"Project Jalan Sebaya - Bukit Bujang Balai Badang - Mensudut Lama, Segamat, Johor"
_____________________________________________________________________________________________
INTRODUCTION
A properly planned and designed alignment (which included bridges, junction,
etc.) can minimize impact and expedite the travel time between Lebuhraya
Tun Abdul Razak and Kampung Bukit Bujang Balai Badang. The various
impacts have been examined at this stage in order the road avoid sensitive
areas or resources.
Mitigation involves the possible preventive, remedial or compensatory
measures for each of the adverse impacts evaluated to be significant.
Prevention is done during the project planning and design stage whereby the
route layout can be considered and modified to suit the existing structure
plan based on sensitive environmental parameters such as topography, land
use, ecology, population and others. At this environmental assessment stage
there is a need to rationalized mitigation measures to ensure that an
unreasonable cost budget is not recommended which will result in the project
being costly or not taking off. Thus base on environmental concerns the
acceptance of the route depends not on minimal adverse impacts but on low
mitigation costs.
Mitigation measures need to be incorporated into planning stage of the
project to minimize or mitigate potentially significant adverse impacts later
during the construction and operation phases.
Residual impacts (impacts that remain after mitigation measures have been
applied) need to be identified early so that there is awareness on the longterm effects of the project.
IMPACTS OF CONSTRUCTION ON THE ENVIRONMENTAL
Most construction activity involves a dramatic change the natural
environmental, through clearing of the natural vegetation an earthwork
activities.
In general construction activity results in the exposure of topsoil to erosive
rain and siltation from surface runoff those impacts upon drainage systems
and receiving water bodies. The loss of vegetative cover also increases the
risk of flash floods in low-lying areas as a result it increased surface runoff.
There is an appreciable increase in dust levels within the immediate
construction area as well as an increase in noise and heavy vehicular traffic.
The potential impact has to be evaluated against nearby receptors.
The following construction activities have been identified as having potential
impacts at the site and on the surrounding areas:
Site Clearing
Earthworks
Construction of road and other facilities
Operation of machinery
________________________________________________________________________________________________________
_____________________________________
Report No. ECS.2013.SSSB.EMP
CONTROL MEASURES
A site management measures with a system of non-structural and structural
erosion and sediment controls for incorporation into an erosion and sediment
controls by decreasing erosion potential, whereas structural controls are both
preventive and mitigative because they control both erosion and sediment
movement.
An Erosion and Sediment Control Plans (ESCPs) are required to be
formulated as an integral part of the project site planning. The "Guideline for
Prevention of Soil Erosion and Sedimentation", issued by the DOE, and
Volume 16 (Construction BMPs and Plans) of the Urban Storm water
management Manual for Malaysia should be referred to when preparing soil
erosion and sediment control plans for the whole development.
This ESCP is prepared in according to the overall earthwork planning and
schedule to serve as a general overview and guideline to pertinent issues for
this project site.
________________________________________________________________________________________________________
_____________________________________
Report No. ECS.2013.SSSB.EMP
Non-structural Control
Typical non-structural erosion controls include-:
Planning and designing the development within the natural constrain of
the site
The road should be constructed as close as possible to the existing
topography in order to minimize cutting, thus increase erosion rate and
increase the risk of slope failure.
Planning and designing the development within the natural constrain of
the site
Implementation of the project, especially site clearing and intensive
earthworks, should be scheduled during the time of year when the erosion
potential of the site is relatively low, i.e. during the dry season. From
examination of the rainfall data, it is observed that the driest months of the
year are between June to July and between January to February. However,
during this period, regular road watering should be conducted as bare, dry
site will be more prone to suspended particles.
Schedule construction of certain structural controls before site clearing
In order to ensure effective slit control during the commencement of the
earthworks phase, certain measures must be implemented. The following
control measures must be constructed prior to commencement of land
clearing of the pertinent phase:
Staged construction
Wide area clearance of the project site should be avoided. Planning and
staging of land disturbance activities will be such that only the area currently
under construction is exposed at any one time. As soon as the grating and
construction in the area are complete, the area should be stabilized.
________________________________________________________________________________________________________
_____________________________________
Report No. ECS.2013.SSSB.EMP
Sediment Basin
A sediment basin is a structure formed by excavation and/or construction of an
embankment across waterways in order to collect and store sediment before it
leaves the construction site. Sediment basins shall be installed prior to full
scale grading and remain in place until the disturbed portions of the drainage
area are fully stabilized. 15 sediment basins shall be constructed recovering all
the construction area. All of the sediment basin shall comply with the drawing
in aspect of location and specification.
Sediment Trap
Sediment trap is a small excavated or bermed area where runoff from small
drainage areas is being detained and sediment can settle.
Silt/Sediment Trap
Silt/Sediment trap is structure that designed to trap or catch sediment from
water runoff. Silt/Sediment traps are typically installed in a drainage way or
other point of discharge from disturbed area, and shall be constructed prior or
any earthworks. As the proposed stretch located at low lying area, and erosion
predicts to be of low rate, hence, silt trap might not be necessary. In this
construction period, numbers of silt traps shall be constructed to minimize the
amount of silt/sediment flows into the river. Constructions of the entire silt trap
shall comply with the locations and specification as shown on the drawing.
Below are the drawings indicating locations and details construction drawings.
KPKR/J/LB/011235/EPW/16
KPKR/J/LB/011235/EPW/1
KPKR/J/LB/011235/EPW/2
KPKR/J/LB/011235/EPW/3
KPKR/J/LB/011235/EPW/4
KPKR/J/LB/011235/EPW/5
KPKR/J/LB/011235/EPW/6
KPKR/J/LB/011235/EPW/7A
KPKR/J/LB/011235/EPW/8A
KPKR/J/LB/011235/EPW/9
KPKR/J/LB/011235/EPW/10
KPKR/J/LB/011235/EPW/11
KPKR/J/LB/011235/EPW/12
KPKR/J/LB/011235/EPW/13A
KPKR/J/LB/011235/EPW/14A
KPKR/J/LB/011235/EPW/15A
KPKR/J/LB/011235/AM/67
KPKR/J/LB/011235/AM/68
________________________________________________________________________________________________________
_____________________________________
Report No. ECS.2013.SSSB.EMP
KPKR/J/LB/011235/AM/69
KPKR/J/LB/011235/AM/70
KPKR/J/LB/011235/AM/71
KPKR/J/LB/011235/AM/72
Vegetation Filter Strips
Vegetated filter strips should have relatively low slopes and adequate length
and should be planted with erosion-resistant plant species. A common species
which is used is vetiver grass which is normally planted in several rows and
over amply long strips. Other applications of such grass are in riparian planting
along narrow streams as well as along the inner faces of sediment ponds.
Inlet Protection
Inlet protection provisions shall be incorporated at inlet points to stormwater
drainage systems in order to prevent excessive silt and sediment from entering
the system. These will include filter fabrics, packed gravel, or sand bags.
However, these structures require regular maintenance to prevent clogging.
Construction of Wash Through at Entrance / Exit Points
At all points of access to and from the project site, a pad of gravel over filter
cloth shall be constructed together with lorry washing through. As vehicles
drive over the gravel, mud and sediment are removed from the vehicles
wheels and contained in the wash through.
Inspection and Maintenance Plan
All structural and non-structural controls must be checked periodically
especially after heavy rains, and maintained sufficiently to ensure efficient
performance. An inspection and Maintenance Plan should be prepared and
implemented. This includes;
________________________________________________________________________________________________________
_____________________________________
Report No. ECS.2013.SSSB.EMP