Sie sind auf Seite 1von 8

20

IEEE TRANSACTIONS ON SMART GRID, VOL. 1, NO. 1, JUNE 2010

Synchronized Phasor Measurement Applications


in Power Systems
Jaime De La Ree, Senior Member, IEEE, Virgilio Centeno, Senior Member, IEEE, James S. Thorp, Life Fellow, IEEE,
and A. G. Phadke, Life Fellow, IEEE

AbstractSynchronized phasor measurements have become a


mature technology with several international manufacturers offering commercial phasor measurement units (PMUs) which meet
the prevailing industry standard for synchrophasors. With the occurrence of major blackouts in many power systems around the
world, the value of data provided by PMUs has been recognized,
and installation of PMUs on power transmission networks of most
major power systems has become an important current activity.
This paper provides a brief introduction to the PMU and wide-area
measurement system (WAMS) technology and discusses the uses of
these measurements for improved monitoring, protection, and control of power networks.
Index TermsElectrical transients, global positioning system,
phasor, phasor measurement unit, power system, power system
control,
power system monitoring, power system protection, real.
time measurements, synchronized measurements, synchrophasor

I. INTRODUCTION
YNCHRONIZED phasor measurement units (PMUs) were
first introduced in early 1980s, and since then have become a mature technology with many applications which are
currently under development around the world. The occurrence
of major blackouts in many major power systems around the
world has given a new impetus for large-scale implementation
of wide-area measurement systems (WAMS) using PMUs and
phasor data concentrators (PDCs) in a hierarchical structure.
Data provided by the PMUs are very accurate and enable system
analysts to determine the exact sequence of events which have
led to the blackouts, and help analyze the sequence of events
which helps pinpoint the exact causes and malfunctions that
may have contributed to the catastrophic failure of the power
system. As experience with WAMS is gained, it is natural that
other uses of phasor measurements will be found. In particular,
significant literature already exists which deals with application
of phasor measurements to system monitoring, protection, and
control.
This paper is organized as follows. Section II reviews the
basic concepts of phasor representation of power system
voltages and currents under normal and abnormal operating
conditions. Section III discusses many of the applications of
the phasor measurements which have been discussed in the
literature. Section IV provides concluding remarks with some
assessment of the direction in which short-term and long-term
applications of this technology will emerge.

Fig. 1. Phasor representation of a sinusoidal signal. (a) Sinusoidal signal. (b)


Phasor representation.

II. PHASOR MEASUREMENT UNITS


A. Classical Definition of a Phasor
A pure sinusoidal waveform can be represented by a unique
complex number known as a phasor. Consider a sinusoidal
signal
(1)
The phasor representation of this sinusoid is given by
(2)
Note that the signal frequency is not explicitly stated in the
phasor representation. The magnitude of the phasor is the rms
, and its phase angle is , the
value of the sinusoid
phase angle of the signal in (1). The sinusoidal signal and its
phasor representation given by (1) and (2) are illustrated in
Fig. 1.
Note that positive phase angles are measured in a counterclockwise direction from the real axis. Since the frequency of
the sinusoid is implicit in the phasor definition, it is clear that
all phasors which are included in a single phasor diagram must
have the same frequency. Phasor representation of the sinusoid
implies that the signal remains stationary at all times, leading to
a constant phasor representation. These concepts must be modified when practical phasor measurements are to be carried out
when the input signals are not constant, and their frequency may
be a variable. This will be discussed in the next section.
B. Phasor Measurement Concepts

Manuscript received January 23, 2010; revised February 09, 2010. Date of
publication April 15, 2010; date of current version May 21, 2010. Paper no.
TSG-00011-2010.
The authors are with the Electrical and Computer Engineering Department,
Virginia Tech, Blacksburg, VA 24060 USA.
Digital Object Identifier 10.1109/TSG.2010.2044815

Although a constant phasor implies a stationary sinusoidal


waveform, in practice it is necessary to deal with phasor measurements which consider the input signal over a finite data
window. In many PMUs the data window in use is one period
of the fundamental frequency of the input signal. If the power

1949-3053/$26.00 2010 IEEE

DE LA REE et al.: SYNCHRONIZED PHASOR MEASUREMENT APPLICATIONS

system frequency is not equal to its nominal value (it seldom


is), the PMU uses a frequency-tracking step and thus estimates
the period of the fundamental frequency component before the
phasor is estimated. It is clear that the input signal may have
harmonic or nonharmonic components. The task of the PMU is
to separate the fundamental frequency component and find its
phasor representation.
The most common technique for determining the phasor representation of an input signal is to use data samples taken from
the waveform, and apply the discrete Fourier transform (DFT) to
compute the phasor. Since sampled data are used to represent the
input signal, it is essential that antialiasing filters be applied to the
signal before data samples are taken. The antialiasing filters are
analog devices which limit the bandwidth of the pass band to less
than half the data sampling frequency (Nyquist criterion).
are the
samples of the input
If
signal taken over one period, then the phasor representation is
given by [1]
(3)
The multiplier in front of the summation sign may need some
explanation. Note that for real input signals, the components
of the signal at a frequency appear in the DFT at
and
are complex conjugates of each other. They can be combined,
giving a factor of 2 in front of the summation sign in (3). The
peak value of the fundamental frequency thus obtained is then
. The DFT calculaconverted to rms value by dividing by
tion eliminates the harmonics of the input signal. However, the
nonharmonic signals and any other random noise present in the
input signal leads to an error in estimation of the phasor. The
error of estimation due to these effects has been discussed in
the literature.
C. Synchrophasor Definition and Measurements
Synchrophasor is a term used to describe a phasor which has
been estimated at an instant known as the time tag of the synchrophasor. In order to obtain simultaneous measurement of
phasors across a wide area of the power system, it is necessary
to synchronize these time tags, so that all phasor measurements
belonging to the same time tag are truly simultaneous. Consider
in Fig. 1 is the time tag of the measurement.
the marker
The PMU must then provide the phasor given by (2) using the
sampled data of the input signal. Note that there are antialiasing
filters present in the input to the PMU, which produce a phase
delay depending upon the filter characteristic. Furthermore, this
delay will be a function of the signal frequency. The task of the
PMU is to compensate for this delay because the sampled data
are taken after the antialiasing delay is introduced by the filter.
This is illustrated in Fig. 2.
The synchronization is achieved by using a sampling clock
which is phase-locked to the one-pulse-per-second signal provided by a GPS receiver. The receiver may be built in the PMU,
or may be installed in the substation and the synchronizing pulse
distributed to the PMU and to any other device which requires it.
The time tags are at intervals that are multiples of a period of
the nominal power system frequency.

21

Fig. 2. Compensating for signal delay introduced by the antialiasing filter.

It should also be noted that the normal output of the PMU is


the positive sequence voltage and current phasors. In many instances the PMUs are also able to provide phasors for individual
phase voltages and currents [2].
III. APPLICATIONS OF PHASOR MEASUREMENTS
A. Power System Monitoring
1) Early PMU Applications: When the first commercial
PMUs became available, postevent monitoring was their only
application due to the low availability and high cost of communications channels required for real-time monitoring, control,
and protection applications. The first recorded wide-area
measurements came from staged tests performed as part of
the EPRI Parameter Identification Data Acquisition System
(PIDAS) project in 1992. The tests consisted of opening and
closing of the Klondike and Bonaire 500 kV lines at Plant
Scherer in Georgia. PMUs were placed at Plant Scherer and
five other locations in Tennessee, Georgia, and Florida [3].
For the four staged states PMU were manually triggered to
guarantee wide-area recording of the event. For the sole PMU
manufacturer of that time this was a test of the units capability
to monitor systemwide events but at the same time. For engineers interested in maintaining system models this became
the first wide-area model validation test. At that time, it took a
week to obtain the plots comparing the measurements with the
estimations. Most of the delay came from the mailing of the
diskettes with data from each PMU to a common location for
analysis and comparison to the simulation results. This event
proved the capabilities of wide-area monitoring systems and
validated the system model for the study area.
Following the successful results of the initial PMU tests,
small numbers of PMUs were placed in different locations
throughout systems in the United States and other countries
to validate and correct system models by simulating records
collected by PMUs. Essentially the PMUs at this stage were
digital system disturbance recorders (DSDRs). Although several experimental applications were made for protection and
control applications, most PMUs functioned exclusively as a
DSDR due to limitation in the availability and bandwidth of
communication channels. To cope with the limited communication bandwidth, the first PMUs reported only positive sequence
phasors and frequency information.
As a DSDR, PMUs have collected interesting information
that has expanded the monitoring application of the devices.
One of these events is the data collected in Texas in July 1993
for the Comanche Peak load rejection test [4]. The frequency
oscillations collected by PMUs revealed an electromechanical
wave propagating through the system and easily observed in

22

the frequency measurements. This and similar measurements in


other parts of the country eventually led to the development of a
frequency monitoring network, FNET. Although limited in the
information provided the time synchronized frequency monitoring network has stimulated high interest among the academic
and regulatory communities due to their operation at residential
voltage level eliminating installation cost and data ownership
issues. PMU and FNET data have shown that any significant
loss of generation in a system will cause an electromechanical
oscillation that will propagate through the system at slow speed.
FNET data have shown that it is not only possible to detect
these oscillations at residential voltage levels but also to use the
frequency change to predict the amount of generation loss. It is
also possible with some limitation to use the traveling wave to
determine the location of the event [5].
In the 2003 Northeastern U.S. blackout and the 1996 U.S. West
Coast blackouts, the PMU monitoring capabilities were essential for the quick and accurate postmortem analysis of the events.
OneoftherecommendationsfromtheUnitedStatesCanadaTask
Force on the 14 August 2003 blackout is to require use of timesynchronized data recorders to all utilities [6]. This and other
recommendations led to the creation of the Eastern Interconnection Phasor Project (EIPP), now known as North American Synchrophasor Project (NASPI). The EIPP performed the first realtime wide-area monitoring in the United States after solving some
minor but interesting problems, such as the determination of a
common phase a for the whole eastern grid. NASPI continues
to solve some of the existing problems for the creation of a reliable
real-timesynchronizedmonitoringsystem suchastheavailability
of a commercial data concentrator capable of handling hundreds
of PMUs at the high communication rates required for most proposed applications.
With PMU installation cost ranging from 10 k to 70 K (dependingontheutility, location,andavailability of communication
channels) placing PMUs in the optimum locations is one of the
first steps of a wide-area monitoring system [7]. PMU placement
aimed at system monitoring is usually developed for full system
observability. Concepts such as depth of observability have been
developed to allow for a maximum utilization of data through a
staged deployment of a monitoring system for full observability
[9]. Other placement algorithms have been developed for specific applications such as Islanding and enhanced state estimation. PMU placement studies require the development of specific
placement system models. System models used in commercial
analysis software include virtual buses that either do not exist or
are not practical locations to install PMUs, such as tapped line
buses, shunt elements and series capacitor nodes. These virtual
buses may add up to 1/3 more nodes to the model and increase the
complexity of the problem. Not eliminating these nodes from the
placement model may result in PMUs being placed in unrealistic
locations. This problem is solved in small models by manually
eliminating virtual buses. In the case of real system models the
problem is solved by developing systematic methods to eliminate
virtual buses from commercial system data models [8].
2) State Estimation: Since the 1965 Northeast blackout,
state estimation has become a critical application function at
energy control centers. Existing state estimation algorithms [1]
use measurements of line flows and injections, both real and

IEEE TRANSACTIONS ON SMART GRID, VOL. 1, NO. 1, JUNE 2010

reactive power, to estimate all bus voltage angles and magnitudes. The complex bus voltages are the state of the system.
The complex power flows in lines and the complex power
injections at buses can be determined from the bus voltages and
an accurate model of the network. Prior to synchronized phasor
measurements, the state could not be measured directly but
only inferred from the unsynchronized power flow measurements. This fact and the process of getting large numbers of
measurements into the control center (a scan) forced early state
estimators to make compromises that persist today and have
an influence on how phasor measurements are integrated into
existing state estimation algorithms. The most significant of
these assumptions is that the system did not change during the
scanthat the system was static. Another view of the resulting
estimate of the state is that it is the state of a hypothetical
system which could support the complete set of measurements.
Depending on how long the scan takes and the changes in the
system that took place during the scan, the hypothetical system
may not exist or may be quite different from the real system.
While scans have become quicker, the introduction of phasor
measurements forces reconsideration of the static assumption.
The direct integration of a few synchronized phasor measurements into an existing nonlinear estimator is straightforward but
results in an estimator that has most of the limitations of the original conventional estimator. The new estimator is still recursive
and still has the assumptions required for the static state estimator. The issue of how to place the precisely timed PMU data
into the scanned data can also introduce a skew.
If an estimate could be formed with only PMU data, then the
issues of data scan and time skew could be eliminated. The PMU
data would be time tagged and the static assumption removed.
Since the voltage and current measurements are linear functions
of the system state, the estimation problem is simple a linear
weighted least squares problem which requires no iterations.
Given PMU data can be reported at rates as high as 60 times
a second, a truly dynamic estimate would be available. An estimate of a dynamic system at an instant in time corresponding
to the measuring instant would be obtained. Issues that must be
addressed include the need for redundancy to eliminate bad data
and determination of how many PMUs are required.
Recognizing that a PMU in a substation would have access to
line currents in addition to the bus voltage reduces the number of
PMUs needed. Measuring line currents can extend the voltage
measurements to buses where no PMU is installed. Using a
model of the transmission line, the line current can be used to
compute the voltage at the other end of the line. With a large
number of PMUs the redundancy issue is addressed. On the
other hand, the smallest number of PMUs needed to indirectly
measure all the bus voltages and the optimum PMU location to
achieve this has been a subject of a number of papers. [9][11].
With different approaches, treatment of zero injection buses,
and differing assumptions about types of PMU used, the consensus is that the minimum number of PMUs is approximately
one-third the total number of buses. A compromise between the
full nonlinear and linear formulations is described in [12].
An interesting subproblem is the issue of sequentially adding
PMUs to a system. With limited annual investments it would
be desirable to add a limited number of PMUs until a final goal

DE LA REE et al.: SYNCHRONIZED PHASOR MEASUREMENT APPLICATIONS

23

was achieved. Initially there will not be enough PMUs to have


a linear estimator. The attempt is to place the PMUs so that
at each stage the selection satisfies some design criteria. One
criterion is the degree of unobservability [11], which measures
how far away a bus is from a PMU. The solution to this problem
is available using the technique from [12]

Fig. 3. The graph for the incidence matrix for the IEEE 14-bus system along
with the branches added when the matrix is squared.

(4)

The busbus incidence matrix is a square matrix with the dimension of the number of buses. There is a one on each diagonal
and a one in the th position if bus is connected to bus . The
matrix for the IEEE 14 bus system is given in (4). If we imagine
placing a PMU at bus 2, for example, we would learn the voltages at buses 1, 2, 3, 4, and 5, which are the nonzero entries in
column 2 of A.
The placement problem for complete observability is then
given by the integer programming problem in (5) [14]. It is interesting to note that the powers of the incidence matrix have an interpretation that helps extend the integer programming problem
to the partial observability problem
subject to

or

TABLE I
PMU LOCATION FOR THE IEEE 14-BUS SYSTEM

is the incidence
The proof is by induction. The signum of
matrix of another graph that has branches added to the graph
in Fig. 3. The dashed branches in Fig. 3 represent connections
between nodes that pass through another node, i.e., those nodes
are one step removed. If we imagine the complete observability
problem is solved [ is the solution to (5)] the one degree of
unobservability problem is the solution of

subject to sign

or
(7)

And the addition of the constraint


forces the
solution to be chosen from the PMU location in
[8]. So in
general the sequence of integer programming problems in (8)

(5)
Theorem: The ij entry in the th power of the incidence matrix
for any graph or diagraph is exactly the number of different
paths of length n, beginning at vertex i and ending at vertex j
[13] [see (6)].

subject to sign
(8)
produce a nested sequence of PMU locations. For the 14-bus
system the locations are given in Table I.
Solutions of (8) for a 1400-bus system with a depth of 5 are
given in [1]. The first problem is a large amount of computation
for large systems. The subsequent problems are much easier.
B. Power System Protection

sign

(6)

Synchronized phasor measurements offer solutions to a


number of complex protection problems. In general, phasor
measurements are particularly effective in improving protection
functions, which have relatively slow response times. For such
protection functions, the latency of communicating information
from remote sites is not a significant issue. A few examples
of protection systems that could benefit from remote phasor
measurements information could include (B-1), control of
backup protection of distance relays (B-2), protection functions
concerned with angular voltage stability of networks (B-3),

24

Fig. 4. Loadability limit imposed by zone-3 setting of a distance relay. The


illustration shows a mho characteristic, which is commonly used in many relays.
As the load increases along the bold arrow, it would enter the tripping zone of
the relay and cause an inappropriate trip.

Fig. 5. Supervisory control for backup protection.

voting schemes where dependability and security could be reassessed based upon the stress of the system. A number of other
WAMS-based protection improvements can be found in [1].
1) Control of Backup Relay Performance: Backup zones of
distance relays are prone to tripping due to load encroachment
during power system disturbances. This has led to a call for
reassessing and sometimes abandoning the use of backup
zonesin particular zone-3 of distance relays (see Fig. 4),
which is used to protect downstream circuits in case their
protection systems fail to remove a fault on those circuits.
[15] Abandoning Zone-3 may be too drastic, and should not
be applied as a blanket policy. The remote backup policy is
designed to cover certain contingencies [16] for which no other
protection is available. Under these circumstances, it becomes
necessary to consider ways in which the loadability limits
imposed by the remote backup zones can be circumvented [17].
Wide-area measurements offer a possibility for restraining
the remote back-up relays in the event that the load swing is

IEEE TRANSACTIONS ON SMART GRID, VOL. 1, NO. 1, JUNE 2010

being interpreted by the relay as a fault [18]. Consider the conditions illustrated in Fig. 5. Zone-3 of relay is assumed to be
picked up. If a significant negative sequence current is present
(indicating an unbalanced fault), the zone-3 pick up is appropriate, and no further action is necessary. However, if the currents in the line are balanced, either a three phase fault on the
neighboring circuits or a possible loadability violation may be
inferred. The PMUs at the buses corresponding to the terminals
of lines which are to be backed-up by relay may then determine if any of them see a Zone-1 three-phase fault. If none of the
PMUs indicate that a Zone-1 three-phase fault exists, then the
Zone-3 pick-up of relay must be due to loadability limit violation. If tripping on this condition by relay is to be avoided,
it would then be possible to block its operation by supervisory
control of its output.
2) Adaptive Out-Of-Step Protection: It is recognized that
a group of generators going out of step with the rest of the
power system is often a precursor of a complete system collapse.
Whether an electromechanical transient will lead to stable or
unstable condition has to be determined reliably before appropriate control action could be taken to bring the power system to
a viable steady state. Out-of-step relays are designed to perform
this detection and also to take appropriate tripping and blocking
decisions.
Traditional out-of-step relays use impedance relay zones to
determine whether or not an electromechanical swing will lead
to instability. In order to determine the settings of these relays, it
is necessary to run a large number of transient stability simulations for various loading conditions and credible contingencies.
Using the apparent impedance trajectories observed at locations
near the electrical center of the system during these simulation
studies, two zones of an impedance relay are set, so that the inner
zone is not penetrated by any stable swing.
Problems With Traditional Out-of-Step Relays: Traditional
out-of-step relays are found to be unsatisfactory in highly interconnected power networks. This is because the conditions
and topologies assumed when the relay characteristics are determined become out-of-date rather quickly, and in reality the
electromechanical swings that do occur are quite different from
those studied when the relays are set. The result is that traditional out-of-step relays often misoperate: they fail to determine
correctly whether or not an evolving electromechanical swing
is stable or unstable. Wide-area measurements of positive sequence voltages at networks (and hence swing angles) provide
a direct path to determining stability using real-time data instead
of using precalculated relay settings.
It should be noted that a related approach was developed for
a field trial at the FloridaGeorgia interface [19][22] where the
interface was modeled as a two machine system. The machines
in Fig. 6 are equivalents of the eastern interconnection on the
left and Florida on the right with the four buses being physical buses in the interconnection. The equation of motion of the
angle difference between the two rotors of the two machines
.
and
are the two
is given by (9) where
rotor inertias, and the remaining terms in (6) are obtained from
the equivalent system. As the system undergoes changes due to
a fault and its clearing the parameters of the differential equaand
change and the classical equal-area criterion
tion

DE LA REE et al.: SYNCHRONIZED PHASOR MEASUREMENT APPLICATIONS

25

Fig. 6. Reduced FloridaGeorgia system.

Fig. 8. Adjustment of dependabilitysecurity balance under stressed system


conditions.

Fig. 7. The equal area criterion.

can be used to determine stability. That is, the area A1 must


be smaller than the area A2 for stability (see Fig. 7). The issue
in adaptive out-of-step is to determine the new parameter values
and
from real time measurements. A least squares esti[22] from samples of is used in [19]. The estimate
mate of
is obtained from five or six consecutive measurements of
(9)
It is of course possible to determine whether or not a swing is
unstable by waiting long enough and observing the actual swing.
However, in order to take appropriate control action it is essential that a reliable prediction algorithm be developed which provided the stableunstable classification of an evolving swing in a
reasonable time. In the FloridaGeorgia experiment a period of
observation of actual angular swings for a maximum of 250 ms
was used to obtain a reliable prediction of the outcome.
For large power networks it is not possible to apply the equal
area criterion as used in the example of FloridaGeorgia interface. As a first step after a transient stability event begins, groups
of coherently swinging machines are identified. After two distinct groups of coherent machines are determined, they may be
converted to a system of two equivalent generators connected
by a network. At this point one may apply an equal area criterion to this system, or using a time-series prediction algorithm
determine whether or not the evolving swing is stable or unstable. Such studies are currently under way, and it has been
found that in a majority of cases the prediction can be accomplished in about 250 ms after the start of the event, which is a
similar time frame as observed in the FloridaGeorgia interface
problem. Much work remains to be done in this area.
3) Security-Dependability: It should be recognized that a
relay has two failure modes. It can trip when it should not trip (a
false trip) or it can fail to trip when it should trip. The two types
of reliability have been designated as security and dependability by protection engineers. The existing protection systems

with their multiple zones of protection and redundant systems


are biased toward dependability, i.e., a fault is always cleared by
some relay. The result is a system that virtually always clears the
fault but as a consequence permits larger numbers of false trips.
High dependability is recognized as being a desirable protection
principle when the power system is in a normal healthy state,
and high-speed fault clearing is highly desirable in order to
avoid instabilities in the network. The consequent price paid in
occasional false trip is an acceptable risk under system normal
conditions. However, when the system is highly stressed false
trips exacerbate disturbances and lead to cascading events.
An attractive solution is to adapt the securitydependability balance in response to changing system conditions as determined by real-time phasor measurements. Adaptive relaying
with digital relays was introduced on a major scale in 1987 [23],
[24]. With three primary digital protection systems it is possible to implement an adaptive securitydependability scheme
by using voting logic (see Fig. 8). The conventional arrangement
is that if any of the three relays sees a fault, then the breaker is
tripped. A more secure decision would be made by requiring that
two of the three relays see a fault before the trip signal is sent
to the breaker. The advantage of the adaptive voting scheme is
that the actual relays are not modified but only the tripping logic
responds to system conditions.
C. Power System Control
Prior to the introduction of real-time phasor measurements
power system control was essentially local. Some subsystems
such as machines were controlled with only local signals. Other
control action was taken based on local measurements and a
mathematical model of the external world. External equivalents
are such models. The introduction of phasor measurements offers the possibility of control based on measurement value of remote quantities. Latency of the phasor measurements is an issue,
but the fact that many of the processes are in the 0.22.0 Hz
range is encouraging. The phasor data will be time tagged so
that control could be based on the actual state of the system a
short time in the past. The frequencies involved are representative of transient stability, electromechanical oscillations, and
certain overload phenomena. The frequency of measurements of
the order of 1560 Hz is certainly sufficient to handle the control task.

26

IEEE TRANSACTIONS ON SMART GRID, VOL. 1, NO. 1, JUNE 2010

IV. CONCLUSION

Fig. 9. A typical control based on remote synchrophasor measurements.

Wide-area measurements allowed the system to react to


threatening situations without employing continuous feedback
control. Monitoring of angles to detect possible instabilities
and taking discrete switching controls in an attempt to militate
against these events is a form of control made possible with
synchrophasors [25], [26]. The training of the switching logic
for such controllers has used simulation to train support vector
machines [27] and decision trees obtained from data mining
[26]. Incorporation of synchrophasor measurements into new
system integrity protection schemes (SIPS) has also been
described. [28]
Early applications with continuous feedback were aimed at
problems where a few phasor measurements could be applied to
problems in which the control objective were global in nature:
for example an HVDC controller may be called upon to damp
electromechanical oscillations between two widely separated
areas of a power system. Control of HVDC systems, excitation control, power system stabilizers, and FACTS devices control [29][37] were approached in a similar fashion. Because of
the nonlinearity of these problems, the power system dynamics
were linearized and linear feedback based on various robust control techniques employed. Uncertain parameters were used to
model unknown time delays [37], unmodeled dynamics were
used to deal with the unmeasured portion of the system [38],
. or
and LMI techniques used to design a robust
controller [29], [39].
These techniques can be used to coordinate a number of local
controllers of different types. For example, a collection of power
system stabilizers, dc lines, and FACTS devices could be coordinated to provide damping for a collection of interarea modes
with a variation of the technique used for PSSs alone [29]. A
representative scheme for such controllers is shown in Fig. 9.
The local controllers retain their local input signals but have additional inputs from the wide-area controller. Selection of the
PMU locations to be used and verification of the robustness of
the overall scheme are important issues.

With the growing interest in PMUs and WAMS throughout


the world, it is clear that these systems will be implemented in
most major transmission networks. To a large extent the success
of this endeavor depends upon adherence to the industry standard governing the PMUs [2]. This standard is being revised to
include requirements for compliance when power system is in
nonstationary state. Compliant PMUs will assure that PMUs of
different manufacture can be used interchangeably.
The earliest applications of PMU technology in most power
systems are likely to be: a) validation of system models, and
b) accurate postmortem analysis. As experience with real-time
PMU data is gained by system operators, the next logical step
would be to include PMU data in system state estimation procedures in energy management systems. With sufficient number of
PMUs installed, it would be possible to perform linear state estimation, and it would be possible to track dynamic phenomena
in real time. Ultimately, this ability will lead to the use of PMUs
for improving protection and control functions. The goal of such
improvements is to make the power system less immune to catastrophic failures and to reduce the severity of such failures when
they do occur.
REFERENCES
[1] A. G. Phadke and J. S. Thorp, Synchronized Phasor Measurements and
Their Applications. New York: Springer, 2008.
[2] IEEE Standard for Synchrophasors for Power Systems, IEEE Standard
C37.118-2005 (Revision of IEEE Std 1344-1995).
[3] R. O. Burnett, M. M. Butts, T. W. Cease, V. Centeno, G. Michel, R.
J. Murphy, and A. G. Phadke, Synchronized phasor measurement of
a power system event, IEEE Trans. Power Syst., vol. 9, no. 3, pp.
16431650, Aug. 1994.
[4] D. Faulk and R. J. Murphy, Comanche peak unit no 2 100% load
rejection testUnderfrequency and voltage phasor measured across
TU electric system, presented at the 47th Annual Texas A&M Conf.
Protective Relay Engineers, College Station, TX, Mar. 1994.
[5] Z. Zhong, C. Xu, B. J. Billian, L. Zhang, S.-J. S. Tsai, R. W. Conners,
V. Centeno, A. G. Phadke, and Y. Liu, Power system frequency monitoring network (FNET) implementation, IEEE Trans. Power Syst., vol.
20, no. 4, pp. 19141921, Nov. 2005.
[6] Final Report on the August 14, 2003 Blackout in the United States
and Canada: Causes and Recommendations Apr. 5, 2004, U.S.Canada
Power System Outage Task Force.
[7] Responses Summary to Questionnaire on PMU Installation and Maintenance May 2006, Eastern Interconnection Phasor Project (EIPP) Performance Requirements Task Team (PRTT).
[8] M. Zhou, V. A. Centeno, A. G. Phadke, H. Yi, D. Novosel, and H.
A. R. Volskis, A preprocessing method for effective PMU placement
studies, in Proc. 3rd Int. Conf. Electric Utility Deregulation and Restructuring and Power Technologies (DRPT 2008), Apr. 69, 2008, pp.
28622867.
[9] R. F. Nuqui and A. G. Phadke, Phasor measurement placement techniques for complete and incomplete observability, IEEE Trans, Power
Del., vol. 20, no. 4, pp. 23812388, Oct. 2005.
[10] B. Gou and A. Abur, An improved measurement placement algorithm
for network observability, IEEE Trans. Power Syst., vol. 16, no. 4, pp.
819824, Nov. 2001.
[11] A. Abur, Optimal Placement of Phasor Measurements Units for State
Estimation PSERC Publ. 06-58, Oct. 2005.
[12] M. Zhou, V. A. Centeno, J. S. Thorp, and A. G. Phadke, An alternative
for including phasor measurements in state estimators, IEEE Trans.
Power Syst., vol. 21, no. 4, pp. 19301937, Nov. 2006.
[13] N. Korevaar, Incidence Is No Coincidence, Univ. Utah Math Circle,
Oct. 2002.
[14] M. Zhou, Phasor measurement unit calibration and applications in
state estimation, Ph.D. dissertation, Virginia Tech, Blacksburg, Mar.
2008.

DE LA REE et al.: SYNCHRONIZED PHASOR MEASUREMENT APPLICATIONS

[15] S. H. Horowitz and A. G. Phadke, Boosting immunity to blackouts,


IEEE Power Energy Mag., vol. 1, no. 5, pp. 4753, Sep.Oct. 2003.
[16] S. H. Horowitz and A. G. Phadke, Third zone revisited, IEEE Trans.
Power Del., vol. 21, no. 1, pp. 2329, Jan. 2006.
[17] A. G. Phadke, D. Novosel, and S. H. Horowitz, Wide area measurement applications in functionally integrated power systems, presented
at the CIGRE B-5 Colloq., Madrid, Spain, 2007.
[18]
[Online]. Available: http://www.nerc.com/~dawg/dawg-disturbancereports.html
[19] V. Centeno, A. G. Phadke, A. Edris, J. Benton, M. Gaudi, and G.
Michel, An adaptive out-of-step relay [for power system protection],
IEEE Trans. Power Del., vol. 12, no. 1, pp. 6171, Jan. 1997.
[20] V. Centeno, A. G. Phadke, and A. Edris, Adaptive out-of-step relay
with phasor measurement, in Proc. 6th Int. Conf. Developments in
Power Syst. Protection, Mar. 2527, 1997, pp. 210213, Conf. Publ.
No. 434.
[21] V. Centeno, A. G. Phadke, A. Edris, J. Benton, and G. Michel, An
adaptive out-of-step relay, IEEE Power Eng. Rev., vol. 17, no. 1, pp.
3940, Jan. 1997.
[22] V. Centeno, J. De La Ree, A. G. Phadke, G. Michel, R. J. Murphy, and
R. O. Burnett, Jr., Adaptive out-of-step relaying using phasor measurement techniques, IEEE Comput. Appl. Power, vol. 6, no. 4, pp.
1217, Oct. 1993.
[23] S. H. Horowitz, A. G. Phadke, and J. S. Thorp, Adaptive transmission
system relaying, IEEE Trans. Power Del., vol. 3, no. 4, pp. 14361445,
Oct. 1988.
[24] G. D. Rockefeller, C. L. Wagner, J. R. Linders, K. L. Hicks, and D.
T. Rizi, Adaptive transmission relaying concepts for improved performance, IEEE Trans. Power Del., vol. 3, no. 4, pp. 14461458, Oct.
1988.
[25] D. Hu and M. Venkatasubramanian, New wide area algorithms for
detection and mitigation of angle instability using synchrophasors, in
Proc. Power Eng. Soc. General Meeting, Jun. 2007, pp. 18.
[26] S. Rovnyak, C. W. Taylor, and J. S. Thorp, Real-time transient stability predictionPossibilities for on-line automatic database generation and classifier training, presented at the 2nd IFAC Symp. Control
of Power Plants and Power Syst., Cancun, Mexico, Dec. 7, 1995.
[27] M. Venkatasubramanian, X. Yue, G. Liu, M. Sherwood, and Q. Zhang,
Wide-area monitoring and control algorithms for large power systems
using synchrophasors, presented at the Power System Conf. Exposition, Pullman, WA, Mar. 1518, 2009.
[28] V. Madani, E. Taylor, D. Erwin, A. Meklin, and M. Adamik, High
speed control scheme to prevent instability of a large multi-unit power
plant, presented at the Clemson Power System Conf., Clemson, SC,
Mar. 1316, 2007.
[29] Y. Zhang and A. Bose, Design of wide area damping controllers for
interarea oscillations, IEEE Trans. Power Syst., vol. 23, no. 3, pp.
11361143, Aug. 2008.
[30] N. Rostamkolai, Adaptive Optimal Control of AC/DC Systems,
Ph.D. dissertation, Virginia Tech, Blacksburg, 1986.
[31] E. C. Manansala, Adaptive Power System Control, Ph.D. Dissertation, Virginia Tech, , Aug. 1989.
[32] N. Rostamkolai, A. G. Phadke, J. S. Thorp, and W. F. Long, Measurement based optimal control of high voltage AC/DC systems, IEEE
Trans. Power Syst., vol. 3, no. 3, pp. 11391145, Aug. 1988.
[33] E. C. Manansala and A. G. Phadke, An optimal centralized controller
with nonlinear voltage control, Electric Mach. Power Syst., vol. 19,
pp. 139156, 1991.
[34] L. Mili, T. Baldwin, and A. G. Phadke, Phasor measurements for
voltage and transient stability monitoring and control, presented at the
Workshop Appl. Adv. Math. Power Syst., San Francisco, CA, Sep. 46,
1991.
[35] A. F. Snyder, N. Hadjsaid, D. Georges, L. Mili, A. G. Phadke, O.
Faucon, and S. Vitet, Inter-area oscillation damping with power
system stabilizers and synchronized phasor measurements, in Proc.
POWERCON98, vol. 2, pp. 790794.
[36] M. A. Smith, Improved Dynamic Stability Using FACTS Devices
With Phasor Measurement Feedback, M.S. Thesis, Virginia Tech,
Blacksburg, 1994.
[37] G. L. Yu, B. H. Zhang, H. Xie, and C. G. Wang, Wide-area measurement-based nonlinear robust control of power system considering
signals delay and incompleteness, in Proc. Power Eng. Soc. General
Meeting, Jun. 2007, pp. 18.
[38] X. Li, Q. Yan, and Y. Hu, Decentralized coordinated robust adaptive
control for AC/DC interconnected power system based on WAMS, in
Proc. APCCAS 2008, Nov. 30Dec. 3 2008, pp. 18961899.
[39] C. Dou, S. Jin, Z. Bo, Q. Jia, and H. Xue, Decentralized stabilizer
design for model-based uncertain large interconnected power systems
based on WAMS, in Proc. IPES 2007, Dec. 36, 2007, pp. 799806.

27

Jaime De La Ree (S80M80SM94) received


the B.S.E.E. degree with honors from The Instituto
Tecnologico y de Estudios Superiores de Monterrey
in 1980 and the M.S.E.E. and Ph.D. degree from
University of Pittsburgh, Pittsburgh, PA, in 1981 and
1984 respectively.
In 1984, he joined the ECE Department at Virginia
Tech, Blacksburg, where he is currently the Associate
Department Head. His primary research area is advanced protection, and control of power systems.
Prof. De La Ree is the recipient of the Sporn and
the Wine Teaching Awards. These are the most prestigious awards granted at
Virginia Tech.

Virgilio Centeno (S88M88SM06) received the


M.S. and Ph.D. degrees in electrical engineering
from Virginia Polytechnic Institute and State University (Virginia Tech), Blacksburg, in 1988 and 1995,
respectively.
He worked as a Project Engineer at Macrodyne,
Inc., Clifton Park, NY, in the development of phasor
measurement units from 1991 to 1997. He joined the
faculty of Virginia Tech as a Visiting Professor in the
fall of 1997 and became an Assistant Professor in the
fall of 2001 and an Associate Professor in 2006. His
area of interest is wide-area measurement and its applications.

James S. Thorp (S58M63SM80F89LF03)


received the B.E.E., M.S. and Ph.D. degrees from
Cornell University, Ithaca, NY, in 1959, 1961, and
1962, respectively.
He was a Faculty Intern, American Electric Power
Service Corporation in 19761977 and an Overseas
Fellow, Churchill College, Cambridge University in
1988. He was the Director of the Cornell School of
Electrical and Computer Engineering from 1994 to
2001. He was the Charles N. Mellowes Professor in
Engineering at Cornell University from 19942004.
He was the Hugh P. and Ethel C. Kelley Professor of Electrical and Computer
Engineering and Department Head of the Bradley Department of Electrical and
Computer Engineering at Virginia Tech from 2004 to 2009.
Prof. Thorp was an Alfred P. Sloan Foundation National Scholar and was
elected a Member of the National Academy of Engineering in 1996. He received
the 2001 Power Engineering Society Career Service award, the 2006 IEEE Outstanding Power Engineering Educator Award, and shared the 2008 Benjamin
Franklin Medal with A. G. Phadke.

A. G. Phadke (M64SM97F80LF04) received


the B.Sc., B.Tech. (Hons.), M.S. and Ph.D. degrees
from Agra University, IIT, Khargpur, IIT, Chicago,
and the University of Wisconsin, Madison, in 1955,
1959, 1961, and 1964 respectively.
He is a University Distinguished Professor (Emeritus) at Virginia Tech, Blacksburg. He is a coauthor
of three books: Computer Relaying for Power
Systems, Power System Relaying, and Synchronized
Phasor Measurements and Their Applications, and
is the editor of and contributor to the book Handbook
of Electrical Engineering Computations. His primary research area is the
microcomputer based monitoring, protection, and control of power systems.
Prof. Phadke was awarded the IEEE Third Millennium Medal in 2000, named
the Outstanding Power Engineering Educator by the IEEE in 1991, and received
the Power Engineering Educator Award of the EEI in 1986. He received the
IEEE Herman Halperin Transmission and Distribution award in 2000. He was
the Chairman of the Technical Committee of USNC CIGRE, and Editor-InChief of IEEE TRANSACTIONS ON POWER DELIVERY. He was elected to the U.S.
National Academy of Engineering in 1993. He was awarded Honorary Doctorate by INP Grenoble, France, in 2006. He shared the 2008 Benjamin Franklin
Medal with J. S. Thorp.

Das könnte Ihnen auch gefallen