
forecast the user need to supply number of processes

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8687334
-1
No
No
No
No
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Optimization Advanced Start


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_ADVIND
This profile option controls whether the planning engine should be set to use
advanced start (profile option value 1).
This means that the optimization engine uses certain values from a previous
run of the plan; it sees improved performance by reusing certain
computations.
This is an optimization engine profile option and should not be changed
under ordinary circumstances.
Values: 0 and 1
Default value is: Null (internally defaulted as a value of 1)

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Optimization Daily Aggregation Buckets


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_AGGREG_DAY_BUCKETS
Specifies the Daily Aggregation Time Bucket to be used by the Planning
Engine if the profile
option MSO: Use Optimization Internal Time Aggregation is set to True.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Optimization Weekly Aggregation Buckets


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_AGGREG_WEEK_BUCKETS
Specifies the Weekly Aggregation Time Bucket to be used by the Planning
Engine if the profile option MSO: Use Optimization Internal Time Aggregation
is set to True.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Optimization debug level


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_DEBUG_LEVEL

MSO: Optimization debug level


While Forecasting the Demantra generated logs
were not exposed to users.
USing the API's and providing the profile option for
the user, the logs are now genrated in
data[plan_id]/mbpoutput/Engine_XXX.log
When method blended was used, several differnt
forecast methods are called to generate the
forecast.
Based on the fit the best forecast method is
choosen and respective forecast numbers are
provided by
the Demantra Engine. User wants to see the Log
demantra engine generates while forecasting the
history series.
The user need to define the debug level and group
level to generate the Demantra Logs
from the PROFILE OPTION :
MSO_SCO_DEBUG_LEVEL
Convention-> DEBUG_LEVEL:GROUP_LEVEL
DEBUG_LEVEL:
valid range from 3 to 6 where:
3 is message,
4 - info
6 - Detailed
GROUP_LEVEL:
The combined filter for the log groups to show

during run time,


any of the LG_XXXX variables can be combined
here to form the group to show.
LG_Events = 32 , LG_ProcDebug = 64, LG_Default
= 128; (these could be combined and the value
could be 64 + 128 )
For Example, to get good amount of log info
MSO_SCO_DEBUG_LEVEL could be set to 5:128
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No

MSO: Order Modifier Max Searching Depth


Profile Code
Profile Option Name
Description

MSO
MSO_OM_CTP_MAX_DEPTH
Use this profile option to specify the maximum number of lower levels in the
supply chain that the planning engine searches for alternate sources, bills of
material, components, and resources to resolve a shortage. The shortages
often occur when the planning engine rounds down planed orders with
respect to capacity constraints and order modifiers.
The planning engine searches this many levels down both in:

The organization with the shortage


Organizations that supply the short organization with the
short item

Oracle suggests that:


The solution quality improves with higher numbers while the processing time
worsens with higher numbers. For each integer increase in the profile option,
processing time worsens at a much higher rate than solution quality
improves. You consider the tradeoffs and tend towards lower rather than
higher numbers.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

6890145
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Overlap Activities by MTQ


Profile Code
Profile Option Name
Description

MSO
MSO_OVERLAP_ACTIVITIES_BY_MTQ
Use this profile option to control overlapping activities inside one operation.
Valid values are:

Yes - Allow overlapping activities inside one operation.


No - Prevent overlapping activities inside one operation.

Default Value - No
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Peg By-product Supplies


Profile Code
Profile Option Name
Description

MSO
MSO_PEG_BYPROD_SUPP

Yes: Pegging is considered when scheduling operations with


by-product supply. Scheduling of these operations respects
demand for the by-product and demand for the main product.
After scheduling these operations, the by-product supply
date is updated to reflect the operation scheduled date.

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No: By-Product Supplies are not pegged to demands For


constraint-based plans. Set this profile option to No with
items that are components on the supply chain bill of
materials and that are by-product on a different level of the
same supply chain bill of materials. Selecting No prevents
the planning engine from continuous looping between the
component demand and the by-product supply.

Default Value: Yes


566497.1
984372.1
957490.1

-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Basis for Changeovers


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_PENALTY_BASIS_FOR_CHANGEOVERS
Indicates whether the changeover time of the changeover penalty is to be
used as the criterion for calculation the ideal sequence.
Valid Values are:

Changeover time :If Changeover Time, ASCP uses the


relative changeover times between setup types as the
criteria for deciding on the ideal sequence of setup types.

Changeover Penalty: If Changeover Penalty, ASCP uses the


relative changeover penalties between setup types as the
criteria for deciding on the ideal sequence of setup types.

Default Value: Changeover time


415276.1

-1
No
No
No
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Exceeding Item


Material Capacity Flexfield Attribute
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_ITEM_CAP_PENALTY
Stores the flexfield column name that contains the value in the corresponding
table. Setup performed only during application install. See 'Flexfield
Attributes, page A-1 of ASCP user guide for more information.
Valid Values: Interger>=0
Default Value: Null
763878.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Exceeding Material


Capacity
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_GLOBAL_ITEM_PENALTY
Defines a penalty cost factor for exceeding material capacity.
Valid Values: Number>=0
Default Value: Null

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Exceeding Material


Capacity Flexfield Attribute
Profile Code
Profile Option Name
Description

MSO
MSO_SUP_CAP_PENALTY
Attribute Number Automatically generated to denote flexfield segment
holding the penalty factor. This profile option stores the item flexfield
segment that holds the penalty cost factor for exceeding material capacity.
The collections process Generate Planning Flexfield concurrent program
captures the segment when it first runs during installation.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Exceeding Org


Material Capacity Flexfield Attribute
Profile Code
Profile Option Name
Description

MSO
MSO_ORG_ITEM_PENALTY
Stores the flexfield column name that contains the value in the corresponding
table. Setup performed only during application install. See 'Flexfield
Attributes,page A-1 for more information. Valid values are:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Interger >= 0

Default Value - Null


1069694.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Exceeding Org


Resource Capacity Flexfield Attribute
Profile Code
Profile Option Name
Description

MSO
MSO_ORG_RES_PENALTY
Stores the flexfield column name that contains the value in the corresponding
table. Setup performed only during application install. See 'Flexfield
Attributes,page A-1 for more information. Valid values are:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Interger >= 0

Default Value - Null


1069694.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Exceeding Org


Transportation Capacity Flexfield Attribute
Profile Code
Profile Option Name
Description

MSO
MSO_ORG_TRSP_PENALTY
Stores the flexfield column name that contains the value in the corresponding
table. Setup performed only during application install. See 'Flexfield
Attributes,page A-1 for more information. Valid values are:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Interger >= 0

Default Value - Null


1069694.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Exceeding Resource


Capacity
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_GLOBAL_RES_PENALTY
Denotes a factor for plan profit computations that is invoked only when the
plan profit parameter for optimization has a value greater than 0. The
penalty cost factor is multiplied by the resource cost to give the cost of
overloading a particular resource.
Valid Values: 0 and 1
Default Value: Null (internally defaulted as a value of 1)
562872.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Exceeding Resource


Capacity Flexfield Attribute
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_RES_PENALTY
Stores the flexfield column name that contains the value in the corresponding
table. Setup performed only during application install. Valid values are:

Interger >=0

Default Value - NULL


147242.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Exceeding


Transportation Capacity Flexfield Attribute
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_TRSP_PENALTY
Penalty Cost for Exceeding Transportation Capacity (Optimized Plan)

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Late Demands


Profile Code
Profile Option Name
Description

MSO
MSO_GLOBAL_DMD_PENALTY
MSO: Penalty Cost Factor for Late Demands Defines a penalty cost factor
common to all demands. The demands include sales orders, forecasts and
safety stock. Can be defined at the site level.
Values Integer > 0
No default value

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4139766
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Late Forecasts


Flexfield Attribute
Profile Code
Profile Option Name
Description

MSO
MSO_FCST_PENALTY
Stores the flexfield column name that contains the value in the corresponding
table. Setup performed only during application install. Valid values are

Integer >= 0

Default Value - NULL


Note Reference(s)
176030.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Late Item Demands


Flexfield Attribute
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_ITEM_DMD_PENALTY
Stores the flexfield column name that contains the value in the corresponding
table. Setup performed only during application install.
Valid Values: Integer>=0
Default Value: Null

Yes
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Late Org Demands


Flexfield Attribute
Profile Code
Profile Option Name
Description

MSO
MSO_ORG_DMD_PENALTY
Stores the flexfield column name that contains the value in the corresponding
table. Setup performed only during application install. See 'Flexfield
Attributes, page A-1 for more information. Valid values are:

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Interger >= 0

Default Value - Null


1069694.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Cost Factor for Late Sales Orders


Flexfield Attribute
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SO_PENALTY
Stores the flexfield column name that contains the value in the corresponding
table. Setup performed only during application install. See 'Flexfield
Attributes,
page A-1 in the ASCP User Guide for more information.
Valid values: integer >= 0
Default value: 0
153919.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty Increase Tolerance Percentage in


Local Search
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_TOLERANCE_PERCENT_FOR_LOCAL_SEARCH
No information on this profile.

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Penalty multiplier outside unconstrained


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_LATE_PENALTY_MULTIPLIER
This profile option specifies an extra lateness penalty when scheduling later
than the unconstrained latest possible completion time for a given activity.

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Percent Complete Before Resequencing


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_PERCENTAGE_OF_OPS_SCHED_BEFORE_RESEQUENCE
No information on this profile

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Postpone Use of Alternates to Latest Possible


Time
Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_USE_ALT_ALAP
This will cause the planning engine to postpone the use of Alternate Rank
sourcing until latest possible time in the plan. Used with sourcing rules where
multiple ranks are used and trying to force use of Alternates.
Best to set to Yes when using Multi-Rank sourcing rules.
872452.1
363069.1

-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
Yes
No
Yes
Yes
No
Yes
No
No
No
No
No
No
No

MSO: Preemption Slack Ratio


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_PREEMPT_SLACK_RATIO
This was introduced in R12 for DS. It is not being used

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Preprocessing Aggregator Fill


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_AGGFILL
Preprocessor aggregator fill
Valid values: Integer >= 0
Default value: See 'Automatic Calculations, page A-1 of the R12.1 ASCP
User Guide.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Preprocessing Aggregator Limit


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_AGGIND
Parameter to control preprocessing aggregator limit.
Values: Integer > 0
Default value: See 'Automatic Calculations, page A-1 of the R12.1 User
Guide.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Preprocessing Flag for LP Matrix


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_PREIND
Contains the presolve indicator.
Values are 0 and 1.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2149275
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Preprocessor LP Compression


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SCO_PREPROCESS_COMPRESS
Not Used by ASCP

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Primal Simplex Parameter


Profile Code
Profile Option Name
Description

MSO
MSO_PARAM_PPRIIND
Gradient parameter for primal simplex algorithm. Valid values are:

-1

Default Value - Automatic Calulations


When the Default Value of a profile option states that it is automatically
calculated, this means that the Planning Engine determines the default value
of that particular profile option. These profile options are included in this
appendix for information purposes only. If you must change these profile
option values, do so only after consulting Oracle Development and Oracle
Support.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No

MSO: Primal/Dual Preprocessing Reduction


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_PREPROC_REDUCTION
Values 0, 1, 2, and 3
See 'Automatic Calculations,in ASCP User Guide page A-1.
Used by optimization

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Pull push base


Profile Code
Profile Option Name
Description

MSO
MSO_PULL_PUSH_BASE
Each time the planning engine needs to search for a new spot to schedule it
looks ahead by a certain time period that is dictated by the settings of the
profile options MSO: Push Pull Base and MSO: Push Pull Offset. Valid
values are:

Positive Interger

Default Value - 1
Used in the HLS code
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2953151
-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Pull push offset


Profile Code
Profile Option Name
Description

MSO
MSO_PULL_PUSH_OFFSET
Each time the planning engine needs to search for a new spot to schedule it
looks ahead by a certain time period that is dictated by the settings of the
profile options MSO: Push Pull Base and MSO: Push Pull Offset. Valid
values are:

Positive Interger

Default Value - 1440


This is used in HLS code
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2953151
-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Queue Time Factor


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_LEAD_TIME_FACTOR
Increases item lead-time in optimization, so that lead-time values are close to
those used in the Scheduling Engine.
Optimization lead-time is padded to include queue time.
Valid values: Number >=0

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Re-computation percentage for sequence


generation
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_RECOMPUTATION_PERCENTAGE_FOR_SDS
No information on this profile

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Reschedule Jobs Out to Reduce Inventory


Carrying Costs
Profile Code
Profile Option Name
Description

MSO
MSO_RESCHEDULE_JOBS_OUT
This profile option involves right justifying standard and lot-based discrete
jobs when rescheduling them out to line up with other supplies for the job.
When there is a constraint, the planning engine always moves the jobs
based on the constraint. When there are no constraints, you have the option
to instruct the planning engine to right justify the jobs. Valid values are:

Yes - The planning engine attempts to schedule the job as


late as possible for one or more demands.

No - The planning engine does not reschedule or right justify


the job beyond its old due date. If there is existing capacity
earlier than the old due date of the job, the planning engine
may recommend a reschedule in.

This profile option does not apply to other order types, for example, purchase
orders and purchase requisitions.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7280156
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Reschedule Shared Supply to Influence


Batching
Profile Code
Profile Option Name
Description

MSO
MSO_BATCHING_BEST_EFFORT
Determines whether the Planning Engine schedules shared supplies early to
avoid item-based resource constraints prior to batch resources. Valid values
are:

Yes - considers whether scheduling shared supplies early


will allow subsequent resource batching; this value improves
the scheduled utilization of batch resources by considering
earlier constraints
No - schedules resource batching when supplies are
available

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Resource Adjustment Factor For Improved


Offloading to Alternates
Profile Code
Profile Option Name
Description

MSO
MSO_SCO_RES_ADJ_FACTOR

The factor that the planning engine uses to reduce


the resource availability when making the sourcing
decision. For example, if the factor is set to 0.8, the
resource availability is reduced by 20% and the
planning engine uses more of the alternate
processes. Then, at the time of scheduling,
planning has more flexibility.
Valid values: A number between and including 0
and 1
Default value: Null (internally defaulted as a value
of 1)

Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

562872.1
374093.1
317501.1
787458.1

-1
-1
-1
-1
Yes
No
No
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Resource Batching Strategy


Profile Code
Profile Option Name
Description

MSO
MSO_BATCHING_STRATEGY
Selects order scheduling strategy used in resource batching. Valid values
are:

Nearest Date - schedules orders to load resources nearest


the due date of the order)

Level Utilization schedules orders to level utilization of the


resource

Note Reference(s)
244748.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Resource Group for the Line Flexfield


Attribute
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_LINE_RESOURCE_GROUP
Stores the name of the flexfield column that contains the value in the
corresponding table. This setup is only performed during
application install.
Valid Values: Integer>=0
Default Value: Null

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Respect Activity Contiguity Flag for Process


Supplies
Profile Code
Profile Option Name
Description

MSO
MSO_MAKE_ACTIVITY_NON_BREAKABLE_AS_PER_FLAG
When the profile is set to "respect" OPM activity flag (profile set to yes), this
is then used in conjunction of profile "MSO: Schedule Across Breaks" .
1. With the profile "MSO: Schedule Across Breaks" to allow breaks set to
'Yes', this will override OPM's activity break indicator (even if flag is not
checked) : APS can schedule across Calendar breaks.
2. With the profile to allow breaks set to 'No', and the OPM activity break
indicator set to 'N', APS does not schedule across breaks. Given these
settings APS does not schedule resources outside of working shifts for an
ECC plan.

Note Reference(s)
1106718.1
1112749.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4517139
-1
-1
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Respect EDD Scheduling windows for Lead


Times
Profile Code
Profile Option Name
Description

MSO
MSO_PRESERVE_OPERATION_LEADTIMES
Do not compress post processing lead time for buy orders if enforce
purchasing lead time option is unchecked.

Yes - The scheduling windows used in enforce demand due


dates scheduling will be respected when scheduling lead
time activities such as pre-processing, processing, postprocessing and fixed+variable lead times.

No - In Enforce demand due dates scheduling, these lead


times will be scheduled backwards from due date and need
not respect the scheduling windows assigned to the supply.

Valid values: Yes/No


Default value: Yes
Available in 12.1.1 and upwards as well
Note Reference(s)
365112.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4413913
4432428
-1
-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: SCO Dual Variables Tolerance


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_DUALVAR_TOL
Parameter used internally for optimization. Consult Oracle Development and
Oracle Support before modifying this profile option.
Valid values: Numeric
Default value: 0.000000001

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
Yes
No
Yes
No
No
No
No
No
No
No

MSO: SCO Reduced Cost Tolerance


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_REDCOST_TOL
Parameter used internally for optimization. Consult Oracle Development and
Oracle Support before modifying this profile option.
Default value: 0.000000001

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: SCO TRIANGULATION


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SCO_TRIANGULATION
Internal (hidden profile)

Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: STL Buffer Size


Profile Code
Profile Option Name
Description
Note Reference(s)

MSO
MSO_STL_BUFFER_SIZE
Not used.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2953151
-1
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Schedule Across Breaks


Profile Code
Profile Option Name
Description

MSO
MSO_SCHEDULE_ACROSS_BREAKS
Determines whether the scheduling engine starts an activity before a break
and ends it after the break. Valid values are:

Yes

No - verify that every activity has enough resource in one


shift (otherwise the activities are moved to the end of the
horizon). Can be defined at the site level.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Schedule All Firm Planned Orders First


Profile Code
Profile Option Name
Description

MSO
MSO_SCHEDULE_FIRM_PLANNED_ORDERS_FIRST
No documentation on this profile option. It appears that this can work to
make sure Firm Planned Orders are scheduled first before any new planned
orders are created. This should work in tandem with other Firm profiles and
could create a Natural Time fence.
Valid values: Yes/No
Default value: No

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Schedule Simultaneous Resources Across


Breaks
Profile Code
Profile Option Name
Description

MSO
MSO_SCHEDULE_ACROSS_BREAKS_FOR_SIM_RES

Details added to recent ASCP Guide - E13358-08


(page A-125)
Valid Values: Yes/No
Default Value: Yes (can schedule across break)
Specifies whether the simultaneous resource
activity is allowed to go across calendar breaks or
not.
This profile option behaves the same as profile
option MSO: Schedule Across Breaks. However, it
only applies to simultaneous resources.
MSO: Schedule Across Breaks: Determines
whether the scheduling engine starts an activity
before a break and ends it after the break. If set to
No, verify that every activity has enough resource
in one shift
(otherwise the activities are moved to the end of
the horizon).
The setting would depend on whether or not the
requirements on the simultaneous resource(s) are
"breakable". It would be best for this to be in sync
with the principal, but there may be cases where
we really can't allow a simultaneous requirement to
span a break even though the principal may be
able to. Generally, we expect the principal resource
to be the one dictating the behavior, but this allows
for the simultaneous resource to actually be
somewhat more restrictive. If we set "MSO:
Schedule Simultaneous Resources Across Breaks"
to "No", but "MSO: Schedule Across Breaks" to
"Yes", then the user should be prepared to see
requirements being pushed out by the
simultaneous if necessary.
When your requirement for the simultaneous is
non-breakable and too long to fit in shift time.
1. MSO: Schedule across break is set to No/

should be Yes
2. MSO: Schedule Simultaneous Resources
Across Breaks should also be yes.
We have this profile precisely to avoid that the
simultaneous would be longer because of breaks.
i.e. the labor finishing his job after the machine has
finished during the night.
Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5028133
-1
-1
No
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Schedule window width


Profile Code
Profile Option Name
Description

MSO
MSO_SCHEDULE_WINDOW_WIDTH
Defines time window (days) that the scheduling engine looks for its primary
resource. If the primary resource is not in this window, the scheduling engine
moves to an alternate resource. Can be defined at the site level. Valid
values are:

Integer >=0

Default Value - 8 days


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Scheduler Time Step


Profile Code
Profile Option Name
Description

MSO
MSO_SCHEDULER_TIME_STEP
According to bug 2920076 this profile should have been removed from the
application and the user guide in 2003.
** However, the User Guide states that this is reserved for future use **

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Scheduling Activity Selection Window


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SELECTOR_FORWARD_WINDOW_SIZE
no documentation on this bug

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Scheduling Window UOM


Profile Code
Profile Option Name
Description
Note Reference(s)

MSO
MSO_DETAILED_SCHEDULING_WINDOW_UOM
Not currently used in ASCP per Bug 4007906

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4007906
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Setup Pattern Calculation Window


Profile Code
Profile Option Name
Description

MSO
MSO_SUB_HORIZON_CYCLE_FOR_HLS_SDS
A window is calculated by multiplying the Resource's Sequencing window
value by the value in this profile. Valid values are:

Integer

The relative mix of various setup types that fall into this window is calculated
and then applied to each resource sequencing window.
When MSO: Use Sequencing Template is set to Yes, ASCP uses this
calculated mix of setup types to determine the desired spots.
Default Value - 1
Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4113649
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Simplex Feasibility Tolerance


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_EPRHS
Parameter to set the simplex feasibility tolerance.
Values: Number between e-9 and e-4

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5090041
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Simplex Optimality Tolerance


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_EPOPT
Parameter to set the optimality tolerance for the simplex algorithm.
Values: Number between e-9 and e-4
Default: e-6

Note Reference(s)

Bug Reference(s)

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

4164443
4416504
5090041
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Simplex Perturbation Constant


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_CPX_PARAM_EPPER
This profile option is a parameter to set the simplex perturbation constant.
Provides a perturbation constant for the Planning Engine. Sets the amount
by which the Planning Engine perturbs the upper and
lower bounds on the variables when a problem is perturbed.
The value is specified as any number greater than e-8. This value is
defaulted by CPLEX. Use for SCO. This profile should not be changed
unless directed by Oracle Development
Available in 12.1.1 and upwards
147222.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Simplex Perturbation Limit


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_PERLIM
Parameter for the simplex perturbation limit.
Values: Integer > 0

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Simplex Perturbation Parameter


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_PERIND
Provides a perturbation constant for the Planning Engine.
Sets the amount by which the Planning Engine perturbs the upper and lower
bounds on the variables when a problem is perturbed.
Values are 0 and 1.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Simplex Presolve Limit


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_PREPASS
Parameter to set the limit on the number of pre-solves.
Values are -1, 0, and integer > 0

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Simplex Singularity Repair Limit


Profile Code
Profile Option Name
Description

MSO
MSO_CPX_PARAM_SINGLIM
Parameter to set the simplex singularity repair limit.
Values: Integer > 0.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Skip Firm SDS Activities During Justify


Profile Code
Profile Option Name
Description
Note Reference(s)

MSO
MSO_SKIP_FIRM_IN_SEQUENCE_FOR_JUSTIFY
This profile was introduced in R12 for DS. Not used anymore

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8538729
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Slack Hours For Batch Resource


Profile Code
Profile Option Name
Description

MSO
MSO_SLACK_HOURS_FOR_BATCH_RESOURCE
This profile value is used by Oracle Advanced Supply Chain Planning to right
justify the maximum end date for a scheduled batch resource.
The value specified is the amount of slack time (in hours) to delay scheduling
the resource so that other supplies can be included in the same batch even
though they cannot be scheduled as early as the original supply. This means
that the batch must wait for the constrained supply.
Valid values: integer
Default value: null

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Solve Dual Problem


Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_CPX_DUAL
Controls whether the Planning Engine solves the dual problem or the primal
problem.
Valid values: 0 and 1
Default value: See 'Automatic Calculations, page A-1 of the R12.1 ASCP
User Guide.
147222.1

-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Sourcing Allocation Window


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_ALLOCATION_WINDOW
Specifies the Allocation Percentages Satisfaction Period. The constraints are
enforced in a rolling horizon manner. Used with Enforce Sourcing Constraints
enabled in specific plan options.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Split Planned Orders for Assigned Units


Profile Code
Profile Option Name
Description

MSO
MSO_SCO_ASSIGNED_UNITS
This profile option is used by Oracle Advanced Supply Chain Planning
optimized plans only. It specifies if the planning engine should attempt to split
planned orders such that they can be scheduled within a specific day. Valid
values are:

Yes: Create more planned orders with quantities that can be


scheduled by the resource units available within a given day.

No: The planning engine generates larger planned orders


that may require a resource duration spanning several days.

Note that the maximum number of resource units at the routing level will
always be respected.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Split Supplies for SPP Release


Profile Code
Profile Option Name
Description

MSO
MSO_SPLIT_SUPPLIES_FOR_RELEASE
Split Supplies to Ensure 1-1 Pegging in Service Parts Planning During
Release
Set on APS Destination in a distributed environment

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

11882204
-1
No
No
No
No
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Spread Resource Consumption Within


Optimization
Profile Code
Profile Option Name
Description

MSO
MSO_SCO_SPREAD_RESOURCE
This profile specifies how the optimization engine should model resource
consumption is modeled in optimization. Valid values are:

Yes: Consume resources at the first operation. This value


provides improved optimization engine performance.

No: Consume resources at the operation to which they


belong. This value provides improved optimization engine
accuracy.

Default value: Null (interpreted as No)


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9020829
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Substitute Item Penalty


Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SCO_SUB_ITEM_PENALTY
Defines an internal penalty weight for substitute item objective in supply
chain optimization.
Valid values: number > 0
Default: none
228459.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Supplies used for satisfying transient safety


stock
Profile Code
Profile Option Name
Description

MSO
MSO_TRANS_SS_SUPPLY_CHOICE
This profile is used in priority based pegging and can be used in constrained
plans. This profile is used only for transient supplies. It has two values

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

Supplies pegging to lower priority demands


Closest pegged supplies

MSO: Supply Reschedule Window Size for Safety


Stock Pegging
Profile Code
Profile Option Name
Description

MSO
MSO_SS_WINDOW_SIZE
This profile options provides an estimate of the number of days by which the
supply and its associated demand (dependent demand) moves due to
constraints. Valid values are:

Integer > 0

You can use this profile option to specify the number of days a specific
supply can satisfy safety stock demand.
Default Value - Null
Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

3500953
-1
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Oracle Advanced Supply Chain Planning Implementation and User's Guide
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Supply Window Size


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SUPPLY_WIN
Used with priority pegging.

B31553-02
MSC: Use FIFO Pegging
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Synchronize Chargeable Resources to


Respect Hard Links
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SYNCHRONIZE_CHARGES
Not enough information in bugs to define this profile

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Target Inventory Level % of Safety Stock


Profile Code
Profile Option Name
Description

MSO
MSO_TGT_INV_LEVEL
Use this option to specify target inventory levels. If no other method of
calculation is defined for an item-organization target inventory level, the
levels are based on the specified percentage of the safety stock level.

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
MSO: Maximum Inventory Level % of Safety Stock
Yes
No
No
Yes
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

MSO: Transfer Quantity Threshold for Enforceing


Hard Links
Profile Code
Profile Option Name
Description

MSO
MSO_HARD_LINK_TRANSFER_QUANTITY_THRESHOLD
Use this profile option to instruct the planning engine to ignore the hard link
constraints if a transfer quantity is less than or equal to this percent threshold
of the corresponding order quantity.
Valid values are

Number between 0 and 1: Ignores hard link constraints for


transfer quantities less than or equal to this percent threshold

Null: Respects all hard link constraints regardless of the size


of the transfer quantities

Default Value: 0
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

8730427
-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: UOM for converting Changeover Time to


Penalty
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_UOM_TO_CONVERT_CHANGEOVER_TIME_TO_PENALTY
no documentation for this profile

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Upper Limit for Maximum Time Offset for


Hard Links
Profile Code
Profile Option Name
Description

MSO
MSO_HARD_LINK_MAX_OFFSET_UPPERBOUND

Use this profile option to set an upper limit for the


maximum time offset. If a maximum time offset is
higher than this number, the planning engine uses
this number instead of what you set. Valid values
are:
Valid Values: Integer (including 0),null: Use
10,000,000
Default value: Null

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

760046.1

-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Use Breaks in Calculation of Unconstrained


Scheduling Windows
Profile Code
Profile Option Name
Description

MSO
MSO_USE_BREAKS_IN_UNCONSTRAINED
The planning engine calculates an unconstrained scheduling window for
each resource activity and supply in a plan. The scheduling window is
defined by the dates:

Unconstrained Earliest Possible Start Time (UEPST)

Unconstrained Earliest Possible Completion Time (UEPCT)

Unconstrained Latest Possible Start Time (ULPST)

Unconstrained Latest Possible Completion Time (ULPCT).

Valid values are:

Yes - the planning engine does not set any of these dates
during a break even if the calculation places it there.

No - the planning engine does set any of these dates during


a break if the calculation places it there.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Default Value - Yes


1080929.1

-1
Yes
No
No
Yes
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Use Collections Start Time


Profile Code
Profile Option Name
Description

MSO
MSO_USE_COLLECTIONS_START_TIME
Use this profile option to coordinate plan start date and collections start time.
This affects how the plan calculates resource availability. Valid values are:

No - Always use plan start time.

Yes - Use collections start time.

Use Input Demand Plan Start Time or Collections Start Time


- If there is an input demand plan, the planning engine uses
the Input Demand Plan Start Time. Otherwise, it uses the
Collections Start Time.

Use Input Demand Plan Start Time or Plan Start Time - The
planning engine uses the Input Demand Plan Start Time.
Otherwise, it uses the Plan Start Time.

Default Value - Yes


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Use Customer Site in End Item Substitution


Rule
Profile Code
Profile Option Name
Description

MSO
MSO_USE_CUSTSITE_IN_ITEMSUBST
Could not find information about this profile in user guides.
For GOP, this profile is NOT in R12.0 or 12.1.x
For SCO Planning, the profile is included in 11.5.10, R12.0 and above
Introduced by SCO and we should be using that to set the partial fulfilment
flag (all_or_nothing) flag appropirately based on that.
This profile indicates if set to No, that rules are defined only at the customer
level and not at the site level.
Used in GOP as well, per bug 5048642
When profile option MSO_USE_CUSTSITE_IN_ITEMSUBST is set to N,we
use specific customer id and customer site id is null to select the specific
rule.
If there is more than one records, we will randomly select one.
GOP like SCO assumes that the user has run the script to set the customer
site id to NULL in the ODS prior to running the plan.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5048642
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
Yes

MSO: Use Decomposition in Optimization


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_USE_DECOMPOSITION
MSO: Use Decomposition in Optimization. This is applicable for Service
Parts Planning and Distribution Planning

No
No
No
No
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Use Discrete Job Resource Usage to


Consume Resource Capacity
Profile Code
Profile Option Name
Description

MSO
MSO_USE_RESOURCE_HOURS_PRECONSUME
Use this profile to instruct the planning engine what data to use for resource
load when it determines resource availability. Valid values are:

Yes: The planning engine uses resource hours to determine


the resource load. Use this value if you do not attend to work
in process timestamps, your work in process times are not
adjusted for efficiency, and you specify resource hours.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No: The planning engine uses timestamps to determine the


resource load. Use this value if your work in process times
are adjusted for efficiency. If work in process is scheduled by
the planning engine scheduling process, choose this value.

Default Value - No
745977.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Use Effectivity Date to Infer End Item


Substitution Priority
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_USE_EFCDATE_FOR_PRIO_IN_ITEMSUBST
Could not find information about this profile in user guides.
564241.1

-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Use Existing Supplies in Alternate BOM/Subs.


Comp
Profile Code
Profile Option Name
Description

Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_SCO_EXIST_SUPP_ABR_SUBSCOMP
This profile will enable the user to adjust the objective sequence so that
optimization will always go to primary BOM before going to alternate BOM.
Controls how SCO will use the existing supply in alternate BOM or substitute
component paths.

NULL or 0 (zero) is the default and indicates all the existing


supply will be used before creating new planned orders in
primary path.

1 means SCO will consume supplies in subs comp path but


will not consume supplies in alternate BOM path.

2 means SCO will consume supplies in alt bom path but will
not consume supplies in substitute component path.

NOTE: This profile, when used with the profile "MSO: Postpone Use of
Alternates to Latest Possible Time" may give you different results. From Note
365112.1 - also see Note 567667.1 for clarification on the use of this profile
in an Enforce Due Date (EDD) plan.
365112.1

-1
-1
Yes
No
No
Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
Yes
No
Yes
No
No
No
No
No
No
No

MSO: Use Item Shelf Life Days in Scheduling


Buy/Transfer Orders
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_USE_SHELF_LIFE
This profile option specifies whether to use item shelf life days as a maximum
time offset between operations that produce and consume the item. Valid
values are:

Yes - the planning engine uses item shelf life days as a


maximum time offset if a maximum time offset value is not
specified on the routing step that produces the item.

No - the planning engine does not use item shelf life days as
a maximum time offset between operations.

Default Value - No
415101.1

-1
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Use JIT dates from high level scheduling


results
Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_USE_JIT_DATES_FROM_HLS
Not currently used in ASCP per Internal Bug 4007906

No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Use Of Assigned Units In Scheduling


Profile Code
Profile Option Name
Description

MSO
MSO_USE_OF_ASSIGNED_UNITS_IN_SCHEDULING
Controls the number of resource units to be used when scheduling a
resource activity. Valid values are:

Variable - Permits a choice ranging between a minimum of


one unit and a maximum value equivalent to the assigned
units specified on the routing for the item.

Fixed at Routing Value - Forces the scheduling engine to


always choose the number of assigned units specified in the
routing when scheduling a resource activity. It is
recommended that you choose this option when you do not
need to use the flexibility of the Variable option.

Note: The assumption that the activity duration is less when more units are
chosen is only valid for the basis type of Item specified in the Operation >
Resources form.
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Use Optimization and Decision Rules for


Simulation
Profile Code
Profile Option Name
Description

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSO
MSO_ONLINE_SCO
For online planner sessions against constrained plans with decision rules or
optimized plans. Valid values are:

Yes: To rerun the optimization and decision rules-based


decisions during the online planner session

No: To retain the optimization and decision rules-based


decisions from the initial planning run for the online planner
session Valid Values: Yes/No

Default Value - No (Do not run Optimization / Decision Rules during Online
Planning)
365112.1

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Use SCO Time Aggregation


Profile Code
Profile Option Name
Description

MSO
MSO_USE_SCO_INT_TIMEAGGREG
Determines whether the Planning Engine should use different aggregate time
buckets than specified in the aggregation settings of the plan options. You
can specify large values for daily and weekly buckets for Planning Engine
output, but this increases Planning Engine calculation time. Valid values are:

True - The Planning Engine uses aggregate time buckets


specified in MSO: Optimization Daily Aggregation Buckets
and MSO: Optimization Weekly Aggregation Buckets. The
period time bucket is derived.

False - The Planning Engine uses the same aggregate time


buckets as specified in the Aggregation tab of the Plan
Options window.

Default Value - False


Note Reference(s)

Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Use Safety Lead Time


Profile Code
Profile Option Name
Description

MSO
MSO_USE_SAFETY_LEAD_TIME
Use this profile option to instruct the planning engine how to plan material to
be completed early as a safety buffer. Valid values are:

Yes - Use safety lead-time planning. The value in item


attribute Safety Stock Percent is the safety lead-time in days;
for example, if safety lead-time is two days, enter 200.
No - Use non-transient / transient safety stock planning. The
value in item attribute Safety Stock Percent is a percent of
demand.

Default Value - No
Note Reference(s)
872475.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Use Sequencing Template


Profile Code
Profile Option Name
Description

MSO
MSO_NEED_USE_SOFT_PATTERN
This profile option specifies whether Oracle Advances Supply Chain Planning
tries to schedule activities in accordance with a determined preferred
sequence of activities. Valid values are:

Yes - the planning engine determines a preferred sequence


of activities on resources and tries to schedule activities in
accordancewith the sequence. This setting is recommended
if the sequence dependent setup resource is the primary
bottleneck.
No - the sequence of activities is determined more
dynamically when scheduling other activities.This setting is
recommended if there are multiple bottleneck resources.

Default value: No
Note Reference(s)
415276.1
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

9500377
-1
-1
No
No
No
Yes
No
No
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No

MSO: Use Shift Definitions When Scheduling Lead


Times
Profile Code
Profile Option Name
Description

MSO
MSO_USE_SHIFT_TIMES_IN_LEAD_TIME_SCHEDULING
Determines whether the planning engine needs to take into account shift
times for calculating lead-times on shipping, receiving, and carrier calendars.
Valid values are:

Yes - Considers shift definitions for calculating lead-times on


calendars in case of constrained plans.
No - Shift definitions are not considered when offsetting leadtimes on calendars.

If the plan planning mode is Constrained (Without Detailed Scheduling), the


planning engine does not use this profile option. (Default)
Note Reference(s)
950994.1
978623.1
1301132.1
Bug Reference(s)
Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


-1
-1
-1
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Use Up Existing Supply of Primary


Components Before Substitute
Profile Code
Profile Option Name
Description

MSO
MSO_SCO_SUBSCOMP_SEQ
Use this profile option to specify whether to use the supply of substitute
components or the primary component first. Valid values are:

Yes: Use the supply of the primary component before using


the supply of the substitute components

No: Use the supply of the substitute components before


using the supply of the primary component

Note Reference(s)

834624.1

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

-1
Yes
No
No
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSO: Write Inline forecasting flat files


Profile Code
Profile Option Name
Description

MSO
MSO_FORECASTER_WRITE_FLATFILE

If this profile is set to "Yes" then Inline forecasting


calculation details are written in the flat files. This
should only be set if you would like to debug the
inline forecasting results.

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
All Plan Types
Enforce Constraints Not Optimized
Enforce Constraints Optimized
Disable Constraints Not Optimized
Disable Constraints Optimized
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

7621495
-1
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No

MSR: Budget Category Set


Profile Code
Profile Option Name
Description

MSR
MSR_BUDGET_CATEGORY_SET
Use this profile option to specify the categories that you can use when
defining budgets in Oracle Inventory. Valid values are:

NULL - Define budgets with any category.

Any category set: Define budgets only with categories that


are in the category set.

Default Value - NULL


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No

MSR: Budget Enditem Favor Factor


Profile Code
Profile Option Name
Description
Note Reference(s)

MSR
MSR_BUDGET_ENDITEM_FAVOR_FACTOR
Could not find details of this profile in user guides.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

5182644
-1
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No

MSR: Budget Heuristic


Profile Code
Profile Option Name
Description
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

MSR
MSR_BUDGET_HEURISTIC
Profile to enable use of budget heuristic for single level supply chain instead
of use of budget LP
1081430.1

-1
Yes
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No

MSR: Enable Cycle Stock Adjustment


Profile Code
Profile Option Name
Description
Note Reference(s)

MSR
MSR_ENABLE_CYCLE_STOCK_ADJUSTMENT
Enables cycle stock adjustment to safety stock

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

13936760
-1
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No

MSR: Postponement Factor


Profile Code
Profile Option Name
Description

MSR
MSR_POSTPONEMENT_FACTOR
Specifies maximum depth in the bill of materials and sourcing tree to which
uncertainty must be postponed. Valid values are:

Integers >= 0

Default Value - 10
Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSR: Probability Distribution Type


Profile Code
Profile Option Name
Description

MSR
MSR_PROB_DISTR_TYPE
Determines probability distribution type associated with forecast sets as input
to Oracle Inventory Optimization. Valid values are:

Probabilities - Demand uncertainty is stated in terms of a


(non-cumulative) probability distribution.
Cumulative Probabilities - Demand uncertainty is stated in
terms of a cumulative probability distribution.

Default Value - Probabilities


Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Oracle Advanced Supply Chain Planning Implementation and User's Guide


Yes
No
No
Yes
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No

MSR: Safety Stock Holding Strategy


Profile Code
Profile Option Name
Description

MSR
MSR_SS_HOLDING_STRATEGY
Specifies where safety stock should be held when the carrying cost is the
same for an item in the destination organization and a source organization.
Valid values are:

0 - causes the safety stock to be held at the destination


organization.

1 - causes the safety stock to be held at the source


organization.

Default Value - Source Organization


Note Reference(s)

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

2260006
Oracle Advanced Supply Chain Planning Implementation and User's Guide
-1
Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

MSR: Warehouse Capacity Granularity


Profile Code
Profile Option Name
Description

MSR
MSR_ORGANIZATION_WAREHOUSE_CAPACITY
Profile to indicate whether warehouse capacities have been defined at Org or
Cat-Org level. Valid values:

Category-Organization Level

Organization Level

Note Reference(s)
1453788.1

Bug Reference(s)

Document References(s)

Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

13936760
14369385
13820125
-1
-1
-1
-1
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No

MSR: Warehouse Category Set


Profile Code
Profile Option Name
Description
Note Reference(s)

MSR
MSR_WAREHOUSE_CATEGORY_SET
Category set to use for storage capacities.

Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

14141868
-1
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No

POR: Sync up Need by date on IR with OM


Profile Code
Profile Option Name
Description

POR
POR_SYNC_NEEDBYDATE_OM
Required to be Yes for the rescheduling or Internal Reqs (IR) and Internal
Sales Orders (ISO) to be called to synchronize the IR/ISO when
rescheduled.
Only available when EBS source is on 12.1
Set on EBS Source in a distributed environment

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

No
No
No
Yes
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

WIP:Discrete Job Prefix


Profile Code
Profile Option Name
Description

WIP
WIP_JOB_PREFIX
Set on EBS Source in a distributed environment
Default prefix for discrete job name

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
Yes
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No

WSM: Create Job Level BOM and Routing Copies


Profile Code
Profile Option Name
Description

WSM
WSM_CREATE_LBJ_COPY_ROUTING
Create Job Level BOM and Routing Copies for OSFM jobs
Set on EBS Source in a distributed environment

Note Reference(s)
Bug Reference(s)
Document References(s)
Dependent Profiles
11.5.10 Profile
12.1.1 Profile
Data Collections
Item Mass Maintenance
Advanced Supply Chain Planning
All Plan Types
Unconstrained Plan
Constrained EDD
Constrained ECC
Distribution Planning
Collaborative Planning
Inventory Optimization
Service Parts Planning
Rapid Planning
Demand Planning
Demantra
Strategic Network Optimization
Advanced Planning Command Center
Manufacturing Operations Center
Global Order Promising

Yes
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

Das könnte Ihnen auch gefallen