AT TALEGAON DEPOT SPECIFICATION FOR STRUCTURAL WORKS 1. Wind Loads Wind loads shall generally be as per IS: 875. The basic wind speed of the site is taken as 47 m/s. Values of coefficients k1, k3 shall be as: k1 = 1 for permanent structures k3 = 1 Value of coefficient k2, as in IS: 875, shall be suitably taken for relevant class of structure with Category 3 terrain w.r.t. actual height of the structure for UNITS and Category 2 for remaining areas. The mean probable design life of all structures (units & offsite) shall be taken as 50 years. To account for surface area of piping, platforms and other attachments fixed to the equipment the surface area of the equipment (vessel/column) exposed to wind shall be increased by 20%. 2. Seismic Loads Seismic forces shall designed as per Zone 4 of IS: 1893
3. Anchor Bolt Design
- Grade of concrete is M30 for foundations and M25 for superstructure conforming to IS: 456:2000 - Permissible bearing Stress in concrete is 12 & 10 N/mm2 for M30 & M25 respectively. - Maximum Permissible stresses in mild steel bolts of property class 4.6 (IS: 1367-1967) shall be: Axial Tension 120 N/mm2 Shear 80 N/mm2 Bearing 250 N/mm2 4. Structural Steel Materials: Hot Rolled Structural Steel Sections shall conform to the following BIS Codes of practice: IS: 808 Indian Standard on dimensions of Hot Rolled Steel Beams, Columns, Channel and Angles IS: 12778Indian Standard on Hot Rolled Parallel Flanged Steel Sections for Beams, Columns and Bearing Piles IS: 2062Indian Standard on Steel for General Structure purposes Specifications 5. GRATINGS Floor gratings shall be fabricated from mild steel. These shall be honey combed type and as per attached standard drawing. 6. HANDRAILS Hand rails shall be pipe conforming to IS: 1239 with top rail as 32 NB (M) and vertical stands of ISA 75 x 75 @ 1.5 M Centre to centre with toe guard of 100 mm flat section and mid guard of 50 mm flat section. Page 2 of 3
VAPOUR RECOVERY SYSTEM TO COMPLY EMISSION NORMS
AT TALEGAON DEPOT 7. LADDERS Ladders shall be as per bidders standard specifications and a copy of the same shall be attached to offer. 8. LOADING Live loading on service Platform shall be - 3.0 kN/m2 9. PAINTING All steel structures, equipment, vessels, pipelines, the underside of the skid and bought in item MS must be shot blast to (SA 2 ), prior to painting. One coat (DFT 60 microns) of inorganic Zinc Silicate primer followed by one suitable intermediate epoxy based tie coat (DFT 50 microns max) and two coats (each 75 micron DFT) of high built polyamide cured epoxy paint will be provided (total DFT 260 microns max).Underside of skid and vessel skirts to be painted with two coats of coal tar epoxy paint, total DFT 200 microns after shot blasting to SA 2 . 10. STRUCTURAL DRAWINGS TO BE REVIE WED Following drawings shall be got reviewed by Owner/Owners representative: i. General Arrangement of skids ii. General Arrangement of platforms iii. Foundation Loading Plan