Beruflich Dokumente
Kultur Dokumente
THRESHOLD ATTEMPTED
Points Attempted: 0
ALL PROJECTS
TARGET FINDER
The following fields are required, but the values have no bearing on EA Prerequisite 2 compliance. Use the Target Energy
Performance Results calculator on the ENERGY STAR website to generate the values. If using prescriptive compliance paths
(Options 2 or 3), leave the Design energy consumption and cost values blank in the Target Finder website, and set the Design
values equal to the Target values in this form.
Design
Target
metric tons/year
metric tons/year
Upload
Files:
The building is not able to get a Target Finder score because the tool does not support the primary
building type of the project building and/or the project is not located in the United States. (Optional)
PREREQUISITE COMPLIANCE
Total gross square footage:
13,220
sf
The content highlighted in yellow above is linked to PIf2, PIf3, SSc2, EAp1, EAc1, EAc2, EAc6,
MRc1.1 & MRc1.2.
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 1 of 13
Trace
Solar/site recovered
ASHRAE 90.1-2007
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 2 of 13
List the ASHRAE addenda used in the modeling assumptions, if any. (Optional)
Zip/Postal Code:
96913
Weather file:
AGANA, GUAM
Climate zone:
ZONE 1A
List the climatic data from ASHRAE Standard 90.1-2007 Table D-1. Specify if another source is
referenced for HDD & CDD data.
Heating Degree Days:
10,690
13,220
13,220
100
The content highlighted in yellow above is linked to PIf2, PIf3, SSc2, EAp1, EAc1, EAc2, EAc6,
MRc1.1 & MRc1.2.
Gross square footage used in the energy model, if different than gross square
footage above: (Optional)
11,793
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 3 of 13
For all elements included in the Architect's scope of work for the project building, the project building design complies with
all ASHRAE Standard 90.1-2007 mandatory provisions (Sections 5.4, 6.4, 7.4, 8.4, 9.4 and 10.4) or USGBC approved
equivalent standard mandatory provisions, and the information provided regarding the proposed case energy model in
Section 1.4 is consistent with the building design.
For all elements included in the Mechanical Engineer's scope of work for the project building, the project building design
complies with all ASHRAE Standard 90.1-2007 mandatory provisions (Sections 5.4, 6.4, 7.4, 8.4, 9.4 and 10.4) or USGBC
approved equivalent standard mandatory provisions, and the information provided regarding the proposed case energy
model in Section 1.4 is consistent with the building design.
For all elements included in the Electrical Engineer's scope of work for the project building, the project building design
complies with all ASHRAE Standard 90.1-2007 mandatory provisions (Sections 5.4, 6.4, 7.4, 8.4, 9.4 and 10.4) or USGBC
approved equivalent standard mandatory provisions, and the information provided regarding the proposed case energy
model in Section 1.4 is consistent with the building design.
Upload
Files:
Upload
Files:
Upload
Files:
Upload
Files:
Space Area
(sf)
Regularly
Unconditioned
Occupied Area
Area
(sf)
(sf)
Typical
Hours/Week
in Operation
Assembly Hall
Assembly
7,773
40
Office
Office
2,377
2,377
40
Rest room
Rest room
524
40
Lobby
Lobby
1,119
40
11,793
2,377
20.16
Totals
Percentage of total (%)
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 4 of 13
Proposed Design
Total
Notes:
1 Baseline design and proposed design unmet load hours each may not exceed 300
2 Unmet load hours for the proposed design may not exceed the baseline design by more than 50 hours.
Upload
Files:
Energy
Type
Electricity
Utility Company
Name
GPA
Baseline
Proposed
2
Virtual Rate Virtual Rate2
($ per unit
($ per unit
energy)
energy)
0.499
Units of
Energy
0.499 kWh
Units of
Demand
kW
Natural Gas
+
LEED 2009 for New Construction and Major Renovations
EA Prerequisite 2: Minimum Energy Performance
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 5 of 13
Notes:
1 Per ASHRAE 90.1-2007 G2.4, project teams are allowed to use the state average energy prices published by DOE's EIA for commercial
building customers, available on EIA's website (www.eia.gov). If project uses backup energy for on-site renewable energy, please specify the
rate of backup source energy.
2 Rate is defined as the total annual charge divided by the metered energy from the plant for each resource.
If the proposed and baseline rates vary significantly, describe the building input parameters (e.g. demand reduction
measures) leading to the variation in energy rates, and provide detailed information regarding the utility rate structure
including all demand and energy charges, and the seasonal and time-of-use structure of the utility tariff. (Required when
proposed and baseline rates vary by more than 10%)
The proposed design input parameter is to meet 90.1 2007 minimum enveloped and providing high efficient lighting and hvac system,
providing domestic solar hot water system and 10 kw PV panel for electric use.
Upload
Files:
End
Use
Interior Lighting
Process
In the table below, list each energy end use for the project (including all end uses reflected in the baseline and
proposed designs). Then check whether the end-use is a process load, select the energy type, and list the energy
consumption and peak demand for each end-use for all four baseline design orientations.
Baseline
Design
Energy
Type
Electricity
Units of Annual
Energy & Peak
Demand
Energy Use kWh
Demand
kW
Baseline
Building
Results
29,802
29,802
29,802
29,802
29,802
11.9
11.9
11.9
11.9
11.9
105,962
105,348
105,806
106,379
105,873.75
56.6
55.9
56
56.1
56.15
8,593
8,559
8,571
8,601
8,581
4.6
4.5
4.5
4.5
4.53
Energy Use
Exterior Lighting
Demand
Space Heating
Electricity
Space Cooling
Electricity
Pumps
Electricity
Electricity
kW
Heat Rejection
kW
kW
kW
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 6 of 13
Fans-Interior
Electricity
Demand
kW
125,872
126,809
124,246
122,331
124,814.5
14.4
14.5
14.2
14.2
14.33
34,725
34,725
34,725
34,725
34,725
14.5
14.5
14.5
14.5
14.5
3,888
3,888
3,888
3,888
3,888
1.1
1.1
1.1
1.1
1.1
Energy Use
Fans - Parking
Garage
Demand
Service Water
Heating
Electricity
Receptacle
Equipment
Electricity
kW
Energy Use
Refrigeration
Equipment
Energy Use
kW
Demand
Demand
Energy Use
Cooking
Demand
Industrial
Process
Energy Use
Elevators and
Escalators
Energy Use
Demand
Demand
Energy Use
Demand
1,053.77
1,054.75
1,047.61
1,043.14
1,049.82
131.75
1
Notes:
1 Determined using Section 1.9 cost calculations after Section 1.9A is complete. Annual process energy costs must be at least 25% of the total
energy costs for the proposed design. Process energy costs should be modeled to accurately reflect the proposed building. To claim process
cost savings, use an exceptional calculation in Section 1.7.
The project does not comply with minimum compliance requirements for process energy modeling (determined after Section
1.9A is complete). Describe any exceptions, special circumstances or modeling difficulties that occurred relating to the
process energy noncompliance.
Upload
Files:
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 7 of 13
End
Use
Interior Lighting
Process
Baseline
Units of Annual
Energy & Peak
Demand
Energy Use kWh
Demand
Proposed
Design
Energy
Type
Building
Results
29802
Electricity
kW
Units of Annual
Energy & Peak
Demand
11.9
Demand
Energy Use
Energy Use
Demand
Demand
Building
Results
%
Savings
19,424
34.82
kW
Exterior Lighting
Space Heating
Space Cooling
56.15
kW
4.53
Demand
Demand
Demand
14.33
Demand
Fans - Parking
Garage
Energy Use
Energy Use
Demand
Demand
Service Water
Heating
Receptacle
Equipment
Interior Lighting
- Process
Energy Use
Energy Use
Demand
Demand
Refrigeration
Equipment
Energy Use
Energy Use
Demand
Demand
Energy Use
Energy Use
Demand
Demand
Industrial
Process
Energy Use
Energy Use
Demand
Demand
Elevators and
Escalators
Energy Use
Energy Use
Demand
Demand
Demand
Demand
14.5
1.1
Demand
53.9
6,381
0
kW
5
8,380
2.34
kW
4.3
45,286
63.72
kW
12.1
22.1
99.94
kW
3888
Electricity
kW
Demand
113,217
-6.94
kW
34725
Electricity
kW
0
kW
124814.5
Electricity
kW
Demand
8581
Electricity
kW
Fans-Interior
Electricity
kW
105873.75
Heat Rejection
kW
Pumps
Electricity
0.1
3,888
0
kW
1.1
Cooking
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 8 of 13
Energy Use
Energy Use
Demand
Demand
1,049.82
670.79
131.75
13.34
Energy savings from process energy should be claimed via Section 1.7 Exceptional Calculation Methodology. Please recheck and revise values as appropriate.
Process
Subtotal
Units
kWh
MMBtu
Proposed
Energy Use
38,613
307,684.25
196,598.1
131.75
1,049.82
670.79
Natural Gas
Totals
Total
Energy Use
Process
Subtotal
Units
Total
Energy Cost
Proposed
Energy Cost
Electricity
19,267.89
153,534.44
98,102.45
Natural Gas
19,267.89
153,534.44
98,102.45
Total
Table EAp2-8. Section 1.6 Energy Cost Summary (Manual Cost Input) - Baseline Case
Baseline Costs ($)
Energy Type
Electricity
0 rotation
90 rotation
84,004
84,083
180rotation
83,514
270 rotation
83,157
Building
Performance
83,689.5
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 9 of 13
Natural Gas
0
0
Totals
84,004
84,083
83,514
83,157
83,689.5
Table EAp2-9. Section 1.6 Energy Cost Summary (Manual Cost Input)
Baseline
Energy Type
Units
Proposed
Section 1.6
Energy Cost
Process
Section 1.6
Energy Cost
Electricity
19,267.89
83,689.5
53,529
Natural Gas
19,267.89
83,689.5
53,529
Totals
Renewable
Energy
Source
Allocation
On-Site only
Renewable
System
Owner
Building Owner
Backup
Rated
1
Capacity
Energy Type
Electricity
4.5
Annual
Energy
Generated
Units
Annual
Energy Cost
($)
(Optional2)
221 kWh
114,920
221 kWh
114,920
Energy savings -
0.75 MMBtu
114,920
Notes:
1 Per ASHRAE 90.1 G2.4 Exception, baseline performance shall be based on the energy source used as backup energy or on the use of
electricity if no backup energy source is specified.
2 Annual energy cost is required to document credit compliance with EA Credit 2, if attempted.
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 10 of 13
Proposed Renewable
Energy Savings
Units
Electricity
110.28
Natural Gas
110.28
Total
Energy Type
Electricity
Units
kWh
Natural Gas
Totals
MMBtu
Proposed
Section 1.6
Total Energy
Use
Process
Subtotal
Section 1.8
Renewable
Energy
Savings
Section 1.7
Energy
Savings
Section 1.6
Energy Use
Total Energy
Use
38,613
307,684.25
196,598.1
221
196,377.1
131.75
1,049.82
670.79
0.75
670.04
36.18
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 11 of 13
Baseline
Energy Type
Section 1.6
Total Energy
Cost
Process
Subtotal
Units
Proposed
Section 1.8
Renewable
Energy
Savings
Section 1.7
Energy
Savings
Section 1.6
Energy Cost
Total Energy
Cost
Electricity
19,267.89
83,689.5
53,529
110.28
53,418.72
Natural Gas
19,267.89
83,689.5
53,529
110.28
53,418.72
Totals
23.02
36.17
13
Proposed EUI
Electricity (kWh/sf)
Interior Lighting
2.254
1.469
Space Heating
Space Cooling
8.009
8.564
Fans - Interior
9.441
3.426
2.627
0.002
Receptacle Equipment
0.294
0.294
Miscellaneous
0.649
1.116
23.274
14.871
Subtotal
Miscellaneous
Subtotal
0.001
0.001
Other (kBtu/sf)
Miscellaneous
Subtotal
79.411
50.741
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 12 of 13
End Use
Energy Savings
(%)
Proposed Case
(%)
9.68
9.88
9.34
Space Heating
Space Cooling
34.41
57.59
-6.61
Fans - Interior
40.56
23.04
71.58
11.29
0.01
31.24
Receptacle Equipment
1.26
1.98
Miscellaneous
2.79
7.51
-5.56
Upload
Files:
ADDITIONAL DETAILS
Special circumstances preclude documentation of prerequisite compliance with the submittal
requirements outlined in this form.
The project team is using an alternative compliance approach in lieu of standard submittal paths.
SUMMARY
EA Prerequisite 2: Minimum Energy Performance Compliance
Documented:
Check Compliance
Version 5.0
Copyright 2009 U.S. Green Building Council. All Rights Reserved.
Save Form
Page 13 of 13