Sie sind auf Seite 1von 41

Aggregate Planning

Sasadhar Bera, IIM Ranchi

Outline
Production Planning Framework
Understanding Aggregate Planning
Demand Management and Capacity Options
Aggregate Planning Strategies
Aggregate Planning Input and Output
Different Solution Approaches to Aggregate
Planning Problems
Sasadhar Bera, IIM Ranchi

Production Planning System


A production plan requires both external and internal
inputs. It cannot be determined by only manufacturing
person alone.
Production plan includes external inputs such as
competitors behavior (new product introduction,
promotional price and special offers), raw material
availability, market demand, subcontracting capacity and
economic conditions of regions or country.
The internal inputs are workforce size and skills, available
machine capacity, and anticipated inventory level.

3
Sasadhar Bera, IIM Ranchi

Inputs in Production Planning


Competitors
behavior

External
capacity

Current
physical
capacity

Raw material
availability

Planning
for
production

Current
workforce

Inventory
levels

Market
demand

External
to firm

Economic
conditions

Activities
required
for
production

Internal
to firm

4
Sasadhar Bera, IIM Ranchi

What is Manufacturing Requirement Planning ?


Manufacturing Requirement Planning (MRP II) involves a
hierarchy of decisions. Its planning framework provides both
production and capacity decisions in different levels as
described below.
Sales and operations planning (S&OP) translates corporate
strategic and capacity plans to meet the demand in plant level.
The second level is master production schedule (MPS), in
which production plans are specified by individual product.
Third level material requirement plan (MRP) determines
subparts and material needed to produce a product. It
provides a procurement schedule.
Shop floor scheduling schedules the manufacturing operations
required to make each component.
Sasadhar Bera, IIM Ranchi

Manufacturing Requirement Planning MRP II


Production
Planning

Capacity
Planning

Resource
Level

Product lines or
families

Sales and
operation
planning
(S&OP)

Resource
requirements
plan

Plants

Individual
product

Master
production
schedule
(MPS)

Rough-cut
capacity plan
(RCCP)

Critical
work
centers

Components

Material
requirements
plan (MRP)

Capacity
requirements
plan (CRP)

All work
centers

Manufacturing
operations

Shop
floor
schedule

Input/ output
control

Individual
machine

Items

6
Sasadhar Bera, IIM Ranchi

Capacity Planning
In capacity planning, a resource requirement plan is
developed to verify that sales and operations plan can be
performed or achieved.
Rough-cut-capacity plan (RCCP) is quick check to see if the
master production schedule is feasible in terms of resource
requirements.
Capacity requirement plan (CRP) provides more details plan
that matches and adjusts the factorys machine and labour
resources to the material requirements plan.
Finally, input/output control monitors the production that
takes place at individual machine or work center.
7
Sasadhar Bera, IIM Ranchi

Overview of Planning Levels


Long-range planning: Planning is done annually and
focusing on a horizon of a year or more. Adjustments are
made usually quarterly or monthly. Long range planning are
product selection, determining facility size and location,
equipment decisions, and layout of facilities.
Intermediate-range planning: Covers a period of 6 to 12
months with weekly or monthly adjustments. Examples:
Material
requirement
planning
(MRP),
Capacity
requirement planning (CRP).
Short-range planning: Covers less than 6 months with
either daily or weekly monitoring activities. Examples:
machine loading, job assignment.
8
Sasadhar Bera, IIM Ranchi

What is Aggregate Planning ?


In operations and supply chain management, sales and
operations planning is called Aggregate Planning. An
aggregate planning is process for coordinating supply and
demand. The new terminology, aggregate planning,
captures both the cross functional activities viz. sales and
operations plan, and resource requirements plan in MRP II
framework. It is an intermediate-range planning, usually
covering 6 to 12 months.
The term aggregate refers to groups of product or product
families. The plans are developed for groups of product
rather than individual product. Choosing meaningful groups
require a thorough knowledge of the products as well as
manufacturing processes.
9
Sasadhar Bera, IIM Ranchi

What is Aggregate Planning ? (Contd.)


For example, an aggregate operation plan regarding motor
bikes manufacturng might specify how many bikes are to be
produced in each quarter in a year but not segregated by
colour, engine cylinder, and tires. In this case, product
families can be divided into two groups such as mountain
bikes, and road bikes.
Resource capacity is also expressed in aggregate terms,
typically as labour or machine hours. Labour hours would
not be specified by types of labour (full time or part time),
nor machine hours by types of machine.

10
Sasadhar Bera, IIM Ranchi

Dimension of Aggregation
Product families: Families are defined considering process
operations, workforce requirements and material
requirements. Sometimes product families is related to
market groupings such as location and customer segments.
Resource availability: Workforce skills and types, types of
machine.
Time: The planning horizon covered by aggregate planning
typically is one year, although it can differ in various
situations. Adjustments are made usually quarterly or
monthly. Hence company looks in aggregation in terms of
month, or quarter, or season.
11
Sasadhar Bera, IIM Ranchi

Why Aggregate Planning is Necessary?


Aggregate level forecasts are generally more accurate
than individual item forecast. Hence to cope up with
demand fluctuation, production should be planned in
aggregate to obtain effective resource utilization.
It is easy to incorporate corporate level strategy
considering aggregate level capacity and resources.

12
Sasadhar Bera, IIM Ranchi

Objective of Aggregate Planning


The main purpose of the aggregate plan is to specify the
optimal combination of production levels, workforce levels
and inventory levels in a time horizon. The objective
function is to minimize the total cost over a multi-period
planning horizon.
Given a demand forecast Ft for each period t in the
planning horizon that extends over T periods, determine
the production level Pt, workforce level Wt , and inventory
level It for periods t = 1, 2, . . ., T that minimizes total cost
over the planning horizon.

13
Sasadhar Bera, IIM Ranchi

Demand Management
The process of changing demand pattern using one or more
demand options is known as demand management. The
demand options to manage uneven demand are:
Pricing: Differentials pricing is commonly used to shift demand
from peak periods to the off-peak periods.
Promotion: Promotional campaigns such as advertising,
displays, and direct marketing, discount coupons.
Complementary product: Products that have similar resource
requirements but different demand cycles make demand
even.
Backorder: Taken customer order that is temporarily out of
stock and cannot be filled immediately but is filled as soon as
possible.
14
Sasadhar Bera, IIM Ranchi

Capacity Options
Anticipation inventory: The finished goods inventory in one
period can be used to absorb fluctuation of demand in
another period.
Workforce adjustment: Hire or layoff of workers to match
demand by producing more or less.
Overtime and under time: Increase or decrease working
hours during the day or fewer days per week in case of high or
low demand situation.
Subcontracting: Outsource from another firm to get supply of
components, subassemblies, or even an entire product in case
of high demand.
Part time workers: Hire part-time employees when they are
needed.
15
Sasadhar Bera, IIM Ranchi

Aggregate Planning Strategies


Aggregate planning evaluates alternative capacity sources
to find an economic strategy for satisfying demand. There
are two major strategies as described below:
Pure strategy: When one of the capacity options is used to
absorb demand fluctuation is known as pure strategy.
Mixed strategy: Two or more capacity options are used in
combination to constitute a mixed strategy. It may consider
combinations of all capacity options such as anticipation
inventory, workforce adjustments, part-time worker,
subcontract, and backorder to determine a feasible
production plan.
16
Sasadhar Bera, IIM Ranchi

Aggregate Planning Strategies (Contd.)


Level strategy: It is come under pure strategy. The
production rate kept constant and uses inventory to absorb
variations in demand. During period of low demand,
overproduction is stored as inventory. This inventory is to
be depleted in high demand period.

Units

Demand

Average Production

Time
17
Sasadhar Bera, IIM Ranchi

Aggregate Planning Strategies (Contd.)


Chase strategy: It is come under pure strategy. The chase
strategy involves in hiring and laying off workforce size to
match the demand over the planning horizon. Additional
workers are hired during high demand period and workers
are laid off in low demand period. This strategy is applicable
for low skill jobs.
Demand
Units

Production

Time
18
Sasadhar Bera, IIM Ranchi

Advantages and Disadvantages


Level strategy:
Workforce levels and production output are stable
Involve high inventory and labour costs

Chase strategy:
Reduce inventory costs
High level of workforce utilization
Cost involves in fluctuating workforce levels
Potential damage to employee morale

19
Sasadhar Bera, IIM Ranchi

Example: Toy Production Planning


Demand for Quantum Corporations action toy series
follows a seasonal pattern growing through the fall
months and culminating in December, with smaller peaks
in January.
MONTH
January

DEMAND
(CASES)
1000

February
March
April
May
June

400
400
400
400
400

MONTH
July

August
September
October
November
December

DEMAND
(CASES)
500

500
1000
1500
2500
3000
20
Sasadhar Bera, IIM Ranchi

Example: Toy Production Planning (contd.)


Each worker can produce on an average 100 cases of action toys
each month. Overtime is limited to 300 cases, and
subcontracting is unlimited. No action toys are currently in
inventory. The wage rate is $10 per case for regular production,
$15 for overtime production, and $25 for subcontracting. No
stock outs are allowed. Holding cost is $1 per case per month.
Increasing the workforce costs approximately $1,000 per worker.
Decreasing the workforce costs $500 per worker.
Management wishes to test the following scenarios for planning
production

i.

Level production over the 12 months

ii.

Produce to meet demand each month

21
Sasadhar Bera, IIM Ranchi

Example: Level Strategy


Input:

Beg. Wkrs 10

Regular

$10

Hiring

$1,000

Units/Wkr 100

Overtime

$15

Firing

$500

Beg. Inv.

Subk

$25

Inventory

Cost:

$146,000

$1

Month

Demand

Reg

OT

Subk

Inv

#Wkrs

#Hired

#Fired

Reg
Prod Cost

Inv
Cost

Jan

1000

1,000

10

10,000

Feb

400

1,000

600

10

10,000

600

Mar

400

1,000

1,200

10

10,000

1,200

Apr

400

1,000

1,800

10

10,000

1,800

May

400

1,000

2,400

10

10,000

2,400

Jun

400

1,000

3,000

10

10,000

3,000

Jul

500

1,000

3,500

10

10,000

3,500

Aug

500

1,000

4,000

10

10,000

4,000

Sept

1000

1,000

4,000

10

10,000

4,000

Oct

1500

1,000

3,500

10

10,000

3,500

Nov

2500

1,000

2,000

10

10,000

2,000

Dec

3000

1,000

10

10,000

Total

12,000

12,000

26,000

120,000

26,000
22

Sasadhar Bera, IIM Ranchi

Example: Chase Strategy


Input:

Beg. Wkrs 10

Regular

$10

Hiring

$1,000

Units/Wkr 100

Overtime

$15

Firing

$500

Beg. Inv.

Subk

$25

Inventory

Cost:

$149,000

$1

Month

Demand

Reg

OT

Subk

Inv

#Wkrs

#Hired

#Fired

Reg
Prod
Cost

Hiring/
Firing
Cost

Jan

1000

1000

10

10,000

Feb

400

400

4,000

3,000

Mar

400

400

4,000

Apr

400

400

4,000

May

400

400

4,000

Jun

400

400

4,000

Jul

500

500

5,000

1,000

Aug

500

500

5,000

Sept

1000

1000

10

10,000

5,000

Oct

1500

1500

15

15,000

5,000

Nov

2500

2500

25

10

25,000

10,000

Dec

3000

3000

30

Total

12,000

12,000

26

30,000
120,000

5,000
29,000

Sasadhar Bera, IIM Ranchi

23

Example: Subcontracting
Suppose that Quantum Corporation has decided to produce
600 units per month and meet rest of the demand by
subcontracting. It is also decided no overtime to the workers
and hiring/firing of workers.
What should be the total cost in such situation?

24
Sasadhar Bera, IIM Ranchi

Example: Subcontracting (Contd.)


Input:

Beg. Wkrs 10

Regular

$10

Hiring

$1,000

Units/Wkr 100

Overtime

$15

Firing

$500

Beg. Inv.

Subk

$25

Inventory

Month

Demand

Reg

OT

Subk

Inv

#Wkrs

Reg
Prod Cost

Inv
Cost

Subk
Cost

Jan

1000

600

400

6,000

10,000

Feb

400

600

200

6,000

200

Mar

400

600

400

6,000

400

Apr

400

600

600

6,000

600

May

400

600

800

6,000

800

Jun

400

600

1,000

6,000

1,000

July

500

600

1,100

6,000

1,100

Aug

500

600

1,200

6,000

1,200

Sept

1000

600

800

6,000

800

Oct

1500

600

100

6,000

2,500

Nov

2500

600

1,900

6,000

47,500

Dec

3000

600

2,400

6,000

60,000

Total

12,000

7,200

4,800

6,100

72,000

6,100

1,20,000

Cost:

$1,98,100

$1

Sasadhar Bera, IIM Ranchi

25

Aggregate Planning Input


Demand forecast

Resources
Workforce
Facilities
Policy statements
Overtime
Subcontracting
Inventory levels
Back orders

Costs
Regular time cost
Overtime cost
Hiring cost
layoff cost
Under-time cost
Subcontracting cost
Inventory carrying cost
Shortage cost/Back
order cost
Set-up cost
26
Sasadhar Bera, IIM Ranchi

Aggregate Planning Output


Total cost of a plan

Projected level of
Workforce
Inventory
Subcontracting
Back orders

27
Sasadhar Bera, IIM Ranchi

Solution Approaches to Aggregate Planning


Problems
The below mentioned solution approaches use
combinations of all capacity options (i. e. mixed strategy) to
determine optimal production plan.

I.
II.
III.
IV.

Linear programming approach


Transportation model based approach
Dynamic programming approach
Quadratic model HMMS Rule

28
Sasadhar Bera, IIM Ranchi

LP approach: Candy Production Planning


The Good and Rich candy company makes a variety of candies
in three factories worldwide. Given the quarterly sales
forecasts and costs, determine optimum production level,
workforce level, and inventory level.
Quarter
Spring
Summer
Fall
Winter

Sales forecast (lbs)


80,000
50,000
120,000
150,000

Hiring cost = $100 per worker , Layoff cost = $500 per worker
Inventory carrying cost = $0.50 per pound per quarter
Regular production cost per pound = $2
Production per employee = 1000 pound per quarter
Beginning workforce = 100 workers
29
Sasadhar Bera, IIM Ranchi

Problem Formulation: Candy Production Planning


Dt : demand at time t, where t = 1, 2, 3, 4 (four quarters)
Wt : workforce size at time t
Rt : regular quarterly production
Ht : Number of workers hired for time t
Ft : Number of workers layoff/fired for time t
It : Inventory (in units) at the end of time t
Zmin = 100 (H1 + H2 + H3 + H4)
+ 500 (F1 + F2 + F3 + F4)
+ 0.50 (I1 + I2 + I3 + I4)
+ 2 (R1 + R2 + R3 + R4)
30
Sasadhar Bera, IIM Ranchi

Problem Formulation: Candy Production Planning


Subject to
Demand constraint:

It-1 + Rt - Dt = It => It-1 + Rt - It = Dt


R1 - I1 = 80,000
(1)
I1 + R2 - I2 = 50,000
(2)
I2 + R3 - I3 = 120,000
(3)
I3 + R4 - I4 = 150,000
(4)
Production constraint: k Wt = Rt
1000 W1 = R1
(5)
1000 W2 = R2
(6)
1000 W3 = R3
(7)
1000 W4 = R4
(8)
Workforce constraint: Wt-1 + Ht Ft = Wt
100 + H1 - F1 = W1
(9)
Work force
W1 + H2 - F2 = W2
(10)
constraints
W2 + H3 - F3 = W3
(11)
W3 + H4 - F4 = W4
(12)
31
Sasadhar Bera, IIM Ranchi

Solution: Candy Production Planning


Beg Wkforce
Units/wker
Beg Inv.
Quarter
Spring
Summer
Fall
Winter
Total

100
1000
0

Prod. Cost
Inv. Cost

$2.00
$0.50

Demand Production Inventory


80,000 80,000
0
50,000 80,000
30,000
1,20,000 90,000
0
1,50,000 1,50,000
0
4,00,000 4,00,000
30,000

Firing cost
Hiring cost

$500
$100

Worker Worker Worker


Needed Hired Fired
80
0
20
80
0
0
90
10
0
150
60
0
70
20

Total cost = 4,00,000*2 + 30,000*0.5 + 70*100 + 20*500


= $8,32,000
Note: Overtime and subcontracting is not considered in this
formulation
Sasadhar Bera, IIM Ranchi

32

Transportation model based Approach


This approach is restricted version of linear programming
approach. Transportation model based approach considers
six different cost components viz. regular time, and
overtime cost, subcontracting, and under-time cost,
inventory and shortage cost.

This approach does not consider variable workforce costs


(hiring/layoff). Another cost component, set-up cost,
cannot be incorporated in this model. But linear
programming approach can consider set-up cost
component. Computation time is less in case of
transportation model due to the special structure of the
model.
33
Sasadhar Bera, IIM Ranchi

Transportation Model based Approach (Contd.)


r, o, and c regular, overtime, and subcontracting cost. i is
inventory holding cost /period. M indicates very large value,
no allocation is possible in this cell.

34
Sasadhar Bera, IIM Ranchi

Transportation Model based Approach (Contd.)


In this tableau back order is allowed. Cell having cost (r +2b)
indicates that cost at period 3 for demand of period 1. b is
back order cost/period.

Sasadhar Bera, IIM Ranchi

35

Example: Transportation Model based Approach

36
Sasadhar Bera, IIM Ranchi

Example: Transportation Model based Approach

37
Sasadhar Bera, IIM Ranchi

Example: Transportation Model based Approach

It is to be noted that Northwest corner rule is used to get


initial solution with minimum cost allocation. It may not be
optimal solution. The optimal solution is generated by using
stepping stone method or modified distribution method.
38
Sasadhar Bera, IIM Ranchi

Dynamic Programming Solution Approach


In this approach, generally three costs are considered viz.
set-up cost, regular production cost and inventory carrying
cost.
Decision variable is the amount of quantity that should be
produced in each time period in a planning horizon. The
state variable is the amount of inventory available at the
beginning of each period.
Objective function is total cost (set-up + production +
inventory).
Wagner and Whitin algorithm (1958) used to get optimal
solution.
39
Sasadhar Bera, IIM Ranchi

Quadratic Model HMMS Rule


Quadratic model was developed by Holt, Modigliani, Muth,
and Simon (1960) is known as HMMS rule. The decision
variables considered in this model are production levels,
workforce size, and inventory levels.
The objective function is quadratic, not linear but
constraints are linear. The cost components considered in
objective function are regular production cost, hiring and
layoff cost, overtime and under-time cost, inventory and
shortage cost. All cost components are in quadratic form.

The optimization technique is similar to quadratic


optimization problem. This model gives closer results
towards actual situation because in actual practice cost
component are not linear.
40
Sasadhar Bera, IIM Ranchi

References
i.

Production Planning and Inventory Control, Narasimhan,


McLeavey, Billington, 2th edition, Prentice Hall India.

ii.

Operations Management: Processes and Supply Chains,


Krajewski, Ritzman, Malhotra, and Srivastava, 9th edition,
Pearson publication.

iii. Operations Management, Russell and Taylor, 7th edition,


International student edition.
iv. Operations Management: Concepts, Techniques, and
Applications, Evans and Collier, Cengage learning India
edition.

v.

Introduction to Material Management, Arnold, Chapman,


and Clive, 6th edition, Pearson publication.
Sasadhar Bera, IIM Ranchi

41

Das könnte Ihnen auch gefallen