DAILY / WEEKLY SAFETY INSPECTION

REPORT
Date
Name of person Undertaking
Inspection
Job Title
Work Location
Safety Checklist:
House Keeping
Material Storage
Access/egress

03/01/2015
Aftab Majeed
Sr. HSE Officer
SANG Villas

Power tools

Electrical

Waste disposal

General Health and

st
First aid (equipment,1

Office safety

Sub-contractors

Safety Induction

(guards,training)
Manual handling

issues(Cables,110V)
Barricades/barriers

safety
Working at height

Plant &
machinery(Hoists etc)
Edge Protection
Ladders/stairwells
Scaffold towers
Safety harness/fall
arrest
PPE

aiders)
Trained operatives

Welfare facilities

SMS documentation
Emergency procedures

Safety signage

Slips, trips and falls

Excavations

Vibration

Control of noise

Toolbox talks

Smoking at site/office

Protection of the public


Fire (exits, assembly

Fire extinguishers (in


date)

points etc)

Observations

Action required

Scaffolding

Temporary

electricity
COSHH/MSDS
Lifting
equipment
Pedestrian/
traffic routes

Close out
Name / Date

1# In Dev.# 5, zone# 4, cluster#


3, unit# 13 electrical workers are
performing work at height coring
activity with power tools standing
on unsafe working platform in
staircase, also small ladder is used
as a means of access.

2# In Dev.# 5, zone# 4, cluster#


3,unit# 13 electrical workers
performing coring rope pulling
activity on top roof of staircase
while using small ladder as a
means of access and also no
appropriate edge protection is
provided.

All Engineers and


supervisors are
responsible to ensure
prior to start work at
height activity that
provided working
platform is safe.
All supervisors and
foreman are responsible
to ensure that workers
performing work at
height have full body
harness.
All site engineers and
supervisors are
responsible to ensure
access to work platform
is adequately secured
and safe.
Only competent workers
are
allowed to perform work
at height activities.

All Site Engineers and


supervisors are
responsible to ensure
prior to start any activity
on top roof that
adequate means of
access and egress is
provided or not.
All site engineers and
supervisors are also
responsible to ensure
that appropriate edge
protection is provided at
edge point of roof.
Only competent workers
are allowed to perform
2

work at height activity.


All Supervisors are
responsible to make sure
that workers have full
body harness for work at
height activity.

3# In dev.# 5,
zone#4,cluster#4,unit# 7
plumbing workers are using
damaged cables to perform coring
activity with power tool.

4# In dev.# 5, zone# 3, electrical


workers are performing their rope
pulling and coring activities but no
appropriate housekeeping is
maintained near surrounding
areas.

All Supervisors/ foreman


and storekeepers are
responsible to ensure
that all power cables
issued to site are in good
working condition.

All Supervisors and


foreman are responsible
to ensure that
appropriate
housekeeping is
maintained prior to start
the activity, during and
after work finished.

Distribution:
Name:

Signature:

____________________________
_____________________________ Close out meeting: The purpose of a close out meeting is
to discuss issues raised during the inspection, apportion responsibility to close the issue with
a degree of urgency attached and a timescale, whether it be urgent, or routine.