Beruflich Dokumente
Kultur Dokumente
Revision status
Instruction
No.
Revision
Issue Date
March 2011
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
2.12
2.13
2.14
2.15
2.16
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
3.1
3.2
3.3
3.4
0
0
0
0
March 2011
March 2011
March 2011
March 2011
March 2011
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
5.11
5.12
0
0
0
0
0
0
0
0
0
0
0
0
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
Transmission Substation
Work Practice Manual
Revision status
Instruction
No.
Revision
Issue Date
5.13
5.14
5.15
5.16
5.17
5.18
5.19
5.20
5.21
5.22
5.23
5.24
0
0
0
0
0
0
0
0
0
0
0
0
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
6.10
6.11
6.12
6.13
0
0
0
0
0
0
0
0
0
0
0
0
0
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
7.1
March 2011
App 1
App 2
App 3
App 4
App 5
App 6
0
0
0
0
0
0
March 2011
March 2011
March 2011
March 2011
March 2011
March 2011
Transmission Substation
Work Practice Manual
Revision status
Contents
1.
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
2.12
2.13
2.14
2.15
2.16
3.1
3.2
3.3
3.4
4.
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
5.11
5.12
5.13
5.14
5.15
5.16
5.17
5.18
5.19
5.20
Definitions
Provisional emergency procedures
Portable earthing/shorting equipment
Electrical storms
Hazardous workplace safety
Confined space safety
Tags
Pyrolysis in vehicle tyres
Temporary barriers and signs
Asbestos and fibreglass working procedures
Electronic communications in vehicles and operational areas
Height safety
High voltage insulated tools and equipment testing and use
Fall prevention equipment
This section has been left intentionally blank
This section has been left intentionally blank
Fire precautions for transmission substations
Clothing and personal protective equipment requirements
Glove protection
Head protection
Face and eye protection
Electrical System Safety Procedures (ESSP) 2009
Customer switchyards guidelines
Substation entry requirements
Substation clearances
Secondary isolations
Portable ladders
Scaffolding
This section has been left intentionally blank
Elevated work platforms
Crane use
Dogging
Rigging
Use of SF6 gas
Safety observer role
Induced voltages
Pitch removal
Use of pesticides and herbicides
Vegetation management in substations
Site security
Un-authorised access
Electrical substation insulator washing
Transmission Substation
Work Practice Manual
Contents
5.21
Pilot cable boxes
5.22
Battery banks
5.23
Excavations in substations
5.24
Low voltage work rescue plan
6.1
Leaking oil filled equipment
6.2
Environmentally sensitive areas
6.3
Treated poles
6.4
Dangerous goods safety
6.5
Handling contaminated soil from around removed poles
6.6
Lamps and fluorescent tube disposal
6.7
Oil and chemical spills
6.8
Aboriginal artefacts
6.9
PCBs in streetlight capacitors and choke boxes
6.10
Controlled waste
6.11
Erosion
6.12
Native vegetation clearing and maintenance
6.13
Biosecurity
7.1
Licensing and authorisation
Appendix 1
Tags and signs
Appendix 2
Standard forms
Appendix 3
Westrail data
Appendix 4
Emergency contacts information
Appendix 5
Western Power facilities information
Appendix 6
First aid information
Transmission Substation
Work Practice Manual
Contents
Hierarchy of documentation
This Transmission substation work Practice Manual supersedes all other
documentation covered in the manual for Transmission Substation Work Practices
and Procedures.
Transmission Substation
Work Practice Manual
Responsibilities
The person in charge is responsible for:
Ensuring the persons who will perform each task or activity is provided with the
applicable instructions, has read and understands them.
Ensuring the persons performing each task or activity are made aware of their
responsibilities.
Ensuring persons performing allocated tasks and activities have the necessary
skills, experience and qualifications.
Undertaking the work in such a manner as to ensure others are exposed to the
least possible degree of risk or hazard.
Keeping up to date with all existing and future safety regulations and work
practice instructions.
Transmission Substation
Work Practice Manual
1.
Definitions
Aboriginal
A member of the Aboriginal race of Australia, including a descendant of the
indigenous inhabitants of the Torres Strait Islands.
Above
Greater in height than a given level, at or to a higher point.
Active or phase conductor
Any conductor that is maintained at a difference of potential from the neutral or
earthed conductor (also known as phase, line, red, white, blue, live).
Anchor/anchorage point
A secure point of attachment on a structure to which a fall-arrest device, or lanyard
assembly, or restraint line may be secured.
Apparatus
Any item of electrical machinery or equipment (including primary and secondary) in
which conductors are used, or supported, or of which they form a part.
Approved
Having appropriate Western Power endorsement in writing for a specific function.
Approved work technique
A documented technique which meets the requirements of this manual and which
has been approved by Western Power.
As constructed drawing
A design drawing that has been modified or altered due to changes to the
construction. As constructed drawings should be prepared by a qualified surveyor
where cable routes are shown and should be verified and signed by the person in
charge of the work.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Asbestos
The name given to a group of naturally occurring fibrous, crystalline minerals. The
three main types of asbestos minerals that have been used in products throughout
WA are Crocidolite (Blue Asbestos), Amosite (Brown Asbestos) and Chrysotile
(White Asbestos). Contact with asbestos is strongly linked to fatal illnesses.
Atmospheric monitoring device
A device that can measure continually or at intervals, the composition of the air
including:
Combustible gases.
Oxygen level.
Carbon monoxide.
Hydrogen sulphide.
Authorisation/Authorised
Shall be approved in writing or by means of an approved technique by western
power. See Approved
Authorised Person
Is a competent person with the delegated authority to perform the duty concerned
on behalf of Western Power.
Barrier
A temporary visual device (fence/restraint/person) that restricts or prevents access
to non-authorised personnel.
Brush contact
Momentary accidental or inadvertent contact.
Bush fire
A fire, or potential fire, however caused, including a fire in a building.
Bush Fire Service (previously the Bush Fire Board before 1997)
Co-ordinates the volunteer bush fire brigades that fight fires in rural areas.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Cable
An insulated conductor or two or more such conductors laid together, whether with
or without fillings, reinforcements or protective coverings.
Cable cover
A mechanical protective object that affords protection to cables from inadvertent
contact (e.g. split conduit, planking, slabs, conduit, poly pipe and concrete) covered
with earth placed over the cable in accordance with the design manual.
Cable locator
A device that can be used to detect the presence of buried apparatus either by
sensing fields or signal injection.
CDD/EDD
Controlled Descent Device / Emergency Descent Device. A device or system that
enables a person to descend from a height at a predetermined speed
ChemAlert
A database providing chemical and product information and Material Safety Data
Sheet (MSDS).
Circuit
Circuit is a configuration of electrically connected components or devices that has a
closed loop giving a return path for the current.
Clean down
The removal of all soil and vegetation from a vehicle and/or footwear by either
washing or brushing down. Particular attention is to be made to wheel arches,
mudflaps, tyres and vehicle under-body.
Collapsible area
The area surrounding an excavation that may be subject to collapse due to
excavation work. A safety provision is using the natural angle of the lay of the soil to
the horizontal in which the soil will not collapse (angle of repose up to 30).
Transmission Substation
Work Practice Manual
Section 1 Definitions
Collection tank
A grease trap, oil interceptor, or an impervious vessel, other than an apparatus for
the treatment of sewage, for the collection, storage, transfer or treatment of
controlled waste.
Combined earthing system
A combined earthing system as defined in AS 3000, in which high and low voltage
electrical equipment is connected to a common earthing system.
Combustible material
Any material capable of catching fire and burning.
Commissioning
Activities carried out in order to ensure that new and existing equipment is safely
and accurately connected to the network and, once in service, will operate as
intended. Activities include inspections to verify installation, commissioning tests
and post-energisation tests/checks.
Commissioning Authority
The Commissioning Authority is the group, which conducts pre-commissioning and
final commissioning activities. The Commissioning Authority controls access to
plant and equipment (which cannot be energised by normal switching) during the
commissioning stage.
Commissioning Notice
Issue of this notice signifies that all commissioning tests have been completed and
that a site or items(s) of plant is accepted by the Operating Authority ready for
service. The notice may contain a list of outstanding items.
Competent / competent person
A person having the skills, knowledge and attributes needed to complete a task.
Completion Notice
A Completion Notice is issued to advise that construction work has been
completed. It may be used for a complete site, part of a site, or may only cover
certain items of plant. It may also contain a list of outstanding items.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Concentrated
Oil, chemical, gas or fuel that has collected in one location.
Conductive pole
Concrete poles, steel poles and wooden poles with a down earth conductor.
Conductor
A wire, cable or form of metal designed for carrying electric current (includes
neutral and earth).
Confined space
An enclosed or partially enclosed space that is not intended or designed primarily
for human occupancy, within which there is a risk of one or more of the following:
Connectable
Apparatus capable of being connected to the live system by switching.
Connected
Joined together by a conductor capable of carrying electrical current for its required
function or purpose by physically clamping or bolting conductors together or closing
a circuit breaker, switch or similar device.
Constant leakage monitoring
Monitoring continually or at intervals of leakage (in micro amps) of current across
the insulated section of the boom during high voltage work, 1uA/kV allowable.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Construction authority
The Construction Authority is the group which is responsible for the construction
and installation of the plant and equipment. The Construction Authority controls
access to plant and equipment which cannot be energised by normal switching
during the construction stage.
Construction authority work permit (CAWP)
Construction Authority Work Permit (CAWP) a non-operational permit issued by
a Construction Authority that authorises the work on new or non-operational and
not connected electrical apparatus and associated equipment.
Construction site
A workplace at which construction work (see definition below) is done and includes
any adjoining area where plant or other materials used or to be used in connection
with that work are located or kept and over which the Network Total Workforce has
control for the purpose of doing the construction work.
Construction work
Work in laying any pipe or work in lining pipe that is done at or adjacent to the
place where the pipe is laid or to be laid.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Contact area
The surface area of one object that makes contact with another.
Continuity test
A test to determine whether electrical current flows continuously throughout the
length of a single wire or individual wires in a cable
Contractors
Any person(s) engaged to execute works under a contact.
Control Authority
This is the representative authority responsible for the control of the apparatus.
Typically this includes:
Construction authority
Commissioning authority
Controller
An authorised person who co-ordinates switching, performs switching by remote
control and approves the issue of work permits.
Cover (Insulated)
A barrier of insulating material specifically designed, approved and tested for use
as a line cover or as a cover for equipment or apparatus.
Customer standing agreement (CSA)
Is a document which represents a standing agreement between the high voltage
customer and Western Power. The purpose of a CSA is to ensure that any
customer switching of specified circuits is performed with the network operators
prior permission and approval.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Danger
Is the presence of risk to health and/or risk of bodily injury.
Danger Zone (as defined by the ESSP/ENA)
LINES Distribution and Transmission.
The danger zone is an area surrounding live electrical equipment (such as power
lines), that ordinary persons, equipment and materials must not enter. The size of
the zone varies depending on the voltage.
Danger zone (AS 2067)
SUBSTATIONS
Area limited by the non-flash over distance (N) around live parts that are without
complete protection against direct contact.
Note: Infringing the danger zone is considered the same as touching live parts.
Dangerous goods in bulk
Dangerous goods of Class 2 (gases) in a container with a capacity greater than 500
litres or dangerous goods of another class in a container with a capacity greater
than 450 litres; and a container with a net mass of more than 400 kilograms.
Also See Packaged Dangerous Goods.
De-energised
The electrical supply has been de-energized but not necessarily isolated, tested
and earthed.
DFIS
Distribution Facilities Information System. A geographical information system (GIS)
that allows users to view the electrical distribution network in relation to physical
geographical location in Western Australia. Users can view and analyse network
assets using spatial information.
Discharged (Electrically)
Conductors which have been connected to earth so that any stored electrical
energy has been removed.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Discharged (Mechanical)
Means mechanical, hydraulic, pneumatic or fuel energy apparatus which has had
all stored energy removed.
Discharge
The release or dissipation of stored energy.
DNAR
Distribution Network Access Request. The formal request to Network Operation
Control Centre to access the HV distribution network.
Do Not Operate Danger Tag
An approved tag that reads DO NOT OPERATE DANGER which is affixed to
isolation and program earthing points established for the purpose of issuing a Work
Permit to personnel.
Drop zone
The area below the immediate work where objects could fall or be directed into if
they strike other structures or objects after the fall.
Earth
The conductive mass of the earth, the electric potential of which, at any point, is
conventionally taken as zero.
Earthed
Electrically connected to earth in an approved manner by approved earthing
conductors or switches.
ECL
Electrical Contractors Licence.
EDD / CDD
Emergency Descent Device / Controlled Descent Device. A device or system that
enables a person to descend from a height at a predetermined speed.
Electrical-Access-Permit (EAP)
Western Powers standard form that authorises access to, and work on, electrical
apparatus which has been made safe by isolating and earthing.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Electrical apparatus
Any electrical equipment or machinery, in which conductors are used, or supported,
or of which they form a part.
Emergency
An event, actual or imminent, which endangers or threatens to endanger life,
property or the environment, and requires co-ordination of a number of significant
emergency management activities.
EMISWeb
A database for recording and tracking Western Powers environmental activities
and legal compliance.
ENMAC
Electricity Networks Management and Control (for distribution systems). An
advanced DMS/TCS/SCADA product that completely computerises Electricity
Distribution Control Room operations.
Equipotential mat
A conducting device at ground level, connected electrically to equipment, to avoid
differences of step and touch potential through the body of a person.
ESA
Environmentally Sensitive Area.
ESO
Environmental Support Officer.
ESSP Electrical System Safety Procedures
The intention of the ESSP is to provide Western Power with a standard set of
procedures and rules that govern all access to the network issued and owned by
NOCC and SOOC.
EWL
Electrical Workers Licence.
EWP
Elevated work platform.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Excavation
Any action that digs, displaces or penetrates the ground.
Extra Low Voltage
Not exceeding 50V AC or 120V ripple-free DC.
Extreme fire danger
The fire danger rating for the day in a district that exceeds specific values (as
determined by the Bureau of Meteorology) and aspects of the Bush Fires Act 1954
which are in force for the day.
Ferro-resonance
A resonance condition that may occur when an unloaded delta / star distribution
transformer becomes energised or de-energised by single phase high voltage
switching, causing sustained over-voltages.
Fire danger warning
Advice from the Bureau of Meteorology indicating adverse fire weather conditions.
Fire extinguisher (hand held)
The hand-held fire extinguisher is simply a pressure vessel from which is expelled a
material or agent to put out a fire.
Fire fighting unit
A device that comprises a container filled with a minimum of 400 litres of water and
a motor driven pressurised pump (spray unit) capable of discharging water.
Formal handover
A formal handover is either a verbal or written exchange of information between two
or more people who have responsibility for the job.
The formal handover information must be accurate and understood, thereby
ensuring the continuity of safe work processes.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Section 1 Definitions
Reviewer: Dave Christmas
Hazard
A source of potential harm or a situation with the potential to cause loss or damage.
Hazardous workspace
Any space that, during its occupancy is likely at any time to:
Restricted entry or exit requires the use of three limbs to enter or exit. Therefore it
is impossible for a single person to remove an incapacitated person unaided.
Training must be provided by a registered body and meet national requirements for
Confined Space Entry.
High Voltage (HV)
A nominal voltage exceeding 1000 volts AC or 1500 volts DC.
High voltage earth installation
Any high voltage installation where high voltage earth electrodes are to be installed.
This could be at ground-mounted substations wood poles with a down earth or
conductive poles.
Horizontal work safety clearance
The minimum distance from the extremities of the work object, horizontally to the
nearest live part.
Hot work
Any naked flame, any hot air blower or any gas operated handgun.
Independent earth
An effective earthed reference point used for testing purposes.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Independent scaffold
Scaffolds that consist of two or more longitudinal rows of standards connected
longitudinally and transversely. Independent scaffolds typically but not necessarily
are constructed prefabricated components, prefabricated frames, tubes and
couplers or timber components with bolted connections
Information Caution Tag
An approved general purpose information tag affixed to apparatus to provide
information about changed or unusual network operating conditions. A Caution
Tag would be used for conditions that do not require a Do Not Operate, Restricted
Use or Out of Service tag and may not be apparent to the observer if the tag was
not present.
Inspection
To view or examine to a set criteria as part of a job process.
Inspection tag
A tag which is used to indicate that the equipment to which it is attached has
passed inspection. The Inspection Tag should also show the date when the
equipment was inspected and the date when the next inspection is due.
Instructed Person
A person who, whilst operating mobile plant (crane) near energised overhead
electrical apparatus, is adequately advised and supervised by an Authorised
Person to ensure they avoid the dangers presented or created by energised
equipment.
Insulated
Separated from adjoining conducting material by a non-conducting substance,
which provides adequate resistance to the passage of current, or to disruptive
discharges through or over the surface of the substance at the operating voltage
and to mitigate the danger of shock or injurious leakage of current.
Insulated conductor
A conductor covered by a type of insulation that prevents the danger of electric
shock.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Insulated EWP
An approved and tested insulated EWP fitted with an approved and tested
insulating liner to the inside of the basket glove and barrier method. An approved
and tested insulated EWP without a liner stick method.
Insulated tools and equipment
Tools and equipment specifically designed, approved and tested for use on or near
live electrical apparatus.
Insulating barrier
A barrier of rigid or flexible insulating material specifically designed, approved and
tested for use as an insulated cover.
Insulating equipment
Equipment of insulating material specifically designed, approved and tested for use
on high voltage equipment.
Insulating gloves
Gloves especially designed, approved and tested to a rated voltage for working on
or near live electrical apparatus.
Isolated
De-energised by an isolating device that prevents unintentional energisation of the
electrical apparatus.
Isolating Device
A device for rendering plant and apparatus isolated.
Isolation Point
An isolating device that has been isolated and has a DANGER DO NOT OPERATE
tag fitted.
Issuing Officer (IO)
Is an authorised person who is responsible for issuing and cancelling work permits.
Note: this task is generally handled by the switching officer.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Job briefing
A discussion (for example, during toolbox meetings) which must involve all
members of the work party prior to the commencement of any work, and as
required throughout the job.
The key elements include but are not limited to:
Hazards associated with the job and the control measures required (JRA).
Contingency plans.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Live work
All work performed on components of electrical apparatus, not isolated, nor proved
de-energised or short-circuited or earthed.
Load box
An electrical device used to apply a resistive load to the low-voltage side of a
transformer.
Low Voltage (LV)
A voltage less than 1000 volts AC or 1500 volts DC.
Manual recovery system
A system that is capable of being operated by a person located on the ground to
manually retrieve an EWP basket.
Material Safety Data Sheet (MSDS)
A document providing detailed information on a hazardous substance.
Mats
A insulated material specifically designed, approved and tested for use as a mat to
stand on insulating you from earth.
Mechanical protective glove
A glove that by its design affords the wearer protection against cuts, abrasion and
penetrating hazards.
Medical air cylinder
A cylinder containing air of breathing quality. Used to oxygenate the atmosphere
within a power transformer.
MEN
Multiple Earthed Neutral system of earthing, as defined in AS 3000.
Midspan
The centre of a span between two fixed points or poles.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Section 1 Definitions
Reviewer: Dave Christmas
Network
An interconnected system of transmission and distribution conductors and electrical
apparatus. The word network can be used interchangeably with system.
Network operator
The owner, controller operator of an electricity network (NOCC/SOCC).
Network Total Workforce (NTW)
Is the total workforce who work on Western Powers Assets the network and
consists of Western Power employees, contractors, sub-contractors, Alliances and
partners.
Neutral conductor
The conductor of a three-wire or multi-wire system that is maintained at an
intermediate and approximately uniform potential in respect of the active or outer
conductors, or the conductor of a two-wire system that is connected to earth at its
origin.
NMS
Networks Mapping System.
No Work Zone
An area around a suspected object of Aboriginal origin in which no construction
activities are to be conducted.
NOCC
Network Operations Control Centre. The NOCC is responsible for control of the
Distribution Network.
Noxious weed
A non-native species, which is declared to be harmful and if found, must be
controlled or eradicated by the property owner.
Object of Aboriginal origin
An object, including Aboriginal remains, used, made or adapted for a purpose
consistent with Aboriginal traditional cultural life.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
One Call
(Dial Before you Dig phone number 1100) The service that issues information about
the likely presence of buried apparatus installed by various service utilities.
http://www.1100.com.au
On-site person in charge
A person who is responsible for the work being carried out by a work team.
Operational work
All construction, maintenance, trade based and switching activities undertaken in a
field environment.
Operating Agreement (OA)
The agreement between two parties used to confirm that the state of apparatus will
remain constant for the duration of the agreement.
Operating Authority
The division responsible for the operation and control of the network.
Ordinary Person
Is a person without sufficient training or experience to enable them to avoid the
dangers that electrical apparatus may create.
Organochlorine pesticide
A wide range of organic chemicals, which contain chlorine and sometimes several
other elements.
Other cable systems
Telecommunications cables, pay television cable, control cables, aerial earthed
cables, electrolysis drainage cables.
Out of Service Warning Tag
An approved tag that reads OUT OF SERVICE warning which is affixed to
apparatus and advises of the physical condition of apparatus or network controlled
by the apparatus.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Group III: least danger among regulated goods, and least protective
packaging within the transportation requirement
PCB
Polychlorinated Biphenyl a hazardous substance found in capacitors and
transformers manufactured before 1978.
PCB coffin/drum
A container acceptable for PCB contaminated chokes and capacitors is a steel
drum of gauge 18 or heavier with a gasket made of PCB resistant material.
Person in Charge
The person responsible for the work being carried out by a work party.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Operational impact.
Primary plant
Primary plant is all equipment which can be connected to HV levels, e.g. circuit
breakers, isolators, and current transformers. Primary plant also includes any
equipment directly associated with the major plant, e.g. Buchholz relays on
transformers, SF6 gas pressure switches on circuit breakers, etc.
Process owner
The Process Owner is the person who has been assigned with the authority and
responsibility for managing the whole process from end-to-end. This authority may
extend across more than one division and/or functions, in order to deliver agreed
business results.
Program Earth
Earthing equipment of approved type applied as part of an electrical switching
program/schedule.
Prohibited burning time
The times of the year during which it is declared by the Minister under Part III,
Division 2, Section 17 of the Bush Fires Act 1954, to be unlawful to set fire to the
bush within a zone of the State and, in relation to any land in that zone.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Pyrolysis
The chemical decomposition of a substance by the action of heat.
Rated voltage
The manufacturers recommended maximum voltage to be applied to the specified
equipment.
Recipient
A person authorised by Western Power to sign on and sign off work permits under
control of the Recipient In Charge.
Recipient In Charge (RIC)
Is the authorised person who has the responsibility of accepting and relinquishing
EAPS and VAs and managing the work group activities to ensure compliance with
the conditions of the EAP or VA and the requirements of the ESSP.
Remote control
A module that is used to operate a base unit.
Remote end
The opposite end of the cable from where work is being carried out.
Restricted Use Danger Tag
An approved tag that reads RESTRICTED USE DANGER which is affixed to
apparatus and advises of the person who controls the operation and state of the
apparatus.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
distance.
Safe working load
The maximum load (in kilograms or kilonewtons) to be applied to the specified
equipment, apparatus or hardware.
Sag
The vertical distance between the final conductor position midspan and the
conductor fixing points.
Sanction To Test (STT)
Western Powers standard form which authorises testing of electrical apparatus.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
SCADA
Supervisory Control and Data Acquisition.
Scaffold
A temporary structure, specifically erected to support access platforms or working
platforms.
Secondary equipment
All equipment that is not directly connected to a HV system. Typically, anything that
is installed on a protection panel. This includes (but is not limited to) protection
relays, control relays, contactors, indication equipment, SCADA equipment, panel
wiring, marshalling boxes and control kiosks. The demarcation point on CTs and
VTs is the magnetic interface point. The secondary cores within CTs and VTs are
part of the secondary system.
Secondary isolation schedule (SIS)
The Secondary Isolation Schedule is used to:
Secondary systems
Secondary systems include (but are not limited to) station LV supply, batteries and
battery chargers, protection circuits, pilot cables, control and alarm circuits, SCADA
and communication equipment.
Secondary work activities
All
construction
type
work
for
the
purposes
of
secondary
equipment
Section 1 Definitions
Reviewer: Dave Christmas
Serviceable apparatus
Parts of the network and consumer owned apparatus to which access is allowed by
the Network Operator and Service Providers for the purposes of maintaining
supply.
Short Circuited Low Voltage
Earthing of LV circuits is performed by bonding all phase and neutral conductors
using approved equipment and procedures. This is commonly referred to as shortcircuiting.
Shall and Should
Throughout this manual the word shall is to be interpreted as the minimum
requirement and should is to be interpreted as advisory or discretionary.
SOCC
System Operations Control Centre. The SOCC is responsible for control of the
Transmission Network.
Spiking
The process of proving a cable has no hazardous voltage present, by creating a
short circuit between the core(s) and neutral/earth screen, using a method that
poses no risk to persons during the spiking of the cable.
Stabiliser
An approved, hydraulically deployed stabilising structure fixed to a crane borer subframe.
Substation
Any yard, terminal, switchyard, zone substation or facility that transforms or
switches high voltage.
Switching
The operation of circuit breakers, isolators, disconnectors, fuses or other methods
of making or breaking an electrical circuit and/or the application and removal of
program earths.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Switching Authority
An authority that has been issued an approval to give approval to perform switching
operations.
Switching Device
Any item on the network capable of connecting and disconnecting apparatus.
Switching Operator
A person authorised by the operating authority to carry out switching operations
within the limits of their authorisation.
Switching Program/Schedule
A switching program/schedule is a list of switching operations that are placed in a
logical sequence to ensure operation of electrical apparatus is carried out in a
controlled manner.
System
Refer network.
Test
The measurement of electrical apparatus, with an approved device, to establish the
present condition.
Test voltage
The voltage which shall be applied to the specified equipment for the purpose of
periodic electrical testing.
Tested
Apparatus which has been tested in accordance with the relevant standard.
Tester in Charge (TIC)
A person authorised to receive and relinquish a Sanction to Test (STT) within the
limits of their authorisation.
TNO
Technical Network Officer.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Under Direction
The authorised operator with the D restriction may carry out switching on their
own. However, each item of the program requires direction by telephone or radio
from the authorised switching operator.
Vicinity Authority (VA)
Western Powers standard form that authorises work in close proximity to live
electrical apparatus or apparatus which may become live.
Vertical work safety clearance
The minimum distance from the extremities of the work object, vertically to the
nearest live part.
VIR
Vulcanised Insulated Rubber
Western Power Authorised Representative
Is Authorised to act on behalf of Western Power within their scope of authorisation.
Work area
The area within normal body reach of the working position.
Working earth
Additional to program earths installed by a working crew to ensure a safe work site.
Work place
A place, whether or not in an aircraft, ship,
vehicle, building, or other structure, where employees or
self-employed persons work or are likely to be in the course of their work.
Work site
Colloquial term used by Western Power that refers to a Construction Site.
Refer to Construction Site.
Work team
One or more authorised persons who have been authorised to carry out work on
Western Power equipment/network.
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
Transmission Substation
Work Practice Manual
Section 1 Definitions
Reviewer: Dave Christmas
2.1
Purpose
This instruction applies to any worksite (building or in field) where the job risk
assessment process has identified the need for an emergency procedure.
In accordance with this instruction, it is the duty of the onsite person in charge to be
responsible for developing, implementing and communicating a workplace
emergency procedure.
Instructions
Where the job risk assessment process has identified the need for a
provisional emergency procedure, document the process in the job risk
assessment form and confirm that all team members understand their role and
responsibility.
Obtain the direct telephone numbers of local doctors, ambulance services, fire
brigades and police. When working in country areas, it is essential to know the
direct numbers for emergency services (Refer to Appendix for more
information).
Check the availability of first aid equipment relevant to the potential injury risk
and confirm that a team member is trained in first aid.
In the event of an emergency, stop the work and decide on the appropriate
action. If practicable, immediately document any additional actions in the job
risk assessment form.
Take into
Inform the Formal Leader and comply with the Incident Notification process.
Transmission Substation
Work Practice Manual
9427 0626
SOCC
9427 4287
General emergency
000
SES
Western Power
13 13 51
Police
13 14 44
Ambulance
13 12 33
For more information about contact details for SOCC, NOCC and the shire refer to
the Appendix.
Transmission Substation
Work Practice Manual
2.2
Purpose
This instruction outlines the minimum requirements for the earthing of, vehicles and
plant operating near high voltage electrical apparatus and the earthing of high
voltage conductors within Transmission Substations.
Scope
This instruction covers all works conducted on electrical apparatus where access is
required via a permit within Transmission Substations.
Lightning
Portable earths are not designed to protect persons from the effects of lightning.
Refer Section 2.3 (Electrical storms) for further information.
Instructions
Before applying portable earths, confirm the apparatus has been de-energised
by using an approved proximity sensing device (e.g. Modiewark) set at the
voltage of the apparatus to be tested.
Apply portable earths immediately after a test has proven the high voltage
electrical apparatus is de-energised.
When applying portable earthing equipment, the earth connection must be first
on and last off.
Transmission Substation
Work Practice Manual
Firmly clamp the portable earth lead to the earth connection point.
They are not hung up, crossed over or wound on the ground.
Apply and remove portable earths using the approved stick, with leads kept
clear of person(s).
When work is continuing for a number of days, prior to commencing work each
day, the RIC or TIC must inspect the earthing equipment to make sure it is still
correctly installed.
Program earths
Permission has been granted by the IO who has fitted a Restricted Use
Tag on the earths that can be removed.
All persons working under the permit are notified and cease work.
Transmission Substation
Work Practice Manual
Program earths must be noted on the Electrical Access Permit and Sanction to
Test.
Working earths
Working earths must be installed as close as possible and visible from the
worksite.
Use a common earth bond where multiple vehicles are at the worksite.
Attach the earthing lead of the Equipotential Mat (either bonded or clamped)
to the approved bonding point or a clean metal surface on the vehicle.
Do not connect the earth lead to a structure fitted with an earth to neutral bond.
When in a substation, a vehicle / plant that may be in motion or can alter its
height e.g. elevating work platform, bobcat, concrete pump and tip trucks, must
be earthed as follows:
Attach a drag chain to the chassis earth connection. The chain must have
at least 150mm of 10mm bright or galvanised chain touching the ground.
Static plant or plant moved for positioning must be attached via approved
earthing lead(s) to the earth points in the substation. Care must be
exercised when positioning the plant so as not to damage or release the
earth connection.
Transmission Substation
Work Practice Manual
All portable earthing equipment must clearly display the due date of the next
inspection.
Remove from service and Tag any damaged or defective portable earthing
equipment, until it can be repaired or discarded.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
2.3
Electrical storms
Purpose
This instruction describes the safe systems of work when working near electrical
storm activity when within transmission substations.
Instructions
During the job risk assessment process, assess the electrical storm activity
when the Bureau of Meteorology, NOCC or SOCC has issued a warning.
Determine the electrical storm activity and decide whether to continue working.
If practicable or necessary, notify the Formal Leader of any decision to stop
work.
Seek shelter in a building or enclosed vehicle until the lightning storm passes.
Relocate to safe location as a lightning strike to power lines will often induce
very high voltages and in some events cause the pole to explode sending
debris over several metres.
Avoid standing near a pole during an electrical storm, as a direct strike will
result a voltage dispersing into the ground creating a step potential.
If work continues, monitor the electrical storm activity as changes may occur in
a short period.
Pilot systems are usually interconnected. Do not work on any Pilot systems if
electrical storm or severe winds are identified as being present within 30 km of
the metro area or to the Pilot system nearest to the weather condition
identified.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
2.4
Purpose
The purpose of this instruction is to describe the safe system of work associated
with the entry and activities performed by any person working on behalf of Western
Power who enters a hazardous workspace.
The instruction only provides the key points relevant to hazardous workspaces
identified on Western Power worksites and does not attempt to replicate the OSH
Regulation Division 8 - Work in confined spaces, or any Confined Space training
provisions.
Instructions
Basic requirements
The person in control of the worksite must carry out a suitable and sufficient Job
Risk Assessment for all work activities to be undertaken in the hazardous
workspace.
Task competency.
Transmission Substation
Work Practice Manual
Confirm that all team members are conversant with all risk controls and if required
designate competent safety observers and a rescue team.
Transmission Substation
Work Practice Manual
2.5
Purpose
The purpose of this instruction is to provide an understanding and knowledge of the
requirements when performing work safely in a confined space.
This instruction only provides the key points relevant to confined spaces identified
on Western Power worksites and does not attempt to replicate or supersede the
following references:
Risk control
Fix a warning sign at the entrance and or exits of all confined spaces.
Temporary confined spaces must display a confined space sign for the
duration of the work.
Only remove a permanently fixed confined space sign if the workplace due to a
re-design is no longer a confined space.
Transmission Substation
Work Practice Manual
Training
All persons with tasks associated with a confined space, shall be trained and
assessed as competent to conduct those tasks. Training must be current and
recorded in Ellipse Training module or in the Contractor Authorisation records.
Depending on the confined space work, activity risks, the key confined space
training competencies may be either General Awareness training or Specific
Training.
Confirm at least one (1) member of the work team is trained in the following
first aid competencies:
HLTCPR201APerform CPR
Instruction
The Work Parcel or any pre-job instruction must include all foreseeable
confined space risks associated with the work activity.
Consider methods of completing the work without entering the confined space.
Before commencing the confined space work activity, wear personal protective
equipment and clothing appropriate to the risk.
Transmission Substation
Work Practice Manual
The Recipient in Charge of the Confined Space Entry Permit is responsible for
accepting and relinquishing the permit and managing the work activities to
ensure compliance with approved procedures and processes.
The Recipient in Charge of the permit must carry out a Job Risk Assessment
for all work activities to be undertaken in the confined space.
Explosion or fire.
Electrical arcing.
Unsafe temperatures.
Confirm that all team members are conversant with all risk controls.
Postpone the work activity if all the confined space risk controls cannot be
implemented.
Transmission Substation
Work Practice Manual
The Recipient in Charge of the permit is responsible to ensure the Job Risk
Assessment process is followed and that all permits are completed.
SF6 gas is five times heavier than air. Escaped SF6 gas will displace oxygen at
ground level, especially in confined spaces. This could present a danger of
asphyxiation due to oxygen deficiency if employees are working in deep tanks,
enclosed vessels, and in ducts, trenches or pits where SF6 gas is present.
Permits
Transmission Substation
Work Practice Manual
2.6
Tags
Purpose
This instruction outlines the minimum requirements of Western Powers electrical tagging
system by explaining the application and use of the four (4) approved operational tags on
Western Power network apparatus, including secondary plant and communication systems.
Note 1
The TIC can temporarily remove the Restricted Use tag during the process of
changing the state of the apparatus and then re-apply the Restricted Use tag.
Note 2
The person responsible for maintenance is likely to be general network field staff.
However, in this context they are tasked with repairing / maintaining.
They will remove the Out of Service tag as the initial part of this task.
Note 3
Any authorised person can apply and remove the Information tag which would only
be removed when the normal operating condition has been restored.
ATTENTION
Transmission Substation
Work Practice Manual
Operational
The following tags are the approved tags for use on Western Powers electricity system.
The Do Not Operate tag may only be used when work is being carried out on
the system.
The Do Not Operate tag must be applied to apparatus that has been isolated
and earthed in according to a switching program and an EAP issued.
Authorised switching operators or issuing officers shall fit and remove tags in
accordance with the approved switching program unless during a fault
condition (where there is no program).
Transmission Substation
Work Practice Manual
A Do Not Operate tag must be attached to high visibility warning signs placed
on interconnectable normally open points that could be closed. A sample of the
high visibility warning sign is shown below.
High Visibility
Warning Sign
Stock code:
CZ5012
Once all work has been completed, the Do Not Operate tag must be removed.
If any defect is still present on the apparatus, and work has ceased on the
apparatus or the apparatus is not to be returned to operation, the Do Not
Operate tag must be removed and an Out of Service tag applied.
Transmission Substation
Work Practice Manual
The Out of Service tag must be used to indicate a General and Unusual
Operating Instruction (GUOI).
When a Out of Service tag is used and fitted for switching on primary
apparatus NOCC/SOCC must be advised.
The Out of Service tag must be applied directly to the defective component in a
noticeable position.
Transmission Substation
Work Practice Manual
The Restricted Use tag prohibits all personnel, other than the person
nominated on the tag, from operating the apparatus.
Attached and removed by the Issuing Officer or Switching Officer when issuing
a Sanction to Test.
Transmission Substation
Work Practice Manual
Information Tag
The Information tag is used for conditions that do not require a Do Not
Operate, Out of Service or Restricted Use tag and provides information about
changed or unusual network operating conditions.
Where an Out of Service tag is attached to any equipment, all personnel that
work on the equipment must comply with any instruction or information on the
tag prior to commencing, and during, any tasks associated to the tagged
equipment.
General
Out of Service tag: This tag may be used for non-operational use and does not
have to be recorded with NOCC/SOCC.
Information tag: This tag may be used for non for non-operational use.
Fitting tags
For the tags to be effective, all the relevant information must be filled out on
them correctly and clearly, referenced and placed in a visible location on the
apparatus and remain in place for the duration of the condition indicated on the
tag.
Transmission Substation
Work Practice Manual
Tags must be attached so that they can be easily seen and remain in place for
the duration of the condition indicated on the tag.
The tags may be attached using the hasp of a padlock through the hole in the
tag, or attached to the equipment with string, or cable ties.
Removal of tags
Do Not Operate tags can be removed as per the switching program and
ENMAC schedule by the person who affixed the tag.
If a person other than the person who applied the tag wishes to remove it, they
must first contact:
The team leader of the group responsible for fitting the tag; and
to ensure that removal of the tag will not put any person at risk, will not affect
any other work being performed, and that all persons concerned know the tag
has been removed.
If a tag is encountered in the work environment and it cannot be determined
why it has been affixed, the following must occur before work proceeds:
Identify and contact the person who placed the tag or, if unavailable,
his/her team leader.
Contact relevant control (i.e. NOCC, SOCC, SCADA) to check if any work
is being carried out on the system and if a permit is in existence for the
apparatus.
Transmission Substation
Work Practice Manual
Check the condition of the equipment and any associated section of the
network.
Transmission Substation
Work Practice Manual
2.7
Purpose
This instruction describes the safety precautions to take when a vehicles air-filled
tyres are subjected to extreme heat such as a high voltage flashover.
Overview
This results in an accumulation of flammable gas within the tyre that exceeds a
critical level. That is, parts of the tyre remain hot enough to ignite this explosive
gas mixture.
A lightning strike.
Overheated brakes.
Fire.
Exploding tyres can blast part of wheel rims and tyre fragments over long
distances.
Instruction
Remove all tyres when welding or carrying out any oxy-acetylene works on
wheel rims.
Conduct a risk assessment immediately after vehicle tyres are exposed to the
effects of extreme heat and if practicable and safe, drive the vehicle into a
nearby clear area.
Transmission Substation
Work Practice Manual
Remain clear of any fallen power line until it has been proved de-energised
and earthed.
If in radio or telephone contact, arrange to isolate the supply and contact Fire
and Emergency Services Authority of Western Australia (FESA).
The driver of a vehicle in contact with a power line should remain in the vehicle
until the electrical supply has been isolated. If the driver is alone, he should
attempt to seek assistance before leaving the vehicle. If at risk due to a
potential explosion or fire, leave the vehicle by jumping clear with both feet
together.
Transmission Substation
Work Practice Manual
2.8
Purpose
This instruction outlines the minimum requirements for the installation and erection
of temporary safety barriers or warning signs where a worksite requires protection
or separation from anything that may be impacted by the worksite within
Transmission Substations.
Scope
This instruction outlines the minimum requirements for the installation and erection
of temporary safety barriers or warning signs where a worksite requires protection
or separation from anything that may be impacted by the worksite for the Network
Total Workforce (NTW) within Transmission Substations.
Instructions
Conduct the JRA process and assess the need for temporary safety barriers or
warning signs.
Where practical, install safe access ways through the immediate worksite,
allowing the NTW access. Alternatively, escort NTW through the immediate
worksite.
Position temporary safety barriers or warning signs so that they will not
become a hazard or a workplace obstruction.
Transmission Substation
Work Practice Manual
High-visibility mesh.
Temporary fencing.
If star pickets are used to support temporary safety barriers or warning signs,
drive them into the ground firmly to a maximum depth of 600 mm.
Note:
Take care to avoid driving the picket into underground services. Refer to Field
Instruction 5.23 Excavations. Cover the top of the star picket to prevent injury.
Transmission Substation
Work Practice Manual
High-visibility flag rope is also used to safely guide NTW around, or through, a
hazardous worksite.
Position the high-visibility flag rope barrier between 900 mm and 1200 mm
above the ground.
Plastic barriers
Temporary fencing
Install temporary fencing at a distance that will not create an additional hazard
to the general public.
Transmission Substation
Work Practice Manual
Make sure temporary fencing is far enough away from the safety barrier, (see
Tables 1 and 2 above), to provide protection against a vehicle collision.
Do Not Enter.
Put warning and advisory signs where they are clearly visible and do not
obstruct pedestrians and vehicular traffic.
Ensure all warning and advisory signs are legible and in good condition.
References
Transmission Substation
Work Practice Manual
2.9
Purpose
This instruction outlines the steps to be followed when working on equipment
containing, or is suspected of containing, asbestos materials.
Exclusions
This instruction does not cover thermal and acoustic insulation or automotive
equipment containing, or suspected of containing, asbestos materials.
Product overview
Asbestos can be found in:
Cable ducts.
Cable lagging
Safety precautions
Asbestos
Before starting any work on electrical equipment containing or suspected of
containing asbestos material, carry out an on-site hazard risk assessment.
Apply control measures (outlined below), to minimise the release of, and possible
exposure to, asbestos fibres.
When removing electrical equipment that does not appear to be damaged or
deteriorated (no cracked or broken panels or loose fibres), wear:
PVC disposable gloves (QH-064 or QH-0068) for extra wrist length protection.
Transmission Substation
Work Practice Manual
The material name (in most cases) will be stencilled on the back of the panel.
These panels should not be confused with black Formica panels that are
between 6mm and 10 mm thick.
The asbestos material contained in the panels remains passive until the meter
panels are cut, drilled or damaged. Therefore, all panels installed before 1988
must not be modified by cutting or drilling.
Smear grease or petroleum jelly on the base of the device, and then remove it.
Immediately after removing the device, place grease or petroleum jelly over the
fixing holes.
Smear a small amount of grease or petroleum jelly around the panel screws or
fixings, and then remove the panel.
Wipe away all dust and panel debris within the enclosure with a damp rag.
Transmission Substation
Work Practice Manual
Place the panel and rag into the small plastic bag (OC-3106), seal the bag then
place in the large plastic bag (OC-3109) marked Caution Asbestos.
When work is complete, place disposable coveralls (if used), respirator and
gloves into the large plastic bag (OC-3109) marked Caution Asbestos.
Some older type porcelain fuse bases or holders attached to the panels are
likely to have asbestos braiding inside to prevent the panel from over-heating.
Before you remove porcelain fuse bases and holders, disconnect from all
sources of supply (including the neutral) and prove de-energised.
Remove porcelain fuse bases and holders with asbestos braiding by leaving
the fuses in the porcelain fuse bases and removing the panel as per the panel
removal instructions.
Use a hand drill to drill holes in vinyl floor tiles. Power tools and battery
operated drills are not permitted.
Large holes:
Cur the tile by hand outside the marked area (do not use a rotating or
reciprocating blade).
If required, heat the tile piece to be removed to soften the tile and glue.
Remove the cut-out section in the largest pieces possible and place in the
plastic bag.
Seal the edges of the cut tile with silicon or shaving cream.
Transmission Substation
Work Practice Manual
Wipe up any remaining moisture with a damp rag and place in the plastic bag
with the tile pieces.
Cut the required hole in the timber portion without cutting into the tile.
Place the debris and / or remains and the used PPE and rags into a small
plastic bag (OC-3106), seal the bag and then place it into the large plastic bag
(OC-3109) marked Caution Asbestos.
Note:
Power tools are not permitted when working on asbestos products.
Cable ducts
Cement fibre cable ducts were made of chrysotile white asbestos fibre cement and
can be identified by either of the following:
The asbestos materials contained in the cement fibre cable ducts are passive until
the duct has either deteriorated through age or has been damage.
When removing and replacing ducts take the following steps:
Disconnect all cables within the duct from all sources of supply and prove deenergised.
Dampen down the outside of the ducting with a low pressure water spray.
Apply a cable slipping compound to the cable duct (and cable) at the opposite
end to the cable exit point, minimising the release and possible exposure to
any released material.
Withdraw the cables and remove ducting, taking care not to cause any
unnecessary damage that may release the asbestos fibres.
Place the cable ducting on plastic sheeting (OC-7891), double wrap, seal, and
mark Caution Asbestos.
When the work is complete, place disposable coveralls (if used), respirator,
and gloves into the large plastic bag (OC-3109) marked Caution Asbestos.
Transmission Substation
Work Practice Manual
Storage
Place the bags marked Caution Asbestos into the designated receptacles
at the local depot.
Store large commercial panels, pillars and cable ducts in the designated
storage area.
Disposal
When the receptacle is three-quarters full, inform Depot Governance, who will
arrange for the disposal and replacement of the bin.
Ensure all bags and double-wrapped asbestos equipment and products are
sealed and undamaged before placing them in the designated storage areas.
References
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
2.10
Purpose
This instruction describes the requirements for using electronic communication
equipment in vehicles and workplaces.
Taking the eyes off the road to operate or take a momentary look at a device
screen such as a Go-Book or GPS while driving is a distraction and considered
an at-risk behaviour.
Note:
Western Power will not pay or refund any road traffic penalty imposed on an
employee.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
2.11
Height safety
Purpose
This instruction describes the safe systems required when performing work
above two (2) metres.
This instruction only provides the key safety requirements relevant to working
at heights and does not attempt to replicate any detailed work practices
contained in Codes of Practice, specific workplace instructions or training
documents.
Instructions
When working above two (2) metres, wear approved fall protection appropriate
for the task.
Only work from a stable platform, which has a safe access and egress.
Apply risk controls that prevent accidents, resulting from slippery work platform
surfaces.
Other than a pole structure, a fall arrest system is required when working at
heights above two (2) metres.
Use a fall arrest system, designed to restrain a persons fall from one level to
another and also minimise the risk of injuries or harm during the fall.
Before attaching a fall arrest system, check the anchor point integrity. The
anchor points must be capable of withstanding a force of at least 1.5 Ton in a
direction that simulates the loading likely to be placed on it in the event of a fall.
Transmission Substation
Work Practice Manual
Remove fall arrest equipment from service after it has arrested a fall, pending
inspection and operational certification by a competent person.
A fixed short length lanyard, which will prevent egress from the bucket.
Towers
When ascending or descending a tower use a double lanyard system.
Scaffolding
Above two (2) metres, install edge protection and a guardrail system.
Transformers (above 2 metres high - excluding pole top transformers)
Before stepping onto a transformer, attach fall arrest equipment to the anchor
point.
Remain attached to the fall arrest equipment during the performance of the
work.
Depending on the risk of a fall, consider the use of a restraint line, maypoles,
and redirect anchors.
Transmission Substation
Work Practice Manual
Training
Any person who performs work at height on behalf of Western Power, must be
trained and possess an approved competency.
A person who issues fall protection equipment must provide the user with
instruction in relation to the correct fitting, use, selection, testing, maintenance,
storage of the equipment and explain its limitations.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
2.12
High voltage insulated sticks and equipment testing and use for
Substations
Purpose
This instruction outlines the requirements for the testing and use of high voltage
insulated sticks in substations and associated equipment.
Instructions
General
Prior to the commencement of work, high voltage sticks and associated equipment
must be inspected to ensure they are:
Designed, tested and certified for work on or near live overhead lines.
Testing
Prior to use ensure all high voltage insulated sticks or associated equipment
that has not previously been used is tested.
Test all high voltage insulated sticks or associated equipment at least every six
(6) months.
Transmission Substation
Work Practice Manual
Western Powers Testing Service section or any other similar high voltage
testing facility must test all insulated sticks and associated equipment to the
relevant standard.
Note:
Visual inspections of the insulated stick should be carried out prior to use. If any
physical damage to the surface is reported it should undergo a stick leakage test.
All high voltage insulated sticks and associated equipment must display an
expiry test date six months forward from the date tested.
Put the expiry date in the same position on the high voltage insulated sticks or
associated equipment each time it is tested.
Withdraw from service if the test date has expired and do not re-use until they
have been re-tested and correctly dated.
References
Transmission Substation
Work Practice Manual
2.13
Purpose
This instruction describes the requirements for inspecting and maintaining fallprevention equipment.
Fall prevention equipment is required to avert a fall from height or to mitigate any risk
identified during the job risk assessment process.
As with any personal protective equipment, fall prevention equipment must not be
used in isolation of other risk controls.
Instructions
Refer to Height Safety (in this section) for fall protection instructions when
working above two (2) metres.
Before using fall-arrest equipment, the Formal Leader must ensure that the
wearer attends a use and maintenance training/education session.
Carry out inspection of rescue kits refer Appendix 2 Inspection Checklist for
pole top rescue kits.
Check the fall-prevention equipment expiry date. If the label is illegible or the
date cannot be determined, remove this equipment from service.
Remove and destroy fall-prevention equipment ten (10) years from the date of
manufacture.
Transmission Substation
Work Practice Manual
Using pure soap or soap flakes in lukewarm water, sponge down or hand wash
dirty or gritty webbing.
Thoroughly rinse washed or rain soaked fall-prevention equipment and hang out
to dry at room temperature. Do not expose to direct heat.
DANGER
If a fall has occurred or if a fall indicator activates, withdraw the equipment from
service immediately.
Transmission Substation
Work Practice Manual
2.14
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
2.15
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
2.16
Purpose
When performing any work where there is a risk of starting a fire it is mandatory to
comply with the requirements described in this instruction and record in the job risk
management the risk controls required to eliminate or reduce any risk of damage or
harm.
Responsibilities of the on site person in charge
Ensuring the work can be undertaken without the threat of a fire starting.
General
The following general instructions apply to any situation where fire is a threat.
Any person who starts and then extinguishes a fire must advise the local
shire council for the district (see appendix 4) in which the work is being
undertaken.
The local council will monitor the area in case a flare-up of the fire.
Transmission Substation
Work Practice Manual
Risk assessment
If the job risk management process identifies that the work includes tasks which
have the potential to cause a fire, the following are required:
Switching
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
FESA can issue a total fire ban for any conditions from Low moderate right up
to Catastrophic.
The Western Power FESA exemption only applies to work which cannot be
reasonably postponed to a time with safer weather conditions.
Situations will occur where the nature of the work and its location will not be a
risk of starting a fire and does not conflict with the Western Power FESA
exemption.
The work group formal leader must approve the work before
proceeding.
A copy of the FESA exemption form must be in all vehicles that are required to
work under the conditions of the exemption.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
3.1
Purpose
This instruction outlines the use and maintenance of approved personal protective
clothing.
Scope
This instruction applies to any persons, including visitors, who enter Western
Power construction depot/sites or perform work on behalf of Western Power.
Requirements
General
The minimum clothing requirement for visitors to operational depots/sites are:
Covered footwear.
Note:
Where a person remains outside a three (3) metre zone from exposed electrical
apparatus, the minimum clothing required is Level 0.
Transmission Substation
Work Practice Manual
Safety footwear.
If a person enters inside three (3) metres from any exposed electrical apparatus,
they must comply with the Category 1 personal protective clothing requirements:
Level 1 requirements : Flame retardant cal rating = >7Cal
The following minimum approved personal protective clothing must be worn when
carrying out operational, construction or maintenance activities.
Safety footwear.
Eye protection.
Safety footwear.
Transmission Substation
Work Practice Manual
Safety footwear.
Safety footwear.
Transmission Substation
Work Practice Manual
Safety footwear.
Wet weather and thermal protective garments must be approved before they
can be worn over the protective clothing.
Consider the following when accessing the arc flash hazard area:
Device environment.
Weather.
Face shield and safety
glasses used at LV frame
Transmission Substation
Work Practice Manual
Inspect personal protective clothing before use and replace any item that is
damaged or in a poor condition.
The matrix on the next page must be used when selecting the level of clothing
required to perform switching on different types of equipment. The matrix should
also be used in conjunction with the risk analysis process and the safe work
method statements in determining the level of protective clothing necessary when
working in circumstances such as; on or near live low voltage busbars/conductors,
live low voltage cable jointing, load testing or racking switchgear.
Transmission Substation
Work Practice Manual
Clothing
Combinations
PPE
Level 0:
Level 1:
Level 2:
Level 3:
Level 4:
Level 5:
Hi-vis100%
cotton long
sleeve shirt &
trousers
or
overalls
Hi-vis FR
long sleeve
shirt &
trousers
or
overalls
Level 1
plus
Face shield
with safety
glasses worn
under
Level 2
plus
Overalls
or
FR switching
jacket
Level 2
plus
FR switching
jacket
Safety
footwear,
eye
protection
and head
protection
to risk
needs
Safety
footwear, eye
protection
and head
protection
to risk
needs
Safety
footwear, eye
protection
and head
protection
to risk
needs
Safety
footwear, eye
protection
and head
protection
to risk
needs
Safety
footwear, eye
protection
and head
protection
to risk
needs
Level 1
Plus
FR switching
jacket
plus
FR switching
trousers
plus
FR hood with
Safety
glasses worn
under
Safety
footwear, eye
protection
and head
protection
to risk
needs
14
37
37
FR (Flame
retardant)
Cal rating
HV O/H
equipment
LV O/H
equipment
Uni Pillar air
insulated
Transformer
LV frame
up to
315 KVA air
insulated
Transformer
LV frame
greater than
315 KVA air
insulated
HV RMU SF6
insulated
HV RMU air
insulated
HV RMU oil
insulated
Zone
substation
outdoor
equipment air
insulated
Zone
substation
Indoor CBs
Transmission Substation
Work Practice Manual
Compulsory
Compulsory
Compulsory
Compulsory
Compulsory
Compulsory
Compulsory
Compulsory
Compulsory
Compulsory
3.2
Glove protection
Purpose
This instruction outlines the minimum requirements for the use of gloves when
working on either the high or low voltage network, whether energised or deenergised.
Maintenance and inspections
Before commencing work, check gloves for good condition. For electrical work,
check insulating gloves for any cuts or punctures.
Discard any gloves that are damaged, in poor condition, or have failed the air
pressure test.
Electrically test insulated gloves every six (6) months from date of issue.
Gloves rated 3,300V or less do not need to be electrically tested before initial
use.
Check gloves test expiry date and remove or retest if date has expired.
Insulated gloves must be stored in an approved glove bag and/or a dry
location. Insulated gloves do not have a shelf life.
Transmission Substation
Work Practice Manual
Barriers
Insulated tools
Transmission Substation
Work Practice Manual
3.3
Head protection
Purpose
This instruction outlines the type of approved head protection that must be worn
while carrying out work on the Western Power network.
Head protection is required to reduce the risk of injury such as falling objects, arc
flash burns and effects of exposure to UV radiation.
As with any personal protective equipment, head protection must not be used in
isolation of other risk controls.
Instructions
Based on a specific need identified during a risk assessment, the on site person in
charge has the authority to exceed these instructions.
Safety helmets
Replace the safety helmet after two (2) years service in an operational
environment.
Secure the safety helmet with a chinstrap if there is a probability that it will
dislodge from the head.
Based on a risk assessment, where the on site person in charge considers that
a safety helmet is impracticable an alternative risk control/s must be
implemented.
For maximum sun protection, a new plastic snap brim replaces the fabric sun
visor (Western Power stock code QC0114).
Transmission Substation
Work Practice Manual
Consider such risks as ultra violet radiation and foreseeable head injuries,
which may result from performing maintenance work under machinery or plant.
Transmission Substation
Work Practice Manual
3.4
Purpose
This instruction describes the requirements for use and maintenance of face and
eye protection.
Face and eye protection is required to eliminate the risks associated with flying
particles and extreme heat radiation or any other foreseeable risk.
As with any personal protective equipment, eye and face protection equipment
must not be used in isolation of other risk controls.
Instructions
For arc flash protection, wear eye protection underneath face shields/arc flash
hoods.
Wear approved eye protection, day and night, in the following areas:
All designated eye protection areas.
When working on live electrical apparatus.
When operating switchgear.
All zone and terminal substations and power station switchyards.
Indoors when determined by the JRA that there is a risk of damage to the
eye.
All workplaces where there are mechanical hazards such as flying
are present.
In all workplaces where thermal and radiation hazards such as heat, glare,
Transmission Substation
Work Practice Manual
Inspect eye and face protection before use and replace any damaged or
unserviceable item.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
4
Electrical System Safety
Procedures (ESSP) 2009
Transmission Substation
Work Practice Manual
4
Electrical System Safety
Procedures (ESSP) 2009
5.1
Purpose
The purpose of this instruction is to outline considerations for working in customer
switchyards.
Instructions
Establish who owns the equipment and details of the Operating Authority.
Obtain the correct name and telephone number of the customer contact on site
(both business and after hours).
Obtain a list of any environmental hazards before entry upon the site.
Determine the type of procedures and permits used on site by the customer,
and check they meet Western Powers requirements. If the procedures and
permits are at a standard that is less than WP requirements, then either WP
procedures and permits are utilised, or work on-site shall be refused.
Where applicable, arrange for all Western Power personnel who are to visit site
to attend the customers induction course.
Ensure the customer installation has been approved (after customer lodgement
of a completion certificate) before energising it.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
5.2
Purpose
This instruction outlines the minimum requirements for all escorted and un-escorted
persons who enter Western Power Transmission Substations or Switchyards for
operational and non-operational activities.
Instructions
People who hold this level of access will hold a Substation Entry Authority card
issued by System Management Division.
Meet the minimum PPE requirement for the site they are entering, this is
displayed at the point of entry.
Persons who are required to work on or near Western Powers electrical supply
system shall not do so unless they:
Have been appropriately trained for the work they intend to do;
Note:
Section 4 provides information on the different permits available and their correct
application.
Transmission Substation
Work Practice Manual
Escorted persons
The escorted person must sign the Substation Entry Induction Form
acknowledging their role and responsibilities.
The authorised representative must sign the form to confirm the induction has
been carried out. For auditing purposes, file the completed Substation Entry
Induction Form at the local Western Power depot.
The escorted person may sign onto the Work Permit as part of a work group,
providing the authorised person who is doing the escorting has a NA 3 access
authority. However, it is not possible to sign on as the Recipient In Charge of
Transmission Substation
Work Practice Manual
5.3
Substation clearances
Purpose
The purpose of this instruction is to outline the requirements for Western Power
personnel (Network Total Workforce) who work within substations over 1kV AC
defining the apparatuss nominal voltage and the clearances for that voltage.
Instructions
The clearances to earth between live parts and earthed material apply to
any structure or surface substantially at earth potential, including any fixed
or portable screens which may be provided. Earthed material includes a
poor conductor such as concrete.
Phase to Phase
The distance from live equipment across which a flashover will not occur.
It is slightly more than the Minimum phase to earth clearance. The area
within the non-flashover distance is referred to as the Danger Zone.
The minimum distance from the earthed end of equipment insulators to the
ground or a walkway. It is 2440mm for all voltages (above 1kV).
This
Transmission Substation
Work Practice Manual
The minimum distance measured between live parts and the foot position
of a person standing whether they are on the ground, walkway, or platform
or on top of equipment.
The section safety clearance shall be applied from the foot position
vertically and from the foot position over guard rails or screens by tautstring measurement, to the nearest live parts.
The minimum distance measured horizontally between live parts and the
extremities of the work object.
The minimum distance measured vertically between live parts and the
highest part of the work object.
The distance between two parts measured along a taut string stretched
the shortest way between those parts.
The taut string distance is used to measure the shortest distance away
when measuring from the base of where a person is standing up and over
guard rails and screens to the nearest live point.
Transmission Substation
Work Practice Manual
Area limited by the non-flash over distance (N) around live parts that are
Phase to
Earth
Clearance
mm
Phase to
Phase
Clearance
mm
Up to 3.6
60
70
NonFlashover
Distance
mm
Ground
Safety
Clearance
mm
(N)
(G)
Section
Safety
Clearance
mm
65
Horizontal
Safety
Clearance
mm
Vertical
Safety
Clearance
mm
(S)
(H)
(V)
2505
1965
1405
6.6
90
105
100
2540
2000
1440
11
160
185
175
2615
2075
1515
22
280
325
310
2750
2210
1650
33
380
440
420
2860
2320
1760
66
630
725
695
3135
2595
2035
132
1300
1495
1430
3870
3330
2770
220
1900
2185
2015
4455
3915
3355
330
2200
2530
2330
4770
4230
3670
2440
Safety Clearances
The Section, Vertical and Horizontal work safety clearances are based on the
principal that when a person is inspecting or operating live substation
equipment or working on isolated equipment, they should not be able to reach
into any Danger Zone surrounding live equipment.
It has Been assessed that a tall person holding a small hand tool or material up
to 300mm in length would have a maximum reach of 2440mm vertically or
1900mm horizontally. This is illustrated by Figure 1 page 6.
Applying the principal described above, it follows that the distance to live
equipment must always be at least the dimension of the Danger Zone plus
the vertical or horizontal reach as appropriate.
Transmission Substation
Work Practice Manual
The Section and Horizontal work safety clearances are applied to the
movement of all vehicles and plant.
Section safety clearance is to apply between the highest point on the vehicle
where a person would normally sit or stand and any live conductor.
Transmission Substation
Work Practice Manual
Whether the platform you are working from is scaffolding or an Elevated Work
Platform (EWP) the following work clearances must be maintained.
Section safety clearance is required from the foot position vertically to the
nearest live parts.
Section safety clearance is required from any foot position on the platform over
the guard rail of scaffolding or EWP bucket by taut string measurement to the
nearest live parts.
Horizontal work safety clearance is required from the extremities of the work
object in any horizontal direction to the nearest live part.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
References
Transmission Substation
Work Practice Manual
5.4
Secondary isolations
Purpose
The purpose of this field instruction is to ensure that Transmission Substation
secondary isolations, when performed for the purpose of issuing a Permit or in
conjunction with a primary permit, allow subsequent activities by recipients to be
carried out in a safe manner.
Responsibilities
plant/equipment/sites
under
the
control
of
the
Commissioning Authority.
Instructions
Authorisation for operational sites
Transmission Substation
Work Practice Manual
Commissioning sites
Pilot cables
Secondary Systems Field Protection Services are the operating authority for
pilot cables and associated equipment
Communications Equipment
Transmission Substation
Work Practice Manual
Notification
Secondary Systems Issuing Officers will normally require at least one week
notice from any party requiring access to secondary equipment in an
operational site. The request will normally be by way of an email and Market
Participant which has been approved by System Operations.
Isolations will normally be carried out by an Issuing Officer, however there are
some circumstances where this is not the case, these are:
Transmission Substation
Work Practice Manual
When access is being provided for others, Isolations are complex, the Permit
to be issued is an EAP, the work will last for more than 1 day or where there
are other work parties working in the vicinity, then a Secondary Isolation
Schedule (SIS) is required. This ensures that the risk of making a mistake is
reduced, and, if another person restores the Isolations, they will have a
complete list of what Isolations have been carried out. For this reason a copy
of the SIS must always be left on site with the Permit.
Isolations that are required to ensure personnel safety (i.e. an isolation point is
required to remain isolated or else there would be a risk of electric shock) must
provide a physical/visible break.
applied
(preferably by a lockable fuse insert with the Do Not Operate (Danger) Tag
attached to the lock). If it is not possible to provide a visible break, for example
in the case of a Miniature Circuit Breaker, then isolation will be confirmed by
the use of a test meter and the Miniature Circuit Breaker must be provided with
a locking facility.
As a minimum, the Do Not Operate (Danger) Tag must include the name and
contact details of the person who applied the tag (the applicator), the date of
applying the tag and the reason for applying the tag.
Transmission Substation
Work Practice Manual
The Do Not Operate Danger Tag can only be removed by the applicator or by
another authorised person after following the approved Permit relinquishment
processes. All isolation locations (e.g. each panel, marshalling box, Krone, etc.
must have a Danger Tag or Caution Tag fitted) to identify who, why and when
the Isolations were applied.
Whenever possible the methods used to achieve Isolations should be: Positive
and Visible. The preferred method is by removal of links and/or fuses and by
proving dead using a voltmeter. Where this is not possible a Miniature Circuit
Breaker may be used but it must be wired off and Do Not Operate Danger
Tagged, and the side to be isolated must be proved dead using a voltmeter.
Miniature circuit breakers pose certain risks; often they serve a remote load
circuit and are located with other Miniature Circuit Breakers in an AC
distribution Board. In these circumstances the Miniature Circuit Breaker that is
being utilized as an Isolation point must be locked off or the load wiring be
removed.
Transmission Substation
Work Practice Manual
CT isolations will normally be carried out using test links or test plugs. Care
must be taken not to open-circuit an energised CT or remove its ground
reference connection.
The STT is not to be issued over the telephone, instead it should be issued
personally to the Communications officer responsible for the work. The STT
Permit is to be presented complete with the correct SIP Isolation. The
Communications Officer upon receipt of the STT Permit is then officially the
TIC and therefore has the responsibility to instruct all members of the working
party.
Conflict of responsibilities
In cases where officers are issuing work Permits for their own work party, the
Issuing Officer for an EAP should preferably not also be the Recipient In
Charge, or Tester In Charge for a STT.
Transmission Substation
Work Practice Manual
Existence of Primary EAP and Secondary STT Permits on the same item of
Primary Plant
An SIS is produced for the work and attached to all relevant Permits.
All work parties are agreeable to the Primary and Secondary Isolations to
be applied.
Transmission Substation
Work Practice Manual
Once the Permit has been issued the Issuing Officer must log the Permit with
the appropriate control centre. This is necessary for two reasons:
So that the controllers know that there is someone working on a particular item
of secondary equipment and are aware of any implications to the power
system, such as the risk of unwanted tripping.
Upon completion of the work for which the Permit was issued the Issuing
Officer shall satisfy himself that:
All Recipients have signed off the Permit and are aware that they will no longer
have access to the equipment.
The equipment is in the required condition for the next stage of the work.
All Isolations should then be restored or their condition set up for the next
stage of the work. For a Sanction to Test the final condition of the equipment
should be noted on the Permit. The Issuing Officer should then cancel the
Permit and advise the appropriate control centre that it has been cancelled.
Reference
Transmission Substation
Work Practice Manual
5.5
Portable Ladders
Purpose
This instruction outlines the use and maintenance of ladders within Transmission
Substations.
Instructions
Note:
Never use metal ladders. The only ladders permitted are, approved and nonconductive.
If using as a working platform, a step and trestle ladder must be in the fully
open position.
When positioning the ladder use the 4:1 rule. For example, if the distance
between the ladder base and the supporting structure is one (1) metre the
ladder should be supported approximately four (4) metres from the ground.
Ensure the ladder is not placed so the weight of the ladder and any person
using it are supported by the rungs for example, straddling a scaffold plank.
If the ladder is being used for access or egress, the ladder must extend at least
900mm above the stepping off point of the working platform.
Transmission Substation
Work Practice Manual
Only one person on the ladder at any time and must be within the load rating of
the ladder, unless in the event of a pole top rescue.
Make sure the full body harness and pole strap are in good condition and
attached correctly.
During ascent and decent, face the ladder and maintain three point of contact
with the ladder at all times.
Do not carry tools or equipment whilst climbing up or down a ladder, utilise tool
belts, pouches or rope pulleys carried without compromising the three points of
contact.
Step and trestle ladders must be used in the fully open position.
Use Trestle ladders for light duty work only and the minimum width of the
working platform must not be less than 450 mm. Work performed on a trestle
platform that is over two metres above ground level must have edge protection.
Ladders with metallic reinforcement that may contact the porcelain are not
permitted to be used, unless protected from that contact.
Metallic or rigid pole straps are not permitted unless specifically designed for a
particular insulator.
Transmission Substation
Work Practice Manual
The work on the insulator is not a result of the insulator failing electrically or
mechanically.
The worker is maintaining three points of contact at all time when on the
ladder, or uses an approved harness and pole strap secured around the
insulator to enable both hands to be used.
Maintenance
Inspect all new ladders before use and fit the standard inspection tag to the
reinforcing rod of the bottom rung of the ladder, indicating the next date of
inspection. (See Figure 3, Appendix 1).
Workers name and current date must be written on the inspection tag before
fitting it to the ladder.
At least every six (6) months, carry out a detailed inspection using the ladder
inspection data sheet checklist (see Appendix 2).
If any defects are discovered during the six monthly inspection, tag the ladder
out and return it to the supplier (along with the completed ladder inspection
data sheet) for repair. If the ladder is not to be repaired it is to be destroyed
(rendering it unusable) and removed from the asset register.
Note:
If a ladder falls from a vehicle or structure, inspect it thoroughly before using it
again. If you find or suspect any defects, follow the same procedure as above.
When sending the ladder for repair insert the ladder inspection data sheet into
an adhesive document pouch and attach it to the bottom rung of the ladder.
Transmission Substation
Work Practice Manual
References
Business Process Management of Defective Plant or Equipment NonNetwork Related (DM 404243).
Transmission Substation
Work Practice Manual
5.6
Scaffolding
Purpose
The purpose of this instruction is to outlines the minimum requirements for erecting,
dismantling and maintaining scaffolding within Transmission Substations.
Instructions
Only persons who are trained and certified in scaffolding are permitted to erect
and dismantle scaffolding more than four (4) metres in height.
Construct,
assemble
and
maintain
all
scaffolding
according
to
the
manufacturers specifications.
Tie all scaffolding of four metres and taller to the structure being worked on,
unless the manufacturers specifications state otherwise.
Only use mobile scaffolding which has adequate strength and is on a solid
level surface.
Transmission Substation
Section 5.6
Scaffolding
Mobile scaffolding must be able to safely support the total load imposed by the
weight of the scaffold, the people working on it, and the materials used.
Edge protection
If you cannot install edge protection, use a fall restraint or arrest system
instead.
Place guardrails no more than 100 mm outside the edge of the working
platform.
Position midrails half way between the guardrail and the toe board.
Erect toe boards to the exposed edges of a working platform (or any other
place) where tools or materials could fall more than two metres.
The toe board must be securely fixed to the floor (or posts) and is at least 150
mm high. The gap between the toe board and the working platform must be no
more than 10 mm.
Mobile scaffold
The height of a mobile scaffold must not exceed three times the length of its
smallest base dimension.
Fit four (4) castors under the mobile scaffold to safely support the total load
imposed by the weight of the scaffold, the people using it, and their materials.
Transmission Substation
Section 5.6
Scaffolding
The maximum safe working load for a mobile scaffold is 450 kg. This
comprises:
Ensure castors have an effective wheel brake capable of being locked, and
which cannot be accidentally released when working from the scaffold.
When the assembly is lifted off the ground, ensure the castors do not fall out of
the scaffold tube.
The height of the tower or independent scaffold must not exceed three times its
smallest base width (unless specifically stated in the manufacturers
specifications).
Where the height of the tower exceeds three times its smallest base width, tie it
to the supporting structure.
The minimum size of the base plates for independent scaffolding must be 150
mm x 150 mm or 170 mm in diameter.
Insulated scaffolding
If the scaffolding is used to carry out Live work, the following will apply.
Prior to erection, wipe insulated scaffolding clean and then dry with a siliconeimpregnated cloth.
Transmission Substation
Section 5.6
Scaffolding
Store insulated scaffolding in a cool, dark, and dry area, ensuring there are no
distortions and/or mechanical stress.
Make sure the storage area is out of direct sunlight, free of chemicals, oils,
solvents, damaging vapours, and fumes.
An authorised person using an insulated stick leakage tester can test the
insulated scaffolding at the local depot, or it can be sent to Western Powers
electrical testing section.
Check all insulated scaffolding that displays a test expiry date (month and
year) six months forward from the testing date.
DANGER
DO NOT attach the fall arrest system to, or around, porcelain insulators.
Inspection / maintenance
Only persons trained and certified in scaffolding can inspect and tag
scaffolding.
Tag scaffolding:
When it has been inspected for a second party - at least every 30 days.
Transmission Substation
Section 5.6
Scaffolding
Carry out a detailed inspection of all scaffolding components at least every six
months using the Scaffold Inspection Data Sheet (refer Appendices).
If, during the inspection, any damaged or defective components are found,
remove them from service and tag them out and report to formal leader.
References
Transmission Substation
Section 5.6
Scaffolding
Transmission Substation
Section 5.6
Scaffolding
5.7
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
5.8
Purpose
This instruction provides the key safety requirements relevant to working from an
elevated work platform (EWP) inside a Transmission substation.
It does not
The operator must be competent and authorised to operate the EWP in use.
The EWP operator and safety observer must be trained and competent in the
use of the emergency retrieval system for the unit being used.
Complete a detailed Job risk analysis (JRA) and job briefing before
commencing work when using a EWP. The total work group must be involved
in the process.
During the set up and prior to operation, the EWP must be bonded to the
substation earth grid. Use a minimum of 150mm squared earthing conductor
(in test date), bolted or clamped to the vehicle and substation earth mat.
Transmission Substation
Work Practice Manual
Use a common earth bond where multiple vehicles are at the worksite.
Only use un-insulated EWPs on isolated and earthed apparatus. Do not use
un-insulated EWPs when within the section safety clearances to live
apparatus.
Clearly define the work site with barriers and signs. All assets within the work
site must be de-energised and earthed. Section safety clearances must apply
between the work site boundary and live conductors to ensure the safety of
personnel at all locations within the defined work site.
Un-insulated EWPs are not permitted to enter the Section safety clearance.
A safety observer must be used while the EWP is being manoeuvred (this
includes travelling inside the substation) and positioned into the work position.
Effective and immediate communication must be maintained between the
operator and the observer at all times.
A safety observer must be present if the work requires the work platform to be
repositioned at any time and there is a risk of encroaching on the safe working
clearances. If safe clearances cannot be maintained, additional isolation must
be carried out and the JRA revised.
Where possible, physical barriers must be used to prevent the EWP from
entering the exclusion zone e.g. CT / VT.
Appoint a member of the work party to monitor / assist the EWP operator in
case of an emergency or to manoeuvre the EWP into a new position. Maintain
effective communication between both parties.
Transmission Substation
Work Practice Manual
The operator must be trained and authorised in the use of the EWP.
Undertake a job risk assessment to identify all foreseeable hazards and ensure
risk controls are implemented.
Appoint a designated safety observer for the duration of the work, while the
section safety clearances could inadvertently be broken.
The EWP must be fitted with an emergency decent device. The operator and
safety observer must have achieved a competency in emergency decent with
in a twelve month period.
The EWP must be rated and electrically tested (with in a 6 month period) for
the voltage being worked on.
They carry out daily, pre and post operational checks on the EWP.
They do not exceed the elevated work platform safe working load.
Only operate an elevated work platform when the wind velocity is less than 45
km/h
Transmission Substation
Work Practice Manual
Voltage of conductor
Approach
distances (mm)
Low voltage
1000
1200
66kV
1500
132kV
1800
Over 132kV
3000
Based on industry practice, derived from step and touch potential calculations.
If the above clearances cannot be maintained, insulating gloves rated to the highest voltage within the
boom reach on the structure must be used.
Attach the fall protection harness to the elevated work platform basket anchor
point (lanyard maximum length including shock absorber 1200m) before
operating the boom(s).
A fall arrest system is not required to be worn on scissor lift platform, unless
advised by the manufacture or a person in control of the work place. If a fall
arrest system is required to be worn, a suitable anchor point must be provided.
When performing any work, stay inside the basket and have at least one (1)
foot on the basket floor.
Never tamper with the deadman basket control to bypass its manual function.
Transmission Substation
Work Practice Manual
Person travelling in the basket must at all times, wear a suitable safety harness
and lanyard. (This excludes the scissor lift platform)
The EWP basket must not breach the section safety clearances.
Transmission Substation
Work Practice Manual
References
Transmission Substation
Work Practice Manual
5.9
Crane use
Purpose
The purpose of this instruction is to outline the safe work requirements when
operating a crane within a Transmission substation.
The instruction only provides the minimum requirements relevant to crane
operations and does not attempt to replicate any detailed work practices or
maintenance requirements contained in training or other pertinent documents.
Refer to section 5.10 of this manual for the role of a dogman on Western Power
construction sites.
Competency and authorisation
The crane operator must:
Note:
A dogman who is considered competent by the on site person in charge may be
delegated as a Safety Observer.
The Dogman must:
Basic instructions
The crane operator must:
Transmission Substation
Work Practice Manual
Check and inspect all chains, slings and other lifting devices for wear, tear
damage and counterfeit.
Ensure the crane is suitable for the lift capacity and jib manoeuvrability.
Never leave the crane unattended unless all safeguards have been
implemented.
Mitigate any risks associated with step and touch potential by imposing a
ground approach distance.
Where practical, position the crane so that the maximum reach of the jib is
unable to enter the minimum approach distance of live or de-energised
apparatus. Consider inadvertent movement clearances.
Stand on a conductive mat electrically bonded to the vehicle when using side
controls or wear insulated gloves rated to at least the voltage of the nearby
power lines.
Stow the crane jib when travelling (except when performing pick and carry
movements).
Conduct the job risk assessment process and implement risk controls.
Confirm that any person who is involved in the task understands the risk
controls.
Transmission Substation
Work Practice Manual
Position warning signs, barriers, etc. to delineate the safe work area and warn
others not involved in the task of any foreseeable risk.
Crane operations
The following are additional instructions that apply when operating a crane in a live
substation.
The crane operator must:
Possess a current Substation Entry Permit (NA1 for work not requiring a permit
or NA2 when required to sign onto a permit) or under the direct escort of a
person who possess a current NA 3.
Perform the logbook pre-start crane operation checks before entering the
substation.
Comply with the maximum 15kph speed restriction. When performing pick and
carry movements, do not exceed walking speed.
Enter the substation and notify SOCC via the substation telephone landline.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
5.10
Dogging
Purpose
The instruction describes the role of a licensed dogman on any Western Power
Transmission Substation.
The instruction only provides the key points relevant to a dogman and does not
attempt to replicate comprehensive instructions defined in legislation, Western
Power guidelines or training documentation.
Instructions
The onsite person in charge must confirm that the dogman posseses a current
License to Perform High Risk Work DG, and is competent in their designated
role.
The onsite person in charge must provide the necessary tools and equipment
required by a dogman for the task. For example, first aid kit, communication
device and barricades.
Transmission Substation
Work Practice Manual
Slinging loads
Transferring loads from a vehicle to the ground or from the ground onto a
vehicle when on construction sites.
The person having control of the workplace must confirm that the dogman and
crane operator are licensed and experienced in construction work and relevant
crane operations.
The crane operator must clearly define the task the dogman is required to
undertake.
The dogman and crane operator must complete an assessment of the worksite
and scope of the lift then apply all controls required to eliminate or reduce the
risk of injury or damage. If required, develop a preliminary dogging plan.
The dogman, in consultation with the crane operator, must calculate and
confirm the load weight and other factors related to the lift such as the centre of
gravity.
The dogman and crane operator must inspect the required lifting gear and tag
and remove any unserviceable equipment.
The dogman must adopt a position whereby he/she is able to provide their
undivided attention to the crane operator. Work must cease if the dogmans
view is impaired.
Transmission Substation
Work Practice Manual
The dogman must ensure the stability of the load during the lift.
In the movement of the load, the crane operator must be directed by a dogman
until the load is in its final position.
If for any reason, the dogman has to leave their position, they must ensure the
crane operator ceases all crane movements.
Whenever any noise factor inhibits clear communication between the crane
operator and dogman, they must establish an at-risk warning system such as:
Hand signals.
Whistle signals.
Two-way radio.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
5.11
Rigging
Purpose
The purpose of this instruction is to outline the requirements for Western Power
personnel (Network Total Workforce) who undertake rigging within Transmission
Substations.
Scope
This instruction covers all Western Power Network Total Workforce (employees and
contractors) who are required to undertake rigging within Transmission Substations.
General
All lifting work (as identified in this section) relating to work undertaken by
Western Power personnel is to be overseen by an authorised Western Power
representative. The authorised person must ensure that any lifting work is
supervised by a competent, qualified person (e,g. Rigger or Dogman).
Instructions
Except for emergency stop signals, ensure crane operator responds only to the
designated signal person.
Before, during, and after using any rigging equipment, inspect it. If defective,
immediately remove from service. Do not weld or alter any rigging or lifting
devices.
Transmission Substation
Work Practice Manual
If the rigging equipment, lifting device, or crane has been shock-loaded, stop
the work and inspect the equipment immediately.
Rigging Qualifications
Steel erection.
Tilt slabs.
Demolition.
Dual lifts.
Advanced rigging consists of all basic and intermediate rigging work outlined
above and:
Transmission Substation
Work Practice Manual
References:
National Standard for Licensing Persons Performing High Risk Work schedule
licence classes and definitions.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
5.12
(SF6) gas
Purpose
This instruction outlines the minimum requirements for safe handling, storage,
maintenance, repair, transport and disposal of equipment containing SF6 gas.
Safety aspects and implications
SF6 gas is colourless, odourless, tasteless, non-toxic and non-combustible.
However, SF6 gas can be a risk to human health due to toxic by-products and its
potential to displace oxygen in confined spaces.
Environmental aspects and implications
SF6 gas is a greenhouse gas with a Global Warming Potential 23,000 times more
than carbon dioxide.
Instructions
Avoid heat, sparks, open flames and other ignition sources as it can produce
toxic bi-products.
Transmission Substation
Work Practice Manual
Recovered SF6 (not reclaimed and returned into equipment) must be returned
to a nominated Western Power Depot (Kewdale and Jandakot).
Transportation
Disposal
Recover all the remaining SF6 before disposing of SF6 filled equipment.
Treat all failed or decommissioned equipment containing SF6 gas or byproducts and/or SF6 gas requiring treatment for re-use as a Controlled Waste.
Safety
You must have a confined space entry ticket before entering any confined space.
Wear the following safety equipment before working on SF6 equipment:
Disposable overalls with elasticised sleeves, legs and close fitting neck or
hood. When worn, the overalls must overlap the gloves and boots.
Transmission Substation
Work Practice Manual
Safety boots/shoes.
Where high volume SF6-filled equipment resides and the depths of enclosures
(cable trenches and pits) near the equipment has been identified as a confined
space, permanent exhaust fans must be installed.
Fit exhaust fan/ with an inlet pipe extending to the lowest level of the room,
ensuring the removal of SF6 from the work area is to an open or well-ventilated
area.
Where exhaust fans are not installed in an enclosed or partially enclosed area,
6
where SF equipment resides, the area must be adequately ventilated before
undertaking work.
References
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
5.13
Purpose
This instruction describes the role of a safety observer on any Western Power
worksite.
The instruction provides the key points relevant to a safety observer and does not
attempt to define the role for all work situations.
Instructions
The on-site person in charge must provide sufficient safety observers for the
duration of the task.
The onsite person in charge must instruct the safety observer of their duties,
clearly define the work activity and the period whereby a safety observer is
required.
While observing a task the safety observers sole role is to observe the
movement of people or equipment and when necessary give warnings in the
event of any risk or non-compliance to safe work procedures.
Transmission Substation
Work Practice Manual
The safety observer must not have any known temporary or permanent
disabilities that would adversely affect their competency to perform their role.
The safety observer must adopt a position whereby they are able to give their
undivided attention to those performing the work. Work must cease if the
safety observers view of the work is impaired.
If for any reason, the safety observer must leave their position, work must be
suspended. Those performing the work must move to a safe distance whereby
they are clear of any risk.
The safety observer must not undertake any other tasks that may distract their
focus on the work being performed, or attempt to observe two or more
separate teams.
The role of the safety observer must be rotated if fatigue becomes a risk factor
or the work must be suspended.
change occurs.
The onsite person in charge must confirm that the safety observer is
appropriately skilled in all aspects of safety observation and fully aware of the
potential risks associated with the work.
For some high-risk work, the safety observer may require specific authorisation
or competency.
The safety observer is required to possess the following first aid competencies:
HLTCPR201APerform CPR.
Transmission Substation
Work Practice Manual
The onsite person in charge must provide any tools and equipment required by
a safety observer.
When noise may impact on the ability for the safety observer to communicate
with those performing the work establish an at-risk warning system such as a
whistle, compressed air horn or two-way radio.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
5.14
Induced voltages
Purpose
This instruction outlines the minimum requirements for working on isolated
apparatus that could be under the influence of induced voltage within Transmission
Substations. It includes an explanation of, and advice on how to reduce or eliminate
the risk of electrical induction on the isolated conductor/ apparatus.
DANGER
Induced voltages may be as little as a few volts and as high as many kilovolts
and could be hazardous or life threatening if the correct procedures are not
followed.
Note:
An induced voltage is often simply referred to as induction.
All persons performing work must comply with the worksite clothing and minimum
PPE requirements of section 3.0 in this Manual
Instructions
Carry out an inspection of the work area to determine the proximity of one set
of conductors to another or an item of electrical apparatus to a set of
conductors to determine the likelihood of the existence of any induced
voltages.
Complete the job risk assessment (JRA) process and job briefing to identify all
foreseeable risks, including induced voltages.
Wear personal protective equipment and clothing appropriate for the risks
identified during the JRA process.
Obtain the relevant permits for the apparatus to be worked on, from the
controlling authority (SOCC).
Transmission Substation
Work Practice Manual
Applied and removed portable earths using an approved and rated insulated
stick.
Wear class 2 insulated gloves to avoid touch potential which may occur when
working around mobile plant and other conductive apparatus.
If any part of the earthing is broken, dangerous voltages may occur when it is
necessary to break a part of the earthing system. Connect a bridging lead
across this part of the earthing system, before it is broken.
Do not remove the earth connections between apparatus and the earth system
while the apparatus is in service, unless it is specifically known this can be
done safely. A dangerous voltage may occur if the earth connection is removed
from high voltage apparatus while in service.
Transmission Substation
Work Practice Manual
Person/s working on any conductor on the ground that may have induced
voltages, must wear a minimum of class 2 insulated gloves in addition to the
working earths applied to the conductor. If the conductor is disconnected, use
a temporary jumper to bridge the gap until the conductor can be pulled
together and reconnected. The temporary bridge can then be removed.
When carrying out conductor jointing, splicing or disconnecting for any other
reason, earth both conductors as close as possible to the apparatus and a
temporary jumper placed across the disconnected conductor, to maintain
electrical continuity. The lead must comply with the Portable earthing
equipment requirements (refer to section 2.2 of this manual).
Transmission Substation
Work Practice Manual
General information
Where possible, leave all earth switches ON at the substation site unless they
need to be opened for testing. Before any earth switches are opened, ensure
all personnel are aware of the changes to the earthing arrangements within
their relevant work area. If operating an earth switch, a Restricted Use tag
must be placed at the switch. Once the testing is completed, the earths are to
be re-applied and all personnel notified.
Transmission lines are considered one of the major sources of induction. The
current in the energised high voltage conductor causes a magnetic field that
may cut through de-energised conductors. This induces a current in the
isolated lower voltage line.
The nature of the dielectric, ambient conditions, moisture, heat wind etc.
1.0
2.0
3.0
4.0
5.0
6.0
60%
50%
40%
30%
20%
10%
The distance between the overhead transmission lines and any object in the
field may change from time to time, according to the electricity loading of the
lines as well as the swinging angle. Induction can be increased or transferred
when conductive object approaches an energised conductor, i.e. pulling or
tensioning equipment, busbars, switchgear and mobile plant.
Transmission Substation
Work Practice Manual
The number of working earths required will be influenced by the value within
the electric field, the main earth resistance, the resistivity of the ground and the
proximity of the working earths to the working position. In severe cases when
induction cannot be totally eliminated, wear class 2 insulating gloves
References
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
5.15
Pitch removal
Purpose
This field instruction outlines the requirements for Western Power personnel
(Network Total Workforce) when carrying out the task of pitch removal within
Transmission Substations.
Instructions
PPE
All personnel who are required to remove pitch must wear the following PPE:
Safety footwear.
Equipment
The approved equipment required to perform a melt out of a pitch box is:
Pitch trough.
Aluminium chute.
Ventilation system.
Transmission Substation
Work Practice Manual
Hand tools.
The following tasks must be completed prior to setting up for a pitch melt out:
Obtain details of the replacement insulator medium required for the cable
box and any other materials required.
DANGER
Equipment will become hot. Ensure all PPE is worn.
Transmission Substation
Work Practice Manual
Heat lamps
Ensure that heat lamps are positioned appropriately to undertake the work
safely.
When initial pitch flow commences, carry out a visual check to ensure the chute
and pitch trough are catching all the pitch.
Melt-out time will vary with the box size. Ambient temperature and air movement
in the pitch box vicinity will also affect melt-out time.
Check the box for melt-out progress at intervals not greater than one hour, and
gauge the amount left and expected time to complete. The final check is close to
full melt-out stage. There is no expected undesirable consequences of leaving
the lamps in place after all the pitch has been melted out.
A gas torch may be used to assist in melting pitch. Due care must be given for
the flame not to come into contact with pitch or electrical apparatus. Additionally
the torch must constantly be moved so as not to cause a hot spot.
Clean up
While the pitch remnants are still heated, use an electric heat gun on medium
setting and rags dipped in the cleaning agent to remove remaining traces of pitch
from the bushings and corners of the box.
removed.
Pitch disposal
with
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
5.16
Purpose
This field instruction outlines the requirements for Western Power personnel
(Network Total Workforce)
Transmission Substations.
Licensing
Certain pesticides and herbicides require that application be carried out only by
a licensed individual.
Instructions
Follow label and material safety data sheet (MSDS) directions to identify
proper safety equipment, handling and application and to note health concerns
of pesticides and herbicides.
Neoprene gloves.
Ensure applicators adhere to the following guidelines for caring for personal
protective equipment:
At the end of each day, wash reusable personal protective equipment with
detergent and clean water. Dry the equipment in a clean, dry place.
Transmission Substation
Work Practice Manual
After eight (8) hours of use, or more frequently if the odour of the pesticide
and herbicides can be detected while wearing the item, replace pesticide
respirator cartridges.
Wash hands with soap and water after handling, mixing or applying
pesticides and herbicides.
Follow the first aid guidelines given on the manufacturers label and/or
MSDS.
Contact local safety and health professional and call local area poison
control centre.
References
Guidance Note for the Assessment of Health Risks Arising from Hazardous
Substances in the Workplace [NOHSC:3017(1994)] (PDF Version).
Transmission Substation
Work Practice Manual
5.17
Purpose
This instruction outlines the minimum safe working requirements for vegetation
management work within the danger zone of live and/or de-energised conductors
within Transmission Substations.
This field instruction must be read in conjunction with section 5.3 of this manual.
Instruction
When carrying out vegetation management work, never breach the section
safety clearance when inside a substation unless covered under a permit.
All work that is less than the work safety clearances (V&H) for the apparatuss
nominal voltage must be isolated and earthed and an Electrical Access Permit
issued.
All work greater than the work safety clearances (V&H) and less than the section
safety clearance (S) to any apparatus nominal voltage must be covered by a
Vicinity Authority. Any work greater that the section safety clearances (S) to any
apparatus nominal voltage may not be required to be covered by a permit.
Transmission Substation
Work Practice Manual
Safety requirements
Personal protective equipment
All workers who operate an elevating work platform must hold a Western
Power High Risk Worker Licence.
Safety observer
A safety observer can be an operational employee or any person who has the
minimum requirements and successfully completed either:
The one-day Tree Pruning Near Power Lines course; or
The three-day High Voltage Vegetation Work course.
The Safety Observer must be competent and instructed in the recognition of relevant
workplace hazards.
References
Transmission Substation
Work Practice Manual
5.18
Site security
Purpose
This field instruction outlines the requirements for Network Total Workforce when
entering and exiting Western Power Transmission Substations.
Instructions
It is Important when entering and exiting substations that all external gates are
left closed and locked. The only exception is when there is a person standing
at the gate to open it when vehicles arrive, then it is to be closed and locked.
Upon arrival report to the call centre (9427 4287) and advise them of:
Site location.
Name.
Contact number.
Purpose of work.
Record in the substation logbook name, date, purpose of work and then sign
the logbook (completed by a member of the work group).
When entering and exiting Western Power Substations (Zone and Terminal)
with security systems:
The following substations have electric fences and security alarms in the relay
rooms:
Southern Terminal
Transmission Substation
Work Practice Manual
Medina Substation
Neerabup Terminal
These substations are monitored, and guards will respond if alarms are
activated. Always assume that electric fences are energised at all times.
Always check the status of the fence before opening gates. If in doubt go
through the disarm procedure.
The procedure for arming and disarming electric fences
Disarm the electric fence before opening the gate to enter / leave the
substation.
Arm the electric fence (if there are no tags / signs) after closing the gate
and ensure the substation secure.
Log out of site with SAT call agent upon leaving the substation and report
any issues.
In the event that personnel require the electric fence to remain disarmed:
Arm the electric fence after closing the gate and ensure substation is
secure.
Log out of site with SAT call agent upon leaving the substation and report
any issues.
Transmission Substation
Work Practice Manual
5.19
Un-authorised access
Purpose
This field instructions outlines requirements for Network Total Workforce who
have arrived at a Transmission Substation to find persons inside or suspicious
activity around the perimeter.
Instructions
Safety of Western Power personnel at substations
to
ensure
their
switchyards/substations,
safety
or
of
against
suspicious
unauthorised
activities
person(s)
outside
in
the
switchyards/substations.
Advise SOCC control room if switching action is required for safety due to
nature of the activities of the unauthorised person(s).
Transmission Substation
Work Practice Manual
Note:
The SOCC controller will, depending on the nature of the suspicious activity
reported, use his discretion in determining whether to call the police or the security
services.
Situations that may require security escorts
There are reasons to believe that the fault(s) are caused by vandals and
that the vandals may still be on site.
Transmission Substation
Work Practice Manual
Wilson Security must be advised of the location where the security guard is
needed, and the name of the employee requiring their services. An estimated
time of arrival (ETA) will be provided by Wilson Security. The SOC shall pass
this information on to the employee concerned and the employee will coordinate his/her ETA accordingly.
Delays may be experienced at some sites because Wilson Security does not
directly cover these areas. They will in these instances use the services of
other security companies. These sites are:
Darlington
Mandurah
Muchea
Mundaring Weir
Sawyers Valley
Note:
There are approximately twenty (20) metropolitan substations that are not
The employee must immediately inform SOCC upon arrival of the security
guard or upon arrival at the affected site (if the security guard has already
arrived).
The security guard must remain with the employee until the employee
considers it safe for the guard to leave. The employee must then contact the
SOC to inform them that the guard is no longer required.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
5.20
Purpose
This field instruction is to provide guidance on the safe handling and application of
Electrical Substation Insulator washing either in a live or de-energised state.
Safety aspects and implications
All personnel engaged in performing this task must observe Western Powers
general safety requirements.
There are specific mandatory safety requirements within this procedure which
must be strictly adhered to for the safe performance of this task.
This standard is to ensure the safety of the person/s carrying out this work, the
general public and the operational integrity of the assets themselves. It also
specifies the minimum standards for equipment required for energised
substation washing methods.
For workers to perform live substation insulator washing, they are required to
be trained (PTS 012) and hold a valid Western Power authorisation for the task
and a current network authority card.
Transmission Substation
Work Practice Manual
Non-trade personnel who have attended the training (PTS 012 Electrical
substation insulator washing), found competent and accredited, may wash in
substations in a de-energised state.
Safe and effective implementation of this task will surely increase the reliability
and stability of high voltage assets and power network in general, whilst
enhancing the quality of professional services we are providing to our
customers.
There are various types of pumps used for washing insulators. They are petrol,
diesel or hydraulically driven and have a working range of up to a maximum of
14,000 KPa.
Transmission Substation
Work Practice Manual
The washing wand consists of three (3) lengths of fibreglass live line stick. The.
sticks can be joined together and adjusted between 2.4m and 4.2m.
This wand is used to wash the insulators, with the nozzle between 300 mm to
450 mm away from the live apparatus. These sticks are to be tested as per
Field Instruction 2.13 of this Manual.
Conductivity meter
Instructions
Conduct a Job Risk Assessment (JRA) process before caring out the task of
substation insulator washing.
Take into account the following:
Tripping hazards.
Permit conditions.
Do not direct the spray at another individual as high-pressure water can cause
harm.
Transmission Substation
Work Practice Manual
It is the responsibility of the person/s on any worksite, plus the on-site person
in charge, to make sure these requirements are complied with.
Approved PPE (Level 1) must be worn at all times when washing high voltage
insulators.
Stop energised spray washing when adverse weather conditions, such as rain,
heavy mist, fog or the likelihood of lighting is present..
Before using the washing wand, check the fibreglass sticks for cracks and
damage to the surface.
Inspect all insulated sticks and equipment before use. Report faulty or
damaged sticks and equipment to the supervisor, and tagged out of service.
Only use if replaced with new or repaired and tested.
Transmission Substation
Work Practice Manual
Test all insulated sticks associated with the washing wand at intervals not
exceeding six months. Attach the test date to the sticks.
Do not use the sticks if the next due test has expired, until they are retested..
Wind velocity
Earth the washing unit,or the vehicle they are mounted on.
Ensure the water container is free of contamination; flush out with low
conductivity water before use.
Use de-mineralised low conductivity water. Check the water quality with a
suitable conductivity meter to confirm it meets the required criteria of no higher
than two millisiemen/meter.
Transmission Substation
Work Practice Manual
The insulator being free from cracks, chips deteriorated glazing or other
surface defects.
Some insulators must only be washed when de-energised such as old design
stacked insulators, or Surge arrestor insulators if required in high pollution
areas.
Sites encountered with a high rate of surface pollution, this upper portion can
still be washed by accredited operators, staying well clear of the circuit breaker
head section. But in this event - de-energized washing is advised and must be
arranged.
Circuit breaker pole insulator assembly flanges must be avoided, with washing
beginning and terminating one full skirt away from any flange or gasket.
Transmission Substation
Work Practice Manual
Take care when washing older design circuit breakers (typically ones rated 33
kV and below), with arcing horns installed across the lower and upper
insulators.
Sub station washing process
Conduct a pre-start inspection on all the washing equipment and check for any
leaks.
Earth the spray-washing unit and or vehicle to the substation earthing system.
Always wash so the overspray drifts (wind assisted), away from unwashed
insulators.
On completion, a rinse down of the insulator (tops only) from the top to the
bottom is required.
On vertical mounted insulators, start the wash process from the bottom moving
to the top of the insulator.
One person will wash the insulators, while the second person operates the
control valve and acts as the observer.
Transmission Substation
Work Practice Manual
The observer watches; clearances, change in the wind direction, along with
other hazards.
References
Transmission Substation
Work Practice Manual
5.21
Purpose
The purpose of this instruction is to outline the requirements for Western Power
personnel (Network Total Workforce) for access to pilot cable termination link and
pilot isolation transformer boxes.
Instructions
General
Before working on a pilot cable termination link and pilot isolation transformer
box, all personnel must have completed (and met the outcomes of) the pilot
training course.
Obtain all relevant permits from the controlling authority for the apparatus
to be worked on.
Isolate the pilot cable termination link or pilot isolation transformer box.
A portable pilot cable high voltage class 2 insulated mat must be used when
carrying out work on a pilot cable termination link or pilot isolation transformer
box.
Transmission Substation
Work Practice Manual
If the Pilot is run as an overhead circuit, examine the Pilot Cable route and
determine what exposure it has to live HV Lines. If necessary, request an
outage on the Line of concern.
Check the insulated mats for signs of damage and deterioration before use.
References
Transmission Substation
Work Practice Manual
5.22
Battery banks
Purpose
To outline the requirements for Network Total Workforce who work on battery
banks within Transmission Substations.
Instructions
Wear the correct PPE when working on lead acid batteries, e.g. full-face
shield, glasses, apron and rubber gloves.
Only use a dampened cloth when cleaning batteries to prevent the build
up of electrostatic charges.
DANGER
Batteries contain corrosive electrolytes and can produce potentially explosive
gases.
Lead acid batteries are installed in an intrinsically safe environment. Maintain
adequate ventilation in these environments. Equipment used in these areas
must also be intrinsically safe.
Transmission Substation
Work Practice Manual
Background
The storage batteries may be lead-acid or nickel cadmium, each with its own
characteristics.
They are vented batteries because the charging process can produce gasses
of hydrogen and oxygen, which needs to be able to escape from the confines
of the battery case.
Use a hydrometer to measure the specific gravity of the cells. This gives the
rate of charge for the battery.
The water level in the battery must be maintained at the correct levels.
Transmission Substation
Work Practice Manual
Lead acid batteries suffer from terminal corrosion because of the corrosive
atmosphere created by the misting of sulphuric acid, which is vented from the
battery or seeping through the battery terminal seals.
The specific gravity of nickel cadmium cells is unchanged by the chargingdischarging process.
The external appearance of lead acid and alkaline batteries can be very
similar. However the electrolyte is not inter changeable. It is important when
doing any testing or servicing the correct identification of battery type is
undertaken. A label is on the battery container to indicate its type.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
5.23
Excavations in substations
Purpose
The instruction describes the safe systems of work that include the
avoidance of any existing underground services.
The instruction only provides the key points relevant to Western Power
worksites and does not attempt to replicate the Worksafe WA Code of
Practice Excavations 2005 or any detailed work practices included in
training manuals.
Training/authorisation requirements
Instructions
Follow the 4 step method:
Plan
Pothole
Protect
Proceed
Transmission Substation
Work Practice Manual
Plan
Dial Before You Dig cannot determine the location of underground
cables/assets inside a substation.
Contact
Western
Power
nominated
representative
(i.e.
Project
Reinforce any structure that has the potential to fall into a trench or
excavation by sheet piling, shoring, bracing, guying or using another
approved appropriate means.
If required, the delegated Issuing Officer will issue a work permit to the
Recipient-in-Charge.
Transmission Substation
Work Practice Manual
Pothole
Advise Western Power and the asset owner immediately of any damage
to an underground asset.
Indicate existing services and their routes with such things as spray paint,
pegs or flagging tape. Where practical, mark the ground to identify an
underground utilities depth.
Transmission Substation
Work Practice Manual
Protect
Install trench shoring whenever it is foreseeable that the soil may collapse
due to vibration, instability, fine sand, water saturation, etc.
Refer to
Transmission Substation
Work Practice Manual
Proceed
Where practicable, backfill all open trenches at the end of each shift.
Compaction shall be done and met design requirements and/or Australian
Standards
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
5.24
Purpose
To outline the requirements for Western Power personnel and the Network Total
Workforce to have a low voltage rescue plan when undertaking work on or near
energised low voltage apparatus within Transmission Substations.
Instructions
Before working on or near low voltage apparatus that is energized the following
precautions must be taken:
Transmission Substation
Work Practice Manual
Provide first aid treatment to the casualty to the level trained to.
Transmission Substation
Work Practice Manual
Direct the flames away from the casualtys face and own body.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
6.1
Purpose
This instruction outlines the minimum requirements for the removal of oil filled
equipment from a transmission substation site, including PCB oil filled equipment.
Responsibilities
It is the responsibility of all personnel who are required to handle, store and
transport transformers that are leaking or not, to comply with this instruction.
Instructions
Personal protective equipment
All personnel who are required to handle, transport and store oil filled equipment,
must wear the following personal protective equipment:
Safety glasses.
Nitrile gloves.
Safety footwear.
If the oil filled equipment is dated pre-1978 or suspected for other reasons
such as make or type to contain PCB, remove it from operation and store
within the transmission substation for PCB confirmation testing.
Arrange for a specialist contractor to sample the oil in the suspected PCB
equipment. Consult Formal Leader for contractor details if unsure.
The contractor will arrange for laboratory analysis of the oil samples to be
conducted at a National Association of Testing Authorities (NATA) accredited
laboratory.
Transmission Substation
Work Practice Manual
Based on the results of the PCB oil testing, label the equipment with either a
PCB free, Contains non-scheduled PCB or Scheduled PCB sticker.
Splash-proof goggles.
If removing the repaired equipment from site, store the leak repaired PCB oil
filled equipment on heavy duty plastic at the substation site.
All used personal protective equipment, absorbent mats / materials used when
handling equipment suspected of containing PCB must, on completion of the
task, be placed in a plastic disposal bag and sealed. These bags must be
placed in the designated container at the Western Power depot
Leaks must be isolated by inserting putty, wiping the area dry and preparing
the metal surface by sanding for the application of the two pack compounds
over the putty. Mix compounds in separate containers to enable further multiple
repairs with remaining compound.
Transmission Substation
Work Practice Manual
Transport oil filled equipment, labelled PCB free, directly to Western Power
Transmission Maintenance depot at Kewdale for repair, refurbishment or
scrapping. The relevant paperwork must accompany the equipment.
References
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
6.2
Purpose
This instruction outlines the minimum requirements for any work undertaken in or
near an environmentally sensitive area.
Overview
Declared weeds.
Organic farms.
Transmission Substation
Work Practice Manual
Pre-planning
When a work package or job card is received, determine whether the work will
be carried out near an environmentally sensitive area.
Western
Power
Environment
Section
on
0419
987
954
or
environment@westernpower.com.au.
Entering and leaving environmentally sensitive areas
When entering an environmentally sensitive area:
Follow instructions issued by the Environment Section and when provided, the
Department of Environment and Conservation.
Follow instructions issued by the Environment Section and when provided, the
Department of Environment and Conservation.
Transmission Substation
Work Practice Manual
Unplanned maintenance
Incidents
Transmission Substation
Work Practice Manual
Kemerton Substation
Environmental issue:
Rare plants
Bridgetown Substation
Environmental issue:
Cataby Substation
Environmental issue:
Transmission Substation
Work Practice Manual
References
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
6.3
Treated poles
Purpose
This instruction outlines the minimum requirements for handling and disposing of
chemically treated poles and pole butts.
Overview
To prevent wood rot and termite attacks, Western Power has used or uses the
following chemicals to treat poles:
Instructions
Avoid skin contact with treated poles and pole butts. When sawing, drilling,
handling and disposing of treated poles and pole butts, you must wear:
Leather gloves.
Safety footwear.
Transmission Substation
Work Practice Manual
Section 6.3
Treated poles
Pole Ash
If it is necessary to make saw cuts on burnt poles, make them in the unburnt
sections where possible.
Transport the pole ash to the nearest depot and place it within a 205 litre steel
drum within the depots controlled waste storage area. Label the drum with a
controlled waste sticker and then inform Facilities Management.
Pole butts
Cut the butts of poles treated with pole mix or chemical treatment rods at a
location 300 mm above the pole mix stain or chemical treatment holes,
Remove treated poles, including pole butts from the site the same day you pull
them out,
Place treated poles, including pole butts in the redundant pole storage area at
the nearest depot.
References
Transmission Substation
Work Practice Manual
Section 6.3
Treated poles
6.4
Purpose
This instruction outlines safe methods for handling, storing, transporting and
disposing of dangerous and explosive goods.
Overview
Dangerous and explosive goods include, but are not limited to:
Explosives.
Read the relevant Materials Safety Data Sheets before handling, storing,
transporting or disposing of dangerous or explosive goods.
A list of the dangerous, explosive and hazardous goods stored at the depot or
work-site (along with accompanying dangerous and hazardous goods codes).
Transmission Substation
Work Practice Manual
Instructions
Prerequisites
Check all dangerous and/or explosive goods are packaged and stored in
accordance with the requirements in the Materials Safety Data Sheets.
Follow guidance notes for the Requirements for the Road Transport of
Explosives in Risk Category 1, 2 and 3 Quantities, issued by Department of
Mines and Petroleum.
Transmission Substation
Work Practice Manual
References
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
6.5
Purpose
This instruction outlines the minimum requirements for managing soil from around
removed poles.
Overview
To prevent wood rot and termite attacks, Western Power has used the
following chemicals to treat poles:
Copper chromium arsenate (used from the early 1980s to the present).
Instructions
Leather gloves.
Safety footwear.
When removing the pole, avoid skin contact with soil surrounding the pole.
Transmission Substation
Work Practice Manual
After removing the pole, dig the soil immediately around the hole to a depth of
300mm and 400mm out from the hole
(1 metre from the hole for transmission poles).
Shovel the excavated soil back into the pole hole and compact every 300 mm
to within 300 mm of the top.
Fill the remaining 300 mm with clean soil and compact it until the soil is slightly
raised.
If the excavated soil cant be put back in the pole hole and can be reached by
animals or humans, remove it from the site by following Field instruction 11.10controlled waste.
References
Transmission Substation
Work Practice Manual
6.6
Purpose
This instruction outline the correct method to replace and dispose of lamps and
fluorescent tubes.
Instructions
Leather gloves.
Safety footwear.
Blown lamps should be placed in the box supplied with the replacement lamp
or within a sealed globe bag (UA#OC3107).
Blown fluorescent tubes should be placed in the box supplied with the
replacement fluorescent tube.
If the lamp or fluorescent tube is broken, put the broken glass and bayonet or
Edison screw base into a globe bag (UA#OC3107) and seal it.
Note:
Place all lamps and fluorescent tubes in the box supplied with the
replacement or within a padded globe bag.
References
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
6.7
Purpose
This instruction outlines how to respond to oil and chemical spills.
Instructions
The following Oil and Chemical Spill Card guides you on how to respond to oil and
chemical spills and includes who you must contact after the spill. You must follow
the Oil and Chemical Spill Card whenever a spill occurs.
OIL / CHEMICAL SPILL CARD
Is the oil/chemical spill:
You must wear the following Personal Protective Equipment when responding
to a spill:
Safety glasses
Safety footwear
Transmission Substation
Work Practice Manual
Spills and spill cleanup is managed by the Pollution Group within the
Environment, Community Engagement and Approvals Branch. The Pollution
Group can be contacted on pollution@westernpower.com.au or 0437 900 737.
You must report all spills in Guardian as an incident. Make sure you tick the
Environmental box in the Incident Details section.
Transmission Substation
Work Practice Manual
6.8
Aboriginal artefacts
Purpose
This instruction outlines the appropriate steps to take when, during ground and
excavation activities, objects are discovered which might be Aboriginal in origin.
Instructions
The on-site person in charge must establish a No Work Zone around the site,
large enough to ensure the discovery will not be disturbed.
Note:
Work may continue outside the No Work Zone.
The on-site person in charge must contact NOCC (9427 0626) to advise them
of the discovery. (If NOCC cannot be reached, contact the Environment,
Community Engagement and Approvals Branch).
The on-site person in charge must inform all personnel on site of the
Environment, Community Engagement and Approvals Branch procedures to
follow.
References
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
6.9
Purpose
This instruction outlines the minimum requirements for safely removing, handling,
and storing streetlight capacitors and choke boxes containing PCBs.
Instructions
Personal protective equipment
When removing, handling and/or storing streetlight capacitors and choke boxes
containing PCBs, wear:
Safety footwear.
When handling streetlight capacitors and choke boxes containing PCBs, follow
the Material Safety Data Sheet procedures for working with PCBs.
Put the plastic bag containing the removed streetlight capacitor and/or choke
box into a suitable container for transportation.
Transmission Substation
Work Practice Manual
At the depot or workshop, store all plastic bags containing streetlight capacitors
and choke boxes in the undercover PCB drum provided for this purpose. That
drum must be kept closed.
When the PCB drum is three-quarters full, order a replacement PCB drum.
Arrange with the Environmental Land Management Branch to send the (three
quarters full) drum to the PCB Stores at Western Powers Welshpool
Substation.
Note:
Before transporting the PCB drum to the PCB Stores at Welshpool Substation,
the lid of the drum must be checked to ensure it has been sealed with silicon or
firmly secured.
Transmission Substation
Work Practice Manual
6.10
Controlled waste
Purpose
This instruction outlines the minimum requirements for handling, storing,
transporting, and disposal of controlled waste.
Overview
There are designated storage areas for controlled waste at each Western
Power depot.
Asbestos.
Mercury.
Oils and emulsions (including waste mineral insulating oils unfit for
intended use).
Solvents.
Alkalis.
Transmission Substation
Work Practice Manual
Instructions
Personal protective equipment
Safety footwear.
Store controlled waste in its original packaging (or containers) when placing it
into designated storage containers at the depot.
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
6.11
Erosion
Purpose
This instruction outlines how to minimise erosion and soil disturbance for planned
or unplanned construction or maintenance works.
Instructions
Land
Water
References
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
6.12
Purpose
This instruction outlines what to do when the work may require clearance or
maintenance of native vegetation.
Overview
Native vegetation clearing is removal, damage or destruction of West Australian
native vegetation and can include driving over or trimming native plants.
Vegetation maintenance is work that keeps vegetation clear of power lines and
other assets.
To determine whether vegetation is native to Western Australia, contact the
Environment,
Community
Engagement
and
Approvals
Branch
at
Transmission Substation
Work Practice Manual
If DEC markers are sighted which indicate rare plants are present in a road
reserve [yellow hockey sticks pointing in their direction]:
Stop work
Follow biosecurity instruction 6.13 to limit the spread of pests and diseases
(e.g. Phythophthora dieback or weeds).
If any of the following occurs, immediately call NOCC (9427 0626) as it may
be a significant incident:
Clearing that
does
not
Environmental
References
Transmission Substation
Work Practice Manual
6.13
Bio-security
Purpose
This instruction outlines the minimum requirements for bio security when working
on agricultural properties, in and around native vegetation and water bodies and
Department of Environment and Conservation (DEC) Estate.
Instruction
Environmental weeds.
Declared plants.
Pests.
Agricultural property
Prior to entry, consult with the property owner, if contactable, to identify any bio
security issues.
DEC Estate
At least ten (10) days prior to entry, contact DEC office in the local area before
entering a DEC estate.
presence of Phytophthora dieback with the DEC officer. Obtain a Disease Risk
Area permit if entering a Disease Risk Area.
Transmission Substation
Work Practice Manual
Before leaving the depot, familiarise yourself with all bio security permits and
plans, Disease Risk Area Permits, hygiene plans and/or Environmental
Management Plans. Ensure vehicles and equipment are clean and free of soil
and plant material prior to leaving the depot.
Entry
Agricultural property
Closed farm gates shall be closed after access/egress. Open gates shall be left
open.
DEC Estate
Exit
All vehicles, personnel, equipment, plant and machinery must be clean on exit.
Use clean down facilities at exit points, if available.
Report any plant or animal species which you suspect may be a declared pest
to the Environment, Community Engagement and Approvals Branch.
Obtain help
Contact the numbers below for assistance in:
Transmission Substation
Work Practice Manual
Complying with a DEC requirement (if you are unable to comply, or unsure of
how to comply).
environment@westernpower.com.au
Distribution
9326 6329
Transmission
9425 5074
References
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
7.1
Purpose
The purpose of this instruction is to outline the requirements for the Network Total
Workforce (employees and contractors) Licensing and Authorisation who work
within Transmission Substations.
Instructions
Network Authority Card
All individuals requiring access to a Western Power Construction site (as defined
in the W.A. Occupational Safety and Health Regulations), will require a Network
authority card.
Refer to section Four (4) of this manual for the requirements to gain access to
substations
It must be the exception and not the norm for a person to be escorted in a
substation to carry out work.
References
http://www.docep.wa.gov.au/EnergySafety/Content/Licensing/Electrical_contra
ctors_and_workers/Licensing.html
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Information tag
Transmission Substation
Work Practice Manual
Inspection tag
Scaffolding tag
Transmission Substation
Work Practice Manual
Document
DM Reference
7678094
5236790
5237319
5237308
6783836
4778786
5236891
6617609
N/A
Sanction To Test
N/A
Vicinity Access
N/A
Operating Agreement
N/A
N/A
6460100
N/A
N/A
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Plant hire sheet for contractor use combined elevated work platform & crane/borer
external hire checklist (this is a representation of the form)
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Function Level
Work Level
NA0
FSA
NA1 *
NPA
NA2*
NA3V
NA3T
NA3D
NA4T
NA4D
NA5V
NA5T
NA5D
VA only
T
D
T
D
VA only
T
D
RIC
TIC
IO
Legend
Function Level
FSA=Fully Supervised Access
NPA=No Permit Access
R=Recipient
RIC=Recipient In Charge
TIC=Tester In Charge
IO=Issuing Officer
NA1*=Substation Entry Authority 1 (SEA1)
NA2*=Substation Entry Authority 2 (SEA2)
Details of Access
Transmission Substation
Work Practice Manual
Purpose
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Conductor weights
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Appendix 4 Emergency
contacts information
Reviewer: Dave Christmas
Transmission Substation
Work Practice Manual
Appendix 4 Emergency
contacts information
Reviewer: Dave Christmas
Transmission Substation
Work Practice Manual
Kewdale
Doctor
Healthpoint Belmont Medical Centre
4/321 Abernethy Rd Cloverdale 6105
(08) 9479 1555
Hospital
Royal Perth Hospital (Public)
Wellington St Perth 6000
(08) 9224 2244
Police
273 Abernethy Rd Belmont 6104
(08) 9424 2700
Mount Claremont
Doctor
Mt Claremont Medical Centre
32 Strickland St Mt Claremont 6010
(08) 9384 0950
Hospital
Sir Charles Gairdner Hospital (Private)
Hospital Ave Nedlands 6009
(08) 9346 3333
Police
379 Cambridge St Wembley 6014
(08) 9387 6777
Forrestfield
Doctor
Healthpoint Belmont Medical Centre
4/321 Abernethy Rd Cloverdale 6105
(08) 9479 1555
Hospital
Royal Perth Hospital (Public)
Wellington St Perth 6000
(08) 9224 2244
Police
273 Abernethy Rd Belmont 6104
(08) 9424 2700
Site:
Chief Fire Warden Doug Dixon
Phone: 9359 7543 Mobile: 0417 951
437
Appendix 4 Emergency
contacts information
Reviewer: Dave Christmas
Emergency -
Three Springs
Doctor
No Permanent Dr Locum Only Three Springs Medical Centre
Thomas Street Springs WA 6519
(08) 99 541013
Hospital:
North Midlands District Hospital
Thomas Street Three Springs WA 6519
(08) 99 543200
Police
Three Springs Police Station
Carter Street Three Springs WA 6519
(08) 99 541016
Jurien Depot
Doctor
Jurien Bay Medical Centre
Whitfield Street Jurien Bay WA 6516
(08) 96 521484
Hospital
Closest Hospitals are Moora, Three
Springs and
Dongara-Eneabba-Mingenew Public
Hospital
48 Blenheim Rd, DONGARA, WA,
6525
(08) 9927 0200
Police
Jurien Bay Police Station
Bashford Street Jurien Bay
(08) 96 521017
Moora
Doctor
Moora Doctors Surgery
Dandaragan Street
(08) 96 511433
Hospital
Moora Hospital
Dandaragan Street
(08) 96 511403
Police
Moora Police Station
Roberts Street
(08) 96 511106
Northam
Doctor
Grey Street Surgery
Grey Street
(08) 9622 1599
Hospital
Northam Regional Hospital
Robinson Street
(08) 9690 1300
Police
Northam Police Station
Gairdner Street
(08) 9622 4260
Merredin
Doctor
Merredin Medical Centre
91 Todd Street, Merredin, WA
6415
(08) 9041 5588
Hospital
Merredin Health Service
Kitchener Road,
Merredin WA 6415
(08) 9081 3222
Police
Merredin Police Station
22 Mitchell Street, Merredin, WA
6415
(08) 9041 2945
Southern Cross
Doctor
Southern Cross Medical Centre
Achernar Street, Southern Cross, WA
6426
(08) 9049 1321
Hospital
Southern Cross Hospital
Coolgardie Road, Southern
Cross WA 6426
(08) 9081 2222
Police
Southern Cross Police Station
Canopus Street, Southern Cross, WA
6426
(08) 90491144
Koorda
Doctor
Nursing Post
Allenby Street
9684 1288
Hospital
Wyalkatchem-koorda District Hospital
Honour Avenue Wyalkatchem WA
6485
(08) 9681 1000
Police
Koorda Police Station
36 Haig Street Koorda WA 6475
(08) 9684 1241
Kalgoorlie
Doctor
Plaza Medical, 335 Hannan St, 9021
3988
Lamington Medical, 18 Addis St, 9021
3022
Boulder Medical, 49 Burt St, 9093
1044
Hospital
Kalgoorlie Hospital
Piccadilly Street, Kalgoorlie WA 6430
(08) 9080 5888
Police
Kalgoorlie Police Station
31-33 Dugan Street, Kalgoorlie, WA
6430
(08) 9021 9777
Transmission Substation
Work Practice Manual
Appendix 4 Emergency
contacts information
Reviewer: Dave Christmas
Emergency -
Margaret River
Hospital:
Margaret River District (Public)
Farrelly St Margaret River 6285
(08) 9757 2000
Police
20 Willmott Ave Margaret River 6285
(08) 9757 2222
Site
Fire Warden Paul Ablett
Ph: 9757 9071
Albany
Hospital
Albany Regional Hospital (Public)
Warden Ave (cnr Hardie Rd) Albany
(08) 9892 2222
Police
210 Stirling Tce Albany 6330
(08) 9892 9300
Site
Fire Warden Michelle Miller
Ph: 9841 0826
Fire Warden Kim West
Collie
Hospital
Collie District Hospital (Public)
Deakin St Collie 6225
(08) 9735 1333
Police
Wittenoom St Collie
(08) 9734 1444
Site
Jerramungup
Nursing Post
Nursing Post (Public)
Kokoda Rd Jerramungup 6337
(08) 9821 1011
Police
Vaux St Ongerup
(08) 9828 2172
Site
Narrogin
Hospital:
Narrogin District Hospital (Public)
Williams Rd Narrogin 6312
(08) 9881 0333
Police:
Earl St Narrogin
(08) 9881 1911
Site:
Fire Warden Bill Rybarczyk
Ph: 0428934654
Kondinin
Hospitial:
Graham Street, Kondinin, WA, 6367
(08) 9889 1000
Police:
Stubbs Street, Kondinin, WA, 6367
(08) 9889 1100
Site:
Busselton
Hospital:
Busselton District (Public)
Mill Rd Busselton 6280
(08) 9754 0333
Police:
20 Stanley St Busselton 6280
(08) 9754 9555
Site:
Fire Warden Ruth Green
Ph: 0427473145
Katanning
Hospital:
Katanning District (Public)
Clive St Katanning 6317
(08) 9821 1011
Police:
Clive St Katanning
(08) 9821 1888
Site:
Fire Warden Rod Zilm
Ph: 0429927125
Transmission Substation
Work Practice Manual
Appendix 4 Emergency
contacts information
Reviewer: Dave Christmas
Transmission Substation
Work Practice Manual
Appendix 4 Emergency
contacts information
Reviewer: Dave Christmas
Telephone
After Hours
Albany
Augusta-Margaret River
Beverley
Boddington
Boyup Brook
Bridgetown-Greenbushes
Brookton
Broomehill / Tambellup
Bruce Rock
Bunbury
Busselton
Capel
Carnamah
Chapman Valley
Chittering
Collie
Coolgardie
Coorow
Corrigin
Cranbrook
Cuballing
Cunderdin
Dalwallinu
Dandaragan
Dardanup
Denmark
Donnybrook-Balingup
Dowerin
Dumbleyung
Geraldton Greenough
Gingin
Gnowangerup
Goomalling
Gosnells
Harvey
Irwin
Jerramungup
Kalamunda
Kalgoorlie-Boulder
Katanning
Kellerberrin
Kojonup
Kondinin
9841 9333
9780 5255
9646 1200
9883 4999
9765 1200
9761 1555
9642 1106
9825 1002
9061 1377
9792 7000
9781 0444
9727 0222
9951 7000
9920 5011
9576 4600
9734 9000
9080 2111
9952 0100
9063 2203
9826 1008
9883 6031
9635 1005
9661 0500
9652 0800
9724 0000
9848 0300
9780 4200
9631 1202
9863 4012
9956 660
9575 2211
9827 1007
9629 1101
9391 3222
9729 0350
9927 0000
9835 1022
9257 9999
9021 9600
9821 9999
9045 4006
9831 1066
9889 1066
9841 9349
0409 805 255
9646 1390
0428 838 025
0428 611 125
9642 1117
9825 1114
9061 1230
9792 7000
9781 0444
0417 953 959
0427 511 186
0429 205 011
0427 576 127
0408 931 274
0407 479 035
0428 521 106
0429 632 203
0427 261 008
0427 836 031
0427 991 000
0427 611 001
0419 937 203
0419 918 287
0429 482 244
0417 180 423
0429 311 202
9863 4151
9956 6600
0408 943 576
9827 1283
9629 1210
Transmission Substation
Work Practice Manual
Appendix 4 Emergency
contacts information
Reviewer: Dave Christmas
Koorda
Kulin
Lake Grace
Mandurah
Manjimup
Merredin
Mingenew
Moora
Morawa
Mount Marshall
Mukinbudin
Mullewa
Mundaring
Murray
Nannup
Narembeen
Narrogin
Northam
Northampton
Nungarin
Perenjori
Pingelly
Plantagenet
Quairading
Ravensthorpe
Serpentine-Jarrahdale
Swan
Tambellup / Broomehill
Tammin
Three Springs
Toodyay
Trayning
Victoria Plains
Wagin
Wandering
Waroona
West Arthur
Westonia
Wickepin
Williams
Wongan-Ballidu
Woodanilling
Wyalkatchem
Yilgarn
York
Bureau of Meteorology
FESA
Department of Environment and Conservation
Transmission Substation
Work Practice Manual
Appendix 4 Emergency
contacts information
Reviewer: Dave Christmas
9684 1219
9880 1204
9890 2500
9550 3777
9771 7777
9041 1611
9928 1102
9651 1401
9971 1204
9685 1202
9047 1102
9961 1007
9290 6666
9531 7777
9756 1018
9064 7308
9881 1866
9622 6100
9934 1202
9046 5006
9973 1002
9887 1066
9892 1111
9645 1001
9839 0000
9526 1111
9267 9267
9825 1002
9637 1101
9954 1001
9574 2258
9683 1001
9628 7004
9861 1177
9884 1056
9733 7800
9736 2222
9046 7063
9888 1005
9885 1005
9671 1011
9823 1506
9681 1166
9049 1001
9641 2233
1300 659 213
9323 9300
9334 0375
DM7863894, Rev 0, Mar 2011
Authoriser: Lewis Potterton
42 of 62
9684 1360
9880 1023
0429 651 101
9550 3630
6454 4600
0427 413 450
0429 111 354
0428 511 808
9971 1025
9685 1317
9047 1213
9961 1180
9290 6666
0408 081 898
0427 062 940
9064 7320
9881 1246
9574 4555
0427 341 202
9046 5042
9973 1120
0429 887 106
0419 042 237
9645 1001
0427 264 377
0428 955 471
0416 001 350
9825 1114
9637 1550
0429 111 354
9574 4555
0428 831 035
9628 7115
0429 611 493
9884 1023
9733 1947
9736 1222
9046 7082
9888 1445
0419 941 829
0428 322 123
0429 108 140
0429 960 000
9049 1230
000
9334 0375
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
Telephone
NOCC Coordinator
9427 0637
9427 0612
9427 0604
9427 0615
9427 0608
9427 4288
9427 4287
9427 4339
Transmission Substation
Work Practice Manual
Depot locations
Depot
Address
Albany
Region
Bridgetown
South
Busselton
South
Collie
South
Forrestfield
Metro
Geraldton
North
Jandakot
Metro
Jerramungup
South
Jurien
North
South
Kalbarri
North
Kalgoorlie
North
Katanning
South
Kewdale
Metro
Kondinin
South
Koorda
North
Mandurah
Metro
Margaret River
South
Merredin
North
Moora
North
Mt Claremont
Metro
Narrogin
South
Northam
North
Picton
South
Metro
Southern Cross
North
Stirling
Metro
Three Springs
North
Waroona
Metro
Transmission Substation
Work Practice Manual
Phone No
Street
Town / Suburb
Nearest Cross
Street
Branch
Shire
Imperial Street
South
Country
South Metro
Albany
South
Country
South Metro
Murray
Albany 132/22kv
9841 1343
Albany Hwy
Albany
Alcoa Kwinana
9410 3111
Naval Base
Alcoa Pinjarra
9531 6850
Amherst Street
132/22kv
Anderson Street
66/22kv
9335 1973
9173
1659
Off Cockburn
Road
Pipeline
Road
Amherst
Street
Anderson
Street
Arkana
132/22kv
9349 3171
Arkana Road
Balga
Walderton Ave
North Metro
Stirling
Australian Fused
Materials 132kv
Australian Paper
Mills
66/22kv
Baandee
Substation
B.P. 66/22kv
9438 8827
East Rockingham
Patterson Road
South Metro
Rockingham
9418 1307
Alumina
Road
Sudlow Road
Bibra Lake
Phoenix Road
South Metro
Cockburn
Southcott
Road
Mason Road
Baandee
9419 2962
Great Eastern
Hwy
Rockingham
Road
James Ct
Marriott
Road
Kwinana
Wellesley
Railway
Parade
Beechboro
Nth. Road
B.P.Refinery
Barrack Silicon
Beckenham
132/25kv
Beechboro
132/22kv
9797 2088
9279 9175
Beenup 132kv
9758 2519
Belmont 132/22kv
Bennet Street
132/22kv
9277 3082
Bentley 132kv
BHP Kwinana
Bibra Lake
Bluewaters
Power Station
330kv
Bluewaters
Terminal 330kv
(82) 3243
(82) 3315
9499 5411
Transmission Substation
Work Practice Manual
Oakley
Fremantle
Port Hedland
Pilbara
Power
Fremantle
Port Headland
North Metro
Kellerberrin
South Metro
Kwinana
Mason Road
Devlin Street
South Metro
South
Country
Kwinana
Harvey
East Cannington
Station Street
North Metro
Canning
Morley
Wandoo Road
North Metro
Kwinana
Off Scott
River Road
Alexander
Road
Belmont
McKay
Street
Bentley
Leath Road
Morse Road
Boys Home
Road
Access From
Boys Home
Road
Refinery
Complex
Stevens Street
Kwinana
Margaret
River/Augusta
Paget Road
Belgravia
Street
South
Country
Bayswater
Augusta Margaret River
South Metro
Belmont
South Metro
Victoria Park
Naval Base
Marquis Street
Sth Of Beard
Street
South Metro
Kwinana
Bibra Lake
Wellard Street
North Metro
Cockburn
Palmer
Williams Collie
Road
South
Country
Collie
South
Country
Collie
Palmer
Description
Black Flag132/33kv
Phone No
042 910
6786
Boddington
132/22kv
9499 5458
Boulder 132/33kv
9093 1925
Bounty 132/33kv
9039 4425
Bridgetown
132/22kv
Bulgarra 132/11kv
Bunbury Harbour
132/22kv
Bunbury Power
Station
Street
End Of Soldiers
Road
South
Country
Boddington
Goldfields
Kalgoorlie Boulder
Jilbaldji
Reserve
Goldfields Hwy
Hyden
Norseman
Road
Sth Western
Hwy
Boulder
Karratha
9499 5486
Byford 132/22kv
Canning Vale
132/22kv
Cannington Terminal
Cape Lambert Power
Station
Cape Lambert
33/132/220kv
9525 1392
9455 1404
9458 2980
Vulcan Road
Liege Street
Vittoria
Vittoria
9727 2142
9651 4116
9322 5721
Chapman 132/11kv
Chidlow
9938 2163
Bussell
H'way
Carrabin
South Road
W Brand
Hwy
St. Georges
Terrace
Chapman
Valley Road
Kondinin
South
Country
Bridgetown Greenbushes
Victoria Pk
Estuary Dve
Great Eastern
Hwy
Vasse
Boallia Road
South Metro
South
Country
Byford
George Street
South Metro
Canningvale
Cannington
Magnet Road
Grose Ave
South Metro
South Metro
Pilbara
Power
Pilbara
Power
South
Country
North
Country
Capel
Carrabin
Cooljarloo
Tuart Dr
Off Railway
Line
Nth Of
Cooljarloo
Road
Perth
William Street
Geraldton
Nerrel Street
North
Country
Pilbara
Power
South
Country
South
Country
Finnerty Street
Koombana
Dve
9187 1771
Carrabin 66/22kv
Transmission Substation
Work Practice Manual
Boddington
Millstream
Road
Busselton 66/22kv
Cataby 132/33kv
Kalgoorlie Boulder
9185 1101
9781 4200
Shire
Goldfields
Hester
Burswood 66/22kv
Branch
Kalgoorlie
Hester Road
972 1791
Nearest Cross
Street
Turn Off
Approx 20kms
From Kalgoorlie
On
Meekatharra
Road
9761 1843
Estuary Dve
Leshenault
Road
Burswood
Road
Rendezvous
Road
Thomas
Road
Capel 66/22kv
Town /
Suburb
Roebourne
Bunbury
Bunbury
Victoria Park
Busselton
Serpentine
Jarrahdale
Canning
Canning
Roebourne
Roebourne
Capel
Westonia
North
Country
Dandaragan
Metro
North
Country
Perth
Geraldton Greenough
Description
Phone No
Clarence Street
66/11kv
9367 2125
Clarkson 132//22kv
Cockburn Cement
132/22kv
Cockburn Cement
Limited
Cockburn Power
(82) 1262
9410 1638
9411 2740
94995494
Collie 66/22kv
9734 1889
Collier 66/11kv
Cook Street
132/11kv
9367 4440
9321 9096
Coolup 66/22kv
Cottesloe 132kv
9530 3224
9384 2666
Cottesloe 66/6.6kv
9384 2666
Street
Clarence
Street
Quinn's
Road
Holmes
Road
Holmes
Road
Leath Road
Boys Home
Road
Patsone
Road
Morrison
Street
South Perth
Nearest Cross
Street
Branch
Shire
Onslow Street
Cnr Hidden
Valley Retreat
South Metro
South Perth
Clarkson
North Metro
Wanneroo
Munster
Russell Road
South Metro
Cockburn
Munster
Kwinana
Cockburn
Kwinana
Palmer
Russell Road
Beard Street
Off Williams
Road
Collie
Rowlands Road
South Metro
South Metro
South
Country
South
Country
Como
Thelma Street
South Metro
South Perth
Cook Street
West Perth
Valli Road
Curtin Ave
Coolup
Cottesloe
Thomas Street
Off Sth West
Hwy
Jarrad Street
North Metro
South
Country
South Meto
Murray
Cottesloe
Cottesloe
Kwinana
Beach
Jarrad Street
South Metro
Cottesloe
Port Road
Second Street
Geraldton
Hudman Road
Opp George
Road
South Metro
North
Country
Pilbara
Power
Pilbara
Power
North
Country
North
Country
Kwinana
Cunderdin
Mundaring
Geraldton Greenough
East Perth
Joel Tce
North Metro
Vincent
East Perth
North Metro
Vincent
CSBP132/22kv
9419 0892
Cunderdin 66/22kv
Dampier Main
(Hamersley Iron)
9635 1283
Curtin Ave
Kwinana
Beach Road
Cubbine
Street
Dampier 33/132kv
9183 1474
Off Parker Pt
Road
Darlington 32/22kv
Durlacher Street
33/11kv
9299 6851
9427 4306
9427 4305
Edgewater (Westrail)
Edmund Street
66/11kv
9326 2218
9921 0343
Town /
Suburb
Victor Road
Durlacher
Street
Summers
Street
Summers
Street
Dampier
Darlington
Collie
Collie
Perth
Cunderdin
Roebourne
Roebourne
Edgewater
Joondalup
North Metro
Joondalup
9335 2324
George Grey
Pl
Stevens
Street
Fremantle
Edmund Street
South Metro
Fremantle
Main 9425
1212
Backup
0427 991
380
Control
Room
9425 1213
Bibby Road
Nambung
Brand Hwy
Emu Downs
Transmission Substation
Work Practice Manual
North
Country
Dandaragan
Description
Phone No
Eneabba132 / 33kv
9952 9024
Esperance 33kv
Finucane Island
66/6.6kv
Flynn Drive
132/22kv
Forrestdale
Street
25km South
Of Eneabba
Harbour
Road
Finucane
Island
Town /
Suburb
Eneabba
Nearest Cross
Street
Branch
Off Brand
Highway
North
Country
Esperance
Pilbara
Power
Forrest Ave
East Perth
Dubs Close
Forrestfield
Wellington
Street
Abernethy
Road
Eighth Street
Training
Place
55kms From
Yalgoo On
Rhs Of
YalgooPaynes Find
Road
Crandon
Street
Woorree
Stirling Crs
9325 8741
018 942
732
Geraldton132 / 33kv
9921 3339
Glen Iris
(82) 3235
Golden Grove
9961 0342
Gosnells132 / 22kv
Guildford Terminal
330/132kv
9398 2834
(132kv)
9250 5330
(330KV)
92508160
Hadfields132 / 22kv
9279 2704
Railway
Parade
9325 4429
Hay Street
Hazelmere
Hedland 220/66kv
Terminal
Henley Brook
132/22kv
Herdsman Pde
66/6.6kv
HISMELT 132kv
(Customer S/S)
(82) 3245
Hazelmere
9387 5178
Central Ave
Whim Creek
Road
Barrambie
Road
Herdsman
Pde
9410 2411
Hopelands Terminal
James Street
132kv
Jandakot Training
Centre
Carnamah
Esperance
Port Hedland
Shire
Port Hedland
North Metro
Port Hedland
Jenark Road
South Metro
North
Country
Kalamunda
Geraldton Greenough
Jandakot
Hope Road
South Metro
Cockburn
Yalgoo
Find Wagga
Wagga Road
North
Country
Gosnells
Walter Street.
South Metro
Gosnells
Midland
Central Ave
North Metro
Swan
Bassendean
Iolanthe Street.
North Metro
Bassendean
Perth
North Metro
Perth
North Metro
Pilbara
Power
Swan
Port Hedland
Pier Street.
Bushmead
Road
N/W Coast
Highway
Port Hedland
Henley Brook
Lord Street
North Metro
Swan
Jersey Street.
Sth Of Beard
Street
North Metro
Cambridge
Leath Road
Wembley
Kwinana
Beach
South Metro
Kwinana
James Street
Linesman
Line
Northbridge
Shenton Street
9411 7878
Jandakot
North Metro
South
Country
Cockburn
9328 8318
Joel Tce
East Perth
Summers
Street
Kalamunda 132/22kv
9293 1853
Wilkins Road
Walker
Street
Kalamunda
Lewis Road
Kalbarri
Magee Cres
9172 3445
(82) 1273
Yalgoo
Hocking
Kalbarri
33/6.6kv
Transmission Substation
Work Practice Manual
North Metro
Vincent
South Metro
North
Country
Kalamunda
Perth
Northampton
Description
Karratha Terminal
132kv
Katanning
66/22kv
Kadathinni
Terminal
Kellerberrin
66/22kv
Kemerton
330/132kv
Kemerton Power
Station
Kenwick Link
Connector
330/132kv
Kerr McGee
Minerals Kwinana
Kerr McGee
Minerals Cataby
Kerr McGee
Minerals Muchea
Kewdale
Kojonup
132/66/22kv
Kondinin
220/33kv
Phone No
9185 2918
9821 1312
9045 4044
9720 1378
330kv
Yard 9499
5479
Control
9729 0821
Karratha
Road
Kojonup
Road
Lot 20
Perenjoir
Doy Road
Three Springs
Gr.Eastern Hwy
North
Country
Kellerberrin
Kellerberrin
Harvey
Harvey
Wellesley
East Of
Wellesley Road
South
Country
9831 1110
9889 1072
Corrigin
Road
9499 5367
Illareen Road
Three Springs
Road
Off Treasure
Road
Grand Hwy
Hazelhurst
Street
Tunney
Road
Landwehr
Terminal
Katanning
Three
Springs
Shire
Pilbara
Power
South
Country
North
Country
Karratha
Leach Road
Mason Road
W Of Brand
Hwy
(82) 3293
Branch
Wellesley
9411 1426
9571 9301
Nearest Cross
Street
South
Country
Horley Road
9690 9200
Town /
Suburb
Off Wellesley
Road
(82) 3265
Koolyanobbing
66/22kv
Kwinana
Desalination
Plant
Kwinana
Substation 132kv
Kwinana
Substation 330kv
Landsdale
Malaga 22kv
Mandurah
132/22kv
Manjimup
132/22kv
Manning St
132/11kv
Street
Roebourne
Katanning
Wimbledon
Street
South Metro
Gosnells
Cooljarloo
Thomas Road
Nth Of
Cooljaroo Road
South Metro
North
Country
Dandaragan
Muchea
North Metro
Chittering
Kewdale
Mackay Street
South Metro
South
Country
Belmont
Kojonup
W Of
Narambeen
Road
North
Country
Kondinin
Kenwick
Kwinana
Beach
Kojonup
Kondinin
Kwinana
(97) 3209
9499 5302
Barter Road
Naval Base
Leath Road
South Metro
Kwinana
9411 2473
Leath Road
Naval Base
Weston Street
South Metro
Kwinana
9411 2599
9247 5932
Leath Road
Hepburn Ave
Naval Base
Darch
Weston Street
Mirrabooka Ave
South Metro
North Metro
Kwinana
Wanneroo
Wangerup
Buller Road
South
Country
Waroona
Malaga
Weir Road
North Metro
Swan
Mandurah
Manjimup
Elizabeth Street
10k Sth On Sw
Hwy
South Metro
South
Country
Manjimup
Scarborough
Joyce Street
North Metro
Stirling
(82) 1233
9581 2188
9771 1220
9341 3249
Transmission Substation
Work Practice Manual
Landwehr
Road
Marshall
Road
Dower Street
Eastbourne
Road
Manning
Road
Mandurah
Description
Margaret River
66/22kv
Marriott Road
132/22kv
Mason Road
132/22kv
Phone No
Street
9757 9240
Forrest Road
Marriott
Road
9721 6917
9419 5958
Meadow Springs
Medical Centre
66/6.6kv
9499 5377
Medina 132/22kv
Merredin
Terminal
220/132kv
Merredin
132/66kv
Merredin
66/22kv
Midland Junction
132/22kv
Milligan Street
132/11kv
Mirrambeena
Moonyoonooka
Terminal
9419 4802
Moora 132/33kv
9651 1128
Morley 132/11kv
Mt. Barker
132/22kv
Mt. Newman
66/11kv
Mt.Lawley
132kv Switchyard
Muchea
132/22kv
Muja 330kv No.1
Switchyard
Muja 330kv No.2
Switchyard
Muja 220kv
Switchyard
Muja 132kv R &
M
Muja 132kv
Switchyard East
Muja 132kv
Switchyard West
Muja 66kv
Switchyard
Mullaloo
132/22kv
9276 1217
9386 7614
9041 2180
9041 2476
9041 1116
9274 1514
9321 2539
9851 2907
Mason Road
Off Yindana
Bvd
Monash Ave
Abercrombie
Road
Robartson
Road
Combes
Drive
Combes
Drive
Town /
Suburb
Nearest Cross
Street
Margaret
River
Tingle Pl
Branch
Shire
South
Country
South
Country
Wellesley
Devlin Road
Kwinana
Beach
Nth Of Railway
X
South Metro
Kwinana
Nedlands
Hampden Road
North Metro
Nedlands
Postans
Thomas Road
South Metro
Kwinana
Merredin
Merredin
Sth Of GE Hwy
Great Eastern
Hwy
Great Eastern
Hwy
North
Country
North
Country
North
Country
Parklands
Harvey
Mandurah
Merredin
Merredin
Merredin
Merredin
Lloyd Street
Milligan
Street
Down Road
Midland
The Crescent
North Metro
Swan
Perth
Albany
Hay Street
North Metro
Perth
Albany
Miling Moora
Road
Moora
Coode Street
Quangellup
Road
Morley
Barber Street
Catherine
Street
Mt. Barker
Wilson Road
Hedland
North
Country
Moora
Muirs Highway
North Metro
South
Country
Pilbara
Power
Bayswater
Plantagenet
9272 1560
Central Ave
Menora
Alexander Dr
North Metro
Stirling
9571 4006
Byrne Road
Powerhouse
Road
Powerhouse
Road
Powerhouse
Road
Powerhouse
Road
Powerhouse
Road
Powerhouse
Road
Powerhouse
Road
Joondalup
Drive
Muchea
North Metro
South
Country
Chittering
9734 0628
9734 0630
9734 0632
9734 0633
9734 0631
9405 3118
Transmission Substation
Work Practice Manual
Collie
Collie
Collie
Collie
Collie
Collie
Collie
Collie
Collie
Collie
Collie
Collie
Collie
Collie
Ocean Reef
Road
Edgewater
North Metro
Joondalup
Description
Mumbida
132/66kv
Mundaring Weir
66/6.6kv
Mungarra
11/132kv S/S
Murdoch
Substation
Murdoch Drive
66/22kv
Murray Street
66/11kv
Myaree
66/22kv
Narrogin South
220/66kv
Narrogin
66/22kv
Nedlands
66/6.6kv
Neerabup
Terminal
330/132kv
New Gen
Kwinana
North Beach
132/22kv
North Fremantle
66/6.6kv
North Perth
66/11kv
Northam
66/22kv
Northam
132/66kv
Northern
Terminal 330kv
Northern
Terminal 132kv
Oakley Terminal
330kv
O'connor
66/22kv
Osborne Park
132/11kv
Padbury
Narrogin South
220/66kv
Phone No
9295 1725
132kv
Yard 9927
6057 Gt
Site
9927 6039
9172 2740
9321 8101
9330 1209
9881 2637
9881 1391
9386 6283
330kv
Yard 0408
945 643
132kv
Yard 0429
883 167
330kv
Yard 0439
979 737
9447 3296
9335 2498
9328 8097
9622 6241
9622 2630
9249 3044
9249 3172
9531 3788
9337 1995
9446 1843
9425 1214
9881 2637
Transmission Substation
Work Practice Manual
Street
Mundaring
Weir Road
Nangetty
Walkway
Road
Murdoch
Drive
Murdoch
Drive
Murray
Street
Town /
Suburb
Nearest Cross
Street
Mundaring
Base Of
Mundaring Weir
Mungarra
Kelly Road
Farrington
Road
Murdoch
South
Hedland
Demarchi Road
Branch
Shire
Mundaring
North
Country
South Metro
Pilbara
Power
Mullewa
Melville
Port Hedland
Perth
King Street
North Metro
Perth
Norma Road
Gt.Southern
Highway
Booragoon
Booth Street
Rockton
Road
Narrogin
Graham Road
South Metro
South
Country
South
Country
Melville
Narrogin
Kitchener Road
Narrogin Valley
Road
Narrogin
Nedlands
Barcoo Ave
North Metro
Nedlands
Ziatas Road
Pinjar
Pinjar Road
North Metro
Wanneroo
Leath Road
Retford
Place
Tydeman
Road
Bourke
Street
NorthamYork Road
NorthamYork Road
Marshall
Road
Marshall
Road
Naval Base
Waldorf Street
North Metro
Stirling
Pearse Street
South Metro
Fremantle
North Metro
North
Country
North
Country
Northam
Northam
Campsie Street
Woodley Farm
Dr
Woodley Farm
Dr
Malaga
Weir Road
North Metro
Swan
Malaga
Oakley
North Metro
South
Country
Swan
Oakley Road
Garling
Street
Scarborough
Bch Road
Gibson Ave
Gt.Southern
Highway
Weir Road
Pinjarra /
Williams Road
Bowen Street
Ellen Stirling
Bvd
Brisbane Road
Narrogin Valley
Road
South Metro
Fremantle
North Metro
North Metro
South
Country
Stirling
Joondalup
Kwinana
Carine
North
Fremantle
North Perth
Northam
O'connor
Innaloo
Padbury
Narrogin
Narrogin
Vincent
Northam
Murray
Narrogin
Description
Phone No
Parkeston
133/33kv
Parklands
Pegs Creek
132/11kv
Piccadilly Street
132/11kv
Picton 66/22kv
(New)
Picton Terminal
132/6kv
Pinjar
11/132kv
Pinjar Gas
Turbine
Pinjarra
132/22kv
Quinninup
66/22kv
Qv1 11kv
Rangeway
13/11kv
Redbank
11/66kv
Red Hill 22kv
Regans
132/33kv
Riverton
132/22kv
Rivervale
132/22kv (New)
Rockingham
132/22kv
Roebourne
33/11kv
Rudds Gully
132/33/11kv
Sawyers Valley
66/22kv
Shenton Park
66/6.6kv
Shotts 330kv
9091
0150
(82) 3286
9185 2019
9021
6099
9725 6300
9725 6300
9400 3910
Main Gate
9400 3911
9531 1434
9773 1247
9322 5628
9425 1242
(86) 6211
Town /
Suburb
Bulong Road
Off Yindana
Road
Dampier
Road
Piccadilly
Street
Boyanup
Picton Road
Boyanup
Picton Road
Parkeston
Perry Road
Pinjar
Perry Road
Paterson
Road
Wheatley
Coast Road
St. Georges
Terrace
Hutchinson
Street
Redbank
Road
Redhill Road
Pinjar
Nearest Cross
Street
Branch
Shire
Kalgoorlie Boulder
Yarri Road
Parklands
Mandurah
Pilbara
Power
Pegs Creek
Kalgoorlie
Parsons Street
Picton
Harris Road
Picton
Harris Road
Quinninup
Mandurah
Road
Off Sth West
Hwy
Perth
Milligan Street
Geraldton
Nw Hwy
Pinjarra
Port Hedland
Red Hill
Toodyay Road
1.3k Sth Of
Orange Spring
Road
Goldfields
South
Country
South
Country
Roebourne
Kalgoorlie Boulder
Bunbury
Bunbury
North Metro
Wanneroo
North Metro
South
Country
South
Country
Wanneroo
Murray
Manjimup
Metro
North
Country
Pilbara
Power
North Metro
Perth
Geraldton Greenough
Port Hedland
Swan
North
Country
Dandaragan
9655 0089
Brand Hwy
Regans Ford
9332 8544
Camm Ave
Midgley
Street
Off
Broughton
Way
Stephen
Street
Bull Creek
Salmond Way
South Metro
Melville
Lathlain
Rutland Ave
South Metro
Victoria Park
Rockingham
Swinstone/Tow
nsend
Withnell Street
South Metro
Pilbara
Power
Rockingham
Roebourne
Sawyers
Valley
Stephenson
Street
Daglish
Selby Street
Collie
Williams Road
9361 7192
9527 3331
9295 1204
9381 6385
9734 5164
South East
Terminal
South Fremantle
Southern Cross
66/33kv
Street
9335 8533
9049 1221
Transmission Substation
Work Practice Manual
Great
Eastern
Highway
Lonnie Street
Salvation
Road
Lots 232 &
231 Orton
Road
Robb Road
Bullfinch
Road
North Metro
Mundaring
North Metro
South
Country
Nedlands
Hamilton Hill
Southern
Cross
Collie
Serpentine
Jarrahdale
Oldbury
Reobourne
Mctaggert Cve
South Metro
North
Country
Cockburn
Yilgarn
Description
Phone No
Southern River
Southern
Terminal 132kv
Southern
Terminal 330kv
Summers Street
9499 5379
Lot 101
Southern
River Road
9417 9283
Annois Road
9417 9395
9328 7254
Tate Street
66/22kv
Three Springs
132/33kv
Ti-West Pigment
Plant
Tomlinson Road.
(Was
Chamberlain
John Deere)
Tully Road
132/22kv
University
66/6.6kv
Victoria Park
66/6.6kv
Wagerup
132/22kv
9458 5773
Annois Road
Summers
Street
Tate Street
Bentley
Perenjori
Road
Mason Road
Three
Springs
Kwinana
Beach
Welshpool
Wagin
66/22kv
9861 1427
Waikiki
Walkaway
Windfarm
9954 1104
9411 1444
Street
Tomlinson
Street
9386 7396
9361 1363
9733 5295
Fairway
Street
Bank Street
Town /
Suburb
Nearest Cross
Street
Southern
River
Branch
Shire
Landor Street
Metro
Gosnells
Bibra Lake
Windmill Dve
South Metro
Cockburn
Bibra Lake
East Perth
Windmill Dve
East Parade
South Metro
North Metro
Cockburn
Vincent
Sevenoaks
Street
Morowa Road
South Metro
Canning
North
Country
Three Springs
Kwinana
Adams Dve
South Metro
Canning
Crawley
Myers Street
North Metro
Subiaco
Victoria Pk
Somerset
Street
Entry To
Refinery
South Metro
Victoria Park
Off
Willowdale
Road
Tillellan
Road
Wagerup
South
Country
Waroona
Wagin
Arthur Road
South
Country
Wagin
(82) 3276
Safety Bay
Road
Safety Bay
Read Street
0427 429
731
Off Burma
Road
Walkway
9306 8166
Clarkson Ave
Wanneroo
9172 3000
Harwell Way
Wedgefield
Tennant
Street
Welshpool
Ellam Street
South Metro
Canning
Perth
Pier Street
North Metro
Perth
Boddington
Welshpool
Furnace Road
South
Country
South Metro
Wembley
Downs
Weaponess
Road
North Metro
Cambridge
Rockingham
Geraldton Greenough
Waterloo
Terminal 132kv
Wattleup
Wanneroo
132/22kv
Wedgefield
66/22kv
Webforge
Wellington Street
66/11kv
Wells Terminal
9325 5710
Welshpool
132/22kv (New)
Wembley Downs
66/6.6kv
9458 1800
Wellington
Street
Off Soldiers
Road
Kurnall Road
9341 3953
Empire Ave
Transmission Substation
Work Practice Manual
Wanneroo
Road
Pilbara
Power
Boddington
North Metro
Wanneroo
Port Hedland
Canning
Description
Phone No
Street
West Kalgoorlie
Terminal
220/132kv
West Kalgoorlie
Terminal 33/11kv
9021 7606
Western
Collieries
132/22kv
West. Mining
Kambalda
132/11kv
9734 4127
West
Kalgoorlie
Road
West
Kalgoorlie
Road
Shotts Road
South
West. Mining
Smelter 132/11kv
Western Mining
132/11kv
Western Terminal
9022 3475
9021 1866
9021 6122
9419 2161
9387 5061
Off
Kambalda
Road
Off
Celebration
Road
Charles
Street
Brockway
Road
Westralian Sands
Modal
Crescent
Willeton
Wickham No.1
Wickham No.2
(Cliffs Robe)
Wongan Hills
132/33kv
Worsley
132/22kv
Wundowie
66/22kv
Yanchep
132/22kv
Yerbillon
66/0.440kv
Yilgarn
220/33kv
Yokine
132/11kv
Yornup
66/22kv
Town /
Suburb
Nearest Cross
Street
Kalgoorlie
G. Eastern
Highway
Kalgoorlie
G. Eastern
Highway
Collie
Goldfields
Road
South
Country
Collie
Boulder
East
Rockingham
Goldfields
Kalgoorlie Boulder
Patterson Road
South Metro
Rockingham
Mt Claremont
Nedlands
Bunbury
North Metro
South
Country
Bunbury
Canning Vale
South Metro
Canning
9734 3086
Worsley
Gastaldo Road
9573 6216
Hawke Ave
Wundowie
9407 5247
Romeo Road
Carabooda
9047 5050
Smyth Road
E.Sth.CrossMarvel Loch
Road
Carrabin
Wanneroo
Road
7km E Of
Carrabin
Southern
Cross
10km Sth Of Sx
Darch Street
Gommes
Road
Yokine
Transmission Substation
Work Practice Manual
Kalgoorlie Boulder
Coolgardie
Wilding Road
9761 9047
Kalgoorlie
Boulder
Goldfields
Wongan Hills
9349 3847
Goldfields
Shire
Kambalda
Serio Road
Worsley
Refinery
9049 1465
Branch
Cape Street
Sth Western
Hwy
Yornup
Pilbara
Power
Pilbara
Power
North
Country
South
Country
North
Country
North Metro
North
Country
North
Country
North Metro
South
Country
Wongan Ballidu
Collie
Wanneroo
Westonia
Yilgarn
Stirling
Bridgetown Greenbushes
Transmission Substation
Work Practice Manual
Transmission Substation
Work Practice Manual
First Aid
When possible, the person with the best first aid knowledge should stay with the
casualty while someone else calls for the emergency assistance.
To call for the Ambulance, Police or Fire Service, use 000 from all phones
(including mobiles). If you are using a digital mobile phone and 000 fails, call
112 unless your service provider has advised otherwise.
When the emergency operator answers, state clearly which service is required.
Stay calm and speak clearly to convey the message. Be ready to answer any
questions.
The exact address or location with any clear landmarks or closet street
cross reference
Any hazards relevant to the area, such as fire, chemical, spills, fumes
The Telephone number where the caller can be contacted in case further
information is needed
DIAL 000
Transmission Substation
Work Practice Manual
The Chain of Survival describes the sequence of critical intervention stages in the
initial care of a cardiac arrest patient.
The Critical stages are:
Early CPR
This will increase the casualtys chance of survival by encouraging oxygenated
blood flow to the brain.
Early Defibrillation
The restoration of an adequate heart rhythm is necessary for the casualty to
survive a cardiac arrest.
Transmission Substation
Work Practice Manual
DRABCD
Check for danger to yourself, bystanders and the casualty
D - Danger
R - Response
A - Airway
B - Breathing
Look down the chest, listen for breath and feel it on your
cheek. Rest your hand on the person's diaphragm and feel for
breathing.
If they are not breathing, give 2 rescue breaths. If the casualty
is breathing but unconscious, place in the recovery position
and monitor ABC. Seek emergency assistance.
C - Compressions
D - Defibrillation
Transmission Substation
Work Practice Manual
Secondary survey
Once a Primary Survey has been carried out and the breathing, circulation and
severe bleeding has been controlled, a secondary survey is required.
A Secondary Survey is designed to determine if the casualty is suffering from any
other injuries that require treatment. Complete a full secondary survey of a casualty
before treating the injuries so that injuries may be prioritised.
Always wear rubber gloves and check hands regularly for blood or fluid.
Speak calmly and reassuringly to the casualty and ask them for the:
History: What happened and previous injuries (this will give an indication
to possible new injuries).
Allergies: What are they allergic to? Record this information. Medical
alert bracelet/necklace.
Check the pulse rate and note the breathing rate and characteristics.
If rolling a casualty into the recovery position, ensure keys and other objects from
pockets have been removed so that further damage or injury is not caused.
Transmission Substation
Work Practice Manual