Beruflich Dokumente
Kultur Dokumente
155.00 set
155 set
1464 l.m
2
0.5
0.3
2
0.5
0.4
0.4
2
155.00
155
4,650.00
25.00
2109
set
set
l.m
set
l.m
2.5
35
2.5
pcs
55
8
pcs
pcs
0.4
25.00 mm
12.00 mm
32.00 mm
25.00 mm
155 set
Excavation
4 column
Removed and demolished
1 column
Assumed 8 working hours/day for 2 columns
4
4
hrs
hrs
77.5 days
days
Vol
248.00 cum
77.50 cum
175.68 cum
387.50
16,275.00
4,650.00
4,125.00
16,872.00
cum
l.m
l.m
l.m
l.m
Rebar
100.00 kg/cum
350 kg/cum
170 kg/cum
100.00
3.85
0.088
6.31
3.85
kg/cum
kg/l.m
kg/l.m
kg/l.m
kg/l.m
24,800.00
27,125.00
29,865.60
Rebars in Kg
62,590.00
89,096.70
26,028.75
66,689.39
kg
kg
kg
kg
kg
kg
kg
12.00
12.00
12.00
297,600.00
325,500.00
358,387.20
981,487.20
800,272.70
2,620,513.10
Equipment no rental
- Backhoe 2-unit for 8hrs(1day)
- operator
- labor
- oxygen/acetylene
Liquidated Damages
Duration
Rebars
62,590.00
89,096.70
66,689.39
39,323.00
218,376.09
155
Unit
kg
kg
kg
kg
set
2.00 column
31.00 days
Qty
200
2
3
3
Qty
31
Price/kg
Total Amount
12.00
751,080.00
12.00
1,069,160.40
12.00
800,272.70
12.00
471,876.00
3,092,389.10
Unit
li/day
man/day
man/day
set
in 4 hrs
to complete excavation of
columns/footings & tie beams
For 31 days
Amount
7,000.00
1,600.00
1,260.00
3,600.00
13,460.00
417,260.00
Unit Cost
10,000.00
Amount
310,000.00
2,365,129.10
Unit
days
Unit Cost
35.00
800.00
420.00
1,200.00
Rebars
Unit
62,590.00
kg
89,096.70
kg
66,689.39
kg
39,323.00
kg
218,376.09
155
set
2.00 column
96.00 days
Qty
200
2
3
3
Unit
li/day
man/day
man/day
set
Price/kg
Total Amount
12.00
751,080.00
12.00
1,069,160.40
12.00
800,272.70
12.00
471,876.00
3,092,389.10
average per day
to complete excavation of
columns/footings & tie beams
Unit Cost
35.00
800.00
420.00
1,200.00
For 96 days
Liquidated Damages
Duration
Qty
100
1
1
Qty
96
Unit
li/day
man/day
man/day
For 30 days
Amount
3,500.00
800.00
420.00
4,720.00
141,600.00
Unit Cost
10,000.00
Amount
960,000.00
698,629.10
Unit
days
Unit Cost
35.00
800.00
420.00
Amount
7,000.00
1,600.00
1,260.00
3,600.00
13,460.00
1,292,160.00
Description
Amount of Penalty for each day of delay
Amount/Qty
Php. 10,000.00
2.0
3.0
Php. 320,000.00
Description
Amount of Penalty for each day of delay
Amount/Qty
Php. 10,000.00
2.0
3.0
Php. 360,000.00
Su
Su
7
14
21
Mo
1
8
15
22
Tu
2
9
16
We
3
10
17
Th
4
11
18
Fr
5
12
19
Sa
6
13
20