Beruflich Dokumente
Kultur Dokumente
www.elsevier.com/locate/solener
b,*,1
Department of Renewable Energy and Water, Technological Institute of the Canary Islands, Playa de Pozo Izquierdo s/n,
35119 Santa Luca, Gran Canaria, Canary Islands, Spain
b
Department of Mechanical Engineering, University of Las Palmas de Gran Canaria, Campus de Tara s/n,
35017 Gran Canaria, Canary Islands, Spain
Received 25 September 2002; received in revised form 7 July 2004; accepted 9 August 2004
Available online 18 September 2004
Communicated by: Associate Editor Cornelis P. van Dam
Abstract
In this paper a model is presented for the technical and economic sizing of the various components that make up
medium sized wind-powered pumped hydrostorage systems. A further aim of this model is the optimisation of the operation of such systems, thereby making full use of the synergy of the unit as a whole.
A general model is described for use as an analytical tool in implementing such systems in topographically suitable
sites with sucient wind resources. The general model developed allows for six strategies for the system operating conguration. Each strategy is based on the hypothesis that there is a centralised operator to control all the system components, except for the load systems.
The characteristics and unit energy cost of each technically feasible combination of components are determined by
applying the model. This enables the selection of the most viable composition for the system from an economic point of
view given certain technical restrictions.
2004 Elsevier Ltd. All rights reserved.
Keywords: Wind penetration; Pumped storage; Model
1. Introduction
In order to satisfy demand the energy producing
companies have traditionally used electricity generating
0038-092X/$ - see front matter 2004 Elsevier Ltd. All rights reserved.
doi:10.1016/j.solener.2004.08.006
383
Nomenclature
maximum percentage of electrical energy demand that can be met by electrical wind-sourced energy without aecting the safety and stability of the system, %
b
parameter which can take a value between 0 and 1
d
the percentage d of peak demand which has to be covered with hydraulic energy, %
g0
eciency of the PS
g
eciency of the HP and its electrical system
g01
eciency of the pumps P1
g02
eciency of the pumps P2
u
wake factor
q
water density, kg/m3
n
reliability factor of the WT
C(k, j) cost of the unit energy supplied by the conguration system k operating in accordance with strategy i,
Euros/kW h
C(j, i)
minimum local cost of unit energy supplied which is obtained amongst the Nj congurations, Euros/
kW h
C(PCP(t)) CP production cost, Euros/kW
CF
capacity factor of the WP, %
CI
the investment costs of the electrical and control infrastructure, Euros
Cmin
minimum overall cost of the unit energy supplied, Euros/kW h
CP
conventional electrical generator set
CPS
conventional electrical power system
CS
control system
DLS(t) electrical demand in time t, kW h
DLS,max maximum peak demand, kW
ECPS(t) conventional energy of the CPS in time t, kW h
EHP(t) hydraulic energy of the HP in time t, kW h
Etotal(t) the total energy generated by a combination of components which must satisfy the demand DLS(t), kW h
EWP(t) wind energy of the WP in time t, kW h
g
acceleration due to gravity, m/s2
he
height of the rotor shaft of the WT, m
Hg
gross height, m
Hl
hydraulic losses, m
Hn
net height, m
HP
hydroelectric plant
hr
height of wind speed measurement, m
HT
hydraulic turbine and its corresponding electrical generator
Hu
useful height, m
IRR
the internal rate return, %
L
number of years over which the investment in the system is to be recovered, years
LR
lower reservoir
LS
load system
M
number of initial dierent congurations of the system which can be analysed on the hypothesis that each
subsystem can meet the demand by itself
nc
number of conventional generator sets that make up the CPS
ncc
number of CPs connected
nc0,j
initial number of CP units of type j (j = 1, . . . ,Ncp)
Ncp
number of dierent types of CP
Nht
number of dierent types of HT
number of congurations which are analysed, from an initial conguration j (j = 1, . . . ,M), in order to
Nj
determine the optimum economic conguration
Np1
number of dierent types of pumps P1
Np2
number of dierent types of pumps P2
a
384
NPV
nt
z1
z1c
z2
z2c
z0
(z1)0,j
(z2)0,j
385
to cover the peak load periods. In this way, customer demand can be supplied at minimum cost with a highly
reliable system (Conejo, 1990).
In the last few decades, pumping with storage has
played an important part in the development of electrical power systems throughout the world (Kuan, 1989).
It is considered by engineers and designers to be an
attractive alternative, allowing a considerable amount
of energy to be stored. As the generating equipment is
highly reliable, the power output can be easily regulated
and a practically constant eciency can be maintained
in the power output range.
From the 1970s onwards, and probably due to the
complementary characteristics of pumped hydrostorage
systems and wind parks (Chabot, 2000), there have been
several projects designed with the aim of making use of
wind energy to pump water for its later hydroelectric use.
However, no general methodology has been developed in
the projects undertaken in relation to the sizing optimisation of the systems components and its operating modes.
In this paper a general model is presented for the
implementation of pumped hydrostorage systems using
wind energy. This model is suitable for any site that
meets the necessary topographical requirements and
has sucient wind resources.
The general model developed allows for six strategies
for the system operating conguration. Each strategy is
based on the hypothesis that there is a centralised operator to control all the system components, except for the
load systems.
The application of the proposed model provides the
characteristics of each technically feasible and commercially available combination, as well as the costs per unit
energy generated, the net present value (NPV), the internal rate return (IRR) and the payback period (PBP) for
each combination. This will enable a decision to be taken
on the most viable composition of the system from an economic point of view given various technical restrictions.
386
b 0 if EHP t P DLS t
0 < b < 1 if 0 < EHP t < DLS t
b 1 if EHP t 0
3.2. Strategy 2
This strategy only diers from Strategy 1 in the ith
stages of initial connection (tc,i) of the HP, and will only
be executed when the volume V(t) of the upper reservoir
reaches its maximum value (V(t) = Vmax), and when
when
tc;i ! V t tc;i V max ; td;i ! V t td;i < V co ;
td;i1 ! V t td;i1 < V co
387
3.3. Strategy 3
All the generating subsystems are connected to the
same electrical grid (switches a and b closed and switch
c open, Fig. 1). As was mentioned in the introduction to
this paper, the aim is for as much of the electricity demand (DLS) as possible to be covered by renewable-sourced energy (wind and hydraulic). Consequently, it is
important to remember that the direct feeding of windsourced energy into a small or medium sized system
can have serious drawbacks. When there is a high degree
of wind energy penetration the variations in the active
power generated by such levels (due to variations in
the wind speed) cause imbalances between the power
output and demand. These imbalances can result in
frequency and voltage variations that can lead to potentially dangerous operating conditions (Gavanidou et al.,
1993; Papadopoulos et al., 1991). Therefore, in order to
avoid serious problems (which could aect the safety
and stability of the system) the wind-sourced energy
has to be limited to a specic percentage of the conventional synchronous capacity connected to the grid,
which in turn depends on the load of the system (Kabouris and Contaxis, 1992; Gavanidou et al., 1993). A dynamic study that takes into account wind speed
variations and other operating conditions, such as the
size of the system, is required to determine the percentage of wind-sourced energy which can be fed into a particular electrical system. In the model used in this paper,
a is dened as the maximum percentage of electrical
energy demand that can be met by wind-sourced energy
without aecting the safety and stability of the system.
a is an input parameter in this model and can take a value of between 0% and 100%.
With Strategy 3 the potential drawback of a high
direct wind penetration in the power grid (a high)
can be resolved by the use of a HP system. This enables the percentage of renewable-sourced energy to be
increased (Schafer and Simond, 1998; Mansoor,
2000).
In this strategy the CS controls the dierent subsystems in accordance with the following procedures:
(a) A minimum percentage (100 a) of the energy
demanded by the LS will be covered by the HP
and/or the CPS in the following sequence, Eq. (6),
(Eq. (6) is conditioned by Eqs. (7) and (9)). First,
by the HP if the volume of water in the upper reservoir (V(t)) is sucient; secondly, by the HP in parallel with the CPS if the water level in the upper
reservoir is not sucient; and thirdly by the CPS
alone if the level of water in the upper reservoir is
lower than the technical minimum, Vmin required
to drive the turbines.
(b) A maximum percentage a of the electricity demand
will be covered by wind-sourced energy if there is
sucient wind. The CS will attempt to connect the
pumps in succession with the aim of reaching an
electrical balance, Eq. (8), provided there is sucient energy and provided the wind energy is higher
than aDLS(t)/100.
388
aDLS t
EWP t 6
100
9
DLS t ECPS t >
=
10
b 1 if EHP t 0
9
3.4. Strategy 4
The non-controlled load demand is covered by dierent electricity generation subsystems, Eq. (6), depending
on whether the upper reservoir has reached its maximum
volume, Vmax or not. If the upper reservoir has not
reached its maximum volume (b = 1 in Eq. (4)), a minimum percentage (100 a) of demand will be covered by
the CPS and a maximum percentage a by the WP, Eq.
(7), provided there is sucient wind. If the wind energy
is higher than aDLS(t)/100 the pumps are connected in
succession to drive the water from LR to UR in order
to attempt to balance the electrical system, Eq. (8).
When the volume of water in the upper reservoir has
reached its maximum value (t = tc,i) the percentage of
the demand which was being covered by the CPS
will be covered by the HP (b = 0 in Eq. (4)). The advantage of this approach compared to Strategy 3 is that
it is possible to forecast the periods of connection/
disconnection of the CPS and the HP, making maintenance easier and reducing the number of connections/
disconnections.
During the periods a (Fig. 2) of the lling of the
UR, energy from hydraulic resources is not fed into
the grid, and so demand is covered by fossil-fuel and
wind-sourced energy. During the periods b of the
emptying of the UR, demand is met by energy from
hydraulic resources and wind-sourced energy.
3.5. Strategy 5
This strategy is a particular instance of Strategy 4
with the only dierence being in the lling stage of the
upper reservoir, when all non-controlled demand is covered by the CPS and all the wind-sourced energy is used
for water pumping, Eq. (10).
12
389
13
14
After determination of the net pumping height Hn, calculation of the ow (Qmax)0 which the HT require for
maximum demand, and the establishment of the eciency of the motor pumps g 0 , it is possible to obtain
the initial nominal pumping power, Eq. (15), and the
minimum initial installable nominal power of the WP,
Eq. (16), estimating a capacity factor (CF) of the WP
(Hau, 2000).
P PS 0 P qgH g H l Qmax 0 =g0
15
P WP 0 P P PS 0 =CF=100
16
The initial nominal power (PCGS)0 which has to be installed must be able to cover by itself all the demand
and, therefore, (PCPS)0 P DLS,max must be satised.
If dierent models of the components of each subsystem are to be tested (with dierent technical and economic characteristics) then, after determination of the
initial power estimates of the dierent subsystems, an
initial conguration of the system will be generated for
each combination of components, Eq. (17). In Eq.
(17), j varies between one and the number of dierent
models of components. The numbers of dierent models
of wind turbines, hydraulic turbines, higher power
pumps, lower power pumps, and conventional generator
sets, are represented by Nwt, Nht, Np1, Np2 and Ncp,
respectively.
4
The useful height and the gross height are considered to be
the same in the pre-sizing stage.
390
nw0;j P INT P WP 0 =P WT;j ; nt0;j P INT P HP 0 =P HT;j ;
nc0;j P INT P CPS 0 =P CP;j ;
z1 0;j P INT P PS 0 =P p1;j ;
nh
i
o
z2 0;j P INT P PS 0 z1 0;j P p1;j =P p2;j
17
As can be deduced from this design description, for a
given degree of autonomy and a given height between
reservoirs, the number M of initial dierent congurations of the system which can be analysed will be given
by Eq. (18).
M
N wt !
N ht !
N p1 !
N p2 !
N cp !
N wt 1! N ht 1! N p1 1! N p2 1! N cp 1!
18
20
391
22
392
Qt t nt QnT P
0
<
23
24
0
Qt t jQmt P
<
If the result of Eq. (24) is positive, the number of turbines which can be connected ntc is determined, as well
as the hydraulic power which can be supplied for 1 h,
Eq. (26), and the energy loss of the HP subsystem which
has to be covered by other subsystems, if possible.
25
26
If the result of Eq. (24) is negative or null, the ow required to cover the demand is compared with the technical minimum ow of the HP system, Eq. (27). If Eq. (27)
is negative or null for all j, it is concluded that it is
impossible to supply energy from hydroelectric re-
393
27
P p1 jg01 = qgHg H l Qp t 6 0
29
31
394
the generator, and (b) from the fuel price (Kirchmayer, 1958). There are dierent proposals
to relate fuel consumption and production
(Lipman and Ineld, 1990; Muselli et al.,
1999; Ashari and Nayar, 1999). 7 In this work
a linear relation has been used between the percentage of fuel consumption and the percentage
of the load seen by the diesel generator
(Carta and Gonzalez, 2001), indicating the
presence of a consumption at zero load of
40% of the full load and a minimum load of
40% of the full load (Hunter and Elliot,
1994). The emission of CO2 (in grams) in the
atmosphere is determined in proportion to the
fuel consumption (in grams), with a proportionality constant of 3.15. 8
5.5. Economic model
able to supply, at an instant t, a particular energy demand DLS(t), the CS proceeds along the following basic
steps (Fig. 8): 6
Step 1. Determination, subject to the production limits
max
P min
CP , P CP ) of the conventional generator sets,
of the number of sets (j = ncc) which need to
be connected to satisfy the demand, Eq. (32)
P min
CP jDt
6 DLS t 6
P max
CP jDt
32
6. Conclusions
A general model has been presented for the technical
and economic sizing of the various components that
make up medium sized wind-powered pumped hydrostorage systems.
The application of the proposed model provides the
characteristics of each technically feasible and commercially available combination, as well as the costs per unit
energy generated, the net present value (NPV), the internal rate return (IRR) and the payback period (PBP) for
each combination. Accordingly, this will enable a decision to be taken on the most viable composition of the
system from an economic point of view given various
technical restrictions.
Furthermore, the algorithm of the model developed
simulates the operation of each feasible combination
by making energy balance calculations for each of the
8760 h in a year. Therefore, the model developed in this
paper can be used as an analytical tool in implementing
such systems.
References
Ashari, M., Nayar, C.V., 1999. An optimum dispatch strategy
using set points for a photovoltaic (PV)dieselbattery
hybrid power system. Solar Energy 66, 19.
Canada, J.R., Sullivan, W.G., White, J.A., 1996. Capital
Investment Analysis for Engineering and Management.
Prentice-Hall, New Jersey, pp. 1566.
Carta, J.A., Gonzalez, J., 2001. Self-sucient energy supply for
isolated communities: winddiesel systems in the Canary
Islands. The Energy Journal 22, 115145.
Carta, J.A., Gonzalez, J., Subiela, V., 2003. Operational
analysis of an innovative wind powered reverse osmosis
system installed in the Canary Islands. Solar Energy 75,
153168.
Chabot, B., 2000. A long term wind power prospect from
hydropower retrospect and prospect: scenarios and lessons.
In: WIP (Eds.), Proceedings of Wind Power for the 21st
Century, Kassel, Germany, pp. 1922.
395