Beruflich Dokumente
Kultur Dokumente
DEPARTMENTAL PROCEDURE
DP-EPD-302
VII.
7.1
TRAINING MANUAL
FOR PIPING DESIGNER
Piping
Indicate all piping 12 and blow as single line and all piping 14 and
above as double line.
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
Give location, elevation, and line number of all lines leaving an area
outside the area match line, even though some of the information may be
repeated elsewhere on the drawing.
Locate, but do not give the length of, flanged piping components such as
separators, strainers, etc., even if these are specials. The isometric shall
give this information.
Indicate and locate branch lines to pumps from cooling water headers,
gland oil headers, etc., the continuation of this piping is detailed on the
isometric only.
At pumps with lube oil consoles and /or vacuum exhaust turbines, an
auxiliary plan should be made, indicating such piping as cooling water,
gland oil, lube oil, etc., with dimensions.
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
Indicate handwheel orientation for socket weld, flanged, and butt welded
valves.
Partially indicate cold insulation over 3 thick.
Give dimensions up to but excluding 1-0 in inches, and round off to the
nearest 1/16.
Show, but do not dimension, level Controllers, Level Alarms, and Level
Gauges, along with connecting piping.
a) Tag every instrument with the primary identification number given on
the flow sheet.
b) Do NOT locate Tis, Pis, or Sample Points.
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
Indicate and identify electrical components which may affect the design
of piping, such as lighting panels, receptacle panels, pull boxes, etc.
Indicate, identify and locate by coordinate, flood light poles within the
area limits.
Orifice runs which are larger than the lines of which they form a part are
identified by line number and size, with the increased size in brackets :
e.g. 0-111-3 (40).
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
Notes
The following notes shall appear on the main key plan of each area above
the revision box.
1. For General Notes
2. For Abbreviations
3. For additional piping plans in this area
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
7.2
TRAINING MANUAL
FOR PIPING DESIGNER
Since the layout drawings do not contain piping details, the isometric is
required to present sufficient pipeline information for the field or shop
fabricator to produce detailed fabrication drawings. Isometrics shall be
drawn for all piping except as noted in the detail design highlights portion
of the project technology work plan.
Complicated and overcrowded isometrics shall be avoided since they
require excessive drafting and checking time and are more prove to
mistakes. The following rules shall be adhered to when preparing
isometrics :
One line number can be on more than one isometric (sheet 1 of 2, etc.)
Field lines from one adjacent area to another shall terminate at the area
match line
All alloy
All aluminum
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
The Work Group Leader will make available any special stamps or
notes required on the isometric with implementation directions
included in the design highlights. Any stamps or notes should be
placed in the area above the title block.
Place line number, size and direction of flow on the isometric pipeline.
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
For out of spec flanges, call-out the flange requirement (e.g. 3 300#
WNF) rather than indicating a spec break.
Identify item number for in-line and branch instruments, relief valves,
traps, specialty, item, in-line piping, mechanical items and structural
columns in diameter circles.
Indicate, but do not locate, the matchline where a line passes from one
plan drawing to another in the same area (horizontal and vertical).
Except for in spec flanges, 90 long radius elbows, equal tees and
standards bolts and gaskets all other piping material shall be called out
on the isometric using the pipe spec short codes. When both slip-on
and weld-neck flanges are in the spec, the slip-on should be called out
on the isometrics.
Figure 8s, blanks and spacers shall be indicated and called out on the
isometric.
When Y type strainer is not in the pipe spec it shall be called out and
listed under miscellaneous material.
When T type strainers are out of spec. It shall be indicated and called
out on the isometric and listed under miscellaneous material. When
strainer is in horizontal line and angled down at 45, a drain valve
must be tapped in the blind flange with adequate clearance for basket
removal.
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
No partial piece marks shall be used. The field weld should be placed
at the last natural break on the isometric with a dotted line continuing
to the match line and the piece mark assigned by the continuing
isometric.
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
For butt welds and in the vertical field welds shall preferably be in the
horizontal position for socketwelds. Check with design highlights for
Constructability preference.
Indicate the short code on the body of the isometric for all in-spec
valves.
Indicate the handwheel for all flanged, butt welded and socket welded
valves. Give handwheel orientation if it is other than N, S, E, W or up.
Rotate flanged valves to standard bolt hole orientation where possible.
Otherwise, call out the required flange rotation.
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
Orifice flanges shall be called out and shown per indicating tap
orientation, size and type from the following :
Tap size =
Flanged extra length bolts shall not be called out. Usually is set up to
account for them with orifice flanges. Restriction orifices shall be
located and identified along with extra bolt lengths called out.
Shop fabricated bends shall be called out as bend with prefix indicating
diameter i.e., 5 dia. Radius bend. Allow for tangent requirements per
the design highlights.
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
All specialty in-line items, such as SP, ST, RV, Instruments, Piping
Mechanical, Trunnions, etc. shall be listed in the miscellaneous
material section, under description column. Items, such as equipment
and branch type instruments should not be listed.
The pipe schedule must be entered from the nomenclature when the
line class indicated calculate. The column shall not be filled in when
schedule is per spec. Standard bolts shall be entered as the number of
sets required, not individual bolts.
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
All reducers and swages shall give both sizes under the size column.
When Y-strainers are in the line class, list the short code in the fittings
section. When not, list the strainer in the miscellaneous materials
section with description. Branch welds shall be listed in the fittings
section as BRW per size of the branch.
Orifice flanges shall be taken off as a set in the flange column along
with bolts and gaskets in field column. The bolts and gaskets (even
though 300 # and extra length) shall not be called out on the isometric
and will accounted for in special form sheet with the orifice flange.
When isometric require 300# flanges, bolts or gaskets that are in 150#
specs, they shall be listed in the miscellaneous column with the rating
shown under description. (except for orifice flanges)
Indicate nipple length under size column, only when 7 long nipple is
required, (1/2 X 7 ). Do not indicate standard 4 length. The Pipe
Spec, Temperature, Pressure, Insulation and Paint columns shall not be
repeated when the input data is the same. Pipe lengths shall be
determined from point to point dimensions, without deducting for
valves and fittings for 4 SS/10 CS and below. For 6 SS / 12 CS
and above the valves and fittings shall be deducted from the point to
point dimensions.
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0
DEPARTMENTAL PROCEDURE
DP-EPD-302
TRAINING MANUAL
FOR PIPING DESIGNER
7.3. EXERCISES
Originator: Wisnu S.
D:\Buku Pintar\Training Manual for Piping Designer\DP-EPD-302 PDsign_7c\Session_7.doc
Revision No.: 0