construction?
Angelica Salas
18/03/14
1325065/7CN005
CONSTRUCTION
delivery
Making services as efficient as possible through the use of innovative
technologies and management techniques.
Above procedures can help for a more communicated design stage, but what
about planning? LC also provides a very successful tool that begins in the
planning stage and extents until the end of the project: Last Planner System.
The Last Planner System (LPS) was described by Kalsaas (2012) as A
practical approach in which construction managers and team leaders
collaborate to prepare work plans that can be implemented with a high
degree of reliability, thus improving work stability and predictability. He
explains how it differs from traditional planning by the uncertainty of making
predictions until all constraints are out of the way and can only be removed
in the final instance by the team leader, who is called Last Planner. LPS
can manage a project even if it is complex and uncertain, because of the
planning and control tools that provides. Nieto-Morote and Ruz-Vila (2011)
describe the three different schedules that are used in LPS:
1325065/7CN005
CONSTRUCTION
1. The master schedule is the entire project schedule and includes only the
major milestone.
2. The look-ahead schedule contains the activities that need to be completed
in order to successful execute the milestone at the times set in the master
schedule. These activities are reviewed to find the constraints and make sure
that it ends before the scheduled start date. The duration of the look-ahead
depends on the time to eliminate all constraints.
3. The short term schedule has duration of one week. Includes all activities
that need to begin in that week, in order to comply with the completion
dates of the look-ahead schedule.
With this schedules, LPS is able to reduce uncertainty, integrate all projects
participants and improve planning and controlling. When you implement a
new philosophy as LC or its tool LPS, it is inevitable to have challenges as
lack of integration, lack of commitment to the program, staff without
appropriate learning and resistance to change. Nevertheless, when the
success of this tools is experienced, these challenges become opportunities,
as everyone become more committed to the program.
The other approach that will help to simplify construction in all its stages is
BIM. Some people mistakenly think of BIM as just a new variety of software,
but is actually a process that relies on information rich models that helps to
more efficiently plan, design, construct, and manage building and
infrastructure projects (Autodesk, 2011). The truth is that with BIM,
miscommunication, design errors, and, in turn risk are mitigated, while
decision making is improved with the ability to use the model to simulate
nearly all aspects of the project (Autodesk, 2012). The overall advantage of
implementing BIM is that even though the algorithms that define the objects
created by the users are no less complex than those developed for CAD
applications, with BIM the software design and computation effort creates a
much closer to reality user experience that understands that these objects
1325065/7CN005
CONSTRUCTION
represent real world components (Smith and Tardif, 2009). As stated by the
BIM handbook (2008), these are some of the advantages of implementing
BIM in the design stage:
disciplines
Extract cost estimates during design stage: At any stage of the design,
BIM technology can extract an accurate bill of quantities and spaces
that can be used for cost estimation.
could be more approachable because the LPS get access to the most
complete and up to date information about the project in all its stages.
Therefore, by applying both methodologies, there will be a simultaneous
visualization of the product planning process, visualization of the BIM model,
and a mapping of the tasks to the corresponding BIM element. Problems
faced before with any change that the client will need, will be easily applied
with BIM, which means it will also be effortless change in the planning with
LPS. In fact, it is important to mention that there is a new research software
called VisiLean, which provides integration between lean workflow and the
BIM model. It aims to bring the simultaneous visualization of process and
product to production management through a single interface (Dave, Boddy
and Koskela, 2013). Imagine having the best of LC and BIM in one place,
being able to have a visual representation of the project through BIM with
planning.
Returning to the question posed at the beginning of this essay, applying
either LC or BIM will definitely simplify construction, but nothing as strong as
implementing both. BIM can be used effectively to address the conceptual
design of the LC principles and rapidly do any type of change that the client
will need. LC will achieve a more cooperative working environment, where
the designers will be able to work with the entire team and this will enhance
the communication. LPS as a tool of LC will help for a more predictable
construction, where variance will not be an issue anymore. Furthermore,
applying all this together will attack most of the problems faced during
planning and design, which will eventually lead to a more stable and inbudget construction. The biggest challenge with the implementation of this
tools its resistance to change, but research has shown that eventually when
they experienced success, people get more cooperative. Hence, the tools are
there, its not what could be done to simplify construction, but when we will
start simplifying construction?
1325065/7CN005
CONSTRUCTION
References
Autodesk (2011) Realizing the benefits of BIM. [online]. Available at:
<www.autodesk.com/bim>
Autodesk (2011) BIM for infrastructure: A vehicle for business transformation
[online]. Available at: <www.autodesk.com/bim>
Aziz, R.F. and Hafez, S.M. (2013) Applying lean thinking in construction and
performance improvement. Alexandria Engineering Journal [online], 52(4),
pp. 679-695 Available at: <http://www.sciencedirect.com>.
Dave,B., Boddy,S. and Koskela,L. (2013) Challenges and opportunities in
implementing lean and BIM on an infrastructure project. Proceedings of the
21st Annual Conference of the International Group for Lean Construction. ,
2013.
Eastman, C.M. (2008) BIM handbook: a guide to building information
modelling for owners, managers designers, engineers, and contractors.
[online] Chichester: Wiley.
El Reifi, M.H. and Emmitt, S. (2013) Perceptions of lean design management.
Architectural Engineering and Design Management [online], 9(3), pp. 195
Freire,J. and Alarcon,L. (2000) Achieving a lean design process. Proceedings
of the 8th Annual Conference of the International Group for Lean
Construction. , 2000.
Kalsaas, B.T. (2012) The last planner system style of planning: its basis in
learning theory. Journal of Engineering, Project, and Production Management
[online], 2(2), pp. 88-100 [Accessed 2/11/13]. Available at:
<http://www.ppml.url.tw/EPPM_Journal/>.