Sie sind auf Seite 1von 52

NORTH AUCKLAND AND NORTHLAND GRID

UPGRADE PROJECT

ATTACHMENT B
TECHNICAL REPORT

Revision 1 May 2008

Attachment B: Technical Report May 2008 Revision

Executive Summary
A number of transmission development options were considered for providing a secure
power supply to North Auckland and Northland. This report presents analysis of four
options from the preliminary long list of options. These are the options which remained as
viable options after a high level analysis of the long list.
With some minor upgrades, the existing transmission system reaches its capacity by 2016
and a major new investment is required to be in place before then. The long list of
options included building new transmission assets, upgrading the existing lines, providing
generation north of the constriction, distributed generation or load control in the North
Auckland-Northland region.
The four options analysed in detail in this report include:
Installing a single new 220 kV cable circuit across Auckland from Penrose to Albany,
with a second circuit installed if and when required;
Upgrading the existing 220 & 110 kV networks by replacing existing conductor with
high temperature conductor of equal dimensions;
Installing a new 220 kV cable circuit from Penrose to Mount Roskill and a 220/110 kV
interconnection at Mount Roskill;
New generation in the area north of Auckland.
Option 1: Single 220 kV cable circuit from Penrose to Albany
This option involves a single 220 kV cable circuit from Penrose to Hobson Street via an
existing tunnel, then from Hobson Street to Wairau Road using cable buried along the
roading system and attached to the Harbour Bridge, and a section from Wairau Road to
Albany mostly buried in a new busway currently under construction.
The new 220 kV cable circuit is assumed to have a capacity of 630 MVA in winter. The
cable circuit will include a series reactor to balance power flow north between this circuit
and existing overhead lines. A new 220kV cable connection is also installed between
Pakuranga and Penrose substation.
The augmented transmission system into Northland is expected to reach its n-1 capacity
by 2036,1 requiring an additional 220 kV cable circuit to be installed.
Option 2: High Temperature Conductor
This option includes replacing the conductor on the 220 kV HEN-OTA line and on the 110
kV OTA-MNG-ROS-HEP-HEN lines as n-1 capacity is exceeded. The type of conductor
used is assumed to be of similar dimension to the existing conductor to avoid any change
in the physical appearance of the lines.
Eventually a new circuit from Penrose to Mount Roskill will be required as the n-1 capacity
of the upgraded circuits is exceeded.
Option 3: Single 220 kV cable circuit from Penrose to Mount Roskill
This option involves installing a 220 kV cable from Penrose substation to Mount Roskill
substation and initially a single 220/110 kV transformer at Mount Roskill.
The new circuit has a rating of 630 MVA and is approximately 10 km in length. This will be
installed before the Henderson-Otahuhu overhead circuit exceeds n-1 capacity, and will
increase supply capacity to the Northland region by increasing power flow north on the
110 kV circuits across Auckland. A new 220kV cable connection is also installed between
Pakuranga and Penrose substation.
1

Note that the n-1 analysis in this attachment was carried out on the basis of the security criteria set out at
section 2.7 of this attachment.
Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

Attachment B: Technical Report May 2008 Revision

A second interconnecting transformer is installed at Mount Roskill when required to


increase power flow north on the 110 kV system. The second transformer increases the
220-110 kV total n-1 transfer capacity and delays further major investment by four more
years. Ultimately a cross-harbour cable as in Option 1 will be installed.
Option 4: Installing new generation north of the Auckland
A technical analysis of this option is provided for information only. A discussion on the
status of this option is provided in the proposal document.
This option includes installing new generation north of Henderson substation. For the
purposes of this work, it is assumed that the new generation is connected into the 220 kV
Huapai-Marsden circuit. The maximum amount of reliable generation assumed to be
available is 240 MW.
The new generation delays the requirement to reinforce the supply into Northland. The
110 kV system is reinforced as its n-1 capacity is exceeded, by installing a 220 kV
Penrose-Mount Roskill circuit and an interconnection at Mount Roskill. Eventually under
this option a cross-harbour cable will be installed including new GXPs at Hobson Street
and Wairau Road
Reactive support is planned to meet reactive power losses and ensure voltage stability of
the power system. Dynamic reactive power support is planned such that there are
sufficient reserves to cover the worst transmission contingency, whether the Ngawha
power station new generation (15 MW) is in service or not

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

Attachment B: Technical Report May 2008 Revision

Contents
EXECUTIVE SUMMARY.......................................................................................2
1

INTRODUCTION ............................................................................................6

EXISTING SYSTEM........................................................................................9

2.1

Transmission .....................................................................................................................................9

2.2

Voltage Support ..............................................................................................................................12

ASSUMPTIONS AND METHODOLOGY......................................................13

3.1

General Assumptions......................................................................................................................13

3.2

Demand Forecast ............................................................................................................................13

3.3

Generation .......................................................................................................................................14

3.4

Component Ratings ........................................................................................................................15

3.5

Description of Modelled New Circuits ..........................................................................................15

3.6

Distribution System ........................................................................................................................15

3.7

Security Criteria..............................................................................................................................17

3.8

Planning Horizon ............................................................................................................................17

3.9

Methodology for Analysis...............................................................................................................17

COMMON AUGMENTATIONS.....................................................................19

4.1

North Island Grid Upgrade Project ..............................................................................................19

4.2

Other Projects .................................................................................................................................20

4.3

Voltage Support Plan......................................................................................................................21

4.4

Penrose 110 kV Reinforcement......................................................................................................22

PROJECT ALTERNATIVES.........................................................................24

5.1

Option 1 Cross Harbour Cables .................................................................................................25

5.2

Option 2 High Temperature Conductor ....................................................................................28

5.3

Option 3 New interconnection at Roskill ...................................................................................31

5.4

Option 4 New generation north of Auckland.............................................................................34

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

Attachment B: Technical Report May 2008 Revision

DISCUSSION ON REACTIVE PLANS .........................................................37

6.1

Static Reactive Requirements ........................................................................................................37

6.2

Dynamic Reactive Requirements...................................................................................................37

SUMMARY ...................................................................................................41

APPENDIX A EXISTING CIRCUIT RATINGS .................................................42


APPENDIX B - INTERCONNECTION TRANSFORMER RATINGS...................43
APPENDIX C - PARAMETERS OF NEW COMPONENTS USED......................44
APPENDIX D - SUBSTATION CODES...............................................................46
APPENDIX E - FORECAST LOAD DATA ..........................................................48
APPENDIX F - CHARACTERISTIC OF NAAN LOAD........................................49
APPENDIX G - CHARACTERISTIC OF PENROSE LOAD ................................50

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

Attachment B: Technical Report May 2008 Revision

Introduction
For the purposes of this report, the North Auckland and Northland (NAaN) region includes
the loads at Hepburn and Henderson, and everything north of that. The peak load of this
region was about 839 MVA in 2006 and is expected to be in excess of 850 MVA in 2007.
The historical average annual increase over the past five years is approximately 3%.
This report describes the technical assessment of alternatives for augmenting the
transmission capacity across Auckland and into the NAaN area, to ensure adequate
security of supply out to 2039. The results of the analysis are summarised in the form of a
timed development plan for each transmission alternative. The timings of the planned
transmission developments are based on Electricity Commissions prudent demand
forecast as of August 2007, adjusted by Transpower and as used for the 2008 Annual
Planning Report.
The scope of this report is limited to:
steady state analysis of the Auckland and Northland power system to ensure that it
would remain in a satisfactory state following any single credible contingency event
occurring on the core grid. This assumes that Ngawha generation is 10 MW, which
allows for an outage of 15 MW of Ngawha generation (due to be commissioned).
analysis of the power transmission system across Auckland and into the NAaN area.
It does not address security issues into the Auckland area from the south. For security
of supply into Auckland (specifically into Otahuhu and Pakuranga), the analysis
assumes the development plans as described in the North Island Grid Upgrade
Project (NI GUP) Amended Proposal, Option 2.
The reactive power support plan is developed to ensure stable operation of the power
system. The plan for each development option ensures the set voltage (1.02 pu for this
study) can be maintained at each controlled bus, under n-1 conditions, to a demand level
of the forecast peak demand in each year. Sufficient dynamic support is planned so that
no capacitor switching is required post-contingency.
The reactive plan from Otahuhu south is as developed for the NI GUP, and it is assumed
that the voltage at Otahuhu is maintained at 1.02 pu under all contingencies.
Four transmission options were analysed in detail for enhancing the security of supply into
the NAaN area as follows:

1.

Installing a 220 kV cross-harbour cable, from Penrose to Albany, connecting into


new grid exit points (GXPs) along the route at Hobson Street and Wairau Road.

2.

Upgrading existing transmission circuits using high temperature conductor,


avoiding as far as possible constructing any new lines

3.

Installing a new 220 kV cable circuit from Penrose to Mount Roskill with a
220/110 kV interconnection at Mount Roskill. This would be followed by a cross
harbour cable as per option 1 but deferred by 10 years.

4.

New generation in the Northland region modelled as being connected into the
220 kV Huapai-Marsden circuit.

Table 1-1 below summarises the development plans for the four options considered in
detail.

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

Attachment B: Technical Report May 2008 Revision

Table 1-1 Summary of Development Plans for the Four Preferred Options
Year*

2009

Option 1

Option 2

Option 3

Option 4

Cross harbour cable

HTC

Reinforce Mt Roskill

Northern generation

nd

nd

nd

nd

2 220/110 kV
transformer at PEN in
parallel with PEN T10

2 220/110 kV
transformer at PEN in
parallel with PEN T10

2 220/110 kV
transformer at PEN in
parallel with PEN T10

2 220/110 kV
transformer at PEN in
parallel with PEN T10

1st PEN-HOB-WRUALB cable

High Temp conductor


on 220 kV HEN-OTA
circuits

One 220 kV PAK-PEN


circuit

New HOB and WRU


GXP's
One 220 kV PAK-PEN
circuit

One 220 kV PAK-PEN


circuit

New 220 kV transformer


feeder at ROS (one
220 kV PEN-ROS
cable) and a ROS
220/110 kV
interconnecting
transformer (ICT)

2010
2011
2012
2013
2014
2015
2016

120 MW new generation


at Rodney connected to
220 kV MDN-HPI 1
circuit

One 220 kV PAK-PEN


circuit
2017
2018

Upgrade HEN
220/110 kV
transformers with 2 x
250 MVA 7% units

Replace existing HEN


220/110 kV
transformers with 2 x
250 MVA 7% units

2019

Install a second ICT at


ALB

2020

Second 220/110 kV
transformer at ALB

2021

High Temp conductor


on 110 kV MNG-ROS
circuits

Install a second ICT at


ALB

New 220 kV transformer


feeder at ROS (one
220 kV PEN-ROS cable
& one ROS 220/110 kV
transformer)

Upgrade 200m of ALBHEN 3 to duplex zebra


conductor
2022

Install a second ICT at


ROS

2023

Second 220/110 kV
transformer at HOB

2024

2 supply transformer
at WRU

nd

One series reactor in


the PAK-PEN 1 circuit
Third 220/110 kV
transformer at OTA in
parallel with T3 & T5

Upgrade HEP-ROS 1 &


2 circuits

High temp conductor on


Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

Attachment B: Technical Report May 2008 Revision

Year*

Option 1

Option 2

Option 3

Option 4

Cross harbour cable

HTC

Reinforce Mt Roskill

Northern generation

110 kV OTA-ROS 1 & 2

2025

2026

Series reactor in OTAPEN 2 circuit


2nd 220 kV PAK-PEN
circuit

Install first crossharbour cable PENHOB-WRU-ALB plus


GXPs at HOB and WRU

2nd 220 kV PAK-PEN


circuit

Install a second supply


transformer at WRU
Install a second PAKPEN cable and a series
reactor
2027
2028

Series reactors In
220 kV PAK-PEN
circuits

High temp conductor on


110 kV MNG-OTA 1 & 2

120 MW additional
generation at Rodney

New 220 kV transformer


feeder at ROS
(one 220 kV PEN-ROS
cable & one ROS
220/110 kV transformer)
2029

High temp conductor on


ALB-HEN-HPI circuits

2030

Series reactor on OTAPEN 2 circuit

Third 220/110 kV
transformer MDN

Third 220/110 kV
transformer MDN
2031

Third 220/110 kV
transformer MDN

Third 220/110 kV
transformer MDN

2032

Install a series reactor


on OTA-PEN 2 circuit

Install a second ICT at


ROS
Install series reactors in
PAK-PEN 1 & 2 circuits

2033
2034
2035
2036

2nd 220 kV ALB-PEN


cable, this one not
connected into HOB or
WRU GXP's

New 220 kV transformer


feeder at ROS
(one 220 kV PEN-ROS
cable & one ROS
220/110 kV transformer)
Series reactors in
110 kV ALB-HEN 1&2
circuits

Second 220/110 kV
transformer at HOB

1st PEN-HOB-WRUALB cable


New HOB and WRU
GXP's, two ICTs at
HOB
Install second HOB ICT
Instal second WRU
supply transformer

High temp conductor on


HEP-ROS 1&2 circuits

2nd 220 kV PAK-PEN


circuit

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

Attachment B: Technical Report May 2008 Revision

Year*

Option 1

Option 2

Option 3

Option 4

Cross harbour cable

HTC

Reinforce Mt Roskill

Northern generation

High temperature
conductor on HEN-WEL
1 & 2 circuits

Upgrade PAK-PEN
circuits from 667 MVA to
1100 MVA

2037
2038

Upgrade PAK-PEN
circuits from 667 MVA to
985 MVA

2039
2040

2nd 220 kV ALB-PEN


cable, this one not
connected into HOB or
WRU GXP's

* Year in which development is required, e.g. 2013 = development required to be commissioned by winter (May)
of 2013

These four options were short-listed for further detailed analysis because they:
represent different strategic approaches which could potentially improve the supply
security to the NAaN area
are considered to provide similar benefits
Other transmission options that were studied during the preliminary phase, but not short
listed are discussed in the document Assessment of Options. These options are listed in
Table 1-2.
Table 1-2: Options Not Considered
Description

Type

Deep tunnel Hobson Street Albany

Transmission

Deep tunnel Penrose - Henderson

Transmission

Central corridor 110 kV to 220 kV line replacement

Transmission

Distributed generation

Supply side

Ripple Control

Demand side

Huntly Huapai cables via harbour

Transmission

Deep tunnel Hobson Street Henderson

Transmission

HVDC light from Penrose to Albany


(two terminal)

Transmission

HVDC light Pakuranga Penrose Albany (three terminal)

Transmission

Huntly Henderson overhead / underground

Transmission

Huntly to Huapai 220 kV double circuit overhead line

Transmission

Existing System

2.1

Transmission
The transmission system across Auckland supplying the North Auckland and Northland
(NAaN) area is composed of two branches:

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

Attachment B: Technical Report May 2008 Revision

1. A double circuit 220 kV line from Otahuhu to Henderson, with Southdown power
station connected into one of these circuits just north of Otahuhu.
2. Two 110 kV lines from Otahuhu to Mount Roskill (with one double-circuit line going
via Mangere) then to Hepburn Road and on to Henderson. This system is presently
split for operational reasons between Mount Roskill and Hepburn Road. The split is
due to be closed in 2008 following the installation of new secondary equipment.
Figure 2-1: Existing transmission System in the Auckland and Northland Region

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

10

Attachment B: Technical Report May 2008 Revision

Table 2-1 below gives the ratings of the existing circuits supplying the NAaN area,
including conductor ratings and limiting components. Refer to Appendix A for a full list of
circuit ratings in the NAaN area.
Table 2-1: Existing circuits supplying NAaN area
Circuit

HEN-HEP

Line

Conductor

V
(kV)

Conductor
Rating
(MVA)

Branch
Rating
(MVA)

Notes on limiting
component

HEN-ROS A

Simplex Wolf
o
75 C

110

92/101

92/101

HEN-OTA 1

HEN-OTA A

Duplex Zebra
o
120 C

220

938/985

915/915

Disconnector

HEN-SWN 1

HEN-OTA A

Duplex Zebra
o
120 C

220

938/985

915/915

Disconnector

HEP-ROS
1&2

HEN-ROS A

2 bonded Wolf
o
75 C

110

184/202

114/114

Disconnector at 114
MVA then single span
at 174/191 MVA

MNG-OTA
1&2

MNG-OTA A

Duplex Zebra
o
75 C

110

355/390

305/305

Disconnector

MNG-ROS
1&2

MNG-ROS A

Simplex Wolf
o
75 C

110

92/101

92/101

OTA-ROS
1&2

OTA-PEN B &
PEN-ROS A

Simplex Wolf
o
75 C

110

92/101

92/101

OTA-SWN 1

HEN-OTA A

Duplex Zebra
o
120 C

220

938/985

912/912

1 to 4

Transducer

The capacity of the transmission system into Northland is presently equal to the n-1
capacity of the 220 kV HEN-OTA line. This is a double-circuit line, each circuit being
duplex zebra conductor with a temperature rating of 120oC. The resulting n-1 rating is
938/985 MVA summer/winter.

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

11

Attachment B: Technical Report May 2008 Revision

Figure 2-2: Reduced network between Otahuhu and Henderson

Figure 2-2: shows the transmission system supplying the NAaN area.
Consent to operate the 220 kV HEN-OTA line at 120C during forced outages has been
attained, however this is subject to an appeal. The appeal is expected to be heard some
time in mid to late 2008, but until then Transpower are permitted to make use of the
consent that has been granted.
The split shown in the 110 kV system at Mount Roskill is to be normally closed by late
2008. Closing this split will increase the transfer limit to Northland. While there is very little
power flow from Mount Roskill to Hepburn when the system is operating normally, an
outage of one 220 kV Henderson-Otahuhu circuit does result in power flow north via the
110 kV system, reducing load on the remaining 220 kV circuit.
The balance of load flow between the 110 kV and 220 kV systems has a significant effect
on the transfer limit to the NAaN area. This is determined mainly by the impedance of the
circuits and interconnecting transformers at Otahuhu and Henderson, as well as loads on
the 110 kV system and in particular at Mount Roskill.
Under this configuration, n-1 transmission capacity into Northland is more difficult to
quantify, and is dependant on various factors including the load at Mount Roskill
substation. With the present load distribution, closing the 110 kV split adds the equivalent
of about four years average load growth capacity to the Northland transmission system, or
about 100 MVA. The Penrose 110 kV bus must be reinforced due to the recent load shift.
From Henderson, the region is supplied by parallel 220 and 110 kV systems as far north
as Marsden, and a 110 kV system north to Kaitaia. There are 220/110 kV
interconnections at Henderson, Albany and Marsden.

2.2

Voltage Support
Table 2-2 lists the existing and planned voltage support in the NAaN region. Dynamic
support at Marsden is contracted as an ancillary service by the System Operator to
maintain a specified voltage during outages and other times it may be required.

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

12

Attachment B: Technical Report May 2008 Revision

Table 2-2: Planned and Existing Voltage Support in the NAaN Region

Location

Size

Dynamic/St
atic

Notes

Kaikohe

20 Mvar

Existing

Albany

110 Mvar

Existing

Henderson

135 Mvar

Existing

Marsden

+60/-20 Mvar

Existing

Hepburn

2 x 50 Mvar

Existing

Albany

100 Mvar

Existing

Albany

+/- 100 Mvar

Due to be commissioned 2008

Kaitaia

24 Mvar

Committed Project

Henderson

+/- 100 Mvar

Seeking approval may not be at HEN

Assumptions and Methodology


The following assumptions are made in the technical analysis.

3.1

General Assumptions
Pakuranga substation will be entirely converted to 220 kV by 2011 and there will be two
220 kV OTA-PAK circuits (on the existing OTA-PAK A line). In addition, as part of this
conversion;
The 110 kV ARI-PAK 1 circuit will be decommissioned;
The 110 kV PAK-PEN 1 circuit will be decommissioned; and
110 kV OTA-PAK 1 & 7 circuits will be converted to 220 kV.
The BOB-GLN interconnection is built by 2015.
All system upgrades south of Otahuhu as defined in the North Island Grid Upgrade
Project (NI GUP) are common to all of the alternatives and will be modelled as occurring
in the year proposed by the NI GUP Amended Proposal, Option 2. A complete list of
common projects is provided in section 4.
All Upper North Island voltage support projects from Otahuhu south are assumed to be as
in the Amended NI GUP. For simplicity the analysis assumes the Otahuhu bus voltage
remains at 1.02 pu throughout the studies.
Voltage support in the NAaN area will include dynamic support at Henderson, Albany and
Marsden, and the 220 kV buses at these substations will be maintained at 1.02 pu
voltage.

3.2

Demand Forecast
The load forecast used is based on the EC prudent forecast August 2007, as adjusted by
Transpower for use in the 2008 Annual Planning Report.
The graph below shows the load forecast for the NAaN area as used for the technical
assessment. It has been assumed that this forecast takes distributed generation into
account. See the Appendix for a summary of Northland and Auckland forecast regional
load peaks.

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

13

Attachment B: Technical Report May 2008 Revision

Figure 3-1: EC Prudent Demand Forecast for Northland and North Auckland 2010-2040
2000

1750

MW

1500

1250

1000

750

500
2010

2015

2020

2025

2030

2035

2040

Year

As the distribution of loads in the EC forecast does not exactly match the distribution of
loads that Transpower use in modelling the system, some rearrangement of loads was
required. This is detailed below.
The EC loads LST_110A and LST_110B were combined then split as follows:
52% to LST_110/ROS
24% to ROS_KING/1
24% to ROS_KING/2
The EC loads PEN_110A and PEN _110B were combined then split as follows:
56% to LST_110/PEN
22% to PEN_QUAY/1
22% to PEN_QUAY/2
PEN_33A

and

PEN_33B

are

regarded

as

PEN22

and

PEN33

respectively.

Total PEN110 load for this study is based on a diversity factor of 81% for loads supplied
from this GXP. This is the peak region diversity for these loads as in the draft peak
demand forecast used. The Penrose 110 kV load includes: Hobson St (LST/PEN),
Liverpool St (LST/ROS), Quay St (PEN/QUAY 1 + 2) and Freemans Bay (25% of
diversified ROS_KING total).

3.3

Generation
Ngawha is assumed to be generating at 10 MW out of a total capacity of 25 MW, and 8.7
Mvar voltage support controlling the Ngawha 33 kV bus voltage.

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

14

Attachment B: Technical Report May 2008 Revision

Southdown generating 170 MW with 4 machines, controlling the SWN 220 kV bus voltage
at 1.02 pu.

3.4

Component Ratings
a)

Percentage loading on transformers refers to the percentage of post-contingency


winter rating of the transformer, unless otherwise specified.

b)

Loading on circuits is a percentage of the winter conductor rating, unless


otherwise specified.

c)

For cables, all ratings are assumed to be winter peak capacity, based on typical
load profiles. No additional capacity has been assumed for short-term
contingencies.

d)

For high temperature conductors, the ratings were assumed to be equal to the
existing conductor operating at a temperature of 220oC. This approximates the
rating of a high temperature conductor that has physical dimensions similar to the
existing conductor.

N.B. See Table A-0-1 and Table B-0-1 for a list of line ratings and transformer ratings in
the Auckland area. See Table C-0-1 for a list of electrical parameters of the new
components used in these studies.

3.5

Description of Modelled New Circuits


PEN-HOB cable
10.21 km of 1600mm2 trefoil in air (tunnel)
HOB-WRU cable
1.39 km of 1600mm2 trefoil in air (bridge)
8.46 km of 2000mm2 trefoil in ducts
WRU-ALB cable
8.45 km of 2000mm2 trefoil in ducts (busway)
PEN-ROS cable
10.2 km of 2000mm2 trefoil in ducts
PAK-PEN cable
8.6 km of 2500mm2 direct buried (forced cooled for upgraded options)

Notes:

3.6

1.

The 220 kV cross-harbour cables are installed such that the winter cyclical rating
for the entire length is 630 MVA.

2.

See Table C-0-1 for electrical parameters of new components.

3.

The cross sectional areas and ratings provided above are minimums. Installed
cross sectional areas (and ratings) may differ from those provided following the
detailed design phase of the works.

Distribution System

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

15

Attachment B: Technical Report May 2008 Revision

Vectors distribution system in the Greater Auckland area is assumed to be configured as


follows:
Freemans Bay load is approximately 25% of the total Kingsland load, and as of 2007
is permanently transferred from Mount Roskill to Hobson Street.
Quay Street load will be transferred from Penrose to Hobson Street if and when a
new grid exit point (GXP) is built there
If no GXP is built at Hobson Street, Quay Street will be supplied via new 110 kV
cables out of Penrose.
The Mount Roskill-Liverpool Street cable will normally be in standby mode and not
supplying load. All Liverpool St load is transferred to PEN110 via the PEN-LST
cables.
Hobson Street will be supplied from Penrose until a new GXP is built at Hobson
Street.
If no GXP is built at Hobson Street, the Hobson Street load will continue to be
supplied via existing (and if necessary additional) 110 kV Penrose-Liverpool StreetHobson Street cables
Paralleling of the local lines companys network with Transpowers network will be
allowed until it causes overloading, at which time Vectors network will be split
If no new GXP is built at Wairau Road, Vector will reinforce the 110 kV supply from
Albany as necessary
Two new grid exit points (GXPs) are proposed as part of upgrade options 1, 3 & 4. These
are at Vectors existing zone substation sites of Hobson Street and Wairau Road. The
studies have assumed the following:
The first 220 kV cross-harbour cable will be diverted into each new GXP, giving n-1
security.
The Hobson Street GXP will include a single 250 MVA 220/110 kV transformer
initially, with a second added when required to maintain n-1 security of supply. This
generally occurs when the Lines Companys and Transpowers systems can no
longer be operated in parallel.
The Wairau Road GXP will include a single 250 MVA 220/33 kV transformer initially,
paralleled with existing supply transformers on the 33 kV side. When the load
exceeds the combined post-contingency rating of the three existing 110/33 kV supply
transformers, a second 220/33 kV transformer will be added, and 110/33 kV
transformers taken out of service.
Note: Specifications of the actual supply transformers installed will be decided in
discussion with the customer.

3.6.1

Configuration of 110 kV system into CBD


Vector presently supply their Liverpool Street 110kV CBD substation from both Penrose
(via two 110kV cables) and Mt Roskill (via a single 110kV cable). Due to Vector concerns
over security of sub transmission into the CBD, they have decided to reconfigure their
110kV sub transmission network so that Liverpool Street substation is supplied solely
from Penrose, i.e. the ROS 110kV cable will be out of service and all of the CBD 110kV
load will be supplied out of PEN.
The consequence of this is an overall increase of load on the Transpower 110kV bus at
Penrose (equating to about 90MW in 2007).
Penrose 110kV bus is supplied from:
T10 (220/110kV transformer)
110kV PAK PEN circuit
110kV OTA PEN circuit

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

16

Attachment B: Technical Report May 2008 Revision

Prior to Vectors shifting of load from ROS, PEN will be in need of reinforcement by 2013,
this is independent of the installation of the first cross harbour cable, which coincidentally
would also occur in 2013. Following the shifting of Vectors load from ROS, PEN would
require reinforcement in 2009 in order to meet increased demand. This reinforcement
would include a new 220/110kV transformer at Penrose.
This work can be deferred by switching the ROS cable back into service in 2009, thereby
reducing the 110kV load at PEN. Transpower however assume that the Liverpool Street
load is now permanently shifted to the PEN 110kV bus, and will not be shifted back in
order to manage load peaks at the Penrose 110 GXP.

3.7

Security Criteria
The analysis was carried out on the basis that committed generation from Ngawha is
unavailable. It should be noted that the amount of generation at Ngawha is relatively small
compared to the NAaN load, and that therefore this assumption does not have a material
impact on the results.

3.7.1

Contingencies
In addition to an outage of the Ngawha generation, the following contingencies were
considered to determine the development plans for all the options:
Loss of any single 220 kV or 110 kV transmission circuit from Otahuhu to Marsden;
Loss of one of Vectors 110 kV cable connections between Penrose and Liverpool
Street and Hobson Street
Loss of a 220/110 kV interconnecting transformer (from Otahuhu to Marsden).

3.7.2

Steady State Planning Criteria


The planning criteria used in the studies are as follows:
Transmission lines are limited to 100% of their respective winter or summer rating
with no short term overload capability
Cables are limited to 100% of their cyclic rating with no additional short term overload
capability
Existing transformers are limited to their winter or summer 24hr rating, assuming that
the transformers are cyclically loaded
New 220/110 kV 250 MVA interconnecting transformers are equivalent to the existing
Otahuhu T5 transformer, with the same overload ratio (1.27/1.33 summer/winter)
Loading was rounded to the nearest percentage point and anything loaded to 100%
or more was considered to be overloaded

3.8

Planning Horizon
The analysis extends out 32 years to 2040 as follows:
Every second year from 2008 to 2040
Other years where necessary to determine the accurate timing of the critical
investments

3.9

Methodology for Analysis


This is a steady-state analysis based on load flow calculations. All the plans developed
have assumed winter demand and winter component ratings. This is justified by the
significantly winter peaking nature of the NAaN area load (see Figure F-0-1), as well as
that of all the GXPs in the Auckland area, including Mangere, Pakuranga and Mount
Roskill. Penrose loads are less strongly winter peaking and are described in Appendix G
- Characteristic of Penrose Load.

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

17

Attachment B: Technical Report May 2008 Revision

Deterministic grid reliability criteria were assumed for planning the transmission grid. The
grid is planned to provide the supply reliability to the loads for an outage of one
transmission element together with an outage of a single generating unit in the NAaN
area (i.e. n-g-1). The transmission plans developed for all the options satisfy the
assumed grid reliability criteria.
Transmission development plans ensure that the system remains stable and the
transmission assets remain within their rated capacity for all credible contingencies.
Appropriate winter demand and circuit ratings were assumed in determining the loading of
the transmission circuits.
Note that summer loadings and ratings were also analysed in order to confirm whether the
binding constraints would occur in summer or winter. The analysis shows that even
though the ratings of circuits drop in the summer, the nature of the load (refer to
appendices F and G) is such that the winter situation remains the most onerous and
hence winter ratings and winter peak loads are those that are used in the subsequent
analysis.
3.9.1

Reactive Power Support


In planning the reactive power support requirements, outages of the critical transmission
components were modelled. Adequate reactive power support ensures that:
acceptable voltages (0.90 pu 1.1 pu) are maintained at all the 220 kV and 110 kV
buses, and
sufficient reactive reserves are maintained, pre-contingency, in the dynamic reactive
devices (generators, synchronous condensers and SVCs) so that post-contingency
switching of capacitors is not required
This analysis has not attempted to optimise the location or the quantity of reactive power
support. For the purpose of comparing the transmission options, all the dynamic reactive
support is assumed to be located at Henderson, Albany and Marsden. The voltage was
maintained at 1.02 pu at all buses that had dynamic support. Switched capacitors at
Kaitaia were modelled as an SVC with a 24 Mvar limit. Otahuhu voltage is assumed to
remain constant under all contingencies.

3.9.2

Dynamic Analysis
The proposed development plans provide adequate transmission capacity into the NAaN
area and maintain steady state voltages within the Electricity Governance Rule limits
following a contingency. The plans were developed using steady state analysis (power
flow and voltage stability) of the power system.
Transient performance of the connected generators and the loads (especially the motor
loads) could affect the stability of the power system following a transmission disturbance
and will require more detailed power system simulation.
Past studies2 indicate that additional investment in the form of dynamic reactive power
support (e.g. synchronous condensers or SVCs) may be required to ensure power system
stability. As the extra dynamic reactive support is mainly dependent on the characteristics
of the connected rotating plant, it is assumed that additional reactive power requirements
will be similar for all transmission alternatives.

NP306 Auckland Reactive Power Requirements by 2010, Transpower NZ Ltd, October 2005

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

18

Attachment B: Technical Report May 2008 Revision

Common Augmentations
A number of augmentations common to all of the development alternatives have been
drawn from the following sources:
North Island Grid Upgrade Project Amended Proposal October 2006
Annual Planning Report

4.1

North Island Grid Upgrade Project


The table below lists the common augmentations that are part of the North Island Grid
Upgrade project.
Table 4-1: Common Augmentations that are part of the North Island Grid Upgrade project
Year

Augmentation

2009

Decommission the 110 kV ARI-PAK line

2011

Build new 400 kV double circuit line (Triplex AAAC Sulphur conductor) from WKM to BHL, operated at
220 kV
Install two new 220 kV cables from BHL-PAK
Build a new cable transition station at BHL
Build a new 220 kV substation at PAK
Increase operating voltage of the OTA-PAK 1 & 2 circuits (OTA-PAK A transmission line) to 220 kV

2013

Re-conductor 110 kV ARI-HAM 1 & 2 circuits (ARI-HAM B double circuit line) with Nitrogen 75C
conductors.

2021

Install 55% compensation on WKM-BHL 1 and 2 circuits


Install 110 kV OTA-WIR cable
Build new switching station at BHL
st

Install 1 220 kV BHL-OTA cable


nd

2023

Install 2 220 kV BHL-OTA cable

2026

Re-conductor HAM-BOB 110 kV circuits to Nitrogen Conductors.

2027

Thermally upgrade the 220 kV HAM-HLY-1, HLE-WKM and HAM-WKM-1 circuits ( HLE-HAM-WKM
section of the OTA-WKM C double circuit line) to 2xGoat 80C

2028

Install 20 Ohm reactors on the OTA-WKM 1 & 2 circuits (OTA-WKM A&B lines)

2031

Install forced cooling on the 220 kV BHL-PAK cables

2033

Install forced cooling on the 220 kV BHL-OTA cables


Build new 400 kV substation at Whakamaru
Build new 400 kV substation at Ormiston Road
Increase operating voltage of the WKM-BHL circuits to 400 kV
Install six 400/220 kV, 600 MVA interconnecting transformers at BHL
Install six 400/220 kV, 600 MVA interconnecting transformers at WKM
Reduce series compensation on the 400 kV BHL-WKM circuits to 45%

2037

Install a 75 MVA Phase Shifting Transformer on the 110 kV ARI-BOB circuit

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

19

Attachment B: Technical Report May 2008 Revision

4.2

Other Projects
The table below lists the other common augmentations that are not part of the North
Island Grid Upgrade project.
Table 3-2: Common Augmentations that are not part of the North Island Grid Upgrade project
Year

Common Augmentation

2008

Upgrade the bus protection at Mount Roskill and close the 110kV split between Hepburn Road and
Mount Roskill substation.

By 2010

Thermal upgrade of 220 kV HLY-OTA-1 circuit (HLY-OTA section of OTA -WKM C double circuit line)
from 493/404 MVA to 670/614 MVA.
Thermal upgrade of 220 kV WRK-PPI-WKM-1 circuit (WRK- WKM B single circuit line) from 292/239
MVA to 448/421 MVA
Shift half of HAM 33 kV load to new substation at TWH on HLY-TMN 220 kV circuit.
Thermal upgrade of 220 kV BPE-HAY-1 circuit (BPE-HAY A single circuit line) from 247/202MVA to
335/307 MVA
Thermal upgrade of 220 kV BPE-HAY-2 circuit (BPE-HAY B single circuit line) from 247/202MVA to
335/307 MVA
Thermal upgrade of 220 kV TKU-WKM-1 circuit (TKU-WKM section of single circuit BPE- WKM A line)
from 281/244 MVA to 335/307 MVA
Thermal upgrade of 220 kV TKU-WKM-2 circuit (TKU-WKM section of single circuit BPE- WKM B line)
from 281/244 MVA to 335/307 MVA
Thermal upgrade of 220 kV RPO- WRK-1 circuit (RPO- WRK section of BPE-WRK A single circuit line)
from 292/239 MVA to 370/333 MVA
Thermal upgrade of 220 kV BPE-TKU-1 circuit (BPE-TKU section of BPE- WKM A single circuit line)
from 246/202 MVA to 335/307 MVA
Thermal upgrade of 220 kV BPE-TKU-2 circuit (BPE-TKU section of BPE- WKM B single circuit line)
from 246/202 MVA to 335/307 MVA
Thermal upgrade of 220 kV OTA-WKM-1 circuit (OTA-WKM A single circuit line) from 246/202 MVA to
323/293 MVA
Thermal upgrade of 220 kV OTA-WKM-2 circuit (OTA-WKM B single circuit line) from 246/202 MVA to
323/293 MVA
Bus the 220 kV HAM-HLY-1, HLY-OTA-1 and OTA-WKM-3 circuits (OTA -WKM C double circuit line) at
HLE in a breaker-and-a-half configuration
Install second Wilton 100 MVA, 220/110 kV Interconnecting transformer
Shift 40% of Load from HIN to ARI (to compensate for new GXP at Putaruru)
Install new +/- 100 Mvar SVC at ALB
Install new 24 Mvar Capacitors at KTAInstall new +/- 100 Mvar SVC at ALB
Install new 25 Mvar Capacitors at TGA
Reconductor the 220 kV BPE-TKU-1 circuit (BPE-TKU section of BPE- WKM A single circuit line)Install
new 24 Mvar Capacitors at KTA
Reconductor the 220 kV BPE-TKU-2 circuit (BPE-TKU section of BPE- WKM B single circuit line)Install
new 25 Mvar Capacitors at TGA

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

20

Attachment B: Technical Report May 2008 Revision

Year

Common Augmentation
Reconductor the 220 kV TKU-WKM-1 circuit (TKU-WKM section of single circuit BPE- WKM A
line)Reconductor the 220 kV BPE-TKU-1 circuit (BPE-TKU section of BPE- WKM A single circuit line)
Reconductor the 220 kV TKU-WKM-2 circuit (TKU-WKM section of single circuit BPE- WKM B
line)Reconductor the 220 kV BPE-TKU-2 circuit (BPE-TKU section of BPE- WKM B single circuit line)

2011

Thermal upgrade of 220 kV BPE-TNG-1 and RPO-TNG-1 circuits (BPE-TNG-RPO section of the BPEWRK A single circuit line)Reconductor the 220 kV TKU-WKM-1 circuit (TKU-WKM section of single
circuit BPE- WKM A line)
Reconductor the 220 kV OHK-WRK-1, ATI-OHK-1 and ATI-WKM-1 circuits (WRK-WKM A single circuit
line)Reconductor the 220 kV TKU-WKM-2 circuit (TKU-WKM section of single circuit BPE- WKM B line)
Install two new 220/110kV interconnecting transformers at HHI and operate the HHI-TGA-1 circuit at
220kV.Thermal upgrade of 220 kV BPE-TNG-1 and RPO-TNG-1 circuits (BPE-TNG-RPO section of
the BPE-WRK A single circuit line)
Build a third 110kV HAM-WHU CircuitReconductor the 220 kV OHK-WRK-1, ATI-OHK-1 and ATIWKM-1 circuits (WRK-WKM A single circuit line)
Bus the 220 kV HLY-SFD-1 circuit at TMNInstall two new 220/110kV interconnecting transformers at
HHI and operate the HHI-TGA-1 circuit at 220kV.
Add BOB Tee (59% from HLY) to 220 kV GLN-HLY circuit and feed BOB via a new 200 MVA, 220/110
2
kV interconnecting transformer Build a third 110kV HAM-WHU Circuit
Install a third 200 MVA, 220/110 kV interconnecting transformer ,at TRKBus the 220 kV HLY-SFD-1
circuit at TMN

2014

Reconductor the WRK-PPI-WKM-1 circuit (WRK- WKM B single circuit line)Add BOB Tee (59% from
HLY) to 220 kV GLN-HLY circuit and feed BOB via a new 200 MVA, 220/110 kV interconnecting
2
transformer

2015

Install a third 200 MVA, 220/110 kV interconnecting transformer ,at TRK


Reconductor the WRK-PPI-WKM-1 circuit (WRK- WKM B single circuit line)

The development plan for the common reactive support requirements is shown in Table
4-3. Reactive support specific to each alternative project is provided in section 5.

4.3

Voltage Support Plan


Table 4-3: Voltage Support Common to all Options
YEAR

Location

Quantity
(Mvar)

Static(S) /
Dynamic(D)

2008

ALB

100

2008

ALB

100

2008

KTA

24

2009

HEN

100

2009

MDN

60

2024

KTA

24

2024

MPE

30

2025

WKO

30

2030

MPE

30

2033

WKO

30

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

21

Attachment B: Technical Report May 2008 Revision

2036

MPE

30

2039

HAM

50

2039

HAIRINI

100

For the purposes of these studies, reactive support at


Otahuhu was modelled as a single large SVC of a magnitude
no greater than that modelled in the NIGU project.

4.4

Penrose 110 kV Reinforcement


The Liverpool Street load has a forecast 2008 peak of approximately 100 MW. In mid2007, Vector shifted this load from the Mount Roskill GXP to the Penrose GXP, supplied
via the 110 kV PEN-LST cables. Vector now maintain the Mount Roskill-Liverpool Street
cable on standby, and will not use this cable to supply load under normal circumstances.
This load shift has an effect on the load flows into the NAaN area, as it removes load from
the Mount Roskill GXP, allowing greater capacity for supplying Northland via the 110 kV
system. At the same time, the increased load on Penrose and in particular the PEN 110
kV bus, means that the need for reinforcement of this bus is brought forward.
The Penrose and Pakuranga 110 kV loads are supplied from three points;
The Penrose interconnection (PEN T10)
The Otahuhu interconnection (OTA T2 & T4)
The 110 kV ARI-PAK 1 circuit

There is also a 110 kV connection to Bombay but there is virtually no load flow north on
this circuit.
In 2009, the ARI-PAK 1 circuit is scheduled to be decommissioned as part of the North
Island Grid Upgrade project, leaving the Otahuhu and Penrose interconnecting
transformers to supply the Pakuranga and Penrose 110 kV load. By 2009 these
interconnecting transformers will not be able to provide sufficient n-1 capacity.
In 2011, the Pakuranga substation will be converted to 220 kV as part of the North Island
Grid Upgrade project. This will reduce the 110 kV load in the area (because the PAK
110 kV load is transferred to 220 kV system), but it will also reduce the security of supply
into the Penrose 110 kV bus with the removal of the 110 kV PAK-PEN circuit.
Therefore the two issues are:
Not enough n-1 capacity supplying PAK and PEN 110 kV loads from 2009 to 2011
A loss of n-1 security into PEN110 from 2011
A number of options were investigated to resolve these issues, including
Install another interconnecting transformer at Penrose or Otahuhu
Parallel Vectors 110 kV network with Transpowers between Penrose and Mount
Roskill (this will move some of the 110 kV load back to Mt Roskill)
Retain one 110 kV PAK-PEN circuit and either install an interconnecting transformer
at Pakuranga or retain one 110 kV OTA-PAK circuit
The Penrose interconnection option works well if the impedance is chosen to balance flow
between the 220 kV and 110 kV OTA-PEN circuits. This will mean that no additional
reinforcement will be required prior to the installation of the cross harbour cable until
2016.

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

22

Attachment B: Technical Report May 2008 Revision

The option to parallel the Vector network would require two reactors on the 110 kV cables
(approximately 20 Ohm each), which would be redundant once the cross-harbour cable
was installed. It would also mean that the Vector assets become part of the transmission
network and would require monitoring and control capability for the System Operator.
The option to retain the 110 kV PAK-PEN circuit would require additional interconnecting
capacity at Otahuhu initially. Then when Pakuranga is converted to 220 kV, either this
interconnector is transferred to Pakuranga or alternatively, one of the existing overhead
OTA-PAK circuits can be operated at 220 kV with the other retained at 110 kV. The
110 kV PAK-PEN 1 circuit would be retained, and Penrose 110 kV bus would effectively
have another circuit connection to Otahuhu via Pakuranga.
The preferred option is to install a second interconnecting transformer at Penrose, parallel
to the existing PEN T10. This is a low cost option that allows the PAK-PEN 1 circuit to be
removed and means that two OTA-PAK circuits are available for the 220 kV connection. A
suitable Penrose interconnecting transformer would be a 15% impedance, 250 MVA unit.

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

23

Attachment B: Technical Report May 2008 Revision

Project Alternatives
Four alternatives have been studied to provide comparisons on cost, effectiveness, build
ability and operability.
Alternatives considered are as follows:
1.

Installing a single 220 kV cross-harbour cable from Penrose to Albany, followed


by a second parallel cable as load growth makes this necessary. 220 kV
Pakuranga-Penrose circuits are also installed one at a time as necessary to
reinforce Penrose.

2.

Upgrading the existing 220 kV overhead double-circuit line from Otahuhu to


Henderson, including replacing existing conductor with high-temperature
conductor (HTC), and upgrading the existing 110 kV transmission system with
HTC as required. Assume no new lines are built until all HTC upgrade options
have been exhausted.

3.

Reinforcing the 110 kV system across Auckland prior to installing the crossharbour cable. This involves adding an interconnection at Mount Roskill, supplied
at 220 kV from Penrose.

4.

New generation in the North Isthmus area, connected into the 220 kV HPI-MDN
circuit.

The tables below show the system limitations and recommended augmentations based
on forecast load growth. The Year column gives the year at which the limitation will first
occur. Therefore to avoid the limitation the recommended augmentation would need to be
complete before the winter peak of that year

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

24

Attachment B: Technical Report May 2008 Revision

5.1

Option 1 Cross Harbour Cables


This involves Installing a single 220 kV cross-harbour cable from Penrose to Albany,
followed by a second parallel cable as load growth makes this necessary. 220 kV
Pakuranga-Penrose circuits are also installed one at a time as necessary to reinforce
Penrose.

5.1.1

Development Plan
Table 5-1: Option 1 - Cross-harbour cable development plan
Year

NAaN load

Limitation

Augmentation

2009

910 MW

OTA T2 & T4 and PEN T10 do


not provide n-1 security to 110
kV loads they supply

Install a 2 250 MVA 15%


interconnecting
transformer at PEN

2013

1025 MW

OTA-PEN 5 102% with OTAPEN 6 out of service

Special protection scheme;


take PEN T10 out of service
when either 220 kV OTAPEN cct trips

2016

1097 MW

OTA-PEN 5 101% with OTAPEN 6 out of service, with PEN


T10 switched out

Install one 220 kV


PAK-PEN cct

HEN-SWN 1 101% with HENOTA 1 out of service

Install one 220 kV cable


PEN-HOB-WRU-ALB plus
HOB and WRU GXPs

LST-HOB 1(2) o/l with LSTHOB 2(1) out of service

Special protection scheme; if


one cable trips, its parallel
circuit is taken out of service.

nd

LST-PEN 1(2) o/l with LST-PEN


2(1) out of service

2020

1191 MW

OTA-PEN 2 102% with PEN


T10 out of service

Special protection scheme;


Intertrip OTA-PEN 2 with
PEN T10, leaving PEN T12
to take the load

2023

1256 MW

LST-PEN 1 & 2 100% with


HOB-PEN 1 out of service

Split Vector network between


HOB and LST.

HOB has no n-1 security with


the HOB-LST split

Install a second
interconnecting
transformer at HOB.
nd
Assume 2 WRU 220/33 kV
supply Tx is installed and
110 kV supply taken out of
service

2024

1279 MW

Notes

WRU load approximately equal


to total 110 kV supply capacity

Leaving the new PEN


interconnecting
transformer in service
delays the need to
split Vectors
HOB-LST connection
and therefore delays
the second
interconnecting
transformer at HOB
from 2021to 2023
Due to new
interconnecting
transformer at HOB
being operated in
parallel with the LSTPEN 110 kV cables:

One PEN
interconnecting
transformer may be
removed (or the
OTA-PEN 2 cct may
be removed)

Later than in original


GUP due to the new
assumption that
James St Load
(about 33 MW)
remains shifted to
ALB 33.

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

25

Attachment B: Technical Report May 2008 Revision

2026

1323 MW

HEN-SWN 1 100% with HENOTA 1 out of service


OTA-PEN 6 100% with PAKPEN 1 out of service

2028

1366 MW

HEN-HEP 1-4 100% with OTA


T3 or T5 out of service

Reduce impedance of PENHOB cable reactor to 12.4


Ohms
Install second PAK-PEN
cable

Brought forward by
reduction in PENHOB reactor and
consequent increase
in power flow north
out of PEN

Install one PEN-ROS 220 kV


feeder and 220/110 250 MVA
15% interconnecting
transformer at ROS

HEN T1 102% with HEN T5 out


of service
Two of HEN-SWN 1,
HEN-OTA 1 & HOB-PEN 1
95% loaded with any one out of
service
PAK-PEN 1 100% with PAKPEN 2 out of service

Install reactors in
PAK-PEN cables to balance
load flow between these and
OTA-PEN 5 & 6 o/h circuits

1.2 Ohm reactance is


about right

May change as the


existing MDN
transformers may be
replaced in the near
future

2031

1435 MW

MDN T1 101% with T2 out of


service

Install a 3rd
interconnecting
transformer at Marsden
equivalent to the existing
T1 & T2

2036

1554 MW

HEN-SWN 1 100% with HENOTA 1 out of service

Install 2 cross-harbour
cable direct from Penrose
to Albany

nd

HOB-PEN 1 99% with HENSWN out of service

2038

1605 MW

PAK-PEN 1 101% with PAKPEN 2 out of service


OTA-PEN 6 98% with PAKPEN 1 out of service

2040

1656 MW

HEN-HEP 1-4 highly loaded


with PEN-ROS 1 out of service

Increase rating of these


circuits by adding forced
cooling
Bypass PAK-PEN circuit
reactors to reduce load on
OTA-PEN 5 & 6

An upgrade of these
circuits (presently 75
wolf) or a second
PEN-ROS circuit will
be required within 2
3 years

*Note: Upgrading PAK-PEN 1 & 2 in 2038 will involve cooling stations for the cable cooling system.

5.1.2

Reactive Plan
The reactive plan includes the common support shown in Table 4-3 as well as that listed
in the table below:
Table 5-2: Option 1 Voltage Support Plan
YEAR

Location

Quantity
(Mvar)

Static(S) /
Dynamic(D)

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

26

Attachment B: Technical Report May 2008 Revision

5.1.3

2022

HEN

50

2028

ALB

100

2034

HEN

50

Single Line Diagram


Figure 5-1: Option 1 - Development Plan Single Line Diagram

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

27

Attachment B: Technical Report May 2008 Revision

5.2

Option 2 High Temperature Conductor


This option involves upgrading the existing 220 kV overhead double-circuit line from
Otahuhu to Henderson, including replacing existing conductor with high-temperature
conductor (HTC), and upgrading the existing 110 kV transmission system with HTC as
required. Assume no new lines are built until all HTC upgrade options have been
exhausted.

5.2.1

Development Plan
Table 5-3: High Temperature conductor development plan
Year

NAaN load

Limitation

2009

910 MW

OTA T2 & T4 & PEN T10 do


not provide n-1 security to 110
kV loads they supply

Install a 2 250 MVA 15%


interconnecting
transformer at PEN

2013

1025 MW

OTA-PEN 5 102% with OTAPEN 6 out of service

Special protection scheme;


take PEN T10 out of service
when either 220 kV OTAPEN circuit trips

2016

1097 MW

OTA-PEN 5 101% with OTAPEN 6 out of service, after


PEN T10 is switched out

Install one 220 kV


PAK-PEN circuit

HEN-SWN 1 101% with HENOTA 1 out of service

2018

1144 MW

HEN T1 100% with HEN T5


out of service

2020

1191 MW

ALB-HEN 1 & 2 102% with


ALB T4 out of service

2021

1213 MW

MNG-ROS 1&2 101% with


HEN-SWN 1 out of service
ALB-HEN 3 100% with HENHPI 1 out of service

2024

1279 MW

OTA T5 101% with T3 out of


service

HEN-WEL 1 & 2 101% with


HPI-MDN 1 out of service

Augmentation

Notes

nd

High temperature
conductor on HEN-OTA
circuits
Replace HEN transformers
with two 250 MVA 7%
interconnecting
transformers
Install a second
interconnecting
transformer at ALB equal
to existing
Upgrade MNG-ROS circuits
to high temperature
conductor
Upgrade terminal spans to
duplex zebra conductor
Install a third
interconnecting transformer
at OTA in parallel with and
equivalent to T5
Thermal upgrade of HEN-WEL
o
1 & 2 from 50 C Coyote to
o
75 C coyote

OTA-ROS 1 & 2 108% with


HEN-OTA 1 out of service

High temperature
conductor on OTA-ROS
circuits

2025

1301 MW

OTA-PEN 2 100% with PEN


T10 out of service

Special protection scheme:


Trip OTA-PEN 2 with PEN
T10

2028

1366 MW

MNG-OTA 1 100% with MNGOTA 2 out of service

High temperature
conductor on the
MNG-OTA 1 & 2 circuits

2029

1388 MW

HEN-HPI 1 100% with ALB-

Upgrade HEN-HPI 1 to

Brought forward by
the lower impedance
rd
at OTA due to 3
interconnecting
transformer

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

28

Attachment B: Technical Report May 2008 Revision

2030

1411 MW

HEN 3 out of service

high temperature
conductor

MDN T1 101% with T2 out of


service

Install a 3rd
interconnecting
transformer at Marsden
equivalent to the existing
Assume by now PEN T10 has
been replaced due to condition
with 15% 250 MVA
interconnecting transformer.
Install reactor on OTA-PEN 2
to balance load flow into
PEN110

Pen T10 is 1972,


nearly 60 yrs old by
this time. If this is not
the case, increase
T10 impedance with
a reactor

ALB-HEN 3 100% with HENHPI 1 out of service

High temperature
conductor on ALB-HEN 3

Likely do this at same


time as HEN-HPI 1

OTA T4 101% with T2 out of


service

Special protection scheme


trip T2 & T4 together. PEN
interconnecting transformers
take the load

PEN T12 100% with PEN T10


& OTA-PEN 2 out of service
(Special protection scheme)

2032

2036

1458 MW

1554 MW

HEN-SWN 1 100% with HENOTA 1 out of service

ALB-HEN 1&2 100% with HENHPI 1 out of service


PAK-PEN 1 overloads for
various outages due to
installation of new PEN-ROS
circuit

2039

1631 MW

2040

Install 10 Ohm reactors in


ALB-HEN 1&2 circuits
nd

Install 2
circuit

220 kV PAK-PEN

HEP-ROS 1&2 overload with


HEN-SWN 1 out of service
due to new PEN-ROS circuit

Upgrade HEP-ROS circuits


to high temperature
conductor

HEN-WEL 1&2 100% with


HPI-MDN 1 out of service

High temperature
conductors on HEN-WEL 1
&2

ALB-HPI 1 101% with ALBHEN 3 out of service

Upgrade ALB-HPI 1 to high


temperature conductor

HEN-OTA 1 96% with HENSWN 1 out of service

5.2.2

Install PEN-ROS cable and


250 MVA interconnecting
transformer at ROS

Likely done at same


time as HEN-HPI 1

First ALB-PEN cable


will be required within
about 2 years

Reactive Plan
The reactive plan includes the common reactive plant shown in table 4-3 well as the
reactive plant support listed in the table below.
Table 5-4: Option 2 Voltage Support Plan
YEAR

Location

Quantity
(Mvar)

Static(S) /
Dynamic(D)

2016

ALB

50

2016

HEN

100

2024

ALB

50

2026

HEN

100

2030

ALB

50

2038

ALB

50

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

29

Attachment B: Technical Report May 2008 Revision

5.2.3

Single Line diagram


Figure 5-2: Option 2 Development Plan Single Line Diagram

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

30

Attachment B: Technical Report May 2008 Revision

5.3

Option 3 New interconnection at Roskill


This option involves reinforcing the 110 kV system across Auckland prior to installing the
cross-harbour cable. This involves adding an interconnection at Mount Roskill, supplied at
220 kV from Penrose.

5.3.1

Development Plan
Table 5-5: New Interconnection at Roskill
Year

NAaN load

2009

910 MW

Limitation
OTA-PEN 5 (6) exceeds
branch capacity when cct 6 (5)
is out of service
OTA T2 & T4 & PEN T10 do
not provide n-1 security to 110
kV loads they supply

Augmentation
Remove branch restriction
nd

Install a 2 250 MVA 15%


interconnecting
transformer at PEN

2013

1025 MW

OTA-PEN 5 102% with OTAPEN 6 out of service

Special protection scheme;


take PEN T10 out of service
when either 220 kV OTAPEN cct trips

2016

1097 MW

OTA-PEN 5 101% with OTAPEN 6 out of service, with


PEN T10 switched out

Install one 220 kV PAKPEN cable

HEN-SWN 1 101% with HENOTA 1 out of service

Notes

Install PEN-ROS cable and


250 MVA interconnecting
transformer at ROS
nd

2020

1191 MW

ALB-HEN 1 & 2 101% with


ALB T4 out of service

Install 2 interconnecting
transformer at ALB,
equivalent to ALB T4

2022

1234 MW

HEN-SWN 1 100% with HENOTA 1 out of service


HEP-ROS 2 101% with HENOTA 1 out of service

Install 2 interconnecting
transformer at ROS
Upgrade a single span to
get the full capacity of the
existing HEP-ROS 1&2
circuits (184/202 MVA)

2023

1256 MW

PAK-PEN 1 101% with OTAPEN 6 out of service

Install a series reactor (1.2


Ohm) in this circuit to
balance flow between this
and OTA-PEN 5&6

2024

1279 MW

HEP-ROS 2 102% with HENSWN 1 out of service

Upgrade HEP-ROS 1 & 2


o
o
from 75 C wolf to 90 C wolf

2026

1323 MW

HEN-SWN 1 100% with HENOTA 1 out of service

Install first PEN-HOBWRU-ALB cable and HOB


and WRU GXPs

Vectors WRU load exceeds


the capacity of their 110 kV
supply system

Install 2 supply
transformer at WRU

OTA-PEN 5 & 6 overload with


PAK-PEN 1 out of service

Install a second 220 kV


PAK-PEN cable (including
a series reactor)

nd

nd

Balancing the power


flow delays the cable
installation work for
~3 yrs, until the cross
harbour cable is
installed
This delays need for
cross-harbour by
about 2 years

Assuming that the


reinforcement that
Vector do in 2010 is
removed to allow for
installation of the
220 kV ALB-WRU
cable

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

31

Attachment B: Technical Report May 2008 Revision

OTA-PEN 2 o/l with PEN T10


out of service

Special protection scheme


to take OTA-PEN 2 out of
service when PEN T10 trips

2028

1366 MW

OTA T4 102% with OTA T1


out of service

Special protection scheme


inter-trip OTA T4 with OTA T2

2031

1435 MW

MDN T1 100% with T2 out of


service

Install a third
interconnecting
transformer at MDN
equivalent to existing

2032

1458 MW

OTA-PEN 2 101% with PEN


T12 out of service

Install a series reactor (10


Ohms) on OTA-PEN 2 to
balance flow between this
circuit and the two
interconnecting
transformers.

2036

1554 MW

Vector lose n-1 security on


their PEN-LST cables about
this time

Assume 2 HOB
interconnecting
transformer is installed at
this time, and LST-HOB
cables and PEN-QUAY
cable are normally open

2040

1656 MW

PAK-PEN 1 101% with PAKPEN 2 out of service

Upgrade these cables to


force-cooled, increasing
capacity from 660 MVA to
1100 MVA

HEN-OTA 1 100% with HENSWN 1 out of service

Install the second cross


harbour cable, ALB-PEN

HEN-WEL 1 & 2 100% with


HPI-MDN out of service

Reconductor these circuits

PEN interconnecting
transformers take the
load

If T10 hasnt been


replaced by this time,
increase its
impedance using a
series reactor (5
Ohms). PEN T10 is
circa 1972

nd

Bypass series
reactors to reduce
load on OTA-PEN 5
& 6 circuits

*Note: Upgrading PAK-PEN 1 & 2 will involve cooling stations for the cable cooling system.

5.3.2

Reactive Plan
The reactive plan includes the common reactive plant shown table 4-3 as well as the
reactive plant listed in the table below
Table 5-6: Option 3 Voltage Support Plan
YEAR

Location

Quantity
(Mvar)

Static(S) /
Dynamic(D)

2016

ALB

50

2018

HEN

50

2028

HEN

50

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

32

Attachment B: Technical Report May 2008 Revision

5.3.3

Single Line Diagram


Figure 5-3: Option 3 Development Plan

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

33

Attachment B: Technical Report May 2008 Revision

5.4

Option 4 New generation north of Auckland


This option involves installation of new generation in the North Isthmus area, connected
into the 220 kV HPI-MDN circuit.
This development plan is provided for information only.

5.4.1

Development Plan
Table 5-7: New generation north of Auckland
Year

NAaN load

2009

910 MW

Limitation
OTA-PEN 5 (6) exceeds
branch capacity when cct 6
(5) is out of service
OTA T2 & T4 & PEN T10 do
not provide n-1 security to 110
kV loads they supply

Augmentation
Remove branch restriction
nd

Install a 2 250 MVA 15%


interconnecting
transformer at PEN

2013

1025 MW

OTA-PEN 5 102% with OTAPEN 6 out of service

Special protection scheme;


take PEN T10 out of service
when either 220 kV OTAPEN cct trips

2016

1097 MW

OTA-PEN 5 101% with OTAPEN 6 out of service, with


PEN T10 switched out

Install one 220 kV PAKPEN cable

HEN-SWN 1 101% with HENOTA 1 out of service

Install 120 MW generation


at Rodney connected to
the HPI-MDN 1 circuit

2018

1144 MW

HEN T1 102% with T5 out of


service

Replace HEN T1 & T5 with


two 250 MVA 7%
interconnecting
transformers

2019

1167 MW

ALB-HEN 1 & 2 100% with


ALB T4 OOS

Install a second ICT at ALB


equivalent to ALB T4

2020

1191 MW

HEN-SWN 1 100% with HENOTA 1 out of service

Install one ROS


interconnecting
transformer with a single
220 kV cable feeder from
PEN

2025

1301 MW

OTA-PEN 2 101% with PEN


T10 out of service

Install a 9 Ohm series


reactor in OTA-PEN 2 cct to
balance power flow with PEN
interconnecting transformers

2026

1323 MW

OTA-PEN 6 100% with PAKPEN 1 out of service

Install a second 220 kV


PAK-PEN cable

2028

1366 MW

HEN-OTA 101% with HENSWN out of service

Increase ROD generation


from 120 MW to 240 MW

2030

1411 MW

MDN T1 101% with T2 out of


service

Install a third
interconnecting
transformer at MDN
equivalent to existing

2032

1458 MW

HEN-SWN 1 101% with HENOTA 1 out of service

Install a second
interconnecting
transformer at ROS
Upgrade HEP-ROS 1 & 2 to

HEP-ROS 1 o/l with HEN-

Notes

Not required in other


options where the
new WRU GXP takes
load from ALB 110

nd

A 2 interconnecting
transformer at ROS
would overload
HEP-ROS

Brought forward by

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

34

Attachment B: Technical Report May 2008 Revision

SWN 1 out of service

PAK-PEN 1 100% with PAKPEN 2 out of service

2036

1554 MW

HEN-OTA 1 101% with HENSWN 1 out of service and vice


versa
Vector lose n-1 security on
their PEN-LST cables about
this time

90 C wolf

Install series reactors on


PAK-PEN 1 & 2
Install the first cross
harbour cable PEN-HOBWRU-ALBN, and HOB and
WRU GXPs
nd
Assume 2 HOB
interconnecting
transformer is installed at
this time, and LST-HOB
cables and PEN-QUAY cable
are normally open
nd

Vectors WRU load exceeds


the capacity of their 110 kV
supply system

2040

5.4.2

1656 MW

the installation of a
second
interconnecting
transformer at ROS

Install 2 interconnecting
transformer at WRU

Assuming that three


200 MVA cables
supply the CBD from
PEN (a new PENQUAY is installed by
Vector around 2013)
Assuming that the
reinforcement that
Vector do in 2010 is
removed to allow for
installation of the
220 kV ALB-WRU
cable

OK

Reactive Plan
The reactive plan includes the common reactive plant shown table 4-3 as well as the
reactive plant listed in the table below.
Table 5-8: Option 4 Voltage Support Plan

5.4.3

YEAR

Location

Quantity
(Mvar)

Static(S) /
Dynamic(D)

2016

ALB

50

2022

HEN

50

2024

ALB

50

2038

HEN

50

Single Line Diagram

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

35

Attachment B: Technical Report May 2008 Revision

Figure 5-4: Option 4 - Single Line Diagram

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

36

Attachment B: Technical Report May 2008 Revision

Discussion on Reactive Plans


The reactive power losses in the power system increase quadratically as the loading in
the transmission circuits are increased. The reactive power losses in the transmission
circuits are supplied from the two ends of each transmission circuit. Generally a higher
amount of reactive power needs to be supplied from the receiving end compared to the
sending end.
For the cross-Auckland transmission, the sending end reactive power requirements are
supplied from the reactive support at Otahuhu. The reactive power available from
Otahuhu based on the NI GUP reactive plan Option 2 is sufficient to provide this reactive
requirement. Additionally, planned and committed reactive power support in the NAaN
area will be sufficient to meet the reactive power losses in the transmission system until
at least 2010.

6.1

Static Reactive Requirements


For each modelled option, sufficient reactive power was supplied at the Henderson,
Albany and Marsden 220 kV buses to maintain 1.02 pu voltage at these buses at peak
load times and with normal operating configuration. The additional static reactive support
required in the NAaN area for the four transmission options is shown in Figure 6-1.
Figure 6-1: Reactive Support Requirement in NAaN Area
900

800

700

600
Option 1
Option 2

MVAR

500

Option 3
Option 4

400

300

200

100

0
2010

2015

2020

2025

2030

2035

2040

Year

6.2

Dynamic Reactive Requirements


The reactive power loss in the transmission system north of Otahuhu may undergo a
significant step change following an outage of a transmission circuit. In a voltage stability
constrained system such as the power system supplying the NAaN region, it is not
prudent to rely on post-contingency switching of the capacitor banks for ensuring system
stability. It is considered good industry practice to carry sufficient dynamic reserves in the
system, pre-contingency, to cater for such events. The dynamic reactive power reserves

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

37

Attachment B: Technical Report May 2008 Revision

can be maintained in the form of reactive power from synchronous generators,


synchronous condensers, SVCs and thyristor switched capacitors.
In analysing the dynamic reactive power reserves required in NAaN region for power
transmission north from Otahuhu, the total reactive power supplied to the transmission
system from Henderson, Albany and Marsden under the worst contingency is assessed
both pre and post-contingency. The reactive power difference between the pre and postcontingency situation represents the minimum level of dynamic reactive reserves required
at these substations.
By 2010, it is likely that the dynamic reactive support in the Northland area will be
supplied from three sources; synchronous condensers at Marsden and Henderson (1 x 60
Mvar and 2 x 50 Mvar respectively) and an SVC at Albany (100 Mvar). The dynamic
reactive power requirements for Option 1, 2, 3 and 4 are shown in Figure 6-2, Figure 6-3,
Figure 6-4 and Figure 6-5.
Figure 6-2: Dynamic reactive requirement for Northland for Option 1
120

100

MVAr

80

MDN dynamic
ALB dynamic
HEN dynamic

60

40

20

0
2005

2010

2015

2020

2025

2030

2035

2040

Year

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

38

Attachment B: Technical Report May 2008 Revision

Figure 6-3: Dynamic reactive requirement for Northland for Option 2


120

100

MVAr

80

MDN dynamic
ALB dynamic
HEN dynamic

60

40

20

0
2005

2010

2015

2020

2025

2030

2035

2040

Year

Figure 6-4: Dynamic reactive requirement for Northland for Option 3


120

100

80

MVAr

MDN dynamic
ALB dynamic

60

HEN dynamic

40

20

0
2005

2010

2015

2020

2025

2030

2035

2040

Year

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

39

Attachment B: Technical Report May 2008 Revision

Figure 6-5: Dynamic reactive requirement for Northland for Option 4


120

100

MVAr

80
MDN dynamic
ALB dynamic
60

HEN dynamic

40

20

0
2005

2010

2015

2020

2025

2030

2035

2040

Year

The graphs for each option indicate that the existing dynamic support (at Marsden) plus
that already committed (Albany SVC) and under consideration (Henderson condensers) in
the NAaN region will be sufficient to maintain a stable power system following the worst
likely single transmission contingency.

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

40

Attachment B: Technical Report May 2008 Revision

Summary
The existing transfer limit into the NAaN area is limited by the capacity of the 220 kV HEN
OTA circuits. This limit will be reached by winter 2011. One interim measure planned to
increase this transfer limit is closing the 110 kV HEP-ROS split.
Under present load growth forecasts and with existing interconnecting transformers in
service, the power flow will be well balanced between the 220 and 110 kV systems when
the HEP ROS split is closed. This allows the best possible load transfer given the circuit
ratings. Where interconnecting transformers are added in the reinforcement plans, 15%
impedance is preferred as the standard value except where a variation is required to
achieve a higher n-1 transfer limit, or where the new transformer has to match an existing
transformer.
To increase the transfer limit into the NAaN area further, four transmission options have
been developed and analysed. Each option takes a different approach to supplying the
increasing NAaN area load for the next thirty years. The four options are:
1.

A new 220 kV cable circuit across Auckland from Penrose to Albany

2.

Replacing existing 220 & 110 kV conductors with High Temperature Conductors

3.

Additional 220/110 kV interconnection to increase transmission across the


existing 110 kV transmission system

4.

New generation in the NAaN area used to delay new transmission options

A new 220 kV cable circuit is required to be built by winter 2016 in option 1. The new
transmission system reaches its capacity by 2028 when the 110 kV system needs to be
reinforced, and then in 2036 the transmission capacity needs to be further augmented by
adding a second 220 kV cable.
Option 2 minimises the number of new lines required to be built. Existing circuits are
upgraded using high temperature conductor; the first upgrade being required by 2016.
The entire 110 and 220 kV systems from Otahuhu to Henderson must be upgraded as the
load increases, beginning with the 110 kV MNG-ROS and 220 kV HEN-OTA circuits.
Eventually in 2036 an interconnection is required at Mount Roskill to prevent the
upgraded lines from overloading.
This option has the highest reactive support requirement of all those studied, being about
double that of the other options. By the end of the study period this option has about
800 Mvar of support in the NAaN region, compared to about 400 Mvar for the other
options.
Option 4 assumes that new generation is installed north of Auckland, reducing the load on
the cross-Auckland transmission system. This generation does not remove the
overloading on the 110 kV system, which is relieved by an interconnector at Mount Roskill
in 2017. Assuming a maximum of 240 MW of new generation in the Rodney area, the first
220 kV cable is required in 2033.
Reinforcement of the 110 kV system in preference to the 220 kV system is examined in
Option 3, where the Mount Roskill interconnection is installed in 2016 when the system
reaches its limit. This delays the reinforcement of the 220 kV system until 2025, when the
first
cross-harbour
cable
is
installed
between
Penrose
and
Albany.

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

41

Attachment B: Technical Report May 2008 Revision

Appendix A Existing Circuit Ratings


Table A-0-1: Existing Circuits in Upper North Island south of Albany

Circuit

Asset

Conductor

Conductor
Rating
(MVA)

Branch
Rating
(MVA)

ALB-HEN 1

ALB-HEN A

Simplex Wolf 80 C

ALB-HEN 2

ALB-HEN A

Simplex Wolf 80 C

ALB-HEN 3

ALB-HPI A &
HEN-MDN A

Duplex Zebra 71 C

HEN-HEP 1

HEN-ROS A

Simplex Wolf 75 C

96/105

96/105

96/105

96/105

680/756

561/617

92/101

92/101

92/101

92/101

92/101

92/101

92/101

92/101

938/985

915/915

Disconnector

938/985

915/915

Disconnector

184/202

114/114

Disconnector at 114
MVA then single span
at 174/191 MVA

184/202

114/114

Disconnector at 114
MVA then single span
at 174/191 MVA

355/390

305/305

Disconnector

355/390

305/305

Disconnector

92/101

92/101

HEN-HEP 2

HEN-ROS A

Simplex Wolf 75 C

HEN-HEP 3

HEN-HEP A

Simplex Wolf 75 C

HEN-HEP 4

HEN-HEP A

Simplex Wolf 75 C

HEN-OTA 1

HEN-OTA A

Duplex Zebra 120 C

HEN-SWN 1

HEN-OTA A

Duplex Zebra 120 C

HEP-ROS 1

HEN-ROS A

2 bonded Wolf 75 C

HEP-ROS 2

HEP-ROS A

2 bonded Wolf 75 C

MNG-OTA 1

MNG-OTA A

Duplex Zebra 75 C

MNG-OTA 2

MNG-OTA A

Duplex Zebra 75 C

MNG-ROS 1

MNG-ROS A

Simplex Wolf 75 C

MNG-ROS 2

MNG-ROS A

Simplex Wolf 75 C

Notes

200m simplex chukar

92/101

92/101

561/617

235/235

Earth fault relay

OTA-PAK 1

OTA-PAK A

Duplex Chukar 75 C

OTA-PEN 2

OTA-PEN A &
OTA-PEN B

2 bonded Wolf 75 C

184/202

174/191

Connecting spans of
simplex zebra

OTA-PEN 5&6

OTA-PEN C

Simplex Zebra 120 C

469/492

455/455

Transducer limit

OTA-PEN 7

OTA-PAK A

Duplex Chukar 75 C

561/617

Inactive

92/101

92/101

92/101

92/101

938/985

912/912

114/140

114/140

OTA-ROS 1

OTA-PEN B &
PEN-ROS A

Simplex Wolf 75 C

OTA-ROS 2

OTA-PEN B &
PEN-ROS A

Simplex Wolf 75 C

OTA-SWN 1

HEN-OTA A

Duplex Zebra 120 C

PAK-PEN 1

PAK-PEN A

2 Bonded 19/2.57 Cu 50 C

transducer

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

42

Attachment B: Technical Report May 2008 Revision

APPENDIX B - Interconnection Transformer Ratings


Table B-0-1: Ratings of Auckland Area 220/110 kV Interconnecting Transformers
IC
Transformer

Continuous

Summer

Winter

Notes

200

274

290

Limited to 267 MVA by MV &


HV protection settings

200

274

290

200

254

270

200

254

270

Limited to 229 MVA by MV


circuit breaker rating

200

274

290

Limited to 267 MVA by MV


circuit breaker rating

200

274

290

141

190

201

141

190

201

141

190

201

141

190

201

117

158

170

100

135

145

250

324

338

260

337

351

200

254

270

200

254

270

OTA T5

2-winding

250

318

332

PEN T10

206

309

313

200

296

300

ALB T4

HEN T1

HEN T5

MDN T1

MDN T2

OTA T2

OTA T3

OTA T4

Winding
(for 3 winding
transformers )

Limited to 183 MVA by tap


changer rating

Limited to 183 MVA by tap


changer rating

Limited to 291 MVA by HV


protection settings

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

43

Attachment B: Technical Report May 2008 Revision

Appendix C - Parameters of New Components Used


Table C-0-1: Parameters of New Components used in Studies
Component

Length (km)

R (Ohms)

X
(Ohms)

Winter
Rating
(MVA)

Summer
Rating
(MVA)

notes

ALB-WRU

8.45

0.127

1.463

543

630

cyclic
rating

HOB-WRU

9.85

0.152

1.618

543

630

cyclic
rating

HOB-PEN

10.21

0.183

1.133

543

630

cyclic
rating

Total (ALB-PEN)

28.51

0.462

4.214

543

630

cyclic
rating

220 kV PAK-PEN ccts - cable


section

8.6

0.085

1.424

667

667

Direct
buried

220 kV PAK-PEN ccts - cable


section

8.6

0.085

1.424

1115

1115

Forcecooled

220 kV PEN-ROS cable

10.2

0.153

1.766

543

630

cyclic
rating

4th ALB-WRU 110 kV cct (cable)

8.5

0.252

1.038

120

120

Vector's

LST-PEN 1&2

0.238

0.982

205

205

Vector's

LST-ROS 1

10.2

0.304

2.228

150

150

Vector's

HOB-LST 1&2

1.5

0.070

0.202

150

150

Vector's

HEN ICT1 & 2

0.2%

7%

318

338

Continuous
250 MVA

HOB ICT1 & 2

0.2%

15%

318

338

Continuous
250 MVA

ROS ICT1 & 2

0.2%

15%

318

338

Continuous
250 MVA

WRU T1 & 2

0.2%

15%

250

250

Continuous
250 MVA

ALB-HPI / ALB-HEN / HEN-HPI

1350

1300

R & X as
per
existing

HEN-OTA

1350

1300

R & X as
per
existing

x-harbour cables (ALB-PEN):

Vector CBD 110 kV cables:

Transformers:

High Temperature Conductor

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

44

Attachment B: Technical Report May 2008 Revision

HEP-ROS

350

340

R & X as
per
existing

MNG-OTA

670

660

R & X as
per
existing

MNG-ROS

180

170

R & X as
per
existing

OTA-ROS

180

170

R & X as
per
existing

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

45

Attachment B: Technical Report May 2008 Revision

Appendix D - Substation Codes


Table D-1: Substation 3-letter Codes
Short
Code

Site

Short
Code

Site

Short
Code

Site

Short
Code

Site

ABY

Albury

HEN

Henderson

MTR

Mataroa

TAK

Takanini

ADD

Addington

HEP

Hepburn Road

NMA

North Makarewa

TAP

Te Apiti

ALB

Albany

HIN

Hinuera

NPK

National Park

TCC

Taranaki
Combined
Cycle

ALD

Arnold

HKK

Hokitika

NPL

New Plymouth

TGA

Tauranga

ANC

Anchor Products (Te


Awamutu)

HLE

Huntly East
(Ohinewai)

NSY

Naseby

TIM

Timaru

ANI

Aniwhenua

HLY

Huntly

OAM

Oamaru

TKA

Tekapo A

APS

Arthurs Pass

HOR

Hororata

OHA

Ohau A

TKB

Tekapo B

ARA

Aratiatia

HPI

Huapai

OHB

Ohau B

TKH

Te Kaha

ARG

Argyle

HTI

Hangatiki

OHC

Ohau C

TKR

Takapu Road

ARI

Arapuni

HUI

Huirangi

OHK

Ohakuri

TKU

Tokaanu

ASB

Ashburton

HWA

Hawera

OKE

Okere

TMH

Three Mile Hill

ASY

Ashley

HWB

Halfway Bush

OKI

Ohaaki

TMI

Te Matai

ATI

Atiamuri

IGH

Inangahua

OKN

Ohakune

TMK

Temuka

AVI

Aviemore

INV

Invercargill

ONG

Ongarue

TMN

Taumarunui

BAL

Balclutha

ISL

Islington

OPI

Opihi

TMU

Te Awamutu

BDE

Brydone

KAI

Kaiapoi

OPK

Opunake

TNG

Tangiwai

BEN

Benmore

KAW

Kawerau

OPU

Opuha

TOB

Tokomaru Bay

BLN

Blenheim

KEN

Kensington

BHL

Brownhill (400 kV
Cable-Line
interface)

TRK

Tarukenga

BOB

Bombay

KIK

Kikiwa

ORO

Orowaiti Tee

TUI

Tuai

BPE

Bunnythorpe

KIN

Kinleith

OTA

Otahuhu

TVT

Teviot

BRB

Bream Bay

KKA

Kaikoura

OTB

Oteranga Bay

TWH

Te Kowhai

BRK

Brunswick

KOE

Kaikohe

OTC

Otahuhu CC

TWI

Tiwai

BRR

Branch River

KPI

Kapuni

OTG

Otahuhu Power
Station

TWZ

Twizel

BRY

Bromley

KPO

Karapiro

OTI

Otira

UHT

Upper Hutt

BWK

Berwick

KPU

Kopu

OWH

Owhata

UTK

Upper Takaka

CBG

Cambridge

KTA

Kaitaia

PAK

Pakuranga

WAA

Whareroa

CLH

Castle Hill

KUM

Kumara

PAL

Palmerston

WAH

Wahapo

CML

Cromwell

KWA

Kaiwharawhara

PAP

Papanui

WAI

Waiotahi

COB

Cobb

LFD

Lichfield

PEN

Penrose

WDV

Woodville

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

46

Attachment B: Technical Report May 2008 Revision

COL

Coleridge

LIV

Livingstone

PKE

Poike

WEL

Wellsford

CPK

Central Park

LTN

Linton

PNI

Pauatahanui

WES

Western Road

CST

Carrington Street

MAN

Manapouri

PPI

Poihipi

WGN

Wanganui

CUL

Culverden

MAT

Matahina

PRM

Paraparaumu

WHE

Wheao

CYD

Clyde

MCH

Murchison

PTA

Patea

WHI

Whirinaki

DAR

Dargaville

MDN

Marsden

RDF

Redclyffe

WHU

Waihou

DOB

Dobson

MGM

Mangamaire

RFT

Reefton

WIL

Wilton

DVK

Dannevirke

MHO

Mangahao

ROB

Robertson Street

WIR

Wiri

EDG

Edgecumbe

MLG

Melling

ROS

Mount Roskill

WKM

Whakamaru

EDN

Edendale

MNG

Mangere

ROT

Rotorua

WKO

Waikino

FHL

Fernhill

MNI

Motunui

ROX

Roxburgh

WMG

Waimangaroa

FKN

Frankton

MOK

Mokai

RPO

Rangipo

WPA

Waipapa

GFD

Gracefield

MOT

Motueka

RTR

Retaruke

WPI

Waipori

GIS

Gisborne

MPE

Maungatapere

SBK

Southbrook

WPR

Waipara

GLN

Glenbrook

MPI

Motupipi

SDN

South Dunedin

WPT

Westport

GOR

Gore

MRA

Moturoa

SFD

Stratford

WPW

Waipawa

GYM

Greymouth

MST

Masterton

SPN

Springston

WRA

Wairoa

GYT

Greytown

MTI

Maraetai

STK

Stoke

WRK

Wairakei

HAM

Hamilton

MTM

Mt Maunganui

STU

Studholme

WTK

Waitaki

HAY

Haywards

MTN

Marton

SVL

Silverdale

WTU

Whakatu

HBK

Highbank

MTO

Maungaturoto

SWN

Southdown

WVY

Waverley

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

47

Attachment B: Technical Report May 2008 Revision

Appendix E - Forecast Load Data


Table E-1: MW Load Forecast for Northland and Auckland as per EC Website April 2007

Year

Northland MW

Auckland MW

2007

839

1365

2008

870

1424

2009

910

1481

2010

1538

2011

978

1594

2012

1001

1638

2013

1025

1683

2014

1049

1730

2015

1073

1776

2016

1097

1822

2017

1121

1867

2018

1144

1912

2019

1167

1958

2020

1191

2004

2021

1213

2047

2022

1234

2090

2023

1256

2133

2024

1279

2179

2025

1301

2223

2026

1323

2266

2027

1345

2309

2028

1366

2351

2029

1388

2394

2030

1411

2439

2031

1435

2486

2032

1458

2531

2033

1482

2580

2034

1505

2626

2035

1529

2673

2036

1554

2724

2037

1579

2775

2038

1605

2826

2039

1631

2878

2040

1656

2930

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

48

Attachment B: Technical Report May 2008 Revision

Appendix F - Characteristic of NAaN Load


The graph below gives the 2006 load profile of the NAaN area based on half-hourly
SCADA logs of the HEN-OTA 1 and HEN-SWN 1 MW circuit loading.
Figure F-0-1: NAaN Area 2006 MW Load Profile
900
800
700
600
500
400
300
200
100

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

49

26/12/2006

26/11/2006

27/10/2006

27/09/2006

28/08/2006

29/07/2006

29/06/2006

30/05/2006

30/04/2006

31/03/2006

1/03/2006

30/01/2006

Attachment B: Technical Report May 2008 Revision

Appendix G - Characteristic of Penrose Load


The graphs below indicate the nature of the total load on the Penrose GXP. Data for
these graphs comes from half-hourly SCADA data for the 2006 calendar year.
There is occasional load shifting to Penrose from the Mount Roskill GXP. This makes the
summer/winter nature of the usual load unclear.
Figure G-0-1: Total 2006 Penrose GXP Load including 22 kV, 33 kV, Liverpool St Feeders and
Quay St Feeders

600

500

MW

400

300

200

100

31/12/06

1/12/06

1/11/06

1/10/06

1/09/06

1/08/06

2/07/06

1/06/06

2/05/06

2/04/06

2/03/06

31/01/06

Date

Figure G-2 below shows the load on the Liverpool St feeders from Penrose. The
occasional high peaks indicate periods when the lines company has shifted the Liverpool
St load from Mount Roskill to Penrose. Apart from those periods and an apparent step
change around August, the load on the Penrose-Liverpool St feeders is seen to be flat
across the year.

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

50

Attachment B: Technical Report May 2008 Revision

Figure G-0-2: 2006 Liverpool St Feeder Load

160
140
120

MW

100
80
60
40
20

31/12/06

1/12/06

1/11/06

1/10/06

1/09/06

1/08/06

2/07/06

1/06/06

2/05/06

2/04/06

2/03/06

31/01/06

Date

Figure G-3 shows the Penrose GXP load without the Liverpool St feeder load. This graph
indicates clearly that the Penrose loads as a whole are winter peaking, if load shifting from
Mount Roskill is avoided.
Figure G-3: 2006 Penrose Load without Liverpool St Feeder Load

400
350
300

MW

250
200
150
100
50

1/12/06

1/11/06

1/10/06

1/09/06

1/08/06

2/07/06

1/06/06

2/05/06

2/04/06

2/03/06

31/01/06

Date

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

51

Attachment B: Technical Report May 2008 Revision

Figure G-4 shows the annual load profile at Liverpool St supplied from Mount Roskill. This
may be added to the Penrose load under certain upgrade scenarios. The profile indicates
that Penrose will remain winter peaking overall if this load transfer occurs.
Figure G-4: 2006 Mount Roskill Liverpool St Feeder Load

120

100

MW

80

60

40

20

1/12/06

1/11/06

1/10/06

1/09/06

1/08/06

2/07/06

1/06/06

2/05/06

2/04/06

2/03/06

31/01/06

Date

Grid Upgrade Plan 2007 Instalment 1, Part III North Auckland and Northland Investment Proposal May 2008
Revision Transpower New Zealand Limited 2008. All rights reserved.

52

Das könnte Ihnen auch gefallen