Beruflich Dokumente
Kultur Dokumente
SED
R I
A L
LICE
M AT E
WARNING:
Please read the License Agreement
on the back cover before removing
the Wrapping Material.
Effective December 6, 2006, this report has been made publicly available in
accordance with Section 734.3(b)(3) and published in accordance with Section
734.7 of the U.S. Export Administration Regulations. As a result of this
publication, this report is subject to only copyright protection and does not require
any license agreement from EPRI. This notice supersedes the export control
restrictions and any proprietary licensed material notices embedded in the
document prior to publication.
Technical Report
EPRI 3412 Hillview Avenue, Palo Alto, California 94304 PO Box 10412, Palo Alto, California 94303 USA
800.313.3774 650.855.2121 askepri@epri.com www.epri.com
ORDERING INFORMATION
Requests for copies of this report should be directed to EPRI Orders and Conferences, 1355 Willow
Way, Suite 278, Concord, CA 94520, (800) 313-3774, press 2 or internally x5379, (925) 609-9169,
(925) 609-1310 (fax).
Electric Power Research Institute and EPRI are registered service marks of the Electric Power
Research Institute, Inc. EPRI. ELECTRIFY THE WORLD is a service mark of the Electric Power
Research Institute, Inc.
Copyright 2002 Electric Power Research Institute, Inc. All rights reserved.
CITATIONS
This report was prepared by
Dominion Engineering, Inc.
6862 Elm Street
McLean, VA 22101
Principal Authors
S. Hunt, Dominion Engineering, Inc.
K. Hart, PPL Electric Utilities Corp.
This report describes research sponsored by EPRI.
This report is a corporate document that should be cited in the literature in the following manner:
Valve Packing Performance Improvement: Sealing Technology & Plant Leakage Reduction
Series, EPRI, Palo Alto, CA: 2002. 1000923.
iii
REPORT SUMMARY
Background
Leakage from valve packing was identified as a major concern by participants in the EPRI Fluid
Sealing Technology Program Working Group. This group has provided the technical guidance
for research into the causes of, and solutions to, valve packing leakage.
Objectives
To provide maintenance personnel, work planners, engineers, quality control (QC) personnel,
and plant management with an understanding of the causes of leakage from valve packing
Note: Because many different valve designs and conditions are encountered in the field, it is
recognized that a guide of this type cannot cover all situations. Users must work closely with
experienced and qualified packing suppliers to select and apply the best products for difficult
applications.
Approach
EPRI Fluid Sealing Technology Program documents are provided in two parts. The first part is a
technical guide that is directed toward engineers, craft supervisors, and trainers. This technical
guide provides an in-depth review of the causes of leakage and the basis for the EPRIrecommended approach to reducing valve packing leaks. The second part consists of training
materials including viewgraphs for classroom instruction and information on the use of a Valve
Packing Performance Demonstration Unit to demonstrate the principles presented in the
classroom.
v
Results
Upon completion of the training:
Engineers should be prepared to work with valve packing suppliers to select the best products
for each application, to update plant maintenance procedures to reflect the latest knowledge,
and to assess the root cause of leaks from valve packing.
Maintenance technicians should have a better understanding of the key factors that led to
high-integrity packing and how to apply this knowledge in the field.
QC personnel should have the knowledge to determine which of the assembly practices
warrant the most attention.
Plant management should have a better overall perspective of issues associated with leakage
from valve packing.
EPRI Perspective
EPRI views this series of reports pertaining to plant leakage reduction as an important and
needed contribution to the state of the art with respect to plant maintenance practices and
operation and maintenance (O&M) cost reduction. Because mitigation of leakage from valve
packing is important to supporting many plant applications, this document within the series is of
significant potential benefit to members concerned with improving plant safety, operability, and
availability, while reducing associated O&M costs.
Keywords
Maintenance
Leakage
Valves
Valve packing
Packing
Live load
vi
PREFACE
In 1995, EPRI initiated a training program to help utilities reduce leakage from bolted joints with
spiral-wound gaskets. The current version of these training materials is reported in EPRI TR111472, Assembling Bolted Connections Using Spiral-Wound Gaskets [11]. This training
consists of classroom instruction in the fundamentals of gasketed joints and hands-on instruction
on an EPRI-patented Bolting Performance Demonstration Unit. As of June 2001, this EPRI
training program had been conducted at more than 30 nuclear plants and also at several fossil
electric plants, government facilities, and industrial plants.
In 1998, the leakage reduction program was expanded to cover other aspects of external leakage
from piping systems and components at nuclear plants. This work is coordinated by a utility
Fluid Sealing Technology Program working group. Current documents published under this
program cover:
This document describes the results of work to determine the causes of leakage from valve
packing and cost-effective solutions to this leakage. This work included the following activities:
vii
CONTENTS
1 BACKGROUND......................................................................................................................1-1
1.1
Objective ......................................................................................................................1-1
1.2
1.3
1.4
1.5
Summary .....................................................................................................................1-3
2.2
2.3
Summary .....................................................................................................................2-4
3.2
3.3
NUREG/CR-6582 ........................................................................................................3-4
3.4
Summary .....................................................................................................................3-6
4.1.1
4.1.2
4.1.3
4.1.4
4.2
4.2.1
4.2.2
Anti-Extrusion Rings..........................................................................................4-10
4.2.3
Spacers .............................................................................................................4-11
ix
4.2.4
Bushings ...........................................................................................................4-12
4.2.5
Lantern Rings....................................................................................................4-12
4.2.6
4.2.7
Cushion Rings...................................................................................................4-13
4.2.8
4.2.9
4.2.10
4.3
4.3.1
4.3.2
Braided PTFE....................................................................................................4-15
4.3.3
4.3.4
4.3.5
4.4
Commercial Products.................................................................................................4-16
4.5
Summary ...................................................................................................................4-19
5.2
5.3
5.4
5.5
5.6
5.7
5.8
Product Misapplication...............................................................................................5-11
5.9
Aging..........................................................................................................................5-13
5.10
5.11
Summary...............................................................................................................5-14
6.1
6.2
6.3
6.3.1
6.3.2
Low-Friction Packing...........................................................................................6-3
6.3.3
6.4
6.5
6.6
6.6.1
6.6.2
6.7
Summary .....................................................................................................................6-5
7 GLAND PRELOAD.................................................................................................................7-1
7.1
7.2
7.2.1
7.2.2
7.2.3
7.3
Stem Friction................................................................................................................7-5
7.4
7.5
Diagnostics ................................................................................................................7-11
7.6
7.6.1
7.6.2
Gland Length.....................................................................................................7-13
7.6.3
7.6.4
7.6.5
7.7
Summary ...................................................................................................................7-14
8.2
8.3
Summary .....................................................................................................................8-7
9.1.1
9.1.2
Inspect Valve.......................................................................................................9-2
9.1.3
xi
9.1.4
9.1.5
9.1.6
9.1.7
9.1.8
Periodic Retorquing.............................................................................................9-5
9.2
9.3
9.4
Summary .....................................................................................................................9-8
10.2
10.3
10.4
10.5
10.6
10.7
Work Planning.......................................................................................................10-5
10.8
10.9
10.10
10.11
Summary...............................................................................................................10-8
11 OVERVIEW.........................................................................................................................11-1
11.1
11.2
12 REFERENCES ...................................................................................................................12-1
A TRAINING SLIDES ............................................................................................................... A-1
B SAMPLE VALVE PACKING SURVEILLANCE AND RETORQUING PROGRAM .............. B-1
xii
LIST OF FIGURES
Figure 1-1 Valve Packing Performance Demonstration Unit .....................................................1-2
Figure 2-1 Alternative Methods for Sealing Valve Stems ..........................................................2-1
Figure 2-2 Idealized Model of Valve Packing.............................................................................2-3
Figure 3-1 Sources of Leaks Causing Reported Boric Acid Corrosion ......................................3-2
Figure 3-2 Recent EPRI Analysis of Sources of Leaks at Six Plants.........................................3-4
Figure 3-3 Sources of Leaks per NUREG/CR-6582 ..................................................................3-5
Figure 3-4 Number of Valve Packing Leaks per Year per NUREG/CR-6582 ............................3-6
Figure 4-1 Evolution of Valve Packing Systems ........................................................................4-2
Figure 4-2 Typical Component Parts of Engineered Die-Formed Packing System ...................4-6
Figure 4-3 Design and Performance of Wedge-Type Packing ..................................................4-9
Figure 4-4 Damage to Graphite Spacer Caused by Angled Surface at Bottom of Stuffing
Box ...................................................................................................................................4-13
Figure 4-5 Typical High-Pressure Valve Gland Bolting Without Live Load ..............................4-14
Figure 5-1 Consolidation of Die-Formed Flexible Graphite Packing ..........................................5-2
Figure 5-2 Packing Consolidation ..............................................................................................5-3
Figure 5-3 Effect of Consolidation on Gland Load .....................................................................5-4
Figure 5-4 Running Tolerances and Clearances (MSS SP-120) ...............................................5-5
Figure 5-5 Stuffing Box Tolerances (MSS SP-120) ...................................................................5-6
Figure 5-6 Stem Tolerances (MSS SP-120) ..............................................................................5-6
Figure 5-7 Stem Corrosion Test Fixture (MSS SP-121) ............................................................5-8
Figure 5-8 Typical Effects of Stem Misalignment.......................................................................5-9
Figure 5-9 Use of Bushings to Mitigate Stem Misalignment ....................................................5-10
Figure 5-10 Effect of Stem Thermal Taper on Packing Consolidation.....................................5-11
Figure 5-11 Decomposition Rate of PTFE at Elevated Temperature.......................................5-13
Figure 7-1 Galling on Follower Caused by Lack of Hardened Steel Washers ...........................7-4
Figure 7-2 Galling of Soft Steel Washers Provided by Valve Supplier ......................................7-4
Figure 7-3 Live Loading Using Belleville Washers.....................................................................7-7
Figure 7-4 Alternative Live Loading Configurations ...................................................................7-8
Figure 7-5 Effect of Live Loading on Valve Gland Stress ..........................................................7-9
Figure 7-6 Live Loading Spring Packs .....................................................................................7-10
Figure 7-7 Potential Gland Follower Improvements.................................................................7-13
Figure 8-1 Valve Packing Performance Demonstration Unit (VPDU) ........................................8-2
xiii
xiv
LIST OF TABLES
Table 3-1 Evaluation of Leakage-Related Work Orders for Two Sites (19951999) ................3-3
Table 4-1 Valve Packing Products Commercial Products Survey ........................................4-17
Table 8-1 Initial VPDU Experimental Results ............................................................................8-6
Table 8-2 Summary of Initial VPDU Experimental Results ........................................................8-7
Table 10-1 Valve Retorque Schedule Used at BWR Plant With Reported Small Number
of Leaks............................................................................................................................10-7
Table B-1 Sample Valve Packing Surveillance and Repacking Program (BWR Plant) ........... B-2
xv
BACKGROUND
Icons
represent the
accompanying
course slides,
which can be
found in
Appendix A.
1.1
Objective
The objective of this training is to help nuclear plant personnel reduce the
number and severity of leaks from valve packing. This objective will be
accomplished by providing a better understanding of the key factors that
contribute to valve packing integrity. These factors include:
1.2
Target Audience
1-1
1.3
1.4
Figure 1-1
Valve Packing Performance Demonstration Unit
1-2
1.5
Summary
1-3
This section briefly reviews several methods that can be used to seal valve
stems and describes how valve packing functions to produce a seal.
5
2.1
Figure 2-1
Alternative Methods for Sealing Valve Stems [1]
2-1
Packing rings are used for most applications in nuclear plants. Rings of
flexible packing material are inserted into the annulus between the valve
stem and stuffing box and are then compressed axially by a gland
follower. The axial load on the flexible packing forces the packing to
expand outward and to create radial seals to the stem and stuffing box.
Chevron, or V packing, is designed to be installed using the same
approach as packing rings, but to produce higher radial forces, and
theoretically a better seal, for the same amount of axial force.
O-rings provide low leakage and low friction, but the elastomeric
materials used in o-rings typically have a limited temperature capability
and often contain chemicals such as halogens that preclude their use in
many nuclear applications. However, o-rings are used successfully in
many instrument and pneumatic system applications.
Metallic bellows and diaphragms produce a hermetic seal that results in
the lowest achievable leak rates. However, metal diaphragms are limited
to low-stroke applications, and it is difficult to achieve a long stroke with
high system pressures using metallic bellows.
The majority of valves in commercial nuclear plants are sealed by packing
rings. This relatively low-cost solution can accommodate large valve
strokes at high system temperatures and pressures. In addition, when
properly matched to the application and properly installed, packing rings
will provide a reliable low-leakage seal. This report focuses on commonly
encountered packing ring valve stem seals.
7
2.2
Packing is inserted between the valve stem and the stuffing box in the
valve bonnet
The axial force on the packing causes the packing to expand both
inward and outward, creating radial seals at both the stem and the
stuffing box
2-2
Figure 2-2
Idealized Model of Valve Packing
Braided materials that are intended for use as seals, rather than only as
anti-extrusion rings, include blocking materials to fill up the voids
between the braided strands. Some examples of blocking materials are
graphite, polytetrafluoroethylene (PTFE), and lubricants.
Because packing materials are flexible and can flow under load,
provisions must be made to keep the material from extruding between
the stem and gland, between the gland and the stuffing box, and
between the stem and bonnet. Many braid-type packing materials can
accommodate the normal clearances between the stem and gland and
between the gland and stuffing box without adding anti-extrusion
rings. However, die-formed flexible graphite has less strength and
typically requires the addition of anti-extrusion rings.
The axial load on the gland decreases over time due to wear, or loss of
braid ring blocking material. Ideally, there should be some compliance
in the packing that can accommodate small amounts of consolidation,
wear, stem imperfections, and stem thermal taper.
The radial force between the packing and valve stem results in friction
that must be overcome during valve operation. High axial preload
forces, large depths of packing in the stuffing box, and high-friction
packing materials all contribute to high packing friction.
2.3
Summary
When packing rings are loaded axially by a gland, the packing material
expands both inward and outward to develop radial seals at the valve
stem and the stuffing box.
2-4
This section briefly reviews industry experience with leakage from valve
packing. The description is brief because valve packing leakage represents
an ongoing source of significant operation and maintenance (O&M)
expenditures at most plants and has been described at length in previous
Sealing Technology & Plant Leakage Reduction Series reports.
3.1
3-1
Figure 3-1
Sources of Leaks Causing Reported Boric Acid Corrosion [2]
3.2
10
3-2
Total
WO's
Total
WO's
Plant A
Plant B
Average
WO's
Percent
Average WO
Man-Hours for
Plant B
per Year
per Unit
Flanged Joints
and Gaskets
850
189
69
23%
32
500
359
57
19%
31
Valve Packing
663
563
82
27%
16
Seals
302
220
35
12%
24
Other
263
620
59
20%
69
Total
2,578
1,951
302
100%
38*
*This total is generated from more information than is presented in this table.
3-3
11
Figure 3-2
Recent EPRI Analysis of Sources of Leaks at Six Plants
12
13
3.3
NUREG/CR-6582
3-4
Figure 3-3
Sources of Leaks per NUREG/CR-6582 [4]
Of the 199 reportable leak events during the study period, approximately
60% (121 events) occurred during the first four years and the remaining
40% occurred during the last eight years. One reason for the significantly
lower rate over the last eight years was the elimination of reportable
leakage from valve packing, illustrated in Figure 3-4, which is also
excerpted from the INEL report. However, some primary system valve
packing leaks have not been included in the INEL survey report.
3-5
Figure 3-4
Number of Valve Packing Leaks per Year per NUREG/CR-6582 [4]
3.4
Summary
A study conducted by INEL for the NRC in 1997 showed that valve
packing was a major source of primary system leakage prior to
approximately 1992. Since that time, significant progress appears to
have been made in reducing leakage from primary system valves.
3-6
This section briefly describes the evolution of valve packing and the basic
valve packing configurations and products in widespread use.
15
4.1
Valve packing has evolved significantly over the past thirty years. Several
key stages in this evolution are illustrated in Figure 4-1. A review of the
evolutionary stages provides an overview of how packing designs were
changed to improve performance.
4-1
Figure 4-1
Evolution of Valve Packing Systems
The evolution of packing designs was gradual, with several different types
of packing commonly in use at any point in time. With the exception of
the braided asbestos packing in Figure 4-1.a, all of these configurations
are used to some extent in plants today.
4-2
16
Blocking material is used to fill in gaps between the fiber strands in braided packing
and thereby produces a better seal for a given gland pressure. Graphite, PTFE, and
lubricants are examples of blocking materials. If low-friction materials are used for
blocking, then the valve stem friction forces can also be reduced.
4-3
factors lead to the need for periodic retorquing, especially for applications
that involve significant valve stroking. Consolidation during operation was
partially addressed by reducing the number of packing rings to four to five
so that all rings would be more uniformly compressed.
17
NP-2455
NP-5697
4-4
17
Graphite bushings to keep the stem centered for cases involving lateral
stem loads
The use of Belleville washer packs to provide a live load on the gland
19
Figure 4-2 shows a typical modern nuclear plant valve packing system
using die-formed flexible graphite packing rings. The major component
parts are described in Sections 4.2.1 through 4.2.10 of this report. Some of
the parts such as live loading are not used for all applications.
20
21
4-5
Figure 4-2
Typical Component Parts of Engineered Die-Formed Packing
System
Experiments using the EPRI VPDU (see Section 8) show how adding a single dieformed flexible graphite packing ring significantly reduces the rate of leakage of
nitrogen gas relative to the leakage for braid ring packing only.
4-6
Self lubricating
Corrosion resistance
No asbestos
Die-formed flexible graphite also has the highest radiation resistance of all
packing materials and has a coefficient of thermal expansion that results in
little differential thermal expansion of the graphite relative to the valve
stem and body materials.
In the 1970s, Union Carbide introduced a Grafoil expanded flexible
graphite to provide superior sealing without the use of asbestos. Flexible
graphite is a high-purity graphite material that has been chemically treated
to form a compound with and between the layers of graphite structure.
This material is heated rapidly to produce an eighty-fold expansion in size
relative to the raw flake graphite material. This expanded material is then
molded or calendered into sheet form with a density of approximately
70 lb/ft3 (1,120 kg/m3) or approximately half of the theoretical 140 lb/ft3
(2,240 kg/m3) of solid graphite [8].
Die-formed rings are manufactured from flexible graphite ribbon that is
wrapped around a mandrel and then compressed in a die to form a single
packing ring. The amount of material used and the compression force
applied determines the density of the manufactured rings. Ring density is
typically in the range of 90100 lb/ft3 (1,4401,600 kg/m3) or 6570% of
the theoretical density of solid graphite.
4-7
Die-formed rings typically have a square cross section, but the cross
section can also be a reduced-height rectangular or a wedge shape. The
EPRI valve packing improvement study showed that wedge-shape packing
such as shown in Figure 4-3 can develop a seal under lower axial gland
stresses than square packing. However, subsequent qualification tests and
field experience have demonstrated that square packing can also provide
reliable sealing at acceptable gland preload stresses.
4-8
Figure 4-3
Design and Performance of Wedge-Type Packing [7]
4-9
4-10
4-12
Figure 4-4
Damage to Graphite Spacer Caused by Angled Surface at Bottom of
Stuffing Box [10]
that prevents the torque from producing the desired gland preload force.
Figure 4-5 shows gland bolting for a typical high-pressure valve with
hardened steel washers to minimize damage and high parasitic friction at
the point where the gland nut turns against the follower surface.
Figure 4-5
Typical High-Pressure Valve Gland Bolting Without Live Load [10]
4.3
4-15
4.4
Commercial Products
Alternative
Products
Positive Features
Negative Features
Die-Formed
Graphite Packing
Rings
Square or
Rectangular Rings
Excellent sealing
Low friction
Low consolidation
Wedge-Shaped
Rings
Anti-Extrusion Rings
Low cost
Low halogen
Not tolerance sensitive
Consolidation
Increased friction
Gland stress limited to 46 ksi
Low friction
Low consolidation
Composite Ring
Graphite/Resin
Lowest friction
Low consolidation
Spacers and
Bushings
Washers
Graphite Sheet
Rings
Low cost
Aids in assembly
Cushions bottom of spacer
Argo
Chesterton
Garlock
6300 J
5200
5300
GRAPH-LOCK
Rings
5800
9000-EVSP
includes various
end ring types
One
One-CI
G-700
5600
GRAPH-LOCK
Rings
524
6000
5005 std-density
5010 high-density
6200 N
N/A
5100
4525
N/A
4-17
Alternative
Products
Positive Features
Negative Features
Argo
Chesterton
Garlock
N/A
N/A
Braided Packing
Rings
Asbestos Yarn
Graphite/Mica Filler
Health hazard
Hardening in service
N/A
Low cost
Low halogen
Not tolerance sensitive
7300
N/A
Low cost
Low friction
Not tolerance sensitive
525
G-200
Low cost
Low halogen
Not tolerance sensitive
526
N/A
Low cost
Low friction
Not tolerance sensitive
5000
#98
Graphite Tape
High Temp BA
Low cost
Low halogen
Not tolerance sensitive
7000
1400
GRAPH-LOCK
Tape
Graphite Tape
Wire Reinforced
Low cost
Low halogen
Not tolerance sensitive
7300-I
1601
1398
1399
Graphite Tape
Wire Reinforced
PTFE BA/Lube
Low cost
Low friction
Not tolerance sensitive
7301-I
1600
1303-FEP
4-18
4.5
Summary
Valve packing has evolved over the years from braided asbestos
packing rings, to non-asbestos braid rings, to die-formed flexible
graphite rings with braid ring backup, to fully engineered die-formed
flexible graphite packing systems.
The best approach for most nuclear plant valves is to use die-formed
flexible graphite packing rings with appropriate (braided or composite)
anti-extrusion rings.
A packing system can contain many parts including braid rings, dieformed flexible graphite rings, anti-extrusion rings, spacers, bushings,
lantern rings, washers, junk rings and live loading. Selection of the
best assembly of parts for given applications is described in Section 6
of this report.
4-19
28
This section describes the main causes of leaks from valve packing and the
measures that can be taken to mitigate these causes.
A common misconception is that the majority of packing leaks are caused
by the material simply wearing out. This often leads to the conclusion
that valve packing leakage is inevitable. However, experience with wellexecuted valve packing programs has demonstrated that properly packed
valves do not leak and do not require frequent retorquing or repacking. It
is, therefore, important for engineers and maintenance technicians to
search for and to resolve the actual root causes of leaks rather than just to
repack leaking valves using previously used methods.
29
5.1
The gland stress must be high enough to create and maintain the seal
under operating conditions. The required gland stress is described in
Section 7. For most nuclear plant applications using die-formed flexible
graphite packing rings, the gland preload stress should be 3,0004,000 psi
(2128 MPa) to ensure proper initial consolidation and to provide margin
for the inevitable loss in preload over time due to service-induced
consolidation and wear.
Gland preload is typically applied by torquing gland nuts. However, the
amount of load on the gland produced by the torque depends on factors
including the applied torque, friction between the nut and gland stud
threads, friction between the nut and follower, surface condition of the
threads and the nut/follower interface, and the type of lubricant used. In
this regard, gland bolting behaves essentially the same as flange bolting.
Work in EPRI TR-111472, Assembling Bolted Connections Using SpiralWound Gaskets [11], another document in the Sealing Technology & Plant
Leakage Reduction Series, shows that the actual bolt load can be as little
as one-third of the desired load for a given torque depending on these
factors. The actual load is rarely higher than the desired load.
The keys to achieving the desired gland preload stress are typically to
have:
Clean studs/nuts
Good lubrication at the threads and between the nut and follower
30
5.2
Packing Consolidation
31
Figure 5-1
Consolidation of Die-Formed Flexible Graphite Packing [7]
If the packing were frictionless, a gland stress of 4,000 psi (28 MPa)
would be sufficient to compress most packing materials to the desired
density. However, as shown in Figure 5-2, friction between the packing,
stem, and stuffing box can result in parts of the packing not being properly
5-2
32
33
compressed. As shown in this figure, the top of the packing that is loaded
by the gland is subjected to the desired compressive stress while the
bottom of the packing has a lower compressive stress due to friction at the
stem and stuffing box wall. During operation, thermal cycling and valve
stroking will result in the decrease of compressive stress at the initially
higher stress locations, and the increase of compressive stress at the
initially lower stress locations. With time, the packing will shake down
to an equilibrium stress that is less than the initial target compressive
stress. It is said that the packing has consolidated in service and the
resultant lower gland stresses may result in leakage.
Figure 5-2
Packing Consolidation [7]
High-friction packing
Rough stem and stuffing boxes surfaces that contribute to high friction
Use lower-friction coefficient packing materials (PTFE-filled, antiextrusion braid rings in lieu of unfilled graphite anti-extrusion braid
rings where practical).
34
Ensure that the valve stem and stuffing box finish are smooth so that
unnecessary friction is not created.
Ensure that the bolting materials are in good condition and lubricated,
and, preferably, include a hardened steel washer between the nut and
follower so that the specified torque results in the desired gland
preload force.
Repeatedly stroke the valve stem and retorque the gland nuts until
there is no further gland nut rotation for the specified final torque. At
this point, the packing should be uniformly compressed and there
should be little relaxation of gland load during service. Figure 5-3
illustrates the beneficial effect of initial consolidation. This can require
many cycles of stroking and torquing the gland nuts.
Figure 5-3
Effect of Consolidation on Gland Load [7]
Finally, for problem valves, valves that are in cyclic service, or critical
valves that cannot be retorqued during plant operation, live loading
(typically Belleville washers) can be used to maintain the desired
compressive load on the packing and thereby compensate for serviceinduced consolidation or wear.
5-4
35
36
5.3
37
38
39
The MSS Standard Practices (SP) 120, Flexible Graphite Packing System
for Rising Stem Steel Valves (Design Requirements) [12], provides
suggested tolerances for each of the main parts that affect performance of
valve packing. Figures 5-4 through 5-6 show suggested clearances and
tolerances for the stuffing box, stem, and gland. If problems are
encountered, the clearances and tolerances should be reviewed. Solutions
include replacing out-of-spec parts or using an alternative packing system
that better accommodates the as-found conditions. Packing suppliers
should be consulted for the best solution for difficult or important cases.
Figure 5-4
Running Tolerances and Clearances (MSS SP-120) [12]
5-5
Figure 5-5
Stuffing Box Tolerances (MSS SP-120) [12]
Figure 5-6
Stem Tolerances (MSS SP-120) [12]
5.4
40
The stem surface must be smooth to create a good seal, to allow for proper
initial packing consolidation, and to minimize packing wear and friction.
Guidance regarding stem condition includes:
MSS SP-120 specifies that the stem surface should have a finish of 32
inch (0.81 meter) root mean square (RMS) or better and should be
free of scratches, pits, or voids deeper than 0.002 in. (0.051 mm)
5-6
42
5.5
43
5-7
Figure 5-7
Stem Corrosion Test Fixture (MSS SP-121) [14]
Corrosion has been a significant concern with valves and valve parts
stored in warehouses where there is moisture, or in locations where
packing is wet due to water trapped during valve hydrostatic testing. Some
utilities have avoided these conditions by removing the packing during
storage. Installing new packing when the valve is placed in service will
ensure that the new valve is packed to the latest plant standards.
44
5.6
Stem Misalignment
Contact between the stem and gland can cause friction, wear, and
degradation of the stem surface finish
Lateral loads on the packing can potentially cause corrosion, and under
worst case conditions, open up a gap between the stem and packing
Wedging of the gland on the stem so that the gland force is not applied
to the packing (this is often a problem for valves with short glands)
5-8
Figure 5-8
Typical Effects of Stem Misalignment [10]
45
In most cases, the solution to misalignment is to ensure that the parts (for
example, stuffing box, stem, and gland) meet previously noted
dimensional tolerances. It can be desirable to include graphite bushings at
the top and bottom of the packing set as illustrated in Figure 5-9. The
bushings act to keep the stem centered in the packing and to take side
loads.
5-9
Figure 5-9
Use of Bushings to Mitigate Stem Misalignment
46
47
5.7
5-10
Figure 5-10
Effect of Stem Thermal Taper on Packing Consolidation
48
Provide live loading (Belleville springs) that acts to keep the packing
loaded at all times.
5.8
Product Misapplication
49
50
5-12
Figure 5-11
Decomposition Rate of PTFE at Elevated Temperature [13]
5.9
Aging
Packing can age under operating conditions and typically results in the
loss of blocking agents or lubricants that reduce the sealability and
increase friction. Aging can also result in hardening of packing so that it
no longer follows operationally induced displacements. The main issue is
whether the life achieved is acceptable or if changes should be made to
use materials that have a potentially improved life.
Pure graphite materials, such as die-formed flexible graphite and braid
rings without fillers, are not susceptible to aging mechanisms that affect
many other materials. Therefore, pure graphite products should be selected
for applications where long life is desired.
51
When braid rings are used for sealing or anti-extrusion rings, include
small amounts of PTFE in the packing to reduce friction where
technically acceptable. Small amounts of PTFE can be dispersed in the
packing material, or thin PTFE washers can be provided between
packing rings. In both cases, the PTFE will tend to flow and provide
lubricity at the stem to packing interface.
Ensure that the valve stem is smooth and free of corrosion products. A
rough and corroded surface will increase friction and accelerate
packing wear.
5.11 Summary
There are many causes of valve packing leaks. Key factors include:
Packing consolidation
Stem misalignment
Product misapplication
Aging
5-14
5-15
6.1
The ideal packing would have high leak-tight integrity, low friction, ease
of installation, no need for tight tolerances, minimal inventory
requirements, and low cost. Work in the EPRI sealing technology program
suggests that this objective can be achieved using a relatively simple
building block approach.
For cases where even lower friction is required, the plain braided
graphite end rings can be replaced with lubricated graphite braid rings
or with composite rings.
6-1
6.2
=
=
=
=
=
=
A typical five-ring set with three die-formed graphite rings and braided
graphite end rings would be designated:
top
bottom
X000X
6.3
55
A graphite spacer below and a graphite bushing above the packing rings
minimize the amount of material to be consolidated, provide for alignment
of the stem in the stuffing box, take side loads, and minimize the potential
for wear of the stem against metal parts. Finally, a flexible graphite washer
below the graphite spacer minimizes the potential for cracking of the
bottom edge of the spacer. Hardened steel washers should be used
between the gland nuts and follower in all cases.
For applications where friction must be minimized within the standard
package, half-height rectangular rings can be used, or the number of dieformed flexible graphite rings can be reduced to two or, in some cases,
even one.
56
57
6.4
6.5
Inventory Optimization
If complete packing sets are stocked for each different configuration used
in the plant, then a large number of different sets must be procured and
stored.
An alternative approach is to limit the complete sets to fully-engineered
packages with composite anti-extrusion rings and possibly live loading for
the most critical or problem valves. For the balance of the valves, dieformed flexible graphite rings, plain braided graphite end rings, lowfriction braid graphite end rings, graphite bushings/spacers, flexible
graphite washers, and Belleville springs can be procured and stocked in
standard sizes and the packages assembled from the parts as needed. The
assembled parts can be packaged in a box or tube and issued to the craft
performing the work. This approach would protect the parts prior to
assembly and reduce the probability that incorrect parts will be used.
Assistance in inventory optimization can be obtained from packing
suppliers.
6-4
59
6.6
Products offered
Training programs
6.7
Summary
6-5
6-6
GLAND PRELOAD
61
7.1
The required gland force is the gland preload stress times the gland cross
sectional area:
Fg =
Pg Do Di
2
where
Fg
Pg
Do
Di
=
=
=
=
7-1
Fg = 0.7854 Pg Do 2 Di 2
7.2
In most cases, the gland loads are applied by torquing the nuts on the
gland studs to the level necessary to achieve the desired preload force.
There are three main factors involved in achieving preload by torquing: 1)
determining the appropriate torque, 2) ensuring that the material
conditions will result in achieving the desired preload when the specified
torque is applied, and 3) providing for packing consolidation.
7.2.1 Determining Appropriate Torque
63
KDFg
12 N
where
Tp
K
D
Fg
N
=
=
=
=
=
Combining these two equations gives the following expression for the
required torque as a function of the desired gland stress:
Tp =
KD
0.7854 Pg Do 2 Di 2
12 N
)]
For the case of studs and nuts in good condition, and well lubricated with
a high-pressure nickel- or graphite-based thread lubricant on the threads
and between the nut and follower, the nut factor (K) can be taken as 0.16.3
3
7-2
64
T p = 0.00524 Pg Do 2 Di 2 D
65
7-3
Figure 7-1
Galling on Follower Caused by Lack of Hardened Steel Washers
[10]
Figure 7-2
Galling of Soft Steel Washers Provided by Valve Supplier [10]
7-4
Lubrication
Lubrication should be applied to the stud threads and also to the surface
between the bottom of the nut and the follower or hardened steel washer.
Further details regarding the effect of these factors on the load-torque
relationship are provided in EPRI TR-111472, Assembling Bolted
Connections Using Spiral-Wound Gaskets [11].
7.2.3 Providing for Consolidation
Packing consolidation can reduce the gland stud load. It is, therefore,
important to repeatedly stroke the valve stem and torque the nuts until
there is no further nut rotation at the final specified torque. Each stroke
should be at least equal to the height of the packing.
To ensure that this important step is not missed, many plants include a
minimum number of stroke and tightening cycles. At least approximately
five cycles is suggested for typical braided packing sets. Deep packing
sets, double-packed valves with lantern rings and leakoff ports, and small
valves with large packing cross sections typically increase the difficulty of
achieving consolidation and may require more stroking and torquing
cycles. The best approach for these cases is often to consolidate small
groups of rings as they are installed.
66
7.3
Stem Friction
67
Number of packing rings (short packing depth vs. large packing depth)
Applied gland preload force (low preload force/stress vs. high preload
force/stress)
Type of motion (that is, rotational, rising stem, and rising and rotating
stem)
[Sg Y] [ Ds H] L
7-5
where
Fs
Sg
Y
Ds
H
L
68
=
=
=
=
=
=
=
The first term in the equation () is the friction coefficient between the
packing and stem; the second term (Sg Y) is the radial packing stress on the
stem; the third term ( Ds H) is the surface area of the packing in contact
with the stem; and the last term (L) is a measure of how well the load is
applied to and maintained on the packing during service.
The friction coefficient typically varies between 0.05 and 0.15 depending
on the packing material, stem material, stem surface finish, and whether
the friction is static or dynamic. The friction coefficient can be obtained
from the packing supplier or by test under actual plant conditions.
The ratio of the radial to axial stress in the packing (Y) is a function of the
packing material, number of rings, stem and stuffing box surface finish,
and shape of the packing (square vs. wedge). Reported values range from
0.50 to 0.85.
The load factor (L) is primarily a function of how well the torque is
converted into preload force and how well the gland load is maintained by
either live loading or periodic retorquing. Reported values range from 0.75
to 1.00. However, the preload can be as little as one-third of the desired
preload if the threads are not in good condition, there is poor lubrication,
or there is galling between the nut and follower.
69
7-6
7.4
70
71
Live Loading
Figure 7-3
Live Loading Using Belleville Washers
7-7
Figure 7-4
Alternative Live Loading Configurations [7]
72
Figure 7-5 shows how Belleville washers act to maintain the load as the
packing consolidates or wears. With live loading, significantly more inservice consolidation can occur before the axial packing compressive
stress drops below the level at which leakage will occur.
7-8
Figure 7-5
Effect of Live Loading on Valve Gland Stress [7]
Many users have believed that live loading is a cure-all that will solve
most packing leakage problems. However, live loading should only be
considered as an additional level of assurance after other precautions have
been followed. The sole purpose of live loading should be to
accommodate small amounts of service-induced consolidation.
73
One utility that has been an industry leader in developing a sound valve
packing program has applied live loading to approximately 150 out of the
total 12,000 packed valves at their two plants. This represents
approximately 1.25% of the total packed valve inventory.
7-9
74
75
76
Vendors can provide recommendations for live load spring stacks for
various applications. EPRI NP-5697, Valve Packing Improvements [7],
also provides guidance for sizing spring packs. Key points from the EPRI
recommendations are as follows:
The ideal spring stack should have four to eight washers in order to
provide reasonable stroke, although success in some cases has been
achieved with as few as two Belleville washers.
The spring stack must be designed so that the spring washers will not
hang up on the stud threads. It may be necessary to use guides as
shown in Figure 7-6 to prevent interference.
Figure 7-6
Live Loading Spring Packs [7]
7-10
77
7.5
Diagnostics
A review of stem friction obtained from more than 200 MOV diagnostic
tests at one plant were compared to the predicted stem friction. In all cases
where the measured stem frictions were significantly lower than the
calculated value, packing leaks developed. A review of additional testing
and data has found that the correlation between measured and predicted
stem friction continues to be accurate, generally within 1020%. Some
sites now require that valve packing be retorqued when the measured stem
friction drops below approximately 70% of the predicted valve. This drop
in friction is generally indicative of a loss of gland preload stress.
7-11
If during MOV or AOV diagnostic testing, stem frictions are found below
the calculated values, the packing is either torqued to increase running
loads within the acceptable range or a detailed specific review is
performed. This review should consider:
System pressure
Until the accuracy of the stem friction formula had been confirmed, the
only measure of proper packing load was inferred from the torque value
applied to the packing studs. As has been noted in EPRIs bolt torquing
research, numerous factors can affect the actual load developed by the
bolts so that the actual applied load can be as little as one-third of the
desired load. Measurement of stem friction during the MOV or AOV
testing is a more direct measurement of the actual load on the packing.
78
7.6
Gland Design
Poor gland design can result in the applied preload force not meeting
expectations. The main causes of these losses are friction caused by
cocking of the gland and excessively tight clearances. The causes and
several possible solutions are described in Sections 7.6.1 through 7.6.5.
7.6.1 Gland and Follower Design One- vs. Two-Piece
Valve manufacturers have not standardized on the design parameters of
the gland and follower. Some vendors use a one-piece cast gland and
follower but most provide a two-piece gland and follower.
The apparent advantage of the two-piece gland and follower is that it
appears to be self-aligning, so that if the nut on one side is tightened more
than on the other side, the follower will rock and the gland will be
unaffected. Although this design does accommodate some mismatch in
bolt-to-bolt tightening, it provides the mechanical technician with no
practical means to straighten cocked glands, which is a major cause of
stem damage. With a one-piece design as shown in Figure 7-7, by
tightening on one side and loosening on the other, a slightly cocked gland
can be straightened.
7-12
Figure 7-7
Potential Gland Follower Improvements [10]
Potential for the gland cocking and scoring the valve stem
Short followers such as shown in Figure 7-1 have very little stuffing box
penetration and tend to cock more easily and score valve stems. A longer
gland will perform better provided that it can be accommodated by the
valve yoke area. For the case of short glands, it is also difficult to provide
for packing consolidation and to ensure that there is adequate take-up for
future valve retorquing.
7.6.3 Gland-to-Stuffing Box Clearance
The clearance between the gland and the stuffing box is critical. If the
clearance is too small, a little corrosion buildup or dirt can cause the gland
to stick in the stuffing box and not transmit the gland nut force to the
packing. If the clearance is too large, the gland can cock, score the valve
7-13
7.7
Summary
7-14
7-15
80
81
82
83
8.1
84
8-1
Figure 8-1
Valve Packing Performance Demonstration Unit (VPDU)
8-2
Figure 8-2
VPDU Packing Assembly and Valve Stems
85
The VPDU is designed to accept any packing that is intended for a 0.75in. (1.91-cm) stem and 1.25-in. (3.18-cm) stuffing box. The VPDU
includes three interchangeable stems as shown in Figure 8-2:
86
87
88
The VPDU can be used to perform experiments that illustrate the effects
of key parameters on leakage, consolidation, friction, and wear. These
include:
Packing length
Packing preload
Live loading
Stem material
8.2
The first use of the VPDU was at the August 2000 Fluid Sealing
Technology Program Working Group meeting. Attendees at this meeting
participated in performing tests on four different packing material
configurations with several different levels of consolidation for one of the
configurations. The procedure used for each test was as follows:
89
The packing was loaded to an axial gland stress of 3,000 psi (21 MPa)
by torquing the gland nuts to the specified value.
The packing chamber was pressurized to 100 psi (0.7 MPa) with
nitrogen and the pressure decay after three minutes was recorded. The
pressure drop provides an indication of the initial packing tightness.
The stem was stroked in and out through a 1-in. (2.54-cm) stroke
length 20 times over an additional three-minute period.
8-4
90
The stem friction force was measured in both directions during the
stroking.
The pressure in the chamber and the pressure drop from the initial 100
psi (0.7 MPa) after 20 strokes were measured.
Results of the experiments are reported in Tables 8-1 and 8-2. These tests
showed the following:
91
92
The tightest seal was achieved for the case involving a single dieformed graphite seal ring. This suggests that at least one die-formed
graphite ring can significantly reduce leakage as compared to using
only braid rings.
8-5
ZZZZ
ZZZZ
ZZZZ
X000
CC00
Z0Z
Initial Consolidation
No Consolidation
5 Strokes
5 Strokes + Live
5 Strokes
5 Strokes
5 Strokes
Force
(lb)
Pressure
(psi)
8-6
Force
(lb)
Pressure
(psi)
Force
(lb)
Pressure
(psi)
1780
1830
1840
1900
1970
Force
(lb)
Pressure
(psi)
------1460
1700
Force
(lb)
Pressure
(psi)
1800
1970
2020
2090
2130
Force
(lb)
Pressure
(psi)
1670
2110
2270
2340
2380
1900
100
95
1910
99
94
2130
98
94
1690
98
97
2130
99
97
2340
99
98
1460
260/-230
89
245
1790
360/-300
91
325
1740
360/-310
92
335
1580
425/-375
96
400
2060
300/-250
97
275
2160
375/-325
98
350
11
Consolidation
Average
Friction
Force (lb)
ZZZZZ
None
+/-245
11
ZZZZZ
5 Strokes
+/-325
ZZZZZ
+/-335
X000X
5 Strokes
+/-400
CC00C
5 Strokes
+/-275
Z0Z
5 Strokes
+/-350
8.3
Summary
8-7
This section describes the steps of installing valve packing for typical
applications. In some cases, these typical steps may be superseded by
vendor-specific requirements.
9.1
94
95
96
The main steps in valve packing are described in Sections 9.1.1 through
9.1.8.
9.1.1 Remove Old Packing
Prior to disassembling packing, the as-found conditions should be
assessed. This should include inspections for evidence of current or prior
packing leakage and boric acid corrosion of any low-alloy steel parts in
PWR plants.
The gland nuts and gland studs should be checked for signs of galling and
poor lubrication.
After removing the gland nuts, the gland can be pulled from the stuffing
box, ensuring that it does not cock as it is being removed. After removal it
is sometimes useful to tie the gland out of the way so that it does not
interfere with repacking.
The old packing can be removed using standard packing hooks or pullers
or specialized equipment such as hydraulic tools. Care should be exercised
to not damage the stem or stuffing box during removal. The packing
should be inspected as it is being removed to ensure that the proper
materials had been used when last packed. If a lantern ring or graphite
bushing has been used, these parts should also be removed using packing
removal tools if the parts have been tapped. If the parts have not been
tapped, it may be necessary to use hydraulic packing removal tools or
shim stock in combination with stem movements to aid in removal. The
final step should be to confirm that all of the old packing has been
removed. This can be accomplished using tools and mirrors.
9-1
97
98
9-2
location. In many cases, valve vendors did not include hardened steel
washers.
In some cases, studs will have been permanently stretched due to
excessive preload. Stretching a stud increases the pitch between the
threads, leads to internal interference between the stud and nut threads,
and results in a lower load for the same applied torque. Thread pitch can
be easily checked by running the nut down the portion of the threads that
will be engaged during assembly. If the nut runs freely, the threads have
not been excessively stretched. If the nut binds, it is possible that the stud
has been permanently stretched and should be replaced.
Finally, the threads and the interface between the nut and follower should
be lubricated with an approved thread lubricant.
99
100
101
9-3
102
103
All braid ring packing sets (braid rings require more consolidation than
die-formed graphite or composite rings)
Double-packed valves with lantern rings and leakoff ports (the lower
sets of packing should be installed and consolidated before installing
and consolidating the upper sets of packing)
9-4
104
9-5
9.2
105
Figure 9-1 shows many of the key steps and precautions in valve packing.
Figure 9-1
Summary of Key Valve Packing Points [10]
9.3
9-6
can then be repacked prior to the next outage. This approach will
minimize radiation exposure and foreign material exclusion concerns.
Use tools to engage drilled and tapped holes in the lantern rings
Shim the lantern ring to the stem and then stroke the stem to free
the ring
107
Remove the leakoff port and attempt to push and pry the lantern
ring through the port
108
While installing packing sets that have split bushings, use thin flexible
graphite washers to hold packing sets together.
For valves with short glands, the glands can sometimes cock, thereby
scraping the stem. Possible solutions in these cases are to add bronze
bushings at the top and bottom of the gland and to add a chamfer on
109
110
111
9-7
Figure 9-2
Use of Shims to Ensure Gland Alignment [10]
9.4
Summary
Valve inspections
Preparation of bolting
Installation of packing
Consolidation of packing
Periodic retorquing
9-8
10
113
114
An average valve repacking time of less than five man-hours per valve
Identify the best packing products for the range of plant applications
taking into account plant-specific preferences and requirements
Provide training
116
117
Key valve dimensions (for example, stuffing box, stem, and gland)
Valve operating experience (that is, leaks, leak rates, and repairs)
Retorquing experience
The database entry could include information such as a note that next time
the valve is repacked the stem, gland, and gland studs/nuts should be
replaced, or that if the packing leaks, the torque should be increased to a
specified higher value.
The selected packing supplier should be able to assist in creating and
populating the database.
118
Problem valves
10-3
Special program valves (that is, local leak rate test boundary, 89-10
MOVs, and AOVs)
The first three of these groups are likely to have the greatest economic
impact because increased integrity for these valves will reduce the risk of
expensive repairs and possible lost production.
Other factors in the prioritization could include replacing packing when
the valve is being serviced for other purposes, replacing packing in all
valves of one type, and replacing packing in all valves in one system or
area of the plant. These factors will result in improved efficiency by
working one type of valve, or valves, in close proximity.
The selected packing supplier should be able to assist in prioritization
efforts.
119
10-4
120
121
122
123
10-5
10-6
Accessible High
Pressure/Temperature
BOP Valves
Accessible Low
Pressure/Temperature
BOP Valves
X
X
Comments
Every Outage
Every Other
Outage
Every 34
Outages
Preventive Retorque
10 Year
Intervals
Leak During
Operation
Leak During
Outage
Valve Type/Application
Retorque as specified by
engineering
Manual Valves
MOVs
Manual Valves
MOVs
Manual Valves
MOVs
Notes:
- Leak checks should be performed at the start of each outage at the highest possible system pressure
- Leak checks should be performed at the end of each outage with emphasis on valves that have been repaired
- Recommendations are for a plant where few leaks are expected due to following sound practices
- Recommendations are intended to maintain leak tight integrity, not to prevent leaks from large numbers of poorly packed valves
- Results of inspections and retorquing should be recorded on valve datasheets to identify the need for future maintenance and the need for retorque on similar valves.
10-7
124
10.11 Summary
10-8
11
OVERVIEW
Pure graphite packing sets with die-formed flexible graphite seal rings
and plain braided end rings (X000X) should form the core of a plants
valve packing program. The die-formed flexible graphite rings provide
excellent sealing, and the absence of lubricants and blocking materials
in the plain braid rings minimizes the potential for service-induced
consolidation.
11-1
11-2
12
REFERENCES
1. Valve Application, Maintenance, and Repair Guide. EPRI, Palo Alto,
CA: 1999. TR-105852-V1.
2. Boric Acid Corrosion Guidebook. EPRI, Palo Alto, CA: 1995. TR104748.
3. Boric Acid Corrosion Guidebook, Revision 1. EPRI, Palo Alto, CA:
2001. 1000975.
4. U.S. Nuclear Regulatory Commission. Assessment of Pressurized
Water Reactor Primary System Leaks. NUREG/CR-6582, 1997.
5. Valve Stem Packing Improvement Study. EPRI, Palo Alto, CA: 1982.
NP-2560.
6. Valve Stem Packing Improvements. EPRI, Palo Alto, CA: 1986. NP2455.
7. Valve Packing Improvements. EPRI, Palo Alto, CA: 1988. NP-5697.
8. Grafoil Brand Flexible Graphite Engineering Design Manual, Volume
1, Sheet and Laminate Products. Union Carbide Corporation, 1987.
9. Radiation Data for Design and Qualification of Nuclear Plant
Equipment. EPRI, Palo Alto, CA: 1985. NP-4172SP.
10. Photographs and figures provided by K. Hart of PPL Susquehanna,
LLC.
11. Assembling Bolted Connections Using Spiral-Wound Gaskets. EPRI,
Palo Alto, CA: 1999. TR-111472.
12. Manufacturers Standardization Society of the Valve and Fittings
Industry, Inc. Flexible Graphite Packing System for Rising Stem Steel
Valves (Design Requirements). SP-120, 1997.
13. Control Valve Packing Systems. Technical Monograph 38. Fisher
Controls International, Inc., 1992.
12-1
12-2
TRAINING SLIDES
The viewgraphs are to be used for classroom instruction. They are linked to the full report text
for further information.
A-1
EPRI
Plant Leak Reduction Training
Objective
! The objective is to help nuclear plants reduce the number and severity of
leaks from valve packing
! This objective will be accomplished by providing a better understanding
of the key factors that contribute to valve packing performance:
Contents
! Valve Packing Concepts
! Industry Experience With Valve Packing Leaks
! Valve Packing Products
! Causes of Valve Packing Failures
! Selecting Packing Configurations and Products
! Gland Preload
! Experiments Using VPDU
! Valve Packing Procedures and Tips
! Valve Packing Improvement Programs
Bellows-type seals
Diaphragm-type seals
O-rings
Packing rings
V (Chevron) packing
To tal
WO's
To tal
WO's
Plant A
Plant B
Ave rag e
WO's
Pe rc e nt
Ave rag e WO
Man-Ho urs fo r
Plant B
pe r Ye ar
pe r Unit
Fla nge d J oints
a nd Ga s ke ts
850
189
69
23%
32
P ipe a nd Tube
Fittings
500
359
57
19%
31
Va lve P a cking
663
563
82
27%
16
S e a ls
302
220
35
12%
24
Othe r
263
620
59
20%
69
Tota l
2,578
1,951
302
100%
38*
! Bushing (optional):
! Anti-extrusion rings:
! Spacers:
Minimizes consolidation
Reduces friction
Figures from
EPRI NP-5697
Alternative Products
Positive Features
Die-Formed Graphite
Packing Rings
Washers
Composite Ring
Graphite/Resin
Lowest friction
Low consolidation
Negative Features
Cost and increased inventory
Tolerance sensitive
Increased installation effort
Cost and increased inventory
Tolerance sensitive
Increased installation effort
Consolidation
Increased friction
Gland stress limited to 4-6 ksi
Cost and increased inventory
Tolerance sensitive
Increased installation effort
High cost and increased inventory
Tolerance sensitive
Increased installation effort
Increased cost and inventory
Increased installation effort
Bushings tolerance sensitive
Extra cost and inventory
Increased installation effort
Argo
Chesterton
Garlock
6300 J
5200
5300
GRAPH-LOCK
Rings
5800
9000-EVSP
includes various
end ring types
One
One-CI
G-700
5600
GRAPH-LOCK
Rings
524
6000
5005 std density
5010 high density
6200 N
N/A
5100
4525
N/A
Alternative Products
Positive Features
Negative Features
Argo
Chesterton
Garlock
N/A
N/A
Braided Packing
Rings
Asbestos Yarn
Graphite/Mica Filler
Health hazard
Hardening in service
N/A
Low cost
Low halogen
Not tolerance sensitive
Low cost
Low friction
Not tolerance sensitive
Low cost
Low halogen
Not tolerance sensitive
Low cost
Low friction
Not tolerance sensitive
Low cost
Low halogen
Not tolerance sensitive
Low cost
Low halogen
Not tolerance sensitive
Low cost
Low friction
Not tolerance sensitive
7300
N/A
525
G-200
526
N/A
5000
#98
7000
1400
GRAPH-LOCK
Tape
7300-I
1601
1398
1399
7301-I
1600
1303-FEP
! The axial load in the packing will become more uniform with time:
This will reduce the maximum radial load that produces the seal
Stem to gland
Gland to stuffing box
Stem to bonnet
Anti-extrusion ring to stem and stuffing box
Spacer to stem and stuffing box
Top bushing to stem and stuffing box (if used)
! Binding can cause high friction and wear between metal parts
! Excessive gaps can cause:
32 Ra (microinch) or better
Free of scratches, pits, or voids deeper than 0.002 inches
Lateral loads on the packing that can potentially open up a gap between
the stem and the packing
Contact between the stem and gland that can cause wear and degrade the
stem surface finish
Wedging of the gland on the stem so that the gland load is not applied to
the packing. This is often a problem for valves with short glands
However, there should seldom be a need to exceed 4,000 psi gland stress
bottom
X000X
graphite spacers
graphite bushings
Not ideal for cyclic duty applications due to increased stem wear
! Replace plain braided graphite end rings with composite end rings
(BC000CSW):
Composite end rings are very stiff and live loading may be necessary to compensate for
lost compliance
All-braid packing has greater potential for leakage than packing including dieformed flexible graphite rings
There is increased potential for not achieving the desired initial consolidation
and for increased service-induced consolidation
All-braid packing is likely to require more frequent retorquing and repacking
than systems with die-formed flexible graphite
All-braid packing may be easier for less skilled maintenance technicians to
install
Gland Preload
Gland Preload
Required Gland Preload Stress
! EPRI NP-5697 suggests that most packing should be preloaded to:
! Field experience has shown that gland stresses of 2,000 psi may be too
low to ensure adequate consolidation and to provide margin for:
Gland Preload
Required Gland Force
! The required gland force is the gland pressure times the gland cross section
area:
where
Fg = Pg [Do2 - Di2] / 4
Fg
Pg
Do
Di
=
=
=
=
Gland Preload
Required Gland Nut Torque
! The required torque for the case where 1) the studs are in good condition, 2)
the nut-to-follower interface is smooth, flat, and hard, and 3) lubrication is
applied to the threads and to the nut-to-follower interface, is given by the "nut
factor" equation:
Tp = [Fg/N] K D / 12
where
Gland Preload
Required Gland Nut Torque (cont.)
! Combining the equations for preload force and torque, the following
expression is obtained for the typical case where there are two studs:
Tp = 0.00524 Pg [Do2 - Di2] D
! As previously noted, this depends on:
! It also depends on the gland not cocking and creating high friction
against the valve stem
Gland Preload
Required Gland Nut Torque (cont.)
! Significant preload can be lost by
friction (galling) at the interface
between the gland nuts and
follower:
Gland Preload
Stem Friction
! Historically, stem friction was estimated as 1,000 lb per inch of valve
stem diameter
! However, this is an oversimplification, because valve stem friction is
a function of several variables including:
Gland Preload
Packing Friction (cont.)
! Packing suppliers use variations of the following basic model to
calculate stem friction:
Fs = [Sg Y] [ Ds H] L
Load factor
Surface area of packing on stem
Radial packing stress on stem
where
Fs =
=
Sg =
Y =
Ds =
H =
L =
Friction coefficient
Gland Preload
Packing Friction (cont.)
! The friction coefficient () typically varies between 0.05 and 0.15
depending upon the packing material, stem surface finish, and whether
the friction is static or dynamic
! The ratio of radial to axial stress in the packing (Y) is a function of the
packing material, number of rings, stem and stuffing box surface
finishes, and shape of packing (square vs. wedge). Reported numbers
range from 0.50 to 0.85
! The load factor (L) is typically in the range of 0.75 to 1.0, and a
function of:
How well the preload torque on the nuts is converted into preload stress on the
packing (with poor conditions the load can be 1/3 of desired load)
How well the gland load is maintained by either live loading or periodic retorquing
Gland Preload
Packing Friction (cont.)
! The stem friction equation illustrates the main principles to be
applied in reducing stem friction for a given valve design. These
are:
However, materials that achieve low friction by use of lubricants have the potential for more
service-induced consolidation due to loss of the lubricant
Gland Preload
Live Loading
! Live loading consists of adding some type
of spring between the gland nuts and
follower to maintain a load on the packing:
Gland Preload
Other Live Load Configurations
Gland Preload
Live Loading (cont.)
! Live loaded valves can
accommodate much
more consolidation
before a leak occurs
Gland Preload
When to Apply Live Loading
! All valves can be live loaded
! An alternative approach is to live load valves based on cause.
Typical candidates for live loading include:
Gland Preload
Sizing Live Load Packages
! Live load packages can be purchased from the packing supplier or
assembled by the utility based on data from EPRI and the Belleville
washer suppliers
! EPRI provides guidelines and two flow charts in NP-5697, Valve
Stem Packing Improvements, to design and specify live load
packages:
Figure 5-6 from NP-5697 is a flow diagram for selection of disc springs
Figure 5-7 from NP-5697 is a flow diagram for determining spring stack
specifications
Gland Preload
Sizing Live Load Packages (cont.)
! Simplified sizing of live load packages
Gland Preload
Sizing Live Load Packages (cont.)
! Confirmation that the washers will not hang up on the stud threads is
necessary
! Belleville washers can be installed in guides if necessary
Gland Preload
Diagnostics
! A close correlation has been demonstrated between stem friction
measured in AOV/MOV testing and predicted friction:
Previously there was no method to determine how well the torque on the nuts was
converted to axial load in the packing
Gland Preload
Gland Design
! Two-piece glands were designed to be
self aligning, yet a one-piece gland is
actually easier to keep in alignment:
It is not the purpose of the VPDU to replicate the valve packing qualification tests
specified by MSS SP-121
It is useful to have the capability to readily perform experiments to demonstrate
specific packing-related issues and compare some performance features of
different packing products
! Simulate different stuffing box and stem finishes, and thermal stem
taper
! Impose controlled speed, travel length, and numbers of cycles
! Monitor the following variables:
Program #1
Program #2
Program #3
Program #4
ZZZZ
ZZZZ
ZZZZ
X000
CC00
Z0Z
5 S troke s
5 S troke s + Live
5 S troke s
5 S troke s
5 S troke s
Force
(lb)
P re s s ure
(ps i)
Afte r 20 1 S troke s
S troking Friction
Tota l DP ove r 6 minute s +
20 cycle s (ps i)
P re s s ure
(ps i)
Force
(lb)
P re s s ure
(ps i)
Force
(lb)
P re s s ure
(ps i)
Force
(lb)
P re s s ure
(ps i)
Force
(lb)
P re s s ure
(ps i)
1670
2110
2270
2340
2380
1800
1970
2020
2090
2130
------1460
1700
1780
1830
1840
1900
1970
Force
(lb)
1900
100
95
1910
99
94
2130
98
94
1690
98
97
2130
99
97
2340
99
98
1460
260/-230
89
245
1790
360/-300
91
325
1740
360/-310
92
335
1580
425/-375
96
400
2060
300/-250
97
275
2160
375/-325
98
350
11
Average Friction
Force (lb)
ZZZZZ
None
+/- 245
11
ZZZZZ
5 Strokes
+/- 325
ZZZZZ
+/- 335
X000X
5 Strokes
+/- 400
CC00C
5 Strokes
+/- 275
Z0Z
5 Strokes
+/- 350
Packing
Configuration
The tightest seal was achieved with single die-formed graphite ring
Check that gland nuts are not galled and were properly lubricated
Stuffing box shape (that is, slopes and angles) steam cuts and cleanliness
Stuffing box bottom surface (that is, angle, flat bottomed, and washer)
Fit of gland in stuffing box, damage, binding, and angle at bottom
Stem surface free of nicks, gouges, and corrosion
Stem alignment and change of alignment on backseat
! Clean valve
Confirm dimensions for valves with composite rings, high density end
rings, and bushings
Check that dimensions are compatible with packing to be installed
! Confirm that bushing length allows for at least one ring's worth
of take up after final consolidation
Stroke the valve stem a minimum of five times, retorquing after each stroke
Continue stroking and retorquing until there is no further nut rotation
It is only necessary to stroke the full height of a packing set (the biggest
consolidation occurs due to change in stroke direction)
Additional strokes may be required under several conditions
-
There is also less chance of damaging the stem and packing chamber
Stroke the valve and observe if the lantern ring follows the stem
Shim the lantern ring to the stem to determine if it will follow the stem
when stroked
Remove the leakoff port and attempt to push and pry the lantern ring free
Use a hydraulic packing removal tool to get water pressure underneath the
ring to push it out
If the end of the lantern ring is drilled and tapped, build fixtures to pull on
the ring
The washer is not able to cock on the stem, thereby preventing the split
rings from dropping into the stuffing box
These packages can include all of the necessary parts including die-formed rings,
anti-extrusion rings, bushings, washers, and live load washers (if used)
! The packing vendor should be able to help in creating and populating the
database
Problem valves
Special program valves (LLRT boundary, 89-10 MOVs, AOVs)
Category I valves*
Category II valves*
* EPRI leakage reduction program categories
Category III valves*
! The first three of these groups will have the greatest economic impact
! For most valves, a good approach would be to replace the packing when the
equipment is being serviced for other reasons
! Packing vendors can often provide training materials and on-site training
! Support of technicians is essential. Problems frequently result when the
attitude is:
! Having one or two crews perform most valve repacking work improves
efficiency and encourages team spirit and pride
Leakage can create paths through the packing materials similar to steam cutting of metal
flanges
Once leaks reach a certain point, retorquing may not be effective in stopping the leak
The data should be evaluated and a determination made if corrective action should be
performed
! The retorque schedule in Slide 123 has been used by a BWR plant with a
reported small number of leaks
Every
Outage
Retorque as specified by
engineering
Manual Valves
MOVs
Accessible High
Pressure/Temperature
BOP Valves
Manual Valves
MOVs
Accessible Low
Pressure/Temperature
BOP Valves
Manual Valves
MOVs
Valves Inaccessible
During Operation
Every Other
Outage
Every 3-4
Outages
X
X
10 Year
Intervals
L eak During
Operation
Preventive Retorque
X
X
L eak During
Outage
AOV Drag
Test Results
Valve Type/Application
VOT ES Test
Results
Comments
Notes:
- Leak checks should be performed at the start of each outage at the highest possible system pressure
- Leak checks should be performed at the end of each outage with emphasis on valves that have been repaired
- Recommendations are for a plant where few leaks are expected due to following sound practices
- Recommendations are intended to maintain leak tight integrity, not to prevent leaks from large numbers of poorly packed valves
- Results of inspections and retorquing should be recorded on valve datasheets to identify the need for future maintenance and the need for retorque on similar valves
The attached program was developed by one BWR plant to provide guidance regarding valve
packing surveillance and retorquing.
B-1
Valve Packing
Packing-1
All Types of Valves with Packing
Criticality
Duty Cycle
(Continuous, Standby, Cycles, Loading)
Service Condition
(Temp., Vibration, Dust, Water Chemistry)
Group
Walkdown of
All Areas
Outside of
Containment
During Startup
ID(s)
No
components
attached
Item
Activity
Number
Description
Scope
Basic Information
Operations Rounds
Procedure
Operator Rounds
Operator Rounds are defined in Operations Rounds Procedure. See a detailed list
of inspection of the scope of this inspection in the associated PM Background
Information Document.
DA
D1
M1295-02
M1295-52
Walkdown Areas
Outside
Containment for
Leaks During S/U
Inspect for Leaks and Record Results. Be sure to use proper WALKDOWN MAPS
as attached to the Valve Packing Background Information Document (BID).
For Manual Valves:
If leaks are found:
YR
YR
Since Unit is starting up, every effort must be taken to stop all identified leaks.
Follow guidance in MT-GM-011, and contact Foreperson/Engineering if leak
cannot be stopped, for consideration to increase torque values.
For MOVs and AOVs:
Report leaks to Maintenance Valve Lead Foreperson.
If leak does not stop, contact Argo Rep. or MOV/AOV engineer to increase
torque higher and to evaluate Post Maintenance Testing.
Utilize the Valve Walkdown Datasheet (attached to the Valve Packing BID).
For all actions taken:
Walkdown of
Drywell During
Rx Shutdown
B-2
No
Components
attached
D2
M1297-01
M1297-51
Walkdown Drywell
During Reactor
Shutdown
Checking for Leaks
Measure amount of take-up on the gland and record any valves found within
minimal take-up.
Walkdown the Drywell and identify any leak such as packing, pressure seal and
bolted valve bonnet flanges that may be leaking.
Utilize the Valve Walkdown Datasheet contained in the Valve Packing BID
Measure amount of take-up on the gland and record any valves found with
minimal take-up or signs of leakage.
Valve Packing
Packing-1
All Types of Valves with Packing
Criticality
Duty Cycle
(Continuous, Standby, Cycles, Loading)
Service Condition
(Temp., Vibration, Dust, Water Chemistry)
Group
Walkdown
Whole Unit
other than
containment
During
Shutdown
ID(s)
No
Components
attached
Item
D3
Activity
Number
M1296-01
M1296-51
Description
Walkdown Areas
Outside
Containment
During Shutdown
Checking for Leaks
Scope
Inspect for Leaks and Record Results. Be sure to use proper WALKDOWN MAPS
as attached to the Valve Packing Background Information Document (BID).
For Manual Valves, if leaks are found:
Measure amount of take-up on the gland and record any valves found within
minimal take-up. Record number of flats turned.
Walkdown
Hydro
Walkdown
Hydro
No
Components
attached
No
Components
attached
D4
D5
M1365-01
M1365-51
M1295-01
M1295-51
Measure amount of take-up on the gland and record any valves found within
minimal take-up.
Support Operations
Hydro SE-100-002
and other pressure
tests by Adjusting
MOV and AOV
Packing Leaks
when Required
Inspect for Leaks and Record Results on the Valve Walkdown Datasheet contained
in the Valve Packing BID.
Packing adjustments cannot be made without:
Support Operations
Hydro SE-100-002
and other pressure
tests by Torquing
Manual Valve
Packing and
Flange Leaks when
Required
Inspect for Leaks and Record Results on the Valve Walkdown Datasheet contained
in the Valve Packing BID.
Basic Information
This activity has proven to be successful at
eliminating or significantly minimizing plant
impacts from packing leaks over the past 15
years. This activity is performed every refueling
outage during shutdown while still at pressure to
ensure leaks in all critical areas of the plant are
identified. Walkdown maps provide a plan to
access areas at the highest pressure but lowest
radiation doses, for ALARA. Areas of the plant
that can be taken out of service without impacting
plant performance, such as Radioactive Waste,
are not inspected at this time.
YR
YR
YR
B-3
Valve Packing
Packing-1
All Types of Valves with Packing
Criticality
Duty Cycle
(Continuous, Standby, Cycles, Loading)
Service Condition
(Temp., Vibration, Dust, Water Chemistry)
Group
ID(s)
Item
Activity
Number
Description
Scope
Basic Information
Walkdown
Leak-off
Headers
V0507-01 is
Disc. Med.,
RTPM
No
Components
attached
D6
V0507-01
V0507-51
Walkdown All
Accessible LEAKOFF Headers
YR
Drywell
Manual Valves
2 diff.
Elevation
levels
No
Components
attached
DM
V0503-01
V0503-51
V0503-03
V0503-52
Retorque Valve
Packing for
Manual Valves in
the Drywell
Retorque packing of all manual valves in the half of the Drywell for this RTPM.
Document only the problem valves identified that are:
YR
B-4
Valve Packing
Packing-1
All Types of Valves with Packing
Criticality
Duty Cycle
(Continuous, Standby, Cycles, Loading)
Service Condition
(Temp., Vibration, Dust, Water Chemistry)
Group
New RTs
ID(s)
No
Components
attached
Item
M1
Activity
Number
V0505-05
V0505-55
Description
Retorque Valve
Packing for
Manual Valves
IDd by
Argo/Engineering
Scope
Retorque packing of manual valves that are identified by Argo or Engineer based on
their review of:
Past history.
Failure investigators.
Industry events/experience.
Walkdown results.
Document only the problem valves identified that are:
New RTs
No
Components
attached
M2
V0505-06 A Cell
V0505-07 B Cell
V0505-08 C Cell
V0505-56 A Cell
V0505-57 B Cell
V0505-58 C Cell
Retorque Valve
Packing for
Manual Valves in
Heater Cell
Retorque packing of all manual valves in the Feedwater Heater Cell identified for this
RTPM.
Document only the problem valves identified that are:
Basic Information
This activity provides for an overall routine review
of valve packing performance, and investigation
of any areas that may seem weak. Based on the
age of our packing >1214 years, which is
significantly older then any other industry
program, we must remain vigilant for the first
signs of degradation or excessive wear. If no
unique issues develop, this RT may be
waived/closed based on the other RT that should
cover all known areas.
YR
YR
B-5
Valve Packing
Packing-1
All Types of Valves with Packing
Criticality
Duty Cycle
(Continuous, Standby, Cycles, Loading)
Service Condition
(Temp., Vibration, Dust, Water Chemistry)
Group
ID(s)
Manual Valves
in Main Steam
Drip Legs
Bypass Drip
Legs Steam
Tunnel
No
Components
attached
New RTs
No
Components
attached
Item
M3
M4
Activity
Number
V0505-01
V0505-51
V0505-10
V0505-60
Description
Scope
Basic Information
Retorque Valve
Packing for
Manual Valves in
Main Steam Drip
Legs Bypass Drip
Legs Steam
Tunnel
Retorque packing of manual valves in the Main Steam Bypass Drip legs identified for
this RTPM.
Document only the problem valves identified that are:
YR
Retorque Valve
Packing for
Manual Valves in
Moisture
Separator Drain
Tank
Retorque packing of all manual valves in the Moisture Sep Drain Tank identified for
this RTPM.
Document only the problem valves identified that are:
YR
B-6
Valve Packing
Packing-1
All Types of Valves with Packing
Criticality
Duty Cycle
(Continuous, Standby, Cycles, Loading)
Service Condition
(Temp., Vibration, Dust, Water Chemistry)
Group
New RTs
New RTs
ID(s)
No
Components
attached
No
Components
attached
Item
M6
M7
Activity
Number
V0505-12
NEW
V0505-62
NEW
V0505-14
V0505-64
Description
HPCI Manual
Valve Retorques
RCIC Manual
Retorques
Scope
Retorque packing of manual valves along the HPCI steam line outside containment.
Document only the problem valves identified that are:
Retorque packing of all manual valves along the RCIC steam line outside
containment.
Document only the problem valves identified that are:
Basic Information
This type of activity has proven to be the least
cost approach to maintaining critical manual
valves in Severe environments.
Valves have been retorqued in the past under
PCWOs, but an RT was never created. This new
RT is established with an initial frequency of 6
years, to ensure we proper monitor packing
performance in this area. HPCI is a critical safety
system; out of service time must be minimized
and temperature is monitored in areas and will
cause isolations. Due to the severe environment
of HPCI Main Steam and its pressure pulsations,
this is a prudent RT. It is believed that retorquing
after repack is a progressive frequency and need
not remain fixed, but should increase after each
successive interval. After review during the next
implementation, extension of frequency should be
reviewed; actual results should dictate frequency
change.
YR
YR
B-7
Valve Packing
Packing-1
All Types of Valves with Packing
Criticality
Duty Cycle
(Continuous, Standby, Cycles, Loading)
Service Condition
(Temp., Vibration, Dust, Water Chemistry)
Group
RWCU
Manual
Retorques
ID(s)
No
Components
Attached
Item
MS
Activity
Number
V0505-02
V0505-52
Description
Reactor Water
Cleanup Manual
Valve Retorque
Scope
Basic Information
YR
YR
10
YR
S1
BOP MOV
Main Steam
S2
BOP MOV
Low-Pressure
Steam
See List
Attached to
PMT for RT
Components
See List
Attached to
PMT for RT
Components
S1
S2
See List
Attached to
PMT for RT
Numbers
See List
Attached to
PMT for RT
Numbers
Prior to retorquing the gland stud nut, it should be verified to turn free by
breaking with a box wrench loosen/tighten the nut turn in each
direction, returning the nut to its original position.
Torque the gland follower nuts to the identified torque value on the valve
data sheet.
Inspect for degraded conditions, i.e., loose nuts, signs of leakage (new).
B-8
Valve Packing
Packing-1
All Types of Valves with Packing
Criticality
Duty Cycle
(Continuous, Standby, Cycles, Loading)
Service Condition
(Temp., Vibration, Dust, Water Chemistry)
Group
ID(s)
S5 BOP MOV
Low-Pressure
Steam
See List
Attached to
PMT for
Components
Item
S5
Activity
Number
No RTs
Description
BOP MOV Valve
Packing (Very
Low-Pressure
Steam)
Scope
Retorque the packing per MT-GM-011 on the identified valve(s):
Prior to retorquing the gland stud nut, it should be verified to turn free by breaking
with a box wrench loosen/tighten the nut turn in each direction, returning the nut
to its original position.
Torque the gland follower nuts to the identified torque value on the valve data
sheet.
Inspect for degraded conditions, i.e., loose nuts, signs of leakage (new).
Basic Information
Based on the extreme low pressure of the steam
at these valves, a benefit to a periodic retorque
could not be found for these valves. Adequate
monitoring of these valves is provided by the
extensive and detailed walkdowns performed to
the entire plant.
If repetitive problems begin to occur, this group of
valves should be reevaluated.
Never
Never
8 YR
See List
Attached to
PMT for
Components
S6
No RTs
Prior to retorquing the gland stud nut, it should be verified to turn free by breaking
with a box wrench loosen/tighten the nut turn in each direction, returning the nut
to its original position.
Torque the gland follower nuts to the identified torque value on the valve data
sheet.
Inspect for degraded conditions, i.e., loose nuts, signs of leakage (new).
See List
Attached to
PMT for
Components
S6R
V0506-01
V0506-56
V0501-06 in
Drywell
V0501-56 in
Drywell
V0506-01 Outside
V0506-51 Outside
MOV (NonVOTES)
Retorque Packing
(Hot Water RX
Water Cleanup)
Prior to retorquing the gland stud nut, it should be verified to turn free by breaking
with a box wrench loosen/tighten the nut turn in each direction, returning the nut
to its original position.
Torque the gland follower nuts to the identified torque value on the valve data
sheet.
Inspect for degraded conditions, i.e., loose nuts, signs of leakage (new).
B-9
Valve Packing
Packing-1
All Types of Valves with Packing
Criticality
Duty Cycle
(Continuous, Standby, Cycles, Loading)
Service Condition
(Temp., Vibration, Dust, Water Chemistry)
Group
ID(s)
S9 BOP MOV
(NON VOTES)
(Special App.
Drywell,
Wingslab)
Retorque
See List
Attached to
PMT for
Components
V1 VOTES
Valves with
Critical History
See List
Attached to
PMT for
Components
Item
S9
V1
Activity
Number
Description
Scope
Retorque the packing per MT-GM-011 on the identified valve(s):
V0501-15 deleted
V0501-16
V0501-17
V0501-18
V0501-65 deleted
V0501-66
V0501-67
V0501-68
MOV (NonVOTES)
Retorque Packing
(Special
application
Drywell and
WingSlab)
DELETED
HV1/241F032A/B
since PM
disassembles
every 4 yrs
VOTES packing
Retorque
ALL AOV
Valves
See
Program for
Components
X1
Retorque Valve
Packing for ALL
CRITICAL AOVs
B-10
Basic Information
Because these valves are not VOTES-tested but are located in
critical areas that are not easily accessible (Drywell/WingSlab)
and have Tech Spec Limits for which packing leaks could
cause a Plant Shutdown, these activities were created.
Drywell >3 gpm leak Plant Shutdown
Wingslab High-temperature MSIV Isolation
These valves have never been retorqued on a regular
frequency, but because of the impact discussed above, an
initial frequency of 8 years was selected.
Due to ALARA, the results of this PM should be closely
reviewed to determine if PM frequency extension is advisable,
noting that it is believed that retorquing after repack is a
progressive frequency and need not remain fixed, but should
increase after each successful interval.
8
yr
4
yr
The scope of AOV PMT covers all related valve packing issues.
Originally the packing program drove the AOV diagnostic
testing, but as the AOV program has matured, the testing has
expanded to address additional issues. However, packing
performance monitoring remains a critical task on all AOV RTs.
As-found packing drag is monitored, and packing loads are
adjusted to ensure adequate load is provided via as-left
measurement.
N/
A
6yr
Valve Packing
Packing-1
All Types of Valves with Packing
Criticality
Duty Cycle
(Continuous, Standby, Cycles, Loading)
Service Condition
(Temp., Vibration, Dust, Water Chemistry)
Group
ID(s)
VOTES MOVs
See
Program for
Components
Item
X2
Activity
Number
Description
MOV Retorque
During VOTES
Testing
Scope
Valve packing performance monitoring is directly integrated into all VOTES MOV
PMs.
NOT FOR UPLOAD.
Refer to MOV PMT and BID for details.
MSIVs
HV141F022
A-D
HV141F028
A-D
X3
MSIV Retorques
MSIV PM routine includes step that addresses inspection and retorquing of MSIV
valve packing.
Basic Information
The scope of VOTES MOV PMT covers all
related valve packing issues. PPL pioneered the
use of VOTES data to monitor and maintain valve
packing load. Packing performance monitoring
remains a critical task on all VOTES MOV RTs.
As-found packing drag is monitored, and
packing loads are adjusted to ensure adequate
load is provided via as-left measurement.
N/A
N/A
HV241F022
A-D
HV241F028
A-D
B-11
Target:
Nuclear Power
Technology for Equipment
Assessment & Maintenance (TEAM)
About EPRI
EPRI creates science and technology solutions for
the global energy and energy services industry. U.S.
electric utilities established the Electric Power
Research Institute in 1973 as a nonprofit research
consortium for the benefit of utility members, their
customers, and society. Now known simply as EPRI,
the company provides a wide range of innovative
products and services to more than 1000 energyrelated organizations in 40 countries. EPRIs
multidisciplinary team of scientists and engineers
draws on a worldwide network of technical and
business expertise to help solve todays toughest
energy and environmental problems.
EPRI. Electrify the World
2. COPYRIGHT
This package, including the information contained in it, is either licensed to EPRI or owned by EPRI and is protected by United States
and international copyright laws.You may not, without the prior written permission of EPRI, reproduce, translate or modify this package, in any form, in whole or in part, or prepare any derivative work based on this package.
3. RESTRICTIONS
You may not rent, lease, license, disclose or give this package to any person or organization, or use the information contained in this
package, for the benefit of any third party or for any purpose other than as specified above unless such use is with the prior written
permission of EPRI.You agree to take all reasonable steps to prevent unauthorized disclosure or use of this package. Except as specified above, this agreement does not grant you any right to patents, copyrights, trade secrets, trade names, trademarks or any other
intellectual property, rights or licenses in respect of this package.
4.TERM AND TERMINATION
This license and this agreement are effective until terminated.You may terminate them at any time by destroying this package. EPRI has
the right to terminate the license and this agreement immediately if you fail to comply with any term or condition of this agreement.
Upon any termination you may destroy this package, but all obligations of nondisclosure will remain in effect.
5. DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
NEITHER EPRI,ANY MEMBER OF EPRI,ANY COSPONSOR, NOR ANY PERSON OR ORGANIZATION ACTING ON BEHALF
OF ANY OF THEM:
(A) MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER, EXPRESS OR IMPLIED, (I) WITH RESPECT TO THE USE
OF ANY INFORMATION,APPARATUS, METHOD, PROCESS OR SIMILAR ITEM DISCLOSED IN THIS PACKAGE, INCLUDING
MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE, OR (II) THAT SUCH USE DOES NOT INFRINGE ON OR
INTERFERE WITH PRIVATELY OWNED RIGHTS, INCLUDING ANY PARTYS INTELLECTUAL PROPERTY, OR (III) THAT THIS
PACKAGE IS SUITABLE TO ANY PARTICULAR USERS CIRCUMSTANCE; OR
(B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER (INCLUDING ANY CONSEQUENTIAL DAMAGES, EVEN IF EPRI OR ANY EPRI REPRESENTATIVE HAS BEEN ADVISED OF THE POSSIBILITY OF SUCH
DAMAGES) RESULTING FROM YOUR SELECTION OR USE OF THIS PACKAGE OR ANY INFORMATION, APPARATUS,
METHOD, PROCESS OR SIMILAR ITEM DISCLOSED IN THIS PACKAGE.
6. EXPORT
The laws and regulations of the United States restrict the export and re-export of any portion of this package, and you agree not to
export or re-export this package or any related technical data in any form without the appropriate United States and foreign government approvals.
7. CHOICE OF LAW
This agreement will be governed by the laws of the State of California as applied to transactions taking place entirely in California
between California residents.
8. INTEGRATION
You have read and understand this agreement, and acknowledge that it is the final, complete and exclusive agreement between you
and EPRI concerning its subject matter, superseding any prior related understanding or agreement. No waiver, variation or different
terms of this agreement will be enforceable against EPRI unless EPRI gives its prior written consent, signed by an officer of EPRI.
EPRI 3412 Hillview Avenue, Palo Alto, California 94304 PO Box 10412, Palo Alto, California 94303 USA
800.313.3774 650.855.2121 askepri@epri.com www.epri.com