Beruflich Dokumente
Kultur Dokumente
Index
Index
Item
Issue 1
January 2007
January 2007
2.1.2 F l a m m a b i l i t y o f M e t h a n e , O x y g e n a n d N i t r o g e n
January 2007
Issue 2
Issue 3
Mixtures
January 2007
January 2007
January 2007
Illustration
E-Mail: company@pentatech.co.kr
1. Modification/Correction Records
Item
Issue 1
Issue 2
Issue 3
January 2007
January 2007
January 2007
January 2007
January 2007
Index
January 2007
January 2007
Text
January 2007
January 2007
Abbreviations
January 2007
January 2007
January 2007
Text
1.1 Principal Particulars
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
Illustration
Illustration
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
Text
Issue 1
Issue 2
Item
Issue 3
Issue 1
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
Text
4.1 Cargo Piping System
January 2007
January 2007
January 2007
January 2007
January 2007
4.4.1a HD Compressor
January 2007
January 2007
4.4.2a LD Compressor
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
4.4.1 HD Compressors
January 2007
January 2007
4.4.2 LD Compressors
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
Text
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
Illustration
Issue 2
Issue 3
Item
Issue 1
Issue 2
Issue 3
Item
Issue 1
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
6.3.5 De-Ballasting
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
Illustration
5.1a Temperature Sensors in Cofferdams
January 2007
January 2007
January 2007
January 2007
Keel
January 2007
January 2007
6.5.4 Ballasting
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
6.6.3 Inerting
January 2007
January 2007
6.6.4 Aeration
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
6.3.5 De-Ballasting
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
Text
6.1 Post Dry Dock Operation
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
6.5.4 Ballasting
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
6.6.3 Inerting
January 2007
January 2007
6.6.4 Aeration
January 2007
6.3 Loading
January 2007
Illustration
January 2007
January 2007
Issue 2
Issue 3
January 2007
Issue 1
Issue 2
Issue 3
Item
Issue 1
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
Illustration
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
Text
January 2007
January 2007
January 2007
January 2007
6.5.4a Ballasting
January 2007
January 2007
6.6.1a Stripping
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
6.6.3a Inerting
January 2007
January 2007
6.6.4a Aeration
January 2007
January 2007
Text
Issue 2
Issue 3
Illustration
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
January 2007
4. Description
The purpose of this manual is to fill some of the gaps and to provide the ships
officers with additional information not otherwise available on board. It is
intended to be used in conjunction with the other plans and instruction books
already on board and in no way replaces or supersedes them.
In addition to containing detailed information on the machinery and related
systems, the machinery manual provided by each vendor contains safety
procedures and procedures to be observed in emergencies and after accidents.
Used in conjunction with the SMS MANUAL, this information is designed to
ensure the safe and efficient operation of the ship. Quick reference to the relevant
information is assisted by division of the manual into Parts and Sections, detailed
in the general list of contents on the preceding pages.
Reference is made in this book to appropriate plans or instruction books.
For other information refer to:
1) Books and Publications contained in the SMS Directory
2) SMS Manual
In many cases the best operating practice can only be learnt by experience.
Where the information in this manual is found to be inadequate or incorrect,
details should be sent to HHI so that revisions may be made to manuals of other
ships of the same class.
3. Safe Operation
The safety of the ship depends on the care and attention of all on board. Most
safety precautions are a matter of common sense and good housekeeping and are
detailed in the various manuals available onboard. However, records show that
even experienced operators sometimes neglect safety precautions through over
familiarity and the following basic rules must be remembered at all times.
1) Never continue to operate any machine or equipment which appears to be
potentially unsafe or dangerous and always report such a condition
immediately.
2) Make a point of testing all safety equipment and devices regularly.
3) Never ignore any unusual or suspicious circumstances, no matter how
trivial. Small symptoms often appear before a major failure occurs.
4) Never underestimate the fire hazard of petroleum products, whether fuel
oil or cargo vapour.
5) Never start a machine remotely from the control room without checking
visually if the machine is able to operate satisfactorily.
In the design of equipment and machinery, devices are included to ensure that as
far as possible in the event of a fault occurring, whether on the part of the
equipment or the operator, the equipment concerned will cease to function
without danger to personnel or damage to the machine. If these safety devices are
neglected, the operation of any machine is potentially dangerous.
Trading Area
(6) Special equipment needed for the safe handling of the particular cargo;
(7) Minimum allowable inner hull steel temperatures; and
(sec)
where:
U = ullage volume at operating signal level (m3)
LR = maximum loading rate agreed between ship and shore
facility (m3/h).
The loading rate should be adjusted to limit surge pressure on valve closure to
an acceptable level taking into account the loading hose or arm, the ship and
the shore piping systems where relevent.
Operating Requirements
Description
Symbol
Description
Symbol
Symbol
Description
Description
Filling Cap
Rose Box
Ball Valve
Mud Box
Solenoid Valve
Expansion Bend
Bellows type Expansion Joint
Blank Flange
Spectacle Flange
Orifice
M
Colour
Description
LNG Liquid
LNG Spray
LNG Vapour
Inert Gas
Superheated Steam
De-superheated Steam
Nitrogen
Y-type Strainer
Reducer
Steam Trap
Spool Piece
Globe Angle
Hand Pump
Angle Valve
Ejector, Eductor
Oil Coaming
Suction Bellmouth
Open Scupper
Surface Valve
Condensate/Distilled Water
Compressed Air
Hand Operated
Pressure Gauge
Deck Stand
Compound Gauge
Flow Meter
Sight Glass
Center Flange
10
Lubricating Oil
Heavy Fuel Oil
Glycol Water
Sea Water
Fresh Water
Hydraulic Oil
Diesel Oil
Bilge
Sludge & Waste Oil
Fire Sea Water
CARGO/CONTROL
DP
DIFFERENTIAL PRESSURE
GW
GLYCOL WATER
CAS
CASCADE
DV
DRAIN VALVE
HIGH/HOUR
AIR
CIRC
CIRCULATING
DW
HD
HIGH DUTY
A/B
CO
CHANGE-OVER
DWG
DRAWING
HDR
HEADER
ABNORMAL
CAB
CABINET
DRN
DRAIN
HFO
ABS
ABSOLUTE
CCR
DRV
DRIVE, DRIVING
HH
HIGH-HIGH
ACB
C/D
COFFERDAM
DSHTR
DESUPERHEATER
HLA
ACC
CENT
CENTRAL/CENTRIFUGAL
ECDIS
HORI
HORIZONTAL
ACCOMMODATION.
CFW
INFORMATION SYSTEM
HP
HIGH PRESSURE
AC/H
CH-VR
CHANGE-OVER
EGE
HPT
ACK
ACKNOWLEDGE
CIRC
CIRCULATING
EDSHTR
EXTERNAL DESUPERHEATER
HSE
ACT
ACTIVATE
CL
CLOSE
EER
HSC
ADJ
ADJUST
CLASS
CLASSIFICATION SOCIETY
ELE.
ELECTRIC
HR
HOUR
ADV
ADVANCE
CLR
COOLER
ELEV
ELEVATOR
H/T
HIGH TEMPERATURE
A/E
AUXILIARY ENGINE
CRT
EMCY
EMERGENCY
HTR
HEATER
AFT
AFTER
CNR
CORNER
EMR
HVAC
AHD
AHEAD
CO2
CARBON DIOXIDE
ENG
ENGINE
HYD
HYDRAULIC
AI
ANALOG INTPUT
C/D
COFFERDAM
E/R
ENGINE ROOM
INDICATOR
ALM
ALARM
COMP
COMPRESSOR
E.R.W
IAS
AM
APPLICATION MODULE
COND
CONDENSATE/CONDENSER
ESBD
EMERGENCY SWITCHBOARD
IBS
ANG
ANGLE
CONN
CONNECTION
ECR
IG
INERT GAS
AO
ANALOG OUTPUT
CONT
CONTROL
ESB
EMERGENCY SWITCHBOARD
IGG
APPROX
APPROXIMATELY
COOL.
COOLING
ESD
IGV
APT
CP
CONTROL PANEL
ESDS
IN
INLET
ASTERN
CPP
EXH
EXHAUST
INCIN
INCINERATOR
ATM
ATMOSPHERE
CSB
CARGO SWITCHBOARD
EXP
EXPANSION
IND
INDICATION
ATOM
ATOMISING
CSBD
EXT
EXTENSION
INH
INHIBIT
AUTO
AUTOMATIC
CSL
CONSOLE
FCV
INSUL
INSULATION
AUXILIARY
CST
CENTISTOKES
FDB
IR
INFRA-RED
BASE
CSW
FDF
IGG
B/L
BALLAST/LADEN
CTS
FG
FUEL GAS
ILLC
B/T
BOW THRUSTER
CUR
CURRENT
FLG
IMO
BALLAST
CYL
CYLINDER
FM
FROM
IRD
BATT
BATTERY
DUMP
FO
FUEL OIL
IS
INSULATION SPACE
BGB
DB
FPT
ISO
ISOLATING
BHT
DBT
FRP
IWRC
BULKHEAD
D/A
DEAERATOR
FW
FRESH WATER
JIS
BLG
BILGE
DEL
DELIVERY
FWC
JSRA
BLK
BLOCK
DET
DETECTOR/DETECTION/ DETAIL
FWD
FORWARD
BLR
BOILER
D/G
DIESEL GENERATOR
FWE
kg/cm G
BLWR
BLOWER
DGPS
GA
GENERAL ARRANGEMENT
KS
SYSTEM
GACP
LOW/LEVEL/LITRE
ABNOR
ACCOM
AST
AUX
BA
BHD
JAPAN
2
BMS
BNR
BURNER
DI
DIGITAL INPUT
GALV
GALVANIZED
LBP
BO/WU
DIAM
DIAMETER
GC
GLASS CLOTH
LCV
BOIL-OFF GAS
DIA
DIAMETER
GE
GENERATOR ENGINE
LD
LOW DUTY
BRG
BEARING
DIFF
DIFFERENTIAL
GEN
GENERATOR
LDO
BW
BILGE WELL
DISCH
DISCHARGE
GMS
LG
LEVEL GAUGE
BWC
DK
DECK
GRP
LIQ
LIQUID
DMCR
G/S
GENERAL SERVICE
LL
LOW-LOW
BUZZER
DO
GTT
LLA
BOG
BWL
BZ
11
Abbreviation
OVBD
OVERBOARD
SEL
SELECT
TYP
TYPICAL
LO
LUBRICATION OIL
OVFL
OVERFLOW
SEPTR
SEPARATOR
TX
TEMPERATURE TRANSMITTER
LOA
OVLD
OVERLOAD
SEQ
SEQUENCE
UPP
UPPER
LP
LOW PRESSURE
OVRD
OVERRIDE
SERV
SERVICE
UPS
LPT
PRESSURE/PRIMARY/PORT
SETT
SETTLING
VOLTAGE/VALVE
LS
LEVEL SWITCH
PB
PUSH BUTTON
S/G
STEERING GEAR
VAP
VAPOUR
LSC
PCV
SHP
VDR
LT
LOW TEMPERATURE
PD
PIPE DUCT
SHTR
SUPERHEATER
VDU
LTG
LIGHTING
PI
PRESSURE INDICATOR
SIGTTO
VIB
VIBRATION
LVL
LEVEL
PID
VISC
VISCOSITY
L.W.L
PST
PISTON
SMLS
SEAMLESS
VL
VERY LOW
LWR
LOWER
PKG
PACKAGE
SNAME
VPR
VAPOUR
MACH
MACHINERY
PMS
MARINE ENGINEERS
VRC
MAN
MANUAL
PNL
PANEL
SOL
SOLENOID
V/V
VALVE
MANI
MANIFOLD
POS
POSITION
SOLAS
MARVS
P/P
PUMP
SETTING
PRESS
PRESSURE
MAIN BOILER
PRI
M/B
WTR
WATER
OF LIFE AT SEA
W/H
WHEELHOUSE
SP
SPACE/SET POINT
WHC
WHEELHOUSE CONSOLE
PRIMARY/PRIMING
SPR
SPRAY
WIND
WINDING
MBL
PROV
PROVISION
ST
START
WO
WASTE OIL
MCR
PSU
S/T
STERN TUBE
WS
WORKSHOP
M/E
MAIN ENGINE
PURI
PURIFIER
STBD
STARBOARD
WU
WARM UP
MFWPT
PURIF
PURIFIER
STBY
STAND-BY
CROSS/TRANSMITTER
MG
MASTER GAS
PV
PROCESS VALUE
STC
MGPS
PVC
POLYVINYL CHLORIDE
STM
STEAM
MID
MIDDLE
PWR
POWER
STOR
STORAGE
MIN
MINIMUM
PX
PRESSURE TRANSMITTER
STR
STARTER/STRAINER/STRAIGHT
MSB
MAIN SWITCHBOARD
QTY
QUANTITY
STRG
STEERING
MSBD
MAIN SWITCHBOARD
REDUNDANT
SUC
SUCTION
MSBR
RECIRC
RECIRCULATING
SUP
SUPPLY
MT
MAIN TURBINE
REG
REGULATOR
SV
SOLENOID VALVE
MT.
METRIC TONNES
REM
REMOTE
SVB
MTH
METRES IN HEIGHT
REV
REVERSE
SW
SEA WATER/SWITCH
MTR
MOTOR
RM
ROOM
SWBD
SWITCHBOARD
MV
MAGNETIC VALVE
RPB
SWL
N2
NITROGEN
RPM
SYN
SYNCHRONIZE
NAV
NAVIGATION
RTN
RETURN
SYS
SYSTEM
NCR
RVI
TAL
NIM
RW
ROCK WOOL
TC
TURBOCHARGER/THERMOCOUPLE
NO.
NUMBER
SECONDARY/ STARBOARD
T/C
TURBO CHARGER
NOM.
NOMINAL
SBT
TCV
NOR
NORMAL
SEC
SECOND
TEMP
TEMPERATURE
NPSH
SEQ
SEQUENCE
T/G
TURBO GENERATOR
NZL
NOZZLE
S/S
SHIP SIDE
THK
THICKNESS
OBS
OBSERVATION
S/T
STERN TUBE
THR
THRUSTER
O/C
OPEN/CLOSE
SAH
TI
TEMPERATURE INDICATOR
OCIMF
SAL
SALINITY
TIAL
FORUM
SB
SOOT BLOWER
TK
TANK
O2
OXYGEN
SC
SEA CHEST
TPS
OMD
SDC
TRB
TROUBLE
OP
OPEN/OUTPUT
SEC
SECONDARY
TSWT
12
Abbreviation
Part 1
Design Concept of the Vessel
Part 1 Design Concept of the Vessel
Type of Cargo:
Type of Ship:
Stem:
Stern:
Navigation:
Freeboard Type:
Classification:
HHI-MHI
MS 40-2
Cross Compound Marine Steam
Turbine.
MCR 40,000 PS x 88 RPM
NCR 36,100 x 85 RPM
5.88 MpaG, 510 C
1
Output:
Length Overall:
Length Between Perpendiculars:
Breadth Moulded:
Depth Moulded:
Draft Design:
Scantling Draft:
Cargo Tank Capacity:
Cargo Tank Safety Valve:
Inter Barrier Space Safety Valve:
Insulation Space Safety Valve:
Main Engine Type:
MCR:
NCR:
288 m
275 m
44.2 m
26.0 m
11.35 m
12.35 m
149,730 m3
25 kPa
3 kPa
3.5 kPa
HHI-MHI MS40-2
40,000 SHP x 88 RPM
36,000 SHP x 85 RPM
Steam:
No. of set:
Main Boiler
Maker:
Model:
Type:
Max. Evaporation:
Nor. Evaporation:
Steam:
No. of sets:
Generator Turbine
Maker:
Model:
Type:
Steam:
Turbine rated speed:
Generator output & speed:
No. of sets:
HHI-EMD
7L 27/38
4 Stroke, Trunk Piston type
720 RPM
1
Cummins
KTA38
850 kW, 1062.5 kVA at p.f. 0.8
1
3 x 450V
Steering Gear
Maker:
Type:
Capacity:
No. of set:
ROLLS-ROYCE
Vane
3500KN-M (at 35 deg.)
1
Ballast Pump
Maker:
Model:
Type:
Capacity x Total head:
Motor output & speed:
No. of sets:
1-1
F.W Generator
Maker:
Model:
Type:
Capacity:
Max. salinity:
No. of sets:
Alfa-Laval Korea
VSP-36-C125CC / VSP-36-125SWC
Cond. Water Cooled(VSP-C25CC)
S.W. Cooled(VSP-C125SWC)
60 ton/day per unit
1.5 PPM
2
ATLAS COPCO
M.D. Rotary Screw, F.W Cooled
350 m3/h x 0.9MPa
2
JONGHAP PNEUTEC
M.D. 2 Stage reciprocating, Air
Cooled
25 m3/h x 2.5 MPa
2
Windlass
Maker:
Type:
No. of sets:
Rolls-Royce
LBFM41,100
2
Mooring Winch
Maker:
Type:
No. of sets:
Rolls-Royce
LW. M22. 030
5
Capstan
Maker:
Type:
No. of sets:
Provision Crane
Maker:
Type:
Capacity:
No. of sets:
Anchor
Maker:
Weight:
No. of sets:
DaiHan
100 mm x 742.5m
1
1-2
Shinko
SM350
1,800 m3/h x 155 MLC
469kW
81%
720 m3/h
1 MPaG
-163 C
8 (2 per each cargo tank)
Shinko
SMR200
550 m3/h x 155 MLC
161 kW
72 %
220 m3/h
1 MPaG
-163 C
1
Motor
Manufacturer:
Rated output:
Synchronous speed:
Electric power source:
Starting & Rated current:
Starting method:
Number of poles:
Shinko
575kW
1800 RPM
AC 6600 V / 60Hz
400A / 66 A
Soft start or Direct on line
4
Motor
Manufacturer:
Rated output:
Synchronous speed:
Electric power source:
Starting & Rated current:
Starting Method:
Number of Poles:
Shinko
200 kW
3600 RPM
AC 440 V / 60Hz
2500 A / 355 A
Direct on line
2
Stripping/Spray Pump
Maker:
Model:
Capacity:
Shaft power:
Efficiency:
Minimum flow:
Design pressure:
Design temperature:
No. of sets:
Shinko
SM65
50 m3/h x 145 MLC
22.4 kW
46 %
20 m3/h
1 MPaG
-163 C
4 (1 each cargo tank)
Motor
Manufacturer:
Rated output:
Synchronous speed:
Electric power source:
Starting & Rated current:
Starting method:
Number of poles:
Shinko
30 kW
3600 RPM
AC 440 V / 60Hz
380 A / 60 A
Direct on line
2
HD Compressor
Maker:
Model:
Type:
Volume Flow:
Inlet pressure :
Outlet Pressure:
Inlet Temperature:
IGV setting:
No. of sets:
LD Compressor
Maker:
Model:
Type:
Volume Flow:
Inlet pressure :
Outlet Pressure:
Inlet Temperature:
IGV setting:
No. of sets:
Cryostar
CM 400/55
Centrifugal. Single stage. Fixed speed
with adjustable guide vanes.
32,000 m3/h
0.103 MPa
0.196 MPa
-140C
-30 ~ +80
2
Cryostar
CM 300/45
Centrifugal. Single stage.
Adjustable guide vanes.
8,500 m3/h
0.103 MPa
0.196 MPa
-40C
-30 ~ +80
2
1-3
BOG/WARM-UP Heater
Maker:
Model:
Type:
Mass Flow:
Inlet volume flow & temp:
Outlet volume flow & temp:
Heat exchange:
Design temperature (Tube):
Design pressure:
No. of sets:
Cryostar
108-UT-38/34-4.6
BEU
37,200 kg/h (Design)
17,394 m3/h , -90C (Design)
38,346 m3/h , 80C (Design)
4,003 kW (Design)
-196 ~ +200C
1 MPa
2
LNG Vapouriser
Maker:
Model:
Type:
Mass Flow:
Inlet volume flow & temp:
Outlet volume flow & temp:
Heat exchange:
Design temperature (Tube):
Design pressure:
No. of set:
Cryostar
65-UT-38/34-5.6
BEU
22,000 kg/h (LNG disch)
49 m3/h , -163C (LNG disch)
12,367 m3/h , -130C (LNG disch)
3,581 kW (LNG disch)
-196 ~ +200C
0.1 MPa
1
Forcing Vapouriser
Maker:
Type:
Mass Flow:
Inlet volume flow & temp:
Outlet volume flow & temp:
Heat exchange:
Design temperature (Tube):
Design pressure:
No. of set:
34-UT-25/21-3.6
BEU
7,100 kg/h
16 m3/h , -163C
4,313 m3/h , -40C
1,560 kW
-196 ~ +200C
0.1 MPa
1
Air Products As
Membrane Separation of Nitrogen
from Air
2 X 125Nm3/h
97%
-65C
min. 0.65MPa / max. 50C
2
SMit
Gin 15,000-0.25BUFD
14,500 m3/h
0.025 MPa
About 30C average
(max. 65C during switch-over of
dryer vessels)
max. -45C
440V, 3ph, 60Hz
1
DongHwa Entec
Shell/Tube Type
63.04 m3/h X 2
1
1-4
No.1
No.2
No.3
No.4
CG100
CG200
CG300
CG400
CL100
CL110
CL101
CL102
CL103
CL200
CL210
CL201
CL202
CL203
CL300
CL310
CL301
CL302
CL303
CL400
CL410
CL401
CL402
CL403
CS101
CS100
CS103
CS104
CS105
CS107
CS108
CS201
CS200
CS203
CS204
CS205
CS207
CS208
CS301
CS300
CS303
CS304
CS305
CS307
CS308
CS401
CS400
CS403
CS404
CS405
CS407
CS408
CG701
CG702
CL700
CG703
CS701
CS700
CS702
CS600
CG601
CG602
Cargo Tank
Manifold
No.1
No.2
CG513
CG521
CG514
CG522
CG515
CG523
CG516
CG524
Port
Stbd
CL001
CL005
CL009
CL013
CG001
CL004
CL008
CL012
CL016
CG002
CG504
CG510
CG003
CG004
CL002
CL006
CL010
CL014
CL003
CL007
CL011
CL015
CG503
CG509
CS505
CG501
CS001
CS003
CS005
CS007
CS002
CS004
CS006
CS008
CS506
CG502
CG530
CG512
CG529
CG511
CG606
1-5
NAME OF
EQUIPMENT
CARGO PUMP
MAKER
SHINKO
TEL/FAX/E-MAIL
ADDRESS/
PERSON IN CHARGE
TEL)
81-82-508-1000
HIROSHIMA, JAPAN
SER
NO.
10
FAX)
81-82-508-1020
2
SPRAY PUMP
SM65
SHINKO
TEL)
81-82-508-1000
NAME OF
EQUIPMENT
ELECTROPNEUMATIC
TANK LEVEL GAUGE
HANLA
LEVEL CO.
LTD
SYSTEM
HIROSHIMA, JAPAN
FAX)
FWD H.F.O
EMERGENCY
CARGO
PUMP
SMR200
SHINKO
TEL)
81-82-508-1000
TRANS. PUMP
FAX)
81-82-508-1020
4
CARGO
COMPRESSOR
CM 300/45
CRYOSTAR
FRANCE S.A.
TEL)
Cryostar-France SA
33-389-7027 27
Zone Industrielle, BP 48
FAX)
F-68220 Hesingur/France
108-UT-38/34-4.6
CRYOSTAR
FRANCE S.A.
TEL)
Cryostar-France SA
33-389-7027 27
Zone Industrielle, BP 48
FAX)
F-68220 Hesingur/France
CUSTODY
TRANSFER
SYSTEM
(CARGO
INSTRUMENTATION)
21-UT-38/34-3.2
CRYOSTAR
FRANCE S.A.
81-82-52-3112
Kumage - gun,
FAX)
Yamaguchi - Pref.
81-82-53-1001
Japan
KONGSBERG
TEL)
Kongsberg Maritime As
MARITIME AS
47-73-58-1000
FAX)
FLOAT TYPE
FLOAT TYPE
WHESSOE
LEVEL GAUGE
LNG VAPOURISER
65-UT-38/34-5.6
CRYOSTAR
FRANCE S.A.
TEL)
FAX)
14
TRIM / LIST
INDICATOR
CSM-2DD
UTSUKI
TEL)
WM-2
FAX)
TEL)
Cryostar-France SA
DVF-11E
81-45-811-0425
Japan
33-389-7027 27
Zone Industrielle, BP 48
MC-DBPH
FAX)
F-68220 Hesingur/France
TEL)
31-24-352-31-00
ST.
FAX)
6531 LB NIJMEGEN
31-24-356-49-95
15
33-389-7029 00
7
FAX)
47-73-58-1417
13
33-389-7029 00
LOW DUTY
COMPRESSOR
INDUSTRIES
CM 400/55
5
82-51-601-3000
33-389-7029 00
HIGH DUTY
COMPRESSOR
TEL)
CO, LTD
12
TEL)
TAIKO KIKAI
TEL)
Cryostar-France SA
33-389-7027 27
Zone Industrielle, BP 48
FAX)
INERT GAS
GENERATOR
CB-2S
81-45-813-1239
2 x 100%
MULT-STAGE FANS
SMIT GAS
SYSTEM
F-68220 Hesingur/France
FORCONG
VAPOURISER
34-UT-25/21-3.6
CRYOSTAR
FRANCE S.A.
TEL)
Cryostar-France SA
33-389-7027 27
Zone Industrielle, BP 48
FAX)
F-68220 Hesingur/France
NETHERLANDS
16
NITROGEN SYSTEM
33-389-7029 00
9
MIST SEPARATOR
VMS-12/12-1000
CRYOSTAR
FRANCE S.A.
HUBERTUSSTRAAF
GD NIJMEGEN
33-389-7029 00
8
ADDRESS/
PERSON IN CHARGE
TEL/FAX/E-MAIL
82-51-831-1850
VG-50MAB
81-82-508-1020
3
MAKER
TEL)
Cryostar-France SA
33-389-7027 27
Zone Industrielle, BP 48
FAX)
F-68220 Hesingur/France
NITROGENERATOR
AIR
PRODUCTS
TEL)
Air Products AS
(MEMBRANE
47-3803-9900
SEPARATION OF
FAX)
NITROGEN FROM
47-3801-1113
TEL)
81-72-857-4527
6, 1-Chome, Shodai-Tajika,
FAX)
AIR)
17
33-389-7029 00
PILOT OPERATED
1-6
FUKUI
SEISAKUSHO
SPRING LONDED
CO., LTD
81-72-857-3324
SER
NO.
18
NAME OF
EQUIPMENT
CRYOGENIC
MANUAL
BUTTERFLY VALVE
REMOTE
MAKER
TEL/FAX/E-MAIL
KSB AMRI
TEL)33-553-924-965
ADDRESS/
PERSON IN CHARGE
SER
NO.
KSB AMRI
27
Zone industrielle
FAX)33-553-924-920
NAME OF
EQUIPMENT
GAS FLOW METER
MAKER
DAEYANG
INSTRUMENT
CO., LTD
24490 La
France
CRYOGENIC BALL
REMOTE/MANUAL
VALVE
20
FRUFLO
RONA S.A.
CRYOGENIC GLOBE
REMOTE
VALVE
OPERATED
SNRI
TEL)
32-42-40-6886
FAX)
32-42-48-0246
TEL)
Route du treuil bp
33-5-45-29-6000
28
GLYCOL WATER
HEATER
TYPE
21
22
CRYOGENIC CHECK
SWING CHECK
VALVE
SDNR
CRYOGENIC GATE
TEL)
EN'TEC
30
VALVE
Route du treuil bp
33-5-45-29-6000
31
STAINLESS STEEL
SFZ
SUSPENDED
33-4-7247-6200
Lumie'res 69680
UNIVERSAL TYPE
FAX)
CHASSIEU FRANCE
32
CARGO VALVE
REMOTE
CONTROL AND ESD
NAKAKITA
SYSTEM
TEL)
NAKAKITA
81-72-871-1341
FAX)
DAITO-SHI OSAKA
81-72-874-7501
25
VALVE REMOTE
NAKAKITA
CONTROL SYSTEM
FOR WATER
BALLAST
TEL)
RX-515
KEIKI
82-51-518-3613~5
Bugok-dong,
GW-2X
KOREA
FAX)
Keumjung-gu,
GV-100S
CO. LTD
82-51-512-7737
Busan, Korea
SHINKO
TEL)
5-7-21, Ohzu,
81-82-508-1000
Minami-ku,
FAX)
Hiroshima,
81-82-508-1020
Japan
TEL)
5-7-21, Ohzu,
81-82-508-1000
Minami-ku,
FAX)
Hiroshima,
TEL)
5-7-21, Ohzu,
81-82-508-1000
Minami-ku,
FAX)
Hiroshima,
81-82-508-1020
Japan
TEL)
499
82-51-204-2211
SHINPYUNG-DONG, SAHA-KU
SYSTEM
FAX)
PUSAN, KOREA
RVP 250MS
SVA125M
SHINKO
IND. LTD,
GLYCOL W.CIRC.
PUMP
GJ40-20MH
SHINKO
N2 BLEED CONTROL
8821114/HW/78/4701E
VALVE
8821114EB/HW/78/4701E
3535202/HW/78/4700E
DRESSER
FLOW
CON.
MASONEILAN
DRESSER
PRODUITS
INDUSTRIELS
NK CO., LTD
81-51-204-2215
FAX)
DAITO-SHI OSAKA
34
CO2 FIRE
SYSTEM
81-72-874-7501
26
DRY CHEMAICAL
NAKAKITA
81-72-871-1341
DETECTOR
IND. LTD,
33
051)970-1070
#301-16,
33-4-7247-6201
24
TEL)
F.W.PUMP
TEL)
TEL)
051)970-1031
33-5-45-31-1291
EXPANSION
BELLOWS
RIKEN
IND. LTD,
FAX)
23
Busan, Korea
FAX)
SADD-P
Route du treuil bp
TEL)
82-51-200-5212
PORTABLE GAS
33-5-45-29-6000
SNRI
FAX)
CONCENTRIC
29
33-5-45-31-1291
SNRI
DongHwa
EDGE
FAX)
MANUAL OPERATED
TEL)
82-51-200-5210
Roche-chalais,
19
ADDRESS/
PERSON IN CHARGE
TEL/FAX/E-MAIL
EXTING.
NK CO., LTD
TEL)
499
82-51-204-2211
SHINPYUNG-DONG, SAHA-KU
FAX)
PUSAN, KOREA
81-51-204-2215
TEL)
33-2-31-59-59-59
PIERRE-B.P.87-14110 CONDE
FAX)
33-2-31-59-59-60
1-7
Blank Page
1-8
Fan
Room
Vent Mast
Cargo Gear
Locker
L.P.
Vent Mast
Manifold Service Handling
Crane, 10 Ton (P&S)
Vent Mast
Fore Mast
L.P.
L.P.
Drinking W.
Tank (P)
F.W Tank (S)
B.V.H.
Room
No.2 Trunk
No.1 Trunk
G/E
M.L.O
L.O
Settling
Tank Storage
Tank(S)
M.L.O
M.L.O.
Storage
Grav.
Tank
Tank(S)
3rd Deck
Dry Powder
Room (P&S)
Trunk (Void)
S.L.
2nd Deck
Distilled
Water Tank
(P&S)
No.3 Trunk
G/E M.D.O
Service
Tank
Bosun Store
Low
M.D.O Sulphur
Storage Fuel
Tank Tank (S)
(S)
AFT
H.F.O
Bunk
ank (S)
H.F.O
Settling
Tank (S)
H.F.O Overflow
Tank
Engine Room
Cargo Tank
Fore Peak
Tank
(Void)
H.S.C
C.W. Tank
Filling (D.W.Tank)
L.S.C
No.5 Cofferdam
No.3 Cofferdam
No.4 Cofferdam
No.2 Cofferdam
LNG Liquid
AIR CON
ROOM
POOL TANK
LNG Liquid
Fuel Oil
Diesel Oil
Fresh Water
Fuel Oil
Diesel Oil
Fresh Water
UPPER DECK
LNG Vapour
CHANGE
ROOM
(ENG)
No.1 Cofferdam
Pipe
Duct
DRY
CABLE POWDER
SPACE SPACE
NO.1 CARGO
SWBD. RM
NO.1 CARGO
(LOW)
TRANSFOEMER
ROOM
C.D.
&
P.D
NO.1 CARGO
SWBD. RM
(HIGH)
C.L.
DRY
ROOM
SHIP'S
LAUNDRY
GARB.
STR
PAINT
STORE
DECK
STORE
INCINERATOR
ROOM
FIRE
EQUIP'T
LKR.
E/R
BATT.
ROOM
SUEZ
WORKER
(4-P)
CHANGE
ROOM
(DECK)
LINEN
LKR
PUR.
C.G
LIFT
C.D.
&
P.D
NO.2 CARGO
SWBD. RM
(HIGH)
NO.2 CARGO
NO.2 CARGO TRANSFORMER
FIRE
ROOM
CONTROL LBY SWBD. RM
CABLE
(LOW)
STATION
SPACE
WINCH
MOTOR
ROOM
CARGO
COMPRESSOR
ROOM
ONLY
Filling (F.W.Tank)
Fresh Water
Diesel Oil
Fuel Oil
Fresh Water
Diesel Oil
Fuel Oil
LNG Liquid
Principal Dimensions
LNG Liquid
Overall Length
Length Between Perpendiculars
Breadth (Moulded)
Depth (Moulded)
Trunk Depth (Moulded)
Draught Design (Moulded)
Scantling Draught (Moulded)
LNG Vapour
1-9
288.0
275.0
44.2
26.0
33.09
11.35
12.35
m
m
m
m
m
m
m
51850 (Bontang-3)
19450 (Sines)
18250 (Higashi-Ohgisima) :
Strengthened Rail
18250 (Futtsu No.1 & 2):
Strengthened Rail
18000 (Qalhat)
17800 (Ras Laffan No.2)
17050 (Senboku No.2-2) :
Strengthened Rail
41000(Range41000-46000)
(Montoir Up/Down Stream Removable Gangway): Strengthened Rail
31000 (Bintulu No.2)
20750 (Heulva)
20000 (Inchon No.2)
17500 (Pyeong Taek No.2)
15600 (Bontang-1)
15250 (Bontang-2)
14050 (Yung-An East)
15250 (Yanai)
14050 (Yung-An East)
13000 (Penuelas)
UPPER DECK
CO2 ROOM
NO.1 CARGO
SWBD. RM
(LOW)
AIR CON
ROOM
C.D.
&
P.D
POOL TANK
DRY
CABLE POWDER
SPACE SPACE
NO.1 CARGO
TRANSFOEMER
ROOM
NO.1 CARGO
SWBD. RM
(HIGH)
C. L.
SHIP'S
LAUNDRY
GARB.
STR
PAINT
STORE
DECK
STORE
INCINERATOR
ROOM
FIRE
EQUIP'T
LKR.
E/R
BATT.
ROOM
LIFT
CHANGE
ROOM
(DECK)
DRY
ROOM
SUEZ
WORKER
(4-P)
LINEN
LKR
C.D.
&
P.D
PUR.
C.G
FIRE
CONTROL
STATION
LBY
NO.2 CARGO
SWBD. RM
(LOW)
NO.2 CARGO
SWBD. RM
(HIGH)
NO.2 CARGO
TRANSFORMER
ROOM
WINCH
Cargo Gear
Locker
MO T O R
RO OM
CA RGO
COMPRESSOR
RO OM
ONLY
CABLE
SPACE
15100 (Himeji) :
5700
(barcelona)
15deg.
10000 (Oita)
16000(Chita) :
Strengthened Rail (Span:2000)
16000(Kawagoe) :
4500 (Max. Slew : 4500)
Strengthened Rail (Span:4000)
17000 (Negishi) :
Strengthened Rail
17500 (Pyeong Taek No. 1&2)
18000 (Qalhat)
19000 (Lake Charles) : Securing
Braket With Removable Rail
36000 (Revithousa)
41000 (Range 41000-46000) (Motior Up/Down Stream Removable Gangway) : Strengthened Rail
104000 (Lake Charles) : Securing Braket Welded on Deck With removable Rail
1 - 10
Location
Frame
Number
Volume
100% (m3)
Weight
98%
(Tons)
S.G.=0.47
Centre of Gravity
(100% Base)
V.C.G.
Above B.L
(m)
L.C.G.
From
Mid.(m)
Free
Surface
Moment
(m4)
118.1-128.9
24653.8
24160.8
17.797
79.57
103566
103.1-116.9
43266.88
42401.5
16.662
38.00
206520
88.1-101.9
43235.6
42370.9
16.662
-10.19
206520
74.1-86.9
38630.2
37857.6
16.662
-56.01
184617
149786.5
146790.8
16.849
6.66
Total
Compartment
Location
Frame
Number
130-154
2009.7
130-154
2009.7
Volume
100%
(m3)
Weight
100%
(Tons)
Compartment
Location
Frame
Number
V.C.G.
Above B.L
(m)
L.C.G.
From Mid.
(m)
2060.0
12.198
107.08
2060.0
12.198
107.08
Weight
100%
(Tons)
V.C.G.
Above B.L
(m)
L.C.G.
From
Mid. (m)
Free
Surface
Moment
(m4)
Distilled W. TK (P)
2.0-10.0
145.8
145.8
18.386
-132.51
206
Distilled W. TK (S)
2.0-10.0
145.8
145.8
18.386
-132.51
206
Drinking W. TK (P)
10.0-17.0-
170.8
170.8
18.386
-126.59
417
10.0-17.0
170.8
170.8
18.386
-126.59
417
633.1
633.1
Total
18.386
-129.31
S.G.=1.025
Centre of Gravity
(100% Base)
Centre of Gravity
(100% Base)
Capacities
Volume
100% (m3)
S.G.=1.000
Free
Surface
Moment
(m4)
Capacities
Compartment
Location
Frame
Number
1361
130.0-154.0
2570.1
1361
130.0-154.0
63.0-73.0
Volume
100%
(m3)
Weight
95%
(Tons)
S.G.=0.970
Centre of Gravity
(100% Base)
Free
Surface
Moment
(m4)
V.C.G.
Above B.L
(m)
L.C.G.
From Mid.
(m)
2368.4
12.685
106.88
745
2599.4
2395.4
12.685
106.80
758
465.5
428.9
17.965
-83.37
34
117-130
6161.4
6315.5
10.769
76.63
10884
117-130
6161.4
6315.5
10.769
76.63
10884
63.0-73.0
355.7
327.8
17.966
-82.47
23
102-117
6367.6
6526.8
8.903
36.39
27780
53.0-63.0
537.6
495.4
18.063
-91.07
51
102-117
6367.6
6526.8
8.903
36.39
27780
55.0-65.0
542.2
499.6
18.005
-89.48
51
87-102
6459.6
6621.1
8.805
-11.57
28957
49.0-53.0
207.6
191.3
18.337
-96.70
20
87-102
6459.6
6621.1
8.805
-11.57
28957
49.0-55.0
295.9
272.7
18.009
-95.78
31
73-87
5604.5
5744.6
9.072
-56.92
23824
No. 4 W.B. TK P)
73-87
5604.5
5744.6
9.072
-56.92
23824
7574.0
6979.5
A.P. TK
-6.1-17
2320.6
2378.7
14.291
-131.40
44268
Total
55526.4
56914.6
9.792
13.43
Total
1 - 11
14.383
44.67
Compartment
Location
Frame
Number
Capacities
Volume
100% (m3)
Weight
95%
(Tons)
Other Tanks
S.G.=0.900
Centre of Gravity
(100% Base)
V.C.G.
Above B.L
(m)
L.C.G.
From Mid.
(m)
Free
Surface
Moment
(m4)
Compartment
Location
Frame
Number
Capacities
Weight
100%
(Tons)
Volume
100% (m3)
S.G.=1.000
Centre of Gravity
(100% Full)
V.C.G.
Above B.L
(m)
L.C.G.
From Mid.
(m)
Free
Surface
Moment
(m4)
32.0-37.0
69.9
59.8
2.746
-109.94
102
C.W. TK (C)
8.6-17.0
70.7
70.7
4.916
-125.80
47
38.0-41.0
106.5
91.9
20.461
-105.90
15
17.0-28.0
119.2
119.2
1.724
-118.32
206
35.0-38.0
106.5
91.1
20.461
-108.30
15
28.0-31.0
47.9
47.9
2.608
-113.32
240
41.0-43.0
28.1
24.0
16.765
-103.90
57.0-73.0
87.6
87.6
8.517
-85.22
22
41.0-43.0
16.6
14.4
23.627
-103.90
31.0-38.0
38.2
38.2
2.766
-109.39
19
41.0-43.0
16.7
14.3
23.598
-103.90
Sludge TK (S)
33.0-41.0
14.0
14.0
9.356
-108.12
41.0-43.0
16.9
14.4
23.627
-103.90
41.0-43.0
16.7
14.3
23.598
-103.90
377.7
377.7
21.0-24.0
5.4
4.6
2.163
-119.44
383.6
327.9
Total
17.255
Compartment
Location
Frame
Number
45.0-51.0
Centre of Gravity
(100% Full)
Free
Surface
Moment
(m4)
V.C.G.
Above B.L
(m)
L.C.G.
From Mid.
(m)
211.0
170.4
15.813
-99.10
31
51.0-59.0
134.2
108.3
23.613
-93.10
41
49.0-54.0
83.9
67.8
23.613
-96.30
26
429.1
346.5
19.777
-110.20
Other Tanks
S.G.=0.850
Weight
95%
(Tons)
Volume
100% (m3)
4.397
-107.00
Total
-96.80
Compartment
Location
Frame
Number
Capacities
Volume
100% (m3)
Weight
100%
(Tons)
S.G.=1.000
Centre of Gravity
(100% Full)
V.C.G.
Above B.L
(m)
L.C.G.
From Mid.
(m)
Free
Surface
Moment
((m4)
C.W. TK (C)
8.6-17.0
70.7
70.7
4.916
-125.80
47
17.0-28.0
119.2
119.2
1.724
-118.32
206
28.0-31.0
47.9
47.9
2.608
-113.87
240
57.0-73.0
87.6
87.6
8.517
-85.22
22
Sludge TK (C)
33.0-41.0
14.0
14.0
9.356
-108.12
339.5
339.5
Total
1 - 12
4.581
-110.29
11) SIGTTO Guidelines for ship to shore access for gas carriers, 1993
12) International Electro-Technical Commission (IEC) Publication 60092Electrical Installations in Ships except :
- Enclosure test for electric equipment (IEC 60092-12, 30)
- Graphic symbols (60092-2)
- Fire resistance cables (60092-401 Amendment no 1, 32, 3)
Rules of Class have preference over IEC
13) IEC Publication 60533 Electromagnetic Compatibility of Electrical and
Electronic Installations on Ships
14) ISO 6954-1984 (for hull vibration)
15) VDI 2056 Criteria for Assessment of Mechanical Vibrations in Machines
Above Rules and Regulations are applied without inspection or survey by third
parties unless certificate is required by section 1.7 Certificate and/ or other
sections
5) International Convention for the Safety of Life at Sea (SOLAS), 1974 with
Protocol of 1978, and the Amendments
6)
1 - 13
Void Area
Cofferdam
Membrane Sheet
Primary Membrane
Secondary Membrane
Ballast
Void
Cofferdam
Insulation Space
Duct Keel
Ballast Tank
Pipe Duct
Duct Keel
1 - 14
High duty and low duty compressors (hereinafter called H/D compressor and
L/D compressor), boil-off/warming up heaters, LNG vapouriser and forcing
vapouriser are installed in the cargo machinery room.
An oil fired inert-gas generator unit is installed in a separate compartment
within the engine room to supply the inert-gas and dry air necessary to prepare
the cargo tanks for filling with LNG, or for inspection and repair.
Standard(Mole%)
Nitrogen
0.04 1.00
0.35
Methane
86.70 90.40
88.0
Ethane
7.00 8.50
7.8
Propane
1.10 3.10
2.8
Butane
0.10 1.15
1.0
0.007 0.10
0.05
A cargo machinery room and an electric motor room is provided on the trunk
deck.
HHV
53.8 MJ/kg
LHV
49.2 MJ/kg
NOTE
Standard Composition is used for designing equipment. The equipment shall
work with any composition complying with the range shown in the above
table.
The cargo containment, cargo systems and ships hull structures are designed
on the following bases.
5. Boil-off rate
This dome is used as a common access for the cargo handling equipment into
the tank and also for various instrumentation and control lines, and as a means
for personnel access into the tank.
Each tank is also fitted with a gas line at the middle of cargo tank top.
The domes are properly insulated inside to reduce thermal heat flow and
provide feed-through for cargo pipes, electric power, instrumentation and for
other necessary installations.
Density, cargo LNG : 470kg/m for general design of the ship, 500
kg/m for hull scantlings, cargo containment system and cargo pumps.
The maximum boil-off rate of the cargo during a loaded voyage (tanks to be
full but cargo piping to be empty) is less than 0.15% per day of the cargo
volume at the fully loaded condition (98.5% of their total capacity) under the
following conditions.
Temperature
+45C
+32C
Cofferdam temperature
+5C
Other compartments
no heating
Temperature of cargo
-161.5C
Cargo
The cargo handling piping system shall consist basically of fore and aft LNG
liquid and vapour headers connected to their respective crossover and branch
lines leading to each cargo tank.
The shore connections with two (2) liquid crossovers with Y piece and one (1)
vapour crossover are provided, and the lines are arranged to allow for easy
access for operation.
The cargo pumps and stripping/spray pumps are of the electric motor-driven,
submerged type, and are installed in each cargo tank.
Range(Mole%)
Two nitrogen generators are installed in the engine room to supply the N2 gas
necessary to fill and make up the insulated spaces and purge the pipes, etc.
1. Cargo
Composition
4 Cargo composition
The make up of the LNG to be handled as loaded is expected to be within the
following range.
1 - 15
Sea condition
Cargo tank surface condition
Pure methane
106 kPa Absolute
calm
100% wetted
NOTE
The natural boil-off rate of 0.15% per day is achieved without the use of
vacuum conditions in the insulation space.
425 kg/m
Latent Heat
511 KJ/kg
Cargo tanks are said to be full when they are filled to within 98.5% of their
total capacity.
Metered under a constant pressure of 106 kPa Absolute in the cargo tanks
(steady state established for 48 hours at least)
Checked from readings made at sea in fine weather (Beaufort 5) during a
voyage in the loaded condition, after the ship has been loaded and upon arrival
in harbour before unloading takes place.
No liquid pumping is done using the forcing vapouriser and sprayer during the
voyage.
The average of corrected calculated rates from the readings made during at
least ten (10) voyages in the loaded condition, excluding the first voyage on
entering service.
6. Design and calculation
Cargo Tank Pressure
The design normal operation pressure Range of cargo tanks is between 7 kPa
and 19 kPa.
The maximum pressure of gas in the tank is 25 kPa MARVS (Maximum
Allowable Relief Valve Setting) above atmospheric pressure.
Insulated Spaces
There are two (2) different spaces located between the primary barrier and the
inner hull.
-
The inter-barrier space (I.B.S) between the primary and the secondary
barrier.
- The insulation space (I.S) between the secondary barrier and inner hull.
The two (2) spaces are maintained in a dry and inert condition using nitrogen
gas.
The pressure in these spaces is regulated at a pressure slightly above
atmospheric pressure in order to prevent any air ingress.
For the inter-barrier space the pressure is maintained between 0.5 kPa and 1.0
kPa above atmospheric pressure.
Sailing at sea with filling ratios between 10% of the tank length and 70% of
the tank height is prohibited.
7. Construction of the Insulation and Barriers
- Elongation at break 10 %
Glasscloth
The specified material for the prefabrication of the insulating panels are
supplied by manufacturers and approved by GTT.
12mm plywood
Fibreglass content : 10 %
The 12mm plywood is used at the verso face in the fabrication of the
insulating panels and top bridge pads:
- Wood species : Birch
Aluminium foil
1 - 16
9mm plywood
The 9 mm plywood is used for the fabrication of the insulating panels
92 mm plywood
The 92mm plywood is made by the bonding of several plywood panels of
15mm nominal thickness. This plywood is used for the fabrication of
hardwood keys.
Adhesive Products
Three (3) different kids of adhesive product are supplied by manufacturers and
approved by GTT.
-
Epoxy glue.
Polyurethane glue.
Epoxy glue
Epoxy glue is used for assembling the insulating elements
Product with two components: resin + hardener
Volumetric mass of mixture: 1.3
Load bearing mastic
Loading bearing mastic is used for the supporting of insulating panels.
Product with two components: resin + hardener.
Mixing and application with automatic machine
Volume mass of mixture: 1.5
Polyurethane glue
1 - 17
1 - 18
Angle Piece
Membrane Sheet
Plugs
Anchoring Strip
Flat Panel
Stud
Corner Panel
Retainer
Stud
Levelling W edge
1 - 19
Inner Hull
Fitting Components
for Flat Panel
Cylindrical plug
Top bridge pad
Cylindrical plug
Nut HM 10
Washer LL 10
Flat panel
Secondary
barrier joint
Stud
Level wedge
Anchoring strip
Secondary
barrier (Triplex)
Flat joint
1 - 20
Sandwich Panel
Note :
Actual dimensions of inner hull are
compensated by tolerance 40
Secondary barrier
curve joint
S+P
S
Glass wool
Secondary barrier
Insulating foam
Flat panel
Back Plywood
Th. 9mm
A
A
A
Insulating foam
A
525
Flat Panel
75 40
Junction band
1020
Transverse Bulkhead
525
510 40
340 40
210
340
340
340
75 40
210
90
S+P+210+210 = 690
340
40
Longitudinal bulkhead
55
30
70
880
120
1 - 21
140
Sandwich Panel
B
Note :
Actual dimensions of inner hull
+40
are compensated by tolerance
-20
Secondary barrier
curve joint
A
Top plywood
Th. 9mm
Secondary barrier
A
A
Insulating foam
Plywood Th. 12mm
Corner 3 BIS
Top plywood A
Th. 9mm
S+
P
A
A
Insulating foam
A
Back plywood
Th. 9mm
Back plywood
Th. 9mm
S+
P
Corner 3
8
0.
48
8
0.
48
Junction band
396
Flat Panel
396
4
0.
24
381 +40
-20
E-
211 +40
-20
340
381 +40
-20
340
211 +40
-20
-K
E-
-H
170
340
340
-H
151
Flat Panel
-K
151
45 +40
-20
Fl
at
P
170
45 +40
-20
an
el
0
+4 0
-2
45
0
+4 0
-2
45
6
39
321
6
39
70
15
40
A-C
321
70
55
15
20
(S+P)/Tan(135/2)+151+170 = 432.8
55
70
F-J
20
40
70
(S+P)/Tan(135/2)+321 = 432.8
(X+S+P)/Tan(135/2)+321+15 = 453.1
(X+S+P)/Tan(135/2)+321+15 = 453.1
1 - 22
Tank construction
1. General description
The following components of the MARK- containment system are applied as
follows:
z
The 1.2mm thick stainless steel primary barrier, whose main feature
consists of an orthogonal system of corrugations which compensate for
thermal contraction and mechanical ships deflections.
The insulation, which consists mainly of rigid polyurethane foam with
reinforcing glass fibre in between two (2) plywood sheets. The
insulation transmits cargo pressure to the internal structure of the vessel.
The upper face plywood of insulation panels are used to fit stainless steel strips
for the membrane fastening and also to support the membrane.
Two and Three-way corner panels:
The corner panels include reinforcing components for anchoring of the
membrane in the corners of the tank and are;
z
z
Welding of the studs for the panels and corner panels are done.
Welding of retainers for corner panels are performed at the blockconstruction stages as their position is perfectly determined with respect to
the edge of the tank.
3) Setting of the leveling wedges
Load bearing mastic application and corner panel installation are done.
Bonding and putting the flat wall panels at their locations are done.
The panels are kept in place with the studs.
5) Inserting of the joint between panels
Insulation manuals and check sheets for the components, approved by the GTT,
the class and Buyer, are used at every stage of installation work and the results
are recorded.
Welders and operators for the welding machines are certified on the basis of
approved qualification procedures.
All welds are subjected to qualification tests for authorization and supervision by
the GTT during the actual construction work.
Main procedure of the cargo containment works are carried out as follows.
1) Hold preparation
1 - 23
8) Tracing
Tracing and membrane sheet positioning are done.
9) Installation of membrane sheets
Installation of the membrane sheets and temporary fixing by clamps are
done.
10) Tack welding
Tack welding of the edge of membrane sheets onto the anchoring pieces
and/or on the overlapped membrane sheet already in place are done.
11) Continuous welding operation
Continuous welding operation is achieved in order to ensure tightness of
the primary barrier. This welding operation is performed either manually
or automatically.
Simultaneously, angle pieces are put in place and welded as for the
membrane sheets.
1 - 24
E
E
Watertight Bulkhead
E
E
A
B
E
In addition to the failure of the membrane, local cold spots can occur due to
failure of the insulation.
Whilst the inner hull steel quality has been chosen to withstand the minimum
temperature likely to occur in service, prolonged operation at steel temperatures
below 0C will cause ice build-up on the plating, which in turn will cause a
further lowering of steel temperature due to the insulating effect of the ice.
To avoid this, glycol heating coils are fitted in the cofferdam spaces, of sufficient
capacity to maintain the inner hull steel temperature at 0C under the worst
conditions.
DH
DH
AH
Pipe Duct
1 - 25
B.V.H.
Room
Distilled
Water Tank
(P&S)
2nd Deck
M.L.O
Stor.
Tank
(S)
M.L.O
Sett.
Tank
(S)
Engine Room
1.5
m
Trunk (Void)
1.5
m
No.1 Trunk
G/E
M.D.O
Service
Tank (S)
Bosun Store
Low
Sulphur
M.D.O Fuel
Storage Tank
(S)
Tank
(S)
H.F.O
Settling
Tank (S)
4th Deck
AFT H.F.O
Bunk
Tank (S)
H.F.O Overflow
Tank (S)
M.L.O Grav.
Tank (S)
Cargo Tank
Fore Peak
Tank
(Void)
H.S.C
Pipe
Duct
L.S.C
C.W. Tank
1.5
m
3
m
m
3
3
No.2 Trunk
S.L.
3rd Deck
No.3 Trunk
Pool
Tank
Incinerator
Room
Deck
Store
m
3
Paint
Store
L.P.
3m
L.P.
Fore
Mast
No.4 Trunk
25
.0
1.5
1.5
Vent Mast
Vent Mast
Cargo Hose Handling Crane (P&S)
(S.W.L. 10 Ton, 5-25 m, P&S)
6.0 m
L.P.
4.0 m
Cargo Gear
Locker
6.0 m
m
3
1.5
Vent Mast
1.5
3
G/E L.O
Storage
Tank (S)
25
.0
4.0 m
1.5
Vent Mast
6.0 m
1.5
4.0 m
Fan
Room
6.0 m
5 Ton
(P&S)
4.0 m
1.5
25
.0
25
.0
No.5 Cofferdam
No.4 Cofferdam
No.3 Cofferdam
No.2 Cofferdam
No.1 Cofferdam
Key
m
1.5
UPPER DECK
AIR CON
ROOM
POOL TANK
NO.1 CARGO
SWBD. RM
NO.1 CARGO
(LOW)
TRANSFOEMER
ROOM
C.D.
&
P.D
25
.0
CHANGE
ROOM
(ENG)
CO2 ROOM
DRY
CABLE POWDER
SPACE SPACE
NO.1 CARGO
SWBD. RM
(HIGH)
C.L.
DRY
ROOM
SHIP'S
LAUNDRY
GARB.
STR
PAINT
STORE
DECK
STORE
INCINERATOR
ROOM
FIRE
EQUIP'T
LKR.
E/R
BATT.
ROOM
SUEZ
WORKER
(4-P)
CHANGE
ROOM
(DECK)
LINEN
LKR
PUR.
C.G
LIFT
C.D.
&
P.D
NO.2 CARGO
SWBD. RM
(HIGH)
NO.2 CARGO
NO.2 CARGO TRANSFORMER
FIRE
ROOM
CONTROL LBY SWBD. RM
CABLE
(LOW)
STATION
SPACE
WINCH
MOTOR
ROOM
CARGO
COMPRESSOR
ROOM
ONLY
1 - 26
The entire cargo piping system and cargo tanks are also considered gas
dangerous.
When testing enclosed spaces for the presence of natural gas, it is important to
ensure that pockets of gas are not trapped near deck-head structures, etc.
In the case of a leak or spillage of LNG the following procedure must be carried
out;
1.
5
5
Gas dangerous spaces or zones are zones on the open deck within 3.0 m of any
cargo tank outlet, gas or vapour outlet, cargo pipe flange, cargo valve and
entrances and ventilation openings to the cargo compressor house. They also
include the open deck over the cargo area and 3 m forward and aft of the cargo
area on the open deck up to a height of 2.4 m above the weather deck, and a zone
within 2.4 m of the outer space of the cargo containment system where such
spaces are exposed to the weather.
1.
Under the IMO code for the Construction and Equipment of Ships Carrying
Gases in Bulk, the following are regarded as hazardous areas:
All electrical equipment sited in hazardous areas is of the intrinsically safe type.
Fresh air intakes supply and exhaust ventilators for the cargo compressor room,
cargo electric motor room, side passage and pipe duct are provided.
The area around the air-swept trunk, in which the gas fuel line to the engine
room is situated, is not considered a gas dangerous zone under the above Code.
Trunk (Void)
NOTE
Cargo Tank
Safety Precaution
The piping system fitted on board enables the cargo system to be operated safely,
provided that certain procedures are followed. Since flammable gases are
involved, inert gas or nitrogen gas is used to eliminate the possibility of an
explosive mixture existing in the cargo system during any part of the gas-freeing
operation. The system will also enable the cargo tanks to be purged with inert gas
or nitrogen prior to filling with cargo. The piping has been arranged to eliminate
the possibility of pockets of gas or air remaining after gas-freeing or purging.
Pipe
Duct
The gas-freeing process follows a distinct cycle from cargo vapour, to inert gas,
to air, with the cargo vapour displaced by good quality inert gas before air is
introduced into the tanks. The reverse procedure is adopted when preparing the
ship for resumption of service after dry docking or lay-up.
Boil-off gas is supplied to the main boilers through an air-swept trunk that is
continuously monitored for gas leakage. Any interruption or failure of the gas
supply initiates a closure of the gas supply and an automatic nitrogen purge of
the whole engine room gas supply system.
1 - 27
1 - 28
Part 2
Properties of Gases
Part 2 Properties of Gases
+20
0
- 20
- 40
Methane vapour
temperature
- 60
- 80
-100
-120
Heavier than air
-140
-160
1.5
1.4
1.3
Ratio =
1.2
1.1
1.0
0.9
0.8
0.7
0.6
0.5
21
-165
-160
-155
-150
-145
-140
-135
-130
-125 -120 -115 -110 -105 -100 -95 -90 -85 -80 -75 -70 -65 -60-55 -50 -40 -30 -20 -10 0
25
50
75
100
60
50
40
30
20
P
Propane
2mol% Ethane
Methane
Ethylene
Ethylene
Propylene
10
9
8
7
Propane
bar
6
5
4
Butadrene
1.3
N. Butane
ata
1
0.9
0.8
0.7
-165
-160
-155
-150
-145
-140
-135
-130
-125 -120 -115 -110 -105 -100 -95 -90 -85 -80 -75 -70 -65 -60-55 -50 -40 -30 -20 -10 0
25
50
75
0.6
100
TEMPERATURE(0 C)
22
Blank Page
23
The composition of the LNG is changed by this boil-off because the lighter
components, having lower boiling points at atmospheric pressure, vaporise first.
Therefore the discharged LNG has a lower percentage content of nitrogen and
methane than the LNG as loaded, and slightly higher percentages of ethane,
propane and butane, due to methane and nitrogen boiling off in preference to the
heavier gases.
Composition of LNG
Ethane
Propane
Butane
Pentane
Nitrogen
CH4
C2H6
C3H8
C4H10
C5H12
N2
16.042
30.068
44.094
58.120
72.150
28.016
-161.5
-88.6
-42.5
-5
36.1
-196C
kg/m3
426.0
544.1
580.7
601.8
610.2
808.6
0.554
1.046
1.540
2.07
2.49
0.97
619
413
311
311
205
649
5.3 to 14
3 to 12.5
2.1 to
9.5
2 to 9.5
3 to 12.4
Auto-Ignition Temperature
595
510
510/583
510/583
Molecular Weight
55,550
51,916
50,367
49,530
49,404
49,069
48,944
kJ/kg
510.4
489.9
426.2
385.2
357.5
199.3
-82.5
43
bar(a)
24
Standard
90.28
84.5
89.63
C2H6
6.33
12.9
6.32
(mol %)
n-C3H8
2.49
1.5
2.16
Butane
(mol %)
n-C4H10
0.49
0.5
1.20
Iso-Butane
(mol %)
i-C4H10
0.00
0.00
0.00
Pentane
(mol %)
n-C5H12
0.02
0.00
0.00
Iso-Pentane
(mol %)
i-C5H12
0.00
0.00
0.00
Nitrogen
(mol %)
N2
0.41
0.6
0.69
17.88
18.56
18.12
-160.8C
-161.0C
-160.9C
461.8
456.8
459.4
54,414
54,031
54,090
Methane
(mol %)
CH4
Ethane
(mol %)
Propane
Density (kg/m )
Higher Specific Energy (kJ/kg)
kJ/kg
Critical Pressure
Das
Islands
Nonflammable
Critical Temperature
Ras
Laffan
21
The ship must be operated in such a way that a flammable mixture of methane
and air is avoided at all times. The relationship between gas/air composition and
flammability for all possible mixtures of methane, air and nitrogen is shown in
the diagram (See Illustration 2.1.2.a).
Area EDFE
flammable
B
E
20
18
17
16
15
14
G
13
12
%
O
x
y
g
e
n
Caution
This diagram assumes complete mixing
which, in practice, may not occur.
19
M
N
X
D
Any single point in the diagram within the triangle ABC represents a mixture of
all three components, methane, oxygen and nitrogen, each present in a specific
proportion of the total volume. The proportions of the three components
represented by a single point can be read off the diagram.
For example, at point D:
11
y
y
y
10
9
1) The Flammable Zone Area EDF: Any mixture the composition of which
is represented by a point that lies within this area is flammable.
7
6
5
Area HDFC
capable of forming flammable
mixtures with air, but containing
too much methane to explode
4
3
2
1
A 0
10
H 20
30
40
50
60
70
80
Methane %
Area ABEDH
not capable of forming
flammable mixture
with air
90
C
100
25
3. Cryogenic Temperatures
Contact with LNG or with materials chilled to its temperature of about -160C
will damage living tissue.
Most metals lose their ductility at these temperatures; LNG may cause the brittle
fracture of many materials. In case of LNG spillage on the ships deck, the high
thermal stresses generated from the restricted possibilities of contraction of the
plating will result in fracture of the steel. The Illustrations 1.3.3a and 2.1.3a
show a typical ship section with the minimum acceptable temperatures of the
steel grades selected for the various parts of the structure.
26
When loaded in the cargo tanks the pressure of the vapour phase is maintained as
substantially constant, slightly above atmospheric pressure.
The external heat passing through the tank insulation generates convection
currents within the bulk cargo; heated LNG rises to the surface and boils.
The heat necessary for the vaporisation of LNG comes from the outer
environment of the cargo tanks leaking through the cargo tank insulation. As
long as the generated vapour is continuously removed by maintaining the
pressure as substantially constant, the LNG remains at its boiling temperature.
If the vapour pressure is reduced by removing more vapour than is generated, the
LNG temperature will decrease. In order to make up the equilibrium pressure
corresponding to its temperature, the vaporisation of LNG is accelerated because
of an increased heat leak into the cargo tanks.
If the vapour pressure is increased by removing less vapour than is generated, the
LNG temperature will increase. In order to reduce the pressure to a level
corresponding to the equilibrium with its temperature, the vaporisation of LNG
is slowed down and the heat transfer from LNG to vapour is reduced.
LNG is a mixture of several components with different physical properties and in
particular with different vaporisation rate; the more volatile fraction of the cargo
vaporises at a greater rate than the less volatile fraction. The vapour generated by
the boiling of the LNG contains a higher concentration of the more volatile
fraction than the LNG.
The properties of the LNG, i.e. the boiling point, density and heating value, have
a tendency to increase during the voyage..
NOTE
For environmental conditions, refer to section 1.3.3 Deterioration or Failure
.
-19.4
Grade E
Grade E
-22.8
-27.1
-21.5
Insulation Thickness
Secondary = 170 mm
+ Primary
= 100 mm
270 mm
Grade A
Grade E
Grade A
Grade E
Cofferdam
Without Heating
Grade E
Grade E
Grade A
Grade E
Grade E
Grade A
-14
Cofferdam
Without Heating
Grade D
-60.8
LNG Cargo
Temperature = -163
Cofferdam With
Heating
Grade E
Grade E
-16
Grade E
Grade A
Grade D
-53
-55
Grade D
-64.0
Grade A
Grade D
-3
Grade A
-4.0
-5.2
-6.9
0
Grade A
0
-15.9
Grade E
+5
LNG Cargo
Temperature = -163
Cofferdam With
Heating
-22.5
Insulation Thickness
Secondary = 170 mm
+ Primary
= 100 mm
270 mm
Grade E
-25.9
-15.8
-23.3
-20
+5
-16.9
-20.8
Grade E
Grade B
Grade B
Grade B
-9
Grade B
-1.9
Grade B
-1.6
Grade B
Grade B
Grade B
-3.3
Grade AH
Grade AH
Grade DH
Grade DH
27
During any type of cargo transfer and particularly whilst loading and discharging,
constant patrolling must be conducted on deck to ensure that no leakages have
developed.
In the event of a spillage or leakage, water spray should be directed at the spillage
to disperse and evaporate the liquid and to protect the steelwork. The leak must be
stopped and cargo operations suspended if necessary.
In the event of a major leakage or spillage, cargo operations must be stopped
immediately, the general alarm sounded and the emergency deck water spray
system put into operation.
Illustration 2.1.4a Structural Steel Ductile to Brittle Transition Curve
Fracture transition
range (mixed fracture
appearance)
Brittle
fracture
Ductile
fracture
Notched
bar test
Energy
absorbed
For a typical mild steel:
T1 might be -30C
T2 might be +15C
Although this depends
on composition, heat
treatment etc. the curve
can shift to left or right.
In order to avoid brittle fracture occurring, measures must be taken to ensure that
LNG and liquid nitrogen do not come into contact with the steel structure of the
vessel. In addition, various equipment is provided to deal with any leakages that
may occur.
The manifold areas are equipped with a stainless steel drip tray which collects
any spillage and drains it overboard. The ship, in way of the manifolds, is
provided with a water curtain that is supplied by the deck fire main. The fire
main must always be pressurised and the manifold water curtain in operation
when undertaking any cargo operation. In addition, fire hoses must be laid out at
each liquid dome to deal with any small leakages that may develop at valves and
flanges. Permanent drip trays are fitted underneath the items most likely to cause
problems and portable drip trays are provided for any other needs.
T1
T2
Temperature
28
Inert gas is used to reduce the oxygen content in the cargo system, tanks, piping
and compressors in order to prevent an air/CH4 mixture prior to aeration post
warm up, before refit or repairs and prior to the gassing up operation post refit
before cooling down. Inert gas is produced on board using an inert gas generator,
which produces inert gas at 15,000 Nm3/h with a -45C dew point burning low
sulphur content gas oil. This plant can also produce dry air at 15,000 Nm3/h and
-45C dew point.
Carbon dioxide
Carbon monoxide
Nitrogen
balance
< -45C
Molecular weight
28.016
Dew point
196C
1.81
0 (complete absence)
The inert gas is slightly denser than air; approx. 1.35 kg/m3 at 0C.
0.97
695
CAUTION
Due to its low oxygen content, inert gas is an asphyxiant.
None
< 80C
3) Chemical Properties
Nitrogen is considered an inert gas; it is non flammable and without
chemical affinity. However, at high temperatures, it can be combined
with other gases and metals.
CAUTION
Due to the absence or very low content of oxygen, nitrogen is an asphyxiant.
.
At liquid state, its low temperature will damage living tissue and any spillage of
liquid nitrogen on the ships deck will result in failure as for LNG.
29
Part 3
Integrated Automation System (IAS)
Part 3 Integrated Automation System (IAS)
W/H
Monitoring only
for Cargo and
Machinery System
Color Hard
Copier
20" LCD
CCR
ECR
Cargo System
Machinery System
Color Hard
Copier
20" LCD
20" LCD
PCNS
DOPC
DOPC
DOGS
8 Sets
Receptacles for
4 Other
Engineer's Cabins
Serial Communication
For Cargo System
- Custody Transfer System (CTS)(Dual)
- Secondary Level Gauging System (Cargo Tanks)
- VDR (Dual)
- INS (Dual)
- IGG
- Gas Detection System
- No.1 N2 Generator
- No.2 N2 Generator
For Machinery System
- Performance Monitor
- Fire Detecting System
- No.1 T/G
- No.2 T/G
- No.1 D/G
- No.2 D/G
DOHS
TCP I/P
OPC Communication
SMS
Loading Computer
Plasma Display
(50" Inches)
for Cargo Overview
in CCR
Ext. Alarm
Panels
Duty Selector : 2 Units
Cargo & Machinery : 8 Panels
Machinery : 10 Panels
Cargo : 2 Panels
Legend
DOSS : DEO Open Supervisory Station
DOHS : DEO Open History Station
DOGS : DEO Open Gateway Station
DOPC : DEO Process Controller
PCNS : PC Network Server
3-1
W/H
Extension VDUS
CCR
Plasma Display
(50" Inches)
for Cargo Overview
OPT.
CONV.
OPT
(2 Fibers)
DOGS
DEO-Net
(Ethernet)
DOPC
PCNS
OPT.
CONV.
DOHS
OPT.
CONV.
OPT
(2 Fibers)
OPT.
CONV.
DOPC
DOPC
OPT.
CONV.
OPT.
CONV.
OPT
(2 Fibers)
I/O
I/O
I/O
OPT
(2 Fibers)
OPT.
CONV.
OPT
(2 Fibers)
OPT
(2 Fibers)
OPT.
CONV.
OPT.
CONV.
OPT
(2 Fibers)
OPT.
CONV.
OPT
(2 Fibers)
OPT.
CONV.
OPT
(2 Fibers)
OPT
(2 Fibers)
I/O
OPT
(2 Fibers)
No.1
LVSBR
OPT.
CONV.
OPT
(2 Fibers)
OPT.
CONV.
I/O
OPT
(2 Fibers)
ECR
OPT.
CONV.
DOPC
OPT
(2 Fibers)
OPT
(2 Fibers)
No.2
LVSBR
OPT.
CONV.
DOPC
DOPC
I/O
I/O
I/O
3-2
I/O
I/O
OPT
(2 Fibers)
OPT.
CONV.
DOPC
I/O
I/O
DOPC
I/O
I/O
I/O
I/O
Legend
DOSS : DEO Open Supervisory Station
DOHS : DEO Open History Station
DOGS : DEO Open Gateway Station
DOPC : DEO Process Controller
PCNS : PC Network Server
OPT. CONV. : Optical Convertor
W/H
CCR
Color Hard
Copier Logging Printer
Alarm Printer
Plasma Display
(50" Inches)
for Cargo Overview
AC 220V
Battery Room
(Nav.-DK)
Battery Room
(Upp.-DK)
Batt
Batt
A
B
A B
AC 440V/60Hz
or
AC 380V/50Hz
(Normal)
UPS
No.2 LVSBD
IAS
I/O Cabinet
Room (FWD)
AC 440V/60Hz
or
AC 380V/50Hz
(Em'cy)
UPS
A
B
DOHS
DOGS
PCNS
A
B
UPS
UPS
ECR
Legend
DOSS : DEO Open Supervisory Station
DOHS : DEO Open History Station
DOGS : DEO Open Gateway Station
DOPC : DEO Process Controller
PCNS : PC Network Server
Color Hard
Copier Logging Printer
A B
UPS
B
A
IAS
I/O Cabinet
Room (AFT)
UPS
B
A
PS
PS
PS
PS
DOPC
DOPC
I/O
I/O
PS
I/O
Alarm Printer
B
A
PS
PS
DOPC
DOPC
I/O
I/O
No.1 LVSBR
Cabinet
3-3
PS
PS
DOPC
DOPC
I/O
I/O
No.2 LVSBR
Cabinet
PS
DOPC
DOPC
I/O
I/O
The Zener Barriers are applied to the 4-20mA Input/Output signals and the RTD
Input signals from hazardous areas and contact barriers are applied to the contact
input signals.
Each field devices can be manipulated from dedicated graphics. Operator just
clicks the pre-configured devices symbol and will appear the faceplate. The
clicks and enters numerical on the faceplate make him control the devices.
1. System configuration
4. Power Supply
Pressure :
Temperature :
Level :
Flow :
Controllers/Receivers :
.
Environmental Conditions
Fully covered all of IAS power, except engineers cabin human interface
station(Extension VDU), is assured by uninterrupted power supplies. A UPS is
fed from normal feeding line, the other fed from emergency feeding line. The
autonomy of each is 30min. Both of normal and emergency feeding power are
always coming from ships power bus. On the wheelhouse station(DOSS), ECR
stations(DOSS), CCR station(DOSS), DOHS, DOGS, and PCNS are used
normal line in case of both feeding alive. When the normal feeding fails, those
are change to emergency feeding by automatically. This change has a specific lag
time then supported by small UPS to compensate the interruption during change
over.
-
2. Display Layout
Display Call-up Toolbar
Ship's Time(*1)
One Line Alarm Indication
1. General
0.75% of span reading
0.75% of thermocouples
3.0% for resistive temperature
detectors
According to maker standard, but
not more than 25mm
1.5% unless otherwise specified
2% of set point (steady states)
It is fully integrated with Marine-DEO and can be a client node for DOPC and
DOHS for LNGC monitoring control.
NOTE
* 1 : Ships Time : MM / DD/ YYYY HH:MM
* 2 : System Standard Time : MM / DD / YYYY (WWW) HH : MM : SS
3. Intrinsic Safety
MM : Month
DD : Day
YYYY : Year
Operating temperature :
Relative humidity :
Vibration :
3-4
HH : Hour
MM : Minute
WWW : Week
3. Keyboard
Graphic displays can be built so that the operator can monitor and manipulate the
process directly from them. Both continuous and discontinuous processes can be
managed from graphic displays. Basically, any data point parameter or sequence
can be monitored and manipulated from any graphic display.
Graphic behaviors such as blinking, color changes, bar graphs, appearance of
subpictures, and numeric values can be controlled by parameters of data points
POWER
GOOD FAIL
RESET
STATS
MAN
AUTO
SP
"
&
<
>
SP
CAS
OUT
ENTER
ACK
SIL
Prev
Page
Next
Page
Close
Cancel
Prev
Disp
Next
Disp
Last
Cancel
Message
Clear
ALARM button
3.
SYS
button
4.
MESSGE button
5.
SEQ
button
6.
PREVIOUS
button
7.
NEXT button
8.
GRAPHIC button
9.
GROUP button
10
TREND button
11.
DETAIL button
12.
REPORT button
13.
SYS
button
14.
PRINT button
Execute
TAB
Alpha
Shift
2.
STATS
EVENT
CONF
Display Items
Contents
Free Memory
Mode Indicator
.
Access
Indicator
Level
One-Line
Window
Alarm
Display Items
Contents
1.
SILENCE button
3-5
No.
Display
Items
Contents
1.
Page
2.
Group No.
3.
Group Title
4.
Faceplate
No.
Display Items
Contents
1.
Trend No.
2.
Trend title
3.
Trend area
4.
Pen No.
5.
Trend operation
buttons
7.
Relative time
8.
Digital Value
9.
Display range
10.
Trend display
Time stamp
11.
Point parameter
Area
12.
Connection
Information part
13.
14.
15.
16.
Scroll buttons
17.
Time-axis scroll
Slide buttons
18.
19.
Collection period
(only for Local
trend)
Display items
Contents
1.
Filter
2.
Sort by
3.
Update
display
4.
Associate
display
Operation status
(only for Local
trend)
5.
Unit
alarm
summary
6.
Online manual
7.
ACK
3-6
No.
8.
Page
9.
Select button
10.
Priority
11.
Time stamp
12.
Alarm
indicator
13.
Point
description
14.
EU
15.
Set value
16.
Alarm value
17.
ID
18.
Tag name
19.
Select unit
20.
Column resize
21.
Horizontal
scrollbar
3-7
1. General
1. General
E-1
ETM
E-3
MSC
I-A
E-1
E-A
E-2
E-B
E-3
E-A
MSC
I-B
I-A
I-2
I-3
E-B
MSC
I-B
I-1
XBM
DOCM Configuration shows the DOCM system. The DOCM is composed of the
following modules.
- Control Module (MSC)
- Ethernet Module (ETM)
- X-BUS Module (XBM)
E-2
E-B
I-1
ETM
E-A
2. Reliability
DOHS
DEO-Net
DEO-Net
DOPC consists of ;
DOSS
I-A
I-2
I-3
XBM
DOCM
X-BUS A
X-BUS B
Three (3) sets of control modules (MSC) have redundant configuration, and
execute the same processing synchronized with each other. The ethernet module
(ETM) and the X-BUS module (XBM) compare outputs of three (3) MSCs, and
get data by logic of majority, i.e., 2 out of 3. Even though one of MSC outputs
incorrect data, the remaining two (2) data are correct and used for the control and
monitoring.
3-8
I-B
I/O
I/O
The monitoring & control system provides some kinds of alarms as follows.
1. Process Alarm
Start
2. System Abnormal
-
DOSS abnormal
Alarm Printer abnormal
DOHS abnormal
DOGS abnormal(PCNS)
DOPC abnormal
DEO-NET communication abnormal
Buzzer
Sounding
Buzzer Stop
Alarm
Printout
Remarks
: Operator's action
System Abnormal
Alarm Occurred?
: Phenomenon
Yes
No
Call-up Related
Graphic Display
Recovery Operation
Recovery Operation
Alarm Acknowledgement
Alarm Acknowledgement
(Flicker Stop)
End
3-9
Clock)
- TAG name
- Description
In addition to the above, the system status changes including system abnormal
are printed out on the alarm printer.
Description
CCC
Alarm Set-point
Tag Name
Alarm Priority
Alarm Type
DOSS
1
DOSS
2
DOSS
3
DOSS
4
Printer Cable
Cargo
Alarm Printer
Current
Value/Status
Tag Name
Current Status
2001/05/18 13:42:55.652
XABI11
STOP
MA
2001/05/18 13:42:56.296
PALLBI106_2
L-L
MA
2001/05/18 13:42:57.064
PALLBI106_1
L-L
MA
2001/05/18 13:42:57.426
XABI104_2
FAIL
MA
2001/05/18 13:42:58.014
XABI104_1
FAIL
MA
2001/06/18 11:24:18
OFFNORM
XAFD22_1
ABNOR
MA
ALM
2001/06/18 11:24:29
OFFNORM
XAFD22_1
ABNOR
MA
ACK
2001/06/18 11:24:58
OFFNORM
XAFD22_1
NOR
MA
RTN
2001/06/18 11:26:11
OFFNORM
LALOF83_1
LOW
MH
ALM
2001/06/18 11:29:03
OFFNORM
LALOF83_1
NOR
MH
RTN
2001/06/18 11:29:19
PVHI
TIAMS11
530.1
525.0
DEG C
MD
ALM
2001/06/18 11:29:19
PVHI
TIAMS11
510.0
525.0
DEG C
MD
RTN
2001/06/18 11:29:19
BADPV
PIAEX51_1
MG
ALM
2001/06/18 11:29:47
PVHI
TIAMS11
MD
ACK
505.0
525.0
DEG C
E : Em'cy
OFFNORM : Off-normal Alarm (Digital Alarm)
PVHH : PV High-high Alarm
PVHI : PV High Alarm
PVLO : PV Low Alarm
PVLL : PV Low-low Alarm
BADPV : Bad PV Alarm
ECC
DOSS
6
DOSS
5
Printer Cable
Machinery
Alarm Printer
The historical alarm information is printed out on the alarm printer with a
reference time. For the process alarm, the alarm printout provides the following
events.
- Alarm occurrence
- Alarm acknowledgement
- Alarm recovery
The major printout item is as follows.
- ALM, ACK, RTN
DATE/Time : YYYY/MM/DD XX:XX:XX (HH:MM:SS)(Ships
The IAS provides data logging function in accordance with the following
specification.
1. Fixed time Report
Description
E.U.
DOSS
8
The fast alarm function is a high speed scanning function for finding out a trip
cause. The fast alarms are recorded on the hard disk of DOSS(DEO Open
Supervisory Station) automatically. The operator can display and print the
recorded Fast Alarms.
If an equipment comes to trips, the procedure for finding out the trip cause is as
follows.
This report is printed out automatically in accordance with the selected time
interval (Based on Ships Time).
- 1 hour interval : 0:10 ~ 00:00
- 2 hour interval : 0:00, 2:00, 4:00, 6:00, 8:00, 10:00, 12:00,
14:00, 16:00, 18:00, 20:00, 22:00
- 4 hour interval : 0:00, 4:00, 8:00, 12:00, 16:00, 20:00
- 8 hour interval : 0:00, 8:00, 16:00
- 12 hour interval : 0:00, 12:00
2. Demand Report
2) The Fast Alarms are indicated on the dedicated display and printed on
the logging printer with operators request.
This report is printed out at the operators request. The format of Demand
Report is same as Fixed Time Report.
3) The Fast Alarms are indicated and printed the order of its occurrence
time..
Operator can find out the trip cause for that equipment.
To realize the Fast Alarm Function, The IAS applies specialized digital I/O
modules, i.e. DISOE, Digital Input Sequence of Event.
The DISOE provides high-resolution scanning within 20 ms. the Figure 3.8.1
shows the sample printing.
3 - 10
Control Console
Buzzer
& ACK
Signal
Duty
Selection
Buzzer
Signal
DOSS
Engineer/
Officer
Call
Patrolman
Alarm
Group Alarm
Condition
DOPC II
DOPC II
SIM
I/O
Hard Wiring
Bi-directional
Serial Communication
Extension
Alarm
LCD
Engineer
Call Lamp
BZ
Extension
Alarm
LCD
BZ
BZ
Engineer
Call Lamp
BZ
Note :
DOSS : DEO Open Supervisory Station
DOPC II : DEO Process Controller II
SIM : Serial Interface Module
LCD : Liquid Crystal Display
BZ : Buzzer
3 - 11
Extension alarm indicator consists of the color LCD indicator. A set of LCD can
be displayed both extension alarm indication and duty indication on an extension
alarm panel.
One set of duty selector is furnished in the Cargo Control Console and Main
Control Console for Cargo and Machinery Systems.
These duty selectors are used for duty officer and duty engineer selection.
The duty officer selector is furnished on a Cargo Control Console.
1. Alarm Groups
It is possible to select plural officers as the duty
The extension alarm groups are shown on the following tables.
4. Display Layout
Table 3.10.1 Extension Alarm Group of Cargo System
Extension Alarm Group
Group Description
CA
ESD
CB
PRIORITY
CC
NN PRIORITY
CD
FIRE
CE
GAS
CF
SYSTEM TROUBLE
MACHINERY
CARGO
ESD
M/T TRIP
PRIORITY
M/T TROUBLE
NON PRIORITY
FIRE
GAS
SYSTEM TROUBLE
Group Description
MA
MB
M/T TRIP
MC
M/T TROUBLE
FIRE
MD
GAS
ME
MF
MG
MH
E/R BILGE
MJ
FIRE
MK
GAS
ML
SYSEM TROUBLE
SYSTEM TROUBLE
Note
: Alarm Indicator
: Duty Indicator
When the alarm occurs, the indicator that is involved the event is flashing in red
and audible alarm will be initiated. The duty assigned engineer / officer can do
silence the audible.
The event is accepted in the control console, the group alarm indicator will be
steady. It remains as steady in red until the condition disappears.
3 - 12
W/H
(INS)
ECR
Off Duty
Abnormal
Happen
Audible buzzer only initiated under unmanned condition. The sound is passed
only duty assigned engineers / officers and public room.
Reset
Timer
Cut SW
Other
Panels
Non
*2
*2
5 Min.
Time
Delay
Cut
5 Min.
Time
Delay
Flicker
Flicker
Flicker
Flicker
Flicker
Flicker
Flicker
Flicker
Sound
Sound
Sound
Sound
Stop
Sound
Stop
Sound
Buzzer
Stop
Buzzer
Stop
Buzzer
Stop
Buzzer
Stop
Buzzer
Stop
Buzzer
Stop
Flicker
Flicker
Stop
Stop
Flicker
Flicker
Flicker
Flicker
Flicker
Stop
Stop
Stop
Stop
Stop
Flicker
Steady
Steady
Steady
Steady
Steady
Steady
Steady
Stop
Stop
Stop
Stop
Stop
Stop
Stop
Stop
Off
Off
Off
Off
Off
Off
Off
Off
Stop
Stop
Stop
Stop
Stop
Stop
Stop
Stop
Acknowl
-edge
Steady
Stop
Return to
Normal
Note :
Lamp
Buzzer
*1. The indication is on Alarm Summary Display, the actions are by keyboard.
: Indication / Status
*2. If the alarm is not stopped by duty engineer within 5 min, the buzzer
sound is activated.
: Action
*3. When ECC buzzer is not stop within 10 minutes, Machinery Engineer
alarm will be activated automatically.
*4. Buzzer of all panel is not activated during no duty engineer is selected,
but, lamp indication is always enabled.
: Condition
3 - 13
CCR
W/H
Off Duty
Abnormal
Happen
Reset
*2
5 Min.
Time
Delay
Flicker
Flicker
Flicker
Flicker
Flicker
Flicker
Sound
Sound
Sound
Sound
Stop
Sound
Buzzer
Stop
Buzzer
Stop
Buzzer
Stop
Buzzer
Stop
Buzzer
Stop
Flicker
Flicker
Stop
Stop
Flicker
Flicker
Flicker
Flicker
Stop
Stop
Stop
Stop
Flicker
Steady
Steady
Steady
Steady
Steady
Stop
Stop
Stop
Stop
Stop
Stop
Indication Lamp
- Chief Engr's Room
ECR
ECR
1/E
1/E
1/E
On Duty
2/E
2/E
2/E
On Duty
3/E
3/E
3/E
On Duty
4/E
4/E
4/E
On Duty
Steady
Indication Lamp
- Chief Engr's Room
Stop
Return to
Normal
Off
Off
Off
Off
Stop
Stop
Stop
Stop
Stop
Stop
Note :
Lamp
Buzzer
*1. The indication is on Alarm Summary Display, the actions are by keyboard.
: Indication / Status
*2. If the alarm is not stopped by duty engineer within 5 min, the buzzer
sound is activated.
: Action
*3. When CCC buzzer is not stop within 10 minutes, Cargo Engineer
alarm will be activated automatically.
*4. Buzzer of all panel is not activated during no duty engineer is selected,
but, lamp indication is always enabled.
: Condition
1st Engineer
2nd Engineer
3rd Engineer
4th Engineer
ECR
Selector
Position
Off
Acknowl
-edge
Off
Duty State
3 - 14
Duty State
- Chief Officer
- Gas Engineer
- 1st Officer
CCR
CCR
CCR
C/O
C/O
C/O
On Duty
G/E
G/E
G/E
On Duty
1/O
1/O
1/O
On Duty
3 - 15
Part 4
Cargo System
Part 4 Cargo System
POINT DESCRIPTION
CODE
R_LOW
R_HIGH
ALARM DETECTION
LL
HH
FB
ST
ALM ALM
UT
ALM
INH GRP
ID
TM
TD
IS
I/O TB LOC
ASSOCIAT
ADDRESS
IOM
EXT
DISPLAY
ND IOM SLT
REMARK
AC905
AL
1000
ppm
D0
250
BAD
C05
CE
SM-1F
SM-1F
14
AC906
AL
1000
ppm
D0
250
BAD
C05
CE
SM-1F
SM-1F
14
AC912
AL
1000
ppm
D0
250
BAD
C05
CE
SM-1F
SM-1F
14
12
BA078
1 SWBT P LEVEL
LIAH
0.00
26.166
D2
14.2
BAD
20
C03
CC
15
--
60
BA077
1 SWBT S LEVEL
LIAH
0.00
26.166
D2
24.45
BAD
20
C03
CC
15
--
61
B_077
1 SWBT S LEVEL
CONT
0.00
26.166
D2
(24.45)
--
CX
17
--
101
BA061
PI
0.0
800.0
kPa
D1
250
BAD
C03
CC
C-3F
C-3F
15
11
BA047
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-3F
C-3F
15
11
BA048
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-3F
C-3F
15
11
BA049
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-3F
C-3F
15
11
BA046CR
AL
0 00
0.00
60 00
60.00
D2
40 1
40.1
BAD
C03
CC
C-3F
C
3F
C-3F
C
3F
15
BA080
2 SWBT P LEVEL
LIAH
0.00
26.165
D2
24.92
BAD
20
C03
CC
15
--
62
BA079
2 SWBT S LEVEL
LIAH
0.00
26.165
D2
24.92
BAD
20
C03
CC
15
--
63
B_079
2 SWBT S LEVEL
CONT
0.00
26.165
D2
(24.92)
--
CX
17
--
102
BA065
PI
0.0
800.0
kPa
D1
250
BAD
C03
CC
C-8F
C-8F
17
BA056
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-8F
C-8F
17
13
BA057
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-8F
C-8F
17
13
BA058
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-8F
C-8F
17
13
BA056CR
AL
0.00
60.00
D2
40.1
BAD
C03
CC
C-8F
C-8F
17
BA091
3 SWBT P LEVEL
LIAH
0.00
26.165
D2
24.9
BAD
20
C03
CC
15
--
64
BA092
3 SWBT S LEVEL
LIAH
0.00
26.165
D2
24.9
BAD
20
C03
CC
15
--
65
B_092
3 SWBT S LEVEL
CONT
0.00
26.165
D2
(24.9)
--
CX
17
--
103
BA063
PIAL
0.0
800.0
kPa
D1
250
BAD
C03
CC
C-8F
C-8F
17
BA053
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-8F
C-8F
17
13
BA054
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-8F
C-8F
17
13
BA055
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-8F
C-8F
17
13
BA051CR
AL
0.00
60.00
D2
40.1
BAD
C03
CC
C-8F
C-8F
17
13
4-1
IAS TAG
POINT DESCRIPTION
CODE
R_LOW
R_HIGH
ALARM DETECTION
LL
HH
FB
ST
ALM ALM
UT
ALM
INH GRP
ID
TM
TD
IS
I/O TB LOC
ASSOCIAT
IOM
EXT
DISPLAY
ADDRESS
REMARK
ND
IOM SLT
BA083
4 SWBT P LEVEL
LIAH
0.00
26.165
D2
24.97
BAD
20
C03
CC
15
--
66
BA082
4 SWBT S LEVEL
LIAH
0.00
26.165
D2
24.97
BAD
20
C03
CC
15
--
67
B_082
4 SWBT S LEVEL
CONT
0.00
26.165
D2
(24.97)
--
CX
17
--
104
BA087
LIAH
0.000
6.960
D3
6.09
BAD
C03
CC
15
--
68
B_087
0.000
6.960
D3
(6.9)
--
CX
--
--
17
--
112
BA085
LIAH
0.00
22.17
D2
20.98
BAD
20
C03
CC
15
--
69
BA084
LIAH
0.00
22.17
D2
20.99
BAD
20
C03
CC
15
--
70
B_084
CONT
0.00
22.17
D2
(20.99)
--
CX
17
--
105
BA067
PIAL
-100.0
800.0
kPa
D1
0.0
BAD
C03
CC
C-8F
C-8F
17
BA066
PIAL
-100.0
800.0
kPa
D1
0.0
BAD
C03
CC
C-3F
C-3F
15
12
CH030
1C TK COFDM F BHD S UP T
TIAL
-200
200
100
Deg C
Deg_C
D0
BAD
C02
CB
IS
C-2F
C
2F
C-1F
C
1F
16
10
CH031
1C TK COFDM F BHD P UP T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
10
CH032
1C TK COFDAM F BHD M T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
10
CH033
1C TK COFDAM F BHD P L T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
10
CH034
1C TK COFDAM F BHD S L T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
10
10
CH035
1C TK COFDAM A BHD U T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
10
11
CH036
1C TK COFDAM A BHD M T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
10
12
CH037
1C TK COFDAM A BHD L T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
10
13
CH073
2C TK COFDAM F BHD U T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
13
12
CH074
2C TK COFDAM F BHD M T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
12
11
CH075
2C TK COFDAM F BHD L T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
13
13
CH076
2C TK COFDAM A BHD U T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
12
12
CH077
2C TK COFDAM A BHD M T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
13
14
CH078
2C TK COFDAM A BHD L T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-2F
C-1F
16
12
13
CH115
3C TK COFDAM F BHD U T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
CH116
3C TK COFDAM F BHD M T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
12
CH117
3C TK COFDAM F BHD L T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
4-2
20
IAS TAG
POINT DESCRIPTION
CODE
R_LOW
R_HIGH
ALARM DETECTION
LL
HH
FB
ST
ALM ALM
UT
ALM
INH GRP
ID
TM
TD
IS
I/O TB LOC
ASSOCIAT
IOM
EXT
DISPLAY
ADDRESS
REMARK
ND
IOM SLT
CH118
3C TK COFDAM A BHD U T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
12
CH119
3C TK COFDAM A BHD M T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
10
CH120
3C TK COFDAM A BHD L T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
12
CH155
4C TK COFDAM F BHD U T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
11
CH156
4C TK COFDAM F BHD M T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
11
CH157
4C TK COFDAM F BHD L T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
11
CH158
4C TK COFDM A BHD P UP T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
11
10
CH159
4C TK COFDM A BHD S UP T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
11
11
CH160
4C TK COFDAM A BHD M T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
10
16
CH161
4C TK COFDAM A BHD S L T
TIAL
-200
100
Deg_C
D0
BAD
C02
CB
IS
C-7F
C-6F
18
11
12
CH162
4C TK COFDAM A BHD P L T
TIAL
-200
200
100
Deg C
Deg_C
D0
BAD
C02
CB
IS
C-7F
C
7F
C-6F
C
6F
18
11
13
CH040
TIAL
-200
100
Deg_C
D0
-10
BAD
C02
CB
IS
C-2F
C-1F
16
10
16
CH039
TIAL
-200
100
Deg_C
D0
-10
BAD
C02
CB
IS
C-7F
C-6F
18
11
16
CH019SW
1C TK IBS N2 PRESS
0.000
3.000
kPa
D3
0.2
1.5
C02
CB
16
--
50
CH023SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
100
CH026SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
99
CH028SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
98
CH041
1C TK IBS/IS N2 DIFF P
DPIAHL
-4.000
3.000
kPa
D3
C02
CB
--
--
16
--
48
BY 8-PX-4C/4D (IAS
INTERNAL INDICATION)
CH001
1C TK IS N2 PRESS
PIAHL
0.000
4.000
kPa
D3
0.4
2.5
BAD
C02
CB
IS
C-2F
C-1F
16
CH017SW
1C TK IS AFT TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
96
CH013SW
1C TK IS BOTTOM TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
95
CH005SW
1C TK IS CEIL TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
97
CH015SW
1C TK IS FWD TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
94
CH002I
1C TK IS IBS/IS DP
0.000
4.000
kPa
D3
BAD
C02
CB
IS
C-2F
C-1F
16
CH011SW
1C TK IS P LOW TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
93
CH009SW
1C TK IS P MID TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
92
CH007SW
1C TK IS P UPP TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
91
DPIC
4-3
IAS TAG
POINT DESCRIPTION
CODE
R_LOW
R_HIGH
ALARM DETECTION
LL
HH
FB
ST
ALM ALM
UT
ALM
INH GRP
ID
TM
TD
IS
I/O TB LOC
ASSOCIAT
IOM
EXT
DISPLAY
ADDRESS
ND
REMARK
IOM SLT
CH025
1C TK LIQ DM IBS N2 P
PIAHL
0.000
4.000
kPa
D3
0.2
1.5
BAD
C02
CB
IS
C-2F
C-1F
16
CH042
TIAL
-200
100
Deg_C
D0
-20
BAD
C02
CB
IS
C-2F
C-1F
16
11
11
CH043
TIAL
-200
100
Deg_C
D0
-20
BAD
C02
CB
IS
C-2F
C-1F
16
13
CH901SW
1C TK IS P MID WALL T SW
-200
100
Deg_C
D0
--
C02
CB
--
--
16
--
90
CH081
TIAL
-200
100
Deg_C
D0
-10
BAD
C02
CB
IS
C-7F
C-6F
18
12
CH080
TIAL
-200
100
Deg_C
D0
-10
BAD
C02
CB
IS
C-2F
C-1F
16
12
15
CH066SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
89
CH069SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
88
CH071SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
87
CH062SW
2C TK IBS N2 PRESS
0.000
3.000
kPa
D3
0.2
1.5
C02
CB
16
--
40
CH084
2C TK IBS/IS N2 DIFF P
DPIAHL
-4
4.000
000
3 000
3.000
kPa
D3
C02
CB
--
--
16
--
38
CH044
2C TK IS N2 PRESS
PIAHL
0.000
4.000
kPa
D3
0.4
2.5
BAD
C02
CB
IS
C-2F
C-1F
16
CH060SW
2C TK IS AFT TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
86
CH056SW
2C TK IS BOTTOM TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
85
CH048SW
2C TK IS CEIL TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
79
CH058SW
2C TK IS FWD TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
78
CH045I
2C TK IS IBS/IS DP
0.000
4.000
kPa
D3
BAD
C02
CB
IS
C-2F
C-1F
16
CH054SW
2C TK IS P LOW TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
82
CH052SW
2C TK IS P MID TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
81
CH050SW
2C TK IS P UPP TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
16
--
80
CH068
2C TK LIQ DM IBS N2 P
PIAHL
0.000
4.000
kPa
D3
0.2
1.5
BAD
C02
CB
IS
C-2F
C-1F
16
10
CH082
TIAL
-200
100
Deg_C
D0
-20
BAD
C02
CB
IS
C-2F
C-1F
16
13
15
CH083
TIAL
-200
100
Deg_C
D0
-20
BAD
C02
CB
IS
C-2F
C-1F
16
13
16
CH903SW
2C TK IS P MID WALL T SW
-200
100
Deg_C
D0
--
C02
CB
--
--
15
--
99
CH123
TIAL
-200
100
Deg_C
D0
-10
BAD
C02
CB
IS
C-2F
C-1F
16
10
15
CH122
TIAL
-200
100
Deg_C
D0
-10
BAD
C02
CB
IS
C-7F
C-6F
18
12
CH108SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
100
DPIC
4-4
IAS TAG
POINT DESCRIPTION
CODE
R_LOW
R_HIGH
ALARM DETECTION
LL
HH
FB
ST
ALM ALM
UT
ALM
INH GRP
ID
TM
TD
IS
I/O TB LOC
ASSOCIAT
IOM
EXT
DISPLAY
ADDRESS
REMARK
ND
IOM SLT
CH111SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
99
CH113SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
98
CH106SW
3C TK IBS N2 PRESS
0.000
3.000
kPa
D3
0.2
1.5
C02
CB
--
--
18
--
78
CH101
3C TK IBS/IS N2 DIFF P
DPIAHL
-4.000
3.000
kPa
D3
C02
CB
--
--
18
--
50
BY 8-PX-6C/6D (IAS
INTERNAL INDICATION)
CH085
3C TK IS N2 PRESS
PIAHL
0.000
4.000
kPa
D3
0.4
2.5
BAD
C02
CB
IS
C-7F
C-6F
18
CH102SW
3C TK IS AFT TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
97
CH097SW
3C TK IS BOTTOM TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
96
CH089SW
3C TK IS CEIL TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
95
CH099SW
3C TK IS FWD TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
94
CH086I
3C TK IS IBS/IS DP
0.000
4.000
kPa
D3
BAD
C02
CB
IS
C-7F
C-6F
18
CH095SW
3C TK IS P LOW TEMP SW
-200
200
100
Deg C
Deg_C
D0
-140
140
--
C02
CB
--
--
18
--
93
CH093SW
3C TK IS P MID TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
92
CH091SW
3C TK IS P UPP TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
91
CH110
3C TK LIQ DM IBS N2 P
PIAHL
0.000
4.000
kPa
D3
0.2
1.5
BAD
C02
CB
IS
C-7F
C-6F
18
CH124
TIAL
-200
100
Deg_C
D0
-20
BAD
C02
CB
IS
C-7F
C-6F
18
10
11
CH125
TIAL
-200
100
Deg_C
D0
-20
BAD
C02
CB
IS
C-7F
C-6F
18
10
12
CH905SW
3C TK IS P MID WALL T SW
-200
100
Deg_C
D0
--
C02
CB
--
--
18
--
90
CH166
TIAL
-200
100
Deg_C
D0
-10
BAD
C02
CB
IS
C-7F
C-6F
18
11
15
CH165
TIAL
-200
100
Deg_C
D0
-10
BAD
C02
CB
IS
C-2F
C-1F
16
12
16
CH148SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
89
CH151SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
88
CH153SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
87
CH164
4C TK IBS/IS N2 DIFF P
DPIAHL
-4.000
3.000
kPa
D3
C02
CB
--
--
18
--
40
BY 8-PX-7C/7D (IAS
INTERNAL INDICATION)
CH126
4C TK IS N2 PRESS
PIAHL
0.000
4.000
kPa
D3
0.4
2.5
BAD
C02
CB
IS
C-7F
C-6F
18
CH146SW
4C TK IBS N2 PRESS
0.000
3.000
kPa
D3
0.2
1.5
C02
CB
--
--
18
--
77
CH142SW
4C TK IS AFT TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
86
CH138SW
4C TK IS BOTTOM TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
85
PIC
4-5
IAS TAG
POINT DESCRIPTION
CODE
R_LOW
R_HIGH
ALARM DETECTION
LL
HH
FB
ST
ALM ALM
UT
ALM
INH GRP
ID
TM
TD
IS
I/O TB LOC
ASSOCIAT
IOM
EXT
DISPLAY
ADDRESS
REMARK
ND
IOM SLT
CH130SW
4C TK IS CEIL TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
84
CH140SW
4C TK IS FWD TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
83
CH136SW
4C TK IS P LOW TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
82
CH134SW
4C TK IS P MID TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
81
CH132SW
4C TK IS P UPP TEMP SW
-200
100
Deg_C
D0
-140
--
C02
CB
--
--
18
--
80
CH127I
4C TK IS IBS/IS DP
DPIC
0.000
4.000
kPa
D3
BAD
C02
CB
IS
C-7F
C-6F
18
CH150
4C TK LIQ DM IBS N2 P
PIAHL
0.000
4.000
kPa
D3
0.2
1.5
BAD
C02
CB
IS
C-7F
C-6F
18
10
CH167
TIAL
-200
100
Deg_C
D0
-20
BAD
C02
CB
IS
C-7F
C-6F
18
12
12
CH168
TIAL
-200
100
Deg_C
D0
-20
BAD
C02
CB
IS
C-7F
C-6F
18
12
13
CH907SW
4C TK IS P MID WALL T SW
-200
100
Deg_C
D0
--
C02
CB
--
--
18
--
79
CL029I
1C TK C P/P1 CURRENT
IND
0 00
0.00
75 00
75.00
D2
28
62
BAD
H:5L:10
C03
CC
C-2F
C
2F
C-2F
C
2F
16
CL031I
1C TK C P/P2 CURRENT
IND
0.00
75.00
D2
28
62
BAD
H:5L:10
C03
CC
C-7F
C-7F
18
CL037I
2C TK C P/P1 CURRENT
IND
0.00
75.00
D2
28
62
BAD
H:5L:10
C03
CC
C-2F
C-2F
16
CL040I
2C TK C P/P2 CURRENT
IND
0.00
75.00
D2
28
62
BAD
H:5L:10
C03
CC
C-7F
C-7F
18
CL043I
3C TK C P/P1 CURRENT
IND
0.00
75.00
D2
28
62
BAD
H:5L:10
C03
CC
C-2F
C-2F
16
11
CL046I
3C TK C P/P2 CURRENT
IND
0.00
75.00
D2
28
62
BAD
H:5L:10
C03
CC
C-7F
C-7F
18
CL050I
4C TK C P/P1 CURRENT
IND
0.00
75.00
D2
28
62
BAD
H:5L:10
C03
CC
C-2F
C-2F
16
13
CL055I
4C TK C P/P2 CURRENT
IND
0.00
75.00
D2
28
62
BAD
H:5L:10
C03
CC
C-7F
C-7F
18
CL034
IND
0.0
500.0
D1
76
320
BAD
H:5L:10
C03
CC
C-7F
C-7F
18
CMV009SW
-2.00
30.00
kPa
D2
19
20
C02
CB
16
--
84
CMV012
PIAH
-2.00
30.00
kPa
D2
11
14
BAD
C03
CC
IS
C-2F
C-1F
16
CS004I
1C TK S P/P CURRENT
IND
0.00
75.00
D2
15
60
BAD
H:0L:10
C03
CC
C-3F
C-3F
15
CS009I
2C TK S P/P CURRENT
IND
0.00
75.00
D2
15
60
BAD
H:0L:10
C03
CC
C-3F
C-3F
15
CS014I
3C TK S P/P CURRENT
IND
0.00
75.00
D2
15
60
BAD
H:0L:10
C03
CC
C-8F
C-8F
17
CS019I
4C TK S P/P CURRENT
IND
0.00
75.00
D2
15
60
BAD
H:0L:10
C03
CC
C-8F
C-8F
17
CT003
1C TK VAPOUR CONNECT T
TIAL
-200
100
Deg_C
D0
-20
BAD
C03
CC
IS
C-2F
C-1F
16
14
CT032
2C TK VAPOUR CONNECT T
TIAL
-200
100
Deg_C
D0
-20
BAD
C03
CC
IS
C-2F
C-1F
16
14
4-6
POINT DESCRIPTION
CODE
R_LOW
R_HIGH
ALARM DETECTION
LL
HH
FB
ST
ALM ALM
UT
ALM
INH GRP
ID
TM
TD
IS
I/O TB LOC
ASSOCIAT
IOM
EXT
DISPLAY
ADDRESS
REMARK
ND
IOM SLT
CT060
3C TK VAPOUR CONNECT T
TIAL
-200
100
Deg_C
D0
-20
BAD
C03
CC
IS
C-2F
C-1F
16
14
10
CT089
4C TK VAPOUR CONNECT T
TIAL
-200
100
Deg_C
D0
-20
BAD
C03
CC
IS
C-2F
C-1F
16
14
11
CT008PV
LIAHL
0.00
27.54
D2
25.587
BAD
C03
CC
--
--
16
--
61
CT004
PIAHL
-2.00
30.00
kPa
D2
20
22
BAD
C02
CB
IS
C-2F
C-1F
16
CT005
PIAL
-2.00
30.00
kPa
D2
(3)
BAD
C03
CC
IS
C-2F
C-1F
16
CT036PV
LIAHL
0.00
27.54
D2
25.491
BAD
C03
CC
--
--
16
--
51
CT033
PIAHL
-2.00
30.00
kPa
D2
20
22
BAD
C02
CB
IS
C-2F
C-1F
16
8-PX-20A,20B:DUAL
TRANSMITTER
CT034
PIAL
-2.00
30.00
kPa
D2
(3)
BAD
C03
CC
IS
C-2F
C-1F
16
CT064PV
LIAHL
0.00
27.54
D2
25.491
BAD
C03
CC
--
--
18
--
61
CT061
PIAHL
-2.00
30.00
kPa
D2
20
22
BAD
C02
CB
IS
C-7F
C-6F
18
11
8-PX-21A,21B:DUAL
TRANSMITTER
CT062
PIAL
-2
2.00
00
30 00
30.00
kPa
D2
(3)
BAD
C03
CC
IS
C-7F
C
7F
C-6F
C
6F
18
12
CT093PV
LIAHL
0.00
27.54
D2
25.491
BAD
C03
CC
--
--
18
--
51
CT090
PIAHL
-2.00
30.00
kPa
D2
20
22
BAD
C02
CB
IS
C-7F
C-6F
18
13
CT091
PIAL
-2.00
30.00
kPa
D2
(3)
BAD
C03
CC
IS
C-7F
C-6F
18
14
CV010I
TICAHL
-150
100
Deg_C
D0
-70
BAD
C03
CC
C-8F
C-8F
17
10
FV010I
TICAHL
-150
100
Deg_C
D0
-70
80
BAD
C03
CC
C-3F
C-3F
15
GHH009I
TICAHL
-100
150
Deg_C
D0
-10
90
BAD
C03
CC
C-3F
C-3F
15
12
GHL012I
TICAHL
-100
150
Deg_C
D0
-10
90
BAD
C03
CC
C-8F
C-8F
17
14
GW009
TIAL
-50
150
Deg_C
D0
80
BAD
C03
CC
C-3F
C-3F
15
11
13
GW056
GW HEATER 1 GW INLET P
PIAL
1000
kPa
D0
150
BAD
C03
CC
C-3F
C-3F
15
GW022SW
GW HEATER 1 OUT T
-50
150
Deg_C
D0
90
C03
CC
--
--
15
--
97
GW014
TIAL
-50
150
Deg_C
D0
10
BAD
C03
CC
C-3F
C-3F
15
11
14
GW011
TIAL
-50
150
Deg_C
D0
80
BAD
C03
CC
C-8F
C-8F
17
13
13
GW018
GW HEATER 2 GW INLET P
PIAL
1000
kPa
D0
150
BAD
C03
CC
C-8F
C-8F
17
10
GW027SW
GW HEATER 2 OUT T
-50
150
Deg_C
D0
90
C03
CC
--
--
17
--
98
GW017
TIAL
-50
150
Deg_C
D0
10
BAD
C03
CC
C-8F
C-8F
17
13
14
HD078
TIAH
100
Deg_C
D0
75
BAD
C03
CC
C-3F
C-3F
15
10
12
80
4-7
20
20
20
20
8-PX-19A,19B:DUAL
TRANSMITTER
TO ESDS PANEL(BY 8-PX19A,B)
LO alarm priority NoAction
8-PX-22A,22B:DUAL
TRANSMITTER
LO alarm priority NoAction
*:High Alarm Automatica
djusted.Refer to III-2-13 5
4-20MA
IAS TAG
POINT DESCRIPTION
CODE
R_LOW
R_HIGH
ALARM DETECTION
LL
HH
FB
ST
ALM ALM
UT
ALM
INH GRP
ID
TM
TD
IS
I/O TB LOC
ASSOCIAT
IOM
EXT
DISPLAY
ADDRESS
REMARK
ND
IOM SLT
HD056
TIAHL
100
Deg_C
D0
15
70
BAD
C03
CC
C-3F
C-3F
15
10
HD045
TIAH
-200
200
Deg_C
D0
90
BAD
C03
CC
C-3F
C-3F
15
10
HD062
PIAL
0.0
600.0
kPa
D1
100
BAD
C03
CC
C-3F
C-3F
15
10
10
HD063
TIAHL
100
Deg_C
D0
20
55
BAD
C03
CC
C-3F
C-3F
15
10
11
HD061
DPIAH
0.0
500.0
kPa
D1
250
BAD
C03
CC
C-3F
C-3F
15
10
HD004
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-3F
C-3F
15
12
HD005
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-3F
C-3F
15
12
HD006
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-3F
C-3F
15
12
HD053
VIAH
0.0
100.0
um
D1
50
BAD
C03
CC
C-3F
C-3F
15
10
HD079
TIAH
100
Deg_C
D0
75
BAD
C03
CC
C-8F
C-8F
17
11
12
HD057
TIAHL
100
Deg C
Deg_C
D0
15
70
BAD
C03
CC
C-8F
C
8F
C-8F
C
8F
17
11
HD047
TIAH
-200
200
Deg_C
D0
90
BAD
C03
CC
C-8F
C-8F
17
11
HD066
PIAL
0.0
600.0
kPa
D1
100
BAD
C03
CC
C-8F
C-8F
17
11
10
HD067
TIAHL
100
Deg_C
D0
20
55
BAD
C03
CC
C-8F
C-8F
17
11
11
HD065
DPIAH
0.0
500.0
kPa
D1
250
BAD
C03
CC
C-8F
C-8F
17
11
HD011
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-8F
C-8F
17
14
HD012
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-8F
C-8F
17
14
HD013
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-8F
C-8F
17
14
HD055
VIAH
0.0
100.0
um
D1
50
BAD
C03
CC
C-8F
C-8F
17
11
IG005
TIAH
180
Deg_C
D0
130
140
BAD
C03
CC
C-2F
C-2F
16
4-20MA
IG006
TIAH
180
Deg_C
D0
130
140
BAD
C03
CC
C-2F
C-2F
16
4-20MA
IG007
TIAH
180
Deg_C
D0
130
140
BAD
C03
CC
C-2F
C-2F
16
4-20MA
IG011
TIAH
180
Deg_C
D0
130
140
BAD
C03
CC
C-7F
C-7F
18
4-20MA
IG012
TIAH
180
Deg_C
D0
130
140
BAD
C03
CC
C-7F
C-7F
18
10
4-20MA
IG013
TIAH
180
Deg_C
D0
130
140
BAD
C03
CC
C-7F
C-7F
18
11
4-20MA
IG050
TIAH
180
Deg_C
D0
130
140
BAD
C03
CC
C-7F
C-7F
18
15
4-20MA
IG048
TIAH
180
Deg_C
D0
130
140
BAD
C03
CC
C-7F
C-7F
18
13
4-20MA
4-8
4-20MA
4-20MA
IAS TAG
POINT DESCRIPTION
CODE
R_LOW
R_HIGH
ALARM DETECTION
LL
HH
FB
ST
ALM ALM
UT
ALM
INH GRP
ID
TM
TD
IS
ASSOCIAT
EXT
DISPLAY
ADDRESS
C-7F
C-7F
18
14
ND
REMARK
IOM SLT
IG049
TIAH
180
Deg_C
D0
130
140
BAD
C03
CC
LC044PV
IND
0.0
100.0
D1
95
C03
CC
17
--
106
LC045PV
IND
0.0
100.0
D1
95
C03
CC
15
--
22
LC046PV
IND
0.0
100.0
D1
95
C03
CC
17
--
107
LC047PV
1 SWBT S VOLUME
IND
0.0
100.0
D1
95
C03
CC
17
--
108
LC048PV
1 SWBT P VOLUME
IND
0.0
100.0
D1
95
C03
CC
15
--
25
LC049PV
2 SWBT S VOLUME
IND
0.0
100.0
D1
95
C03
CC
17
--
109
LC050PV
2 SWBT P VOLUME
IND
0.0
100.0
D1
95
C03
CC
15
--
27
LC051PV
3 SWBT S VOLUME
IND
0.0
100.0
D1
95
C03
CC
17
--
110
LC052PV
3 SWBT P VOLUME
IND
0.0
100.0
D1
95
C03
CC
15
--
29
LC053PV
4 SWBT S VOLUME
IND
0 0
0.0
100 0
100.0
D1
95
C03
CC
17
--
111
LC054PV
4 SWBT P VOLUME
IND
0.0
100.0
D1
95
C03
CC
15
--
31
LD082
TIAH
200
Deg_C
D0
75
BAD
C03
CC
C-2F
C-2F
16
13
LD061
TIAHL
100
Deg_C
D0
15
70
BAD
C03
CC
C-2F
C-2F
16
LD046
TIAH
-200
200
Deg_C
D0
90
BAD
C03
CC
C-2F
C-2F
16
LD069
PIAL
0.0
250.0
kPa
D1
120
BAD
C03
CC
C-2F
C-2F
16
10
LD070
TIAHL
100
Deg_C
D0
20
55
BAD
C03
CC
C-2F
C-2F
16
11
LD077
DPIAH
0.0
250.0
kPa
D1
250
BAD
C03
CC
C-2F
C-2F
16
12
LD052
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-2F
C-2F
16
14
13
LD053
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-2F
C-2F
16
14
14
LD054
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-2F
C-2F
16
14
15
LD058
VIAH
0.0
100.0
um
D1
50
BAD
C03
CC
C-2F
C-2F
16
LD025
TIAH
-200
200
Deg_C
D0
-40
BAD
C03
CC
C-2F
C-2F
16
4-20MA
LD083
TIAH
200
Deg_C
D0
75
BAD
C03
CC
C-7F
C-7F
18
13
4-20MA
LD063
TIAHL
100
Deg_C
D0
15
70
BAD
C03
CC
C-7F
C-7F
18
LD048
TIAH
-200
200
Deg_C
D0
90
BAD
C03
CC
C-7F
C-7F
18
LD074
PIAL
0.0
250.0
kPa
D1
120
BAD
C03
CC
C-7F
C-7F
18
10
4-9
I/O TB LOC
IOM
4-20MA
4-20MA
POINT DESCRIPTION
CODE
R_LOW
R_HIGH
ALARM DETECTION
LL
HH
FB
ST
ALM ALM
UT
ALM
INH GRP
ID
TM
TD
IS
I/O TB LOC
ASSOCIAT
IOM
EXT
DISPLAY
ADDRESS
ND
REMARK
IOM SLT
LD075
TIAHL
100
Deg_C
D0
20
55
BAD
C03
CC
C-7F
C-7F
18
11
LD079
DPIAH
0.0
250.0
kPa
D1
250
BAD
C03
CC
C-7F
C-7F
18
12
LD055
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-7F
C-7F
18
13
10
LD056
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-7F
C-7F
18
13
11
LD057
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-7F
C-7F
18
13
12
LD059
VIAH
0.0
100.0
um
D1
50
BAD
C03
CC
C-7F
C-7F
18
LD034
TIAH
-200
200
Deg_C
D0
-40
BAD
C03
CC
C-7F
C-7F
18
MDO008
LIAHL
0.100
5.040
D3
0.45
4.69
BAD
C03
CC
14
--
64
NG020PV
1 N2 GEN DISCH/RECEIV P
1600
kPa
D0
300
650
C03
CC
16
--
71
NG917PV
2 N2 GEN DISCH/RECEIV P
1600
kPa
D0
300
650
C03
CC
17
--
71
NG038
PIAL
0 0
0.0
800 0
800.0
kPa
D1
190
BAD
C03
CC
C-8F
C
8F
C-8F
C
8F
17
12
RF010
TIAHL
-50
50
Deg_C
D0
-23
-15
BAD
C03
CC
SM-1F
SM-1F
14
RF008
TIAHL
-50
50
Deg_C
D0
-23
-15
BAD
120
C03
CC
SM-1F
SM-1F
14
RF006
TIAHL
-50
50
Deg_C
D0
-23
-15
BAD
120
C03
CC
SM-1F
SM-1F
14
10
RF009
TIAL
-50
50
Deg_C
D0
BAD
C03
CC
SM-1F
SM-1F
14
12
WS003
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-8F
C-8F
17
14
14
WS005
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-8F
C-8F
17
14
15
WS004
TIAH
200
Deg_C
D0
130
BAD
C03
CC
C-8F
C-8F
17
14
16
4 - 10
20
4-20MA
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
Liquid Crossover
(650A)
(500A)
CL-003
CS-002(80A)
ESD
CL-004
(400A)
(400A)
ESD
CL-008
ESD
CG-004
CG-002
(400A)
(400A)
(300A)
CG-700
CG-701
(400A)
CG-100
CS-100
(50A)
SP-100
CG-101
CS-108
(40A)
CL-110
(300A)
(300A)
(300A)
CR-104
(PORT)
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(600A)
(50A)
CR-105
(STBD)
(80A)
CS-101
CS-102
CL-101
CL-102
CL-103
CL-104
S
Spray Pump
(50A)
(65A)
(400A)
(400A)
(400A)
CL-206
(600A)
Sprayers
CL-205
Cargo Pump
CS-104
FL-100
SA-156 SA-155
SA-154 SA-153
(8A)
SA-152 SA-151
(8A)
(8A)
CS-207
SP-200
CG-201
(300A)
(50A)
(50A)
CS-208
(40A)
CL-200
CG-200
CS-200
CR-205
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
(PORT)
4 - 11
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
(50A)
(300A)
Sprayers
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
SP-700
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
CS-701
CS-700
CL-700
(300A)
Spray Main
(450A)
(400A)
CG-301
CS-307
(50A)
(50A)
SP-300
CG-702
(100A)
(50A)
(65A)
(400A)
(400A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
(600A)
CG-703
ESD
(400A)
(8A)
(40A)
CS-308
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(450A)
CG-300
CS-300
(300A)
(300A)
Liquid Main
CL-305
CL-306
Flow Meter
(650A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(400A)
CS-303
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
(600A)
(PORT)
S
Spray Pump
Vapour Main
(STBD)
(80A)
Cargo Pump
Control Valve
(700A)
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
(PORT)
(50A)
(8A)
SA-354 SA-353
SA-352 SA-351
(8A)
(8A)
SP-400
CG-401
CS-407
CR-404
(50A)
(50A)
CS-408
(40A)
CL-400
(300A)
(300A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
(300A)
Needle Valve
To Cofferdam
No.3 LNG
Vent Mast
(400A)
CR-405
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(750A)
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
(650A)
CS-600
(80A)
(700A)
(65A)
(400A)
(300A)
(450A)
Y-type Strainer
Gas Main
(300A)
CL-600
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
Ballast Line
Strip/Spray Line
(400A)
(50A)
(50A)
SP-701
(80A)
CS-008(80A)
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
ESD
(40A)
(500A)
CS-504
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
CG-525 CG-521
SP-602
(80A)
Liquid Crossover
CG-503
(450A)
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
Relief valve set pressure is equal to the design pressure of the system.
The relief valves discharge vapour to the cargo tank.
Liquid dome connections:
-
All major valves such as the midships port and starboard manifold valves (also
called ESD Manifold Valves) and individual tank loading and discharge valves,
are remotely power operated from the IAS, so that all normal cargo operations
can be carried out from the Central Control Room (CCR).
2. Stripping/Spray Lines
When an ESD is activated the manifold valves are closed, discontinuing loading
or unloading operations.
The Spray Header is led between No. 1 and No. 4 cargo tank and is connected
with crossovers at the shore connection.
A non-return valve is fitted at the discharge flange of each cargo pump. A hole is
drilled in the valve disc to allow the tank discharge lines to drain down and be
gas freed. Non-return valves are also fitted at the discharge flange of the
compressors. The stripping/spray and emergency cargo pump discharge lines
have non-return valves located directly after the hydraulically operated discharge
valves.
Fluid velocity in the pipe lines in normal service shall be generally applied as
below.
Liquid line
7 m/s
40 m/s
45 m/s
One (1) spray connection is branched off the spray header and led to each cargo
tank.
The system is used for cooling down the cargo tanks before loading as necessary.
At initial cooling down, the liquid is fed from shore to the spray header through
the liquid crossover. The spray header is connected to two (2) groups of spray
nozzles in each cargo tank.
Liquid nitrogen is supplied to the LNG vaporiser through the spray lines from
the cargo manifold.
The liquid supply to the spray header is remotely controlled by throttling the
valve of the spray return line. The spray nozzles are located along the top edge of
the top chamfer of the tanks.
1. Liquid Lines
One (1) liquid header is led between No. 1 and No. 4 cargo tanks on thetrunk
deck and is connected with the crossovers.
One (1) liquid connection is branched off the liquid header and led to each cargo
tank.
The nozzles in each cargo tank are installed depending on the tank size. The
capacity of the spray nozzles is decided based on the initial cooling down of the
cargo tank and cooling down before loading at the end of the ballast voyage.
Y-type strainer is provided in the spray lines to the nozzles in the tank.
The following valves are provided near each liquid dome:
In each cargo tank, two (2) cargo discharge lines with cargo pumps at the bottom,
and one (1) cargo filling line extended to the bottom are provided. In addition, a
well is provided for lowering down the emergency cargo pump. These lines shall
penetrate the liquid dome and are connected to the cargo liquid branch for each
tank.
4 - 12
A hydraulic remotely operated globe valve and lift check valve for the
discharge line of each stripping / spray pump.
hydraulic remotely operated globe valve for each spray nozzle inlet line.
-
3. Vapour Lines
The water curtain pipe shall be fitted with a drain valve at the lowest point.
One (1) vapour header is led between No.1 and No.4 cargo tanks, used for gas
handling operations such as loading and discharging of cargo, warm up and cool
down.
Sea water for the sea water curtain is supplied from the fire and wash deck main
line near the loading station.
This header is led to each cargo tank via a vapour branch line, provided with a
manually operated butterfly valve and a spectacle flange, and connected to the
vapour crossover which leads to the shore connection.
One (1) vapour return line is provided between the H/D compressor discharge
and the vapour crossover at the shore connections for discharging cargo vapour
during loading, warming up, cooling down and inert gas purging operations.
Pressure control devices are provided to vent excessive boil-off vapour to the
atmosphere through No. 1 vent mast.
The pressure control of vapour to shore is provided by automatic remote control
from the IAS
4. Gas Pipe Connection
-
One (1) emergency vent header is led between No.1 and No.4 cargo tanks, used
for tank gas freeing operations.
This header shall be led to near each vapour branch line and connected to the
vapour branch line using an expansion bellows type spool piece which is
provided separately. The Emergency Vent line is not insulated.
5. Cargo Manifold
Loading stations are provided port and starboard on a platform above the main
deck as shown on the G.A.
The cargo manifold consisting of four (4) liquid lines and one (1) vapour line is
provided port and starboard on platforms above the main deck and is in
compliance with OCIMF standards at the loading and discharging ports.
During transportation of LNG at sea, gas vapour is produced due to the transfer
of heat from the outside sea and air through the cargo tank insulation; energy is
also absorbed from the cargo motion due to the vessels movement. Under
normal conditions the boil-off gas is used as fuel in the ships boilers.
The gas vapour is taken from the vapour header into the LD Compressors. It then
passes through the LD gas heater before going to the ships boilers where it is
burnt as fuel. The fuel gas pipe to the engine room is 300A and is fitted with the
fuel gas master valve (CG613) and a flow meter.
Sea water hose connections are provided for de-icing the cargo manifolds.
8. Inerting/ Aeration Lines
All remotely operated valves as well as emergency shutdown valves are operable
from the IAS and valves are capable of manual operation locally at the solenoid
rack and by hydraulic hand pump in general.
The system supplies inert gas or dry air to the cargo tanks and pipelines for
inerting and drying during refit periods.
The inert gas or dry air is supplied from the inert gas generator situated in the
engine room.
The line is connected to the gas header and the liquid header by means of Blind
Flange Valve and spool piece.
By selective use of the spool pieces it is possible to inert/aerate all or any single
cargo tank.
The spacing between liquid and vapour lines is in accordance with loading and
discharging terminals arm locations and the distance between the ship manifold
flanges and the ships side is 3.5m.
4 - 13
600
24
809.4
650
26
186.8
700
28
203.4
750
30
187.9
Inch
15
20.0
20
28.0
25
32.0
32
1+
42.6
40
1+
55.5
50
90.5
65
2+
108.9
80
133.3
100
99.1
125
151.4
150
179.8
200
229.3
250
10
258.6
300
12
307.2
350
14
413.4
400
16
486.3
450
18
625.3
500
20
609.7
550
22
698.2
4 - 14
inhibit order is set from the wheelhouse or telegraph astern signal. In this mode
manual operation of the vent mast valve is not available. The tank protection
vent mode will override the manual vent inhibit and open the valve under high
vapour header pressure.
This function has first priority.
pressure relief
valve open
25
kPa g
24
23
In the tank protection vent mode, the vent control valve CG701 will open to full
flow (100% capacity) when a pressure on the vapour header exceeds the set
value 23 kPa. The valve will stay in this mode until the pressure registered on the
vapour header drops below 21 kPa at which point the valve will close. In the
tank protection vent mode, the manual vent is inhibited and vent control at vent
mode is disabled and manual operation of the vent valve is not available.
Vapour venting valve is locked in auto mode.
This function has second priority.
PAHH
22
vent valve close
21
PAH
20
PAHH
Trip vaporizer
PAH
19
steam dump
2. Under Pressurizing
To protect the cargo tanks from being under pressurized the LD compressor logic
has two (2) tank pressure protection controllers; one for Ballast mode and one for
Laden mode.
The controller for the LD compressor shall limit the compressor capacity when
the vapour header pressure falls below a set pressure of 2 kPa.
When the vapour header pressure falls to 3.0 kPa, a FO Auto Backup signal will
be sent to the burner management system (BMS) to start a FO burner. The FO
Auto Backup signal will be reset when the pressure increases to 3.5kPa..
PT
Vent Inhibit
Tank Protection vent Control.
Vent Control at Vent mode.
Manual Operation.
15
Vent
Control
H Valve
7 ~ 19 kPa g
(Operation Range)
CG701
At Very Low cargo header pressure (2.0 kPa) a FO Boost Up signal will be sent
to the boiler management system and the LD compressor stop sequence is
initiated.
The Ballast and Laden mode controllers will limit the available BOG flow to
the boilers when the cargo header pressure falls below a set pressure.
Vent
Mast
OPEN : 23 kPa
CLOSED : 21 kPa
5.5
5
Pumps start
interlock
4
3.5
3
PAL
4. Manual Operation
When any of the above automatic controls are not activated, the IAS doesnt
manipulate the valve position controller and the vent valve can be manipulated
by the operator.
When the vent control valve is under automatic control of the IAS (under the
conditions 1, 2, 3 above), point mode of the valve position controller is fixed at
P-AUTO mode, and manual operation of the point is not available.
4 - 15
0.3
0
Vacuum relief
valve open
Tank Pressure
PAL
PALL - FO Boost up
- Close Gas
Master valve
- Trip LD compressor
PAVL - ESD
-1
Vapour header
pressure
Ballast mode
press controller
Set
Abs
Laden mode
press controller
Set
Pressure Sensor
Ballast
Gauge
Ballast
Absolute
Laden
Gauge
Laden
Effect
Comments
Gauge pressure
Effect
Comments
Gauge
pressure
Absolute
pressure
4 - 16
324mm
DISCHARGE
TERMINAL BOX
CABLE
STATOR COIL
SHAFT
ROTOR CORE
STATOR CORE
600mm
2,270mm
1,780mm
SUCTION STRAINER
INDUCER
810mm
SUCTION
TANK BOTTOM
4 - 17
During the course of discharge, changes in flow rate and tank levels alter these
readings. Thus the discharge valve have to be readjusted accordingly.
ESDS signifies that all cargo plant is shut down in addition to the pump(s) on the
tank(s) in question.
Under normal conditions it should be possible to maintain the full discharge rate
until the tank level approaches 1.98 m, at which time the pump will start to
cavitate and lose suction as indicated by fluctuations in the discharge pressure
and ammeter readings.
NOTE
An insulation test of all pumps is to be carried out after leaving the loading
port to establish that all pumps are operational and to allow time for the
installation of the emergency cargo pump should it be necessary. Disconnect
the earth line of insulation monitor before carrying out this test.
The discharge valves should be throttled to stabilize conditions and one pump
stopped if necessary. The remaining pump should be progressively throttled to
maintain suction and prevent the operation of the motor low current trip.
By trimming the vessel one (1) meter or more by the stern, it should be possible
to reduce the amount of liquid remaining in the tanks to a minimum, if requested.
NOTE
The pump should not be started or operated against closed discharge valve
due to potential damage which may result to insufficient cooling and
lubrication for motor and bearing and excessive vibration levels associated
with zero flow conditions.
The cargo pumps may be run in closed circuit on their own tanks by opening the
loading valve. This may be required if the discharge is temporarily halted when
the tanks are at low level, thereby avoiding the problems of restarting with low
level and low discharge pressure.
The pump shall be tested before arrival at discharge port on calm sea condition,
and during loading when the tank level is 4~5 m subject to terminals acceptance.
The cargo pumps will be automatically stopped should any of the following
occur:
1) Cargo tank pressure low low (0.2 kPa)
Motor
Type:
Rated output:
Synchronous speed:
Electric power source:
Rated current:
Starting current:
Insulation class:
Min. starting voltage:
Min. resistance value for starting:
The cargo tanks are fitted with two main cargo pumps. These pumps are vertical
single-stage centrifugal pumps with one inducer stage and driven by electric
motors. Each pump is rated to discharge 1,800m3/h at 155m head of LNG.
For optimum discharge results, bulk discharge will be carried out with 8 pumps
running in parallel.
The pump discharge valves will be throttled to ensure optimum performance
indicated by the pump performance graph.
4 - 18
100
90
140
120
100
50
80
40
0.50)
=
(
P
60
30
0.47)
P ( =
40
20
20
10
150
100
180
10
160
200
200
Slip S (%)
Current I (A)
NPSHR Hs (m)
Pump Down Hd (m)
80
PF
80
70
60
60
40
500
20
400
300
200
Hs
Hd
1
0
0
500
1000
1500
2000
I
S
2500
20
40
60
80
100
120
140
Output (%)
Capacity Q (m3/h)
4 - 19
CAUTION
It is necessary to cool down the each part of pump and motor sufficiently
before pump operation. In case the cooling down is too fast, the each part will
shrink irregularly, resulting in damage of the parts and ball bearing due to the
partial excessive heat strength. (In case of pouring the liquid directly to the
cargo tank, the speed of cooling down must be less than 50C/h.) When pump
is cooled down more than three hours, since the shrinking amount of each parts
is balanced. No excessive heat strength is occurred.
4) The cargo pump discharge valve should have a slight opening.
In order to reduce the water hammer at start-up the discharge valve opening
should be set at 18 ~ 25%. However, this valve opening should be modified
as required to reflect actual operating conditions in order to make water
hammer as small as possible.
Start
1) Confirm that all the preparatory conditions described above are met.
2) Depress the start button to start the motor.
- Cavitation operation must not be carried out.
- The pump must not be operated under an idle condition (normal rotation,
opposite rotation) during purging, gas switching or the like.
- The pump must not be operated with the discharge valve fully shut.
CAUTION
If the discharge pressure dose not rise to the required value (0.6MPa) or greater
10 seconds after the start in direct on line starting, stop the motor immediately
and examine possible causes.
The excessively low discharge pressure means that the pump may be rotating in
the reverse direction. In that case, the two phases of the motor power cable
should be replaced with each other.
3) Starting the motor should be carried out only one time whenever possible.
In the case of unavoidable restart, the frequency of starting should be,
according to the liquid level in the tank, as follows:
4 - 20
- Each time the motor is started, the temperature of the motor rises due to
generation of heat. If the temperature of the motor is high at the time of
starting, gas occurs in the motor, so that there is a fear of the bearing being
damaged or the coil being burnt. Therefore, the starting frequency of the
motor should be minimum whenever possible. The temperature of the
motor which has been subjected to continuous running and restrained
running (impossible start) is high, it is necessary to set the cooling time of
the motor until the next starting as described above.
Running
1) It is desirable to operate the pump in a close condition to the rated flow.
When discharge pressure and electric current are stable after starting,
therefore, the discharge valve should be opened little by little immediately,
and unloading operation should be carried out as close to the rated discharge
flow as possible.
720 m/h
1800 m/h
2160 m/h
NOTE
The bearing may be damaged by cavitation, vibration, excessive thrust, or the
like, at the excessive large range (higher than max. flow rate) and at the
excessive small range (lower than min. flow rate).
Therefore, long running at any of other ranges than the above flow range must
be avoided. At the time of starting, carry out discharge valve slight opening
operations as short as possible, and after the completion of starting (stable
discharge pressure and current), open the discharge valve immediately and
increase the discharge amount to approximately rated flow.
CAUTION
If the motor stops during pump running, cargo liquid in the discharge piping
drops, so that the impeller rotates in an opposite direction, serving as a water
wheel, and it takes several minutes to complete stopping.
If the motor is restarted during the opposite rotation, shock is given to the
rotating element, and then there is a fear of causing some damages such as a
bending shaft.
5) When the residual liquid in the cargo tank becomes extremely low even if
discharge valve operation as described above is repeated, it becomes
impossible to prevent large decrease of discharge pressure due to cavitations
or gas inclusion. In such a case, unloading by the pump is impossible, so the
pump should be stopped by hand immediately. When the liquid level in the
tank has reached a prescribed minimum level, the pump should be also
stopped by hand.
- Be careful that the discharge valve may be fully closed immediately before
the completion of stripping.
- If the pump is operated with its discharge valve almost fully closed, the
liquid in the pump and motor may be heated and gasified. This may result
in seizure of bearings, rotating and stationary parts, and damage to the
motor coil or some other accidents. It may generate excessive thrust,
which may also lead to damage to the bearings. It should be noted that
these accidents may not occur during the operation with the discharge
valve fully closed immediately, however they become potential causes for
accidents during subsequent operation.
To prevent such states, the operator shall close down the discharge valve
gradually to decrease discharge flow until the discharge pressure and
electric current have become stable or have increased. Each time the
discharge pressure and electric current fluctuate or lower, repeat throttling
the discharge valve.
Stop
Stripping Pump
Em,cy Stop Button
6) Do not operate the pump with the discharge valve fully closed.
3) When the liquid level in the cargo tank has become considerably low, the
operator should operate the pump while monitoring the discharge pressure
and electric current. When the discharge pressure or electric current
becomes unstable and begins to fluctuate or lower, it means that cavitation
has generated or the pump is being operated in a gas inclusion condition.
2) Auto stop
If current value becomes less than 32A, low-current trip stops the
motor automatically. (Time setting point: 5 sec)
If current value becomes less than 66A, the motor stops
automatically by high current trip. (Time setting point: 0 sec)
CAUTION
Automatic stop device is an emergency trip device to protect the pump and
motor from accidents. Therefore, at the time of the completion of unloading
work, the device should be set at ordinary stop (manual stop). Do not set it
at auto stop due to low current trip.
Measures after stop
1) Ordinary stop
Depress Stop button with the discharge valve slightly opened or closed
condition to stop the motor. When closing the discharge valve, stop the
motor immediately.
4 - 21
A cargo pumps order will activate a request to the Power Management System
(PMS) for available electric power. If the IAS receives power available signal
from the PMS, the power available will be indicated on the IAS VDU.
The cargo pump will be automatically stopped by pre-defined stop level. Also, it
can be manually stopped at any time.
To avoid damage of the pump and the tank, the pump will be stopped if any of
the following trip causes are activated. Trip causes are as follows;
Before confirm the power available on the VDU, the operator should open the
discharge valve more than 5 % for minimum continuous flow. Also an operator
should open the discharge valve full open to re-circulate LNG to cargo tank
before pump start because it is necessary to take the time to stable the pump load
after a pump start. The manual Cargo pump start procedure is summarized as
follows.
Cargo
Cargo P/P
P/P Start
Start
Disch. V/V
>5% ?
Cause
The IAS has function for the operator to easily control the pump load with this
calculated by manipulating the pumps discharge valve.1PID with gap controller
is applied for each pumps load control and this controllers output charges the
position controllers set-point so that manipulates pump discharge valve at the
condition that control mode of position controller is in CAS mode.
Location
TPS Activated
ESDS
ESD Activated
ESDS
CSBD
CSBD
CSBD
Emergency Stop
RPB
Low Level
IAS
YES
Remote
Selected?
NO
(MCC)
Power
Available?
SET BY
AUTO SEQ
SET BY
OPERATOR
YES
AUTO
P-AUTO
NO
(PMS)
SET BY
AUTO SEQ
P-AUTO
PID + GAP
(REVERSE)
SP
POSPROP
OP
CAS
SP
PV
YES
Ready To
Start?
SET BY
OPERATOR
NO
OPEN
REQUST
(MCC)
CLOSE
REQUEST
PV 100
R
PV(A)
VALVE POSITION
Load (%) =
Current Ampere
X 100
Rated Ampere
4 - 22
Discharge
32
169
+3.2
0
230
Stator Core
Rotor Core
45
210
403
610
823
Terminal Box
320
90
+5
0
Suction
Tank Bottom
4 - 23
1. General Description
For the stripping, the stripping/spray pump should be started early enough
to avoid possible starting problems due to very low liquid level (0.22m).
Pump
Manufacturer:
Pump model:
Capacity rated flow:
Total head:
Design temperature:
Cool down time:
Design pressure:
Liquid spec. gravity:
Shaft power :
Efficiency:
Direction of rotating:
Discharge flange:
Minimum starting level:
Minimum restarting level:
Pump down level:
At rated flow:
At minimum flow:
Minimum flow:
0.37 m
0.23 m
20 m3/h
Motor
Type:
Rated output:
Synchronous speed:
Electric power source:
Rated current:
Starting current:
Insulation class:
Min. starting voltage:
Min. resistance value for starting:
A stripping/spray pump is installed in each cargo tank for cooling and forced
vaporization of LNG. It is rated at 50 m3/h at 145 m head of LNG.
The pumps are started and stopped from the CCR via the IAS. In an emergency
all pumps will be stopped by activation of the Emergency Shut Down System
trip.
4 - 24
90
80
180
20
18
16
50
10
50
40
40
0.50)
P ( =
30
30
0.47)
P ( =
20
20
10
10
40
1.5
1.0
Hs
0.5
Hd
0
10
20
30
40
70
60
10
PF
12
120
80
60
60
20
90
14
140
20
100
70
160
80
100
Slip S (%)
Current I (A)
NPSHR Hs (m)
Pump Down Hd (m)
50
60
20
40
60
80
100
120
140
Output (%)
Capacity Q (m3/h)
4 - 25
4 - 26
20 m/h
50 m/h
60 m/h
CAUTION
The bearing may be damaged by cavitation, vibration, excessive thrust, or the
like, at the excessive large range (higher than max. flow rate) and at the
excessive small range (lower than min. flow rate).
Therefore, long running at any of other ranges than the above flow range must
be avoided. At the time of starting, carry out discharge valve slight opening
operations as short as possible, and after the completion of starting (stable
discharge pressure and current), open the discharge valve immediately and
increase the discharge amount to approximately rated flow.
3) When the liquid level in the cargo tank has become considerably low, the
operator should operate the pump while monitoring the discharge pressure
and electric current. When the discharge pressure or electric current
becomes unstable and begins to fluctuate or lower, it means that cavitation
has generated or the pump is being operated in a gas inclusion condition. To
It should be noted that these accidents may not occur during the operation
with the discharge valve fully closed immediately, however they become
potential causes for accidents during subsequent operation.
After confirming the ready to start in the IAS, an operator should open the
discharge valve 5% for minimum continuous flow and reset of start blocking.
Also an operator should open the recirculation valve (strip/spray line pressure
control valve) full open the re-circulate LNG to cargo tank before pump start
because it is necessary to take the time to stabilize the pump load after a pump
start.
Stop
1) Ordinary stop
Depress Stop button with the discharge valve slightly opened or closed
condition to stop the motor. When closing the discharge valve, stop the
motor immediately.
2) Auto stop
Strip/Spray
Strip/Spray P/P
P/P Start
Start
Disch. V/V
>5% ?
YES
Remote
Selected?
NO
(MCC)
(MCC)
YES
Ready To
Start?
NO
Start circuit of the CSBD interior will be released by a start-blocking signal from
the IAS. It is generated from the IAS to not permit starting without the discharge
valve open.
The start blocking functions for each pump in the cargo tank interior are
prepared in the IAS to prevent the strip/spray pump vibration and pressure surge
in the discharge line.
6) Do not operate the pump with the discharge valve fully closed.
- Be careful that the discharge valve may be fully closed immediately before
the completion of stripping.
If the discharge valve position of each pump is less than 5%, the related pump
cannot be started by the start blocking function in IAS.
- If the pump is operated with its discharge valve almost fully closed, the
liquid in the pump and motor may be heated and gasified. This may result
in seizure of bearings, rotating and stationary parts, and damage to the
motor coil or some other accidents. It may generate excessive thrust,
4 - 27
Location
TPS Activated
ESDS
ESD Activated
ESDS
CSBD
CSBD
CSBD
Emergency Stop
RPB
Low Level
IAS
So, it is possible for the IAS to keep or change the pump load by manipulating
the discharge valve according to pump load setting. It means that at cascade
mode, control loop is applied between discharge valve controller and pump load
controller.
1 PID with gap controller is applied for each pumps load control and the
controllers output is pushed to position controllers set-point that controls pump
discharge valve at the condition that control mode of position controller is in
CAS mode.
If motor load is higher than the set point value, the output of load controller
deceases to reduce motor load and consequently deceases discharge valve
position.
The motor load is converted to percentage value from the current of each pump.
The calculating formula is as flow;
Load (%) =
SET BY
AUTO SEQ
P-AUTO
SP
POSPROP
OP
CAS
SP
PV
OPEN
REQUST
CLOSE
REQUEST
PV 100
R
PV(A)
After confirming that pump discharge valve opens at set position, open the strip
& spray header pressure control valve to 100 %. After header pressure control
valve position 100 %, start the pump.
After pump star, input initial set point value to the pumps load controller. Hen
change the pump discharge valves position controller to CAS mode from
AUTO mode and change pump load controllers control mode to AUTO mode.
Then pumps discharge valve will be regulated according to the pumps load.
After the preceding work has finished, input the set point value to the header
pressure controller and change the return line valve controllers control mode to
CAS mode from AUTO mode and change the header pressure controllers
control mode to AUTO. Then, the return line valve will be automatically
manipulated to keep the pressure that the operator entered as set point.
Current Ampere
X 100
Rated Ampere
AUTO
P-AUTO
PID + GAP
(REVERSE)
Change the position controllers mode to AUTO and input the set point valve to
manipulate the valve to the set point position. For the details, please refer to the
Valve position control
SET BY
OPERATOR
SET BY
AUTO SEQ
SET BY
OPERATOR
Is case of achieving the cargo tank cool down work or making necessary gas
with the forcing vaporiser or LNG vaporiser, strip/spray line header pressure
should be kept at the constant pressure.
A throttling valve that is installed on the return line will be controlled according
to the change of header pressure the keep the strip/spray line header pressure
stable. If header pressure is increased more than set point, it required to close
throttling valve, and to open throttling valve in opposite case.
VALVE POSITION
PUMP
CURRENT
P/P Disch.V/V
When LNG supply becomes to low, strip/spray header pressure does not
approximate in the set point. In this case, operator must open the pump discharge
valve to increase the pumps load.
If operator likes to start the strip pump by the sequence, refer to the Strip Pump
Start/Stop Auto Sequence Control. Here, the method for operator to start pump
will be explained by manual.
4 - 28
Terminal
Header Unit
Lifting Eye
1436.1
Column Cover
Column
Working Level
Hang Plate
2747
Guide Roller
Earth Cable
Support Rope
375
171
1600
(Min. Liquid Level for Initial Start Up)
850
(Min. Liquid Level for Restart)
Suction
Foot Valve
520
120+35
1900
Power Cable
1694
Approx. 29750
4020 x 6 Sets
Tank Bottom
4 - 29
1. General Description
Pump
Manufacturer:
Pump model:
Capacity rated flow:
Total head:
Operating temperature:
Cool down time:
Design pressure:
Liquid spec. gravity:
Shaft power:
Efficiency:
Direction of rotating:
Discharge flange:
Minimum starting level:
Minimum restarting level:
Pump down level:
At rated flow:
At minimum flow:
Minimum flow:
Motor
Type:
Rated output:
Synchronous speed:
Electric power source:
Rated current:
Starting current:
Insulation class:
Min. Starting voltage:
Min. Resistance value for starting:
Vertical Submerged
3-Phase Induction
200 kW
3600 rpm
AC 440V / 60Hz
355 A
2500 A
Class F
85 %
1 M
NOTE
Before undertaking this operation it is important to reduce the tank pressure to
near to atmospheric pressure and to keep it at this level throughout the entire
operation.
Electrical connections are made to the fixed junction box which is located
adjacent to each pump well.
2) The liquid level in the cargo tank should be higher than the following:
- The pump starting liquid level of initial unloading is as follows;
1.6 meter or higher from the tank bottom.
- In case of restart after stopping the pump, the minimum pump Starting
liquid level is as follows;
0.85 meter or higher from the tank bottom.
3) The opening degree of the pump discharge valve is to be fully closed.
A dedicated starter is available with one circuit breaker which is placed in the
No.1 cargo switchboard. This starter supplies all 4 fixed junction boxes.
All safety devices are transferred to the emergency pump when the circuit
breaker is engaged, as they are the same for the main cargo pumps.
4) At least three hours must be passed after pressure in the column being
stable.
NOTE
An insulation test of all pumps is to be carried out after leaving the loading
port in order to establish that all pumps are operational and to allow time for
the installation of the emergency cargo pump should it be necessary.
The restart of pumps in normal operation is restricted depending on the liquid
level above the submerged electric motor. Pumps may not be restarted when the
tank liquid level is below 850 mm. The motor should be started only once as far
as possible. If it is necessary to restart unavoidably, restart the motor after more
than 15 minutes has passed since motor stops.
- This cooling down time should be secured so that the pump and motor are
to be cooled down to the same temperature with LNG approximately.
- If cooling down is not enough; it may cause bearing troubles and damages
of parts having small running clearance between rotational element and
stationery element.
Start
1) Confirm that all the preparatory conditions described above are met.
2) Depress the start button to start the motor.
2. Operation
Preparation for Operation (Starting Condition)
1) The overall insulation resistance should be more than 5.
- After turning off the power switch provide in the starter, insulation
resistance between the power cable terminal in the starter and the
grounding should be measured and recorded, using a 500V megger.
- If the measurements are less than 1, do not start the motor because the
motor coil may be burnt. Even if insulation resistance lowers, is
sometimes restored of itself after it is left as it is for a long time, so be
sure to measure the insulation resistance of motor coil again before
unloading.
The weight of the emergency pump overcomes the compression of the springs to
open the foot valve.
4 - 30
250
50
70
200
40
0.50)
P ( =
150
30
0.47)
P ( =
100
20
50
10
60
40
2
1
PF
120
20
100
80
300
60
90
140
100
350
160
200
10
180
450
400
200
80
500
Slip S (%)
Current I (A)
NPSHR Hs (m)
Pump Down Hd (m)
Hs
0
Hd
0
0
100
200
300
Capacity Q
400
500
600
700
(m3/h)
4 - 31
20
40
Output (%)
60
80
100
120
140
2) Even for carrying operation in other conditions than the rated flow rate,
take the following flow rate range:
Minimum flow rate
220 m/h
550 m/h
660 m/h
NOTE
Except above range of flow, the ball bearings may be damaged by cavitation,
vibration, excessively large thrust and so on. Therefore, avoid long operation
out of the above flow rate range. After completion of start-up (after the
discharge pressure and electric current have settled), immediately open the
discharge valve and increase the discharge flow up to the rated flow.
3) If liquid level in the cargo tank has become relatively low, always monitor
and watch the variation of discharge pressure and electric current during
operation.
NOTE
If restarting the pump is done after the pump stops during striping operation,
the bearing or other part may be damaged. The higher the cumulative
frequency of restarting is, the higher the possibility of some accident may
become with increasing speed. When the motor stops during pump running,
cargo liquid in the column drops, the impeller rotates reverse, serving as a
water wheel, and needs several minutes before complete stopping. If restarting
the motor is done during this reverse rotation, a shock is given to the rotating
element, resulting in the bending of the shaft and damage of other parts.
5) If remaining liquid amount in the cargo tank is excessively small even by
repeating discharge valve operation a mentioned above, it will become
impossible to prevent discharge pressure from dropping remarkably due to
cavitations or gas inclusion.
If so, unloading by the pump is impossible to carry out, so the pump must
be stopped manually. Moreover, if liquid level in the tank has reached
the specified level, the pump must be stopped manually.
6) Do not close the discharge valve completely during pump operation.
- There is a possibility of motor auto stop by the low current trip when the
pump is operated with the discharge valve fully closed or slightly opened.
- If discharge pressure and electric current are unstable and begin to change
or drop; the pump may be in cavitations or gas inclusion operation.
Throttle the discharge valve gradually to decrease discharge capacity of
the pump until discharge pressure and electric current has become stable
or has risen. Each time discharge pressure and electric current fluctuate or
drop repeat throttling operation of the discharge valve. But the pump must
not be operated below the minimum flow.
- Although it is not the case of auto stop, shut-off operation should be less
than 15 seconds.
- If the pump is operated with the discharge valve fully closed or
approximately fully closed, liquid in the pump and the motor is heated and
liquid is gasified, so that the bearing, and the rotating part and the
stationary part may be seized each other, thus causing troubles such as a
damage of motor coil. Besides, an excessive thrust may be generated and
there is a possibility of bearing damage. Be very careful that a shut off
operation may be possible causes of troubles thereafter even if a trouble
would not happen at the time of shut-off operation.
Stop
1) Ordinary stop
- It is recommended to stop the pump at the condition of discharge valve
opening is as small as possible (motor low load condition)
- There is a case of motor auto stop by the low current trip when
discharge valve is closed or slightly opened.
- Stop the motor immediately when discharge valve is closed, even though
the motor does not stop automatically.
2) Auto stop
4 - 32
NOTE
Automatic trip device is an emergency trip device for protecting the pump and
motor from trouble. Therefore, the pump should be stopped manually as much
as possible.
Steps to be taken after stopping
1) To prevent dry operation and mis-operation, be sure to turn off the power
switch of the starter.
2) If the amount of gas which passes the pump and discharge piping is large
when carrying changing over of tank loading or other work even with
the pump stopped, the impeller serves as a wind mill, and pump shaft
rotates, so that the bearings are in a dry condition and could be damaged.
Therefore, take proper steps not to make dry operation by gas passing
through the pump.
4 - 33
Blank Page
4 - 34
PALL
11
PI
1A
PAL
11
PI
2A
TAHH
2A
TAH
2B
TI
2B
PI
8
VENT
PAL
8
PALL
8A
TAL
8
TAH
8
TI
8
TAHH
9A
TAL
9F
TAH
9F
TI
9F
PALL
8C
PAL
8C
TAHH
10A
TAH
10B
TI
10B
COMMON
TRIP
A
CUSTOMER
I2
T
TSHH TSH
2A
2B
PSLL
11
F
11
PCV
11
SEAL GAS
PSL
11
TT
2A
TSH
8
PT
8A
TT
2B
PI
8B
PSLL
8A
TSL
8
TLHH
9A
I2
PSL
8A
A
TSHH
9A
TSL
9F
TT
9A
TT
9F
TT
8
PLLL
8C
TSH
9F
TE
8
FI
11
TE
9A
TLHH
10A
PSLL
8C
PSL
8C
PT
8
D
5
PI
11
PLLL
8A
4-20mA
TLHH
2A
TE
9F
TSHH
10A
TSH
10B
TT
10A
TT
10B
TE
10A
TE
10B
4-20mA
I1
4-20mA
I2
PLLL
11
4-20mA
CRYOSTAR
4-20mA
4-20mA
F
3
FIC
1
4-20mA
PT
1
FY
1
PDT
1
PT
2
TE
2A
FG
88
PSV
6A
OP
6A
YE
9
I2
ZT
3
Alarm Circuit
PCV
3C
V
3C
PI
L.O Line
I2
Steam Line
ZLL
1
HIC
3
ZS
3
ZI
3
TI
1
HS
3
START
STOP
L.O. PUMP L.O. PUMP
HSH
HSL
6
6
F
5A
I1
LAL
5
TAH
5
YSHH
9
F
5B
TAL
5
4-20mA
STEAM INLET
YI
9
T
YAH
9
YI
9
CLOSEDOPEN
REMOTE CONTROL SIGNAL
YLHH
9
I1
ZLL
3
YT
9
STEAM OUTLET
4 - 35
PDT
7A
PDI
7A
PDSH
7A
PDAH
7A
PDT
7
PDI
7B
PDI
7A
COMPRESSOR ROOM
AUX.
L.O.
PUMP
OP
6B
MOTOR ROOM
OIL
COOLER
CV
6B
EM
6
V
6F
HS
15.3
TI
6A
TI
6B
EMLH OIL PUMP
RUNNING
6
RESET
PI
6B
CUSTOMER
CRYOSTAR
WATER
IN
READY TO
AUX.
L.O. PUMP START AUX.
RUNNING L.O. PUMP
DV
5
LOCKED
OPEN
TCV
6
C
6
EMY
6
L/R
I2
ZL
3
LOCKED
OPEN
H
5
TCV
5
DAC
3
DV
6
V
6C
TSL
5
HY
3
I/P
FILL
OIL TANK
TI
5A
YSH
9
PCV
3A
ZLH
1
TSH
5
ZI
3
P
PI
ZE
3
PCV
3B
Key
LG
5
ZSL
3
V
6B
PSV
6B
LSL
5
CONTROL SYSTEM
TROUBLE
F
5C
YET
YET
99
COMPRESSOR
RUNNING
COMPRESSOR
HS
CONTROL
MOTOR ABNORMAL
15.5
MOTOR
ABNORMALFLASH LIGHT
STOP
1.5
FEEDBACK
I1
Trip Circuit
DV
1
TE
1
4-20mA
TT
1
CV
6A
V
6A
PSV
6B
Set : 8 bar
MAIN
OIL PUMP
LAMP
TEST
F
7
BULKHEAD
COMPRESSOR
Legend
TI
8
OIL FILTER
IGV
HS
15.4
L
15.8
OIL COLLECTOR
FG
84
F
1
READY TO START
COMPRESSOR
REMOTE STOP
STOP
COMPRESSOR COMPRESSOR
CONTROL
SYSTEM
ABNORMAL
OC
8
PI
1
ZSH
1
REMOTE
HSH
15.2
L
15.9
E-MOTOR
TI
1
Local Instrument
CA
15
TI
2
TE
2B
FE
1
HS
15.1
L
15.2
BULKHEAD
SEAL
PROCESS GAS IN
L
15.3
HSL
15.2
I/P
ZSL
1
L
15.4
EXTERNAL
SHUTDOWN
EMERGENCY
STOP
REMOTE START
FLASH
START
LIGHT COMPRESSOR COMPRESSOR
PT
2A
PT
1A
PI
2
4-20mA
4-20mA
EMERGENCY POWER ON
STOP
C
4-20mA
4-20mA
4-20mA
PDI
1
PDI
1A/1B
EMS
15
L
15.1
PCV
8
1.5
PDI
1
L
15.6
READY TO START
MOTOR
POWER ON
DRTD
SURGE CONTROL
ZI
3A
HEATER
TRIP
COMMON ALARM
COMPRESSOR READY TO
READY TO LOCAL/REMOTE
RUNNING
START
START
COMPRESSOR AUX. L.O. PUMP
GEAR BOX
INSTRUMENT AIR
L
15.1
L
15.10
L
15.5
WATER
OUT
READY TO START
AUX. L.O. PUMP
YAHH
9
REMOTE
START
REMOTE
STOP
4.4.1 HD Compressors
Specification
HD Compressors
Manufacturer:
Model:
Type:
No. of Sets:
Volume flow:
Inlet pressure:
Outlet pressure:
Inlet temperature:
Outlet temperature:
Shaft speed:
Inlet guide vanes setting:
Efficiency:
Cryostar
CM 400/55
Centrifugal Single stage Fixed speed
with adjustable guide vanes
2
32,000 Nm3/h
103 KPa
196 KPa
-140C
-111.0C
11,200 rpm
-30 to +80 deg
80%
2. Compressor Systems
6,600 V/60Hz
900 kW
3565 rpm
1. Description of equipment
The compressor system is skid-mounted as shown on the equipment layout
drawing. The P&I diagram presents a complete flow schematic for the
Compressor System. The system consists of a direct-coupled compressor with
integrated gear box, and the following sub-systems.
A self-contained lube oil system for lubrication of the gears and rotor bearings in
the gear box, a seal gas system, and a control and indicating system for
monitoring and safe operation of the unit (local panel and sub-station)
The sub-systems contain the following main components:
-
A pressure control valve regulates the oil flow to the gear box. Adjustment of this
valve sets the supply pressure to the bearings. Excess oil bypasses the machine
and returns directly to the reservoir. The pump relief valve acts as back up valves
and is set at 0.8 MPa .
The lube oil flow is then directed to the gear box where the lube oil is injected
into the bearings. Separated pressure switches are provided:
Compressor
The skid-mounted compressor features a plug-in closure assembly, which allows
for quick replacement of the rotating portion and adjacent stationary components.
The compressor portion of the machine is of axial inflow type, with variable inlet
guide vanes. The compressor has been designed to operate over the range of
pressures and flow rates. Proximity probe pick-ups are provided to allow the
monitoring of the compressor shaft vibration.
One does activates the alarm and energise the auxiliary lube oil pump and the
second is set to shutdown the system when the pressure falls below minimal
pressure. The seal gas is applied outboard of the lube oil seal. Preventing the lube
oil mist from entering the process stream and avoiding cold gas flow into the
gear box. Temperature sensors at the main bearings sense the oil outlet
temperature of the bearings.
Nominal temperature range is 45 to 50 for the gear bearings. The high
temperature condition (60) will cause actuation of the alarm relays.
HD Compressor Motor
Electric source:
Power:
Speed:
The clogging indicator indicates the pressure drop across the operating filter, and
provides an indication of the condition of the filter element. Differential pressure
over 0.2 MPa indicates that the filter element needs changing. A flow orifice
regulates the oil flow and (oil) pressure to the bulkhead seal. This oil is used for
the lubrication of the bulkhead/ shaft seal and returns back to the oil tank.
Oil from the gear box is stored in a vented 400 liter lube oil sump. The oil sump
includes an integral steam immersion heater. Set-points for the lube oil system
controls are listed on table. Lube oil is supplied from the sump through separate
suction strainer screens and two lube oil pumps. The outlets from the lube oil
pumps are through check valves to a common lube oil line in order to prevent
back-up oil under pressure from entering the non-operating pump lines. The low
speed shaft gear drives the main operational pump. Upon failure of the lead
pump, the stand-by electric pump is ENERGIZED immediately and a remote
alarm indicates that the auxiliary pump is operating.
The lube oil passes through the heat exchanger where it is cooled. The thermal
bypass temperature control valve prevents overcooling of the lube oil within a
limited range (38 to 47)
Then the lube oil passes through either of two filters. The position of the
changeover valve determines through which filter the lube oil passes.
4 - 36
The lube oil then collects in the lube oil sump. The lube oil contains a mixture of
lube oil and seal gas. The seal gas is vented from the reservoir through a mist
separator and piped away to the atmosphere.
Surge control system
An automatic surge control system has to be provided to protect the machines
from inadvertently operating in surge.
Compressor surge is characterized by erratic compressor inlet and discharge
pressure and (usually audible) flow pulsation. It is caused by flow instability in
the compressor. Severe compressor surge causes shaft vibration to increase and
may result in severe damage to the compressor
The two compressors are equipped with an automatic surge control system; using
a by-pass valve responding to a low flow controller. The inlet guide vanes on
both compressor suction sides will be controlled by a process loop. Speed and
inlet guide vanes control the flow.
Inlet Guide Vanes
To achieve the required gas flow, the compressors have inlet guide vanes fitted at
the suction ends. The vanes are operated by pneumatic actuators which receive
control signals from the flow controller. Rotation of the vanes is possible through
an indicated angle of 80 to -30. The position is indicated both locally and at the
cargo control room.
1.9
90
1.7
80
ati
o
70
60
e
Lin
e
g
Sur
(1
)
1.5
Pr
es
su
re
R
2.1
No
te
50
Se
e
40
1.
3
Case 1
30
5
1.1
20
+50
10
etting
+70
ane S
V
e
id
u
Inlet G
Min.
Max.
(2)
0
0
2.0
1.0 0.8
10.0
30.0
20.0
40.0
0.6
Density (kg/m3)
In
le
tT
em
-120
-100 per
at
ur
-80
e
-140
M
o
(k ld W
g/
Km eig
ol ht
)
-60
(
)
-40
-20
0
20
16
18
20
22
24
26
28
30
10.0
20.0
30.0
40.0
50.0
60.0
Note :
1. Minimum flow from ship when recycle loop is open.
2. IGV setting indicative only and subject to change,
will be confirmed during testing.
4 - 37
NOTE
3 or 4 repeated cycles of pressure swings by injection of inert gas (nitrogen)
are necessary to purge the instrument impulse lines.
As long as the seal gas system is operated, the machine can be left stand-by
under gas for extended periods.
d) Seal gas system
- Open seal gas inlet valve.
- Check if filter element of seal gas regulator is clean and adjust the seal
gas supply.
- If necessary, seal gas DP may be adjusted with seal gas regulator.
- As long as the seal gas system is on operation, the machine can be left
stand-by under gas for extended periods.
e) Lube oil system
- Start steam heater, 45 min. to 1.5 hr (depending on ambient temp. level)
prior to expected blower start-up time. The heater will automatically
Open instrument air supply valve on main inlet and panel inlet. This supplies
instrument air to the IGV actuator and transmitter. With local pneumatic
control station, set to MAN. Stroke IGV actuator and observe for full stroke.
Adjust for 0% position (IGVs in start position).
b) Electrical system
Check out for correct wiring and power supply voltage and frequency.
Switch power on and test SPY lamps/ monitors. Eliminate all trip and alarms
and check lamps. Check if all indicators work correctly.
c) Compressor purge system
Sub-system Start-up
This section covers procedures necessary to start the subsystems and establish
electrical power, instrument air, seal gas pressure, lube oil pressures and cooling
water required to safety start the compressor. These instructions provide a
systematic procedure for a safely start-up of the compressor system.
Preliminary checks:
(Principally for initial commissioning of the installation only)
Before any mechanical equipment is put into operation the following main
check points should be observed:
- Check fixing bolts and retightens if necessary.
- Verify allowable forces and moments of process piping connections.
- Check if inlet screen on process side is installed and is clean.
- Remove inlet process pipe and turn by hand the wheel (Rotor).
Long period :
After a period of non-operation of more than 8 days without seal gas and
prior to take any part of the machinery again into operation the unit must be
purged with dry and warm nitrogen. Temp. min. of nitrogen should be +15C.
- Open purge inlet valve.
- Purge system for 10 min. minimum when compressor main inlet and outlet
valve are closed (on process side) until all possible NG introduced within
the machine has been exhausted. Flow minimum 12Nm3/h at 150 kPa max.
- Close by-pass valve and apply seal gas.
Short period :
During periods of less than 8 days of non-operation without seal gas it is
recommended to pressurise the unit with warm and dry air to max. 30 KPa
over-pressure, while the compressor main inlet and outlet valves are shut.
- Open purge inlet valve.
4 - 38
Open bleed valves on top of filter to bleed air from both filters. After
bleeding air from filter, select filter, leaving other on stand-by. Adjust
lube oil supply pressure with press. regulating valve and check pressure
on. Check downstream lube oil pressure switch for correct readings resp.
settings.
- Test operations of auxiliary pump. On running machine check that standby pump comes on automatically by lowering the lube oil pressure with
press. regulating valve.
CAUTION
The lube oil pump is not operating below 15 .
f) Cooling water
-
Open cooling water inlet/ outlet valves from oil cooler in accordance
with lube oil flow. Observe cooling water temperature rise on return line.
g) Surge control
The surge control system is provided to prevent inadvertent surging of the
compressor during start-up and steady state operation. The surge system is a
fully automatic system.
supply and run the lube oil pump for at least 30 min. prior to start-up. Check
the oil temperatures and pressures to be within prescribed limits.
Performance may be expected in the indicated range of pressures and flow rates,
providing that the following normal precautions are observed:
The compressor may be rapidly shut down at any time by depressing the
COMPRESSOR STOP BUTTON at the compressor control panel or at any of
the remote stations. Any shutdown resulting from the compressor safety system
will accomplish the same result.
The compressors are operated locally or from the IAS in the CCR
Safeties in ESDS and Tank protection system:
z
z
z
z
ESDS
z
z
z
z
z
z
b) Press the STOP BUTTON to shut down the main motor drive. Observe that
auxiliary lube pump starts.
c) Controller will open surge control valve.
b) If shutdown occurred as a result of the safety system, reset the cause of the
malfunction before restarting.
d) The unit may be left in cold condition as long as the lube-oil and seal-gas
subsystems are operating satisfactorily. Restart the machine following the
procedures as described in the previous chapters. In case the units are going
to be shut down for a longer period of time the lube oil pump can be
switched-off and the seal gas can be shut off after not less than 30min. after
compressor shut-down to keep cold from creeping towards to bearing.
Tank
Protection
System
Gas
Leakage
Control
Safeties on local control system (oil temperature, oil pressure, discharge gas
temperature, seal gas pressure and shaft vibration).
e) In case the units are shut-down for a period of up to 1 hour with either no
seal gas or oil pump running (power failure) or both then restore seal gas
4 - 39
Blank Page
4 - 40
PALL
11
PI
1A
PAL
11
PI
2A
TAHH
2A
TAH
2B
TI
2B
PI
8
VENT
PAL
8
PALL
8A
TAL
8
TAH
8
TI
8
TAHH
9A
TAL
9F
TAH
9F
TI
9F
PALL
8C
PAL
8C
TAHH
10A
TAH
10B
TI
10B
COMMON
TRIP
A
CUSTOMER
I2
T
TSHH TSH
2A
2B
PSLL
11
F
11
PCV
11
SEAL GAS
PSL
11
TT
2A
TSH
8
PT
8A
TT
2B
PI
8B
PSLL
8A
TSL
8
TLHH
9A
I2
PSL
8A
A
TSHH
9A
TSL
9F
TT
9A
TT
9F
TT
8
PLLL
8C
TSH
9F
TE
8
FI
11
TE
9A
TLHH
10A
PSLL
8C
PSL
8C
PT
8
D
5
PI
11
PLLL
8A
4-20mA
TLHH
2A
TE
9F
TSHH
10A
TSH
10B
TT
10A
TT
10B
TE
10A
TE
10B
4-20mA
I1
4-20mA
I2
PLLL
11
4-20mA
CRYOSTAR
4-20mA
4-20mA
F
3
FIC
1
4-20mA
PT
1
FY
1
PDT
1
PT
2
TE
2A
FG
88
PSV
6A
OP
6A
YE
9
I2
ZT
3
Alarm Circuit
PCV
3C
V
3C
PI
L.O Line
I2
Steam Line
ZLL
1
HIC
3
ZS
3
ZI
3
TI
1
HS
3
START
STOP
L.O. PUMP L.O. PUMP
HSH
HSL
6
6
F
5A
I1
LAL
5
TAH
5
YSHH
9
F
5B
TAL
5
4-20mA
STEAM INLET
YI
9
T
YAH
9
YI
9
CLOSEDOPEN
REMOTE CONTROL SIGNAL
YLHH
9
I1
ZLL
3
YT
9
STEAM OUTLET
4 - 41
PDT
7A
PDI
7A
PDSH
7A
PDAH
7A
PDT
7
PDI
7B
PDI
7A
COMPRESSOR ROOM
AUX.
L.O.
PUMP
OP
6B
MOTOR ROOM
OIL
COOLER
CV
6B
EM
6
V
6F
HS
15.3
TI
6A
TI
6B
EMLH OIL PUMP
RUNNING
6
RESET
PI
6B
CUSTOMER
CRYOSTAR
WATER
IN
READY TO
AUX.
L.O. PUMP START AUX.
RUNNING L.O. PUMP
DV
5
LOCKED
OPEN
TCV
6
C
6
EMY
6
L/R
I2
ZL
3
LOCKED
OPEN
H
5
TCV
5
DAC
3
DV
6
V
6C
TSL
5
HY
3
I/P
FILL
OIL TANK
TI
5A
YSH
9
PCV
3A
ZLH
1
TSH
5
ZI
3
P
PI
ZE
3
PCV
3B
Key
LG
5
ZSL
3
V
6B
PSV
6B
LSL
5
CONTROL SYSTEM
TROUBLE
F
5C
YET
YET
99
COMPRESSOR
RUNNING
COMPRESSOR
HS
CONTROL
MOTOR ABNORMAL
15.5
MOTOR
ABNORMALFLASH LIGHT
STOP
1.5
FEEDBACK
I1
Trip Circuit
DV
1
TE
1
4-20mA
TT
1
CV
6A
V
6A
PSV
6B
Set : 8 bar
MAIN
OIL PUMP
LAMP
TEST
F
7
BULKHEAD
COMPRESSOR
Legend
TI
8
OIL FILTER
IGV
HS
15.4
L
15.8
OIL COLLECTOR
FG
84
F
1
READY TO START
COMPRESSOR
REMOTE STOP
STOP
COMPRESSOR COMPRESSOR
CONTROL
SYSTEM
ABNORMAL
OC
8
PI
1
ZSH
1
REMOTE
HSH
15.2
L
15.9
E-MOTOR
TI
1
Local Instrument
CA
15
TI
2
TE
2B
FE
1
HS
15.1
L
15.2
BULKHEAD
SEAL
PROCESS GAS IN
L
15.3
HSL
15.2
I/P
ZSL
1
L
15.4
EXTERNAL
SHUTDOWN
EMERGENCY
STOP
REMOTE START
FLASH
START
LIGHT COMPRESSOR COMPRESSOR
PT
2A
PT
1A
PI
2
4-20mA
4-20mA
EMERGENCY POWER ON
STOP
C
4-20mA
4-20mA
4-20mA
PDI
1
PDI
1A/1B
EMS
15
L
15.1
PCV
8
1.5
PDI
1
L
15.6
READY TO START
MOTOR
POWER ON
DRTD
SURGE CONTROL
ZI
3A
HEATER
TRIP
COMMON ALARM
COMPRESSOR READY TO
READY TO LOCAL/REMOTE
RUNNING
START
START
COMPRESSOR AUX. L.O. PUMP
GEAR BOX
INSTRUMENT AIR
L
15.1
L
15.10
L
15.5
WATER
OUT
READY TO START
AUX. L.O. PUMP
YAHH
9
REMOTE
START
REMOTE
STOP
pressures and flow rates. Proximity probe pick-ups are provided to allow the
monitoring of the compressor shaft vibration.
Cryostar
CM 300/45
Centrifugal. Single stage.
Adjustable guide vanes.
8,500 Nm3/h
103 KPa
196 KPa
-40C
7.9C
-30 to +80 deg
24,000 rpm
77 %
440 V / 30~60 Hz
300 kW
3585 rpm
1. Description
The compressor system is skid-mounted as shown on the equipment layout
drawing. The P&I diagram presents a complete flow schematic for the
Compressor System. The system consists of a direct-coupled compressor with
integrated gear box, and the following sub-system.
A self-contained lube oil system for lubrication of the gears and rotor bearings in
the gear box, a seal gas system, and a control and indicating system for
monitoring and safe operation of the unit (local panel and sub-station)
The sub-systems contain the following main components:
- Compressor inlet guide vane actuator
- Oil mist separator
- Lube oil immersion heater
- El. Motor driven auxiliary lube oil pump
- Gear driven main lube oil pump
- Oil cooler
- Duplex oil filter
- Gear coupling (low speed)
- Bulkhead/ shaft seal
- Main drive electric Motor
2. Compressor Systems
Then the lube oil passes through either of two filters. The position of the
changeover valve determines through which filter the lube oil passes.
The clogging indicator indicates the pressure drop across the operating filter, and
provides an indication of the condition of the filter element. Differential pressure
over 0.2 MPa indicates filter element changing.
A flow orifice regulates the oil flow and (oil) pressure to the bulkhead seal. This
oil is used for the lubrication of the bulkhead/ shaft seal and returns back to the
oil tank.
To achieve the required gas flow, the compressors have inlet guide vanes fitted at
the suction ends.
The vanes are operated by pneumatic actuators which receive control signals
from the flow controller.
Rotation of the vanes is possible through an indicated angle of 80 to -30.
The position is indicated both locally and at the cargo control room.
Compressor
The skid-mounted compressor features a plug-in closure assembly, which allows
for quick replacement of the rotating portion and adjacent stationary components.
The compressor portion of the machine is of the axial inflow type, with variable
inlet guide vanes. The compressor has been designed to operate over the range of
A pressure control valve regulates the oil flow to the gear box. Adjustment of this
valve sets the supply pressure to bearings. Excess oil bypasses the machine and
returns directly to the reservoir. The pump relief valve acts as back up valves and
is set at 0.8 MPa.
The lube oil flow is then directed to the gear box where the lube oil is injected in
4 - 42
1.89
1 .5
P re
ssu
re
Forced Gas
Lin
70
Ra
tio
80
90
1.7
2.17
LD-ViriableSpeed Motor
Operating Point
rge
60
Su
ote (
1)
40
1.
-30 &
24000 (rpm)
Nat. Boil Off
See
N
32
50
30
3
1 .1
20
10
0
0
1.0 0.8
0.6
7.5
5.0
3
3
Volume Flow (10 m /h)
10.0
Density (kg/m3)
7.0
9.0
11.0
13.0
In
le
-140
t
15.0
17.0
o
(k ld W
g/
Km eig
ol ht
)
17.0
15.0
13.0
11.0
9.0
7.0
-60
(
)
-40
-20
0
20
16
18
20
22
24
26
28
30
1.0
2.0
3.0
4.0
5.0
Te
-120
m
pe
-100
ra
tu
-80
re
2.0
2.5
4 - 43
b) Electrical system
Check out for correct wiring and power supply voltage and frequency.
Switch power on and test SPY lamps/ monitors. Eliminate all trip and alarms
and check lamps. Check if all indicators work correctly.
c) Compressor purge system
This section covers procedures necessary to start the subsystems and establish
electrical power, instrument air, seal gas pressure, lube oil pressures and cooling
water required to safely start the compressor. These instructions provide a
systematic procedure for a safe start-up of the compressor system.
Preliminary checks:
(Principally for initial commissioning of the installation only)
Before any mechanical equipment is put into operation the following main check
points should be observed:
- Check fixing bolts and retightens if necessary.
- Verify allowable forces and moments of process piping connections.
- Check if inlet screen on process side is installed and is clean.
- Remove inlet process pipe and turn by hand the wheel (Rotor).
- Remove low speed coupling.
Open instrument air supply valve on main inlet and panel inlet. This supplies
instrument air to the IGV actuator and transmitter. With local pneumatic
control station, set to MAN. Stroke IGV actuator and observe for full
stroke. Adjust for 0% position (IGVs in start position).
Subsystem Start-up
NOTE
3 or 4 repeated cycles of pressure swings by injection of inert gas (nitrogen)
are necessary to purge the instrument impulse lines.
As long as the seal gas system is operated, the machine can be left stand-by
under gas for extended periods.
Long period :
After a period of non-operation of more than 8 days without seal gas and
prior to take any part of the machinery again into operation the unit must be
purged with dry and warm nitrogen. Temperature. Minimum of nitrogen
should be +15C.
- Open purge inlet valve.
- Purge system for 10 min. minimum when compressor main inlet and outlet
valve are closed (on process side) until all possible NG introduced within
the machine has been exhausted. Flow min. 12Nm3/h at 150 KPa max.
- Close by-pass valve and apply seal gas.
Short period :
During periods of less than 8 days of non-operation without seal gas we
recommend to pressurize the unit with warm and dry air max. 30 KPa overpress, while the compressor main inlet and outlet valves are shut.
- Open purge inlet valve.
4 - 44
e) In case the units are shut-down for a period of up to 1 hour with either no
seal gas or oil pump running (power failure) or both then restore seal gas
supply and run the lube oil pump for at least 30 min. prior to start-up. Check
the oil temperatures and pressures to be within prescribed limits.
Performance may be expected in the indicated range of pressures and flow rates,
providing that the following normal precautions are observed:
- Do not operate compressor in surge. Compressor surge is characterized by
erratic compressor in let and discharge pressures and (usually audible) flow
pulsations.
- There is no surge control protection while in the manual mode. Therefore, it
is important to set up steady state operation and transition from manual to
automatic surge control as quickly and smoothly as possible, per start-up
instructions.
- Do not operate the compressor under conditions, which lead to excessive
thrust load (e.g. Surge, high pressures).
- Check complete operating system for oil-, seal gas-, air-, water leaks and
product leakage regularly. Maintain reservoir level at the level indicated on
the reservoir sight glass. Check periodically.
- Check seal gas and lube oil filter pressure drops regularly. Replace filter
elements.
- Do not operate the unit for longer periods while alarms are indicated.
z
z
z
z
z
ESDS
z
z
Check subsystem for proper operation. Auxiliary (stand-by) lube oil pump will
stop after start of main motor, while gears driven (main) pump delivers enough
pressure for oil system.
z
z
z
z
b) Press the STOP BUTTON to shut down the main motor drive. Observe that
auxiliary motor-pump is coming on.
c) Controller will open surge control valve.
z
z
Master Gas
Valve
d) The unit may be left in cold condition as long as the lube-oil and seal-gas
subsystems are operating satisfactorily. Following the procedures as
described in the previous chapters may restart it.
e) Check complete operating system for oil-, seal gas-, air-, water leaks, and
product leakage.
z
z
Close
Control
z
z
In case the units are going to be shut for a longer period of time the lube oil
pump can be switched-off and the seal gas can be shut after not less than 30
min. of compressor shut-down; this to keep cold from creeping towards to
bearing.
4 - 45
Gas
Leakage
Control
Blank Page
4 - 46
PV
TIC
2
PI
2
Control
Valve
TAHH
2
L/R
Position
Split - Range
Temperature Control
PIPIT
4-20mA
4-20mA
ZI
2
L/R
Position
L
1
ZI
1
Common
Trip
XA
Ext.
Trip
XA
HH
LAHH
4
LAH
4
TALL
4
TAL
4
L/R
Position
L/R
Position
L
2
L
1
T
L
5
H2
TI
2
PI
1
XA
5
TT
4
Common
Trip
Alarm
TI
4
Feeding
Compressor
To Be Tripped
TT
2
L
2
4-20mA
H1
Key
C1
Local Panel
PIT
2
Control Cabinet
Safe Area
HIC
2
TI
2
I.A.S. System in
CCC Cargo Cont. Rm
Safe Area
Set Point
H
C2
PI
3
TI
4
Desuperheated
Steam Line
HS
5
ESD
PCV
2
SV
2
C2
CG-539
CG-538
CS-05
CS-06
Vent
FC CG-546
CG-544
TI
1
ZT
2
TCV
2
ZI
2
LSHH
4
CG-547
CG-545
FC
LI
4
LSH
4
TSLL
4
Automatic Trip
Alarm Circuit
Local Instrument
TE
4
PCV
1
Gas Inlet
Electrical Signal
Steam
Inlet
Local Equipment
Hazardous Area
Gas Outlet
CG-553
CG-552
Condensate Line
TSHH
2
TE
2
TCV
1
L/R
ZS
2
H2
Local Panel
I/P
HS
2
HIC
2
HY
2
4-20mA
Z1
1
Z1
1
Instrument on
Local Panel
Instrument Air
SV
1
C1
L/R
ZS
1
H1
PCV
6
I/P
HS
1
HIC
1
HY
1
4-20mA
CS-13
CS-16
4 - 47
IAS Function
CS-15
CS-18
PI
6
CS-14
CS-17
Condensate
Drain
L/R
Local / Remote
FC
Fail Close
3)
CAUTION
When returning heated vapour to the cargo tanks, the temperature at the heater
outlet should not exceed +80C to avoid possible damage to the cargo piping
insulation and safety valves.
High-Duty Heater
Specification
Manufacturer:
Model:
Type:
Cryostar
108-UT-38/34-4.6
BEU
Tube Side
(Process
Fluid)
Unit
Mass Flow
Low-Duty Heater
Pressure
Drop
(Calculated)
kPa
Heat
Exchange
(Actual)
kW
Design
Pressure
MPa
1.0
Design
Temperature
-196/+200
13
17
Interm
Specification
4,003
Shell Side
(Saturated
Steam)
Unit
Steam
Consumption
kg/h
Inlet Temperature
4,732
820
2,781
874
Operating Case
Manufacturer:
Model:
Type:
Cryostar
21-UT-38/34-3.2
BEU
Tube Side
(Process
Fluid)
Unit
Mass Flow
kg/h
Operating
Case
Operating
Case
Shell Side
(Saturated
Steam)
Unit
12,000
Steam
Consumption
kg/h
1,559
BOG Gas
BOG Gas
Design
Beg
WU
End
WU
Interm
Emcy
BO
Inlet Volume
Flow
m3/h
5,611
Inlet
Temperature
179
7,143
8,443
1,464
4,962
1,559
Outlet
Volume Flow
m3/h
10,442
Outlet
Temperature
174 appx.
Inlet
Temperature
-90
Inlet
Pressure
MPa
0.9
25
Outlet
Pressure
MPa
0.9
179
Outlet
Temperature
Inlet Pressure
MPa
0.9
Outlet
Temperature
Outlet Pressure
MPa
0.9
Inlet
Pressure
MPa
0.1
Design
Pressure
MPa
1.0
Design Pressure
MPa
1.0
Outlet
Pressure
kPa
75
Design
Temperature
+200
Design
Temperature
+200
Pressure
Drop
(Calculated)
kPa
23
Heat
Exchange
(Actual)
kW
874
174 appx.
Operating Case
Emcy
BO
Design
Beg WU
End
WU
kg/h
37,200
42,800
21,600
28,700
12,000
Design
Pressure
MPa
1.0
Inlet Volume
Flow
m3/h
17,394
17,826
16,171
16,720
5,611
Design
Temperature
-196/+200
Outlet Volume
Flow
m3/h
38,346
42,199
22,265
31,936
10,442
Inlet
Temperature
-90
-110
20
-45
-90
Outlet
Temperature
80
Inlet
Pressure
MPa
Outlet
Pressure
kPa
80
25
0.1
75
75
75
75
75
4 - 48
PV
TIC
2
PI
2
Control
Valve
TAHH
2
L/R
Position
Split - Range
Temperature Control
PIPIT
4-20mA
4-20mA
ZI
2
L/R
Position
L
1
ZI
1
Common
Trip
XA
Ext.
Trip
XA
HH
LAHH
4
LAH
4
TALL
4
TAL
4
L/R
Position
L/R
Position
L
2
L
1
T
L
5
H2
TI
2
PI
1
XA
5
TT
4
Common
Trip
Alarm
TI
4
Feeding
Compressor
To Be Tripped
TT
2
L
2
4-20mA
H1
Key
C1
Local Panel
PIT
2
Control Cabinet
Safe Area
HIC
2
TI
2
I.A.S. System in
CCC Cargo Cont. Rm
Safe Area
Set Point
H
C2
PI
3
TI
4
Desuperheated
Steam Line
HS
5
ESD
PCV
2
SV
2
C2
CG-539
CG-538
CS-05
CS-06
Vent
FC CG-546
CG-544
TI
1
ZT
2
TCV
2
ZI
2
LSHH
4
CG-547
CG-545
FC
LI
4
LSH
4
TSLL
4
Automatic Trip
Alarm Circuit
Local Instrument
TE
4
PCV
1
Gas Inlet
Electrical Signal
Steam
Inlet
Local Equipment
Hazardous Area
Gas Outlet
CG-553
CG-552
Condensate Line
TSHH
2
TE
2
TCV
1
L/R
ZS
2
H2
Local Panel
I/P
HS
2
HIC
2
HY
2
4-20mA
Z1
1
Z1
1
Instrument on
Local Panel
Instrument Air
SV
1
C1
L/R
ZS
1
H1
PCV
6
I/P
HS
1
HIC
1
HY
1
4-20mA
CS-13
CS-16
4 - 49
IAS Function
CS-15
CS-18
PI
6
CS-14
CS-17
Condensate
Drain
L/R
Local / Remote
FC
Fail Close
The vapour lines will be set for using the HD compressor to deliver vapour to the
High Duty heater.
The gas outlet temperature is controlled by controllers CG505 on the inlet and
CG507 on the HD heater bypass line.
3) Open the steam side vent and open the drain valve when all the pressure
is off the heater.
2) Open the shell side condensate valves and check the drains.
The steam condensate from the heater is returned to the drains system via the
cargo steam drains cooler and the cargo escape tank, the latter of which is fitted
with a gas detector sampling point.
3) When all the air has been expelled from the shell, shut the vent valve.
4) When water has been drained from the shell, shut the drain valve.
(The temperatures and pressures for the venting and warming up of the
heater should be 30 minutes.)
The same procedure is followed for venting and warming through the No.1
BOG heater as described above, except that the temperature control is set for a
gas outlet temperature of +45C.
The vapour lines will be set for using the LD compressor to deliver vapour to
the Low Duty Heater.
6) Set the vapour lines as detailed for the operation and put the cargo
heater in use.
When the heater has been vented and warmed through, proceed as follows:
7) In the CCR, set the controls for the heater to the ON position on the IAS.
8) Open the instrument air supply to the controls for the heater.
2) Open the shell side condensate valves and check the drains.
3) When all the air has been expelled from the shell, shut the vent valve.
10) Set the temperature and level controller to the correct settings for the
operation being undertaken (first stage: 0C, second stage: +80C for
warming up operation with vapour, 50C for warming up and inerting
operation with inert gas).
4) When water has been drained from the shell, shut the drain valve.
5) Slowly open the manually operated steam inlet valve CS02.
6) Check the condensate level.
11) Open the hydraulically operated gas inlet valve CG503 and manually
operated outlet valve CG509.
7) Set the LNG vapour lines as detailed for the operation to be undertaken.
8) Open the vapour outlet valve CG510 and the vapour inlet valve CG504.
9) In the CCR, set the controls for the LD heater on the IAS.
11) Set the temperature and level controllers to the correct settings for gas
burning of +30C.
3) Close the steam supply valve CS01 to the heater when the temperature
at the heater outlet is above 0C.
4) Open the steam side vent, then open the drain when all the steam has
vented.
4 - 50
Control
Valve
TT
2
FI
1
L
2
L/R
Position
ZI
2
L/R
Position
L
1
ZI
1
Common
Trip
Ext.
Trip
XA
HH
XA
LAHH
LAH
TALL
TAL
4
L/R
Position
L/R
Position
L
2
L
1
A
PI
1
XA
5
LAHH
1
H2
TT
4
C1
H1
Key
LNG Vapour Line
C2
Local Panel
PIT
2
L
Common
Trip
Alarm
TI
2
TI
4.2
Flow Control
Signal 4-20mA
4-20mA
TIC
2
4-20mA
PV
PI
2
4-20mA
Control Cabinet
Safe Area
Set Point
HIC
2
TI
2
PIPIT
I.A.S. System in
CCC Cargo Cont. Rm
Safe Area
Desuperheated
Steam Line
PI
3
TI
4
HS
5
ESD
Condensate Line
LSH
1
Mist
Separator
TE
CG-556
CS-04
Gas Outlet
Vent
CS-03
Electrical Signal
Steam
Inlet
FI
C2
Local Equipment
Hazardous Area
PCV
2
SV
2
CS-503
FC
TCV
2
TI
1
Liquid Gas
Inlet
Liquid Line
CS-507
ZT
2
ZI
2
LSHH
4
CS-502
LI
4
LSH
4
FC
TSLL
4
Automatic Trip
Alarm Circuit
Local Instrument
TE
4
PCV
1
FCV
1
Z1
1
Z1
1
Instrument on
Local Panel
Instrument Air
SV
1
C1
IAS Function
CS-12
L/R
ZS
2
H2
HS
2
HIC
2
Local Panel
I/P
HY
2
4-20mA
L/R
ZS
1
H1
HS
1
HIC
1
PCV
6
I/P
HY
1
4-20mA
PI
6
CS-10
CS-11
Condensate
Drain
L/R
Local / Remote
FC
Fail Close
4 - 51
1. General
The LNG vaporiser is a steam heated shell and tube type heat exchanger located
in the cargo compressor room on the trunk deck. It is equipped with automatic
flow and outlet temperature controllers.
Specification
Manufacturer:
Model:
Type:
Tube Side
(Process fluid)
Cryostar
65-UT-38/34-5.6
BEU
Shell Side
(Saturated steam)
Unit
Vapour
purge
(Methane)
LNG disch
(Methane)
Emcy
Forcing
(Methane)
Steam
Consumption
kg/h
5,059
6,390
2,784
Inlet Temperature
179
Outlet Temperature
174 appx.
Inlet Pressure
MPa
0.9
Outlet Pressure
MPa
0.9
Design Pressure
MPa
0.1
Design
Temperature
+200
Operating Case
Unit
IG Purging
Mass Flow
kg/h
m /h
11,000
24
Unload
22,000
49
Outlet Volume
Flow
m3/h
Inlet Temperature
Outlet
Temperature
Inlet Pressure
MPa
0.3
Outlet Pressure
kPa
30
12,669
12,367
-130
Pressure Drop
(Calculated)
kPa
Heat Exchange
(Actual)
kW
Design Pressure
MPa
0.1
Design
Temperature
-196/+200
12
2,835
54
3,581
Forcing
7,000
16.0
6,503
-163
20
LNG is supplied from the shore to the LNG vaporiser via the
stripping/spray line. The vapour is produced at the required temperature
of +20C is then passed to the cargo tanks.
-40
Set the LNG pipelines as detailed for the operation about to be undertaken.
To prepare the LNG vaporiser for use;
NOTE
LNG discharging without vapour return from shore.
1) Ensure that the deck steam and instrument air supplies are available to
the LNG vaporiser.
Alarms are provided for outlet gas temperature and for condensate water high
level and low temperature. The gas outlet temperature and the condensate low
temperature alarms are both inhibited when the LNG vaporiser is shut down.
2) Open the condensate drain valve and the steam side shell vent valve.
3) Set up the downstream vapour lines for the required operation and
vaporiser outlet valve CG501, to allow for gas expansion during the
warming up stage.
4 - 52
4) Slowly open the vaporiser steam master valve bypass CS04 fully to
warm through and vent the heater.
5) When all the air has been expelled from the shell, shut the vent valve.
6) When the drains are blowing clear open the drain trap outlet and inlet
valves and shut the drain. The temperatures, pressures and condensate
levels of the heater should be allowed 30 minutes to stabilise.
7) Slowly open the main steam valve CS03 fully and close the bypass
valve CS04.
8) Monitor the condensate level in the local level gauge.
9) In the CCR, set the flow control for the vaporiser to the ON position on
the IAS, select MAN mode and ensure that the set point is for zero flow.
Control
Valve
TT
2
FI
1
L
2
L/R
Position
ZI
2
L/R
Position
L
1
ZI
1
Common
Trip
Ext.
Trip
XA
HH
XA
LAHH
LAH
TALL
TAL
4
L/R
Position
L/R
Position
L
2
L
1
A
PI
1
XA
5
LAHH
1
H2
TT
4
C1
H1
Key
LNG Vapour Line
C2
Local Panel
PIT
2
L
Common
Trip
Alarm
TI
2
TI
4.2
Flow Control
Signal 4-20mA
4-20mA
TIC
2
4-20mA
PV
PI
2
4-20mA
Control Cabinet
Safe Area
Set Point
HIC
2
TI
2
PIPIT
I.A.S. System in
CCC Cargo Cont. Rm
Safe Area
Desuperheated
Steam Line
PI
3
TI
HS
5
ESD
Condensate Line
LSH
1
Mist
Separator
TE
CG-556
CS-04
Gas Outlet
Vent
CS-03
Electrical Signal
Steam
Inlet
FI
C2
Local Equipment
Hazardous Area
PCV
2
SV
2
CS-503
FC
TCV
2
TI
1
Liquid Gas
Inlet
Liquid Line
CS-507
ZT
2
ZI
2
LSHH
4
CS-502
LI
4
LSH
4
FC
TSLL
4
Automatic Trip
Alarm Circuit
Local Instrument
TE
4
PCV
1
FCV
1
Z1
1
Z1
1
Instrument on
Local Panel
Instrument Air
SV
1
C1
IAS Function
CS-12
L/R
ZS
2
H2
HS
2
HIC
2
Local Panel
I/P
HY
2
4-20mA
L/R
ZS
1
H1
HS
1
HIC
1
PCV
6
I/P
HY
1
4-20mA
PI
6
CS-10
CS-11
Condensate
Drain
L/R
Local / Remote
FC
Fail Close
4 - 53
11) In MAN mode, crack open the flow control valve and admit LNG to the
vaporiser. Physically monitor all the vaporiser flanges and joints for any
signs of leakage.
12) As soon as a flow has been established, set the correct value for the
desired operation on the temperature controller; -140C for volumetric
replacement during cargo discharge, or +20C for cargo tank purging
after refit and LN2 vaporization for insulation spaces or tank purging
duties.
13) Gradually increase the flow rate up to the desired value and change the
mode to AUTO.
14) Monitor the condensate level until full gas flow has been achieved on
the vaporiser to ensure stable operations.
15) Continue to monitor the vaporiser for leaks, the vapour outlet
temperature, the condensate level and the drains temperature throughout
the operation.
CAUTION
Thorough checks around the LNG vaporiser and associated flange connections
must be conducted during the operation.
On completion of the operation.
1) Close the manually operated liquid line isolating valve CS505.
2) Switch the flow and temperature controllers to manual and manually
open the valves (flow control valve CS501, temperature control valve
CS510) to allow any remaining LNG to vaporize naturally.
3) When the heater outlet temperature is well above 0C and there is no
indication of any frosting anywhere on the heater, shut the main steam
valve.
4) Open the steam side shell vent valve.
5) When steam stops issuing from the vent open the condensate drain
valve and shut the inlet valve to the drain trap.
6) When the heater has cooled down to ambient temperature, shut the
vapour outlet valve CG501 and secure the rest of the system as required.
4 - 54
Control
Valve
TT
2
FI
1
L
2
L/R
Position
ZI
2
L/R
Position
L
1
ZI
1
Common
Trip
Ext.
Trip
XA
HH
XA
LAHH
LAH
TALL
TAL
4
L/R
Position
L/R
Position
L
2
L
1
A
PI
1
XA
5
LAHH
1
H2
TT
4
C1
H1
Key
LNG Vapour Line
C2
Local Panel
PIT
2
L
Common
Trip
Alarm
TI
2
TI
4.2
Flow Control
Signal 4-20mA
4-20mA
TIC
2
4-20mA
PV
PI
2
4-20mA
Control Cabinet
Safe Area
Set Point
HIC
2
TI
2
PIPIT
I.A.S. System in
CCC Cargo Cont. Rm
Safe Area
Desuperheated
Steam Line
PI
3
TI
HS
5
ESD
Condensate Line
LSH
1
Mist
Separator
TE
CG-553
CS-02
Gas Outlet
Vent
CS-01
Electrical Signal
Steam
Inlet
FI
C2
Local Equipment
Hazardous Area
PCV
2
SV
2
CS-510
FC
TCV
2
TI
1
Liquid Gas
Inlet
Liquid Line
CS-508
ZT
2
ZI
2
LSHH
4
CS-509
LI
4
LSH
4
FC
TSLL
4
Automatic Trip
Alarm Circuit
Local Instrument
TE
4
PCV
1
FCV
1
Z1
1
Z1
1
Instrument on
Local Panel
Instrument Air
SV
1
C1
IAS Function
CS-09
L/R
ZS
2
H2
HS
2
HIC
2
Local Panel
I/P
HY
2
4-20mA
L/R
ZS
1
H1
HS
1
HIC
1
PCV
6
I/P
HY
1
4-20mA
PI
6
CS-07
CS-08
Condensate
Drain
L/R
Local / Remote
FC
Fail Close
4 - 55
Alarms are provided for outlet gas temperature and for condensate water high
level and low temperature.
1. General
The Forcing Vaporiser is used for vaporizing LNG liquid to provide gas for
burning in the boilers to supplement the natural boil off gas. Both the LNG and
forcing vaporisers are situated in the cargo compressor room.
The forcing vaporiser is used to supplement boil-off gas for fuel gas burning up
to 105% MCR.
The LNG is supplied by a stripping/spray pump. LNG flow is controlled by an
automatic inlet feed valve which receives its signal from the Boiler Gas
Management System.
Specification
Manufacturer:
Model:
Type:
Tube Side
(Process Fluid)
Mass Flow
Cryostar
34-UT-25/21-3.6
BEU
Unit
Operating Case
Forcing
kg/h
7,100
m /h
16
m3/h
4,313
Inlet Temperature
-163
Outlet Temperature
-34
Inlet Pressure
MPa
0.3
Outlet Pressure
kPa
96
Pressure Drop
(Calculated)
kPa
172
Heat Exchange
(Actual)
kW
1,560
Design Pressure
MPa
0.1
-196/+200
Design Temperature
Shell Side
(Saturated
Steam)
Unit
Steam Consumption
kg/h
2,784
Inlet Temperature
179
Outlet Temperature
174 appx.
Inlet Pressure
MPa
0.9
Outlet Pressure
MPa
0.9
Design Pressure
MPa
0.1
+200
Design Temperature
Operating Case
9) In the CCR, set the flow control for the vaporiser to the ON position on
the IAS, select MAN mode and ensure that the set point is for zero flow.
10) Confirm that the spray header is pressurized and then open the manually
operated liquid line isolating valve CS506.
11) In MAN mode, crack open the flow control valve CS504 and admit
LNG to the vaporiser. Physically monitor all the vaporiser flanges and
joints for any signs of leakage.
12) In the CCR, set the controls for the forcing vaporiser on the IAS mimic.
13) When vapour is produced, switch the control for the liquid valve to
remote and automatic.
14) Monitor the condensate level until full gas flow has been achieved on
the vaporiser to ensure stable operations.
15) Continue to monitor the vaporiser for leaks, the vapour outlet
temperature, the condensate level and the drains temperature throughout
the operation.
CAUTION
Thorough checks around the forcing vaporiser and the associated flange
connections must be conducted during operation.
Open the condensate drain valve and the steam side shell vent valve.
3)
Set up the downstream vapour lines for the required operation and
vaporiser outlet valve CG502, to allow for gas expansion during the
warming up stage.
4) Slowly open the vaporiser steam valve bypass CS06 fully to warm
through and vent the vaporiser.
Forcing
5) When all the air has been expelled from the shell, shut the vent valve.
6) When the drains are blowing clear open the drain trap outlet and inlet
valves and shut the drain. The temperatures, pressures and condensate
levels of the heater should be allowed 30 minutes to stabilize.
7) Slowly open the main steam valve CS05 fully and close the bypass
valve CS06.
8) Monitor the condensate level in the local level gauge.
4 - 56
Control
Valve
TT
2
FI
1
L
2
L/R
Position
ZI
2
L/R
Position
L
1
ZI
1
Common
Trip
Ext.
Trip
XA
HH
XA
LAHH
LAH
TALL
TAL
4
L/R
Position
L/R
Position
L
2
L
1
A
PI
1
XA
5
LAHH
1
H2
TT
4
C1
H1
Key
LNG Vapour Line
C2
Local Panel
PIT
2
L
Common
Trip
Alarm
TI
2
TI
4.2
Flow Control
Signal 4-20mA
4-20mA
TIC
2
4-20mA
PV
PI
2
4-20mA
Control Cabinet
Safe Area
Set Point
HIC
2
TI
2
PIPIT
I.A.S. System in
CCC Cargo Cont. Rm
Safe Area
Desuperheated
Steam Line
PI
3
TI
HS
5
ESD
Condensate Line
LSH
1
Mist
Separator
TE
CG-553
CS-02
Gas Outlet
Vent
CS-01
Electrical Signal
Steam
Inlet
FI
C2
Local Equipment
Hazardous Area
PCV
2
SV
2
CS-510
FC
TCV
2
TI
1
Liquid Gas
Inlet
Liquid Line
CS-508
ZT
2
ZI
2
LSHH
4
CS-509
LI
4
LSH
4
FC
TSLL
4
Automatic Trip
Alarm Circuit
Local Instrument
TE
4
PCV
1
FCV
1
Z1
1
Z1
1
Instrument on
Local Panel
Instrument Air
SV
1
C1
IAS Function
CS-09
L/R
ZS
2
H2
HS
2
HIC
2
Local Panel
I/P
HY
2
4-20mA
L/R
ZS
1
H1
HS
1
HIC
1
PCV
6
I/P
HY
1
4-20mA
PI
6
CS-07
CS-08
Condensate
Drain
L/R
Local / Remote
FC
Fail Close
4 - 57
4 - 58
[C.C.C.]
Main Cabinet
[C.C.C.]
CLN100/806UPS
(W800xH2110xD600)
21"
LX-300+
Alarm Printer
Note 4
WS2
Note 4
Note 4
Work Station 1
CTS
21"
Network
Switches
A
Note 4
Note 4
Note 4
OAS 5
(W760xH600xD210)
GLK-100 Units
RCU-Computers
I/O Units
Ex LON Repeaters
UPS
Back-up Battery
Terminal Boards
Alarm Relays
Net Switches
Ethlon Adapters
WS1
Switch
Cabinet
OMICRON
High Level
& Overfill
Alarm System
NL-290
Back-up Display
Term.
Term.
Note 4
Note 9
Note 4
Note 4
HP LaserJet
Receptacle 1
230 VAC. UPS No. 1
Note 5
Note 2
Note 7
Note 5
Note 8
[Safe Area]
[Hazardous Area]
Note 1
Note 1
Note 2
Note 2
Note 2
Mode
Note 6
10mm
Note 6
Vapour Pressure
Transmitter
GT402
Trim/List Signal
Note 5
Passage-way
Mode
Note 2
(Tank 3)
(Tank 2)
(Tank 3)
Note 1
(Tank 2) Note 1
Radar
GLA-100/5
(Tank 3)
(Tank 2)
Passage-way
Mode
Vapour Pressure
Transmitter
GT402
10mm
(Tank 2)
Stand
Pipe
Sections
ESD/LAH
Sensor
2x5 pcs
Temperature
Sensors
Note 2
Note 2
Radar
GLA-100/5
Stand
Pipe
Sections
ESD/LAH
Sensor
2x5 pcs
Temperature
Sensors
(Tank 3)
Mode
Note 6
Note 2
Note 2
Note 6
Receptacle 2
Note 3
Cables :
(Minimum Cable Requirement)
Note 1 : 5 pair twisted 0.5mm2 w/screen
Note 2 : 2 par 0.5mm2 w/screen
Note 3 : 1 pair 0.5mm2 w/screen
Note 4 : Cat. 7 Ethernet Cable
Note 5 : 3x1.5mm2
Note 6 : 10 pair 0.5mm2 w/screen
Note 7 : 16 pair 0.5mm2 w/screen
Note 8 : 2x2.5mm2
Note 9 : 10 pair 0.75mm2 w/screen
4 - 59
The gas storage tank is designed to form a closed thermal system for the cargo,
and is therefore kept close to the state of saturation. Gas evaporation under this
condition is fairly smooth, and a gradual boil-off process as thermal heating of
the tank content is very slow.
GLA-100
5.0 mm
glpx 0340 (no.1 Tank)
glpx 0341 (no.2 Tank)
glpx 0342 (no.3 Tank)
glpx 0342 (no.3 Tank)
p
Com
e ns
atio
High gas vapour density, the mixture of gases and their partial pressures, and the
Radar Stand Pipe (RSP) will influence the propagation speed of the microwave
signals. All these factors (which are normally not known in detail) have to be
compensated for in order to give exact distance measurement.
1. Measurement Fundamentals
(See Illustration 4.8.1a)
Ech
o
The GL-100 Level Gauge consists of the GLA-100/5 Radar Tank Gauge (RTG),
which contains the transmitter and receiver electronics, connected to the GLK100 Signal Processing Unit (SPU).
A swept 10GHz signal is transmitted toward the liquid, which reflects some of
the energy back. By measuring the phase difference (time delay) between the
transmitted and received signal the distance to the liquid (i.e. ullage) is found.
The raw data will appear as a superposition of signals with different frequencies,
one frequency for each reflection in the tank. By applying Fast Fourier
Transforms (FFT) of the signal a spectrum analysis of the raw data is performed.
M42-00000.180
stre
ngth
(1/R
)
Distance
45m
The echo strength in a free space application is reduced by a factor related to 1/R.
Kongsberg Maritime's patented detection method maintains the echo strength to
be almost constant in the entire measuring range of the radar. This eases the
setting of signal threshold.
The AutroCAL level gauge for LNG applications is based on the Radar Tank
Gauge (RTG) disposed on top of a circular Radar Stand Pipe (RSP). The Radar
Stand Pipe (RSP) extends vertically from the tank top down to the tank bottom,
and is an integral part of the level gauge instrument AutroCAL.
n
atio
ens
p
m
Co
When the SPU has processed the signal and derived the liquid ullage the value is
averaged. The averaging algorithm is exponential and the weighing can be
changed in the SPU configuration. The averaging is incorporated in order to
smooth the ullage reading.
By applying data stored in the SPU, the level and volume can be calculated.
Additionally the values can be compensated for the influence of trim and list.
Echo
M42-00000.180
Radar signals that propagate in a Radar Stand Pipe (RSP) are retarded. The
propagation speed is determined by the interior diameter of the pipe, the
operational frequency of the radar, and the dielectric properties retained by the
gas and vapour constituents (molecular mixture) of the tank atmosphere. The
relative propagation speed in the still-pipe, as compared with signal propagation
in an open and empty space, can be calculated from the equation,
stren
gth
Distance
The pipes used as a Radar Stand Pipe (RSP) is accurately measured and the
distances are configured in to the Signal Processing Unit (SPU). AutroCAL is
applied at each measurement. An additional feature of AutroCAL is for the
surveyor to use the signature readouts, at any time, to verify the accuracy of the
system. The readout can be performed without interrupting the cargo handling.
45m
Vr =
When applied in a still pipe, the pipe will act as a wave-guide for the radar signal
and there will be no free space losses.
However, ohmic losses will reduce the echo strength. These losses are equally
compensated by Kongsberg Maritime's patented detection method.
1 .
r
r - ( fc )
(1)
4 - 60
fc =
c
p. a
(2)
- The ratio between the frequency of operation and cut-off frequency is subject
to change, due to thermal changes of the pipe diameter, and/or thermal drift
of the radar frequency. Such changes will alter the propagation speed of the
radar signal, see eq. (1).
GL0
In the general case, most of these changes have to be considered predictable only
in qualitative terms, but beyond control in quantitative terms.
The distance to each echo produced by the PTFE plates down the pipe, and the
distance to the cargo echo, are all recorded simultaneously for each measurement.
As the location of the active reference marker in use is known, a self-calibration
of the measured distance to the liquid reflection is made possible. This selfcalibration capability allows the radar instrument to perform reliable and
accurate measurements of liquid level.
The system will automatically identify the liquid echo and the closest reference
marker echo, and the latter will be selected as the active reference.
Special super resolution algorithms are implemented in order to resolve the two
echoes, thus allowing the level gauge to monitor the true level of the liquid.
SelSmech
Active Reference
Liquid Level
Ullageel
This means that the propagation speed of the radar signal may change without
control, and exceed the limits defined to meet the accuracy requirements claimed
for the radar level gauge instrument. If the speed is not known with required
accuracy, due to changes in the relevant environmental parameters, the speed has
to be measured. Means to measure the propagation speed has therefore been
implemented in the Radar Stand Pipe (RSP).
Ullage and level calculations
The GL100 level gauging system has multi-target capability, and a complete
reflection picture (all echoes) is available for analysis for every measurement.
As the liquid is raised to a level close to the location of a marker, the echoes
from the marker and the liquid will interfere.
- Gas and vapour mixture and density are both subject to changes, from which
follows that the dielectric properties of the gas and vapour confined within
the still-pipe may change. From this observation follows that the propagation
speed of the radar signal is subject to change, as is evident from eq. (1).
Exact measurements of distance by a radar instrument rely on good control of the
propagation speed of the radar signal. From the reasoning above follows that
temperature, pressure, and composition and density of the gas and vapour in the
tank vapour space is all subject to changes.
During operation the PTFE plates give rise to radar echoes. The locations of the
plates are known, thus serving as reference markers for distance down the RSP.
Below a Reflection Diagram is shown the diagram has been recorded from a
vessel carrying LNG. The pipe contains five PTFE plates, or disks. The locations
of the plates along the pipe are indicated above the respective echoes.
Additionally a typical reflection from LNG is also indicated (LNG cargo will
typically be some 5 to 8 dB stronger than the disks).
The last large peak represents the bottom, which is visible through the liquid due
to the transparency of the LNG.
distHb_m
Tank Bottom
4 - 61
Each RSP is made of several pipe sections. The physical length of each pipe
section is carefully measured at 20 C. As for pipe examination, selection and
final approval KM has implemented a very strict regime to ensure the highest
possible quality of the AutroCAL instrument.
The MIL has been set to 70 mm (datum level) above the bottom.
Below MIL the level of the liquid can not be indicated.
The temperature specification for the tank is -160 to +80, due to the
temperature influence to the Radar Stand Pipe (RSP) the safety margin between
the EOP and the membrane is set to 60 to 70 mm at 20C. When the tank is
cooled down or cargo is loaded the vapour temperature will typically be -135 C
to -155 C. The Radar Stand Pipe (RSP) will then subtract (assuming AISI 316
steel) and the level to EOP will increase to 140 mm. Consequently the error will
typically increase to 20 mm at Minimum Indicated Level (MIL); the accuracy
will be retained at EOP.
The system incorporates the level and the bottom zone sensor, and a configurable
MIL and temperature limit. Even if the level is below MIL this level will be
indicated when the bottom temperature is lower than the temperature limit
(indicating liquid at the temperature sensor). When the temperature increases
above the limit zero level will be indicated.
Radar resolution and Super resolution
c) The final step in the process is qualification of the pipe assembly (RSP) in
regard of cross-polar wave propagation. The qualification requirement
allows 6.3 % (12 dB) of the energy to be transferred to cross-polar waves.
The requirement applies regardless the length of the assembled Radar Stand
Pipe (RSP).
Transfer of energy to the cross-polar wave means that the copular wave loses
energy. As the loss of energy is the same both ways (down and up) in the pipe,
we conclude that the total transfer of energy to the cross-polar wave never
exceeds a tiny 10log10(100%/(100% 26.3%)) = 0.6 dB.
The pipe length data form the basis for the self-calibrating feature of the radar
instrument, and will guarantee that measurement accuracy is maintained during
operations.
The Radar Stand Pipe (RSP) sections are joined together utilizing specially
designed mating flanges. A perforated Teflon (PTFE) plate is mounted inside the
pipe at each flange joint. Based on the measurements of the pipe section lengths
at the factory, the exact location of each of the PTFE plates along the pipe is
known at 20 C.
A higher bandwidth enables the radar to resolve two closely spaced targets.
Alternatively, given a limited bandwidth, super resolution can resolve the two
pulses.
a) The stability of the liquid surface below EOP (surface disturbance caused
by the pumps, etc).
b) The possibilities for the radar to resolve two reflections with the super
resolution procedure given the high relative strength of the bottom
reflection to the liquid reflection.
c) Below EOP the liquid will be outside the pipe. Outside the pipe the radar
wave will be in free space. This will influence the super resolution
capabilities.
4 - 62
PT100
0.2(-165~-145), 0.3(-145~-120,
1.5 (-120~+80)
1508,1509,1510,1511,1512,1513,1514,1515,1516,
1517,1518,1519,1520,1521,1522,1523,1524,1525,
1526,1527,1528,1529,1530,1531,1532,1532,1533,
1534,1535,1536,1537,1538,1539,1540,1541,1541,
1542,1543,1544,1545,1546,1547,1548,1549,1551,
1551,1552
Close to the bottom of the LNG tank there will be two targets present. The first
will be the LNG liquid. The second target will be the reflection from the bottom
which is visible due to the transparency of the liquid. This has been illustrated in
Figure 7.
GT402/LNG
1 F.S
4444,4445,4446,4450,4453
4 - 63
GT-402/LNG
One GT402/LNG Pressure Transmitter is installed on each tank to measure the
gas vapour pressure. The transmitter will be installed on top of the tank and
only the ceramic diaphragm will be exposed to the tank atmosphere. Fastening
arrangement for the transmitter can be adapted to the actual installation.
Cabling for the pressure transmitters can either be via the temperature sensor
cabinet, or via the connection box for the radar sensor.
Main Menu
Click on the CTS and the picture that appears on the screen will be as below.
The Operator Stations are the main presentation unit in the system, and are based
upon the Windows NT operating system with redundant high-speed data
communication between the various computers and microprocessors in the
system. Dedicated process displays are created in conjunction with the customer
to provide the best operational environment.
The Operator Stations are normally situated in the Cargo Control Room, where
the operator can monitor the data and control all essential operating parameters.
A number of Operator Stations can be connected in a network to provide several
operator consoles at different locations onboard. Alarms are handled
continuously in the background to ensure that the operator is immediately alerted
if any alarm limits are exceeded. Failures that may occur in the system are
immediately reported on the screen. Reports on failures and alarms, as well as
history/trend reports on level, volume, vapour pressure and temperature are
logged and stored and can be printed out at any time. Customised reports are also
available.
The system is operated with a track-ball connected to the Operator Station. From
the Main Menu, the selection of each sub-menu can be done. Pop-up windows
for parameter values and alarm limit settings are displayed on the screen.
1) Main functions of the Operator Station:
- Handling of alarms and failures
- Configuration of the system
- Storage of measured parameter values
- Calculation using measured parameter values
- Logging of History/Trend
- Generation/Printout of customised CTS reports
- Graphic presentation of all relevant data
2) Data available on the screen if implemented:
- Cargo tank name
- Cargo tank liquid level
- Cargo tank liquid volumes (total, individual and group)
- Cargo tank temperature (average liquid, average vapour, individual)
- Cargo tank vapour pressure
- Trim, List and Draft
- ATM (atmospheric pressure)
- Miscellaneous level, temperature and pressure readings
- Alarms
- Faults/Diagnosis
- Trend curves
- Clock
- Configuration data
- Parameter settings
- Miscellaneous Reports
The picture gives the operator an overview of all the Cargo tanks. By licking
on the Cargo tank Name button, the following display will appear on the screen:
Detailed information of the tank parameter is displayed. Moving from one tank
to another is easily done by Clicking on the tank name in the upper right corner.
Clicking on the CTS activity button a new pop up menu will appear on the
screen.
CTS activity, details of all the parameter of the chosen tank is displayed. In this
display the buttons START LOADING and UNLOADING will activate the
logging of the system.
To simplify the instruction the term click on the function is used as a short
form for point on the function and click with the left mouse and trackball
button.
4 - 64
In this menu different system parameter can be selected and changed. The system
also allows the user to enter manual values for some parameters that will be used
instead of automatic read values. If TRIM and LIST is selected the following
picture will appear.
Manually values for TRIM and LIST can be inserted and used in the system.
First the sensor must be reset, and then new offset can be set and afterwards
execute the setting.
Returning back to the MAIN MENU click on the SET-UP CARGO the
display will be as follow:
Selecting the CARGO TANKS the below display will come on the screen.
Changing of ALARM limits in the system can be done in this display.
The operator has the possibility to set-up groups of tanks that he wants
information from. One tank can be displayed in different groups if selected.
Click on the CARGO TANK DETAILS in the configuration set up menu the
following display will show. This picture gives information of radar parameter
setting.
4 - 65
Click on the group name of which group you want to set-up. Click on the
tank you want to appear in selected group and then the tank name will be
displayed in the group box. When finish Click on the CARGO GROUPS
button then next display is shown on the screen.
The system also support trending of the parameters, trends can be configured by
the operator and viewed in the trend window.
4 - 66
4 - 67
1. General
Range:
Accuracy:
Serial Number:
0-44m(145ft) standard
0-54m(164ft) extended
7.5mm(gauging LNG over 45m range using 255mm
diameter pan float in a 12 Stillwell)
16652-1,16652-2,16652-3,16652-4
The Whessoe float level measurement system is of conventional tanker type, but
uses an Invar tape to compensate for temperature variations.
A gauge head, containing a mechanical indicator, an invar tape tensioned by a
negator spring and a 12 diameter PV float attached to the lower end of the tape,
is fitted to each liquid dome.
Two guide wires for the float are fixed at the lower ends to an anchor bar 130mm
above the tank bottom, which is secured to the trellis structure base plate. The
sinkage of the float in LNG is 15mm and the minimum level which can be read
from the gauge is 145mm.
CAUTION
To reduce the risk of tape failure and wear on the gauging mechanism, the
floats should be fully stowed at all times, except when taking a sounding.
Care should be taken when stowing the float as excessive tension may cause
tape breakage. It is possible for a failed tape to foul the capacitance column,
resulting in the loss of gauging facilities for that tank.
To obtain the liquid level, the float is released from its stowage position using
the release lever, and allowed to descend freely to the liquid surface. The tank
sounding may then be read from the meter. The Whessoe gauges are checked
against the Kongsberg CTS during each alternate loading.
2. Description
3304 Liquid Level Gauge
The 3304 Liquefied Gas marine liquid level gauge is a rugged mechanical
system of accurately and continuously measuring liquid levels in the refrigerated
tanks of liquefied gas carriers. The gauge can operate in tanks up to 54m deep
and at temperatures as low as -200C. The gauge is entirely mechanical in
operation and does not require any power to provide a constant local readout.
The main components are a float, invar or stainless steel measuring tape, counter
mechanism, tape storage drum, and a negator spring. The gauge is float actuated,
and employs a Tensator spring as a counter-balancing mechanism.
This maintains a constant tape tension at the float so that float immersion is not
affected by the length/weight of the tape throughout the measuring range.
The accurately perforated tape transmits float movement to the sprocket wheel,
which drives to the counter mechanism. This transmits via a magnetic coupling
across a solid barrier flange which completely isolates the counter chamber from
the tank atmosphere.
The system is connected using Field Bus RS485 intrinsically safe technology
offering the advantage that it can be connected in any one loop with only 1 cable
returning to the cargo control room.
2) Put the crank handle in the STORED position, ie, with the handle towards
the gauge cover.
3) Put the spring-loaded automatic float lock-up and the datum plunger up to
release the float and allow it to descend at a controlled rate to the liquid
level.
To Return the Gauge to the Stored Position
1) Put the crank to the CRANKING position, i.e., with the handle outwards.
NOTE
The cranking handle is designed to drive in one direction only and is spring
loaded by a cam arrangement so that it is not in motion during normal gauging
2) Carefully raise the float by turning the crank slowly in a counter clockwise
direction, as indicated by the arrow on the main cover inspection plate.
3) Watch the read out counter, which will indicate when the float nears the top.
When resistance is felt by the float touching the cushion spring, continue
cranking until the plunger is seated and the automatic float lock-up and
datum plunger spring fully inward, securing the float.
The wiring cable between transmitter and receiver or between transmitter and
transmitter must conform to the intrinsically safe standard.
4 - 68
AFT
c
Lo
R
al
do
ea
ind
tW
ow
Inspection Plate
Stating Operation of
Crank Handle
Inspection Chamber
Cylindrical Float
Tank Top
4 - 69
The ship is provided with a fixed Trim-List Indicator system for the Custody
Transfer System.
Trim Indicator
List Indicator
1. Specification
Maker:
Type:
Range:
Accuracy:
Output:
Inclination
Detector
The readings should be periodically checked against the draft marks in calm
weather alongside periodically.
Note
The trim and list measurements in the IAS are derived from the panel, and not
this instrument.
Fwd
220V AC
Port
Stbd
Aft
4 - 70
To Safety Chamber
N2 Generator
(125 Nm3/h x 2 Sets)
Circ. Span
TAH
Oil
Separator
TIC
After
Cooler
Water
Separator
TE
V-8.81
PIC
AY
TDAL
TAH
TS
TAH
TIC
PIAL
MT
MIAH
PT
Test
FI
PT
Membrane
Separator
TE
Electric
Heater
Oil Cooler
FT
FE
V-8.88
Cooling
Water Out
Cooling
Water In
Circ. Span
TAH
Oil
Separator
TIC
After
Cooler
Water
Separator
PIC
AY
TE
V-8.85
TDAL
TAH
TS
TAH
TIC
PIAL
MIAH
PT
Test
MT
FI
PT
Membrane
Separator
TE
Electric
Heater
Oil Cooler
FT
FE
Cooling
Water Out
Cooling
Water In
PIAHL
IAS
PX PI
TI
IAS
TX
PIAHL PIAHL
IAS IAS
32V
Sett.
0.55 MPa
24V
To Boiler Burner
Key
Nitrogen Line
25V
29V
27V
To Cargo System
4 - 71
PI
PX
N2 Buffer Tank
(30 m3)
26V
PCV-4B
Sett. 0.5 MPa
31V
Drain Line
28V
PX PI
PCV-4A
Sett. 0.5 MPa
V-8.61
Sett.
1.3 MPa
ORI-1
PIAHL
IAS
23V
V-8.62
34V
PS
On
P.G.B
PI
To Safety
Chamber
30V
PAL
IAS
33V
Separately Led
To Bilge Well
FI
IAS
PX
V-8.63
V-8.65
Main
Stand-by
STOP
600
600
START
400
350
Air Products As
Operating principle:
Membrane Separation of
Nitrogen from Air
Ambient temperature:
Max. 95 %
3
Max. capacity:
125 Nm /h x 2 sets
N2 Purity (N2+Argon):
97 vol %
-65C
N2 Discharge
design):
pressure
(Process
600 kPa
(At generator
inlet)
Outlet Temperature:
Max. 50 C
0%
outlet/tank
3. Process Description
The compressed air supply to the units is fed from the E/R control/service air
system. Compressed air with no liquid slugs is fed to the Nitrogen generator and
passes through a filter package which will protect the membranes from any
harmful particles, oil, and water condensate.
The air then passes through an electric heater which will heat the air temperature
by min.8 C to 50 C, which is the optimal temperature to reach the design
capacity. The heater is controlled by a temperature controller receiving signal
from a temperature transmitter located downstream of the heater.
A temperature switch in the heater and in the piping will protect the heater and
the membrane from over-temperature. Membranes can withstand temperatures
up to 85~90 C without being damaged. To avoid any potential overheating,
heater shut down set point is 70 C.
The heated air is now fed via a manifold to each individual membrane separator
and the product exiting the membrane is nitrogen.
In order to maintain a constant process and hence constant flow across the
membranes, the nitrogen passes a flow control valves. Regulation of the flow is
done by PLC-software through signals from a pressure transmitter installed
upstream and a flow transmitter downstream the membranes. Fine tuning is done
through signals from the oxygen analyzer. Parameters in PLC-software can be
set to limit the max capacity to design capacity.
Since the inlet pressure defines the nitrogen flow necessary to meet a set O2 level,
a mathematical function in the PLC will make the Nitrogen Generator
automatically producing on-space nitrogen at varying inlet pressures.
Also the fine-tuning done through signals from the oxygen analyzer, will make
the Nitrogen Generator to supply on-spec nitrogen short time after start-up.
The Nitrogen Generator is equipped with an oxygen analyzer that will
continuously monitor the oxygen content in the product nitrogen.
Should the oxygen content for some reason rise above the design value %, an
alarm will be initiated. If the oxygen content continues to rise, a second alarm,
oxygen content high high will be initiated and close the delivery valve and open
the dump valve. When the oxygen content has fallen to limits within
specification, these valves will reverse and the system will supply nitrogen again.
Molecular weight
28.016
-196 C
0.81
0.97
695
Flammable limits
Dew point of 100% pure N2
None
Below -80 C
2) Chemical Properties
Nitrogen is considered as an inert gas; it is non flammable and without
chemical affinity. However, at high temperatures, it can be combined with
other gases and metals.
WARNING
Due to the absence or to the very low content of oxygen, nitrogen is an
asphyxiant.
At liquid state, its low temperature will damage living tissue and any spillage
of liquid nitrogen on the ships deck will result in failure as for LNG.
4 - 72
M0 CONTROL
M1-N2 Generator
M2 Distribution
Operation of block
M1 N2-Generator
Operation of block
MO Control
No
Operation of block
M2 Distribution
No
Start signal is
present?
No
Start signal is
present?
Start signal is
present?
Yes
Yes
Yes
No
Yes
N2 Buffer Tank
Pressure Low?
SD-1 Signal
active?
Wait 2 minutes
Yes
No
Run level=1?
No
Start M1
N2-Generator
Yes
M1 N2Generator
Wait 5 seconds
No
Alarm AAH
active?
Yes
Run level=2?
No
Start M2
Distribution
No
Compressor
control active?
N2 Buffer Tank
Pressure High?
Yes
- Open N2 delivery valve
- Close atm. valve
- Start Compressor
Set RUN Level=2
No
Yes
- Close N2 delivery valve
- Open atm. valve
- Close Air Inlet Valve of
stop compressor.
- Power down heater.
No
M2
Distribution
Stop signal
present?
Yes
- Close N2 delivery valve
- Open atm. valve
- Close Air Inlet Valve of
stop compressor.
- Power down heater.
No
Yes
Alarm PAL
active?
Compressor Run
signal active?
Yes
No
END
Set RUN Level=1
4 - 73
Blank Page
4 - 74
Purge To Outside
(To Funnel Top)
To Pneu.
Equipment
AS
1506
1501 1502
From Control
Air System
1505
PS L
1504
1503
PI
2112
2111
2224
M 2223
To Atm.
Drain Tank
1606
1605 1604 1603
PC
1624
1625
1632
1633
4304 4315
4302
4302
5026
5459
5091
S
5033
5031
Drain
LS
24
LS
Control Air
2416
1631
Drain/Decompr.
(Don't need to be connected
for maintenance only)
To Oily
Bilge Tank
LS
19
9V
(F)
5043
5034
Steam
Heater
5008
5101
5113
5104
LS
S
5053
5413 5413
H
TX TX
L
LS
LS
S
Air
Drain
5036
tro
l
Cooling
Water Out
Cooling
Water In
5403
5107
2321
4303
2323
1634
PS L
LS
LS
Ambient
Air
Fan
1635
1621 1602
1627
1601
1623
5404
5071
PI
5081
22V
Control Air
Dewpoint
Analyser
Tag No. 7100
TI
PS
L
5083
5083
5061
PI
Blower 1
1626
PI
PI
2318
Co
n
1622
PI
Line
Electrical
Heater 5411
5102 5103
LS
2226
Drain
5225
H
TX
Vent To I.G
Sample
Purge Line
4314
LS
H
5051
2222
2227 2229
Drain
5401 Sereen
5041
2221
LS
2322
LS
H
25
Ambient
Air
2228
M
Blower 2
2324
24
M 2203
2315
2204
2206
2410
2316
2207 2209
LS
DPX
2415
2202
PS
H
ion Cha
mber
2314
LS
2015
2320 2317
2201
2011 PS
L
D-20V
Ambient
Air
2010 PS
H
2014
2313
2051
2208
M
Combust
2013
2012 PI
2319
Control Air
2054
2003
Emergency
Blow-off
(Air)
5405
LS
Sample Gas
To O2 Analyser
Demister
Vessel
2303
2304
Main B
urner
LS
5021
5108
Chilled
Water
Out
LS
5011
5008
Chilled
Water
In
5023
5407
Drain
5062
XZA
L
TI
4414
Washing
Cooling
Tower
2021
PI
1637
Pilot Bu
rner
(F)
5028
S
5111 5112
2040
LS
Drain
S
5018
5013
4415
PI
5430
5437
5406
TI 4404
5301 5302
Instrument
Air
5008
H
PI 4406
5303 5305
PI PZA
L
LS
Vent
Cooler
5072
2309
LS
5007
LS
3V
2041
2013
2344
2042
To F.O
Drain Tank
2132
2037 2038
PI
2114
2310
Drain
5016
1506
Drain
H
TS 4407 Signal Lamps Minicboard Generator Unit
H
4411
PS 4410
121V
1507
2032
1509
2V
2103
To I.G.G.
M.D.O
Service Tank
5056
TX
5458
2105
1012
5440
5057
TX
5431
1509
5450
5453
S
5305
1051 1052
5442
LS
5456
1005
LS
5304
1001 1002
1054
PI
5657
1004
From I.G.G.
M.D.O
Service Tank
1053
PS L
1058
1055
1003
PI
1013
5452
5436
5416
TZA
LS
LS
To Oily
Bilge Tank
Key
2V
(A)
Steam Line
Diesel Oil Line
Sea Water Line
Inert Gas Line
1V
4 - 75
The pressure inside the plant is maintained constant to ensure a stable flame
during operation, independent of pressure fluctuations in the piping system. This
is done via a pressure control valve at the end of the installation.
1. General
The inert gas/dry air plant is located in a compartment in the engine room. It
produces inert gas or dry air for the inerting, purging and aerating of the cargo
tanks and associated piping systems prior to and after refits or other inspection
periods. The operating principle is based on the combustion of a low sulphur fuel
and the cleaning and drying of the exhaust gases. The inert gas/dry air plant is
locally operated. The connection to the cargo system is made through two nonreturn valves and a blind flange valve, which is normally in the closed position.
3. Blower Unit
Specification
Manufacturer:
Type:
Capacity:
Discharge pressure:
Dew point:
The fuel oil system is atomised in two steps. First a conventional nozzle sprays
the oil , supplied under pressure to the burner. Then the oil spray is subjected to a
tangential impulse flow of combustion air, which added to the mainly axially
orientated impulse flow of the oil spray itself, results in an ultra-fine dispersion
of the requid.
The tangential impulse flow of combustion air is created by supplying the air
through slots in an atomisng ring, which is fitted at the end of the burner gun.
The combustion process guarantees that absolutely no soot will be produced, not
even at understoichiometric conditions, e.g. during combustion-air shortage,
caused by a lower speed of the combustion air blower, which could occur by
voltage and/or frequency fluctuations in the electrical supply. Soot cannot be
tolerated in the plant, neither in the ships cargo tanks nor in the piping system.
To prevent soot formation, especially on the long run, a stable and well-balanced
combustion process is obligatory.
Temperature:
Tyical gas composition (on dry basis)Oxygen (O2):
Carbon-dioxide (CO2):
Carbon-oxide (CO):
Sulphur-oxides (SOx):
Nitrogen-oxides (NOx):
Nitrogen (N2):
Soot (On Bacharach scale):
2. Working Principle
Inert gas produced by the combustion of oil with air, followed by further
treatments in order to obtain the required quality and properties. The combustion
is a chemical reaction between the hydrocarbon and oxygen, mainly producing
carbon dioxide and water. The water is condensed for the greater part.
The nitrogen of the air leaves the generator unchanged. Some small rest
quantities of carbon monoxide and hydrogen may remain. Thus, the inert gas
produced mainly consists of nitrogen and CO2.
The hot combustion gases are cooled, first indirectly in the combustion chamber
by a seawater cooled jacket. The principal cooling, however, occurs afterwards in
the cooling section.
Because of the intense contact between inert gas and seawater in the cooling
tower, the inert gas temperature is decreased close to the seawater temperature,
while corrosive sulphur oxides are washed out of the inert gas. The cooling /
scrubbing water leaves the generator through the waterseal. At the end of the
cooling section the gas is passed through a demister to separate the water
droplets from the gas stream. Further removal of the water takes place in two
steps. The gas is cooled down in a refrigeration unit first. The bulk of the water
present in the gas is condensed and drained. Then in the first stage, the water is
removed by adsorption in a desiccant dryer. The roots type air blower supplying
the combustion air to the burner achieves the required final pressure of the gas.
The air required for combustion is supplied by means of a blower unit. This unit
is direct driven and mounted on a frame with vibration isolators, coupling-guard,
flexible hose connection, non-return valve, combined filter suction silencer and
discharge silencer.
4. Ultramizing Burner
4 - 76
Purge To Outside
(To Funnel Top)
To Pneu.
Equipment
AS
1506
1501 1502
From Control
Air System
1505
PS L
1504
1503
PI
2112
2111
2224
M 2223
To Atm.
Drain Tank
1606
1605 1604 1603
PC
1624
1625
1632
1633
4304 4315
4302
4302
5026
5459
5091
S
5033
5031
Drain
LS
24
LS
Control Air
2416
1631
Drain/Decompr.
(Don't need to be connected
for maintenance only)
To Oily
Bilge Tank
LS
19
9V
(F)
5043
5034
Steam
Heater
5008
5101
5113
5104
LS
S
5053
5413 5413
H
TX TX
L
LS
LS
S
Air
Drain
5036
tro
l
Cooling
Water Out
Cooling
Water In
5403
5107
2321
4303
2323
1634
PS L
LS
LS
Ambient
Air
Fan
1635
1621 1602
1627
1601
1623
5404
5071
PI
5081
22V
Control Air
Dewpoint
Analyser
Tag No. 7100
TI
PS
L
5083
5083
5061
PI
Blower 1
1626
PI
PI
2318
Co
n
1622
PI
Line
Electrical
Heater 5411
5102 5103
LS
2226
Drain
5225
H
TX
Vent To I.G
Sample
Purge Line
4314
LS
H
5051
2222
2227 2229
Drain
5401 Sereen
5041
2221
LS
2322
LS
H
25
Ambient
Air
2228
M
Blower 2
2324
24
M 2203
2315
2204
2206
2410
2316
2207 2209
LS
DPX
2415
2202
PS
H
ion Cha
mber
2314
LS
2015
2320 2317
2201
2011 PS
L
D-20V
Ambient
Air
2010 PS
H
2014
2313
2051
2208
M
Combust
2013
2012 PI
2319
Control Air
2054
2003
Emergency
Blow-off
(Air)
5405
LS
Sample Gas
To O2 Analyser
Demister
Vessel
2303
2304
Main B
urner
LS
5021
5108
Chilled
Water
Out
LS
5011
5008
Chilled
Water
In
5023
5407
Drain
5062
XZA
L
TI
4414
Washing
Cooling
Tower
2021
PI
1637
Pilot Bu
rner
(F)
5028
S
5111 5112
2040
LS
Drain
S
5018
5013
4415
PI
5430
5437
5406
TI 4404
5301 5302
Instrument
Air
5008
H
PI 4406
5303 5305
PI PZA
L
LS
Vent
Cooler
5072
2309
LS
5007
LS
3V
2041
2013
2344
2042
To F.O
Drain Tank
2132
2037 2038
PI
2114
2310
Drain
5016
1506
Drain
H
TS 4407 Signal Lamps Minicboard Generator Unit
H
4411
PS 4410
121V
1507
2032
1509
2V
2103
To I.G.G.
M.D.O
Service Tank
5056
TX
5458
2105
1012
5440
5057
TX
5431
1509
5450
5453
S
5305
1051 1052
5442
LS
5456
1005
LS
5304
1001 1002
1054
PI
5657
1004
From I.G.G.
M.D.O
Service Tank
1053
PS L
1058
1055
1003
PI
1013
5452
5436
5416
TZA
LS
LS
To Oily
Bilge Tank
Key
2V
(A)
Steam Line
Diesel Oil Line
Sea Water Line
Inert Gas Line
1V
4 - 77
washing/ scrubbing tower will be always alert, also if the generator is totally
switched-off; this alarm is fed by the ships emergency system. (IAS-system).
Level switch (2322) is equipped with two switches for the purpose.
11. Oxygen Content Measurement
- One main separately installed control panel to control the inert gas
generator (combustion and scrubbing) and the whole system. This panel is
giving instructions to the local panels (automatic starting of fuel-oil
pump and blower, checking conditions on refrigeration and dryer site). It
has a mimic diagram in the front. In case of a failure, a sound will be given
and the direct cause of the failure will be indicated in the mimic.
- One starter panel for fuel oil pump, for mounting close to the motor.
- One starter panel for blower, for mounting close to the motor. Both panels
contain a circuit breaker (with manual and automatic disconnection),
thermal overload protection, starter relays and hour counter (ammeter is
optional).
13. Maintenance
Hardly any maintenance is required owing to the application of high-quality
components and the selective choice of materials. Components requiring
maintenance as well as vital parts will be always situated at a readily accessible
place. In the instruction manual you will find a clear description of the
maintenance procedures.
12. Operation
- One control/ starter panel, mounted on the refrigeration skid for fully
independent starting and control of the refrigeration unit, completely
cabled to the components on the skid, with mimic in the front.
- First of all manual valves for utilities (seawater, fuel, etc.) will be opened.
- One control/ starter panel, mounted on the dryer skid for fully independent
starting and control of the dryer unit completely cabled to the components
on the skid, with mimic in the front.
- After flame detection of the main burner and flame stabilization, the pilot
burner is shut down.
- After 4 minutes of purging after start, the delivery line is opened and the
purge line closed, provided that the oxygen content is correct. If not. The
purge line remains open until the correct fuel/ air ratio has been set and the
correct oxygen content is obtained.
- For longer standstill periods it is recommended to purge the seawater
cooling system with fresh water.
- An extra contact is available in the control panel for connection to the
ships main control room to allow for a remote stop of the generator.
4 - 78
Flame
Arrester
DC 24V
DC 4-20mA
Power
Supply
Part
0~100 Vol.%
0~100 % LEL
IR-Type
Detector
Main
AC 220V 60Hz 1
RS422/485(*1)
0~100 Vol.%
0~100 % LEL
IR-Type
Detector
Spare
Sequencer
Alarm
Circuit
EExiad
IR-Type
Detector
DC 24V
& DC 4~20 mA
IS
Barrier
Electric
Parts
Graphic Operation
Panel
RS422/485(*1)
Failure
Cargo Part System
Cargo Mach. Trip System
Engine Room System
Accommodation System
Other Space
DC 4-20mA
Control Panel
(ECR)
IR-Type
Detector
Repeater
Panel
(FCS)
DC 24V
Electric
Parts
Control Part
In Panel (EExiad)
IR-Type
Detector
Rs422/485 (*1)
DC 24V
& DC 4~20 mA
Detector Output
IAS
Control
Panel
(ECR)
DC 4-20mA
Rs422/485 (*1)
Fail. & BZ., PW Cont.
DC 24V
Control
Panel
(ECR)
DC 4-20mA
Rs422/485 (*1)
Detector Output
Control
Panel
(ECR)
DC 4-20mA
Rs422/485 (*1)
Detector Output
System Failure
Cargo Area
(1 Common)
Cargo Mach. Trip
(1 Common)
Engine Room
(1 Common)
Accommodation
(1 Common)
Other Space
(1 Common)
Gas Alarm
Cargo Area
(30 % LEL
20 Point)
(30 VOL %
8 Point)
Cargo Mach. Trip
(30 % LEL
5 Point)
(60 % LEL
5 Point)
Engine Room
(30 % LEL
8 Point)
Accommodation
(30 % LEL
23 Point)
Other Space
(30 % LEL
3 Point)
Analog Data
Cargo Area
(0~100 % LEL)
(0~100 VOL %)
Cargo Mach. Trip
(0~100 % LEL
5 Point)
Engine Room
(0~100 % LEL
8 Point)
Accommodation
(0~100 % LEL
23 Point)
Other Space
(0~100 % LEL
3 Point)
Gas detecting in the panel inside
: 30 % LEL for cutting off power
supply of the panel
(detecting part only)
DC 24V
4 - 79
21
22
23
24
25
3. Engine Room
1) Specification
Model
CP-W
Detecting gas
Methane (CH4)
Detecting principle
Model
FMA-T328UR
26
Detecting range
Detecting gas
Methane (CH4)
27
30% LEL
Detecting principle
28
Detecting range
This device measures the amount of leaking in flammable gas (methane) within
the cargo areas and accommodation of LNG vessels and sounds an alarm if the
value exceeds pre-set limits in order to prevent accidents caused by leaking gas.
This system uses infra-red and catalytic combustion methods for measurement
purposes. The infra-red type (IR type) can be switched automatically or manually
between 28 point gas measurement locations with a single analyzer.
(Automatic switching is performed between 0-100% VOL and 0-100% LEL.)
The infra-red type (IR type) continually measures in detecting panel.
2. Cargo Machinery Trip System
Model
CP-W(IS)
Detecting gas
Methane (CH4)
Detecting principle
10
Detecting range
11
12
13
14
15
16
17
18
19
20
1) Specification
boiler hood 1
boiler hood 2
Gas duct 1
Gas duct 2
The engine room area samples are continuously monitored by its own sampling
analyser.
The gas analysers zero reading should be checked daily and the span checked
weekly.
4. Accommodation System
1) Specification
4 - 80
Model
CP-W
Detecting gas
Methane (CH4)
Detecting principle
Detecting range
30% LEL
Flame
Arrester
DC 24V
DC 4-20mA
Power
Supply
Part
0~100 Vol.%
0~100 % LEL
IR-Type
Detector
Main
AC 220V 60Hz 1
RS422/485(*1)
0~100 Vol.%
0~100 % LEL
IR-Type
Detector
Spare
Sequencer
Alarm
Circuit
EExiad
IR-Type
Detector
DC 24V
& DC 4~20 mA
IS
Barrier
Electric
Parts
Graphic Operation
Panel
RS422/485(*1)
Failure
Cargo Part System
Cargo Mach. Trip System
Engine Room System
Accommodation System
Other Space
DC 4-20mA
Control Panel
(ECR)
IR-Type
Detector
Repeater
Panel
(FCS)
DC 24V
Electric
Parts
Control Part
In Panel (EExiad)
IR-Type
Detector
Rs422/485 (*1)
DC 24V
& DC 4~20 mA
Detector Output
IAS
Control
Panel
(ECR)
DC 4-20mA
Rs422/485 (*1)
Fail. & BZ., PW Cont.
DC 24V
Control
Panel
(ECR)
DC 4-20mA
Rs422/485 (*1)
Detector Output
Control
Panel
(ECR)
DC 4-20mA
Rs422/485 (*1)
Detector Output
System Failure
Cargo Area
(1 Common)
Cargo Mach. Trip
(1 Common)
Engine Room
(1 Common)
Accommodation
(1 Common)
Other Space
(1 Common)
Gas Alarm
Cargo Area
(30 % LEL
20 Point)
(30 VOL %
8 Point)
Cargo Mach. Trip
(30 % LEL
5 Point)
(60 % LEL
5 Point)
Engine Room
(30 % LEL
8 Point)
Accommodation
(30 % LEL
23 Point)
Other Space
(30 % LEL
3 Point)
Analog Data
Cargo Area
(0~100 % LEL)
(0~100 VOL %)
Cargo Mach. Trip
(0~100 % LEL
5 Point)
Engine Room
(0~100 % LEL
8 Point)
Accommodation
(0~100 % LEL
23 Point)
Other Space
(0~100 % LEL
3 Point)
Gas detecting in the panel inside
: 30 % LEL for cutting off power
supply of the panel
(detecting part only)
DC 24V
4 - 81
Monitoring for Cargo Part & Other Space Gas Detection System
1) Specification
Wheel house
CCR
Model
CP-W
Galley
Detecting gas
Methane (CH4)
Detecting principle
Detecting range
10
11
12
13
14
Mess room 1
15
Mess room 2
16
TV room 1
17
TV room 2
18
Lounge 1
19
Lounge 2
20
21
22
23
Central office
Bosun store
4 - 82
[Engine Room]
[Passage Way]
(A) (B)
(A) (B)
(3 sets)
(7 sets)
(1 set)
(1 set)
(2 sets)
(8 sets)
(1 set)
(5 sets)
ESD
Block
(2 sets)
(9 sets)
ESD
Block
25A
(P)
25A
(P)
(P)
FL-25A
3 Units
25A
(R)
25A
(R)
25A
(P)
25A
(R)
25A
(R)
10 Units
25A
(P)
25A
(P)
25A
(R)
FL-25A
(P)
FL-25A
(R)
25A
(R)
11 Units
25A
(P)
25A
(P)
25A
(R)
(R)
FL-25A
(R)
25A
25A Stop Valve
25A
(P)
Accumulator Stand
(APCHHI1728C)
25A
(P)
- Accumulator :
14 sets (60 l)
25A
(R)
25A
(P)
25A
(R)
25A
(R)
25A
(P)
25A
(P)
25A
(R)
(P)
25A
5 Units ESDV
10 Units
(R)
25A
(R)
25A
(P)
FL-25A
Accumulator Stand
(APCHHI1728B)
: Opening Valve
ESD
Block
- Accumulator :
3 sets (60 l)
(2 sets)
(8 sets)
4 - 83
(5 sets)
: Open/Shut Valve
10 Units
ESD
Block
(2 sets)
: ESD Valve
(8 sets)
.
3. Location of Cabinets
1. General Specification
Hydraulic Power Pack
Maker
Accumulators
20
All remotely operated valves are piston operated except for the liquid dome and
the spray header isolating valves, which are vane type actuators.
The supply oil is distributed to 6 solenoid valve boxes situated in the side
passageway (port and starboard) and 1 in the cargo compressor room.
Each cargo tank, manifold area, cargo compressor room and the master BOG
station has its respective solenoid valve box as follows:
Description
No.1 Solenoid valve
box
trunk deck
The ship is equipped with two hydraulic power unit for cargo & ballast valve
control and each power unit is assembled with 3 units of vane-type hydraulic
pumps.
Opening
CG701
CL100, 101, 102, 103, 107
box
CG703
cargo manifold
No.5 Solenoid valve
Stand-by pump acts automatically for helping start when hydraulic power in
reduced to 10 MPa during operation of hydraulic power unit.
box
No.3 cargo tank
Setting Value
13.7 MPa
13.5 MPa
Unloading pressure
13.0 MPa
Loading pressure
11.0 MPa
10.0 MPa
9.0 MPa
ESDS-acting pressure
8.5 MPa
9.5 MPa
6.5 MPa
1) The oil hydraulic circuit should be by-passed from Hydraulic Power Unit,
Control Box and Hydraulic Oil Cylinder.
( Flushing works for above unit, and box were finished completely in
maker factory.)
2) Hydraulic oil pump for flushing should be prepared filter for suction side
(80 mesh) and return oil (300mesh) to be prepared.
CS207, 208
CG001
5) Re-assemble the by-pass piping with care, so as the obstacles does not
enter into the system.
CG002
CL004, 008, 012, 016
CS307, 308
CG502, 503, 504, 513, 514,
CG529
compressor room
3) System oil should be passed through into piping line, and made
hammering to get rid of obstacles.
cargo manifold
b) Open-shut valve
The limit switch shall be supplied and assembled by valve maker
CS107, 108
Two out of 3 units of hydraulic main pumps are used during the work of loading
/ unloading operation (1 pump is used usually , and another is a stand-by). One
topping up hydraulic pump shall be used for forcing vapourisation.
Open-Shut
a) Opening valve
The potentionmeter to be supplied by NAKAKITA to butterfly valve
maker (AMRI) and it shall be assembled by them.
CS600
CL400, 401, 402, 403, 407
CS400, 401, 403
CS407, 408
.
1) Valve Open-Shut Commend (I.S. & Non-I.S. Type)
a) Actuated by oil cylinder operation
After the valve is full opened or shut, the solenoid valve to be
continuously energized.
b) Actuated by oil motor operation
The valve is full opened or shut and 20 seconds after, the solenoid valve
to be de-energized.
4 - 84
1. Process Functions
The two hydraulic power packs are identical, each consisting of two main
pressure pumps, as a stand-by pair, and an additional top-up pump to maintain
the system pressure at sea.
Cut-in and stopping, of the stand-by pump is by using a single pressure
transmitter for each pair of pumps. When the stand-by pump cuts-in (set at 10
MPa), an alarm is generated. When the pressure then rises to 13.5 MPa, the
setting stops the standby pump, with an alarm being sounded.
Automatic stops for all the pumps (cargo and ballast) will be provided in the
event of a hydraulic oil tank low level alarm or a delivery high pressure alarm.
These two stops are active whether the pump is set to Local, Remote,
Auto or Manual. They therefore act like an emergency stop and are always
active.
As the names indicate, one system supplies hydraulic pressure to the cargo
valve control system whilst the other supplies hydraulic pressure to the ballast
valve control system.
When in operation, the pumps will run continuously, whilst the Loading and
Unloading functions will be controlled by the local controls contained within
the package vendor unit. A cross connection is provided between the two
systems in order that either pack can supply the other in the event of a major
malfunction, or during maintenance.
Control of the Cargo and Ballast Hydraulic pumps will be from the Hydraulic
Systems graphic whilst control of the Ballast Hydraulic pumps will also be
from the Ship Side Valve graphic. This is because the ballast hydraulic system
also supplies hydraulic power to the ship side valves and the fuel system
valves. Being controlled from this screen means that they can be controlled
from any operator station as the Ship Side Valve graphic is accessible at all
stations.
As long as the usual criteria are met, then each pair of main pumps can be
controlled typically as a standard standby pair.
Each pair of main pumps has an associated topping-up pump. These are
single pumps having an auto stop function in the event of a hydraulic oil tank
low level alarm or a delivery high pressure. They can also be started and
stopped manually by the operator from the IAS screen.
3. Emergency Control
Two (2) emergency hand pump sets are provided for the cargo system.
Oil Tank capacity :
Max. Pressure :
Flow capacity :
Handle Load :
Accessory:
Location :
6.5 L
13.7MPa
33CC/1strok
20kg at 10.0 MPa
10kg at 5.0 MPa
Rubber Hose 10 m
Cargo Gear Locker
1) Remove the cover lid on the valve actuator, then screw in the supply and
return control studs.
2) At the hand pump check the oil level in the reservoir, if necessary to up
with the correct grade of oil.
3) Move the supply and return valves on the hand pump into the OPEN
position.
4) Close the bypass valve on the hand pump unit.
5) Move the direction control lever to the position that the valve is to be
moved; this is clearly indicated on the plate below the control lever.
6) Operate the hand pump, observe that the valve moves in the correct
direction. When the valve is correctly in its new position, return the
direction selection lever to the mid (neutral) position then close the supply
and return valves. The valve will now be locked in its present position.
2. Operating Mode
1) Local Operation of Solenoids and Pumps
Provided that there is sufficient hydraulic pressure and system integrity, then
the valves may be operated by manually operating the associated hydraulic
solenoid valve. If operating valves in this mode, it would be best to disconnect
the relevant control cables from the solenoid in question before operation.
Pumps may be started and stopped at the local control station as usual.
2) Remote Operation of the Valves from the IAS Graphics Screen
Open/Close valves are controlled either fully open of fully closed. Selection
of these valves on the graphics screen will open up the associated faceplate for
Open and Close control functions.
4 - 85
Blank Page
4 - 86
[Engine Room]
(D) (C)
(A) (B)
(A) (B)
(7 sets)
25A
(R)
For F.O
(4 sets)
(2 sets)
64 Units
(8 sets)
7 Units
(20 sets)
25A
(P)
(9 sets)
(P)
FL-25A
(R)
25A
25A
(P)
(R)
25A
25A
(R)
25A
(R)
25A
(P)
FL-25A
(P)
FL-25A
(T)
For Bilge
Accumulator Stand
(APCHHI1728B)
- Accumulator :
3 sets (60 l)
(R)
25A
(R)
25A
(R)
25A
(P)
25A
(P)
25A
(P)
25A
Accumulator Stand
(APCHHI1728C)
- Accumulator :
14 sets (60 l)
4 - 87
1. General Specification
Description
Opening
FO 01, 03, 10, 11
Maker
Accumulators
box
2. Description
The ship is equipped with two hydraulic power unit for cargo & ballast valve
control and each power unit is assembled with 3 units of vane-type hydraulic
pumps. Two out of 3 units of hydraulic main pumps are used during the work of
loading / unloading operation (1 pump is used usually , and another is a standby). One topping up hydraulic pump shall be used for forcing vapourisation.
Hydraulic pressure control is made by the loading/ unloading system by solenoid
valve, relief valve, pressure switch and accumulators.
Stand-by pump acts automatically for helping start when hydraulic power in
reduced to 10 MPa during operation of hydraulic power unit.
Setting Value
Relief valve setting pressure
13.7 MPa
13.5 MPa
Unloading pressure
13.0 MPa
Loading pressure
11.0 MPa
10.0 MPa
9.0 MPa
3. Location of Cabinets
All remotely operated valves are piston operated except for the liquid dome and
the spray header isolating valves, which are vane type actuators. The supply oil
is distributed to 6 solenoid valve boxes situated in the side passageway (port and
starboard) and 1 in the cargo compressor room. Each cargo tank, manifold area,
cargo compressor room and the master BOG station has its respective solenoid
5. Emergency Control
Two (2) emergency hand pump sets are provided for the ballast system.
box
Open-Shut
6.5 L
13.7MPa
33CC/1strok
20kg at 10.0 MPa
10kg at 5.0 MPa
Accessory:
Rubber Hose 10 m
Location :
Engine Room & Pipe Duct
Stationaly Hand Pump : 5 sets for \shipside valve
4 - 88
Normal Operation
CCR
Normal
Operating
IAS Indication
ESD
TPS1
Interlock Operation
Test
Reset
Cancel
TPS2
Cargo Pump
NO
Q'ty - 8
NO
Strip. & Spray Pump
NO
NO
Q'ty - 4
ESD System
Em'cy Cargo Pump
CSBD
Q'ty - 1
NC
NC
I.S. Barrier
(EEx-ia)
Emergency
Shut Down
Control
NC
Press. Transmitter
Press. Switch
Press. Switch
MSBD
Processor
Self
Diagnosis
Air Control
Board
ESD Signal
(Elec./Optic)
4~20 mA
Press. Switch
CTS
ESD
TPS1
ESD
TPS1
10 11 12 13 14 15
10 11 12 13 14 15
10 11 12 13 14 15
Q'ty - 2
ESD
10 11 12 13 14 15
Q'ty - 2
ESD
10 11 12 13 14 15
TPS1
Q'ty - 2
ESD
10 11 12 13 15
Q'ty - 1
ESD
10 11 12 13 14 15
ESD
10 11 12 13 14 15
NC
ESD
BMS
NC
NC
NC
NC
NC
NC
IGG Blower
Q'ty - 12
ESD
Q'ty - 4
TPS2
Q'ty - 8
TPS1
TPS2
ESD
TPS1
NC
4 - 89
Manual Switch
Fusible Plug
10
11
12
System Fail
13
I/O Failure
14
ESDS Test
15
10 11 12 13 14 15
Emergency
Shut-Down
System
Stop Button
z
z
z
z
z
z
2) Actions
z Manifold valves (shore connection valves) close
z Main cargo pumps stop
z Stripping/Spray pumps stop
z Emergency cargo pump stop
z HD compressors stop
z LD compressors stop
z ESD signal to shore
z Air release solenoid valves open
z No.1 & 2 IGG Blower stop
z Master gas valve off (only vapour main pressure low)
3. Cargo Tank Protection
The operator can manually set the filling valve close override in the
mimic for each cargo tank, so that the logic function of filling valve
close is deactivated. The override function is prepared for each cargo
tank respectively.
4. Gas Burning Safety System
1) Causes
z BOG hood gas detected
z Both boiler trip
z Boil-Off leak ext. fan both stop
z BOG heater outlet temperature low low & high high
z BOG heater trip
z Black-out
z Fusible plug
z Control air pressure low low
z Manual trip signal
z E/R vent fans all trip
2) Actions
z LD compressor stop
z BOG master valve close
5. Functions on the Cargo Console for ESD/TPS
1) ESD Block Input Blocking at Sea
Set the ESD block switch on the Cargo Console. In this mode, all ESD
inputs as defined in the C&E are blocked: i.e. no alarms and no actions
due to ESD inputs will be set from the system. TPS 1 and TPS 2
functions will not be affected.
The extremely high level sensors in the cargo tank can be blocked from
the independent cargo tank level system itself.
The very high level alarm in the cargo tank can be blocked from the
IAS mimic display. These level alarms comes from the radar level
system (CTS).
2) Loading and Unloading Mode
In Loading mode, there is a time delay for shutdown of manifold
valves. This time delay will protect the shore cargo equipment by giving
the shore side time to shutdown before the flow of cargo from the ship
shuts down. The length of the time delay is fixed during commissioning
and can not be configured by the operator. Other outputs than manifold
valves will have no time delay.
Cargo tank very high level sensors - filling level (98.7%) - are installed
in each cargo tank (4) for alarming and closing of the filling valve on
each tank.
3) ESD Reset
Resets all outputs in the ESD/TPS provided inputs are back to normal
and acknowledged.
The sensors are interfaced via the tank level system by serial line to the
IAS. From the IAS the very-high level alarm is interfaced to ESD by the
redundant network.
The Filling valve close override for each cargo tank is prepared to
prevent closing of the filling valve when level very high is activated.
4) ESD Test
Overrides all ESD/TPS outputs in order to facilitate system testing of
inputs and logic.
4 - 90
ACCOMODATION
UPP DK
ELECTRICAL SYSTEM
HEALTHY
TRIP INPUTS
HEALTHY
PORT
ESD HEALTHY
SYSTEM SELECTOR
PRESS
TO
TEST
FIBRE OPTIC
SHORE RECEIVING
HIGH LEVEL HEALTHY
ELECTRIC
SELECTED
SELECTED
LOADING ARM TRIP 1 HEALTHY
LOADING ARM TRIP 2 HEALTHY
INHIBIT
INHIBIT
RESET
RESET
PORT
STBD
SYSTEM
FAULT
LAMP
TEST
CCC6
Telephone SYSTEM
NORMAL
NORMAL
ABNORMAL
CH 1
AUDIO
ALARM
ESD
CH 2
CH 3
CH 4
MLM DESKTOP PC
NORMAL
PRESS
TO
TEST
ABNORMAL
SIGNAL FAULT
PRESS
TO
TEST
CIRCUIT
TEST
220 VAC
1X2X1.0
NORMAL
PSU
MODEN
TELEPHONE
BOOTH
PUBLIC
TELEPHONE
FO ESD MODULE
AC MAINS
SUPPLY
ITT
CANNON
ABNORMAL
HOTPHONE
PRIVATELINE
SHIP TO SHIP
REVERSE CONNECTION
TRIPS ACTIVE
SW 7
ESD
SYSTEM SELECT
C
B
PYLE
B
E
C
D
SW 3
B
E
SW 4
B
E
SW 5
RJ11
GENERAL ALM
GENERAL ALM
SERIAL
C/O
SWITCH
C
D
PSU
TEL CH4
TEL CH3
C
D
SW 2
TEL CH2
C
ITT
CANNON
SW 1
TEL CH1
MIYAKI
D
HOT-LINE
TELEPHONE
SW 6
JB-INT
PABX
TELEPHONE
STBD
GENERAL ALM
RJ11
RJ11
RJ11
RJ45
9w D
ESDS (AMRI-SEIL)
ELECTRIC ESD SHIP SHORE/SHORE-SHIP
FO ESD SHIP SHORE/SHORE-SHIP
YOKOGAWA (DCS)
COMMON ABNORMAL ALARM
4 - 91
In addition to safety, the requirement for the ESD ship to shore link has been
extended to handle communications by telephone.
The Ship-Shore Link Control Panel, for Emergency Shut Down System (ESDS)
& Communications, is supplied for complete compatibility with the Middle
Eastern and Atlantic Basin import LNG Terminals. These systems are used in
30% of all LNG terminals as either a main system or as a back-up system. The
system handles;
z
z
4 telephone channels
Single ship-shore and Shore-ship ESD voltfree contact signals
The main Fibre Optic Ship Shore Link system (FO-SSL) is used in conjunction
with this Electric ESD system (PNC).
The system relies on Pyle National Exd flameproof connectors for connection of
the shore cable the ship shore interface and, once connected to the ship, at the
shore receptacle at the shore cable reel. The system uses a 37 way Pyle National
telecommunications and ESD digital and a 420 mA ship analogue process
signal. The 37 pin connector is fitted to the end of a cable reel on which the
shore end is provided with a second connector provided by NFI. The telephones
on the ship are connected to the shore and are not powered from shipboard
supplies.
1) TEL/IF Module
WARNING
4-way earth bonding connectors are provided but not used due to SIGTTO
regulations recommending they are not to be used
Channel
4. Control Enclosure
Ship-Shore Receive
carriers
Ship-Shore Transmit
carriers
1-Data Channel
18 kHz
78 kHz
30 kHz
90 kHz
This standard unit is an IP55 steel enclosure with part glazed front door panel.
3-Public phone
42 kHz
102 kHz
4-Internal phone
54 kHz
114 kHz
4 - 92
2) ESDS Module
The ESD signal functionality is divided into three operating regions :
y
For the three ESD operation states, the ESD module produces the
appropriate outputs as shown in the table below.
Condition
Input
Output
Normal
Close
Close
ESD
Open
Open
Signal Fault
Disconnection or out
of frequency range
Open
for the system units (CON 1-6). Fuses are 20mm type installed in the
rear panel of the unit, below the connectors. Fuses are 2A AT Slowblow type.
The supply connections are via 2 IEC chassis plugs (AC1, AC2) and
screw terminals for DC.
5) Port/Starboard Selector Module
This 1U module switches the FO ESD and telecommunications
channels between the port and starboard fibre optic shipside connectors
to the SSL cabinet. The ESD tone signals and multiplexed
telecommunication signals, to and from the FO connection box E/O
interfaces, are switched internally through this module and it provides a
switching voltage to the PCBs to change from port to starboard. Port is
the default setting with relays de-energised. The module has a PCB with
embedded microcontroller to monitor the switch selection and control
the signal switching and routing. There are no user settings required in
this module.
which are fitted the terminal blocks, FO box and zener barriers if an
electric system is also integrated.
The incoming 6-core FO cables from the ship-side boxes are connected
to the FO connection box within the SSL.
The electrical signal wiring between the SSL and the control room DCS
is connected to the appropriate terminal blocks on the rear chassis plate.
FO System Operation
1. Description
The SSL control system converts and monitors the electrical and optical
communication signals employed in OFT system.
From the monitored signal information, the control system produces appropriate
module indication, and outputs the status to the ship and shore.
The system communication signals consist of audio signals and volt-free contact
signals.
6) FO Connection Box
y
Monitors signal status information from the fibre optic ESD and
Telephone circuits. The module then controls appropriate signals
to the shipside and shoreside.
The 6-way FO cable from the cable reel is terminated within this box
which is located in the lower rear section of the enclosure. The unit
carries:
y
1 Rx Tel/IF E/O module
y
1 Tx Tel/IF E/O module
y
1 (2) Rx ESD E/O module
y
1 (2) Tx ESD E/O module
2 Rx & Tx ESD PCBs are used in a dual SSB system.
2. Operation
1) ESD Operation
The PCBs use ST fibre optic bayonet connectors for termination. These
employ a spring-loaded glass/ceramic ferrule ground perfectly flat at the
mating face. Normally these connections introduce a small insertion
loss of 0.2 to 0.5 dB into the fibre optic path, but if any dust, or dirt, or
surface scratches are introduced, losses can increase to several dB or
more, rendering the FO signal path ineffective.
4 - 93
Lamp Operation
Green
Yellow
Yellow & Red
Red
3) Fail-Safe Features
For Fail-Safe operation, the control system includes the following
features :
y
Incorporated spare photo-couplers
y
Frequency checking circuits
y
Ship side output circuit has double output contacts available
y
ESD signal (panel output contacts : open) issued in the case of
failure mode
All outgoing contacts fail open with a control system fault condition of :
y
Cable failure
y
System failure
y
Power loss
y
Optical plug disconnected
Pneumatic Systems
Two quick-connect male/female umbilical pneumatic connectors are provided at
main deck level underneath the manifolds for use with the similar systems used
at Ras Laffan and other terminals. These directly trip the loading valves on
pressure loss and are sensed by the Yuken ESD system.
4) Telephone Operation
During normal operation the indicators display the status of each
telephone channel received from the ship and shore as follows;
Green Indicator :
Amber Indicator :
Call
The terminal Hotphone(s) are called by lifting the handset and
pressing the call button whilst the caller speaks into the mouth piece.
These actions result in the caller being heard at the called phones, and a
visual indication. A two way conversation can commence when the
handset on one of the called phones is lifted.
5. PABX/Public Telephones
Standard type European telephones for 48 V DC operation with on-hook line
impedance of 6,000 ohm will be supplied. Line termination shall be by RJ11
standard type socket outlet (USA/International).
The telephones may be mounted on the console. They will be connected into the
Fibre optic ship-shore link cabinet and switched by internal circuitry within the
Fibre optic ship-shore link cabinet. The electric system selector is controlled by a
yard supplied FO-EL selector switch fitted to the Cargo Control console.
The connection box includes a hinged lockable door and is made entirely from
316 stainless steel.
4 - 94
RED DOT
Vantage product has Canadian Standards (CSA) listing 11/2002 reported. To date
no ATEX certification is reported.
1
View on receptacle
ESD CONNECTOR
APPROX
45MM DIA
PIN
Standa
rd
Connect
ion
Ras Laffan
1
(Qatargas)
Ras Laffan
1
(Rasgas)
Higashi
Ohgishi
ma
Futtsu 1
Futtsu 2
ESD
Ship
Shore
No ESD
fitted
ESD
Ship
Shore
Pin 1 +
Pin 4
1
2
3
77.73 DIA
37
4 channels of Telephone/Date
Ship-shore and shore-ship emergency shutdown ESD
Direction
4 channel
Telephone/Date Audio
Ship-Shore
4 channel
Telephone/Data Audio
Shore-Ship
Ship-Shore
Shore-Ship
Spare
Ship-Shore
Spare
Shore-Ship
ESD
Ship
Shore
5
3
The configuration of all plant and shore systems is the same although not all
facilities, (such as MLM) are supported by all terminals.
Spare
Pyeon
g
Taek 1
+2
Incheo
n1
Kawago
e,
Yokkaich
i
ESD
Shore
-Ship
Only
ESD
Shore
-Ship
ONLY
Pin 1 +
Pin 2
ESD
Ship
Shore
Pin 2 - 5
ESD
Ship
Shore
ESD
Shore
Ship
Pin 2 +
Pin 5
ESD
Ship
Shore
Pin 2 - 5
Spare
ESD
Shore
Ship
ONLY
Pin 4 +
Pin 5
6
2
Bintulu
4 - 95
TELEPHONE CONNECTOR #1
P
I
N
Stand
ard
Conne
ction
Ras Laffan
1
(Qatargas)
Ras Laffan
1
(Rasgas)
Higashi
Ohgishim
a
Futtsu 1
Futtsu 2
Sound
Power
ed
Teleph
one
Iwatsu (QG)
Seatechnik(
RG)
Hotline
telephone
PABX
Public
Telephone
Pin 1 +
Pin 2
PABX
Teleph
one
Spare
PABX
Phone 1
PABX
Intern.
Telephone
Pin 3 +
Pin 4
Spare
Spare
spare
InterPh
one
Or
Hotline
Teleph
one
PABX
Phone 2
Bintulu
ESD CONNECTOR
Pyeon
g
Taek 1
+2
Incheo
n1
Kawago
e,
Yokkaic
hi
Hotline
Teleph
one
Not
Used
PIN
Standard
Connection
Incheon 2
Tong Yeong
4
5
B
M
Spare
PABX
Teleph
one
2
3
4
5
6
No connection
connector
No used
PIN
Public
Teleph
one
Standard
Connection
Incheon 2
Tong Yeong
Hotline
Telephone
Pins
Sound
Powered
Telephone
Standard
Connection
Kawagoe,
Yokkaichi
Chita
Spare
PABX
Telephone
Public
Telephone
Public
Telephone
Public
Telephone
C
Hotline
Telephone
Iwatsu
Hotline
Telephone
Plant
(PABX)
Telephone
Plant
(PABX)
Telephone
Not
Used
CONNECTOR
1
5
Higashi
Ohgishima
Futtsu 1
Futtsu 2
Hotline
Telephone
Iwatsu Hotline
Telephone
Pin 1 L1
Pin 2 L2
Spare
No connection
connector
No used
Spare
K
J
TELEPHONE CONNECTOR #1
Ras Laffan 1
(Qatargas)
Ras Laffan 1
(Rasgas)
No connection
connector
No used
F
H
Not
Used
TELEPHONE CONNECTOR #2
C
E
Spare
Standard
Connection
PIN
InterPhone
Or Hotline
Telephone
D
E
Arun
Bontang
Yung An
Himeji
Public
Telephone
Public
Telephone
Iwatsu
Hotline
Telephone
Iwatsu
Hotline
Telephone
Iwatsu
Hotline
Telephone
Plant
(PABX)
Telephone
Plant
(PABX)
Telephone
Plant
(PABX)
Telephone
F
G
H
Iwatsu Hotline
Telephone
Pin 3 -12V
Pin 4 +12V
J
K
L
Spare
4 - 96
c)
1. Winches
d) To cease heaving return the control to the neutral position.
Whenever a winch is in use, a clear view of the overall task in hand
is essential. If the winch operator cannot clearly see the entire
operation from the control position, then a responsible man must be
positioned to guide him.
710 mm
Check the heave in and pay out controls for correct function.
Controls should return to the neutral position when released.
3) Operating Procedure
a)
The drum end is keyed directly on to the drive shaft and always
turns whenever the winch is in use.
b) Personnel and loose gear should be kept well clear. To use the
drum end, ensure that the wire spool has been taken out of gear and
the brake applied.
2. Sunken Bitts
The ship is provided with 16 sunken bitts 4.5~4.8 m above the loaded and
lightship condition waterline respectively.
c)
Selecting a Jetty
To establish communication with the shore-based MLMS and
commence a vessel mooring monitoring session, a jetty must be
selected from the list of available jetties.
General
Shore based Mooring Line Monitoring Systems (MLMS) are present at
many cargo ports. Mooring data is provided from the MLMS via an
RS232 serial communications port to the Ship-to-Shore Link (SSL).
Some jetties provide a direct serial interface SSL cable, others
multiplex/demultiplex signals onto a telephone channel of a common
carrier. The common carrier may use a cable
4 - 97
8) Communications Status
Communication between the Shore Data Monitoring System and the
Mooring Line monitoring system is via the serial port.
Load Monitoring
The operator interface to the Mooring Line Monitoring System displays
the data in a separate window. The figure below shows a typical screen
layout.
Mooring load monitoring is always active once a jetty has been selected.
The load-bar graphs show the current line loads, without further
operator intervention.
Communication Status
Histograms with numerical load readout on and off
c)
Mooring Patterns
A graphical representation of the preferred mooring pattern may be
created, saved edited, recalled or deleted for each jetty. Dragging a line
from a hook to a fairlead position draws a mooring line. Right-clicking
on the fairlead allows a choice of which line to remove. Continue
drawing or deleting lines for each active hook until the mooring pattern
is completed. Once complete the pattern can be saved for this jetty
Red
Grey
Navy
4 - 98
Specification
No. of sets:
Tag No. :
Design Type:
Set pressure:
Closing pressure:
Required capacity:
Relieving capacity:
Specification
No. of sets:
Tag No.
8
CR106, 206, 306, 406,108, 208, 308, 408
Pilot Operated
25 kPa
22 kPa
- Nm3/h
27,030 Nm3/h
16
IBS Type : CR102, 202, 302, 402, 103, 203, 303, 403
IS Type : CR101201, 301, 401, 104, 204, 304, 404
Pilot Operated
3 kPa (For IBS), 3.5 kPa (For IS)
1.8 kPa (For IBS), 2.1 kPa (For IS)
228 Nm3/h (For IBS), 228 Nm3/h (For IS)
420 Nm3/h (For IBS), 481 Nm3/h (For IS)
Type:
Set pressure:
Closing pressure:
Required capacity:
Relieving capacity:
Test Gag
Test Gag
Exhaust Tube
Adjust Screw
OFF SET 20
Offset 20
Exhaust Tube
Adjust Screw
Check Plate
Diaphragm
Diaphragm
Check Plate
Pilot Valve
Pilot Valve
Vent Tube
Field Test Valve
For manual lifting device
connection RC1/2
Diaphragm Retainer
Set Plate
Supply
Pipe
Supply Pipe
Main
Valve
Nozzle
4 - 99
Specification
Manufacturer:
Design Type:
Type & Size:
Number of units:
Number per tank:
Setting Value
Set Pressure:
Reseating Press:
Required Capacity:
Relieving Capacity:
Relieving Pressure:
Vacuum Relieving:
Each section of the cargo pipe work, except the vapour line that can be isolated
by two valves, has an overpressure relief valve fitted. The cargo manifold relief
lines, the cargo machinery space relief lines and No.3 & 4 cargo tanks relief lines
are led to No.3 & 4 vapour domes. No.1 & 2 cargo tank relief lines are led to
No.1 & 2 vapour domes.
Specification
Manufacturer:
Design Type:
Type & Number of units:
Type & Number of units :
Setting Value)
Set Pressure:
Reseating Press:
Relieving pressure:
1 MPa
0.9 MPa
1301.3 kPa
The IBS and IS are protected by 4 relief valves per cargo tank.
25 kPa
22 kPa
- Nm3/h
27,030 Nm3/h
131.3 kPa
-1.0 kPa
The cargo tank relief valves are fitted at the vapour domes of each tank and vent
to their associated vent mast riser. A cargo tank pressure sensing line relays the
pressure directly to the pilot operating valve. In this manner, accurate operation
at the low pressures prevailing inside the tank is assured.
The cargo relief valves are set up initially by the manufacturers for the
requirements on the ship. If overhaul of the valves by ships staff is carried out,
the valves must be checked and reset to the original settings (See manufacturers
instructions for details).
It is extremely important that the vent mast is checked on a regular basis and
drained of any accumulation of water. This is to ensure that the relief valves
operate at their correct settings, which would otherwise be altered if water were
to accumulate in the vent mast and flow into the valve assembly.
A gas detection line is lead out from below the valves, (one point for the I.B.S
and one point for the I.S per cargo tank) to the gas monitoring system, to give a
constant indication of the atmosphere inside the I.B.S and I.S.
The I.B.S relief valve vapour outlet is led to a separate vent line, which runs up
alongside the associated vent mast. This is to prevent any counter pressure or
back flow from the main vent mast should the cargo tank relief valves lift, or
from the nitrogen snuffing system.
It is extremely important that the vent line is checked on a regular basis and
drained of any accumulation of water. This is to ensure that the relief valves
operate at their correct settings, which would otherwise be altered if water were
to accumulate in the vent mast and flow into the valve assembly.
The I.S relief valves vent directly to deck, via a downward facing tail pipe. It is
not necessary for these to be led to a vent mast as the likelihood of LNG vapour
in the insulation space is very remote.
The I.B.S and I.S valves are set up initially by the manufacturer for the
requirements on the ship. If overhaul of the valves by ships staff is carried out,
the valves must be checked and reset to the original settings (See manufacturers
instructions for details).
4 - 100
4 - 101
Part 5
Cargo Auxiliary and Ballast System
Part 5 Cargo Auxiliary and Ballast System
10
6
9
4
10
4
14
1
14
6
2
6
2
7
9
Temp On Secondary Barrier
1 3
5
1
7
10
1 3
10
Trunk DK Aft
Trunk DK Mid
FWD Mid
FWD Port Low
FWD Stbd Low
Side Wall Port
(A/B)
(A/B)
AFT Upp
AFT Mid
AFT Low
Duck Keel Mid
Duck Keel Aft
5-1
10
10
1
4
1
14
8
7
14
3
6
4
3
5
7
9
1 3
7
10
9
3
Trunk DK Aft
Trunk DK Mid
FWD Upp
10
1
Temp On Primary Barrier
FWD Mid
FWD Low
Side Wall Port
(A/B)
(A/B)
AFT Upp
AFT Mid
AFT Low
Duck Keel Mid
Duck Keel Aft
5-2
LI
FLG
LT
(15A)
99%
98.5%
(300A)
Liquid Dome
TI
FLG
TE
100%
TE
TE
TE
Gas
Dome
TE
50%
TE
The thermocouples for the inner hull sensor alarm points are set at 0C.
PI
CTS
85%
(300A)
LI
TI TI TI TI TI
CTS CTS CTS CTS CTS
End
25% 50% 85% 100%
(15A)
SI
CTS
CTS
LAVH
IHS
98%
Back-up
Main
TE
25%
TE
TE
(100A)
Trend curves from the received data can be plotted via the IAS in the
CCR.
End
TE
5-3
TE
PIC
FX/FI
PI PX
PIAHL
TX
PIAL
FX/FI
PX
Trunk Deck
PX
NG-96
NG-97
NG-87
NG-90
NG-89
NG-84
NG-88
TX
NG-93 NG-92
NG-94
NG-95
NG-98
NG-91
PI
NG-83 NG-82
NG-39
Near
Manifold
ESD
CR-100
NG-03
LNG Vent
Master
N2 Master
NG-11
NC-114
I.S.
Gas
Dome
I.S.
NC-108
I.B.S.
I
A-F , J L
To No.1
Dome
Gauge
Board
NC-105
NC-104
NC-106
NC-107
NC-109
NC-110
NC-103
To Fixed Gas
Detection
System
CR-101
NC-112
NC-119
NC-111
NC-101
NC-102
PX To No.1 Dome
PI Gauge Board
NC-115
NG-04
CR-102
NC-113
NC-116
Portable
Sampling
in Cofferdam
NG-01
NG-07
NG-10
NG-08
NG-12
NG-13
CR-103
NG-18
To Fixed Gas
Detection
System
To Fixed Gas
Detection
System
NG-05
NG-06
NG-14
NG-15
NG-16
NG-19
NC-204
NC-117
NC-205
NC-206
NC-203
To Fixed Gas
Detection
System
To Spray Line
NG-62
No.1 H/D
Compressor
No.2 H/D
Compressor
No.2 L/D
Compressor
Compressor Room
NG-63
No.1 L/D
Compressor
Motor Room
I.B.S.
I.S.
I.B.S.
To No.2
Dome
Gauge
Board
NC-207
NC-209
NC-210
NC-219
No.1 Liquid
Dome
FWD AFT
I.S. I.S.
B/W B/W
NC-118
NC-208
Em'cy Cargo
Pump Column
CR-201
CR-301
To Deck
Store
NC-201
NG-02
NG-22
NC-202
To Spray Line
NG-09
NC-212
NC-216
CR-202
PX To No.2 Dome
PI Gauge Board
NC-215
NC-217
NC-304
To Fixed Gas
Detection
System
NC-213
NC-218
NC-303
NG-28
NG-29
I.S.
Gas
Dome
Q
I
A-F , J L
NC-211
NG-17
CR-200
NG-25
NG-26
NG-30
NG-31
CR-203
NG-36
NG-23
NG-24
NG-32
NG-33
NG-34
I.B.S.
I.S.
I.B.S.
NC-305
NC-306
NC-307
To No.1 Dome
Gauge Board
PI
NG-21
No.2 Liquid
Dome
NC-301
NG-47
To Fixed Gas
Detection
System
NG-20
NC-214
NC-308
NG-37
NG-49
NG-50
I.B.S.
I.S.
NC-309
NC-310
Em'cy Cargo
Pump Column
NC-302
NC-319
NC-311
To No.3
Dome
Gauge
Board
NC-312
CR-401
NG-35
CR-300
NG-45
NG-46
NG-51
NG-52
CR-303
NG-43
NG-44
NG-53
NG-54
NG-55
NC-317
NC-404
NC-315
I.S.
NC-405
NC-406
WW
NG-27
To Fixed Gas
Detection
# System
NG-61
NG-81
NC-314
NC-408
NC-409
NC-419
NC-318
NC-414
NC-415
NC-410
NC-411
NC-407
To Spray Line
To No.2 Dome
Gauge Board
PI
NG-42
CR-302
PX To No.3 Dome
PI Gauge Board
NC-316
NC-313
NG-60
CG-613
Gas
Dome
Q
I
A-F , J L
To Fixed Gas
Detection
# System
N
H
To Fixed Gas
Detection
System
NC-412
From
Engine
Room
Boil-off
Gas Line
From
Engine
Room
NG-40
NG-41
No.3 Liquid
Dome
NC-403
To Fixed Gas
Detection
System
To Spray Line
NG-48
NC-402
PX To No.4 Dome
PI Gauge Board
NC-416
To No.4
Dome
Gauge
Board
CR-402
NC-413
NC-418
NC-417
I
A-F , J L
Em'cy Cargo
Pump Column
NC-401
To No.3 Dome
Gauge Board
PI
NG-59
N
G
I.B.S.
Gas
Dome
I.S.
I.B.S.
No.4 Liquid
Dome
NG-69
NG-57
NG-65
S
Em'cy Cargo
Pump Column
NG-56
CR-400
NG-70
NG-68
To Fixed Gas
Detection
# System
NG-58
NG-74
NG-64
NG-66
NG-72
NG-71
NG-75
CR-403
NG-67
NG-73
NC-77
NG-79
NG-78
To No.4 Dome
Gauge Board
PI
NG-80
NG-76
To Fixed Gas
Detection
# System
NG-38
Near
Manifold
TX
5-4
Key
I.S.
: Insulation space
IAS
PV
PV
PV
IBS N2 SUPPLY
CONTROL
N2 HEADER
CONTROL
IBS N2 EXHAUST
CONTROL
IS N2 SUPPLY
CONTROL
SP
SP
PV
PV
IS N2 EXHAUST
CONTROL
SP
SP
PID
PID
PID
PID
PID
[REVERSE]
[REVERSE]
[DIRECT]
[REVERSE]
[DIRECT]
<CHxxx>
<CHxxx>
<NG040>
HIGH/LOW
LIMIT
HIGH/LOW
LIMIT
<CHxxx>
<CHxxx>
IS/IBS
DIFF.
PRESS
<CHxxx>
x-y
HIGH/LOW
LIMIT
HIGH/LOW
LIMIT
kPa
PT
IBS SUPP.
V/V
PT
IS SUPP.
V/V
DPT
IS/IBS
DIFF.
PRESS
PT
kPa
3.5
kPa
Pressure 3.0
Relief Valve
Open
3.0
kPa
Pressure
Relief Valve
3.5
Pressure
Relief Valve
Open
2.5
PAH
Gas
Dome
IBS
IS
Liquid Dome
IBS
IS
2.5
2.0
2.0
PAH
1.5
PAH
1.5
kPa
1.5
N2 SUPP. LINE
IBS EXH.
V/V
PT
Set Point
Exhaust
Set Point 1.0
1.0
Control Valve
DPAH
Exhaust
Operating
0.7
1.0
Set PointControl Valve
Range
Supply
Operating
0.5
PAL
Set Point
Control Valve
Range
0.4 Operating
Supply
0.2
0.5
0.2 Range
Control Valve
PAL
0.0
0.0
0.2
PAL
IS DPAL
IBS0.0
IS EXH.
V/V
N2 HEADER
TO OTHER
CARGO TANK
N2
BUFFER TANK
N2 EXH. LINE
TO VENT MAST
Pressure Control
IBS
5-5
1.5
DPAH
1.0
1.0
Operating
0.7
Range
0.4
0.2
0.0
PressureDiff.
Control
Pressure
Set Point
Exhaust
Control Valve
0.7
P 0.2
0.0
Set Point
Supply
Control Valve
DPAL
Diff. Pressure
IBS
with
IS Pr
with IBS
For the insulation space (I.S) the pressure shall be maintained between 0.2 kPa
and 0.7 kPa above I.B.S pressure.
1. General
Nitrogen is produced by nitrogen generators and stored in a pressurised buffer
tank in the E/R. It is supplied to the cargo side pressurisation headers through
make-up regulating valves. It is also used for purging gas in the fuel gas line in
the E/R with N2.
From the headers, branches are led to the insulated spaces of each tank. Excess
nitrogen is vented through exhaust pressure control valves of each tank vent mast
from the I.B.S. Also insulation spaces excess nitrogen is vented atmosphere.
The barrier space header control valve NG89 reacts to the demand on the system
and maintains the header pressure at 0.5 MPa.
High/Low and differential pressure alarms are fitted to the pressure control
systems for each primary and secondary insulation space.
Two (2) make-up control valves for each tank, one (1) for each inter barrier
and insulation space, shall automatically maintain a minimum pressure for
each space. A by-pass valve shall be provided to each make-up valve.
The control valves shall be designed for the normal make-up flow rate to
the inter barrier and insulation spaces as well as for the make-up flow rate
required for cargo tank loading and cooling down operations.
Audible and visual alarms which are duplicated in the wheel house and the
IAS and are activated in case of insufficient pressure in the pressurised
insulated spaces, shall be provided
If a gas detector shows a gas concentration above 30% of volume in one (1)
inter-barrier space through a micro-leakage of the welded parts of a membrane,
this gas concentration should be reduced by continuous nitrogen purging using
the by-pass to the pressure control valve on the nitrogen supply line of this space
in accordance with the recommendation from GTT.
2) Venting system
The venting system shall be consist of two (2) vent control valves for each
cargo tank, one (1) for each inter barrier and insulation space and a by-pass
valve shall be arranged for each space. Valve operation shall be indicated in
the IAS. Each vent control valve shall be dimensioned to handle the
maximum nitrogen flow rate.
The nitrogen is provided as a dry and inert medium for the following purposes:
The IAS controls each cargo tank IBS N2 pressure via two PID controllers;
one is for the IBS N2 supply valve control, and the other is for the IBS N2
exhaust valve control.
The two PID controllers use the same PV (cargo tank inter barrier space N2
pressure), but the PID controllers are separate from each other.
3) IS/IBS N2 differential pressure control
The IAS controls each cargo tank IS/IBS N2 pressure via two PID
controllers; one is for the IBS N2 supply valve control, and the other is for
the IBS N2 exhaust valve control.
Two PID controllers use the same PV (cargo tank inter-barrier space N2
pressure), but the PID controllers are separate from each other.
4) IS/IBS N2 differential pressure monitoring
The IAS calculates each cargo tank IS/IBS N2 differential pressure by
comparing the IS N2 pressure and IBS N2 pressure.
Monitoring for IS & IBS Pressurisation
y I.S pressure
(High pressure alarm: 2.5 kPa, Low pressure alarm: 0.4 kPa)
There are two (2) different spaces located between the primary barrier and the
inner hull.
For the inter barrier space (I.B.S) the pressure shall be maintained between 0.5
kPa and 1 kPa above atmospheric pressure.
y I.B.S pressure
(High pressure alarm: 1.5 kPa, Low pressure alarm: 0.2 kPa)
2. Insulated Spaces
These two (2) spaces shall be maintained under a dry and inert atmosphere using
nitrogen gas. The pressure in these spaces shall be regulated at a pressure slightly
above atmospheric pressure in order to prevent any air ingress.
In normal operation, the inter-barrier space and insulation space shall be purged
with nitrogen in relation with atmospheric pressure variation and cooling or
warming of the spaces during loading or unloading. The inter-barrier space
should be continuously purged with nitrogen if gas is detected through a microleakage of the membrane.
- The inter barrier space (I.B.S) between the primary and secondary barrier.
- The insulation space (I.S) between the secondary barrier and the inner hull.
The IAS controls N2 header pressure, Inter Barrier Space (I.B.S) N2 pressure and
Insulation Space (I.S) N2 pressure by PID controllers (See Illustration 5.2b
Barrier Space N2 Pressurisation Control).
Both I.B.S and I.S of each cargo tank are provided with pressure relief valves
which open at a pressure, sensed in each space, of 3 kPa for the I.B.S and 3.5
kPa for I.S.
5-6
(65A)
Glycol Water
Expansion
Tank
(1.0 m3)
LS
LAL
Steam
Supply
CH-081
CH-080
TS
TX
(25A)
ZSH
Air
Separator
TX
CH-078
CH-082
TX
TIC
CH-076
MS
CH-073
To Motor
Room
(25A)
CH-102
CH-075
Condensate
PX
PX
PS
CH-094 CH-092
CH-089
TIHH TIAH
CH-083
CH-084
CH-096
CH-098
Steam
Supply
CH-087
CH-100
(65A)
PS
TS
TX
(25A)
TIAL
TX
TIC
CH-079
CH-085
ZSH
Air
Separator
TX
No.2 Glycol
Water Heater
(65A)
CH-113
(25A)
From Motor
Room
(65A)
CH-103
TX
PAL
CH-090
PIAL
(65A)
TIAL
CH-110
TIAL
(65A)
PAL
PIAL
Water/Glycol
Mixing Tank
(0.2 m3)
TIHH TIAH
No.1 Glycol
Water Heater
(65A)
Air Line
Drain Line
(65A)
From
Compressor
Air
CH-099
CH-106
CH-107
CH-109
Glycol Water
Transfer Pump
(2 m3/h x 10 MTH)
CH-088
CH-077
CH-074
MS
To Motor
Room
(25A)
(65A)
(25A)
(25A)
Desuperheated
Steam Line
(25A)
(25A)
Condensate
CH-111
Fresh Water
Filling
FW-13
CH-101
(65A)
(25A)
(65A)
CH-086
From Motor
Room
(65A)
TX
(32A)
TIAL
CH-095
For Glycol
Tank Filling
CA-59
Key
Stand-by Line
Condensate Line
Fresh Water Line
CH-104
Glycol Storage
Tank (4.5 m3)
[Motor Room]
Usual Load Line
CH-105
CH-108
(65A)
(50A)
Filling Cap
5-7
2. Topping up Procedure
If the level falls in the glycol water expansion tank, it must be replenished by
45% glycol water mixture.
1) Ensure that valves CH107 and CH110 at the mixing tank are closed.
6) Open all the test valves/vents in the starboard passageway to both main
and stand-by cofferdam heating systems.
7) Ensure that the rundown and bypass valves to the stand-by coils are
closed and fill the main system via valves CH104 and CH100 until
glycol water just starts to issue from the test valves. The No.2 glycol
water circulating pump can be used to help the flow. Close each test
valve in turn when purged.
3) Open valve CH108 on the Glycol Reservoir and run down strong glycol
to this level as observed on the reservoir gauge glass. Close this valve
and add water to the mixing tank 200liter mark by opening valve FW13.
8) Open the vent valves on No.2 glycol water heater to vent air from the
system. Continue until no more air is vented.
9) Close rundown valve CH100 to the main coils and fill the stand-by
system via CH104 and CH099 until glycol water just starts to issue
from the test valves. No. 1 glycol water circulating pump can be used to
help the flow. Close each test valve in turn when purged.
10) Open the vent valves on No. 1 glycol water heater to vent air from the
standby system. Continue until no more air is vented. Close the
expansion tank rundown valve CH099 to the standby system, leaving
the expansion tank rundown valve CH104 open.
4) Ensure the Glycol Water Expansion Tank outlet valve CH104 is closed,
and transfer the 200liters of glycol water into the glycol water
expansion tank using the pneumatic transfer pump.
5) Repeat until the glycol water expansion tank is full and repeat steps
1) ~ 4) whenever the glycol water expansion tank level falls low.
6) Open the vent valves on No.1 and 2 glycol water heaters to vent any air
from the system.
Monitoring for Glycol Heating
11) Set the main system ready for operation by ensuring all rundown and
bypass valves between the main and stand-by systems are closed.
Open the main system valves CH100, CH102 and CH074 and the inlet
and outlet valves CH098, CH092 on the No.2 Glycol water pump.
Check that the heater valves CH089, CH077 are open and the
thermostatic control valve CH079 is functioning correctly.
12) Open the Standby Glycol system valves in the same way ready for use.
Before starting the standby system, close the expansion tank rundown to
the main system (CH100) and open the valve to the standby system
(CH099).
5-8
4) Exposure Routes
Ethylene Glycol
Synonyms
&
Trade Names
1,2-Dihydroxyethane;1,2-Ethanediol;
Glycol; Glycol alcohol; Monoethylene
glycol
Molecular
Weight
62.07
Molecular
Formula
HOCH2CH2OH
Boiling Point
388 (198)
Freezing Point
Vapour
Pressure
Specific Gravity
1.1088
Solubility
miscible
Lower
Explosive
(Flammable)
Limit In Air
Incompatibilities
& Reactivities
Inhalation
Eyes:
Prevent eye contact
Wash skin:
When contaminated
Remove:
When wet
or contaminated
Change: Daily
protection
to
Ingestion
5) Symptoms
Irritation eyes, skin, nose, throat; nausea, vomiting, abdominal pain,
lassitude (weakness, exhaustion); dizziness, stupor, convulsions,
central nervous system depression; skin sensitization
0.05mmhg(in 20)
2.14
Upper
Explosive
(Flammable)
Limit In Air
10 (-12)
Vapour Density
Flash Point
Skin:
Prevent skin contact
3) First Aid
232
15.3%
Eye:
Irrigate immediately
Skin:
Water wash immediately
Breathing:
Respiratory support
3.2%
Strong oxidizers, chromium trioxide,
potassium permanganate, sodium peroxide
[Note: Hygroscopic (i.e., absorbs moisture
from the air).]
5-9
Blank Page
5 - 10
(15A)
(15A)
(15A)
(15A)
CH-072
CH-071
CH-070
CH-069
(65A)
No.5 Cofferdam
(65A)
(65A)
(65A)
(65A)
(65A)
(65A)
(65A)
(65A)
(65A)
(65A)
(65A)
(65A)
(65A)
(65A)
(65A)
No.3 Cofferdam
5 - 11
No.2 Cofferdam
CH-005
(25A)
CH-007
(25A)
(40A)
Pressure
Test
(40A)
CH-008
CH-014 CH-013
(65A)
No.4 Cofferdam
(40A)
(40A)
(40A)
CH-021
(25A)
(40A)
(25A)
CH-001
CH-002
CH-009
CH-010
ZI
(40A)
CH-022
CH-028 CH-027
(40A)
CH-033
CH-035
(25A)
(40A)
(25A)
(40A)
CH-006
ZI
(40A)
CH-004
CH-012
(40A)
(40A)
CH-036
CH-042 CH-041
(40A)
CH-047
(25A)
CH-048
(25A)
(40A)
CH-049
CH-056 CH-055
(40A)
(40A)
CH-019
ZI
Isolation
Valve
CH-003
CH-011
ZI
(40A)
CH-018
CH-026
CH-020
(40A)
(40A)
TIC
CH-017
CH-025
ZI
(40A)
CH-032
CH-040
CH-034
ZI
TIC
CH-031
CH-039
ZI
(40A)
CH-046
CH-054
(40A)
(65A)
TIC
CH-045
CH-053
CH-015
(40A)
CH-016
(65A)
CH-023
CH-024
(40A)
CH-029
(40A)
CH-030
(65A)
CH-037
CH-038
(40A)
CH-043
(40A)
CH-044
(65A)
CH-051
CH-052
(40A)
CH-050
(40A)
(25A)
(40A)
(40A)
(25A)
CH-062
CH-068 CH-067
(40A)
(40A)
(40A)
ZI
(65A)
ZI
(40A)
CH-060
(40A)
CH-066
TIC
CH-059
ZI
(40A)
CH-057
CH-058
CH-065
CH-061
TIC
CH-063
CH-064
Air Separator
No.1 Cofferdam
Cofferdam temperatures:
Description
There are five (5) temperature controllers in the IAS to manipulate the 3-way
type pneumatic control valves in accordance with the measured temperature at
the cofferdam and liquid dome. Each controller has main and stand-by
temperature control valves.
a)
The purpose of this system is to ensure that the cofferdam temperature is kept at
all times at 5C or above, when the cargo tanks are in a cold condition. Each
cofferdam can be heated by two independent systems; one in service, with the
other on stand-by.
The maximum heating condition is determined by the following extreme
operating conditions:
y
y
y
Any failure of the cofferdam heating system with cargo on board must be treated
as serious and repairs must be effected immediately.
Any accumulation of water in the cofferdam areas can be pumped out using the
bilge eductor located in the engine room.
Special valves (Auto Balancing Valve, see Illustration 5.3.2a) combined with
ball valve and flow regulator function shall be provided on each inlet line of the
cofferdams as follows:
z
Cofferdams :
The purpose of this system is to ensure that the cofferdam temperature is kept at
all times at 5 C or above, when the cargo tanks are in a cold condition. Each
cofferdam can be heated by two independent systems; one in service, with the
other on stand-by.
The IAS provides one (1) controller to control the heater outlet at the required
temperature. The controller is used to control the heater outlet temperature by
manipulating two (2) steam flow control valve.
If the glycol temperature from the heater outlet increases to 105 C, the IAS fully
closes the large and small steam flow control valves automatically and generates
an abnormal alarm.
The above valves shall be set based on the most severe condition in the winter
season and LNG on the primary barrier.
NOTE
In an emergency case with LNG on secondary barrier, the flow cartridge with
spring should be removed from the dynamic auto balancing valve body to
increase the flow rate of glycol water to the maximum.
a)
The system can be operated locally for initial glycol water heater warm-up and
then remotely from the IAS.
The Glycol water circulating pumps can be started locally or remotely.
Main or stand-by lines may be selected.
1) Local Operation
Normally only for initial start-up.
Remote/local operation of the circulating pumps is set locally.
Main or stand-by glycol water supply line set locally
2) Remote Operation
b) Cofferdams:
In each cofferdam, the selected supply line temperature control valve is
modulated to maintain an average temperature of the related bulkheads.
The other supply line valve is maintained closed.
The temperature controllers may be set to automatic or manually
operated from the IAS
Position of the supply line of each temperature control valve is
indicated and low average temperature of each cofferdam is alarmed.
c)
3. Operating
The five (5) PID controllers are provided to ensure that the cofferdam
temperature is kept constant. According to the measured temperature, each PID
controller manipulates either the main or stand-by 3-way control valve,
depending on which coil is in service. The main or stand-by service selection is
done from the schematic display or point detail display in the IAS.
2. Steam Heater Outlet Temperature Control
The glycol water circulating pump is started related to the heater selected.
Steam heaters:
a) Steam pressure for the glycol heater(s) is set.
b) Heater outlet temperature of the glycol water is set.
5 - 12
Differential pressure between the glycol water and the heater steam
pressure will cause an emergency shut down of the circulating pump if
steam pressure is lower that the water pressure. This will also cause the
steam controller to close the steam supply valve.
Steam heater inlet steam pressure to be established before the
circulating pump can be started.
Glycol water outlet temperature is indicated at the IAS with high and
low temperatures alarmed. A Glycol water outlet temperature switch
provides a high-high temperature alarm and trip function for all heater
elements.
5 - 13
1. General
(125A)
(40A)
(125A)
(40A)
(125A)
No.2 H/D
Compressor Motor FC-37
(125A)
(125A)
PX
z
z
TX TX
FC-22
TIC
IAS
FC-02
(15A)
(125A)
(125A)
FC-01
FC-06
(100A)
FC-07
FC-11
FC-23
I
FC-08
(80A)
(125A)
(80A)
Control
Air
TIAH
IAS
(100A)
FC-12
(100A)
PS
(125A)
(125A)
FC-21
PIAL
FC-38
(100A)
(15A)
(25A)
PS
FC-03
FC-04
Chemical
Dosage
Tank
FC-05
(15A)
(125A)
FC-17
FC-10
FC-36
FC-20
FC-19
Each pump can be started locally or remotely. For the remote control of each
pump, the pump control position should be set to remote on the motor starter
panel. Also, if the control position is not in remote position, the stand-by logic
cannot be activated on the IAS. If the following conditions are met, the IAS
activates the stand-by logic control function:
No.1 H/D
Compressor Motor FC-35
(125A)
110 m /h X 30 MTH
No.2
FC-18
(25A)
FC-09
(40A)
(50A)
Rated output
FC-34
(50A)
Number of sets
FC-33
No.2 L/D Compressor
L.O Cooler
De-aeration
Chamber
No.1
Auxiliary Cooling
Fresh Water Pump
(110 m3/h x 30 MTH)
On Deck
(100A)
Type
FC-32
(40A)
(25A)
FC-13
(40A)
FC-24
FC-16
Maker
FC-31
No.1 L/D Compressor
L.O Cooler
LS
FC-14
LAL
(40A)
(40A)
Fresh Water
Expansion
Tank
(1.0 m3)
(65A)
FC-30
FC-26
FC-15
(40A)
FC-25
FC-29
(40A)
(40A)
FC-28
(125A)
(125A)
The cargo machinery cooling fresh water system is provided by two Cargo
Machinery fresh water cooling pumps located in the cargo compressor room.
The Cargo fresh water system is cooled by the cargo machinery fresh water
cooler in the cargo compressor room.
FC-27
(100A)
Key
(100A)
(100A)
(150A)
(150A)
2. Operating Procedures
One auxiliary cooling FW pump is normally required to meet the system cooling
capacity.
1) Open the inlet and outlet valves on both Cargo Machinery cooling FW
pumps.
2) Open the valves on the respective system to be cooled i.e. HD compressor
Lube Oil cooler and motor air cooler, LD compressor Lube Oil cooler,
and steam drain cooler. Check for leaks.
3) Select one of the Cargo Machinery cooling FW pumps on local control
and start the pump. Check that the system pressures are normal.
4) Select the other pump on stand-by.
5) Stop the running pump and ensure that the stand-by pump cuts in.
6) Return the pumps to their original running condition of one pump running
and the other on stand-by.
5 - 14
(350A)
(450A)
LX
(250A)
No.1
BA-44
(300A)
No.2
BA-45
BA-41
FWD Ballast
Water Tank (P)
BA-04
LX
LX
LIAHL
LIAHL
Bow
Thruster
and
Em'cy
Fire
Pump
Room
(40A)
BA-03
BA-46
BA-47
(40A)
LX
BA-05
BA-09
BA-11
LIAHL
BA-07
(250A)
BA-38
LIAHL
LX
(200A)
BA-06
BA-08
BA-10
TV-01
(550A)
(350A)
(200A)
BA-37
BA-42
(350A)
Double O-ring
GRP Sleeve
BA-13
(200A)
(200A)
BA-35
(200A)
BA-40
LX
(350A)
LIAHL
LX
Fore Peak
Tank
(Void)
LIAHL
FWD Ballast
Water Tank (S)
LX
BA-43
Trunk
(750A)
BA-39
(550A)
BA-23
(350A)
No.3 Water
Ballast Pump
3
(3,000 m /h x 30MTH)
(550A)
BA-34
Ballast
Stripping
Eductor
BA-22
BA-36
BA-28
LX
(550A)
(550A)
BA-32
LIAHL
(350A)
BA-21
LX
LIAHL
(350A)
No.2 Water
Ballast Pump
TV-02
BA-20
BA-27
BA-12
(550A)
(40A)
BA-26
BA-19
BA-14
AFT Peak
Tank
No.1 Water
Ballast Pump
BA-15
BA-30 BA-29
BA-25
LIAHL
(550A)
(40A)
(350A)
BA-31
(550A)
LX
BA-18
BA-17 BA-16
BA-24
(350A)
BA-33
LIAHL
LIAHL
(350A)
(350A)
To Main
Condenser
To I.G.G.
High Sea
Chest
Cargo Tank
Key
Sea Water Line
(Steel Pipe)
Sea Water Line
(G.R.P. Pipe)
Water Ballast
Tank (S)
(350A)
5 - 15
Pipe Duct
(350A)
1. General
Ballast pumps
Manufacturer
Model
GVD 500-3M
3
Rating
3,000m /h x 30 m
Speed
1200 rpm
Power
355kW
300m3/h x 25 m
The ballast spaces beneath and around the outboard side of the cargo tanks are
utilized as ballast tanks to optimize draft, trim and heel during the various load
conditions of the vessel.
All valves are butterfly valves, hydraulically operated. The tank aft main
suctions, pump discharge valves etc.
All ballast pipes in the pipe duct are of GRP with galvanised steel bulkhead
pieces and suction bell mouths.
the event of hydraulic accumulator failure. The pump discharge valves, and tank
after main suction valves are multi-positional. All other valves are either open or
closed. In addition to being operable from the CCR, the valves can also be
operated from the solenoid valve station, using the pushbuttons on the individual
solenoids.
The on screen ballast menu also shows when the pumps are switched to remote,
the pumps suction and discharge pressures, the position of the manually
operated valves and the level in each tank, in terms of image.
All valves are butterfly valves hydraulically operated. The tank main suctions,
Pump discharge valves and driving water valves to eductor are of the
intermediate position controlled type.
The ballast tanks stripping suction are not of the intermediate position controlled
type, only the driving water valves to eductor are of the throttling type.
Three ballast pumps are electric motor driven, mounted at the forward end
bottom platform of the engine room. These pumps take their suction from the
sea/sea cross over. The high sea suction is on the port side and the low sea
suction on the starboard side, the latter being the normal operation when loading
ballast. When discharging ballast they take their suction from the ballast
crossover main.
The ballast pumps are also used to supply sea water to the inert gas system.
Ballast will be carried during the ballast voyage, when only sufficient gas is
carried to maintain the tanks and their insulation at cryogenic temperatures.
The ballast spaces are divided into 8 tanks, port and starboard under each of the
4 cargo tanks. There are also two small ballast tanks in the engine room, which
are used to give fine list control this gives a total ballast capacity of 55,526.4m3,
approximately 56,914.6 tonnes when filled with sea water. Three 3,000m3/h,
vertical centrifugal pumps are fitted, which enable the total ballast capacity to be
discharged or loaded in approximately 12 hours for ballasting or de-ballasting.
During cargo loading and unloading two (2) ballast pump sets are used and
during ballast water exchange, three (3) ballast pump sets are used. The pumps
are driven by electric motors and are located on the engine room floor, starboard
side forward.
The 550A fore and aft ballast main runs through the pipe duct with tank valves
mounted on tank bulkheads. The ballast pumps fill and empty the tanks via the
port and starboard side of this main. The stripping eductor suction is also
connected to this main.
Each ballast tank from No.1 W.B. tank (P&S) to No.4 W.B. tank (P&S) is
provided with one (1) main suction (350A) located at the after part of each tank.
An eductor is fitted for stripping and final educting of the tanks, located on the
port side with its own discharge valve.
The driving water for the ballast stripping eductor is from No.2 ballast pump,
though it may be driven from any of the three ballast pumps via the discharge
crossover main.
NOTE
1. The limitation of velocity for ballast water butterfly valves is 4m/sec.
2. The allowable vacuum pressure of GRP pip is -3.53bar.
However, the yard expect the normal vacuum pressure of ballast pump suction
side of -35kPa ~ -40kPa.
So, -50kPa as the limitation/target to be recommended.
2. System Control
The ballast system is controlled entirely from the CCR using the IAS in
conjunction with the ballast mimic.
The ballast pumps are started and stopped using the mimic, provided that the
switches on the local control panel are set to remote. The pumps have an auto
stop sequence control for low and high tank status. When on local control, the
pumps can be started and stopped from the local control panel and can be
stopped from this panel regardless of the position of the local/remote switch. The
local control panels always take priority and can take control from the CCR at
any time.
All hydraulically operated valves in the system are also operated using the on
screen menu/keyboard in conjunction with ballast mimic. Two basic types of
valve are fitted, those which can be positioned at the fully closed position or
fully open, and those which can be positioned at any point between fully open
and fully closed. The position of all valves is shown on the mimic.
Provision is made for a portable hand pump to be used to operate each valve in
5 - 16
The tank throttle valves are controlled by the tank module for opening,
closing and throttling back (to 20% open when the tank content reaches
98% of the set point). The tank valve position is checked by the running
pump start or stop sequence to ensure that it is in the correct position.
The pump discharge valve is limited to 20% open until the active tank
valve or the sum of the active tank valves is greater than 90% open. The
setpoint is then increased to 30%. The operator can then vary the discharge
valve position via mimic using the SP function.
The operator can terminate an automatic ballast operation at any time by
operating one of the terminate buttons on the ballast mimic. A terminate
action stops any sequence that is running and initiates a stop sequence to
close all tank and line valves and stop the duty pump(s).
If either of the ring main line pressure measurements exceed the high-high
or low-low limit, all automatic operations are terminated.
Pump duty selection is carried out by the operator, from the ballast mimic.
It should be noted that when pump No. 2 is selected e.g. as port duty pump
then the starboard No.2 duty select button on the mimic is blocked. It
5 - 17
Condition No.
Condition (Step)
1
Normal Ballast
Cond. Depart.
Step 1
Step 2
Step 3
Step 4
Step 5
Step 6
Step 7
Step 8
FWD.WBTk(P) &
No.4 WB Tk (P)
FWD.WBTk(S) &
No.2 WB Tk (S)
FWD.WBTk(P),
No.1 (P) & A.P. Tk
FWD.WBTk(S) &
No.3 WBTk
F.P.Void
F.P.Void
F.P.Void
F.P.Void
F.P.Void
F.P.Void
Re-filling Tks
FWD W.B.Tk
2060
2060
No.1 W.B.Tk
6316
3616
No.2 W.B.Tk
6527
6527
No.3 W.B.Tk
6621
6621
No.4 W.B.Tk
5745
5745
A.P.Tk
2379
Discharging Tks
F.P.Void
F.P.Void
F.P.Void
F.P.Void
1
Normal Ballast
Cond. Depart
F.P.Void
12.8m
985
12.9m
985
Disch.
Disch.
Empty
Empty
Empty
Empty
Empty
Empty
Empty
Empty
Empty
Empty
Empty
Empty
12.8m
Re-fill
12.9m
Re-fill
12.8m
Ex.com
12.9m
Ex.com
Full
Full
Disch.
Full
Refilling
Full
Exch.
Comp.
Disch.
Exch.
Comp.
Re-filling
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Full
Full
Full
Full
Full
Full
Full
Full
Full
Full
Disch.
Full
Refilling
Full
Exch.
Comp.
Disch.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Full
Full
Full
Disch.
Full
Refilling
Disch.
Exch.
Comp.
Re-filling
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Refilling
Exch.
Comp.
Exch.
Comp.
Full
Full
Full
Full
Full
Full
Full
Full
Full
Full
Full
Disch.
Full
Refilling
Disch.
Exch.
Comp.
Refilling
Exch.
Comp.
Exch.
Comp.
Exch.
Comp.
Full
10.07 m
10.07 m
0.0 m
7.39 m
8.14 %
87.3 %
0.0 deg
351 m
116.0 %
-
Empty
Disch.
7.14
9.53
-2.4
7.29
64.2
55.9
-1.3
472
109.0
-17286
242 Min
9.90
9.40
0.5
7.18
44.2
44.3
0.0
343
108.3
0
12397
310
Empty
7.14
9.53
-2.4
7.92
64.2
55.9
1.2
472
109.0
-12397
310
Exch.
Comp.
Re-filling
9.16
10.54
-1.4
6.47
71.0
86.4
0.0
401
121.0
0
8.08
9.21
-1.1
7.29
94.7
87.7
1.3
415
105.7
15316
383
5 - 18
Exch.
Comp.
-12272
9.16
10.54
-1.4
6.83
71.0
86.4
0.0
401
121.0
0
307
Exch.
Comp.
12270
307
8.08
9.21
-1.1
7.29
94.7
87.7
-1.3
415
105.7
-12272
307
Exch.
Comp.
Exch.
Comp.
10.07
1.07
0.0
6.82
81.4
87.3
0.0
351
116.0
10.07
10.07
0.0
6.82
81.4
87.3
0.0
351
116.0
14242
178
c)
Save Plan: Save the loading current status to disk with a specific file
name.
d) Save As: Save the loading current status to a disk with a different file
name.
e)
Delete Plan: Delete the loading file saved in the current directory.
f)
File Explorer: You can use the File Explorer to format disks, make
backup, get an overall view of your file system and so on.
2) Result Menu
Fig. 2 Result Menu
You can manage loading condition files by use of the File menu. this menu
contains several sub menus and each menu function is as follows.
1) File Menu
Weather Criteria: Data and graph calculated by the IMO.A 562 Criteria.
b) Intact Stability Results: Data and graph calculated by the IMO.A 749
Criteria.
a)
12) GM limit: Loading computer will have the function to display the
message that KMT value is used for even keel condition.
e)
Loading Status : Operator can see the Loading status of vessel which
consists of profile, Tank Top plan, and Midship section.
3) Communication Menu
15) Curves of calculated S.F and B.M and maximum allowable values
required by Classification Society.
a)
b) Open Plan: Read the loading file (*.LDP) saved in the current directory.
5 - 19
OnLine: Select On-Line mode between the ICMS and the Loading
Computer
b) OffLine: Select the Off-Line mode between the ICMS and the Loading
Computer
c)
i)
j)
6) Help Menu
Fig. 6 Help Menu
a)
4) Utility Menu
c)
About
ShipManager-88:
Gives
SHIPMANAGER-88 version.
information
about
the
a)
Heel Adjust: carries out adjustment in the angle of heel by ballast water
to two designated compartments.
f)
f)
5 - 20
1. PULLDOWN MENU
This part controls loading program all main menu is regulated by pull
down method.
2. SPEEDBUTTON MENU
Speed button is the fast method to go work than pulldown menu. If you
want to go Loading menu, Hydrostatics, Constants, Print menu, just click
appropriate speed-button.
STATUS PANEL
It is displayed on this area that all sort of calculated value according to
current loading condition each is as follows.
LWT
Lightweight
DWT
Deadweight
DISP
Displacement
C.O.T.
Prop(%)
LCG
KMT
KG
GM
Metacentric Height
GGo
Loading status
As Fig 8, if you click work tab named LOADING STATUS, you can see
the loading status of vessel which consist of PROFILE, TANK TOP
PLAN, MIDSHIP SECTION. This loading status divided to three (3)
parts such as Cargo Hold, Ballast Tank, and Hull Shape Only and can see
each one at a time. And at Tank Top Plan, can divided and see to Port and
Starboard. If you double click Profile, Plan or Section, screens turn wide
or narrow
B.M.
Deadweight remain
Cargo Tanks
WBT
FOT
Max. Strength (%) value on the summary panel (right below the screen) marks
lowest (most critical) value between allowable S.F. (or B.M.) and actual value.
DOT
LOT
FWT
ETC.T
1.
e Stability
GoM
c Displacement
DWT RE
List
2.
Trend Curve
This is to check the variation of Cargo and Ballast condition at once when
it is connected through on-line.
You can select the optional items such as level, Gross Volume, Volume
Rate, Weight at Trend Curve Option box.
Here you can check and see the variation of level, Gross Volume, Volume
Rate, Weight, per unit hour.
Draft (Eq.)
Equivalent Draft
Fore (F.P)
Mid
After (A.P)
Trim
Draft at Midship
Draft at After Perpendicular
Trim
5 - 21
Key
Fuel Oil Line
Diesel Oil Line
(350A)
Transverse
Cofferdam
FWD H.F.O
Tank (S)
FO-07
From FWD
H.F.O Tank (P)
FO-02
No.1 FO-01
FO-04
No.2 FO-03
(200A)
FO-06
Water Ballast
Tank (P)
Tank Plan
FO-13
FO-17
DO-01
(50A)
FWD Water
Ballast Tank
(P&S)
PI
TIAH
PX
(150A)
FO-07
(350A)
TX
(250A)
(250A)
FO-10
Cofferdam
Cofferdam
(350A)
Cofferdam
TX
LIAHL
LX
FO-08
(150A)
(25A)
DO-03
FO-15
FO-19
(25A)
(25A)
5 - 22
Fore Peak
Tank
(Void)
PI
FO-06
PX
FO-12
(80A)
FO-09
(150A)
DO-04
(350A)
FO-16
(100A)
(50A)
(200A)
FO-20
(350A)
(200A)
LX
(100A)
DO-07
AFT H.F.O
Bunker
Tank (S)
FO-22
No.1 Trunk
TIAH
DO-08
H.F.O
Settling
Tank (S)
FO-21
No.2 Trunk
(350A)
FO-24
(65A)
(40A)
(40A)
G/E
Low
M.D.O Sulphur
Service H.F.O
Tank (S) Tank (S)
No.3 Trunk
FWD H.F.O
Tank LIAHL
(P&S)
FO-11
DO-10 (50A)
(350A)
Fresh
Water
Tank (S)
(100A)
Distilled Water
Tank (S)
(100A)
No.4 Trunk
Cofferdam
Cofferdam
(300A)
(100A)
(100A)
FO-04
FO-14
DO-02
(25A)
FO-18
FO-23
AFT H.F.O
Bunker
Tank (P)
(25A)
DO-05
(65A)
(40A)
H.F.O
Settling
Tank (P)
DO-06
(25A)
IGG
Low
M.D.O Sulphur
Service H.F.O
Tank (P) Tank (P)
(40A)
Drinking
Water
Distilled Water Tank (P)
Tank (P)
Pipe
Duct
FO-03
Pipe Duct
Water Ballast
Tank (S)
Pipe Duct
No.2
Tank Top
Fore Peak
Tank
(Void)
FO-01
(40A)
FO-05
(50A)
No.1
Engine Room
AFT Peak
Tank
Bosun Store
FO-02
AFT
Low
H.F.O
H.F.O
Sulphur
Settling
Bunker
F.O Tank (P) Tank (P)
Tank (P)
(250A)
To H.F.O Tank
(Each)
Cofferdam
Fresh Water
Tank (S)
Cofferdam
Distilled Water
Tank (P&S)
F.O Transfer
Pipe (350A)
IGG
M.D.O
Service
Tank (P)
(25A)
(250A)
(150A)
(200A)
(25A)
(80A)
FO-10
FO-12
FO-11
FO-09
(50A)
Trunk
(25A)
CS-35
CS-01
(50A)
CS-02
(50A)
(80A)
CS-14
LS
CS-38
CS-03
TSLL
TI
(100A)
(50A)
CS-41
CS-18
(50A)
Forcing
Vaporuizer
CS-16
CS-17
LS
LI
LS
TSLL
TI
(50A)
LS
(150A)
CS-42
HC-17
HC-18
CO2 Room
(25A)
(P-Side Unit)
(100A)
HC-19
No.2 Trunk
No.1 Trunk
(80A)
HC-30
(25A)
(S-Side Unit)
(100A)
(150A)
(50A)
(25A)
HC-24
(200A)
(125A)
Steam Supply
(125A)
HC-33
(80A)
HC-31
HC-32
(40A)
HC-04
(40A)
FWD H.F.O
Tank (P &S)
(25A)
HC-05
Fore Peak
Tank
(Void)
(40A)
(25A)
HC-06
(40A)
(25A)
HC-07
(40A)
(25A)
HC-16
(65A)
(80A)
HC-34
Compressor
Room
HC-03
HC-08
(40A)
HC-27
Condensate Return
Motor
Room
(40A)
(25A)
(100A)
(80A)
HC-02
HC-28
To Engine Room
Paint Deck Incinerator
Atmospheric Drain
Store Store Room
Tank
Condensate Return
To Engine Room
Drain Cooler
Steam Supply Main
HC-23
(40A)
(25A)
HC-21
HC-22
HC-01
(25A)
HC-12
HC-29
HC-25
Cofferdam
No.3 Trunk
Cofferdam
No.4 Trunk
Cofferdam
Cofferdam
Engine Casing
Cofferdam
(65A)
HC-26
HC-20
(25A)
HC-09
LAL
LS
(80A)
Fresh
Water
Inlet
Gas Vent
Drain Tank
(1.0 m3)
LS
LI
HC-10
LAH
TI
LNG
Vaporuizer
CS-13
CS-15
(25A)
(100A)
HC-44
TSLL
HC-11
(100A)
CS-72
FC-02
LS
HC-13
CS-36
HC-71
(25A)
(80A)
LS
LI
(80A)
(100A)
CS-37
(25A)
(50A)
FC-01
CS-11
(125A)
CS-32
CS-34
Fresh
Water
Outlet
CS-12
(80A)
(25A)
(100A)
Drain Line
High Duty
Heater
CS-10
(25A)
CS-33
Air Line
TI
HC-14
CS-63
(80A)
(25A)
CS-31
CS-59
TSLL
HC-15
(25A)
CS-28
CS-05
CS-62
(25A)
CS-30
Min. Level MS
(25A)
(25A)
(25A)
CS-29
LS
Condensate Line
(150A)
CS-27
ZSH
No.2 Glycol
Heater
HC-69
CS-50
(50A)
CS-04
(25A)
CS-46
LS
LI
CS-06
(25A)
(25A)
CS-65
(25A)
CS-08
(15A)
HC-56
(50A)
(50A)
CS-67
CS-26
Min. Level MS
CS-49
CS-24
CS-43
(50A)
CS-70
CS-66
ZSH
(25A)
CS-25
Key
Low Duty
Heater
CS-07
CS-09
(25A)
CS-23
No.1 Glycol
Heater
(25A)
(50A)
(40A)
CS-54
(25A)
(100A)
CS-53
(25A)
CS-20
CS-22
(25A)
CS-68
CS-21
(40A)
(50A)
CS-55
(25A)
CS-39
PX
CS-19
CS-40
PX
HC-45
PX
HC-58
PX
[Cargo
Compressor
Room]
(25A)
PIAHL
CS-52
PIC
(50A)
PIAHL
CS-57
PIC
5 - 23
(65A)
(65A)
(40A)
LS
BG-15
(40A)
(50A)
(40A)
BG-17
Drain Plug
LAH
BF-39
(50A)
BG-19
LS
(50A)
(65A)
(50A)
To E/R
LS
To Overboard
Discharge (80A)
Cofferdam
Cofferdam
BG-07
(65A)
Fore Peak
Tank
(Void)
BG-09 BG-08
BG-18
LS
LS
LS
LAH
LAH
LAH
(25A)
(40A)
BG-16
(40A)
LS
LS
(50A)
Bilge Well
Bow
Thruster
Room
FWD H.F.O
Tank (S)
Cargo Gear
Locker
BF-20
Compressor
Room
Cofferdam
LS
BF-40
BF-77
LS
No.1 Trunk
(65A)
LS
Motor
Room
LAH
Pipe Duct
(65A)
BG-20
(65A)
(40A)
(50A)
(65A)
Fresh
Water
Tank (S)
(50A)
Distilled Water
Tank (S)
(25A)
(50A)
LAH
No.2 Trunk
(50A)
Recess for
Drain Tank
Cofferdam
Cofferdam
Steering Gear
Room
No.3 Trunk
No.4 Trunk
Exp. Metal
Wall
FWD Water
Ballast Tank
(P)
FWD H.F.O
Tank (P)
(50A)
(50A)
Rope
Store
(25A)
Distilled Water
Tank (P)
Drinking
Water
Tank (P)
LAH
(65A)
LAH
LS
FWD Water
Ballast Tank
(S)
LAH
LAH
LAH
Fire Main
Drain Plug
Trunk
Ovbd Discharge for
Side Passage B/G
(65A)
(40A)
(40A)
(50A)
(65A)
(50A)
B.W.
B.W.
Transverse
Cofferdam
Key
Bilge Line
Fire Line
Water Ballast
Tank (P)
Water Ballast
Tank (S)
Pipe Duct
5 - 24
(50A)
Top
Air Supply
Compressor
Room
Motor Room
Bilge Line
CA-85
Key
Bilge
Tank
Fire Line
BG-25
LAH
LS
(25A)
Upper Deck
(40A)
(25A)
BG-22
BG-28
BG-29
To be Disconnected
When Not in Use.
(25A)
B.W.
(P&S)
(25A)
(25A)
(25A)
B.W. (C)
BG-23
BG-24
(25A)
Bottom
(25A)
(25A)
BG-27
BG-21
BG-26
Side
Passage
Way
To Engine Room
Bilge Well
4th Deck
Bosun Store
(80A)
(50A)
(65A)
(65A)
(50A)
FWD H.F.O
Tank (P&S)
C.L.
(50A)
BG-06
Engine Room
From Fire
Main
BF-06
(50A)
B.W
From Fire
Main
BG-01
BG-10
BG-13
(40A)
(50A)
(80A)
LS
(50A)
(50A)
BG-05
BG-11
BF-14
BG-04
LAH
(50A)
(50A)
3rd Deck
Cofferdam
(50A)
BF-04
(50A)
2nd Deck
AFT Peak
Tank
C.L.
BG-02
(50A)
BG-03
BG-02 BG-01
BF-14
(50A)
Bilge
Hat
BG-03
BG-14
(50A)
BG-12
(65A)
(50A)
BG-04
BG-10 (80A)
BG-13
(65A)
BG-11
From Fire
BF-06 Main
(80A)
(50A)
LS
Bosun Store
(80A)
BG-12
(80A)
LAH
C.L.
(65A)
Cooling
Water
Tank
Tank Top
Pipe
Duct
FWD W.B
Tank (P&S)
(65A)
BG-09
BG-07
BG-08
Fore Peak
Tank
(Void)
LAH
LS
BG-14
(65A)
(50A)
5 - 25
Mechanical
Rubber Plug
Mechanical
Rubber Plug
Side Shell
Upper Deck
Scupper
Pipe (150A)
2nd Deck
Fresh Water
Tank (S)
AFT Peak
Tank
L.W.L.
Cofferdam
Distilled Water
Tank (P&S)
Engine Room
3rd Deck
Scupper
Pipe (125A)
Side Shell
ABT. 500 mm
Upper Deck
ABT. 400 mm
Upper Deck
Trunk
Trunk Deck
Detail of Cargo
Spill Coaming Drain
Cooling
Water
Tank
Tank Top
(50A)
(50A)
4th Deck
(100A)
Upper Deck
Upper Deck
Side Shell
Pipe Duct
(150A)
ABT. 30 m
Distilled Water
Tank (S)
Fresh
Paint Deck Incinerator
Water Store Store
Room
Tank (S)
No.4 Trunk
Scupper Pipe (50A)
Motor Compressor
Room
Room
No.3 Trunk
Scupper Pipe (50A)
No.2 Trunk
No.1 Trunk
Cofferdam
Accommodation
Area
Cofferdam
Engine
Casing
Cofferdam
CO2 Room
Cofferdam
SC-01
Cargo Manifold (P)
Cofferdam
Drinking
Distilled Water Water
Tank (P)
Tank (P)
Bosun Store
Cargo Gear
Locker
Drain Plug
5 - 26
CA-75
CA-74
Key
CA-77
CA-76
(15A)
(25A)
Trunk
(25A)
(40A)
(15A)
Bosun Store
(15A)
CA-01
(15A)
Compressed Air
Main Line
(15A)
C.L.
(15A)
CA-82
From
E/R
Engine Room
Transverse
Cofferdam
B.W
FWD H.F.O
Tank (P&S)
(15A)
3rd Deck
AFT Peak
Tank
(15A)
(25A)
CA-04
(25A)
Cofferdam
(15A)
(25A)
2nd Deck
CA-84
Cofferdam
CA-83
CA-02
Trunk
Trunk
(15A)
(15A)
(15A)
For
Incinerator
Room
CA-03
For Em'cy Cargo Pump
Handling Davit
(15A)
CA-81
For Em'cy
Generator Room
(25A)
4th Deck
CA-05
Sea
Chest
From
E/R
Tank Top
CA-72
Water Ballast
Tank (P)
CA-12
CA-21
CA-24
This valve to be
arranged nearby
entrance of
bosun store
CA-14
(40A)
CA-16
Bosun Store
CA-60
(40A)
CA-43
CA-06
CA-07
CA-35
CA-19
CA-11
(15A)
CA-08
CA-23
Cofferdam
Cofferdam
CA-50
CA-29
To Pipe Duct
To No.2 Cofferdam
Bilge Pump
Bilge Pump
(FWD) CA-09
For FWD Pump Duct
Cofferdam
CA-37
CA-10
For Fire
Wire Reel
CA-03 CA-02
(25A)
CA-01
(40A)
CA-31
CA-17
CA-15
CA-13
CA-57
(40A)
CA-61 Motor Compressor
Room
Room
To No.3 Cofferdam
Bilge Pump
No.1 Trunk
CA-18
CA-22
CA-85
CA-63
No.2 Trunk
CA-20
CA-52
CA-55
CA-28
CA-25
CA-56
CA-36
CA-33
CA-67
To No.4 Cofferdam
Bilge Pump
Pipe Duct
For F.O & G.O
Manifold Air
Blowing
CA-41
CA-39
(15A)
CA-38
CA-48
Cofferdam
CA-73
(40A)
CA-26
CA-32
CA-44
CA-46
CA-53
CA-64
CA-76
CA-69
CA-71
CA-45
Deck Incinerator
Em'cy
Gen. Store & Room
Room Deck Work
Shop
CA-51
CA-47
(15A)
(15A)
From
E/R
No.4 Trunk
(25A)
CA-30
CA-34
CA-54
Fresh
Water
Tank (S)
CA-42
(40A)
CA-66
CA-68
CA-65
Distilled Water
Tank (S)
Accommodation
Area
CA-79
(15A)
Engine Casing
CA-49
Cofferdam
(25A)
CA-81
CA-83
(15A)
(25A)
For Em'cy
Towing Sys. &
Fire Wire Reel
(40A)
(15A)
CA-72
(15A)
From
E/R
CA-77
CA-84
CA-59
CA-62
(15A)
FWD W.B
Tank (P&S)
CA-58
CA-78
CA-70
(15A)
CA-82
Pipe CA-09
Duct
Pipe Duct
(40A)
(25A)
CO2
Room
(15A)
CA-80
Distilled Water
Tank (P)
For CO2
Drinking
Water
Tank (P)
Fore Peak
Tank
(Void)
CA-73
(15A)
(40A)
Water Ballast
Tank (S)
CA-27
Cooling
Water
Tank
5 - 27
IG-01
To Mach.
Room
Vent for
Pipe Duct
Vapour Main
Liquid Main
IG-08
IG-07
Spool Piece
1. To be disconnected, when
not in use.
2. When connected, ensure
igg at dry air mode.
(450A)
IG-02
To Vapour Return
IG-05
(450A)
(300A)
(300A)
(300A)
No.4 Trunk
IG-06
Gas Main
(300A)
(300A)
No.3 Trunk
(300A)
No.2 Trunk
No.1 Trunk
IG-04 IG-03
IG-04 IG-03
Cofferdam
F.W.D W.B
Tank (P&S)
IG-08
For No.4
Cofferdam
Gas Main
(300A)
For No.3
Cofferdam
(300A)
(300A)
(300A)
IG-07
M/H
For No.2
Cofferdam
M/H
Vapour
Main
M/H
Vapour
Main
M/H
IG-01
(300A)
(300A)
(300A)
(250A)
IG-06
(200A)
(450A)
For No.5
Cofferdam
(450A)
IG-05
IG-01
M/H
(450A)
Vapour
Main
Cofferdam
Cofferdam
No.3 Cargo Tank
Vapour
Main
Tank Top
(300A)
4th Deck
To Ballast Tank
Ventilation
Engine Room
F.W.D
H.F.O
Tank
(P&S)
Cofferdam
3rd Deck
Cofferdam
Manhole
For No.1
Cofferdam
No.4 Liquid
Dome
No.4 Trunk
No.4 Gas
Dome
Liquid
Main
Vapour
Main
Bosun
Store
H
No.3 Liquid
Dome
No.3 Gas
Dome
No.2 Liquid
Dome
No.2 Gas
Dome
No.1 Liquid
Dome
No.1 Gas
Dome
Hatch
No.1 Trunk
No.3 Trunk
Compressor
Room
No.2 Trunk
Vapour
Return
Motor
Room
(300A)
NOTE
The flexible hose having ANSI 150# -300A flanges to be provided by the Owner
5 - 28
Part 6
Cargo Operations
Part 6 Cargo Operations
PIC
FX/FI
PI PX
PIAHL
TX
PIAL
FX/FI
PX
Trunk Deck
PX
NG-96
NG-97
NG-87
NG-90
NG-89
NG-84
NG-88
TX
NG-93 NG-92
NG-94
NG-95
NG-98
NG-91
PI
NG-83 NG-82
NG-39
Near
Manifold
ESD
CR-100
NG-03
LNG Vent
Master
N2 Master
NG-11
NC-114
I.S.
Gas
Dome
I.S.
NC-108
I.B.S.
I
A-F , J L
NC-102
NC-105
NC-104
NC-106
NC-107
NC-109
NC-110
NC-103
To Fixed Gas
Detection
System
CR-101
NC-112
NC-119
NC-111
NC-101
To No.1
Dome
Gauge
Board
PX To No.1 Dome
PI Gauge Board
NC-115
NG-04
CR-102
NC-113
NC-116
Portable
Sampling
in Cofferdam
NG-01
NG-07
NG-10
NG-08
NG-12
NG-13
CR-103
NG-18
To Fixed Gas
Detection
System
To Fixed Gas
Detection
System
NG-05
NG-06
NG-14
NG-15
NG-16
NG-19
NC-204
NC-117
NC-205
NC-206
NC-203
To Fixed Gas
Detection
System
To Spray Line
NG-62
No.1 H/D
Compressor
No.2 H/D
Compressor
No.2 L/D
Compressor
Compressor Room
NG-63
No.1 L/D
Compressor
Motor Room
I.B.S.
I.S.
I.B.S.
To No.2
Dome
Gauge
Board
NC-207
NC-209
NC-210
NC-219
No.1 Liquid
Dome
FWD AFT
I.S. I.S.
B/W B/W
NC-118
NC-208
Em'cy Cargo
Pump Column
CR-201
CR-301
To Deck
Store
NC-201
NG-02
NG-22
NC-202
To Spray Line
NG-09
NC-212
NC-216
CR-202
PX To No.2 Dome
PI Gauge Board
NC-215
NC-217
NC-304
To Fixed Gas
Detection
System
NC-213
NC-218
NC-303
NG-28
NG-29
I.S.
Gas
Dome
Q
I
A-F , J L
NC-211
NG-17
CR-200
NG-25
NG-26
NG-30
NG-31
CR-203
NG-36
NG-23
NG-24
NG-32
NG-33
NG-34
I.B.S.
I.S.
I.B.S.
NC-305
NC-306
NC-307
To No.1 Dome
Gauge Board
PI
NG-21
No.2 Liquid
Dome
NC-301
NG-47
To Fixed Gas
Detection
System
NG-20
NC-214
NC-308
NG-37
NG-49
NG-50
I.B.S.
I.S.
NC-309
NC-310
Em'cy Cargo
Pump Column
NC-302
NC-319
NC-311
To No.3
Dome
Gauge
Board
NC-312
CR-401
NG-35
CR-300
NG-45
NG-46
NG-51
NG-52
CR-303
NG-43
NG-44
NG-53
NG-54
NG-55
NC-317
NC-404
NC-315
I.S.
NC-405
NC-406
WW
NG-27
To Fixed Gas
Detection
# System
NG-61
NG-81
NC-314
NC-408
NC-409
NC-419
NC-318
NC-414
NC-415
NC-410
NC-411
NC-407
To Spray Line
To No.2 Dome
Gauge Board
PI
NG-42
CR-302
PX To No.3 Dome
PI Gauge Board
NC-316
NC-313
NG-60
CG-613
Gas
Dome
Q
I
A-F , J L
To Fixed Gas
Detection
# System
N
H
To Fixed Gas
Detection
System
NC-412
From
Engine
Room
Boil-off
Gas Line
From
Engine
Room
NG-40
NG-41
No.3 Liquid
Dome
NC-403
To Fixed Gas
Detection
System
To Spray Line
NG-48
NC-402
PX To No.4 Dome
PI Gauge Board
NC-416
To No.4
Dome
Gauge
Board
CR-402
NC-413
NC-418
NC-417
I
A-F , J L
Em'cy Cargo
Pump Column
NC-401
To No.3 Dome
Gauge Board
PI
NG-59
N
G
I.B.S.
Gas
Dome
I.S.
I.B.S.
No.4 Liquid
Dome
NG-69
NG-57
NG-65
S
Em'cy Cargo
Pump Column
NG-56
CR-400
NG-70
NG-68
To Fixed Gas
Detection
# System
NG-58
NG-74
NG-64
NG-66
NG-72
NG-71
NG-75
CR-403
NG-67
NG-73
NC-77
NG-79
NG-78
To No.4 Dome
Gauge Board
PI
NG-80
NG-76
To Fixed Gas
Detection
# System
NG-38
Near
Manifold
TX
6-1
Key
I.S.
: Insulation space
1) The IBS nitrogen supply control valves NC111, 211, 311, 411 are
normally set to 0.5kPa at the IAS and the IS supply control valves
NG15, 33, 54, 77 are set for IBS plus 0.2kPa gauge, i.e. 0.7kPa.
2) The IBS exhaust regulating valves NC106, 206, 306, 406 are set for
1.0kPa and the IS is set for IBS plus 0.7kPa, i.e. 1.7kPa.
NOTE
Ensure that the manual isolating valves situated each side of the control valve,
both supply and exhaust on each tank are open, e.g. NC110 and CN112 for No.1
tank IBS supply control valve NC111.
3) Open the manual isolating valves NG90 and NG88 on the insulation
space pressurization header and set the control valve NG89 to 50 kPa,
to allow the supply of nitrogen to the headers from the nitrogen buffer
tank in the engine room.
6-2
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
CS-005
(80A)
(100A)
(650A)
(500A)
CL-003
CS-002(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
(300A)
CG-700
CG-701
(400A)
(50A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6-3
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
SP-700
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
CL-700
(300A)
Spray Main
Sprayers
CG-702
(100A)
(50A)
(65A)
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(400A)
(400A)
CL-305
CL-306
CL-007(500A)
CS-004(80A)
CS-006(80A)
(600A)
CG-703
ESD
(450A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CG-001
(400A)
ESD
(500A) CL-010
CL-011(500A)
CL-012
Liquid Main
(8A)
(40A)
CS-308
(300A)
(300A)
(650A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
Flow Meter
(400A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
(600A)
(PORT)
S
Spray Pump
Vapour Main
(STBD)
(80A)
Cargo Pump
(700A)
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Control Valve
To Cofferdam
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
Needle Valve
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Y-type Strainer
Gas Main
(300A)
Ballast Line
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(300A)
SP-701
CG-600
CG-605
(700A)
CL-016
SP-601
CG-604
(700A)
SP-600
(400A)
(50A)
(50A)
(80A)
CS-008(80A)
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Atmospheric Air
CG-502
ESD
(40A)
(500A)
CS-504
CL-015
(40A)
CS-501
Description
Orifice
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
Symbol
Dry Air
Stripping Crossover
CG-529
(600A)
Liquid Crossover
No.1 H/D
Compressor
(600A)
CS-503
SP-602
ESD
CG-513
CG-525 CG-521
Vapour Crossover
(250A)
(450A)
CG-511
(600A)
CG-517
(600A)
CG-503
Key
Liquid Crossover
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
(300A)
(80A)
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
(300A)
CG-504
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
To Engine Room
CG-520
(750A)
CG-510
CS-007
CL-009
(400A)
S
Spray Pump
1. General
During a dry-docking or inspection, cargo tanks which have been opened and
contained humid air must be dried to avoid primarily the formation of ice when
they are cooled down and secondly, the formation of corrosive agents if the
humidity combines with the sulphur and nitrogen oxides which might be
contained in excess in the inert gas. The tanks are inerted in order to prevent the
possibility of any flammable air/LNG mixture. Normal humid air is displaced by
dry air. Dry air is displaced by inert gas produced from the dry-air/inert gas plant.
Dry air is introduced at the bottom of the tanks through the filling piping. The air
is displaced from the top of each tank through the dome and the vapour header,
and is discharged from the No.1 vent mast riser.
The operation, carried out from shore or at sea, will take approximately 20 hours
to reduce the dew point to less than -20C.
During the time that the inert gas plant is in operation for drying and inerting the
tanks, the inert gas is also used to dry (dew point below -45C ) and to inert all
other LNG and vapour pipe-work. Before the introduction of LNG or vapour,
any pipe-work not purged with inert gas must be purged with nitrogen.
2. Operating Procedure for Drying Tanks
Purpose
Performance Criteria
Auxiliaries Involved
Operation Duration
Check Points
6) Open the valve CG702 to vent through the No.1 vent mast. Eventually,
tank pressure is controlled via the regulating valve CG701, set at 10 kPa
by the inching control, manually set on the IAS.
7) Start the IG Plant (dry air production). When dew point is -45C, open
the delivery valve and close the purge valve on the IAS.
8) Monitor the dew point of each tank by taking a sample at the vapour
domes. When the dew point is -20C or less, close the filling and
vapour valves of the tank.
9) Wet air which may be contained in the discharge lines from the cargo
pumps, float level piping and any associated pipe work in the cargo
compressor room must be purged with dry air. This is normally carried
out in conjunction with the drying of the cargo tanks.
10) When all the tanks are dried to -20C:
(1) Stop the inert gas plant.
(2) Close the dry air supply valve CL601 to the liquid header.
(3) The No.1 vent mast valve CG702 is to be left open at all times,
except for isolation or maintenance.
NOTE
It is necessary to lower the tank dew point by dry air to at least -20 C before
feeding tanks with inert gas in order to avoid formation of corrosive agents.
Dry air, with a dew point of -45 C, is produced by the IG Plant at a flow rate of
15,000 Nm3/h.
1) Prepare the inert gas/dry air generator for use in the dry air mode.
2) Install the spool piece SP600 to connect the inert gas/dry air feeder line
to the liquid header.
3) Open the valves CL601, CL410, CL310, CL210 and CL110 to supply
dry air to the liquid header.
4) Open the tank filling valves CL400, CL300, CL200 and CL100.
6-4
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(400A)
(300A)
(400A)
(50A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6-5
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
Ballast Line
Gas Main
(300A)
SP-701
CG-600
CG-605
(700A)
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-600
Dry Air
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
Inert Gas
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
Inert gas is introduced at the bottom of the tanks through the filling piping. The
dry-air is displaced from the top of each tank through the dome and the vapour
header, and is discharged from the No.1 vent mast riser.
7) When oxygen content is less than 1% and dew point is -45C, open
delivery valve and close purge valve on the IAS.
Inert gas, with an oxygen content of less than 1% and a dew point of -45C, is
produced by the IGG with a flow rate of 15,000 Nm3/h.
Emergency pump wells have to be inerted with nitrogen before inerting the cargo
tanks.
CAUTION
Inert gas from this generator and pure nitrogen will not sustain life. Great care
must be exercised to ensure the safety of all personnel involved with any
operation using inert gas of any description in order to avoid asphyxiation due to
oxygen depletion.
2. Operating Procedure for Inerting Tanks
Purpose
Performance Criteria
Auxiliaries Involved
Operation Duration
Check Points
9) During tank inerting, purge the air contained in the lines and equipment
for about 30 minutes by using valves and purge sample point valves as
described in detail in section 6.6.3.
10) When the operation is completed, stop the supply of inert gas and close
valves CL601, CL410/400, CL310/300, CL210/200, CL110/100,
CG401/400, CG301/300, CG201/200, CG101/100, CG702 and remove
the spool piece SP600.
NOTE
Until the ship is ready to load LNG for gas filling, the tanks may be maintained
under inert gas as long as necessary. If required, pressurise the tanks to 2.0 kPa
above atmospheric pressure and, to reduce leakage, isolate all the valves at the
forward venting system.
Air is purged and replaced by inert gas to attain O2 content less than 2% by the
volume and dew point lower than -40C. This operation will be completed in 20
hours.
CAUTION
All pump discharge valves must remain shut in order to protect the pump from
high speed revolution without lubricant.
6-6
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(400A)
(300A)
(400A)
(50A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6-7
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Inert Gas
Gas Main
(300A)
Ballast Line
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-701
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
There are exceptional cases where it may be necessary to undertake the purging
of one or more tanks at sea using LNG liquid already on board. In this case the
liquid will be supplied to the LNG vaporiser via the stripping/spray header by
using the stripping/spray pump of a cargo tank containing LNG liquid. Due to
local regulations on venting methane gas to the atmosphere, some port
authorities may require the entire operation to be carried out with the exhaust
gases being returned to shore facilities.
CG101/100
First Step
(See Illustration 6.1.4a)
No.2 Tank
CG201/200
No.3 Tank
CG301/300
No.4 Tank
CG401/400
LNG liquid is supplied from the terminal to the liquid manifold where it passes
to the stripping/spray header via the appropriate shore connection liquid valve. It
is then fed to the LNG vaporiser and the LNG vapour produced is passed at
+20 C to the vapour header and into each tank via the vapour domes.
Performance Criteria
Auxiliaries Involved
LNG Vaporiser
Operation Duration
At the start of the operation to fill the cargo tanks, the piping system and LNG
vaporiser are vapour locked. To help break the vapour lock the stripping/spray
header can be purged LNG vaporiser discharge line via CS510.
Check Points
When 5 % methane (the percentage figure will be specified by the particular port
authority) is detected at No.1 vent mast, the exhaust gas is directed ashore via the
HD compressors bypass line, or to the boilers through the gas burning line.
This operation can be done without the compressors, subject to existing back
pressure, or with one or both HD compressors in service. If possible, it is better
not to use compressors to avoid creating turbulence inside the tanks.
The operation is considered complete when the CH content, as measured at the
bottom of the cargo, exceeds 99 % by volume.
The target values for N2 gas and inert gas CO2 is equal to or less than 1 %. These
values should be matched with the LNG terminal requirements.
This normally entails approximately one point eight (1.8) changes of the volume
of the atmosphere in the cargo tank.
On completion of purging, the cargo tanks will normally be cooled down.
The LNG vapour is lighter than the inert gas, which allows the inert gases in the
cargo tanks to be exhausted up the tank filling line to the liquid header. The inert
gas then vents to the atmosphere via the No.1 vent mast.
10) Open the valve CG603 to allow supply to the vapour header.
Purpose
2. Description
9) Open the outlet valve CG501 from the LNG vaporiser in cargo compressor
room.
It is assumed, though unlikely in practice, that all valves are closed prior to use.
1) Install the following spool pieces:
Liquid header to No.1 vent mast (SP700).
Liquid header to compressor (SP600) (only if compressor is required)
2) Prepare the LNG vaporiser for use.
3) Adjust the set point of the LNG vaporiser temperature control valve CS503
to +20 C.
4) Using the IAS, adjust the set point of the pressure control valve CG701 to
6.0 kPa (or required value) by using the inching control (remote manual).
5) Open the valve CL700 at the No.1 vent mast.
6) Open the valve CS701, the stripping/spray header crossover valve to the
manifold.
7) Open the valves CS702 and CS600 on the stripping/spray header to enable
supply to reach the LNG vaporiser.
For safety reasons, ensure that the hull water curtain on the connected side is
in operation.
12) Open the valve CS001 (if using the fwd liquid manifold on the port side),
the isolating valve to the stripping/spray header.
13) Using the IAS, open the individual tank loading valves.
No.1 Tank
CL110/100
No.2 Tank
CL210/200
No3 Tank
CL310/300
No.4 Tank
CL410/400
14) Using the IAS, open CL001, the liquid manifold valve on the port side,
and request the terminal to commence supply of LNG liquid to the ship at
a constant pressure of 200 kPa or as required.
15) Adjust position of CG701 to maintain the required tank header pressure at
6.0kPa initially and then higher when sending vapour to the boilers
without using the LD compressors (free flow).
16) Monitor the inert exhausting gas at each liquid dome (use the mid cargo
tank sample cock initially, followed by the sample cock at the top of the
loading line). Also monitor the inert exhausted gas at No.1 vent mast riser,
using the sample cock.
17) When 5 % methane, (or the quantity the port authority will allow) is
detected at No.1 vent mast and each vapour dome, request permission
from the terminal personnel to direct exhaust gas to the terminal facilities.
8) Open the valve CS505, the inlet valve to the LNG vaporiser.
6-8
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(400A)
(300A)
(400A)
(50A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6-9
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
Ballast Line
Inert Gas
Gas Main
(300A)
SP-701
CG-600
CG-605
(700A)
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-600
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
6) Open the vapour manifold valve CG001 (port side). This will enable a free
flow of gas to the terminal and is a check that the pipeline layout on board
has been arranged correctly.
Second Step
(See Illustration 6.1.4b)
Purpose
Performance Criteria
Auxiliaries Involved
LNG Vaporiser
High Duty Compressors
Operation Duration
Check Points
- HD and LD heater and forcing vaporiser, venting via the sampling cocks.
7) Once the flow to the terminal has been established, close the valve CL700
at No.1 vent mast. Using the IAS, adjust the set point of No.1 vent mast
control valve CG701 to the required value (for example 21 kPa, so that this
valve will remain closed during normal running of the compressors, but
would act in a safety capacity if necessary), and re-open the valve CL700.
8) If the tank pressure increases too much, using the IAS, start one or both of
the HD compressors as necessary.
- Cargo pump lines, stripping/spray pump lines and emergency cargo pump
well via the appropriate line valve and purge sample point.
- Vapour crossover and manifolds CG001 and CG002, venting through the
manifold flanges CG003 (P) and CG004(S).
If the pressure increases, request the terminal to reduce the supply of LNG
or increase the flow through the HD compressors by adjusting the set point
on both HD compressors flow rate by IGV adjusting.
6) Close the valve CS001, the manifold isolating line to the stripping/spray
lines.
When the cargo tank bottom CH content reaches 99.0%, throttle in the individual
tank loading valve until it is only just cracked open.
4. Operating Procedures to Purge the Lines and Equipment with LNG
Vapour
NOTE
Do not shut down the LNG vaporiser until it has been warmed through to the
ambient temperature.
7) Remove the spool pieces after purging with nitrogen and testing the gas
content.
8) Prepare the cargo system cool-down.
During the change of atmosphere, purge the following sections for about 5
minutes each:
3) Purge the following lines and equipment for five minutes each:
1) All sections of the stripping/spray header and tank connections, via the
valves at each liquid dome:
Valve
Description
Position
CG513
Open
No.1 Tank
CG521
Open
No.2 Tank
CG514
Open
No3 Tank
CG522
Open
No.4 Tank
2) Purge manual and ESD valves. The manifold bypass valves are not in use.
The operation is considered complete when all four cargo tanks have at least a
99 % CH content and the acceptable CO2 content and/or N2 content is as
requested by the terminal.
6 - 10
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(50A)
(400A)
(300A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
M
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
(400A)
CL-110
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 11
CS-103
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Gas Main
(300A)
Ballast Line
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-701
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
Cooling down the cargo tanks from +40 C to -130 C, over a period of 10 hours
will require a total of about 800 m3 of LNG to be vaporised. Cool down rate in
the cargo tank and insulation spaces is dependant on the amount of LNG
spraying.
2. Preparation for Tank Cool Down
1) Open the spray header valves on each tank to both spray rails until the
vapour lock has cleared and then close the starboard rail down:
Valve
CS103
CS107,108
CS203
CS207,208
CS303
CS307,308
CS403
CS407,408
Description
Position
Open
Open
Open
Open
Open
Open
Open
Open
Performance Criteria
Auxiliaries Involved
Operation Duration
Check Points
NOTE
The average temperature (except bottom) on IAS is linked to CTS. And this is
not used for cooldown target temperature but used for the averaged vapour
temperature during normal ballast voyage.
Assume that the ship is ready to prepare for cool down after the completion of
gassing up.
6 - 12
NOTE
Only one spray rail is used per tank, the port rail has been used as an
example. The port rail has 79 nozzles and the starboard rail 87 nozzles in
total in all four tanks.
2) Open vapour valves CG101/100, 201/200, 301/300, 401/400 on each
tank.
3) Prepared both HD compressors for use.
4) Adjust the set point of both HD compressors pressure control valve to
6.0kPa (or the required value).
5) Open the HD compressors suction and discharge valves CG513, 514,
521 and CG 522.
6) Open the HD compressors suction from the vapour header CG601 and
discharge valve CG529 to the vapour manifold.
7) Open the vapour manifold valve CG001 (port side). This will enable a
free flow of gas to the terminal and is a check that the pipeline layout on
board has been arranged correctly.
8) Request the terminal to supply LNG liquid for the cooling down
operation at minimum flow rate.
9) Once the vapour lock has cleared and frosting appears on both spray rail
pipe elbows, close the starboard spray rail inlet valves CS108, CS208,
CS308, CS408 and continue the cooldown using the port rail only.
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(50A)
(400A)
(300A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
M
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
(400A)
CL-110
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 13
CS-103
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Gas Main
(300A)
Ballast Line
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-701
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
Description
Position
CG517
Auto
CG518
Auto
11) After cooling down the lines, request the terminal to supply a pressure
of 200 kPa at the ships rail. Monitor the tank pressure and the cooling
down rate.
12) Using the IAS, monitor the pressure inside the tanks and temperature
cooldown rate. Adjust the pressure using the hydraulic driven valve
CS103, CS203, CS303, CS403 if required. Open or close the port spray
rail inlet valves CS107, CS207, CS307, CS407 to obtain an average
temperature fall of 25/30C per hour during the first four hours,
thereafter 10/12C per hour.
If the cargo tank pressure increases to above 1.2kPa, request the
terminal to reduce the supply of LNG, or increase the flow through the
HD compressor by adjusting the set point on the HD compressor control
valves.
If the pressure decreases, reduce the flow through the HD compressors
by adjusting the set point of both HD compressors by the control valve.
13) When the completed cooldown operation, request the terminal to stop
LNG supply, and close CL001. The other valves should remain open
until the lines have warmed up.
14) Stop the HD compressor(s) if loading does not take place after cool
down.
6 - 14
Maintain the cargo tank partially cold during the ballast voyage. At the
discharge port retain a heel in all tanks with the bulk in a single tank,
provided that the level does not exceed 10% of the tank length (see
sloshing). During the voyage the temperature in all tanks is maintained
by periodically spraying LNG into the tanks.
6 - 15
Blank Page
6 - 16
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(50A)
(400A)
(300A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
M
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
(400A)
CL-110
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 17
CS-103
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Gas Main
(300A)
Ballast Line
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-701
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
Performance Criteria
Auxiliaries Involved
-Spray Pump
-Low Duty Compressors
-Low Dury Heater
Operation Duration
Check Points
NOTE
The average temperature (except bottom) on IAS is linked to CTS. And this is
not used for cooldown target temperature but used for the averaged vapour
temperature during normal ballast voyage.
1) Prepare one LD compressor on line to supply the engine room with
boil-off gas for the boilers.
CG508
Auto
CG506
Auto
From the IAS the flow of gas to the boilers is initiated by opening valve
CG606.
4) Check that the nitrogen pressurisation system for the insulation spaces
is in automatic operation and lined up to supply the additional nitrogen
necessary to compensate for the contraction of the nitrogen from
cooling of the tank.
5) Open the header valves at the vapour domes.
No.1 Tank
CG101/100
No.2 Tank
CG201/200
No.3 Tank
CG301/300
No.4 Tank
CG401/400
6) Open the valves on the stripping/spray header CS103, 203, 303, 403,
700 and CS702.
7) The No.4 spray pump is started in sequence after the spray discharge
valve CS401 is opened, to allow minimum flow and to cool down the
spray header.
8) Once cooldown of the spray header to No.4 tank is complete, the
sequence automatically shuts in valve CS400 to allow the remainder of
the spray line to cool down. Open the spray rail inlets on all tanks.
Valve
Description
Open
CS308
Open
CS408
Open
CG515
Open
CG523
Open
CG504
Open
CG510
Open
15.0
5.0
0.0
20
50
70
100
150
200
300
400
500
600 700
Pressure (kpa)
Position
Open
20.0
10.0
CS208
30.0
25.0
Open
CG601
Position
12) On completion of cool down leave the spray header valves open to
allow the spray line to warm up to the ambient temperature before
closing them.
CS108
Description
11) Open the spray return valves on No.1, 2 and 3 tanks, valve CS100, 200,
300 and transfer the required amount of heel to each tank.
Normally, cooling down operations for cargo lines on membrane type LNG
vessels may not be required before arrival alongside the terminal.
Operators should review the implementation procedure agreed between the
seller and the buyer.
Valve
10) When all the tanks have attained the required temperature or lower,
either continue to spray tanks until required heel is transferred or as
follows:
Care should be taken to maintain control of vapour pressure by use of gas in the
boilers as fuel, or in the case of an emergency, vented to atmosphere via No.1
vent mast.
9) Once all spray headers are cool, increase flow by adjusting the spray
pump discharge valve and flow to cargo tanks to maintain an even cool
down and control of vapour pressure.
6 - 18
Nozzle
Capacity
Inlet
Connection Size
NPT
3/4 BD
- 316LSS25
2.5
Body
Orifice
Diam.
Nom
mm
Cap
Orifice
Diam.
Nom
mm
0.5
bar
1
bar
1.5
bar
2
bar
3
bar
6
bar
0.5
bar
1.5
bar
6
bar
7.1
7.5
8.1
11.4
14.0
16.1
19.7
28
63"
70"
74"
SPRAY ANGLE
MATERIAL
SUS316L
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
CS-005
(80A)
(100A)
(650A)
(500A)
CL-003
CS-002(80A)
ESD
CL-004
(400A)
(400A)
ESD
CL-008
ESD
CG-004
CG-002
(400A)
(400A)
(300A)
CG-700
(400A)
SP-100
CG-101
CS-107
(50A)
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
M
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
CG-701
CL-110
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 19
CS-103
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
SP-700
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
CS-701
CS-700
CL-700
(300A)
Spray Main
Sprayers
CG-702
(100A)
(50A)
(65A)
(400A)
(400A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
(600A)
CG-703
ESD
(400A)
(8A)
SP-300
CG-301
CR-304
CS-307
(50A)
CS-308
(40A)
CL-300
(300A)
(50A)
(80A)
CG-001
(400A)
ESD
(500A) CL-010
CL-011(500A)
CL-012
(450A)
(400A)
CR-305
(300A)
Liquid Main
CL-305
CL-306
(CL-308)
Foot Valve
Flow Meter
(650A)
CG-300
CS-300
CS-301
CS-302
CL-301
(300A)
(300A)
(400A)
(600A)
Emergency Pump Column
(400A)
(PORT)
S
Spray Pump
(600A)
(STBD)
(80A)
Cargo Pump
CL-302
CL-303
CL-304
FL-300
(300A)
(50A)
(65A)
(400A)
(400A)
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
2
(CL-408)
Foot Valve
Sprayers
Vapour Main
CS-304
(PORT)
(STBD)
(50A)
SA-356 SA-355
(8A)
SA-354 SA-353
SA-352 SA-351
(8A)
(8A)
CG-401
CS-407
SP-400
(50A)
(50A)
CS-408
(40A)
CL-400
(300A)
(300A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(300A)
CR-404
(50A)
(400A)
CR-405
Control Valve
(700A)
No.3 LNG
Vent Mast
(50A)
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
CS-404
Needle Valve
To Cofferdam
(80A)
CS-403
CL-410
No.4 LNG
Vent Mast
(400A)
(300A)
CS-702
(400A)
(450A)
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
(300A)
Ballast Line
Y-type Strainer
Gas Main
(300A)
CL-601
(300A)
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
SP-701
(400A)
(50A)
(50A)
(80A)
CS-008(80A)
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
CG-502
ESD
(40A)
(500A)
CS-504
CL-015
(40A)
CS-501
Description
Orifice
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
Symbol
Stripping Crossover
CG-529
(600A)
Liquid Crossover
No.1 H/D
Compressor
(600A)
CS-503
SP-602
ESD
CG-513
CG-525 CG-521
Vapour Crossover
(250A)
(450A)
CG-511
(600A)
CG-517
(600A)
CG-503
Key
Liquid Crossover
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
(300A)
(80A)
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
(300A)
CG-504
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
To Engine Room
CG-520
(750A)
CG-510
CS-007
CL-009
(400A)
S
Spray Pump
Assuming a single tank is to be cooled down using heel in that cargo tank.
It is assumed all valves are closed prior to use and it is No.4 cargo tank that is to
be cooled down.
2. Sloshing
Valve
Description
Position
CS403
Open
CS400
Open
1. Operation Procedure for Cooling Down One Tank During Ballast Voyage
1) Prepare one LD compressor on line to supply the engine room with
boil-off gas for the boilers.
2) Adjust the set point of the LD compressor pressure control valve to
0.6kPa (or the required value).
3) On No.1 LD compressor and LD heater open the following valves;
Valve
Description
Position
CG601
Open
CG515
Open
CG523
Open
CG504
Open
CG510
Open
CG508
Auto
CG506
Auto
7) The No.4 spray pump is started in sequence after the spray discharge
valve CS401 is opened, to allow minimum flow and to cool down the
spray header.
8) Once cooldown of the spray header to No.4 tank is complete, shut in on
valve CS400 and open the spray ring inlet valve CS408 on No.4 tank.
Care should be taken to maintain control of vapour pressure either by use of gas
in the boilers as fuel.
8) Increase flow by adjusting the spray pump discharge valve and flow to
the tank in order to maintain an even cooldown and control of vapour
pressure.
10) When the tank has attained the required minimum temperatures stop the
spray pump.
10) On completion of cool down leave the spray header valves open to
allow the spray line to warm up to ambient temperature before closing
them.
The above operation can be repeated for each individual tank.
From the IAS the flow of gas to the boilers is initiated by opening valve
CG606.
4) Check that the nitrogen pressurisation system for the insulation spaces
is in automatic operation and lined up to supply the additional nitrogen
necessary to compensate for the contraction of the nitrogen from
cooling of the tank.
CG101/100
No.2 Tank
CG201/200
No.3 Tank
CG301/300
No.4 Tank
CG401/400
The ships cargo tanks are designed to limit the impact forces and the safety
margin has been considerably enlarged. However, operators should always be
aware of the potential risks to the cargo containment system and also on the tank
equipment due to sloshing.
2. Precautions to Avoid Damage due to Sloshing
1) Filling limit for cargo tank level
The first precaution is to maintain the level of the cargo tanks within the
required limits i.e.:
Lower than a level corresponding to 10% of the length of the tank.
Tank 1
Tank 2
Tank 3
Tank 4
3.2185 m
from the tank
bottom
4.5445 m
from the tank
bottom
4.5445 m
from the tank
bottom
4.0685 m
from the tank
bottom
Tank 2
Tank 3
Tank 4
19.278 m
from the tank
bottom
19.278 m
from the tank
bottom
19.278 m
from the tank
bottom
19.278 m
from the tank
bottom
2) Ships movement:
The second precaution is to try to limit the ships movement, which
would generate sloshing in the tanks.
From the experience gained on the first LNG ships put into service and from a
large number of model tests and computer analyses, Gaz Transport Technigaz
have designed the Mark III system which is reasonably free from any sloshing
risk.
6 - 20
3) The cargo tanks are to be topped off at the fill heights given by the
loading tables (98.5%).
5) Change over the blocking switch for the shut down signal from the
terminal, from the blocked to the terminal position.
6) Connect the terminal loading arms to the four LNG crossovers and one
vapour crossover. This operation is done by the terminal personnel.
7) Check that the coupling bolts are lubricated and correctly torque and
check QCDC (Quick Connect Disconnect) gasket for damage (if
applicable).
8) In the CCR, switch on the cargo tank level alarms and level shutdowns
which are blocked at sea.
9) Switch the independent level alarms from blocked to normal on each
tank.
10) Switch the derived level alarms from blocked to normal on each tank.
At all times when the ship is in service with LNG and mainly during loading, the
following are required:
12) Connect the nitrogen purge hoses to the crossover connections and
purge the air from each loading arm using N2 gas from shore.
13) Pressurise each loading arm with full nitrogen pressure through the
purge valve, and soap test each coupling for tightness.
- The secondary Float Level Gauge system should be maintained ready for
operation.
14) Bring the ship to a condition of no list and trim, and record the arrival
conditions for custody transfer documentation. Official representatives
of both buyer and seller are to be present when the printouts are run
- The temperature recording system and alarms for the cargo tank, barriers
and double hull structure should be in continuous operation.
11) Verify that alarms for level shut downs blocked are cleared.
6 - 21
Blank Page
6 - 22
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(50A)
(400A)
(300A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
M
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
(400A)
CL-110
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 23
CS-103
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Gas Main
(300A)
Ballast Line
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-701
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
Valve
CG601
Description
Position
CL110
Open
CL210
Open
CL310
Open
CL410
Open
CG101/100
Open
CG201/200
Open
CG301/300
Open
CG401/400
Open
CL100
Open
CL200
Closed
CL300
Closed
CL400
Open
Description
CS001
Open
CS701
Open
CS700/702
Open
Position
Open
CG513/521
Open
CG514/522
Open
Open
CG529
Valve
Description
7) Open the vapour manifold vale CG001. This will enable a free flow of
gas to the terminal and is a check that the pipeline layout on board has
been arranged correctly.
8) Open the liquid manifold valves CL002, 006, 010 and the liquid
manifold ESD valves CL001, 005, 009.
9) Request shore to supply LNG at a slow rate through all three loading
arms.
NOTE
In order to avoid the possibility of pipe sections hogging, the liquid header and
crossovers must be cooled down.
10) Adjust the cargo tank filling valves CL110 and 410 to maintain an even
cool-down, nearing the end of the cool-down operation, crack open
cargo tank filling valves CL210 and 310 to cool-down this section.
11) When the temperature at the liquid header has fallen to -100C, ship
cool-down is complete.
Other methods of line up for cooling liquid may be utilized for ship / shore
requirements.
Position
(LNG to the spray nozzle: CS103, 107, 108, 203, 207, 208, 303, 307,
308, 403, 407 and 408.)
4) Prepare both HD compressors for use.
5) Adjust the set point of both HD compressors pressure control valve to
6 kPa (or the required value).
6 - 24
LOADING STARTED
LOADING FINISHED
GASSING UP STARTED
VAPOUR LINE OPENED
OPENING
CTMS
GASSING UP FINISHED
REMOVAL OF
WARNING BUOYS
UNBERTHING
6 - 25
BERTHING
SETTING OF THE SHORE GANGWAY
START LOADING
SAMPLING
REMOVAL OF
WARNING BUOYS
6 - 26
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(50A)
(400A)
(300A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
M
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
(400A)
CL-110
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 27
CS-103
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Gas Main
(300A)
Ballast Line
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-701
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
4) Adjust IBS nitrogen supply control valves are set to 0.5kPa at the IAS
and the IS supply control valves are set for IBS plus 0.2kPa gauge, i.e.
0.7kPa.
5) Adjust IBS exhaust regulating valves are set for 1.0kPa and the IS is set
for IBS plus 0.7kPa, i.e. 1.7kPa.
6) Switch on the unblocking level alarms in the Custody Transfer System
and run the custody transfer print-out for official tank gauging. The
CTMS should be open before the loading arm cool down operation.
7) Open the gas outlet valves on each cargo tank vapour dome (normally
these valves are left open).
CL200
Open
CL300
Open
CL400
Open
1) Ensure that the hull water curtain is in operation on the loading side (in
this case the port side).
No.1 Tank
CG101/100
No.2 Tank
CG201/200
2) Prepare the fire fighting equipment, water hoses and protective clothing
for use. In particular, the manifold dry powder monitors should be
correctly aligned ready for remote operation. Ensure the water spray
system on deck is ready for operation, filters installed and off-shore
blanks removed.
No.3 Tank
CG301/300
No.4 Tank
CG401/400
17) Start the de-ballasting sequence. Keep draught, trim and hull stresses
within permissible limits by controlling de-ballasting.
3) Prepare both HD compressors for use with seal gas and LO systems in
operation.
3. Cargo Loading Operation
(See Illustration 6.3.3a)
Purpose
Performance Criteria
Auxiliaries Involved
Operation Duration
Check Points
Valve
Description
Position
CG513/521
Open
CG514/522
Open
9) Check:
Optical fibre system.
Connection of liquid and vapour arms.
Communications with shore.
Ship/shore electrical and pneumatic connection and safety devices
ESDS.
10) Carry out safety inspections.
11) Complete the relevant ship/shore safety checklist.
12) Set up the tank valves:
Valve
Description
CL110
Open
CL210
Open
CL310
Open
CL410
Open
CL100
Open
3) Check the Inter barrier spaces additional supply valves NC#09, #15 for
each tanks as standby.
6 - 28
Position
19) Ease in the filling valve of each tank as the tank approaches full
capacity.
20) High level alarms. When any tank approaches 98.5 % capacity (signal
from radar level gauge) inform the shore.
High/High level alarms. Standby valve before level approaches about
99 % (signal from radar level gauge).
Close valve at correct filling limit capacity.
WARNING
Extreme and very high level alarms and shut downs are emergency devices only
and should on no account be used as part of the normal topping-off operation.
21) Before topping-off the first cargo tank, request shore to reduce loading
rate and continue reducing when topping off each following tank.
22) When a tank is at its required level, close the corresponding filling valve
and request shore to stop corresponding loading pump: No.1 cargo tank
CL110, No.2 cargo tank CL210, No.3 cargo tank CL310. It is
convenient to finish loading by No.4 cargo tank; for ease of line
draining, leave space for 50m3 available in the tank.
23) Stop loading when the final cargo tank reaches a capacity according to
the filling chart, minus an allowance for line draining and leave No.4
cargo tank filling valve open (CL410).
24) Liquid lines, including the horizontal part of the crossover, will
automatically drain to No.4 cargo tank. The inclined parts of the
manifold are purged inboard with nitrogen.
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(50A)
(400A)
(300A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
M
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
(400A)
CL-110
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 29
CS-103
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Gas Main
(300A)
Ballast Line
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-701
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
6 - 30
(450A)
(350A)
LX
(250A)
No.1
BA-44
(300A)
No.2
BA-45
BA-41
FWD Ballast
Water Tank (P)
BA-38
BA-04
LX
LX
LIAHL
LIAHL
Bow
Thruster
and
Em'cy
Fire
Pump
Room
(40A)
BA-03
BA-46
BA-47
(40A)
LX
BA-05
BA-09
BA-11
LIAHL
LX
(200A)
LIAHL
BA-07
(550A)
(350A)
(200A)
BA-37
BA-42
(350A)
BA-06
BA-08
BA-10
TV-01
(250A)
Double O-ring
GRP Sleeve
BA-13
(200A)
(200A)
BA-35
(200A)
BA-40
LX
LIAHL
LX
(350A)
Fore Peak
Tank
(Void)
LIAHL
FWD Ballast
Water Tank (S)
LX
BA-43
Trunk
(750A)
BA-39
(550A)
BA-23
(350A)
No.3 Water
Ballast Pump
(3,000 m3/h x 30MTH)
(550A)
BA-34
Ballast
Stripping
Eductor
BA-22
BA-36
BA-28
LX
(550A)
(550A)
BA-32
LIAHL
(350A)
BA-21
LIAHL
(350A)
No.2 Water
Ballast Pump
TV-02
BA-20
BA-27
BA-12
(550A)
(40A)
BA-26
BA-19
BA-14
AFT Peak
Tank
No.1 Water
Ballast Pump
BA-15
(550A)
BA-30 BA-29
BA-25
LX
(550A)
(40A)
BA-31
(350A)
LIAHL
BA-18
BA-17 BA-16
BA-24
LIAHL
(350A)
LIAHL
BA-33
LX
(350A)
(350A)
To Main
Condenser
To I.G.G.
High Sea
Chest
Cargo Tank
Key
Ballast Main (550A)
Water Ballast
Tank (P)
Water Ballast
Tank (S)
(350A)
6 - 31
Pipe Duct
(350A)
(450A)
(350A)
LX
(250A)
No.1
BA-44
(300A)
No.2
BA-45
BA-41
FWD Ballast
Water Tank (P)
BA-38
BA-04
LX
LX
LIAHL
LIAHL
Bow
Thruster
and
Em'cy
Fire
Pump
Room
(40A)
BA-03
BA-46
BA-47
(40A)
LX
BA-05
BA-09
BA-11
LIAHL
LX
(200A)
LIAHL
BA-07
(550A)
(350A)
(200A)
BA-37
BA-42
(350A)
BA-06
BA-08
BA-10
TV-01
(250A)
Double O-ring
GRP Sleeve
BA-13
(200A)
(200A)
BA-35
(200A)
BA-40
LX
LIAHL
LX
(350A)
Fore Peak
Tank
(Void)
LIAHL
FWD Ballast
Water Tank (S)
LX
BA-43
Trunk
(750A)
BA-39
(550A)
BA-23
(350A)
No.3 Water
Ballast Pump
(3,000 m3/h x 30MTH)
(550A)
BA-34
Ballast
Stripping
Eductor
BA-22
BA-36
BA-28
LX
(550A)
(550A)
BA-32
LIAHL
(350A)
BA-21
LIAHL
(350A)
No.2 Water
Ballast Pump
TV-02
BA-20
BA-27
BA-12
(550A)
(40A)
BA-26
BA-19
BA-14
AFT Peak
Tank
No.1 Water
Ballast Pump
BA-15
(550A)
BA-30 BA-29
BA-25
LX
(550A)
(40A)
BA-31
(350A)
LIAHL
BA-18
BA-17 BA-16
BA-24
LIAHL
(350A)
LIAHL
BA-33
LX
(350A)
(350A)
To Main
Condenser
To I.G.G.
High Sea
Chest
Cargo Tank
Key
Ballast Main (550A)
Water Ballast
Tank (P)
Water Ballast
Tank (S)
(350A)
6 - 32
Pipe Duct
(350A)
(450A)
(350A)
LX
(250A)
No.1
BA-44
(300A)
No.2
BA-45
BA-41
FWD Ballast
Water Tank (P)
BA-38
BA-04
LX
LX
LIAHL
LIAHL
Bow
Thruster
and
Em'cy
Fire
Pump
Room
(40A)
BA-03
BA-46
BA-47
(40A)
LX
BA-05
BA-09
BA-11
LIAHL
LX
(200A)
LIAHL
BA-07
(550A)
(350A)
(200A)
BA-37
BA-42
(350A)
BA-06
BA-08
BA-10
TV-01
(250A)
Double O-ring
GRP Sleeve
BA-13
(200A)
(200A)
BA-35
(200A)
BA-40
LX
LIAHL
LX
(350A)
Fore Peak
Tank
(Void)
LIAHL
FWD Ballast
Water Tank (S)
LX
BA-43
Trunk
(750A)
BA-39
(550A)
BA-23
(350A)
No.3 Water
Ballast Pump
(3,000 m3/h x 30MTH)
(550A)
BA-34
Ballast
Stripping
Eductor
BA-22
BA-36
BA-28
LX
(550A)
(550A)
BA-32
LIAHL
(350A)
BA-21
LIAHL
(350A)
No.2 Water
Ballast Pump
TV-02
BA-20
BA-27
BA-12
(550A)
(40A)
BA-26
BA-19
BA-14
AFT Peak
Tank
No.1 Water
Ballast Pump
BA-15
(550A)
BA-30 BA-29
BA-25
LX
(550A)
(40A)
BA-31
(350A)
LIAHL
BA-18
BA-17 BA-16
BA-24
LIAHL
(350A)
LIAHL
BA-33
LX
(350A)
(350A)
To Main
Condenser
To I.G.G.
High Sea
Chest
Cargo Tank
Key
Ballast Main (550A)
Water Ballast
Tank (P)
Water Ballast
Tank (S)
(350A)
6 - 33
Pipe Duct
(350A)
BA-13
BA-08
A.P.TK
BA-33
BA-09
BA-10
BA-11
1) Open the valves BA-18, BA-20 and BA-22 (Ballast pump suctions).
BA-12
BA-13
5) Start the water spray pump and open the discharge valve BA-42.
5) Open the pump(s) discharge valve BA-24 (No.1), BA-26 (No.2), BA-28
(No.3).
6) When one tank has been stripped, ensure the next tank valve is opened
before closing the previous tank.
6) As the tank reaches the required level, open the valves on the next tank
before closing the valves on the first tank.
7) When all tanks have been stripped, close the eductor suction valve BA36 and close the spray pump discharge valve BA-42 and stop the pump.
7) When suction has been lost on all tanks, close the discharge valves on
the pumps BA-24 (No.1), BA-26 (No.2), BA-28 (No.3) and stop the
pumps.
9) Close the eductor discharge valve BA-39 and eductor overboard valve
BA-44.
BA-04
BA-05
BA-06
2) Open the drive water supply from the water spray pump, valve BA-37.
BA-07
BA-08
BA-09
BA-10
BA-11
BA-12
BA-04
BA-05
BA-06
BA-07
6 - 34
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
CS-005
(80A)
(100A)
(650A)
(500A)
CL-003
CS-002(80A)
ESD
CL-004
(400A)
(400A)
ESD
CL-008
ESD
CG-004
CG-002
(400A)
(400A)
(300A)
CG-700
(400A)
SP-100
CG-101
CS-107
(50A)
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
M
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
CG-701
CL-110
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 35
CS-103
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
SP-700
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
CS-701
CS-700
CL-700
(300A)
Spray Main
Sprayers
CG-702
(100A)
(50A)
(65A)
(400A)
(400A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
(600A)
CG-703
ESD
(400A)
(8A)
SP-300
CG-301
CR-304
CS-307
(50A)
CS-308
(40A)
CL-300
(300A)
(50A)
(80A)
CG-001
(400A)
ESD
(500A) CL-010
CL-011(500A)
CL-012
(450A)
(400A)
CR-305
(300A)
Liquid Main
CL-305
CL-306
(CL-308)
Foot Valve
Flow Meter
(650A)
CG-300
CS-300
CS-301
CS-302
CL-301
(300A)
(300A)
(400A)
(600A)
Emergency Pump Column
(400A)
(PORT)
S
Spray Pump
(600A)
(STBD)
(80A)
Cargo Pump
CL-302
CL-303
CL-304
FL-300
(300A)
(50A)
(65A)
(400A)
(400A)
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
2
(CL-408)
Foot Valve
Sprayers
Vapour Main
CS-304
(PORT)
(STBD)
(50A)
SA-356 SA-355
(8A)
SA-354 SA-353
SA-352 SA-351
(8A)
(8A)
CG-401
CS-407
SP-400
(50A)
(50A)
CS-408
(40A)
CL-400
(300A)
(300A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(300A)
CR-404
(50A)
(400A)
CR-405
Control Valve
(700A)
No.3 LNG
Vent Mast
(50A)
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
CS-404
Needle Valve
To Cofferdam
(80A)
CS-403
CL-410
No.4 LNG
Vent Mast
(400A)
(300A)
CS-702
(400A)
(450A)
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
(300A)
Ballast Line
Y-type Strainer
Gas Main
(300A)
CL-601
(300A)
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
SP-701
(400A)
(50A)
(50A)
(80A)
CS-008(80A)
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
CG-502
ESD
(40A)
(500A)
CS-504
CL-015
(40A)
CS-501
Description
Orifice
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
Symbol
Stripping Crossover
CG-529
(600A)
Liquid Crossover
No.1 H/D
Compressor
(600A)
CS-503
SP-602
ESD
CG-513
CG-525 CG-521
Vapour Crossover
(250A)
(450A)
CG-511
(600A)
CG-517
(600A)
CG-503
Key
Liquid Crossover
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
(300A)
(80A)
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
(300A)
CG-504
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
To Engine Room
CG-520
(750A)
CG-510
CS-007
CL-009
(400A)
S
Spray Pump
If the tank pressure continues to increase because the steam consumption is not
sufficient to burn all the required boil-off, the steam dump will open.
1. Introduction
The steam dump is designed to open when the normal boil-off valve is 5 % above
the original selected value and when the tank pressure has reached the preselected dump operating pressure.
During a sea passage when the cargo tanks contain LNG, the boil-off from the
cargo tanks is burned in the ships boilers. The operation is started on deck and
controlled by the ships engineers in the CCR and ECR. If for any reason the
boil-off cannot be used for gas burning, or if the volume is too great for the
boilers to handle, any excess vapour is vented to atmosphere via No.1 vent mast.
2. Operation
The cargo tank boil-off gas enters the vapour header via the cargo tank vapour
domes. It is then directed to one of the LD compressors, which pumps the gas to
the LD heater. The heated gas is delivered to the boilers at a temperature of
+45 C via the master gas valve CG606. The LD compressor inlet guide vane
position is governed by fuel gas demand from the boiler(s) and cargo tank
pressure. The system is designed to burn all boil-off gas normally produced by a
full cargo and to maintain the cargo tank pressure (i.e. temperatures) at a
predetermined level.
If the propulsion plant steam consumption is not sufficient to burn the required
amount of boil-off, the tank pressure will increase and eventually the steam
dump will open, dumping steam directly to the main condenser. The main dump
is designed to dump sufficient steam to allow the boiler to use all the boil-off
produced, even when the ship is stopped.
The flow of gas through the LD compressors is controlled by adjusting the inlet
guide vane position. This is directed by the boiler combustion control when gas
burning is initiated. The normal boil-off in the boiler combustion control has to
be selected as well as the maximum and minimum allowed tank pressures and
the tank pressure at which the main dump operates.
For normal operation the normal boil-off valve is selected at 60% (boil-off
provides 60% of the fuel required to produce 90% of the boiler full steam
capacity) and the minimum and maximum tank pressures are selected at
105kPaA and 110kPaA.
If the normal boil off valve has been correctly adjusted, the tank pressures will
remain within the selected values. Should the selected normal boil off value be
too large, the tank pressure will slowly be reduced until it reaches the minimum
value selected. If the tank pressure value reduces to below the minimum value
selected, the normal boil-off value will be reduced until the tank pressure has
increased again above the selected value.
If the selected normal boil-off value is too small, the tank pressure will slowly
increase until it reaches the maximum value selected. If the tank pressure value
increases above the maximum selected value, the normal boil-off value will be
increased until the tank pressure reduces again below the selected value.
The cargo and gas burning piping system is arranged so that excess boil-off can
be vented should there be any inadvertent stopping of gas burning in the ships
boilers. The automatic control valve CG701 at No.1 vent mast is set at 21kPa to
vent the excess vapour to atmosphere as a tank protection system.
In the event of automatic or manual shut down of the gas burning system (or if
the tank pressure falls to 2 kPa above the atmospheric pressure), the valve
CG606 will close and the gas burning supply line to the engine room will be
purged with nitrogen.
3. Operating Procedures
It is assumed that all valves are closed prior to use:
1) Prepare LD compressors, LD heater and the engine room gas burning
plant for use.
CG101/100
NO.2 Tank
CG201/200
NO.3 Tank
CG301/300
NO.4 Tank
CG401/400
2) Check that the following valves on the vapour domes are open
(Always opened in normal operation.):
NO.1 Tank
In CCR
Description
Position
Open
CG508
Auto
CG506
Auto
6 - 36
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
CS-005
(80A)
(100A)
(650A)
(500A)
CL-003
CS-002(80A)
ESD
CL-004
(400A)
(400A)
ESD
CL-008
ESD
CG-004
CG-002
(400A)
(400A)
(300A)
CG-700
CG-701
(400A)
SP-100
CG-101
CS-107
(50A)
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 37
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
SP-700
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
CS-701
CS-700
CL-700
(300A)
Spray Main
Sprayers
CG-702
(100A)
(50A)
(65A)
(400A)
(400A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
(600A)
CG-703
ESD
(400A)
(8A)
SP-300
CG-301
CR-304
CS-307
(50A)
CS-308
(40A)
CL-300
(300A)
(50A)
(80A)
CG-001
(400A)
ESD
(500A) CL-010
CL-011(500A)
CL-012
(450A)
(400A)
CR-305
(300A)
Liquid Main
CL-305
CL-306
(CL-308)
Foot Valve
Flow Meter
(650A)
CG-300
CS-300
CS-301
CS-302
CL-301
(300A)
(300A)
(400A)
(600A)
Emergency Pump Column
(400A)
(PORT)
S
Spray Pump
(600A)
(STBD)
(80A)
Cargo Pump
CL-302
CL-303
CL-304
FL-300
(300A)
(50A)
(65A)
(400A)
(400A)
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
2
(CL-408)
Foot Valve
Sprayers
Vapour Main
CS-304
(PORT)
(STBD)
(50A)
SA-356 SA-355
(8A)
SA-354 SA-353
SA-352 SA-351
(8A)
(8A)
CG-401
CS-407
SP-400
(50A)
(50A)
CS-408
(40A)
CL-400
(300A)
(300A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(300A)
CR-404
(50A)
(400A)
CR-405
Control Valve
(700A)
No.3 LNG
Vent Mast
(50A)
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
CS-404
Needle Valve
To Cofferdam
(80A)
CS-403
CL-410
No.4 LNG
Vent Mast
(400A)
(300A)
CS-702
(400A)
(450A)
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
(300A)
Ballast Line
Y-type Strainer
Gas Main
(300A)
CL-601
(300A)
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
SP-701
(400A)
(50A)
(50A)
(80A)
CS-008(80A)
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
CG-502
ESD
(40A)
(500A)
CS-504
CL-015
(40A)
CS-501
Description
Orifice
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
Symbol
Stripping Crossover
CG-529
(600A)
Liquid Crossover
No.1 H/D
Compressor
(600A)
CS-503
SP-602
ESD
CG-513
CG-525 CG-521
Vapour Crossover
(250A)
(450A)
CG-511
(600A)
CG-517
(600A)
CG-503
Key
Liquid Crossover
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
(300A)
(80A)
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
(300A)
CG-504
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
To Engine Room
CG-520
(750A)
CG-510
CS-007
CL-009
(400A)
S
Spray Pump
3. Operating Procedures
1. Introduction
For illustration purposes, No.3 cargo tank stripping/spray pump and return
operation is shown.
Consideration must be given to the economics of gas versus fuel oil burning
before undertaking forced boil-off.
If, during a loaded passage, additional fuel gas from the cargo tanks is required
to be burned in the ships boilers, it can be made available by forced vapour
using the equipment on board.
The above operation, called Forced Boil-Off, will be used to complement gas
burning up to 100% of the boilers fuel requirement.
2. Operation
The normal gas burning arrangement is maintained and the forcing vaporiser is
brought into operation.
A single stripping/spray pump is used to pump LNG to the forcing vaporiser.
The excess flow from the pump is returned to the tank through the stripping
header pressure control valves CS100, CS200, CS300, CS400 depending on the
tank used to provide the LNG.
2) Alarms:
The cargo piping system is arranged for normal gas burning during a loaded
voyage as detailed in Illustration 6.4.1a.
3kPa
2kPa
4) Open the forcing vaporiser inlet and outlet valve CS506, CG502.
Min. gas flow of F/V control
1,400kg/h (20~100%)
45 C
87 %
In the event of automatic or manual shut down of the gas burning system (or if
the vapour header pressure falls to 2kPa above the atmospheric pressure), valve
CG606 will close and the gas burning supply line to the engine room will be
purged with nitrogen. FO booster devices are incorporated in the control loop to
allow a quick change over should the gas burning be tripped.
When changing over to 100% gas burning, the fuel oil flow through the FO rails
is adjusted to minimum. The FO supply to the burners will then be cut out and
the FO system put on recirculation. The FO combustion control loops are
maintained energized to enable re-lighting of FO burners in an emergency.
21kPa
FO back-up order ON
After vaporization, the LNG vapour combines with the natural boil-off gas from
the cargo vapour line before entering the LD compressor.
Low load:
High load:
23kPa
NOTE
In normal operation the controlled return is directed back to the same tank from
which the liquid is being drawn.
The flow of gas through the LD compressor is controlled via the boiler
combustion control unit by adjusting the opening of the inlet guide vanes and
motor speed. The split control is as follows:
Control range
Ballast voyage
Laden voyage
105kPaA ~ 110kPaA
25kPa
Vacuum
-1kPa
6 - 38
CR-053 CR-054
(50A)
(50A)
(80A)
CS-008
CR-004
CL-057 CL-058
CL-055 CL-056
(40A)
(25A)
(65A)
CG-058 CG-057
CG-056 CG-055
CR-012
CL-016
(65A)
(50A)
(400A)
(40A)
CR-015
(40A)
CR-014
(50A)
(80A)
(400A)
ESD
ESD
CS-007
(50A)
(50A)
6 - 39
CL-073 CL-074
CL-015
CL-082 CL-081
(500A)
CR-709
(500A)
CL-014
(500A)
CL-071 CL-072
(500A)
CL-013
CL-012
CL-011
CL-010
ESD
CS-006
CL-080 CL-079
(80A)
(40A)
(80A)
(50A)
CR-011
CG-703
CS-704
CR-010
CS-005
(50A)
(65A)
(65A)
Ball Valve
(Manual Handle, Flanged Type)
Flow Meter
ESD
CR-013
CL-078 CL-077
(50A)
(600A)
(80A)
CR-009
(40A)
CL-069 CL-070
CL-067 CL-068
CL-076 CL-075
CS-053 CS-054
(50A)
CL-009
(400A)
(400A)
ESD
CS-051 CS-052
(400A)
CG-002
(600A)
(600A)
CR-016
(25A)
CG-001
CG-004
ESD
CG-054 CG-053
CG-052 CG-051
(400A)
(40A)
CR-003
(50A)
CG-003
Description
Butterfly Valve (Flanged Type)
CL-066 CL-065
(65A)
(65A)
Nitrogen Line
Symbol
CR-008
(50A)
(80A)
Spray Line
(400A)
ESD
CS-004
CL-064 CL-063
(500A)
CL-008
CL-007
(500A)
(80A)
Spray
Header
LNG Vapour Line
(400A)
ESD
CR-007
CR-006
CL-004
CL-003
(500A)
(40A)
CS-002
(80A)
(80A)
(80A)
CL-006
CS-003
CR-005
CS-703
CL-005
(50A)
(65A)
(80A)
(80A)
(500A)
ESD
Liquid
Header
Key
(50A)
(80A)
(80A)
CL-002
Vapour
Header
CS-701
CR-703
(50A)
CS-001
ESD
CL-062 CL-061
(65A)
CR-708
(400A)
CL-060 CL-059
CR-002
(40A)
CL-053 CL-054
CL-051 CL-052
CR-001
(50A)
CL-001
(400A)
CR-051 CR-052
CS-700
If the ship has to warm-up tanks for technical reasons, the stripping/spray pumps
will be used to discharge the remaining cargo on completion of the bulk
discharge with the main cargo pumps.
On completion of discharge, the loading arms and pipelines are purged and
drained to No. 4 cargo tank and the arms are then gas freed and disconnected.
Due to the manifold configuration, it is necessary to purge the cargo lines using
nitrogen at a pressure of at least 300kPa, this being done several times to ensure
successful draining at the manifold connections.
During cargo discharge, LNG vapour is supplied from shore to maintain pressure
in the cargo tanks.
The vapour arm remains connected until just before sailing if a delay is expected.
2. Operation
The main cargo pumps discharge LNG to the liquid header and then to shore via
the midship liquid crossover manifold connections.
After an initial rise, the pressure in the tanks decreases. It then becomes
necessary to supply vapour from shore via the manifold and crossover to the
vapour header into the cargo tank gas domes in order to maintain a pressure of
109kPaA.
Should the vapour return supply from shore be insufficient to maintain tank
pressures, other means of supplying vapour to the tanks, either by using the tank
sprayers or the LNG vaporiser, have to be used.
The gas heater should be prepared and lined up for use in order to avoid venting
cold LNG vapour through No.1 vent mast.
NOTE
All LNG terminals prohibit venting of flammable gas.
Ballasting is undertaken concurrently with discharging. The ballasting operation
is programmed to keep the vessel within the required limit of draught, trim, hull
stress and stability following indications obtained from the loading computer.
During the discharge period, the ship is kept on an even keel. If it is required to
empty a cargo tank, the ship is trimmed according to terminal maximum draught
by the stern to assist in stripping the tank.
These valves must be locked open at all times when the ship has cargo
on board, unless a tank is isolated and vented for any reason.
5) Vapour crossover:
Open valve CG703.
6) Main cargo pumps:
Check insulation resistance of electric motors and related cables prior to
supplying power to the cargo pumps.
7) Check connections of liquid and vapour arms.
Check communications with shore.
Check ship/shore link.
When shore is ready to purge the manifold connections with nitrogen supplied
from shore:
8) Liquid manifold connections (assuming port-side discharge):
y
Open drain valves CL053, 054, 061, 062, 067, 070, 077, 078.
y
Purge connections and then close the valves.
9) Vapour manifold connection:
y
Open drain valve CG053, 054.
y
Purge connection and then close the valves.
If shore agree:
10) Vapour manifold:
Open manifold ESD valve CG001.
11) Liquid connections:
Open manifold ESD valves CL001, 005, 009, 013.
2) Safety precautions:
- Ensure sprays for hull mid-ship water curtain are in operation.
- Prepare fire fighting equipment, water hoses and protective clothing
for use.
3) Cargo tank level alarms:
Switch on high level alarms (CTS level alarm enable).
12) Test Emergency Shut down System (ESDS) from shore and from the
ship as required. Re-open liquid and vapour ESD valves.
When it is agreed with shore, cool down may commence.
4) Cargo tank vapour domes - confirm that the following valves are open
and locked in position:
Each tank is normally discharged down to a level of about 0.5m. The quantity
retained in the tanks varies according to the length of the ballast voyage, the
expected elapsed time before loading and the volume of boil-off that is estimated
to be burned in the ships boilers.
NO.1 Tank
CG101/100
NO.2 Tank
CG201/200
NO.3 Tank
CG301/300
NO.4 Tank
CG401/400
6 - 40
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
(300A)
(400A)
(50A)
SP-100
CG-101
CS-108
(40A)
CL-110
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 41
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
(50A)
(65A)
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(400A)
(450A)
CL-305
CL-306
CL-007(500A)
CS-004(80A)
CS-006(80A)
(600A)
CG-703
ESD
Liquid Main
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(650A)
(8A)
(40A)
CS-308
(300A)
(300A)
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
Flow Meter
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
(700A)
(STBD)
(80A)
Cargo Pump
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Control Valve
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
Needle Valve
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Gas Main
(300A)
Ballast Line
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-701
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
Illustration 6.5.2a Liquid Line and Arm Cool Down before Discharging
S
Spray Pump
To cool-down the cargo discharge lines proceed as follows, assuming that No.3
stripping/spray pump is being used, all manifold lines and the ESD valves are
open and have been purged with nitrogen.
1) Open discharge valves CS301/303 from No.3 stripping/spray pump to
30 %.
BERTHING
SETTING OF THE SHORE GANGWAY
2) Open the following manifold valves CS001, 003, 005 and 007.
SHIP/SHORE PRE-UNLOADING MEETING
3) Open the spray line crossover and block valves CS701, 700 and 702.
The cooling down is complete when the shore side line and ships liquid line is
approximately -130 C.
7) Stop the No.3 stripping/spray pump and close discharge valve CS301.
Shut the valves CS001, 003, 005, 007 and CL002, 006, 010, 014.
Open valve CS300 to drain the line back to No.3 cargo tank.
8) When the spray line has warmed up, close the spray line crossover
valve CS071 and No.3 tank return valve CS300.
FINISH UNLOADING
SAMPLING
UNBERTHING
On completion of cool down and when shore is ready for discharge, proceed
with unloading.
6 - 42
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
CS-005
(80A)
(100A)
(650A)
(500A)
CL-003
CS-002(80A)
ESD
CL-004
(400A)
(400A)
ESD
CL-008
ESD
CG-004
CG-002
(400A)
(400A)
(300A)
CG-700
CG-701
(400A)
SP-100
CG-101
CS-107
(50A)
CS-108
(40A)
CL-110
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 43
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
SP-700
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
CS-701
CS-700
CL-700
(300A)
Spray Main
Sprayers
CG-702
(100A)
(50A)
(65A)
(400A)
(400A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
(600A)
CG-703
ESD
(400A)
(8A)
SP-300
CG-301
CR-304
CS-307
(50A)
CS-308
(40A)
CL-300
(300A)
(50A)
(80A)
CG-001
(400A)
ESD
(500A) CL-010
CL-011(500A)
CL-012
(450A)
(400A)
CR-305
(300A)
Liquid Main
CL-305
CL-306
(CL-308)
Foot Valve
Flow Meter
(650A)
CG-300
CS-300
CS-301
CS-302
CL-301
(300A)
(300A)
(400A)
(600A)
Emergency Pump Column
(400A)
(PORT)
S
Spray Pump
(600A)
(STBD)
(80A)
Cargo Pump
CL-302
CL-303
CL-304
FL-300
(300A)
(50A)
(65A)
(400A)
(400A)
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
2
(CL-408)
Foot Valve
Sprayers
Vapour Main
CS-304
(PORT)
(STBD)
(50A)
SA-356 SA-355
(8A)
SA-354 SA-353
SA-352 SA-351
(8A)
(8A)
CG-401
CS-407
SP-400
(50A)
(50A)
CS-408
(40A)
CL-400
(300A)
(300A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(300A)
CR-404
(50A)
(400A)
CR-405
Control Valve
(700A)
No.3 LNG
Vent Mast
(50A)
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
CS-404
Needle Valve
To Cofferdam
(80A)
CS-403
CL-410
No.4 LNG
Vent Mast
(400A)
(300A)
CS-702
(400A)
(450A)
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
(300A)
Ballast Line
Y-type Strainer
Gas Main
(300A)
CL-601
(300A)
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
SP-701
(400A)
(50A)
(50A)
(80A)
CS-008(80A)
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
CG-502
ESD
(40A)
(500A)
CS-504
CL-015
(40A)
CS-501
Description
Orifice
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
Symbol
Stripping Crossover
CG-529
(600A)
Liquid Crossover
No.1 H/D
Compressor
(600A)
CS-503
SP-602
ESD
CG-513
CG-525 CG-521
Vapour Crossover
(250A)
(450A)
CG-511
(600A)
CG-517
(600A)
CG-503
Key
Liquid Crossover
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
(300A)
(80A)
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
(300A)
CG-504
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
To Engine Room
CG-520
(750A)
CG-510
CS-007
CL-009
(400A)
S
Spray Pump
Refer to the next page for LNG quantity required for cooling down operations,
and quantity of cargo remaining in tanks after stripping.
Throttle in the main cargo pump discharge valve to 30% before stopping the
pump. If two main cargo pumps are in use in a tank, when the level reaches 0.80
m, throttle in the discharge valve on one pump to 30% and stop that pump. This
is in order to reduce turbulence around the pump suction.
On completion of cargo discharge and after all cargo pumps have been stopped:
When the shore terminal is ready to inject nitrogen and the pressure at the
manifold is 300kPa:
9) Request the vapour return from shore and continue to monitor the
pressure to confirm that it is stable.
10) As the discharge pressure and flow rate increase, continue to monitor
the pipe work and hard-arms for leakage.
11) Adjust the pump discharge valves to obtain optimum performance as
indicated by electrical load, discharge pressure and pump graph.
12) It is important to maintain the tanks at a pressure of at least 10 kPa in
order to avoid cavitation and to have good suction at the pumps. If the
tank pressure falls to 6 kPa, request shore to increase the gas return.
13) Start ballasting operations. Keep draught, trim and hull stresses within
permissible limits by controlling the various ballast tank levels. Refer to
trim and stability data provided.
14) Continue to monitor the tank pressures and the cargo pump electrical
6 - 44
(450A)
(350A)
LX
(250A)
No.1
BA-44
(300A)
No.2
BA-45
BA-41
FWD Ballast
Water Tank (P)
BA-38
BA-04
LX
LX
LIAHL
LIAHL
Bow
Thruster
and
Em'cy
Fire
Pump
Room
(40A)
BA-03
BA-46
BA-47
(40A)
LX
BA-05
BA-09
BA-11
LIAHL
LX
(200A)
LIAHL
BA-07
(550A)
(350A)
(200A)
BA-37
BA-42
(350A)
BA-06
BA-08
BA-10
TV-01
(250A)
Double O-ring
GRP Sleeve
BA-13
(200A)
(200A)
BA-35
(200A)
BA-40
LX
LIAHL
LX
(350A)
Fore Peak
Tank
(Void)
LIAHL
FWD Ballast
Water Tank (S)
LX
BA-43
Trunk
(750A)
BA-39
(550A)
BA-23
(350A)
No.3 Water
Ballast Pump
(3,000 m3/h x 30MTH)
(550A)
BA-34
Ballast
Stripping
Eductor
BA-22
BA-36
BA-28
LX
(550A)
(550A)
BA-32
LIAHL
(350A)
BA-21
LIAHL
(350A)
No.2 Water
Ballast Pump
TV-02
BA-20
BA-27
BA-12
(550A)
(40A)
BA-26
BA-19
BA-14
AFT Peak
Tank
No.1 Water
Ballast Pump
BA-15
(550A)
BA-30 BA-29
BA-25
LX
(550A)
(40A)
BA-31
(350A)
LIAHL
BA-18
BA-17 BA-16
BA-24
LIAHL
(350A)
LIAHL
BA-33
LX
(350A)
(350A)
To Main
Condenser
To I.G.G.
High Sea
Chest
Cargo Tank
Key
Sea Water Line
(Steel Pipe)
Sea Water Line
(G.R.P. Pipe)
Water Ballast
Tank (S)
(350A)
6 - 45
Pipe Duct
(350A)
6) When all the tanks are at their correct level, shut the each tank filling
valves.
1. Operating Procedures
It is assumed that the main sea water crossover pipe is already in use, supplying
other sea water systems (e.g. the main circulating system, sea water service
system) and that the cargo and ballast valve hydraulic system is also in service.
2. To Ballast by Gravity
CAUTION
Incorrect operation of the ballast system will cause damage to the GRP pipework. Damage is generally caused by a pressure surge due to sudden changes in
the flow and the presence of air pockets. During the ballasting operation great
care must be taken to ensure that flow rates are adjusted smoothly and
progressively. In particular, the pumping rate should be reduced to one pump
when filling only one tank and use made of the discharge to sea to further reduce
the rate before shutting the final tank valve.
It is necessary to eliminate any air pockets that may be present in the piping
before proceeding with the normal ballasting operations. This is achieved by
running ballast into either the forward ballast tank or No.1 ballast tank.
It is important not to compress any air in the system. To achieve this, the valve
admitting water to the system should be opened last.
All operations are carried out from the CCR using the keyboard in conjunction
with the mimic on the IAS graphic.
1) Open the valves BA-04 and BA-05 on the fwd ballast tanks.
2) Open the ballast pump sea suction main valves BA-19, BA-21 and BA23.
3) Open the gravity filling valves BA-18, BA-20, BA-22 and filling line
crossover valves BA-16, BA-17. When a flow has been established to
the fwd deep ballast tanks, the valves BA-04 and BA-05 can be shut.
4) Open the valve(s) on the tank(s) to be filled as per the ballast plan.
NO.1 W.B. TK (P/S)
BA-06 / BA-07
BA-08 / BA-09
BA-10 / BA-11
BA-12 / BA-13
7) Close the sea suction valves and filling line crossover valves BA-19,
BA-21, BA-23, BA-16, BA-17.
NOTE
The speed when filling by gravity will sharply decrease as the level of the water
line is approached. The tanks will require to be filled to their capacity with the
ballast pump.
Description
Position
BA-24
Open
BA-28
Open
6) When all the tanks reach the required final level, stop the pumps and
close the main ballast system down.
BA-06 / BA-07
BA-08 / BA-09
BA-10 / BA-11
BA-12 / BA-13
2) Prepare No.1 and No.3 ballast pumps for discharge to ballast tanks.
Two pumps are normally enough but three can be used if required. One
can be used if started in good time.
Valve
Description
Position
BA-18
Closed
BA-22
Closed
BA-19
Open
BA-23
Open
BA-16 / 17
Closed
BA-29 / 30
Open
BA-25
Open
BA-27
Open
5) As each tank reaches the required level, open the valve of the next tank
before closing the valve of the full tank.
6 - 46
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(50A)
(400A)
(300A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
M
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
(400A)
CL-110
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 47
CS-103
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Gas Main
(300A)
Ballast Line
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-701
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
Pre-dry docking, the ship will carry out a maximum discharge. The tank levels
should be reduced to the point pump down of main cargo pumps. Then, using the
stripping/spray pumps, remove the last of the cargo until they also trip on low
current. The ship will then proceed to sea and commence the warm up, inerting
and aerating operations, prior to arrival at the refit yard.
NOTE
The stripping / spray pump should be started at higher level than minimum start
level for the pump
1) At manifold crossover:
y Open the valve CS003.
y Close the double shut valves CL002, 006, 010, 014 and liquid
manifold ESD valves CL001, 009, 013, leaving CL005 open.
2) Stripping/spray header:
y Open the block valves CS702 and CS700.
y Open the valve CS701 stripping/spray header to liquid manifold
crossover.
3) At required tanks:
y Open the stripping/spray pump discharge valves from individual
tanks to give the required performance, CS101, 201, 301, 401.
y Open the stripping/spray header valves CS103, 203, 303, 403.
y Start the stripping/spray pump(s).
On completion:
When the shore terminal is ready to inject nitrogen and the pressure at the
manifold is 300kPa:
2) Open manifold bypass valves.
3) Close the bypass valve when pressure on manifold drops to 0 kPa.
Repeat the operation twice more. On the last operation shut the bypass
valve at approximately 100kPa, in order to eliminate the risk of liquid
back flow from ships liquid line.
100A Spray
Open the test drain valve on the loading arm to ensure that there is no liquid
present. When the required amount of methane (usually less than 1 %) is showing
at the drain valve, close the shore terminal ESDS valves.
650A Liquid
7118
It is assumed that the cargo tanks have been discharged to their maximum with
the main cargo pumps, which have been shut down. Discharge is via the port
side manifold.
1) Open valves CL002, 006, 010, 014 and No4 cargo tank filling valve
CL400 for liquid draining.
5) Complete the ballasting operations for the final measurement and for
the sailing condition.
650A Liquid
650A Liquid
3800
3800
650A Liquid
650A Liquid
4489
3000
6 - 48
6000
3000
3157
400A Liquid
3000
400A Liquid
400A Liquid
500A Liquid
500A Liquid
5) When completed:
y Leave open the valves CS702, 700 and 701 in order to warm up
the line.
y When the line has warmed up, close these valves.
4460
865
500A Liquid
Case 2 :
Case :
The Cargo collection procedure is as follows.
NOTE
The pressure in liquid cross-over and header during pressurization by N2 supply
shall be monitored on the IAS and also local gauge board near by cross-over,
and the manual valves mentioned on above Case 1 7)&8) can be controlled
easily.
5) Supply N2 gas to the liquid header and monitor the pressure in liquid
line on the IAS and also local gauge board.
6) Pressurisation of liquid line by N2 gas up to about 300~400kPa.
Illustration 6.6.1c Typical Section for Cross-over Piping
6467
14546
650A Liquid
495
2075
650A Liquid
600 900
1849
Trunk Deck
(33,090 A/B)
350
2954
Drain Valve
1082
6 - 49
3150
400A Liquid
Drain Valve
1388
3805
1653
1100
5275
830
651
1691
Liquid Sampling
Valve
Blank Page
6 - 50
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(400A)
(300A)
(400A)
(50A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 51
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
Ballast Line
Gas Main
(300A)
SP-701
CG-600
CG-605
(700A)
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-600
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
3. Operating Procedure
1. Introduction
During the tank warm up, gas burning may be used and manually controlled by
directing some vapour from the heater outlet to the boilers.
Tank warm-up is part of the gas-freeing operations carried out prior to a dry
docking or when preparing tanks for inspection purposes.
Purpose
The tanks are warmed up by re-circulating heated LNG vapour. The vapour is recirculated with the two HD compressors and heated with the HD heater to a
preset value (1st stage: 0C, 2nd stage: 75C).
Performance Criteria
Auxiliaries Involved
The warm up operation continues until the temperature at the coldest point of the
secondary barrier of each tank reaches 5C.
HD Compressor
HD Heater
Operation Duration
Check Points
The warm up operation requires a period of time dependent on both the amount
and the composition of liquid remaining in the tanks and the temperature of the
tanks and insulation spaces. Generally, the warm up will require about 36 hours
after vaporising the remaining liquid.
Initially, the tank temperatures will rise slowly as evaporation of the LNG
proceeds, accompanied by high vapour generation and venting. A venting rate of
approximately 8,000m3/h at 60C can be expected.
On completion of evaporation, tank temperatures will rise rapidly and the rate of
venting will fall to between 1,000 and 2,000m3/h at steadily increasing
temperatures.
Temperatures within the tank and insulation are indicated in the CCR.
Rolling and pitching of the vessel will assist evaporation. Temperature sensors at
the aft end of the tank give a good indication of the progress of warm-up. Slight
listing of the vessel will assist in correcting uneven warm-up in any one tank.
Gas burning should continue as long as possible, normally until all the liquid has
evaporated, venting ceased and tank pressures start to fall.
2. Preparation for Tank Warm Up
1) Strip all possible LNG from all tanks.
2) When discharging the final cargo, remove the maximum LNG with the
stripping/spray pumps.
3) If discharge of LNG to shore is not possible, vaporize it in the LNG
vaporiser and vent the vapour to the atmosphere through the No.1 vent
mast.
4) If venting to the atmosphere is not permitted, the vapour must be burned
in the boilers.
5) For maximum stripping, the ship should have zero list and should be
trimmed down at least 2.6m by the stern.
6) Run the stripping pumps until pump down level.
7) Remove any emergency pump that may have been placed in a cargo
tank.
CL310/CL300
Open
CL410/CL400
Open
12) Start both HD compressors manually and gradually increase flow using
the inlet guide vane position.
13) Monitor the tank pressure and adjust the compressor flow for
maintaining the tank pressure at about 16kPa. It is also possible to
control tank pressure by valve CG701 via No.1 vent mast.
Alternatively the emergency vent header may be used to exhaust excess
vapour to No.1 vent mast through valves CG602 and CG700. However,
the liquid header should normally be used for the warming-up operation
rather then the emergency vent.
14) Check that the pressure in the insulation spaces, which have a tendency
to increase, remains inside the preset limits.
1) Install the spool piece SP600 connecting the heater outlet line to the
liquid header & SP700 connecting to the liquid header to No.1 vent
mast.
15) Monitor the temperatures in each tank and adjust the opening value of
the liquid filling valve to make the temperature progression in all the
tanks uniform.
2) Open the valve CL601 to discharge heated vapour to the liquid header.
17) Purge the emergency pump column with N2 to remove liquid in the
column.
18) At the end of the operation, when the coldest temperature of the
secondary barrier is at least +5C, or before switching to the second step,
stop and shut down the gas burning system if used. Stop both HD
compressors, shut the filling valves on all tanks and restore the normal
venting from the vapour header.
19) As an alternative operation, the target temperature in the cargo tank is to
be at least +5C when inerting with hot inert gas is initiated. In this case
the total operating time for warming up and inerting is approximately
36 hours
Description
Position
CL110/CL100
Open
CL210/CL200
Open
6 - 52
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(400A)
(300A)
(400A)
(50A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 53
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
Ballast Line
Gas Main
(300A)
SP-701
CG-600
CG-605
(700A)
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-600
Inert Gas
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
Warm Natural Gas
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
3) Remove the spool piece SP700 between the liquid header and No.1 vent
mast.
1. Introduction
After the tanks have been warmed up, the LNG vapour is displaced with inert
gas.
Inert gas from the inert gas plant is introduced at the bottom of the tanks through
the LNG filling piping. Gas from the tanks is vented from the top of the tank
through the vapour header. This form of layering the inert gas in the tanks and
the removal of LNG vapour is termed the piston effect. This layering of inert gas
enables the displaced vapour to be directed to the boilers as boil-off gas via an
LD compressor in order that only a minimum amount of vapour will be vented
via the No.1 vent mast during the later stage in the inerting process.
There are sample points in each tank at varying layers from near to the bottom to
near the top of each tank. As the interface of inert gas and LNG vapour is nearing
the upper sample point the gas burning should be stopped and the LD
compressor shut down. Displaced gas should now be directed to No.1 vent mast,
or to shore if in port.
Inerting is necessary to prevent the possibility of having an air/LNG vapour
mixture in the flammable range. The operation is continued until the
hydrocarbon content is reduced to less than 2 %. The operation requires about 20
hours.
In addition to the cargo tanks, all pipe work and fittings must be inerted. This is
best done with inert gas or nitrogen whilst the plant is in operation for inerting
the cargo tanks.
2. Operating Procedure for Inerting Cargo Tanks
(See Illustration 6.6.3a)
Description
Position
CL601
Open
CL110
Open
CL210
Open
CL310
Open
CL410
Open
Description
Position
CL100
Open
CL200
Open
CL300
Open
CL400
Open
Valve
Description
Open valve CG702 to vent through the forward vent mast riser, the tank
pressure is controlled via valve CG701.
13) During tank inerting, purge the LNG vapour contained in the lines and
equipment for about 5 minutes, or until the CH4 content is reduced to
1% at the sample point valves.
When the cargo tanks are fully inerted the inert gas generator can be
shut down. The inert gas in the cargo tanks can be used as a reservoir
for supplying the purge gas to the equipment and associated pipelines.
14) When the operation is complete, stop the supply of inert gas and change
over the inert gas plant to supply dry-air.
WARNING
If any piping or components are to be opened, the inert gas or nitrogen must first
be flushed out with dry air. Take precautions to avoid concentrations of inert gas
or nitrogen in confined spaces which could be hazardous to personnel
Position
CG100,101
Open
CG200,201
Open
Performance Criteria
CG300,301
Open
Auxiliaries Involved
CG300,301
Open
Operation Duration
Check Points
2) Install the spool piece SP600 connecting the IG line to the liquid header.
Purpose
1) Prepare the inert gas plant for use in the inert gas mode.
6 - 54
ESD
CL-001
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
(500A)
CL-003
(100A)
CS-002(80A)
CL-007(500A)
ESD
CL-004
ESD
Flow Meter
CL057CL058
(400A)
(400A)
(400A)
(400A)
CG-100
CS-100
CG-101
CS-107
SP-100
(50A)
(50A)
CS-108
(40A)
CL-100
(300A)
(300A)
(300A)
CR-104
(PORT)
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
CL-105
(400A)
Sprayers
Cargo Pump
(80A)
(80A)
CL-106
(400A)
(600A)
(50A)
CR-105
(STBD)
CS-101
CS-102
CL-101
CL-102
CL-103
CL-104
(300A)
(400A)
(50A)
(65A)
(400A)
(400A)
CL-205
(400A)
CL-206
(600A)
Sprayers
S
Spray Pump
CS-104
FL-100
SA-156 SA-155
(8A)
(8A)
SA-154 SA-153
CG-200
SA-152 SA-151
CS-207
(50A)
SP-200
CG-201
(300A)
(8A)
(40A)
(50A)
CS-208
CL-200
CR-205
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
(PORT)
CG-701
CS-201
CS-202
CL-201
(300A)
CS-103
CL-110
No.2 LNG
Vent Mast
(STBD)
Cargo Pump
SP-700
(450A)
(400A)
(65A)
CL-700
CG-700
(400A)
(100A)
(300A)
6 - 55
(300A)
(450A)
CS-204
CL-202
M
(300A)
(CL-208)
Foot Valve
CG-702
(400A)
(50A)
S
Spray Pump
(300A)
CS-203
CL-210
CL-203
CL-204
M
FL-200
SA-256 SA-255
SA-254 SA-253
Sprayers
(50A)
(65A)
(400A)
(400A)
Cargo Pump
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
CS-004(80A)
CS-006(80A)
CS-701
CS-700
(8A)
(8A)
SA-252 SA-251
SP-300
(50A)
CS-307
CR-304
CG-301
(300A)
(8A)
(40A)
(50A)
CS-308
CL-300
CR-305
CL-305
CL-306
(CL-308)
Foot Valve
(600A)
(400A)
CG-300
CS-300
CS-301
CS-302
CL-301
(300A)
(300A)
(400A)
(600A)
Emergency Pump Column
(400A)
(400A)
(400A)
ESD
CG-003
CG-001
ESD
CL-009
CL-011(500A)
CL-012
(450A)
(400A)
Spray Main
(100A)
(PORT)
S
Spray Pump
CL754 CL753
(STBD)
(80A)
Cargo Pump
CL-302
CL-303
CL-304
FL-300
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
2
(CL-408)
Foot Valve
Main
CS-304
(PORT)
(STBD)
(50A)
SA-356 SA-355
SA-354 SA-353
(8A)
(8A)
SA-352 SA-351
CG-401
CS-407
SP-400
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
CR-404
(50A)
CL065CL066
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
CS-303
CL-310
Control Valve
To Cofferdam
(80A)
CS-403
CL-410
CS-404
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
Needle Valve
(300A)
Liquid Main
(650A)
CS-600
(80A)
CL074CL073
(750A)
(65A)
(400A)
(300A)
(450A)
Y-type Strainer
Gas Main
(700A) Vapour
(700A)
(650A)
CL-600
(300A)
CL-601
(300A)
Ballast Line
(400A)
CG-601
(80A)
CG-602
CG-603
(700A)
CL082CL081
(300A)
(300A)
SP-701
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
(80A)
ESD
CS-502
CS-506
(500A)
Forcing
Vaporuizer
CL-015
CS-505
(600A)
CS-501
CG-502
CS-510
(50A)
CS-704
(600A)
CS-504
(40A)
(25A)
LNG
Vaporuizer
Inert Gas
CS-703
(40A)
CG-501
SP-602
(80A)
(600A)
(300A)
CS-503
CG-511
CG-529
(600A)
Description
Orifice
Stripping Crossover
No.1 H/D
Compressor
(450A)
CG-500
ESD
CG-513
(650A)
(250A)
CG-525 CG-521
Liquid Crossover
CG-503
(400A)
CG-507
(600A)
CG-517
Vapour Crossover
(450A)
Symbol
(600A)
No.2 H/D
Compressor
Key
Warm Natural Gas
CL051 CL052
CG-514
CG-526 CG-522
High Duty
Heater
(300A)
(80A)
Liquid Crossover
CG-505
(700A)
CG-518
(250A)
Mist
Separator
(650A)
(350A)
CG-530
CG-512
CG-509
CG-515
No.1 L/D
Compressor
(250A)
(500A) CL-010
(150A)
CG-527 CG-523
(500A)
CG-504
(300A)
CG-508
(300A)
To Engine Room
CG-519
(300A)
(250A)
CL-014
No.2 L/D
Compressor
(300A)
Low Duty
Heater
CG-606
CG-516
CG-528 CG-524
CL060 CL059
CL067 CL068
CL-013
(150A)
CG-506
(750A)
CG-510
(400A)
CL076 CL075
CG-520
CS-007
(400A)
(400A)
S
Spray Pump
CL011
Open
CL015
Open
During the inerting of the tanks it is also necessary to purge all the dead ends of
the liquid line to ensure there is no hydrocarbon remaining;
CL004
Open
CL008
Open
1) Purge the dead section of the liquid header by opening the liquid header to
No.1 vent mast crossover valve CL700, open the sample valve
CL753/CL754 and vent to atmosphere until the hydrocarbon content is
less than 1%.
CL012
Open
CL016
Open
Description
Position
Valve
Description
Position
CL002
Open
CL057,058
Open
CL006
Open
CL065,066
Open
CL010
Open
CL073,074
Open
CL014
Open
CL081,082
Open
CL001
Open
CL005
Open
CL009
Open
CL013
Open
Description
Position
CL051,052
Open
CL059,060
Open
CL067,068
Open
CL075,076
Open
CR701,706
Description
Position
Operate
CR108
Operate
CR208
Operate
CR308
Operate
CR403
Operate
Description
Position
CL003
Open
CL007
Open
6 - 56
ESD
CL-001
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
(500A)
CL-003
(100A)
CS-002(80A)
CL-007(500A)
ESD
CL-004
ESD
Flow Meter
CL057CL058
(400A)
(400A)
(400A)
(400A)
CG-100
CS-100
CG-101
CS-107
SP-100
(50A)
(50A)
CS-108
(40A)
CL-100
(300A)
(300A)
(300A)
CR-104
(PORT)
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
CL-105
(400A)
Sprayers
Cargo Pump
(80A)
(80A)
CL-106
(400A)
(600A)
(50A)
CR-105
(STBD)
CS-101
CS-102
CL-101
CL-102
CL-103
CL-104
(300A)
(400A)
(50A)
(65A)
(400A)
(400A)
CL-205
(400A)
CL-206
(600A)
Sprayers
S
Spray Pump
CS-104
FL-100
SA-156 SA-155
(8A)
(8A)
SA-154 SA-153
CG-200
SA-152 SA-151
CS-207
(50A)
SP-200
CG-201
(300A)
(8A)
(40A)
(50A)
CS-208
CL-200
CR-205
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
(PORT)
CG-701
CS-201
CS-202
CL-201
(300A)
CS-103
CL-110
No.2 LNG
Vent Mast
(STBD)
Cargo Pump
SP-700
(450A)
(400A)
(65A)
CL-700
CG-700
(400A)
(100A)
(300A)
6 - 57
(300A)
(450A)
CS-204
CL-202
M
(300A)
(CL-208)
Foot Valve
CG-702
(400A)
(50A)
S
Spray Pump
(300A)
CS-203
CL-210
CL-203
CL-204
M
FL-200
SA-256 SA-255
SA-254 SA-253
Sprayers
(50A)
(65A)
(400A)
(400A)
Cargo Pump
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
CS-004(80A)
CS-006(80A)
CS-701
CS-700
(8A)
(8A)
SA-252 SA-251
SP-300
(50A)
CS-307
CR-304
CG-301
(300A)
(8A)
(40A)
(50A)
CS-308
CL-300
CR-305
CL-305
CL-306
(CL-308)
Foot Valve
(600A)
(400A)
CG-300
CS-300
CS-301
CS-302
CL-301
(300A)
(300A)
(400A)
(600A)
Emergency Pump Column
(400A)
(400A)
(400A)
ESD
CG-003
CG-001
ESD
CL-009
CL-011(500A)
CL-012
(450A)
(400A)
Spray Main
(100A)
(PORT)
S
Spray Pump
CL754 CL753
(STBD)
(80A)
Cargo Pump
CL-302
CL-303
CL-304
FL-300
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
2
(CL-408)
Foot Valve
Main
CS-304
(PORT)
(STBD)
(50A)
SA-356 SA-355
SA-354 SA-353
(8A)
(8A)
SA-352 SA-351
CG-401
CS-407
SP-400
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
CR-404
(50A)
CL065CL066
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
CS-303
CL-310
Control Valve
To Cofferdam
(80A)
CS-403
CL-410
CS-404
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
Needle Valve
(300A)
Liquid Main
(650A)
CS-600
(80A)
CL074CL073
(750A)
(65A)
(400A)
(300A)
(450A)
Y-type Strainer
Gas Main
(700A) Vapour
(700A)
(650A)
CL-600
(300A)
CL-601
(300A)
Ballast Line
(400A)
CG-601
(80A)
CG-602
CG-603
(700A)
CL082CL081
(300A)
(300A)
SP-701
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
(80A)
ESD
CS-502
CS-506
(500A)
Forcing
Vaporuizer
CL-015
CS-505
(600A)
CS-501
CG-502
CS-510
(50A)
CS-704
(600A)
CS-504
(40A)
(25A)
LNG
Vaporuizer
Inert Gas
CS-703
(40A)
CG-501
SP-602
(80A)
(600A)
(300A)
CS-503
CG-511
CG-529
(600A)
Description
Orifice
Stripping Crossover
No.1 H/D
Compressor
(450A)
CG-500
ESD
CG-513
(650A)
(250A)
CG-525 CG-521
Liquid Crossover
CG-503
(400A)
CG-507
(600A)
CG-517
Vapour Crossover
(450A)
Symbol
(600A)
No.2 H/D
Compressor
Key
Mixture Gas (Tank Out)
CL051 CL052
CG-514
CG-526 CG-522
High Duty
Heater
(300A)
(80A)
Liquid Crossover
CG-505
(700A)
CG-518
(250A)
Mist
Separator
(650A)
(350A)
CG-530
CG-512
CG-509
CG-515
No.1 L/D
Compressor
(250A)
(500A) CL-010
(150A)
CG-527 CG-523
(500A)
CG-504
(300A)
CG-508
(300A)
To Engine Room
CG-519
(300A)
(250A)
CL-014
No.2 L/D
Compressor
(300A)
Low Duty
Heater
CG-606
CG-516
CG-528 CG-524
CL060 CL059
CL067 CL068
CL-013
(150A)
CG-506
(750A)
CG-510
(400A)
CL076 CL075
CG-520
CS-007
(400A)
(400A)
S
Spray Pump
The spray line, forcing vaporiser and safety valves are inerted after completion
of the liquid line inerting;
1) Open the spray crossover from the liquid line and the spray master to each
cargo tank;
Valve
Description
Valve
Position
Valve
Description
Position
Description
Position
CL057,058
Open
CL065,066
Open
CL001
Open
CL073,074
Open
CL005
Open
CL081,082
Open
CL009
Open
CL013
Open
CS001
Open
CS003
Open
CL600,CS600
Open
CS702,CS701
CS700
Open
CS103
Open
CS005
Open
Valve
CS203
Open
CS007
Open
Operate
CS303
Open
CR001,CR005
CR009,CR013
CS403
Open
CR004,CR008
CR012,CR016
Operate
CR704,CR705
CR703
Operate
CR106
Operate
Valve
Valve
Description
CS100
Open
Open
CS107,108
Position
Description
Position
12) Purge the relief/safety valves on the spray system using the lifting handles.
Description
Position
CL051,052
Open
CL059,060
Open
CR206
Operate
CL067,068
Open
CR306
Operate
CL075,076
Open
CR406
Operate
Description
CS200
Open
Open
Valve
Open
CL004
Open
Open
CL008
Open
Open
CL012
Open
Open
CL016
Open
CS002
Open
CS004
Open
CS006
Open
CS008
Open
CS207,208
CS300
CS307,308
CS400
CS407,408
Position
4) While purging each tank spray lines, remove the blank on the IBS
stripping connection and purge the short section of lie by opening the
valve for approximately 5 minutes;
Valve
Description
Position
CS106
Open
CS206
Open
CS306
Open
CS406
Open
Position
10) Open the vent sample lines in sequence for approximately 5 minutes or
until the hydrocarbon content is less than 1%;
6 - 58
(400A)
(50A)
ESD
(400A)
ESD
CL-001
CL-005
(50A)
CS-001
CL-002
CL-006
(500A)
(65A)
CS-003
(50A)
(65A)
(80A)
(50A)
ESD
(600A)
CS-051 CS-052
CS-005
(500A)
(50A)
(65A)
(80A)
(80A)
Needle Valve
CS-703 (80A)
Control Valve
CR-053 CR-054
(80A)
(50A)
CL-003
CL-007
(500A)
(500A)
CS-002
(80A)
CS-004
(65A)
(50A)
(600A)
(600A)
(80A)
(50A)
CS-006
CL-011
(500A)
(500A)
(65A)
(80A)
(80A)
(65A)
(15A)
CS-553 CS-554
(80A)
CL-015
CS-552 CS-551
(50A)
CG-703
Forcing
Vaporuizer
CR-703
CS-704
CS-008
(40A)
(80A)
Description
Orifice
(50A)
(50A)
(500A)
CG-502
CS-502
CS-506
Symbol
CR-002
(600A)
CR-505
CS-505
CR-708
(600A)
CS-501
Inert Gas
CR-001
(80A)
(80A)
CR-504
CR-006
CG-513
CR-503
CS-504
CR-501
CS-510
LNG
Vaporuizer
(40A)
(40A)
CR-709
CS-054 CS-053
(25A)
(40A)
CG-003
CG-001
(50A)
ESD
ESD
CL-009
(80A)
(65A)
CL-010
CS-007
CL-014
CR-010
(500A)
CR-005
Key
(750A)
(40A)
(25A)
(300A)
CS-509
(40A) CR-009
CR-014
(50A)
(300A)
(50A)
(300A)
CL-013
(40A)
(400A)
CL-053 CL-054
(400A)
CL-051 CL-052
CL-062 CL-061
(400A)
CL-060 CL-059
CG-054 CG-053
(80A)
CG-569 CG-570
CG-567 CG-568
CG-514
(40A)
(25A)
CG-501
CS-508
CG-052 CG-051
CL-069 CL-070
(300A)
CS-503
CR-502
(300A)
CG-529
(25A)
(50A)
Mist
Separator
(600A)
(600A)
CG-500
CG-511
CG-565 CG-566
No.1 H/D
Compressor
(450A)
CL-067 CL-068
CL-078 CL-077
(25A)
(250A)
CG-525 CG-521
CG-515
(600A)
CG-517
CL-076 CL-075
CR-013
CG-516
CG-563 CG-564
CG-571 CG-572
CG-507
No.2 H/D
Compressor
(450A)
CG-503
CG-518
(250A)
CG-526 CG-522
CG-555 CG-556
High Duty
Heater
CG-519
No.1 L/D
Compressor
CG-573 CG-574
CG-505
(700A)
CG-527 CG-523
(250A)
CG-530
CG-559 CG-560
CG-509
(350A)
(300A)
CG-512
To Engine Room
(150A)
No.2 L/D
Compressor
(250A)
CG-504
CG-520
CS-507
CG-508
CG-606
CG-528 CG-524
CG-557 CG-558
Low Duty
Heater
CG-577 CG-578
CG-506
(400A)
(150A)
CG-575 CG-576
CG-561 CG-562
CG-510
CG-601
(700A)
CG-056 CG-055
CL-064 CL-063
CL-073 CL-074
CG-058 CG-057
CL-066 CL-065
Gas Main
(400A)
CR-008
CL-071 CL-072
(50A)
ESD
ESD
CL-004
CL-008
(50A)
ESD
CG-004
ESD
ESD
CG-002
(400A)
(25A)
(40A)
Flow Meter
(40A)
CR-004
CL-055 CL-056
CL-057 CL-058
(300A)
(300A)
Vapour Main
(600A)
(400A)
(650A)
Liquid Main
(450A)
(400A)
6 - 59
(100A)
(65A)
(400A)
(300A)
CG-702
CG-700
(300A)
CS-700
SP-700
CG-701
Spray Main
CL-700
(450A)
(100A)
CS-701
(400A)
CR-704
(300A)
CS-702
(80A)
(450A)
CR-705
(400A)
(80A)
(700A)
(750A)
CR-706
(300A)
CS-600
(400A)
(300A)
(80A)
CR-012
Y-type Strainer
CR-003
To Cofferdam
(150A)
(450A)
CL-600
(450A)
(65A)
CL-082 CL-081
(300A)
(650A)
CL-601
SP-701
(100A)
(300A)
Ballast Line
(700A)
CL-080 CL-079
CR-600
(300A)
SP-600
CG-603
(80A)
(80A)
CG-602
CG-605
CR-016
CG-600
(40A)
CR-007
(400A)
CG-604
(700A)
(400A)
SP-601
SP-602
(400A)
(40A)
(50A)
CR-011
CL-012
CR-015
CL-016
(50A)
(15A)
Valve
Description
CS551,CS552
Description
Position
Position
Open
3) On completion close the sample valves and prepare to purge the next
piece of machinery.
Description
Position
CG523
Open
CG524
Open
CS506
Open
CS502
Open
Compressors
CG521
Open
CS504
Open
CG522
Open
CS507
Open
The HD/LD compressors can be purged via the forcing vvaporiser discharge
line;
CG530
Open
CG503
Open
CG504
Open
CG507
Open
CG508
Open
CG505
Open
CG506
Open
1) Purge the relief/safety valves on the forcing vaporiser using the lifting
handles;
Valve
CR501,CR503
CR505
Description
Forcing vaporiser relief/safety valves
Position
Operate
2) Open the sample valves and purge until the hydrocarbon content is less
than 1%;
Valve
CS553,CS554
Description
Forcing vaporiser sample valves
Position
Open
3) On completion close the sample valves and prepare to purge the next
piece of machinery.
Description
LNG vaporiser inlet block valve
Open
CS501
Open
CS508
CR502,CR504
CS507
Close
CG502
Open
CG515
Open
CG516
Open
CG513
Open
CG514
Open
CG519
Open
CG520
Open
CG517
Open
CG518
Open
Description
Forcing vaporiser relief/safety valves
Valve
Description
No.1 LD compressor sample valves
Open
Open
CG569,CG570
CG577,CG578
Open
Open
CG563,CG564
CG571,CG572
Open
CG565,CG566
CG573,CG574
Open
Position
1) Open the sample valves and purge until the hydrocarbon content is less
than 1%;
Valve
Description
Position
CG555,CG556
CG559,CG560
Open
CG557,CG558
CG561,CG562
Open
2) On completion close the sample valves and prepare to purge the next
piece of machinery.
Position
CG567,CG568
CG575,CG576
1) Purge the relief/safety valves on the LNG vaporiser using the lifting
handles;
Valve
Position
Position
CS505
CS503,CS510
Description
1) Open the sample valve and purge until the hydrocarbon content is less
than 1%;
LNG Vaporiser
Valve
Valve
2) On completion close the sample valves and prepare to purge the next
piece of machinery.
Operate
2) Open the sample valves and purge until the hydrocarbon content is less
than 1%;
6 - 60
(400A)
(50A)
ESD
(400A)
ESD
CL-001
CL-005
(50A)
CS-001
CL-002
CL-006
(500A)
(65A)
CS-003
(50A)
(65A)
(80A)
(50A)
ESD
(600A)
CS-051 CS-052
CS-005
(500A)
(50A)
(65A)
(80A)
(80A)
Needle Valve
CS-703 (80A)
Control Valve
CR-053 CR-054
(80A)
(50A)
CL-003
CL-007
(500A)
(500A)
CS-002
(80A)
CS-004
(65A)
(50A)
(600A)
(600A)
(80A)
(50A)
CS-006
CL-011
(500A)
(500A)
(65A)
(80A)
(80A)
(65A)
(15A)
CS-553 CS-554
(80A)
CL-015
CS-552 CS-551
(50A)
CG-703
Forcing
Vaporuizer
CR-703
CS-704
CS-008
(40A)
(80A)
Description
Orifice
(50A)
(50A)
(500A)
CG-502
CS-502
CS-506
Symbol
CR-002
(600A)
CR-505
CS-505
CR-708
(600A)
CS-501
Inert Gas
CR-001
(80A)
(80A)
CR-504
CR-006
CG-513
CR-503
CS-504
CR-501
CS-510
LNG
Vaporuizer
(40A)
(40A)
CR-709
CS-054 CS-053
(25A)
(40A)
CG-003
CG-001
(50A)
ESD
ESD
CL-009
(80A)
(65A)
CL-010
CS-007
CL-014
CR-010
(500A)
CR-005
Key
(750A)
(40A)
(25A)
(300A)
CS-509
(40A) CR-009
CR-014
(50A)
(300A)
(50A)
(300A)
CL-013
(40A)
(400A)
CL-053 CL-054
(400A)
CL-051 CL-052
CL-062 CL-061
(400A)
CL-060 CL-059
CG-054 CG-053
(80A)
CG-569 CG-570
CG-567 CG-568
CG-514
(40A)
(25A)
CG-501
CS-508
CG-052 CG-051
CL-069 CL-070
(300A)
CS-503
CR-502
(300A)
CG-529
(25A)
(50A)
Mist
Separator
(600A)
(600A)
CG-500
CG-511
CG-565 CG-566
No.1 H/D
Compressor
(450A)
CL-067 CL-068
CL-078 CL-077
(25A)
(250A)
CG-525 CG-521
CG-515
(600A)
CG-517
CL-076 CL-075
CR-013
CG-516
CG-563 CG-564
CG-571 CG-572
CG-507
No.2 H/D
Compressor
(450A)
CG-503
CG-518
(250A)
CG-526 CG-522
CG-555 CG-556
High Duty
Heater
CG-519
No.1 L/D
Compressor
CG-573 CG-574
CG-505
(700A)
CG-527 CG-523
(250A)
CG-530
CG-559 CG-560
CG-509
(350A)
(300A)
CG-512
To Engine Room
(150A)
No.2 L/D
Compressor
(250A)
CG-504
CG-520
CS-507
CG-508
CG-606
CG-528 CG-524
CG-557 CG-558
Low Duty
Heater
CG-577 CG-578
CG-506
(400A)
(150A)
CG-575 CG-576
CG-561 CG-562
CG-510
CG-601
(700A)
CG-056 CG-055
CL-064 CL-063
CL-073 CL-074
CG-058 CG-057
CL-066 CL-065
Gas Main
(400A)
CR-008
CL-071 CL-072
(50A)
ESD
ESD
CL-004
CL-008
(50A)
ESD
CG-004
ESD
ESD
CG-002
(400A)
(25A)
(40A)
Flow Meter
(40A)
CR-004
CL-055 CL-056
CL-057 CL-058
(300A)
(300A)
Vapour Main
(600A)
(400A)
(650A)
Liquid Main
(450A)
(400A)
6 - 61
(100A)
(65A)
(400A)
(300A)
CG-702
CG-700
(300A)
CS-700
SP-700
CG-701
Spray Main
CL-700
(450A)
(100A)
CS-701
(400A)
CR-704
(300A)
CS-702
(80A)
(450A)
CR-705
(400A)
(80A)
(700A)
(750A)
CR-706
(300A)
CS-600
(400A)
(300A)
(80A)
CR-012
Y-type Strainer
CR-003
To Cofferdam
(150A)
(450A)
CL-600
(450A)
(65A)
CL-082 CL-081
(300A)
(650A)
CL-601
SP-701
(100A)
(300A)
Ballast Line
(700A)
CL-080 CL-079
CR-600
(300A)
SP-600
CG-603
(80A)
(80A)
CG-602
CG-605
CR-016
CG-600
(40A)
CR-007
(400A)
CG-604
(700A)
(400A)
SP-601
SP-602
(400A)
(40A)
(50A)
CR-011
CL-012
CR-015
CL-016
(50A)
(15A)
Description
Position
CG509
Open
CG510
Open
CG501
Open
Open
Open
Open
CG600
Open
CG001,CG002
Open
CG003,CG004
Open
CG051,CG052
CG057,CG058
Open
CG511,CG512
CG529
CG601,CG603
CG604,CG605
1) Purge the line through the sample valves until the hydrocarbon contents is
less than 1%.
2) To clear the dead end between valve CG605 and CL601 ease back the
blank flange and purge for approximately five minutes.
Cargo Tank Safety Valves and Pump Discharge Columns
Purge the tank safety valves by operating the manual lifting device, the
hydrocarbon content can be checked at the vent mast sample valves.
Purge all the cargo pump, emergency pump and spray pump columns by opening
the sample valves situated near to the respective pump discharge valves. Check
the hydrocarbon content and when less than 1% close the sample valves.
When all tanks, cargo pipe work and machinery have been purged with inert gas
and the boiler gas inlet with nitrogen, the system can be changed over ready to
aerate.
6 - 62
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(400A)
(300A)
(400A)
(50A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
6 - 63
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
Ballast Line
Gas Main
(300A)
SP-701
CG-600
CG-605
(700A)
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-600
Dry Air
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
Inert Gas
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
3. Operating Procedure
1. Introduction
Purpose
Prior to entry into the cargo tanks the inert gas must be replaced with air.
Performance Criteria
Auxiliaries Involved
Operation Duration
Check Points
Aeration is not complete until, at each stage, the oxygen content is more than
20%, the carbon dioxide content 0.5%, or less and the carbon monoxide content
is 50ppm or less.
With the Inert-Gas and Dry-Air System in Dry-Air production mode, the cargo
tanks are purged with dry air until a reading of 20% oxygen by volume is
reached.
2. Operation
1) Prepare the inert gas plant for use in the dry-air mode.
The Inert-Gas and Dry-Air System produces dry air with a dew point of -45C.
2) Install the spool piece SP600 connecting the Dry air line to the vapour
header
The dry-air enters the cargo tanks via the vapour header, to the individual vapour
domes.
The inert-gas/dry-air mixture is exhausted from the bottom of the tanks to the
atmosphere at No.1 vent mast via the tank filling pipes, the liquid header, valve
CL700, spool piece SP700 and valve CG701. During aerating, the pressure in the
tanks must be kept low to maximize the piston effect
The operation is complete when all the tanks have a 20% oxygen value and a
methane content of less than 0.2% by volume (or whatever is required by the
relevant authorities) and a dew point below -40C.
13) During the time that dry air from the inert gas plant is supplied to the
tanks, use the dry air to flush out inert gas from vaporisers, compressors,
gas heaters, crossovers, pump risers and emergency pump wells. Piping
containing significant amounts of inert gas should be flushed out.
Smaller piping may be left filled with inert gas or nitrogen.
14) During the time a tank is opened for inspection, dry air will be
permanently blown through the vapour header line in order to prevent
the entry of humidity from the ambient air.
The insulation spaces are to be maintained in a vacuum condition during cargo
tank maintenance.
3) Install the spool piece SP700 for venting the mixture of inert-gas/dry-air
from the liquid header.
4) Open the liquid filling valves CL110/100, 210/200, 310/300, 410/400
on each tank.
5) Open the vapour valves CG101/100, 201/200, 301/300, 401/400 on
each tank.
6) Open the valves CG604, 601 to supply dry air to the vapour header.
Before entry, test for traces of noxious gases (carbon dioxide less than 0.5% by
volume, and carbon monoxide less than 50ppm) which may have been
constituents of the inert gas. In addition, take appropriate precautions as given in
the Tanker Safety Guide and other relevant publications.
The pressure in the tanks is adjusted to 12 kPa.
9) Observe the tank pressures and insulation space pressures, to ensure that
the tank pressures are higher than the space pressures by 1.0kPa at all
times.
WARNING
Take precautions to avoid concentrations of inert gas or nitrogen in confined
spaces, which could be hazardous to personnel. Before entering any such areas,
test for sufficient oxygen (> 20 %) and for traces of noxious gases (CO2 < 0.5%
and CO < 50ppm).
10) Approximately once an hour, take samples from the filling pipe test
connections to test the discharge from the bottom of the tanks for
oxygen content.
11) When the oxygen content reaches 20%, isolate and shut in the tank.
12) When all the tanks are completed and all piping has been aired out, raise
the pressure to 10kPa in each tank and shut the filling and vapour valves
on each tank. Restore the tank pressure controls and valves to vent from
the vapour header.
6 - 64
Part 7
Emergency Procedures
Part 7 Emergency Procedures
PIC
FX/FI
PI PX
PIAHL
TX
PIAL
FX/FI
PX
Trunk Deck
PX
NG-96
NG-97
NG-87
NG-90
NG-89
NG-84
NG-88
TX
NG-93 NG-92
NG-94
NG-95
NG-98
NG-91
PI
NG-83 NG-82
NG-39
Near
Manifold
ESD
CR-100
NG-03
LNG Vent
Master
N2 Master
NG-11
NC-114
I.S.
Gas
Dome
I.S.
NC-108
I.B.S.
I
A-F , J L
To No.1
Dome
Gauge
Board
NC-105
NC-104
NC-106
NC-107
NC-109
NC-110
NC-103
To Fixed Gas
Detection
System
CR-101
NC-112
NC-119
NC-111
NC-101
NC-102
PX To No.1 Dome
PI Gauge Board
NC-115
NG-04
CR-102
NC-113
NC-116
Portable
Sampling
in Cofferdam
NG-01
NG-07
NG-10
NG-08
NG-12
NG-13
CR-103
NG-18
To Fixed Gas
Detection
System
To Fixed Gas
Detection
System
NG-05
NG-06
NG-14
NG-15
NG-16
NG-19
NC-204
NC-117
NC-205
NC-206
NC-203
To Fixed Gas
Detection
System
To Spray Line
NG-62
No.1 H/D
Compressor
No.2 H/D
Compressor
No.2 L/D
Compressor
Compressor Room
NG-63
No.1 L/D
Compressor
Motor Room
I.B.S.
I.S.
I.B.S.
To No.2
Dome
Gauge
Board
NC-207
NC-209
NC-210
NC-219
No.1 Liquid
Dome
FWD AFT
I.S. I.S.
B/W B/W
NC-118
NC-208
Em'cy Cargo
Pump Column
CR-201
CR-301
To Deck
Store
NC-201
NG-02
NG-22
NC-202
To Spray Line
NG-09
NC-212
NC-216
CR-202
PX To No.2 Dome
PI Gauge Board
NC-215
NC-217
NC-304
To Fixed Gas
Detection
System
NC-213
NC-218
NC-303
NG-28
NG-29
I.S.
Gas
Dome
Q
I
A-F , J L
NC-211
NG-17
CR-200
NG-25
NG-26
NG-30
NG-31
CR-203
NG-36
NG-23
NG-24
NG-32
NG-33
NG-34
I.B.S.
I.S.
I.B.S.
NC-305
NC-306
NC-307
To No.1 Dome
Gauge Board
PI
NG-21
No.2 Liquid
Dome
NC-301
NG-47
To Fixed Gas
Detection
System
NG-20
NC-214
NC-308
NG-37
NG-49
NG-50
I.B.S.
I.S.
NC-309
NC-310
Em'cy Cargo
Pump Column
NC-302
NC-319
NC-311
To No.3
Dome
Gauge
Board
NC-312
CR-401
NG-35
CR-300
NG-45
NG-46
NG-51
NG-52
CR-303
NG-43
NG-44
NG-53
NG-54
NG-55
NC-317
NC-404
NC-315
I.S.
NC-405
NC-406
WW
NG-27
To Fixed Gas
Detection
# System
NG-61
NG-81
NC-314
NC-408
NC-409
NC-419
NC-318
NC-414
NC-415
NC-410
NC-411
NC-407
To Spray Line
To No.2 Dome
Gauge Board
PI
NG-42
CR-302
PX To No.3 Dome
PI Gauge Board
NC-316
NC-313
NG-60
CG-613
Gas
Dome
Q
I
A-F , J L
To Fixed Gas
Detection
# System
N
H
To Fixed Gas
Detection
System
NC-412
From
Engine
Room
Boil-off
Gas Line
From
Engine
Room
NG-40
NG-41
No.3 Liquid
Dome
NC-403
To Fixed Gas
Detection
System
To Spray Line
NG-48
NC-402
PX To No.4 Dome
PI Gauge Board
NC-416
To No.4
Dome
Gauge
Board
CR-402
NC-413
NC-418
NC-417
I
A-F , J L
Em'cy Cargo
Pump Column
NC-401
To No.3 Dome
Gauge Board
PI
NG-59
N
G
I.B.S.
Gas
Dome
I.S.
I.B.S.
No.4 Liquid
Dome
NG-69
NG-57
NG-65
S
Em'cy Cargo
Pump Column
NG-56
CR-400
NG-70
NG-68
To Fixed Gas
Detection
# System
NG-58
NG-74
NG-64
NG-66
NG-72
NG-71
NG-75
CR-403
NG-67
NG-73
NC-77
NG-79
NG-78
To No.4 Dome
Gauge Board
PI
NG-80
NG-76
To Fixed Gas
Detection
# System
NG-38
Near
Manifold
TX
7-1
Key
I.S.
: Insulation space
the gas concentration and temperatures in the IBS, i.e. secondary barrier temperatures.
In conjunction with the above, record all pressure changes
occurring in the cargo tank and IBS.
To N2 Vent Mast
To Gas Detector
A small leakage of vapour through the membrane may not be readily obvious.
The vapour concentration in each IBS is recorded daily to detect any such small
but steady change. No temperature change will be obvious, unless the fracture is
in the immediate vicinity of the sensors below the cargo tank. Indications of a
more serious leakage are likely to be:
Any porosity in the primary barrier weld will allow the passage of
methane vapour into the primary insulation space. The amount of this
vapour should be kept to a minimum by the use of the nitrogen purging
system. If a fracture occurs in the primary insulation barrier below the
level of the liquid in the tank, the vapour concentration will increase
rapidly and suddenly. If the fracture is above the liquid level, the
concentration will exhibit a fluctuating increase.
W V
FWD IS
Bilge Well (C)
AFT IS
Bilge Well (C)
After the leak is detected, record the gas concentration and IBS
temperature every hour for eight hours.
Cofferdam
IS
7-2
IBS
In Tank
(400A)
(80A) CS-001
ESD
CL-002
ESD
CL-005
(500A) CL-006
(500A)
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
Flow Meter
(400A)
(400A)
ESD
CL-008
ESD
CG-004
(400A)
CG-002
(600A)
Y-type Strainer
(400A)
CG-703
ESD
(300A)
CR-104
CS-107
(50A)
CS-108
(40A)
CL-100
(300A)
(400A)
(400A)
CS-100
CS-101
CS-102
CL-101
M
(300A)
SP-100
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(300A)
CR-105
(PORT)
To Fixed Gas
Spray
Pump
Detection
System
(STBD)
To Fixed Gas
Detection
System
CR-401
NC-407
NC-404
(50A)
NC-406
NC-405
(65A)
(80A)
(400A)
(400A)
CL-205
NC-409
Cargo Pump
NC-403
(50A)
To No.4
Dome
Sprayers
Gauge
Board
PX To No.4 Dome
PI Gauge Board
NC-419
NC-415 (400A)
NC-413
(600A)
(STBD)
CL-102
CL-103
CL-104
FL-100
SA-154 SA-153
SA-156 SA-155
(8A)
(8A)
(8A)
SA-152 SA-151
CG-200
CG-201
NG-65
NC-401
(PORT)
CS-104
NC-408
NG-66
CS-207
I.B.S.
(50A)
I.S.
(50A)
I.S.
I.B.S.
SP-200
NC-402
NC-414
(600A)
CR-402
(300A)
CR-204
NG-69
Gas
Dome
Q
NG-64
NG-68
I
A- F , J L
CL-110
CR-400
NG-71
NG-70
NG-72
NG-73
CS-208
(50A)
No.1 LNG
Vent Mast
(400A)
NG-67
CR-205
(40A)
CS-200
N
G
CS-103
CS-203
CS-201
CS-202
CL-200
NG-74
CL-201
M
NG-75
(300A)
M
(300A) CR-403
CL-202
NG-78
No.4 Liquid
Dome
CL-206
NC-411
NC-412
NC-410
NC-418
NC-417
(50A)
(300A)
7-3
To No.4 Dome
Gauge Board
PI
CG-701
(450A)
(300A)
(400A)
(450A)
CL-210
NG-76
FL-200
(CL-208)
Foot Valve
CS-204
NC-77
NG-79
CL-203
CL-204
M
NG-80
SA-256 SA-255
SA-254 SA-253
(50A)
Em'cy Cargo
Pump Column
(8A)
(50A)
(65A)
S
Spray Pump
No.2 LNG
Vent
To Fixed
GasMast
Detection
# System
(400A)
Sprayers
(80A)
(65A)
(100A)
NC-416
Cargo Pump
CS-701
CS-700
(300A)
Spray Main
SP-700
CG-100
(100A)
CL-700
CG-101
(400A)
CG-700
(450A)
(300A)
Liquid Main
SA-252 SA-251
SP-300
(50A)
(50A)
CS-307
CR-304
CG-702
(650A)
(8A)
(40A)
CS-308
(300A)
(300A)
(400A)
CL-305
CL-306
(600A)
CG-300
CS-300
CR-305
CL-300
(400A)
(400A)
(400A)
(600A)
(CL-308)
Foot Valve
(50A)
(80A)
CL-011(500A)
CL-012
CS-008(80A)
ESD
(400A)
(300A)
CS-303
CS-301
CS-302
CL-301
M
(300A)
(300A)
(400A)
(450A)
M
CL-302
CL-303
CL-304
FL-300
Control Valve
Vapour Main
(STBD)
S
Spray Pump
Needle Valve
(700A)
(PORT)
(80A)
Cargo Pump
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
(50A)
SA-356 SA-355
(8A)
SA-354 SA-353
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(STBD)
(50A)
CG-301
(650A)
CS-600
(8A)
SA-352 SA-351
SP-400
(8A)
CS-407
CR-404
CG-401
(300A)
(50A)
(50A)
CS-408
(40A)
CL-400
(300A)
(300A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
CR-405
(300A)
No.3 LNG
Vent Mast
(400A)
(PORT)
(CL-408)
Foot Valve
CS-702
CL-310
CS-403
CL-410
CS-404
(750A)
No.4 LNG
Vent Mast
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(80A)
(700A)
CS-406
CG-601
CL-601
(65A)
(400A)
(300A)
(450A)
(8A)
CG-603
(80A)
CG-602
(300A)
CL-600
Gas Main
(300A)
Ballast Line
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
SP-701
(80A)
CL-015
(50A)
(700A)
(50A)
Forcing
Vaporuizer
CS-502
CS-506
(50A)
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
(8A)
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(400A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
To Engine Room
CG-519
(300A)
CG-504
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
If any two of the above events occur, immediately segregate the gas
contaminated IBS from the others and vent it to the atmosphere to maintain the
pressure at about 0.5 ~ 1 kPa below the IBS relief valves 3 kPa set point. Refer
to following section for detailed advice.
Increase the set pressure of the IS service header from its normal plus 0.2 ~ 0.7
kPa above IBS set point. This higher pressure in the IS should prevent gas
contamination from the IBS, should the secondary barrier not be completely tight.
If the leak is so severe that the pressure in the IS cannot be maintained above that
in the IBS, then isolate the IS of the contaminated tank from the other Insulation
Spaces by closing the nitrogen supply valve to the IS at the after end of the tank.
As a precaution, immediately remove the flow cartridge and spring from the
dynamic auto balancing valves on the effected tank to permit the glycol to flow
at a higher rate to the coils in the cofferdam. See Illustration 5.3.2a Cofferdam
Glycol Heating System. Increase the hull heating flow rate surrounding the
effected tank as soon as the temperatures in the IS or inner hull are observed to
be dropping (colder).
NOTE
Report any membrane leak immediately to the Operations Department of the
Head Office. At the first opportunity, the damaged tank should be pumped out
and gas-freed and the contaminated IBS gas-freed.
On the damaged tank, ensure that the IBS stays segregated from the IS:
Assuming the leakage is in No.4 tank insulation space.
1) SHUT the nitrogen supply valve to the IBS at the after end of the tank.
2) OPEN first the small manual vent valve on the forward transverse IBS
header of the tank to try and control the pressure in the IBS of the
damaged tank at 0.4kPa. If that valve is not able to vent sufficient gas,
then slowly throttle OPEN the large manual vent valve as needed to
maintain the pressure in the IBS at about 1kPa. Throttle the small
manual vent valve as needed for fine control.
3) Log the IBS and IS gas detection readings in the Cargo Log. If no gas is
detected in the IS, leave its nitrogen supply valve open.
On each intact tank, keep the valves set up as normal:
1) Log the gas concentration in the IBS and IS in each tank on an hourly
basis initially until the extent of the leakage to the damaged tank can be
determined.
2) If the gas concentrations in the intact tank IBS and IS are not changing,
leave the nitrogen supply valves to these spaces unchanged.
LNG in the bottom of the inter barrier space is removed through the eight
nitrogen inlet tubes, at the aft end of each liquid dome.
Prior to the discharge of the affected cargo tank, the portable elbow bend,
situated between valves NC418 and NC416 is swung and connected to the spray
header at the blank flange connection) provided on each tank.
The LD compressor is set to draw from the spray header via the forcing
vapouriser and discharge to the boilers. It will discharge to atmosphere through
the forward vent mast only if the boilers are unable to cope with the vapour
demand. The vapouriser, which is steam heated, is used to vaporize the LNG
prior to entering the compressor and protects the rotors from any LNG carry over.
An increase in pressure due to vapour leakage will be less obvious than an
increase due to leakage liquid leakage. This is because the volume of vapour
passing through a fracture is small compared with the volume of liquid, which
subsequently vaporises, passing through the same fracture. In both cases the
volume is likely to be small in comparison with the volume of the inter barrier
space.
If the damaged cargo tank is to remain out of service with the other tanks in use
for one or more voyages before repairs are to be made, the tank should be filled
with inert gas and shut in at a pressure of about 10 kPa. Throttle OPEN the
manual vent valve (at forward transverse IBS header) from the IBS of the
damaged tank as necessary to maintain the IBS between 0.5 and 1 kPa.
7-4
(400A)
(80A) CS-001
ESD
CL-002
ESD
CL-005
(500A) CL-006
(500A)
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
Flow Meter
(400A)
(400A)
ESD
CL-008
ESD
CG-004
(400A)
CG-002
(600A)
Y-type Strainer
(400A)
CG-703
ESD
(300A)
CR-104
CS-107
(50A)
CS-108
(40A)
CL-100
(300A)
(400A)
(400A)
CS-100
CS-101
CS-102
CL-101
M
(300A)
SP-100
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(300A)
CR-105
(PORT)
To Fixed Gas
Spray
Pump
Detection
System
(STBD)
To Fixed Gas
Detection
System
CR-401
NC-407
NC-404
(50A)
NC-406
NC-405
(65A)
(80A)
(400A)
(400A)
CL-205
NC-409
Cargo Pump
NC-403
(50A)
To No.4
Dome
Sprayers
Gauge
Board
PX To No.4 Dome
PI Gauge Board
NC-419
NC-415 (400A)
NC-413
(600A)
(STBD)
CL-102
CL-103
CL-104
FL-100
SA-154 SA-153
SA-156 SA-155
(8A)
(8A)
(8A)
SA-152 SA-151
CG-200
CG-201
NG-65
NC-401
(PORT)
CS-104
NC-408
NG-66
CS-207
I.B.S.
(50A)
I.S.
(50A)
I.S.
I.B.S.
SP-200
NC-402
NC-414
(600A)
CR-402
(300A)
CR-204
NG-69
Gas
Dome
Q
NG-64
NG-68
I
A- F , J L
CL-110
CR-400
NG-71
NG-70
NG-72
NG-73
CS-208
(50A)
No.1 LNG
Vent Mast
(400A)
NG-67
CR-205
(40A)
CS-200
N
G
CS-103
CS-203
CS-201
CS-202
CL-200
NG-74
CL-201
M
NG-75
(300A)
M
(300A) CR-403
CL-202
NG-78
No.4 Liquid
Dome
CL-206
NC-411
NC-412
NC-410
NC-418
NC-417
(50A)
(300A)
7-5
To No.4 Dome
Gauge Board
PI
CG-701
(450A)
(300A)
(400A)
(450A)
CL-210
NG-76
FL-200
(CL-208)
Foot Valve
CS-204
NC-77
NG-79
CL-203
CL-204
M
NG-80
SA-256 SA-255
SA-254 SA-253
(50A)
Em'cy Cargo
Pump Column
(8A)
(50A)
(65A)
S
Spray Pump
No.2 LNG
Vent
To Fixed
GasMast
Detection
# System
(400A)
Sprayers
(80A)
(65A)
(100A)
NC-416
Cargo Pump
CS-701
CS-700
(300A)
Spray Main
SP-700
CG-100
(100A)
CL-700
CG-101
(400A)
CG-700
(450A)
(300A)
Liquid Main
SA-252 SA-251
SP-300
(50A)
(50A)
CS-307
CR-304
CG-702
(650A)
(8A)
(40A)
CS-308
(300A)
(300A)
(400A)
CL-305
CL-306
(600A)
CG-300
CS-300
CR-305
CL-300
(400A)
(400A)
(400A)
(600A)
(CL-308)
Foot Valve
(50A)
(80A)
CL-011(500A)
CL-012
CS-008(80A)
ESD
(400A)
(300A)
CS-303
CS-301
CS-302
CL-301
M
(300A)
(300A)
(400A)
(450A)
M
CL-302
CL-303
CL-304
FL-300
Control Valve
Vapour Main
(STBD)
S
Spray Pump
Needle Valve
(700A)
(PORT)
(80A)
Cargo Pump
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
(50A)
SA-356 SA-355
(8A)
SA-354 SA-353
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(STBD)
(50A)
CG-301
(650A)
CS-600
(8A)
SA-352 SA-351
SP-400
(8A)
CS-407
CR-404
CG-401
(300A)
(50A)
(50A)
CS-408
(40A)
CL-400
(300A)
(300A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
CR-405
(300A)
No.3 LNG
Vent Mast
(400A)
(PORT)
(CL-408)
Foot Valve
CS-702
CL-310
CS-403
CL-410
CS-404
(750A)
No.4 LNG
Vent Mast
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(80A)
(700A)
CS-406
CG-601
CL-601
(65A)
(400A)
(300A)
(450A)
(8A)
CG-603
(80A)
CG-602
(300A)
CL-600
Gas Main
(300A)
Ballast Line
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
SP-701
(80A)
CL-015
(50A)
(700A)
(50A)
Forcing
Vaporuizer
CS-502
CS-506
(50A)
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
(8A)
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(400A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
To Engine Room
CG-519
(300A)
CG-504
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
3) Connect the portable elbow bend between the nitrogen header and the
spray header.
4) Set up spray system to discharge from the Inter Barrier Space (IBS).
Open inlet valve to spray header CS406.
Open No.4 tank spray master valve CS403.
Open spray header to vaporiser line CS600.
Open outlet from IBS NC416
CAUTION
The vapour heaters and forcing vaporiser should be thoroughly preheated by
steam before the admission of methane vapour. This prevents ice formation.
5) Prepare forcing vapouriser for use.
Open forcing vapouriser inlet and outlet valves CS506 and CG502.
Set controller inlet and bypass valves to forcing vapouriser CS502
and 504.
6) Open valves on the LD compressor to vapour header and prepare for use.
Open inlet valve to No.1 LD compressor CG516.
Open outlet valve from No.1 LD compressor CG524.
Open crossover valve compressor to vapour manifold CG530 and
529.
Open crossover valve vapour manifold to vapour header CG703.
7-6
CB-18
C.D
B.W
CB-12
I.S
B.W
Cofferdam
(50A)
I.S
B.W
C.D
B.W
(65A)
(15A)
CB-01
CB-06
(65A)
CB-03 CB-02
(50A)
FWD
Water
Ballast
Tank
(P&S)
CB-22
(50A)
(50A)
I.S
B.W
I.S
B.W
Cofferdam
(50A)
I.S
B.W
I.S
B.W
Cofferdam
CB-10
(50A)
(50A)
I.S
B.W
I.S
B.W
Cofferdam
CB-01
CB-06
CB-05
No.1 Cargo
Tank
(50A)
I.S
B.W
FWD H.F.O
Tank (P)
(50A)
CB-07
C.D
B.W
CB-04
CB-09
LS
(50A)
CB-13
CB-11
No.2 Cargo
Tank
(65A)
CB-08
CB-16
(50A)
FWD Water
Ballast
Tank (P)
LAH
CB-12
C.D
B.W
(50A)
CB-19
CB-17
No.3 Cargo
Tank
(50A)
CB-15
CB-18
C.D
B.W
To Overboard
Discharge
(50A)
To Overboard
Discharge
CB-14
CB-23
No.4 Cargo
Tank
(50A)
CB-21
(50A)
C.D
B.W
CB-27
CB-32 CB-31
CB-24
(50A)
CB-29
C.D
B.W
(50A)
LS
(50A)
LS
CB-25
CB-26
CB-30
LAH
To Overboard
Discharge
CB-20
(50A)
(65A)
To Overboard
Discharge
LAH
(15A)
(25A)
I.S
B.W
To Overboard
Discharge
CB-28
(15A)
(50A)
(50A)
I.S
B.W
FWD H.F.O
Tank (P&S)
CB-05
(50A)
(50A)
CB-04
CA-23
CB-10
(50A)
I.S
B.W
(50A)
(15A)
(50A)
CB-08
CB-09
(50A)
(15A)
CA-38
C.D
B.W
CA-06
CA-08
I.S
B.W
Bosun Store
No.1 Cargo
Tank
CB-11
(50A)
(50A)
I.S
B.W
To Overboard
Discharge
Oiler, Filter
& Regulator
CB-07
CB-32 CB-31
CB-14
CB-15
CB-24
CB-29
(50A)
(50A)
CA-48
(50A)
CB-28
CA-75
C.D
B.W
CB-16
(50A)
CB-30
I.S
B.W
Compressor
Air Supply
To Overboard
Discharge
(15A)
CB-13
CA-74
(25A)
I.S
B.W
CA-07
No.1 Trunk
CB-19
C.D
B.W
Compressor
Air Supply
No.2 Cargo
Tank
CB-17
CB-25
(15A)
CB-22
(50A)
Compressor
Air Supply
No.3 Cargo
Tank
CB-23
(50A)
CB-27
(15A)
Compressor
Air Supply
NG-01
No.2 Trunk
CB-21
Compressor
Air Supply
(15A)
(50A)
CB-20
(50A)
(50A)
(50A)
No.4 Cargo
Tank
CA-73
Compressor
Air Supply
(50A)
Engine Room
(15A)
NG-19
No.3 Trunk
CB-26
(65A)
No.4 Trunk
(50A)
Compressor
Air Supply
To Overboard
Discharge
(65A)
(15A)
NG-37
NG-58
NG-18
CA-09
(15A)
(15A)
Nitrogen Supply
(After B/W Only)
NG-36
(50A)
Nitrogen Supply
(After B/W Only)
Nitrogen Supply
(After B/W Only)
NG-57
(50A)
To Overboard
Discharge
Nitrogen Supply
(After B/W Only)
NG-80
(50A)
Key
Bilge Line
Nitrogen Line
Air Line
LAH
LS
A
Cofferdam
CB-03 CB-02
(50A)
FWD H.F.O
Tank (S)
FWD Water
Ballast
Tank (S)
7-7
7) Carry out an inner hull inspection to determine the cause of the leak (with particular reference to safe atmosphere in the ballast tank space).
8) After the maximum possible water has been discharged from this insulation space, appreciable moisture will remain in the insulation and over the bottom area.
Increasing the flow of nitrogen through the space can assist drying out the insulation. This should be continued until the moisture level is below that detected
by the water detection system before any cargo is carried in the affected tank.
At the bottom of No.1, 2, 3, 4, and 5 cofferdams, there are two bilge wells for
each tank insulation space. Each of these wells is fitted with water detection
units.
The bilge well serves as the inlet for the nitrogen 50 mm supply pipe to the
insulation space. This supply pipe also acts as a manual sounding pipe to the
bilge well.
Cofferdam
Filter
Regulator
Oiler
Reducer
A
Tight
Man Hole
2. Leakage Detection
Compressor
Air Supply
Cargo Tank
To reduce the risk of damage from leakage, each cargo insulation space has been
provided with water detection units (See Leakage Detection below) and a bilge
piping system connected to five(5) pneumatic pumps for the removal of any
water.
N2 Filling &
Manual Sounding
To Overboard
Discharge
Sounding &
Portable Gas Sampling
Ballast water leakage from the ballast tanks to the insulation spaces can occur
through fractures in the inner hull plating. If the leakage remains undetected and
water accumulates in these spaces, ice will be formed. Ice accumulation can
cause deformation, and possible rupture of the insulation. The resultant cold
conduction paths forming in the insulation will cause cold spots to form on the
inner hull.
Cargo Tank
Insulation Space
Bilge Pump
(20 m3/h x 40 MTH)
Rose Plate
Rose Plate
SUS316L(2T)
Cofferdam
Bilge Well
Water
Detector
Insulation Space
Bilge Well (FWD)
AFT
Water Detector
Insulation Space
Bilge Well (AFT)
FWD
2) Ventilate the cofferdam and pipe duct spaces, carrying out normal
enclosed space safety procedures.
3) Connect a flexible hose to the pump outlet valve for drain water
discharge overboard.
4) Open the bilge well outlet valve on the selected tank insulation space.
5) Open the inlet and outlet valves on the selected pump.
6) Open the air supply to the pump and continue pumping until the
maximum amount of water has been discharged.
7-8
7-9
Blank Page
7 - 10
Earth Cable
Support Rope
Lifting Eye
Hang Plate
Next Support Rope
Hang Plate
Cable Cramp (B)
Hang Plate
Support Rope
Support Rope
Hanger
Hang Plate
Protection Sheet
Protection Sheet
Power Cable
Power Cable
Power Cable
Power Cable
Next Support Rope
Pump Stand
Earth Cable
Work 1
Work 2
Work 3
Work 4
Junction Box
Chain Block
To Switch Board
Support Rod
Flexible Cable
Cable
Load Meter
Column Cover
To Junction Box
Terminal Header
To Junction Box
Gasket Holder
Terminal Header
Support Rope
Gasket
Hang Plate
Hook Plate Set
Hook Plate
Set
Hook Plate Set
Support Rope
Support Rope
Work 5
Work 6
Work 7
7 - 11
Finish
The emergency cargo pump is used in the unusual event that both main cargo
pumps have failed in a cargo tank. The pump is lowered into the emergency
cargo pump column for that tank. Cables and a connection to the local junction
box are used to power the pump. When lowered to its final position, the pump
opens the foot valve in the column and the LNG can be pumped out.
Adjacent to each pump column is a terminal box for the cargo pump connection
and a local start switch. The pump and delivery valve are controlled and started
via the IAS.
The pump is suspended over the column into which it is being lowered by a 3 ton
SWL derrick. For the No.3 tank, the cargo crane is used. A support flange to take
the weight of the pump is used to connect each strop.
4.
6) Fit the hook plate set to the lower side of the support rod.
6) Fit the shackle of the next support rope to the hang plate. Make sure that
measures are taken to avoid the eye bolt for the shackle falling out.
7) Pass the cryogenic cable through the nozzle for lead cable of the
column cover.
2) Attach the hook plate set to the shackle of the hang plate.
3.
4) Replace the hook plate set fitted to the hanger by the next hang plate.
6.
1) Draw out the pump from the storage container and set it vertically.
4) Replace the support rope by the next support rope in accordance with the
same procedure in 5 above.
2) Lower the column cover slowly and remove the gasket holder to set
the gasket on the column flange at a position of about 500mm over
the column flange.
3) Fix the cable cramp (A) of the cryogenic cable to the next hang plate of
the support rope. Make sure that measures are taken to avoid the
butterfly nut for the shackle falling out. Fix the cable cramp (B) to the
middle of the support rope by means of fly nut. Make sure that
measures are taken to avoid the butterfly nut for the shackle falling out.
7.
7 - 12
3) Lower the column cover slowly and place it on the column flange,
taking care not to damage the gasket.
2) Fit the shackle of the next support rope to the hang plate of the support
rope. Make sure that measures are taken to avoid the eye bolt for the
shackle falling out.
The cargo tank will inevitably contain LNG. Therefore the column into
which the emergency pump is being lowered must be evacuated. This is
achieved by injecting nitrogen into the column. In the case of a full cargo
tank, a pressure of between 0.2 and 0.3 MPa required. The nitrogen forces
the liquid out through the foot valve located at the bottom of the column.
2) Fit the shackle of support rope to the lifting eye at the top of pump.
Make sure that measures are taken to avoid the eye bolt for the shackle
falling out.
8.
1) Fit the hanger to the column flange and place the hang plate on the
hanger in order to support the pump weight by means of the hanger.
When all equipment, pump, cables, electrical connection box and accessories are
in position near the tank in which the pump is to be installed, prepare the derrick
to lift the pump and start the pump installation.
9) Lower the column cover and fit the hook plate set to the shackle of the
hang plate.
2.
3) Attach the hook plate set to the crane on board and lift up the pump.
Remove the pump stand.
1.
5) Attach the gasket to the flange face of the column cover by means of
the gasket holder.
5) Fix the shackle cable cramp (B) to the middle of support rope by means
of the butterfly nut.
The pump discharges into the column and to the liquid line via a discharge
connection and valve at the top of the column.
CAUTION
When working near the open pump column, all tools and equipment used must
be attached to avoid anything falling in the column. All personal items have to
be removed from pockets. The column opening must be temporarily covered
when the blind flange is removed. Only brass tools must be used.
4) Lift up the column cover using the eye bolts (4 off) on the column
cover.
4) The hang plate is provided at the opposite end of the support rope. Fix
the cable cramp (A) for the cryogenic cable to the hang plate by means
of the butterfly nut. Make sure that measures are taken to stop the nut
falling off.
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(400A)
(300A)
(400A)
(50A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
7 - 13
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
Ballast Line
Gas Main
(300A)
SP-701
CG-600
CG-605
(700A)
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-600
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
3) Fit the spool piece SP600 between liquid main and HD heater outlet line.
It may be necessary for in-tank repairs to be carried out with the vessel in service,
in which one tank can be warmed up, inerted, aerated, entered and work
undertaken on the tank internals, i.e. change cargo pump, investigate and cure
problems with tank gauging systems etc. It is not envisaged that tank barrier
repairs will be carried out with one tank only warmed up.
The warm-up, inerting and aeration can be carried out with the remaining cold
tanks providing boil-off gas for burning in the boilers.
Performance Criteria
Auxiliaries Involved
HD Compressor LD Compressor
HD Heater
LD Heater
Operation Duration
Check Points
7) Monitor the gas pressure in the tank and adjust the compressor to
maintain tank pressure between 10 ~20kPa.
9) Shut off steam to the gas heaters and allow circulation for 10 minutes.
10) Initiate the set-up for inerting the cargo tank.
5) Open vapour supply valve CG601 to the compressors and the No.1 LD
compressor suction and discharge valves CG515, CG523.
6) LD heater:
Open the steam supply to the LD heater.
Open the heater inlet valve CG504 and outlet valve CG510.
In CCR
7) No.1 LD compressor:
Adjust the normal boil-off valve (IGV) to 60 % for loaded condition:
tank pressures are to be maintained between a minimum 105kPaA and
maximum 110kPaA and the steam dump opening at 113kPaA.
When the engine room is ready to start gas burning, ensure that there is
sufficient nitrogen to purge the lines to the boiler i.e. > 500kPa in the buffer tank.
9) Ensure that the gas outlet temperature of LD heater is approximately
25C.
Open fuel gas master valve CG606, and start the LD compressor.
The operation will then be controlled and monitored from CCR and the ECR.
Warm Up Procedure
1) Open the liquid branch valve CL210 and filling valve CL200 on No.2
tank liquid dome.
2) Open valves CG605 and CL601, the vapour line crossovers to liquid
header.
3) Open valve CG509 the outlet from HD heater.
4) Open valve CG503 the inlet to HD heater.
7 - 14
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(400A)
(300A)
(400A)
(50A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
7 - 15
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
Inert Gas
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
Ballast Line
Gas Main
(300A)
SP-701
CG-600
CG-605
(700A)
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-600
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
Normal gas burning is continued during this operation using vapour from the
three in-service tanks.
Inert gas is supplied to the tank by the Inert Gas Generator via the spool piece
SP600 connecting the IG line with the liquid header. Venting the tank is carried
out via the fitting of a spool piece connecting the vapour outlet from the tank to
the gas header. The isolation valve onto the vapour header (CG200) must remain
closed
Purpose
Performance Criteria
Auxiliaries Involved
Operation Duration
Check Points
11) Open the valve CL210/200 to bring inert gas to the bottom of No.2 tank.
CG101/100
NO.3 Tank
CG301/300
NO.4 Tank
CG401/400
2) Set up the LD compressor and LD heater to supply the boil-off gas from
No.1, 3 and No.4 tanks to the boilers;
Valve
Description
Position
CG601
Open
CG515
Open
CG523
Open
CG519
Auto
CG504
Open
CG510
Open
CG508
Auto
CG506
Auto
16) During tank inerting, purge the LNG vapour contained in No.2 tank spray
header for about 5 minutes by using the sample points valves.
17) When the operation is completed, stop the supply of inert gas and change
over the inert gas plant to supply dry air.
WARNING
If any piping or components are to be opened, the inert gas or nitrogen must first
be flushed out with dry air. Take precautions to avoid concentrations of inert gas
or nitrogen in confined spaces which could be hazardous to personnel
7 - 16
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
CL-007(500A)
CS-004(80A)
CS-006(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(600A)
CG-703
ESD
(400A)
(300A)
(400A)
(50A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
7 - 17
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(450A)
(8A)
(40A)
CS-308
(300A)
(300A)
Liquid Main
(50A)
(65A)
(400A)
(400A)
Flow Meter
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
Control Valve
(700A)
(STBD)
(80A)
Cargo Pump
Needle Valve
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
Dry Air
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Inert Gas
Gas Main
(300A)
Ballast Line
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-701
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Key
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
Normal gas burning is continued during this operation using vapour from the
three in-service tanks.
10) Observe the tank pressures and insulation space pressures, to ensure that
the tank pressures are higher than the space pressures by 3.0kPa at all
times.
Dry air is supplied to the tank by the dry air generator (IGG) via the spool piece
SP701 connecting the IG line with the gas header and the fitting of a spool piece
SP200 connecting the vapour outlet from the tank to the gas header (should
already be in place from the inerting operation). Venting the tank is carried out
via the liquid filling valve CL210/200, exhausting onto the liquid header and
leading to No.1 vent mast via valve CL700 and the spool piece SP700. The
isolation valve onto the vapour header (CG200) must remain closed.
Purpose
Performance Criteria
Auxiliaries Involved
Operation Duration
Check Points
1)
Prepare the inert gas plant for use in the dry-air mode at 50% flow.
2) Fit the spool piece SP700 between liquid header and No.1 vent mast.
3) Fit the spool piece SP200 between No.2 tank vapour line and gas header.
4) Fit the spool piece SP701 between IGG discharge line and gas header.
5) Ensure that valve CG200 is securely closed.
6) Continue supplying LNG vapour to the LD compressor for burning in
the boilers. Confirm that the vapour valves on tanks with LNG heel are
still open;
NO.1 Tank
CG101/100
NO.3 Tank
CG301/300
NO.4 Tank
CG401/400
7 - 18
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
CS-005
(80A)
(100A)
(650A)
(500A)
CL-003
CS-002(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
(300A)
(400A)
M
(50A)
CS-108
SP-100
CG-101
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
7 - 19
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
(50A)
(65A)
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(400A)
(450A)
CL-305
CL-306
CL-007(500A)
CS-004(80A)
CS-006(80A)
(600A)
CG-703
ESD
Liquid Main
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
(40A)
(80A)
CG-001
(400A)
ESD
(500A) CL-010
CL-011(500A)
CL-012
(400A)
(650A)
(8A)
(40A)
CS-308
(300A)
(300A)
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
Flow Meter
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
(700A)
(STBD)
(80A)
Cargo Pump
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Control Valve
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
Needle Valve
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
CS-107
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Dry Air
Gas Main
(300A)
Ballast Line
(400A)
CG-601
(80A)
CG-602
CG-603
(700A)
(300A)
(300A)
SP-701
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
Atmospheric Air
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
CG-502
CL-015
(25A)
(500A)
CS-504
(40A)
CS-501
CS-703
(40A)
CG-501
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CS-503
Description
Orifice
(50A)
CG-529
(600A)
(600A)
Liquid Crossover
No.1 H/D
Compressor
(450A)
SP-602
ESD
CG-513
Vapour Crossover
(250A)
CG-525 CG-521
CG-511
(600A)
CG-517
(600A)
CG-503
Symbol
Liquid Crossover
No.2 H/D
Compressor
(450A)
CG-500
(300A)
(80A)
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
Mist
Separator
Key
Stripping Crossover
(250A)
(500A)
No.1 L/D
Compressor
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
Performance Criteria
Auxiliaries Involved
Operation Duration
Check Points
1) Prepare the inert gas plant for use in the dry air mode.
2)
NO.1 Tank
CG101/100
NO.3 Tank
CG301/300
NO.4 Tank
CG401/400
11) Start the inert gas generator. When oxygen content is less than 1% and
dew point is -45C, open the delivery valve and close the purge valve
on the inert gas discharge line.
3) Fit the spool piece SP600 between IGG discharge line and liquid header.
11) By sampling at the vapour dome, check the atmosphere of the tank by
means of the portable oxygen analyzer. O2 content is to be less than 1%
and the dew point less than -40C.
4) Fit the spool piece SP200 between No.2 tank vapour outlet and gas
header, venting via No.1 vent mast.
12) During tank inerting, purge for about 5 minutes the air contained in the
lines and equipment by using valves and purge sample points.
5) Open valves CL601, CL210/200, to supply dry air to the liquid header
and No.2 cargo tank.
13) Inert emergency cargo pump well with N2 through the foot valve.
6) Open tank vapour valve CG201, and ensure that valve CG200 remains
closed.
7) Open valve CG700 to vent through No.1 vent mast.
8) Start the IGG. When dew point is -45C, open the delivery valve and
close the purge valve on the dry-air/inert-gas discharge line.
9) Monitor the dew point of the tank by taking a sample at the vapour
dome. When the dew point is lower than -20C, drying is complete.
Wet air which may be contained in the discharge lines from the cargo pumps,
float level piping and any associated pipe-work in the cargo compressor room
must be purged with dry air.
(See illustration 7.6.4b Inerting)
Purpose
Performance Criteria
Auxiliaries Involved
Operation Duration
Check Points
14) When the operation is completed, stop the supply of inert gas and close
the valves CL601, CL210/200, CG201, CG700 and remove the spool
pieces.
NOTE
Until the ship is ready to load LNG, the tank may be maintained under inert gas
for as long as is necessary. Pressurise the tank to 20kPa above atmospheric
pressure, and to reduce leakage isolate the valve at the forward venting system.
It is assumed that the maintenance/repair of one tank will take place while the
ship is on ballast passage, having discharged the cargo from the affected tank in
the normal manner. Therefore gas filling will not be undertaken until the ship
returns to the loading port.
On arrival at the loading terminal the first procedure will be to gas fill the
affected tank with vapour from shore, venting the inert gas through the liquid
header via the spool piece to No.1 vent mast.
If coolant is sufficient in the other tanks, the gas filling operation is carried out
on the ballast passage.
The target values for N2 gas and inert gas CO2 is equal to or less than 1%. These
values should be matched with the LNG terminal requirements. This normally
entails approximately two changes of the volume of the atmosphere in the cargo
tank.
10) When the tank is dried, stop the IGG. Change over the IGG to inert gas
production and feed the tank in the same manner as for drying the tank.
NOTE
It is necessary to lower the tanks dew point by dry air to at least -20C, before
feeding tanks with inert gas, in order to avoid formation of corrosive agents.
7 - 20
(400A)
ESD
CL-002
(80A) CS-001
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
CS-005
(80A)
(500A)
CL-003
(100A)
CS-002(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
(300A)
(400A)
M
(50A)
CS-108
SP-100
CG-101
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
7 - 21
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
(50A)
(65A)
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(400A)
(450A)
CL-305
CL-306
CL-007(500A)
CS-004(80A)
CS-006(80A)
(600A)
CG-703
ESD
Liquid Main
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
(40A)
(80A)
CG-001
(400A)
ESD
(500A) CL-010
CL-011(500A)
CL-012
(400A)
ESD
(650A)
(8A)
(40A)
CS-308
(300A)
(300A)
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
Flow Meter
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
(700A)
(STBD)
(80A)
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(STBD)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Control Valve
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
Needle Valve
(300A)
(80A)
CS-403
CL-410
CS-404
Cargo Pump
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
CS-107
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Dry Air
Gas Main
(300A)
Ballast Line
(CL-408)
Foot Valve
(400A)
CG-601
(80A)
CG-602
CG-603
(700A)
(300A)
(300A)
SP-701
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
Inert Gas
(80A)
CS-008(80A)
(50A)
(50A)
CL-015
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
CG-502
(500A)
CS-504
(40A)
(25A)
CS-501
CS-703
(40A)
CG-501
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CS-503
Description
Orifice
(50A)
CG-529
(600A)
(600A)
(650A)
No.1 H/D
Compressor
Liquid Crossover
CG-525 CG-521
SP-602
ESD
CG-513
Vapour Crossover
(250A)
(450A)
CG-511
(600A)
CG-517
(600A)
CG-503
Symbol
Liquid Crossover
No.2 H/D
Compressor
(450A)
CG-500
(300A)
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
Mist
Separator
(80A)
Key
Stripping Crossover
(250A)
(500A)
No.1 L/D
Compressor
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
(300A)
CG-504
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
To Engine Room
CG-520
(750A)
CG-510
CS-007
CL-009
(400A)
S
Spray Pump
Blank Page
7 - 22
(400A)
ESD
ESD
CL-005
CL-002
(500A)
(80A) CS-001
(500A) CL-006
CS-003
(80A)
CS-005
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
ESD
CG-001
(400A)
(100A)
Stripping Crossover
(650A)
Liquid Crossover
(500A)
CL-003
CS-002(80A)
ESD
CL-004
(400A)
ESD
(400A)
(400A)
(300A)
(400A)
(50A)
SP-100
CG-101
CS-108
(40A)
CL-100
CG-100
CS-100
CS-101
CS-102
CL-101
(300A)
(300A)
CR-104
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
(50A)
CR-105
(PORT)
S
Spray Pump
(STBD)
(80A)
M
(300A)
(600A)
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-205
(400A)
CL-206
(600A)
CL-102
CL-103
CL-104
FL-100
SA-156 SA-155
SA-154 SA-153
(PORT)
Cargo Pump
CS-104
(8A)
(8A)
CG-201
CS-207
(50A)
(50A)
(8A)
(40A)
CS-208
SP-200
SA-152 SA-151
CG-200
CS-200
(300A)
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
CR-205
CL-200
(300A)
7 - 23
CS-103
CL-110
(STBD)
(CL-208)
Foot Valve
CS-201
CS-202
CL-201
(300A)
(300A)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
CS-203
CL-210
(50A)
Cargo Pump
(100A)
(300A)
(450A)
(400A)
CS-701
CS-700
SP-700
CG-700
Spray Main
CL-700
(300A)
(100A)
Sprayers
CG-702
(400A)
(50A)
(65A)
(400A)
(400A)
CL-008
ESD
CG-004
CG-002
(400A)
(450A)
CL-305
CL-306
CL-007(500A)
CS-004(80A)
CS-006(80A)
(600A)
CG-703
ESD
Liquid Main
CG-300
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CS-107
(80A)
CL-011(500A)
CL-012
(400A)
(650A)
(8A)
(40A)
CS-308
(300A)
(300A)
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
Flow Meter
(600A)
CS-300
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
FL-300
Vapour Main
(PORT)
S
Spray Pump
(700A)
(STBD)
(80A)
Cargo Pump
To Cofferdam
CS-304
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
Emergency Pump Column
(600A)
(50A)
SA-356 SA-355
SA-354 SA-353
(PORT)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
CG-401
CS-407
CR-404
(8A)
(40A)
(300A)
(50A)
(50A)
CS-408
CL-400
(300A)
(300A)
CR-405
Control Valve
Y-type Strainer
No.3 LNG
Vent Mast
(400A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CS-303
CL-310
Needle Valve
(300A)
(80A)
CS-403
CL-410
CS-404
(STBD)
(CL-408)
Foot Valve
(300A)
(450A)
CS-702
No.4 LNG
Vent Mast
(400A)
(50A)
CL-601
CS-600
(80A)
(750A)
(400A)
(300A)
(450A)
(65A)
(700A)
(650A)
CL-600
Inert Gas
Gas Main
(300A)
Ballast Line
(400A)
CG-601
CG-603
(80A)
CG-602
(300A)
(700A)
CG-600
CG-605
SP-600
CL-016
SP-601
CG-604
(700A)
CS-008(80A)
(50A)
(50A)
SP-701
(80A)
ESD
Forcing
Vaporuizer
CS-502
CS-506
(600A)
CS-510
CS-505
CG-502
(500A)
CS-504
(40A)
CL-015
(40A)
CS-501
Description
Orifice
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
CG-501
(300A)
(500A) CL-010
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
ESD
CG-513
(600A)
(600A)
No.1 H/D
Compressor
Symbol
CG-517
(250A)
(450A)
SP-602
(80A)
Liquid Crossover
CG-503
CG-525 CG-521
CG-511
(300A)
No.2 H/D
Compressor
(450A)
CG-500
Mist
Separator
Key
CG-514
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
(250A)
(500A)
No.1 L/D
Compressor
(250A)
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(300A)
(350A)
CG-530
CG-512
CG-509
(300A)
(150A)
(300A)
CG-504
(300A)
To Engine Room
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CG-606
CG-516
CG-528 CG-524
Low Duty
Heater
CL-013
(150A)
CG-506
(400A)
(750A)
CG-510
CG-520
CS-007
CL-009
(400A)
S
Spray Pump
Performance Criteria
Auxiliaries Involved
LD compressor
LD heater
Spray Pump
LNG Vaporiser
Operation Duration
Check Points
10) Pressure in the LNG vaporiser line shall be controlled by CS300 on the
return line to No.3 tank.
11) Open valve CS505, the inlet valve to the LNG vapouriser.
12) In the cargo compressor room, open the outlet from the LNG vaporizer
CG501.
13) Open valve CG602 to allow supply to No.2 cargo tank gas header.
14) Open the header valve CG201 to No.2 tank vapour dome.
15) Using the IAS, open the individual tank loading valves CL210, CL200.
16) Adjust No.1 vent mast pressure with CG701 set at 21kPa or as required.
17) Monitor the vapour exhausting at each liquid dome (use the mid cargo
tank sample cock initially, followed by the sample cock at the top of the
loading line). Also monitor the vapour exhausted at No.1 vent mast
using the sample cock.
18) Verify that CH content is at least 99.0% by testing at a purge valve at
the bottom side of the tank. Purge for 5 minutes all the related sections
of pipelines, machines, equipment and instrumentation lines.
19) The operation is considered complete when No.2 cargo tank has at least
a 99.0% CH content and the acceptable CO2 content and N2 content of
1.0% or less by volume. (Requested by the terminal.)
NOTE
This function should be performed in open sea only.
7 - 24
(400A)
ESD
CL-002
(80A) CS-001
(100A)
(500A)
ESD
CL-005
(500A) CL-006
CS-003
(80A)
(80A)
CL-001
(400A)
(400A)
ESD
CG-003
CG-001
(400A)
CS-005
(650A)
Liquid Crossover
(500A)
CL-003
(400A)
ESD
CS-002 (80A)
ESD
(400A)
CL-004
CL-007(500A)
CS-004 (80A)
CL-008
ESD
CG-004
CG-002
(400A)
CG-703
ESD
(600A)
CS-006 (80A)
CL-011(500A)
CL-012
(400A)
7 - 25
(50A)
CS-108
(40A)
CL-100
(400A)
CG-100
CS-100
CS-101
CS-102
CL-101
M
(300A)
(300A)
(300A)
CR-104
SP-100
(PORT)
(CL-108)
Foot Valve
(50A)
(65A)
(400A)
(400A)
Sprayers
Cargo Pump
(80A)
CL-105
CL-106
(400A)
Emergency Pump Column
(600A)
(50A)
CR-105
(STBD)
(80A)
(300A)
(400A)
CL-110
M
CL-102
CL-103
CL-104
S
Spray Pump
(50A)
(65A)
(400A)
(400A)
CL-206
(400A)
(600A)
Sprayers
CL-205
1
Cargo Pump
CS-104
FL-100
SA-156 SA-155
SA-154 SA-153
(8A)
SA-152 SA-151
(8A)
(8A)
CS-207
SP-200
CG-201
(300A)
(50A)
(50A)
CS-208
(40A)
CL-200
(300A)
CG-200
CS-200
CS-201
CS-202
CL-201
CR-205
CR-204
(50A)
No.1 LNG
Vent Mast
(400A)
(PORT)
(CL-208)
Foot Valve
CS-103
(STBD)
S
Spray Pump
No.2 LNG
Vent Mast
CS-204
M
(300A)
(50A)
(300A)
(50A)
CL-202
CL-203
CL-204
M
FL-200
SA-256 SA-255
(8A)
SA-254 SA-253
SA-252 SA-251
(8A)
CG-701
(450A)
(400A)
(65A)
(100A)
CS-203
CL-210
(50A)
Cargo Pump
(300A)
CS-701
CS-700
SP-700
CG-101
Spray Main
CL-700
CG-700
(100A)
Sprayers
(300A)
(400A)
(450A)
(400A)
CG-301
SP-300
(50A)
(50A)
CS-307
CR-304
CG-702
(450A)
(8A)
(40A)
CS-308
(300A)
F
R
(300A)
Liquid Main
CG-300
CS-300
(65A)
(400A)
(400A)
Flow Meter
Y-type Strainer
(650A)
CL-305
CL-306
(400A)
(400A)
CR-305
CL-300
(300A)
(300A)
(400A)
(600A)
(CL-308)
Foot Valve
(600A)
CS-303
CS-301
CS-302
CL-301
CL-302
CL-303
CL-304
Control Valve
Vapour Main
(PORT)
S
Spray Pump
(700A)
(STBD)
(80A)
To Cofferdam
CS-304
FL-300
(50A)
SA-356 SA-355
SA-354 SA-353
(300A)
(50A)
(65A)
(400A)
(400A)
Sprayers
CL-405
CL-406
(400A)
(600A)
(50A)
(8A)
(8A)
SA-352 SA-351
SP-400
(8A)
CS-407
CR-404
CG-401
(300A)
(50A)
(50A)
CS-408
(40A)
CL-400
(300A)
(300A)
CG-400
CS-400
CS-401
CS-402
CL-401
CL-402
CL-403
CL-404
FL-400
(50A)
SA-456 SA-455
(8A)
SA-452 SA-451
SA-454 SA-453
(8A)
(8A)
CR-405
(300A)
No.3 LNG
Vent Mast
(400A)
(PORT)
(300A)
(450A)
CS-702
CL-310
CS-406 For IBS
Stripping
(STBD)
Cargo Pump
Gas Main
(80A)
CS-403
CL-410
CS-404
(750A)
No.4 LNG
Vent Mast
(400A)
CS-107
CL-601
(650A)
CS-600
(80A)
(700A)
(65A)
(400A)
(300A)
(450A)
(50A)
(300A)
CL-600
(CL-408)
Foot Valve
(400A)
CG-601
CG-603
(80A)
CG-602
SP-600
(300A)
Ballast Line
CG-600
CG-605
ESD
CG-604
(700A)
CL-016
SP-601
SP-701
(80A)
CS-008 (80A)
(50A)
(700A)
CL-015
Forcing
Vaporuizer
CS-502
CS-506
(50A)
(600A)
CS-510
CS-505
Description
Orifice
CG-502
(500A)
CS-504
(40A)
CS-501
Symbol
CS-703
(25A)
LNG
Vaporuizer
(50A)
CS-704
(600A)
(300A)
(40A)
CG-501
(300A)
ESD
(600A)
Vapour Crossover
CG-529
(600A)
CS-503
(80A)
CG-513
No.1 H/D
Compressor
(450A)
CG-511
(600A)
CG-517
(250A)
(600A)
CG-503
Liquid Crossover
No.2 H/D
Compressor
CG-525 CG-521
SP-602
ESD
CG-514
(450A)
CG-500
(300A)
(80A)
Key
Stripping Crossover
(250A)
CG-526 CG-522
High Duty
Heater
CG-507
CG-518
Mist
Separator
(500A) CL-010
No.1 L/D
Compressor
(650A)
CG-505
(700A)
CG-515
CG-527 CG-523
(250A)
(300A)
(350A)
CG-509
CG-530
CG-512
To Engine Room
(500A)
(150A)
(300A)
(300A)
CG-504
CG-519
CL-014
No.2 L/D
Compressor
(250A)
CG-508
CL-013
CG-516
CG-528 CG-524
Low Duty
Heater
(300A)
(400A)
CG-606
CG-520
(150A)
CG-506
(750A)
CG-510
CS-007
CL-009
(400A)
S
Spray Pump
It is assumed that all valves are closed prior to use, and it is No.3 tank that
contains the heel.
Purpose
Performance Criteria
Auxiliaries Involved
LD compressor
LD heater
Spray Pump
Operation Duration
Check Points
- Tank Pressure
- Insulation space pressure
-Temperature of insulation spaces and cofferdams
-Operating condition of LD compressor/ LD heater /
Spray pump including monitoring of instrument
safety function (alarm & etc.)
NOTE
The average temperature (except bottom) on IAS is linked to CTS. And this is
not used for cooldown target temperature but used for the averaged vapour
temperature during normal ballast voyage.
1) Open the vapour dome outlet valves to the vapour header CG101/100,
201/200, 301/300 and 401/400 (likely to be open already on the three
full tanks for gas burning).
2) Open the spray line block valves CS702, CS700.
3) Open the spray master valve CS203 and Port & Starboard spray supply
valve CS207/ CS208.
3) Open No.3 stripping/spray pump discharge valve CS303 to 30%, fully
open return valve CS300 and Start the No.3 stripping/spray pump.
4) Adjust the spray discharge valve CS303 to allow minimum flow and
fully open CS203 to cool down No.2 spray header. Pressure in the
stripping/spray header shall be controlled by CS300.
5) Once cool down of the spray header to No.2 tank is complete, increase
the flow rate by adjusting No.3 stripping/spray pump discharge valve to
allow an even cool down and control of vapour pressure.
NOTE
Care should be taken to control the vapour pressure either in the boilers as fuel,
or venting to the atmosphere via CG702, CG700 and the No.1 vent mast riser.
7 - 26
All equipment to be used should be thoroughly prepared and tested, and all
safety equipment should be checked and be ready for use if required.
1) Cargo Equipment to be Tested
The person (master or other officer) in overall control of the operation should be
clearly established before the operation commences, and the actual transfer
should be carried out in accordance with the wishes of the receiving ship.
The means of communication should also be well established before transfer and
both ships must be in direct contact with each other during the whole operation.
Radio telephone contact should be established on VHF Channel 16 and thereafter
on a mutually agreed working channel. Approach, mooring, transfer and
unmooring should not be attempted until fully effective communications are
established.
Should there be a breakdown in communications for whatever reason, either on
approach or during transfer, the operation should immediately be suspended.
CAUTION
The ignition of gas vapours may be possible by direct or induced radio
frequency energy and no radio transmissions, other than at very high frequency,
should take place during transfer operations. Arrangements should be made with
an appropriate coast station for blind transmissions which would allow reception
of urgent messages.
2. Pre-Mooring Preparations
Prior to mooring, the organisers of the transfer should notify the local authorities
of their intentions and obtain any necessary permits.
The two vessels should liaise with each other and exchange details of the ships:
y
y
y
y
y
y
y
y
y
y
y
y
y
y
The most successful method of berthing is with both ships underway. One ship,
preferably the larger, maintains steerage way on a constant heading as requested
by the manoeuvring ship, usually with the wind and sea dead ahead. The
manoeuvring ship then comes alongside.
Successful operations have taken place with one ship at anchor in fine weather
conditions, and this is not too difficult if there is an appreciable current and a
steady wind from the same direction. If not, then tug assistance may be necessary.
Mooring should be rapid and efficient and can be achieved with good planning
by the Masters of both ships.
In general, the following points should be noted.
y
y
y
y
2) Safety Precautions
y
y
y
3. Mooring
Contact is then made by the manoeuvring ship, reducing the distance between
the two ships by rudder movements until contact is made by the primary fenders.
NOTE
Masters should be prepared to abort if necessary. The International Regulations
for Preventing Collisions at Sea must be complied with.
On completion of mooring, the constant heading ship will proceed to an
anchoring position previously agreed. The manoeuvring ship will have its
engines stopped and rudder amidships, or angled towards the constant heading
ship. The constant heading ship should use the anchor on the opposite side to that
on which the other ship is berthed.
From the time that the manoeuvring ship is all fast alongside, to the time the
constant heading ship is anchored, the constant heading ship assumes
responsibility for the navigation of the two ships.
7 - 27
4. Transfer Operations
Transfer can begin when the two Masters have ensured that all the pre-transfer
checks and precautions have been completed and agreed between them. Both
ships should be prepared to disconnect and un-moor at short notice should
anything go wrong.
During transfer, ballast operations should be performed in order to keep the trim
and list of both vessels constant. Listing of either vessel should be avoided
except for proper tank draining. Checks should also be kept on the weather,
traffic in the area, and that all safety equipment is still in a state of readiness.
Transfer can take place whilst the two vessels are at anchor. This is the most
common method. Transfer can also take place whilst the two vessels are
underway, though this depends on there being adequate sea room, traffic
conditions and the availability of large diameter, high absorption fenders.
1) After completion of mooring, the constant heading ship maintains
steerage way and the manoeuvring ship adjusts its engine speed and rudder
angle to minimize the towing load on the moorings. The course and speed
should be agreed by the two Masters and this should result in the minimum
movement between the two ships. The Master of the constant heading ship
is responsible for the navigation and safety of the two vessels.
.
2) Drifting Transfer
This should only be attempted in ideal conditions.
3) Completion of Transfer
After transfer has been completed and before unmooring, all hoses
should be purged, manifolds securely blanked and the relevant
authorities informed that transfer is complete.
5. Unmooring
This procedure will be carried out, under normal conditions, at anchor, though if
both Masters agree, unmooring can take place underway.
Before unmooring begins, obstructions from the adjacent sides of both ships
should be cleared and the sequence and timing of the event be agreed by both
ships, and commenced at the request of the manoeuvring ship. Lines should be
singled up fore and aft, then the remaining forward mooring let go allowing the
ships to drift away from each other, at which time the remaining after moorings
are let go and the ships drift clear of each other. Neither ship should, at this point,
attempt to steam ahead or astern until their mid lengths are about two cables
apart.
7 - 28
7 - 29
Part 8
Fire Fighting System
Part 8 Fire Fighting System
BF-81
Key
Sea Water Line
(40A)
BF-83
(40A)
BF-84
(40A)
(40A)
(80A)
Pipe Duct
Pipe Duct
(80A)
BF-06
(50A)
BF-04
To Bilge Eductor Drive
in Side Passage Way
(40A)
(150A)
(40A)
(150A)
BF-62
BF-58
No.1 Trunk
BF-30
BF-24
BF-18
BF-22
BF-44
(40A)
BF-34
BF-55
(80A)
BF-57
BF-32
BF-17
(40A)
(150A)
BF-28
BF-16
(40A)
BF-03
BF-01
BF-04
(80A)
Bosun Store
(125A)
BF-13
BF-36
BF-23
(150A)
BF-48
No.2 Trunk
BF-42
BF-29
Cofferdam
BF-46
BF-31
Cofferdam
BF-50
BF-60
Cofferdam
For Side
Passage
Way
BF-35
BF-20
BF-75
BF-73
No.3 Trunk
BF-41
BF-26
BF-103
BF-64
BF-45
BF-38
BF-65
BF-49
BF-40
(125A)
BF-71
BF-67
Motor Compressor
BF-69 Room
Room
BF-79
(150A)
BF-77
No.4 Trunk
BF-59
BF-56
To
Accom.
For Trunk
Deck
BF-66 BF-63
(40A)
Accommodation
Area
BF-70
Cofferdam
Cofferdam
BF-76
BF-12
(200A)
(150A)
BF-21
BF-07
BF-27
BF-05
BF-33
(80A)
BF-08 BF-06
BF-25
BF-39
BF-43
BF-37
(40A)
(150A)
(40A)
BF-51
(40A)
BF-61
(40A)
(125A)
(125A)
BF-68
(80A)
BF-52
BF-74
BF-72
(125A)
BF-78
BF-54
FWD W.B
Tank (P&S)
BF-97
BF-99
BF-100
BF-94
(40A)
Fore Peak
Tank
(Void)
Fire Hydrant
for Bow Thrust
Room
BF-47
BF-101
BF-122
BF-120
Paint
Deck Incinerator
Store
Fresh
Store
Room
(80A)
Water (40A)
Tank (S)
BF-121
BF-102
From To
E/R Accom.
BF-124
Engine
Casing
BF-123
BF-113
BF-125
Distilled Water
Tank (S)
BF-98
(40A)
(40A)
BF-114
BF-96
BF-118
(150A)
CO2
Room
To Swimming Pool
Drinking
Water
Tank (P)
BF-117
Distilled Water
Tank (P)
BF-116
(40A)
(200A)
BF-10
To Engine Room
BF-53
B.W
Sea
Chest
Tank Top
BF-119
BF-115
(80A)
FWD H.F.O
Tank (P&S)
BF-111
(100A)
BF-05
Swimming
Pool
(50A)
(40A)
Cooling
Water
Tank
C.L.
BF-08
BF-112
(40A)
Eductor
Driving Line
For C.L.B.W
BF-127
BF-130
(40A)
(40A)
BF-07
Bosun Store
(50A)
(40A)
(40A)
4th Deck
BF-107
BF-109
(125A)
(40A)
Sea Water
Supply
BF-114
Eductor
Driving Line
For Bosun
Store
BF-09
BF-110
BF-129
BF-14
BF-14
(40A)
(150A)
BF-19
3rd Deck
BF-12
BF-13
(125A)
(40A)
AFT Peak
Tank
(100A)
BF-128
Engine Room
(125A)
(40A)
BF-108
(P)
BF-94
BF-102
(80A)
(40A)
BF-105
(40A)
(40A)
Trunk
(200A)
BF-126
2nd Deck
(40A)
BF-97
BF-106
(40A)
(150A)
BF-01
BF-02
BF-03
(50A)
BF-95
BF-96
BF-91
(40A)
(80A)
(40A)
BF-125
(125A)
(40A)
Trunk
(40A)
Cofferdam
BF-116
BF-104
BF-92
(40A)
BF-119
CO2 BF-118
Room (40A)
(80A)
BF-93
BF-98
(40A)
BF-99
(80A)
(40A)
BF-120
BF-88
BF-89
Cofferdam
BF-90
BF-85
(40A)
(Overflow)
(40A)
(80A)
(100A)
BF-86
(100A)
BF-87
Drain Line
BF-82
(80A)
BF-02
From Em'cy
Fire Pump
To Bilge Eductor Drive
in Side Passage Way
8-1
No. of sets:
Motor output & speed:
2. General
The fire main system is supplied from the engine room by the two Bilge, Fire &
G/S Pumps. They are electric motor driven vertical centrifugal pumps, with a
delivery capacity of 150/245m3/h at 115/30m.
The Emergency Fire Pump is located in Bow Thruster room, Emcy Fire pump
room. This pump is a vertical centrifugal pump with its own direct sea suction.
The pump rate is a delivery capacity of 72m3/h at 110m.
The fire main system is kept pressurised by a fire line pressurising pump rated at
2m3/h X 50m X 3.7kW. This pump is an electric motor driven horizontal
centrifugal pump and has an automatic pressure cut-in/out switch. Pressure
switches and a low level alarm switch are fitted on the accumulator tank to
maintain pressure on the fire main line when the pump cuts out.
The deck fire main line has a main isolating valve before the port, starboard and
ring main isolating valves. The ring main is fitted with a further four section
isolator valves on each side at regular intervals along the deck to allow any part
of the system to be supplied from either side of the ship.
8-2
WS-14
WS-29
WS-24
(80A)
(25A)
WS-25
No.4 Trunk
WS-04
WS-06
(80A)
WS-01
WS-03
(40A)
(40A)
(40A)
WS-08
WS-05
(100A)
No.3 Trunk
WS-02
(80A)
No.2 Trunk
No.1 Trunk
(300A)
Life Boat
(80A)
WS-07
(40A)
(100A)
WS-16
(100A)
WS-12
WS-21
(80A)
WS-30
WS-27
WS-28
Compressor
Room
WS-13
(200A)
WS-09
WS-17
Motor
Room
WS-20
(40A)
(200A)
WS-18
WS-15
(300A)
WS-22
(80A)
WS-26
WS-23
Key
Sea Water Line
Cofferdam
Cofferdam
Cofferdam
3rd Deck
Cofferdam
Engine Room
Cofferdam
(300A)
2nd Deck
F.W.D
H.F.O
Tank
(P&S)
4th Deck
No.4 Cargo Tank
Tank Top
F.W.D W.B
Tank (P&S)
Life Boat
WS-30
(40A)
(80A)
No.2 Liquid
Dome
No.2 Gas
Dome
(50A)
WS-01
(50A)
WS-02
No.1 Liquid
Dome
No.1 Gas
Dome
Cofferdam
WS-06
(80A)
(50A)
(40A)
WS-03
(40A)
WS-04
Cofferdam
No.3 Gas
Dome
(80A)
WS-05
WS-07
(50A)
WS-16
No.3 Liquid
Dome
(100A)
(80A)
(150A)
(40A)
WS-17
No.4 Trunk
(50A)
WS-14
Cofferdam
No.4 Gas
Dome
(80A)
(50A)
WS-08
WS-10
(80A)
WS-09
(100A)
WS-21
WS-18
Cofferdam
No.4 Liquid
Dome
WS-19
(40A)
WS-20
(50A)
(100A)
Cofferdam
(50A)
Accommodation
Area
(200A)
(25A)
(80A)
(200A)
From E/R
Water Spray
Pump
(300A)
WS-22
(300A)
WS-23
WS-29
Bosun
Store
(80A)
WS-32
(40A)
Life Boat
Motor
Room
Compressor
Room
No.2 Trunk
No.3 Trunk
WS-11
WS-31
WS-25
No.1 Trunk
WS-24
WS-28
(100A)
WS-26
WS-15
WS-27
(300A)
(300A)
(100A)
8-3
1. Specification
It is assumed that the sea water main suction valves at the sea chest(s) are open
to provide sea water suction.
(65A)
(80A)
(65A)
(50A)
2) Open the master valve WS28 and accommodation block valve WS26.
(50A)
(50A)
(50A)
3) Start the water spray pump either from the IAS screen or from the
emergency panel and supply water to the water spray system.
The water spray system is now in use and delivering water to all the selected
spray nozzles on deck.
(50A)
(125A)
(50A)
(100A)
(100A)
(80A)
1) All intermediate isolating valves along the water spray system on the deck
must be open.
(200A)
To Water Spray
Main (300A)
WS-26
Key
Sea Water Line
(10A)
(25A)
(80A)
2. General
(300A)
The pumps supply sea water to the spray nozzles at the following locations:
- Accommodation exterior bulkheads and lifeboat stations
- Cargo machinery and electric motor room exterior bulkheads
- Cargo manifold area
- Cargo tank liquid and gas domes
Cargo Tank
The accommodation block front, cargo machinery and electric motor room,
cargo liquid and gas dome and manifold areas are protected by water spray from
the effects of fire, gas leakage, or liquid spill.
There is one (1) Water Spray Pump, mounted on the bottom platform in the
engine room, delivering to two (2) spray rails across the accommodation block
front with lifeboat embarkation areas port and starboard and cargo machinery
room sides with deck domes/manifolds.
The water spray system can also be supplied by the bilge, fire & G/S pump via
cross-connecting valve 54V.
The main remotely operated hydraulic isolating valve (BA-43) operated from the
fire control station, CCR and manually at the local side. The spray pump can be
started locally and from the wheelhouse, CCR, on the main deck close to the
accommodation exits and the fire control room.
Each spray rail is subdivided into smaller sections, with a section isolating valves
fitted.
8-4
(Spare)
(Main)
No.4 Trunk
(65A)
8
Dry
Power
Unit
(65A)
No.3 Trunk
No.2 Trunk
1
No.1 Trunk
Dry
Power
Unit
Cofferdam
Cofferdam
Cofferdam
3rd Deck
Cofferdam
Engine Room
Cofferdam
2nd Deck
F.W.D
H.F.O
Tank
(P&S)
4th Deck
No.4 Cargo Tank
Tank Top
F.W.D W.B
Tank (P&S)
Drain Plug
(Main)
(Spare)
(80A)
(80A)
Dry
Powder
Space
Cofferdam
No.1 Trunk
Bosun
Store
(40A)
(40A)
(40A)
3
No.2 Trunk
Cofferdam
No.3 Trunk
(40A)
Cofferdam
(40A)
No.4 Trunk
Cofferdam
Cofferdam
(40A)
Accommodation
Area
No.1 Dry
Power
Unit
(65A)
(40A)
(65A)
(40A)
No.3 Dry
Power
Unit
No.4 Dry
Power
Unit
(65A)
(65A)
(80A)
(80A)
(Main)
No.2 Dry
Power
Unit
(Spare)
8-5
1. General Description
The 8 dry powder hose cabinets which are situated along the main deck centre
line from forward to aft. Each hand held hose has a length of 33 m.
Operation of the unit is from any of the four associated hose cabinets. Activation
of the CO2 pilot cylinders in one of the cabinets allows the high pressure gas to
flow into the main valve (before the hose) actuator, thereby causing the valve to
open. The nitrogen is now ported to the release mechanism for the bank of
nitrogen expulsion cylinders.
The dry powder fire fighting system is supplied by NK Co., Ltd. and consists of
4 separate dry powder tank units;
Tank 1 - has monitor directed at manifold port/fwd and 2 hose cabinets.
Tank 2 - has monitor directed at manifold stbd/fwd and 2 hose cabinets.
Tank 3 - has monitor directed at manifold port/aft and 2 hose cabinets.
Tank 4 - has monitor directed at manifold stbd/aft and 2 hose cabinets
The capacities of the monitor nozzles are 19 kg/sec and hand hose nozzles are
3.5 kg/sec. The sufficient quantity of dry powder agent is stored in each tank to
provide a minimum 45 sec. discharge time for monitor and all hand hose nozzles
discharge at their discharge rate.
1) Dry Powder Capacity Required (Including 10% Allowance)
Four(4) monitors and eight(8) hose cabinets
a) One (1) Monitor:
19 kg/sec x 60 sec x 110% x 1set= 1,245 kg
b) Two (2) Hand hose:
3.5 kg/sec x 60 sec x 110% x 2set = 462 kg,
Total: 1,716 kg
d) Pull valve handle in the release station to allow CO2 gas to open
the N2 cylinders. This activates the pressurising (120Kg/cm2) of
the dry powder tank and opens the main discharge valve.
e) The system is now activated.
Fig.2 Deck Dry Powder Hose Cabinet
The 9 high pressure nitrogen cylinders are now released and flow into the main
dry powder tank through an upper and lower injection pipe. When the tank
pressure has reached sufficient pressure, a pressure release valve operates,
thereby allowing the residual nitrogen in the expellent pipe-work to open the
main outlet from the tank.
Operation of the manual valve at any of the 8 hose cabinets supplied by the tank
will now allow the dry powder to be used as required.
After the system has been used it is necessary to ensure the expellent pipe work
and more importantly, that the main valves are blown clear on any remaining dry
powder.
4. Operating Procedure
2)
a)
b)
c)
d)
2. Main System
e)
Two dry powder units are situated on the main deck mid-ships, port and
starboard. Each unit contains a 1,716 kg dry powder storage tank, 9 nitrogen
expellent cylinders of 68 liters and a single dry powder monitor.
Operation of the system can be carried out from a cabinet in the Fire Control
Room, CCR and locally. Activation of the CO2 pilot cylinders in the cabinets
allows the high pressure gas to flow into the main valve (before the monitor)
actuator, thereby causing the valve to open. The CO2 is now ported to the release
mechanism for the bank of nitrogen expulsion cylinders.
The 9 high pressure nitrogen cylinders are now released and flow into the main
dry powder tank through an upper and lower injection pipe. When the tank
pressure has reached sufficient pressure, a pressure release valve operates,
thereby allowing the residual nitrogen in the expellent pipe-work to open the
main outlet from the tank. Operation of the manual valve at the monitor will now
allow the dry powder to be used as required.
After the system has been used it is necessary to ensure the expellent pipe work
and, more importantly, that the main valves are blown clear on any remaining
dry powder.
1) To Operate Monitor
a)
8-6
Local
PORT/AFT
(Main)
Local
Cleaning Line
Cleaning Line
Symbol
Lower Inlet
N2 Gas Line
Tank P/G
Secondary P/G
Upper Inlet
N2 Gas Line
No.2 V/V
Upper Inlet
N2 Gas Line
Lower Inlet
N2 Gas Line
Tank P/G
Selection Valve
Non-return Check Valve
Secondary P/G
Primary P/G
Cleaning Valve
(for Change Over)
Primary P/G
No.2 V/V
Regulator
Main Regulator
Main Discharge Valve
Non-return Check Valve
Ball Valve
Safety Valve (for Tank)
Cylinder
Cleaning Line
Cleaning Line
Local
Lower Inlet
N2 Gas Line
Tank P/G
STBD/AFT
(Main)
Secondary P/G
Upper Inlet
N2 Gas Line
Hand Hose
No.1 Valve
(Main)
No.2 V/V
No.1 Valve
(Main)
PORT
Description
Valve (Normal Close)
STBD
No.1 Valve
(Main)
No.2 V/V
No.1 Valve
(Main)
PORT
PORT/FWD
Instruction Chart
Pressure Gauge
Upper Inlet
N2 Gas Line
Local STBD/FWD
Lower Inlet
N2 Gas Line
Tank P/G
Secondary P/G
Primary P/G
Primary P/G
Key
R
Nitrogen
8-7
Blank Page
8-8
CO2 Room
A-Deck
(40A)
Cargo
Compressor
Room
(24 Bottles)
Engine
Room
(632 Bottles)
Cargo Switch
Board Room
(17 Bottles)
Cargo
Compressor
Motor Room
(11 Bottles)
Emergency
Generator
Room
(4 Bottles)
Symbol
Paint
Store
(3 Bottles)
Pipe Line
318 Bottles
(40A)
b
24 Bottles
Electric Line
254 Bottles
PG
(40A)
PG
B
a
Pilot Line
P
(150A)
(150A)
Description
C
b
E
d
TD
E
F
e
Air Horn
Alarm Buzzer with Lamp
Lamp (EX-Proof)
Buzzer (EX-Proof)
c
E
17 Bottles
(40A)
Relay Box
(40A)
(40A)
TD
E
(40A)
11 Bottles
P
To CO2 Alarm
(40A)
Ball Valve
Beam Scale
(20A)
(25A)
(40A)
(40A)
(50A)
3 Bottles
(150A)
(40A)
5 Bottles
(150A)
Upper Deck
(40A)
Electric Horn
Instruction Chart
Caution Plate
Warning Notice
Limit Switch
Spare Parts
Engine Room
Key Box
Upper Deck
& Casing
PG
2nd Deck
Cargo
Compressor Room
Cargo Switch
Board Room
Cargo Compressor
Motor Room
Emergency
Generator Room
Paint Store
3rd Deck
B
EX
A
EX
4th Deck
A
(5 EA)
EX
9 kg/cm2
Air Supply
Floor &
Under Floor
CO2 Alarm
EX
9 kg/cm2
Air Supply
8-9
2) Ensure that all persons have evacuated the protected room and have
been accounted for.
3) Close and check that all doors, hatches and other openings are closed.
The CO2 flooding system is consists of 632 cylinders, each containing 45kg,
and high pressure cylinders. These are contained in the CO2 room, situated on
the engine room casing A deck.
Gross
Volume
(m)
Mixing
Ratio
(%)
36150
Name of Space
In kg
In 45kg
Cyl.
40%
25821.46
574
39770
40%
218407.14
632
Cargo compressor
room
1292
45%
1038.21
24
10) Check pilot pressure is above 3 MPa. If not, open another pilot
cylinder valve.
1050
40%
750
17
Cargo compressor
motor room
636
40%
454.3
11
11) The main valve will be opened. At the same time ventilation fan will
stop.
Engine generator
Room
257
40%
183.6
Paint store
139
40%
99.3
13) If the pilot system fails to operate, the main valve can be opened
manually from the CO2 room and the cylinders released by hand.
632
Total supplied
CO2
Flooding the protected areas is achieved by the operation of the ball valves from
their respective cabinets in the fire control room or in the CO2 room and the
release of the pilot CO2 cylinders (release cabinets in the fire control room and
in the CO2 room). Upon opening the supply cabinet door, the CO2 alarm is
activated and the ventilation fans stop when the main valves are opened. The
pilot gas is directed by the operation of the respective main valve (having first
operated the time delay switch down stream of the HP cylinders) and the main
valve for the selected area.
14) Do not re-enter the protected compartment for at least 24 hours and
ensure that all reasonable precautions have been taken, such as
maintaining boundary inspections, noting cooling down rates and/or
any hot spots which may have been found. After this period, an
assessment party donning breathing apparatus can enter the space
quickly through a door which is then shut behind them. Check that the
fire is extinguished and that all surfaces have cooled prior to
ventilating the engine room. Premature opening could cause re-ignition
if oxygen contacts hot combustible material.
CAUTION
Release of CO2 into any space must only be considered when all other options
have failed and then only on the direct instructions of the Master.
15) Do not enter the engine room without breathing apparatus until the
engine room has been thoroughly ventilated and the atmosphere
proved safe.
Over pressure of the main line is prevented by a safety valve, which will vent
the gas to atmosphere.
8 - 10
FAULT
FIRE
DISC.
Menu
Power
Test
Alarm Transfer
Alarm Device
Alarm Delay
Zone/Unit
System Fault
Warning
Pre-Alarm
Home
'_'
ABC
Disc.
DEF
GHI
JKL
MNO
PQRS
TUV
WXYZ
OK
F1
OK
F2
F3
Mute
This button gives direct access to the main menu, where all the
functions of the CS4000 system can be accessed.
transfer output.
Next
9) Zone/Unit indicator
Indicates with yellow steady light that a fire detector or zone is
disconnected. Flashing yellow indicates that at least one fire detector
or zone is in fault condition.
23) OK buttons
The OK buttons are used to select a menu alternative or to accept a
function.
Reset
FIRE
Power
Scroll
Fault
Disconnection
Test
Fire
Fault
Disc.
Mute
8 - 11
The repeater panel is used to monitor functions of the CS4000 fire alarm system.
It is possible to view and list fire alarm, faults and disconnections.
1) Fire alarm indicator
The fire alarm indication is flashing with red light to indicate that there
is an un-muted fire alarm in the system. It turns into steady light when
Access
level
Description of user
2B
6) Fire button
Gives direct access to the fire alarm list.
FAULT
FIRE
DISC.
Power
Test
Alarm Transfer
Alarm Device
Alarm Delay
Zone/Unit
System Fault
Warning
Pre-Alarm
Menu
15.53
'_'
ABC
GHI
Home
PQRS
JKL
Disc.
DEF
MNO
TUV
WXYZ
OK
_______________________________________________
RESET=Reset item, MUTE=Mute, OK=Details
0=Disconnect, 1=Print item, 2=Print all.
F1
OK
F2
F3
Mute
Next
Reset
a)
a)
8) Disc. button
Gives direct access to the disconnection list.
9) Alphanumerical display
The blue alphanumerical display has a capacity of 14x40 characters.
Access level 1
Only viewing of fire or fault alarms. Fire alarms have priority over
fault alarms. Possibility to mute local buzzer.
b) Access level 2
As level 1 + access to the menu system. List status. Reset and
muting of alarms.
c)
Access level 2B
As level 2 + make disconnections.
d) Access level 3
As level 2B + possibility to make changes to the configured
system.
Indication
The following information is displayed on the control panel:
Number of alarm(s)
Zone in alarm
Type of unit in alarm
Address number of unit in alarm (only for addressable loop)
Supplementary text 1 (if defined)
Press OK to view more details:
Time of alarm
Date of alarm
Supplementary text 2 about location of detector (if defined)
b) Mute
The MUTE button has different function depending on the current
access level.
3. Operation
e)
1) Access levels
To prevent un-authorized operation of the system there are access
levels to protect the different functions of the CS4000. The user has to
login to the system or unlock the lock (mainly industrial applications)
before any vital operations can be performed. Without access to an
authorization code or a key the user can only view fire and fault alarms
and mute the local buzzer.
The system is in access level 1 when the door is closed or if it is
locked by the key.
The system automatically returns to access level 1 when the lock is
locked or after 30 minutes of inactivity.
Access level 4
All functions available, including advanced service options.
3) Pre-alarm
The CS4000 is equipped with the function Pre-alarm that will give an
early alarm to a slow raise of the fire condition, for example a
smouldering fire. The Pre-alarm level is lower than the ordinary fire
alarm level.
A pre-alarm will activate the local buzzer and the indication
Prealarm will be lit on the control unit. The pre-alarm will also be
added to the pre-alarm list found under:
Menu/ 2 Fire Alarms/ 2 Pre-Alarm List.
8 - 12
Access level 1
Pressing MUTE causes the internal buzzer to silence.
Access level 2 or higher
Pressing MUTE causes the internal buzzer and all external alarms
to silence and mutes the fire alarm indication.
When the alarm is muted the fire indication stops flashing and
turn over to steady light.
Press OK for more details.
c)
Reset
FAULT
FIRE
DISC.
Power
Test
Alarm Transfer
Alarm Device
Alarm Delay
Zone/Unit
System Fault
Warning
Pre-Alarm
Menu
'_'
18.53
Home
ABC
GHI
JKL
PQRS
Reset a fault:
1. Go to the fault list under: Menu/ 1 Fault Alarms/ 1 Fault List
2. Choose the fault in the fault list and then press RESET to reset
the fault alarm.
If the cause of the fault alarm remains the alarm cannot be
reset.
Check the problem and deal with it. Then try to reset the fault
again.
Reset all faults:
1. Go to: Menu/ 1 Fault Alarms/ 3 Reset All Faults
2. Press OK
d) Fault messages
If a fault occurres in the system it will be displayed at the control
panel with information about which part of the system that is
faulty and also a short description of the fault.
Disc.
DEF
MNO
TUV
WXYZ
OK
_______________________________________________
RESET=Reset current entry, MUTE =Mute all
OK=Details, 1=Print i
F1
OK
F2
F3
Mute
a)
Next
Reset
Indication
The following information is displayed in the control unit:
Number of fault(s) (i.e. how many faults are detected)
Type of fault
Identification of the faulty unit
Supplementary text for the faulty unit (if defined)
Press OK for more details:
Time when fault occurred
Date when fault occurred
Supplementary text about location of fault (if defined)
b) Mute
Press MUTE to silence internal buzzer and mute all faults in list.
Press OK for more details.
c)
Reset
8 - 13
2) Specification
When the detector is in alarm condition, a red LED on the detector will
be lit.
1. Heat Detector
1) Description
The NS-AH/AIS is an analogue addressable heat detector for Salwico
addressable fire alarm system. It has a pre-programmed static alarm
level of 54C and it also gives a rate of raise pre-alarm.
This low profile heat detector uses a high quality electronic sensing
element of low thermal mass, which gives very accurate and fast
temperature readings.
The temperature can be displayed on the fire alarm panel. When the
detector is in alarm condition, a red LED on the detector will be lit.
The LED is lit until the alarm has been reset.
The detector can be connected to the fire detection loop by using two
different base plates. In dry and clean spaces the base plate NSBNCL can be used. In harsh environment the IP55 base NS-2IP55
together with the adapter NS-ADAPT can be used. The detector is
polarity independent. It is marked with a green spot.
The address is set with a DIP switch. An external LED indicator,
buzzer etc. can be connected to the remote output.
The LED will be lit until the alarm has been reset at the control panel.
The detector can be connected to the fire detection loop by using two
different base plates. In dry and clean spaces the base plate NS-BNCL
can be used.
In harsh environment the IP55 base NS-2IP55 together with the
adapter NS-ADAPT can be used. The address is set with a DIP switch.
The detector is polarity independent. An external LED indicator,
buzzer etc. can be connected to the remote output.
2) Specification
Sensor type
UV Tron
185 ~ 260mm
Supervising angle
100
-25C to +70C
System voltage
24V DC
2) Specification
Sensing method
-25C to +70C
System voltage
24V DC
4. Call Point
1) Description
The NS-ACP is a manual call point for the addressable fire alarm
systems Salwico NSAC-1 and CS4000 with SPK2000. Pressing the
glass causing it to crack activates the fire alarm. A protective plastic
coating on the glass prevents operator injury.
A red LED is lit on the call point when the control panel has received
the alarm. It will be lit until the glass has been replaced and the alarm
has been reset at the control panel. The address is set with a DIPswitch mounted inside the call point.
The call point is polarity independent.
2) Specification
Operating temperature range
-25C to +70C
System voltage
24V DC
54C
-25C to +90C
System voltage
24V DC
2. UV Flame Detector
1) Description
The NS-AUV is an analogue addressable flame detector for Salwico
addressable fire alarm systems.
It is sensitive to ultraviolet light emitted by flames.
Due to its high sensitivity to UV-light, the detector has a built-in
advanced alarm algorithm to avoid false alarms.
Thanks to the very wide supervising angle it can cover large areas,
and the UV tube is protected by a quartz glass.
This flame detector is very suitable for use in harsh environments.
1) Description
The NS-AOS is an analogue addressable optical smoke detector for
Salwico addressable fire alarm systems.
The address is set with a DIP-switch mounted on the back of the
detector. When the detector is in alarm condition, a red LED on the
detector will be lit.
The LED is lit until the alarm has been reset at the control panel.
The detector can be connected to the fire detection loop by using
different base plates. In dry and clean spaces the base plate NS-BNCL
or UB-1 can be used.
For installation in harsh environment the IP55 base NS-2IP55 together
with the adapter NS-21IP55 together with the adapter NS-ADAPT or
SPB-1 can be used.
The detector is polarity independent. An external LED indicator,
buzzer etc. can be connected to the remote output.
8 - 14
These Cocks/Valves
To be Installed Near
Vent Damper
To be Located
Outside Engine Room
PX
51V
To Funnel Ventilation Damper (S)
PIAL
IAS
52V
PI
Air
Reservoir
for
Quick
Closing
Valve
(A)
G/T L.O
Settling Tank
(10.0 m3)
F-315V
Incinerator
M.D.O Service
Tank (2.0 m3)
G/E L.O
Settling Tank
(10.0 m3)
F-101V
F-126V
F-29V
L-6V
To STBD Group
I.G.G
M.D.O Service
Tank
(70 m3)
To PORT Group
2nd Deck
L-17V
F-36V
F-81V
Casing
F.O
Addictive
Tank
(3.0 m3)
F-304V
63V
G/E M.D.O
Service Tank
(30.0 m3)
L-206V
L-32V
Main L.O
Gravity Tank
(25.0 m3)
Main L.O
Settling Tank
(80.0 m3)
3rd Deck
4th
Deck
H.F.O Overflow
Tank
(70.0 m3)
Low Sulphur
F.O Tank (S)
(205.7 m3)
H.F.O
AFT H.F.O
Settling Tank (S)
Bunker Tank (S)
(535.5 m3)
(462.2 m3)
Floor Deck
8 - 15
F-27V
F-1V
F-201V
F-43V
F-3V
H.F.O
AFT H.F.O
Settling Tank (P) Bunker Tank (P)
3
(540.0 m)
(353.5 m3)
F-6V
Low Sulphur
F.O Tank (P)
(293.2 m3)
F-203V
F-46V
From G/S
Air System
F-318V
M.D.O
Storage Tank
(100 m3)
Key
Air Line
Diesel Oil/ Gas Oil Line
Fuel Oil Line
Lubricating Oil Line
Waste Oil Line
Drain Line
1. Introduction
a)
The main fire damper three-way valve, located at the emergency shut-off
cabinet in the fire control station, must be turned to the VENT position to
actuate all the fire dampers. The dampers will close under the action of
their counterweights when air is vented from their cylinders.
All the outlet valves from the fuel oil and lubrication oil tanks, from which oil
could flow to feed a fire, are equipped with air operated quick-closing valves.
They are supplied and controlled from the quick-closing valve air reservoir
situated in the emergency shut-off device control box located in the fire control
station. The reservoir is supplied with air, at a pressure of 0.9 MPa, from the GS
air system. The air is supplied directly from the GS air manifold after the oil
filters, with an inlet valve on the quick-closing valve air reservoir which is
locked open. A branch pipe on the air line to the reservoir supplies air directly
to the engine room ventilation fire dampers
The quick-closing valve air reservoir is fitted with a low pressure alarm
transmitter. The oil tank quick-closing valves actuator lines are grouped into
two system, each with a three-way operating cock.
In normal operation the supply line to each group of tank valves is vented to
atmosphere. When the three-way operating cock is turned, air is supplied to
pistons which collapse the bridge of each valve in that group, thus causing the
valves to close.
The valves are reset by venting the air supply and operating the valve hand
wheel in a closed direction to reset the bridge mechanism and then opening the
valve in the normal way.
The emergency generator diesel oil tank quick-closing valve is operated by a
directly connected wire from outside the emergency generator room.
Engine room fire dampers are all connected to a three-way operating cock
which supplies air to the damper cylinders in order to keep the dampers open.
When the damper cylinder is vented the damper is closed by means of a gravity
acting on a counterweight. Damper cylinders may be vented as a group by
means of the three-way supply cock or may be operated individually by a threeway cock located close to each damper.
<Emergency Shut-off Control Box in Fire Control Station>
2. Fire Dampers
Engine room fire dampers operate to close ventilation openings in the event of a
fire. The dampers are kept open against a closing force(gravity acting on a
counterweight) by means of air pressure acting on the damper cylinder piston.
When air pressure is vented the damper or dampers will close. The fire damper
pipe work is supplied directly from the GS air system main pipe and air
pressure is constantly applied to the system.
Activation of the three-way control valve at the fire control station control panel
will vent the damper air line and cause all fire dampers to close. Operation of
individual local damper valves will vent each individual damper as required and
allow that damper to close.
8 - 16
1. Introduction
50.8 m A/B
An emergency trunk is fitted at the aft end of the engine room to allow
personnel to escape in the event of a life threatening situation. The emergency
trunk leads to the aft mooring deck.
G/E L.O
Settling
Tank
There are Emergency Escape Breathing Devices (EEBD) situated on all levels
of the engine room, which can be used to protect personnel during the escape
from the engine room.
Fan
Room
W
G/E L.O
Storage
Tank
Proceed aft to the A class fire door leading into the emergency trunk and climb
the vertical ladder to the aft mooring deck.
2. Emergency Escape Breathing Device (EEBD)
Floor : 2 ea
4th deck : 2ea
3rd deck : 2ea
2nd deck : 2ea
B.V.H.
Room
Distilled
Water Tank
(P&S)
Deck Incin.
Store Room
W
Pool
Tank
M.L.O M.L.O
Storage Settling
Tank Tank
2nd Deck
F.W
Tank
(S)
3rd Deck
(25P)
(25P)
G/E M.D.O
Service
Tank
Low
M.D.O
Storage Sulphur
H.F.O.
Tank
Tank (S)
(S)
Engine Room
H.F.O
Settling
Tank (S)
H.F.O
Bunker Tank (S)
Paint
Store
4th Deck
H.F.O Overflow
Tank
H.S.C
C.W. Tank
L.S.C
No.5 Cofferdam
8 - 17