Beruflich Dokumente
Kultur Dokumente
METHOD STATEMENT
Rev.: 0
Date: 19.09.07
Page 1 of 7
METHOD STATEMENT
N2664-W-M-MS-07-A/N 2480
19.09.07
00
UNNI CYRIAC
MECH. ENG.
HAMDY
M&E COORD.
JOHN MEKDISSI
PROJECT
MANAGER
Date
Revision
Description of Revision
Prepared by
Checked by
Approved by
N2664-W-M-MS-07-A/N-2480
METHOD STATEMENT
Rev.: 0
Date: 19.09.07
Page 2 of 7
REVISION RECORDING
Date
Revision
Description of Revision
Prepared by
Checked by
Approved by
19.09.07
00
UNNI CYRIAC
MECH. ENG.
HAMDY
M&E COORD.
JOHN MEKDISSI
PROJECT
MANAGER
N2664-W-M-MS-07-A/N-2480
METHOD STATEMENT
INSTALLATION OF HYPOCHLORITE DOSING
SYSTEM
Rev.: 0
Date: 19.09.07
Page 3 of 7
TABLE OF CONTENTS
TABLE OF CONTENTS...................................................................................................................................
1.
PURPOSE.................................................................................................................................................
2.
SCOPE......................................................................................................................................................
3.
REFERENCE............................................................................................................................................
4.
RESPONSIBILITY....................................................................................................................................
5.
6.
PROCEDURE...........................................................................................................................................
7.
TOOLS......................................................................................................................................................
8.
SAFETY....................................................................................................................................................
9.
ATTACHMENT..........................................................................................................................................
N2664-W-M-MS-07-A/N-2480
METHOD STATEMENT
INSTALLATION OF HYPOCHLORITE DOSING
SYSTEM
1.
Rev.: 0
Date: 19.09.07
Page 4 of 7
PURPOSE
This describes the procedure for the Installation of Hypochlorite dosing
equipment at Lot F.
2.
SCOPE
This method statement covers the installation of the following main plant items :
2x 100% Hypo chlorination dosing pumps and electrical and mechanical
accessories
3.
4.
RTU
REFERENCE
ADWEA Standards
Method Statement for Tapping the existing pipeline to connect the suction line of
the new dosing system for lot-f Ref: N2664-W-M-MS-07-A/N-2473 R0
Method Statement for Commissioning of Hypochlorite Dosing System Ref: N2664W-M-MS-07-A/N 2472 R0
Method Statement for enhancement of VFD KW rating for Lot F Ref: N2664-W-MMS-07-A/N-2470 R1
RESPONSIBILITY
The M/s. ADMMI shall be responsible for supervising, preparing and installation of
electromechanical equipment in the hypo chlorination room.
4.2
4.3
The Site Engineer shall be responsible for making all necessary preparation for the
installation including cleaning and performing the test in accordance with this
instruction.
4.4
The QC Inspector shall be responsible for the witnessing the test, inspection with
Client/Consultant representative and recording the results.
4.5
All the installation shall be carried out during working hours and in the presence of
ADWEA/Engineer.
N2664-W-M-MS-07-A/N-2480
METHOD STATEMENT
INSTALLATION OF HYPOCHLORITE DOSING
SYSTEM
5.
Rev.: 0
Date: 19.09.07
Page 5 of 7
6.
PROCEDURE
The stainless steel pump skid will be moved to the hypo chlorination room with
forklift/ hydraulic trolley or any other suitable lifting equipment.
The skid will be placed on the prepared foundation and checked for the position and
orientation as per the drawings.
The skid is properly aligned and levelled and inspected with Client/Consultant
before grouting.
Once the position and orientation is checked, then skid is grouted to the foundation.
The pumps and pump accessories will be moved and installed on the skid with
supplied bolts and nuts and tightening them to specified torques (Torques values
are attached).
Electrical cabling shall be done B/w skid and ICP, b/w skid and modified MCC
thorough the existing cable tray as per the contract.
The pumps are pre-aligned and inspected at the factory before despatch, so there is
no need of any alignment to be carried out on site. But, if Client/Consultant is
required to check the alignment, M/s. ADMMI Engineers can show this at site.
The ICP and the RTUs will be moved to hypochlorination room to the specified
location as per the drawings and the marked locations.
The orientation of ICP and RTUs will be checked and inspected by the
Client/Consultant prior to carry out further commissioning procedure.
After the installation of pump and its accessories, the GRE pipeline is connected to
the suction & discharge of the pump as per GRE Pipe work method statement.
The GRE Pipeline will be connected to the existing tanks as per the Method
Statement of Tapping the existing pipeline to connect the suction line of the new
dosing system for lot-F
The testing and commissioning will be carried out as per the Method Statement for
Commissioning of Hypochlorite Dosing System.
N2664-W-M-MS-07-A/N-2480
METHOD STATEMENT
Rev.: 0
7.
8.
Date: 19.09.07
Page 6 of 7
TOOLS
The crane/forklift shall be used for unloading and erection purposes. A formal
request shall be submitted to ADWEA/Engineer prior to activity being carried out
for Approval.
Socket spanners(wrenches)
Do not carry anything in your hands when climbing up and down the ladder. Items
that are too large for your pockets or belt should always be fitted or lowered from
the overhead crane by rope
Do not operate a sling / crane if limit switches are out of order, or if the cables
show they are defected
Do not attempt to lift a load beyond the rated load capacity of a crane or sling
hoist.
Never lift a load from the side. Center the overhead crane / sling directly over your
load before attempting to hoist it, to avoid the load swinging
Ensure all loose materials, parts, blocking and packing have been removed from
the load before lifting
Follow signals only from one slinger in charge of the lift, except a stop signal
Make sure everyone is away from the load before hoisting it. Sound a bell, siren or
other warning device and start to hoist the load slowly.
All employees working near exposed energized conductors or circuit parts are
required to use insulated tools or handling equipments.
To be use rubber Insulating gloves, hoods, sleeves, matting and blankets and
Hard Hat (insulated non conductive)
SAFETY
HAZARDOUS
ACTIVITY
1.Electical
shock
RISK
Death
CONTROL
N2664-W-M-MS-07-A/N-2480
METHOD STATEMENT
Rev.: 0
Date: 19.09.07
Page 7 of 7
3.
Lifting Injuries
Equipments
during
installation
and
post
9.
ATTACHMENT