RAMGARH GAS THERMAL POWER PLANT

A
PRACTICAL TRAINING & INDUSTRIAL VISIT REPORT
Submitted for the partial fulfillment of the requirement of the

Degree
of

BACHELOR OF TECHNOLOGY
in

ELECTRICAL ENGINEERING
Submitted To:

Submitted By

Prof. Vidya Sagar Kalla

Jitendra Kumar

(Head, Electrical Engg.)

(IV B.Tech., VII Sem)


Department of Electrical Engineering
S.L.B.S Engineering College,
Jodhpur (Raj.)
Rajasthan Technical University,
Kota (Raj.)

Session-2014-2015

CERTIFICATE
This is to certify that practical training & industrial visit report entitled RAMGARH GAS
THERMAL POWER PLANT being submitted by JITENDRA KUMAR (B.Tech IV Year VII Sem.) for
the partial fulfillment of the requirement of the degree of

Bachelor of Technology in Electrical

Engineering to the Department of Electrical Engineering of S.L.B.S Engineering College, Jodhpur is a


record of seminar given by him/her on his practical training & industrial visit during the period from
02/06/2014 to 30/06/2014.

Mr. Manish Sharma

Prof. Vidya Sagar Kalla

(Asst. Prof., Electrical Engineering)

(Head, Electrical Engineering)

Date:
Place:

ACKNOWLEDGEMENT
an engineer with theortical knowledge is not a complete engineer. practical knowledge is very important to
develope and to apply engineering skills. It gives me a good pleasure
to have an opportunity to acknowledge and to express to those who were associated with me during my
training at Ramgarh Gas Thermal Power Plant.
Special thanks to Mr. Sawantaram (Executive Engineer) for providing me with an opportunity to
undergo training under able guidance. I express special thanks and gratitude to
Ramgarh Gas Thermal Power Plant authority for allowing me to undego the training.
I Will always thanks to them for their constant interest and excellent guidance in my training work,
morever for providing me with an opportunity to work and gain experience.

Jitendra kumar
(B. Tech. IV Year, VII Sem.)
Roll No 11ESLEE011

CONTENTS
Page No
1. Introduction About RGTPP

1.1 First

Unit

1.2 Second Unit


1.3 Availibility Of Water

2
3

1.4 Electrical Transmission System


1.5 Expected System Operation

3
3

1.6 Gas Transportation System

2. Power Plant Cycle

2.1 Open Cycle

2.2 Combined Cycle

2.3 Advantage Of Combined Cycle

2.4 Brayton Cycle

2.5 Rankine Cycle

3. Brief Introduction To Plant Operation

4. Gas Turbine And Their Equipments

4.1 Compressor

4.2 Combustor

4.3Transiton Pieces

4.4 Turbine

4.5 Exhaust

10

4.6 Starting System

10

4.7 Lubricating Oil System

10

4.8 Air Intake System

11

4.9 H.R.S.G. And Steam Turbine Equipments

12

4.10 Condensant Circuit Equipments

12

4.11 Feed Water Curcuit

12

4.12 Common Support System For GT And ST

13

5. Constructional Details of Gas Turbine

14

5.1 Compressor Section

14

5.2 Combustion Section

14

5.3 STG (Steam Turbine Generator)

16

5.4 Heat Recovery Steam Generator (H.R.S.G.)

17

5.5 Water & Steam Cycle Equipment

19

5.6 HP Bypass & LP Bypass(HPBP & LPBP)

19

5.7 Auxillaries

20

6. Constructional Details Of Generator And Exciter

21

6.1 Stator

21

6.2 Rotor

24

6.3 Bearings

24

6.4 Generator And Air Cooler

27

6.5 Excitation System

27

7. 132 KV Switch Yard

28

8. Conclusion