Contents
1
Scope
Reference Documents
Risk Assessment
Pre-commissioning Procedure
5.1
5.2
5.3
5.4
Doc No.
Test Procedure
Punch List
Precommissioning Test Forms
List of Test Equipments
Rev 0
8
11
11
12
Page 2 of 12
APPD.
QP
REV.
Scope
This scope describes the procedure for Pre-commissioning
activities of the new 415V Switchgears located at either
the Tertiary substations or at Secondary Distribution
Substations of all P 965 Berth & Port Infrastructure for
Ras Laffan Port Expansion project.
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------++++++
Doc No.
Rev 0
Page 3 of 12
Reference Documents
All pre-commissioning tests which are performed shall be
in accordance with specifications of International
Electrotechnical Commission (IEC) and the specifications
listed below:
RPGE-0-05-0041:
Pre-commissioning
&
RPGE-0-05-0247:
Pre-commissioning
&
RPGE-0-05-0381:
Pre-commissioning
&
Commissioning Note.
Doc No.
Rev 0
Page 4 of 12
S/N
ACTIVITIES
Check all Safety devices such as display of warning sign, barrication of access
limitation, key box for the panels and fire extinguishers are in compliance with HSC
requirements prior to start performing pre-commissioning activity, as required.
Check the feeder labelling is correct. Verify all safety signs are in place.
Check the earthing bar and connections are firm & tight.
Check the mechanical closing and opening of incomer & outgoing breakers
Rack each circuit breaker from TEST position to SERVICE position and back several
times.
Record fuse type and rating for the control circuits.
10
11
Perform CT testing
12
Perform PT testing
13
Perform IR test.
15
16
17
18
Perform Functional test for the switchgear including the ATS, as applicable.
Doc No.
Rev 0
Page 5 of 12
Risk Assessment
The risk assessment form is a safety management tool
which identifies the major potential risk factors,
preventive controls and additional control measures to be
undertaken prior to performing a specific task or the
whole task associated with the project subsystem
activities during pre commissioning stages of work.
This document is prepared by CCC/Subcontractor and
submitted to project CCC/QP HSE personnel for their
review prior to commencement of pre commissioning
activities
These features as prescribed in the risk assessment form
will be regularly monitored and audited by the field safety
personnel to ensure the pre commissioning activities are
performed in a safe manner for the successful completion
of the task.
Doc No.
Rev 0
Page 6 of 12
Pre-commissioning Procedure
Introduction
The procedure of Pre-commissioning test & checks are
required to ensure LV Switchgear is properly installed,
wired correctly, and the safety devices are tested to verify
the performance and the function to confirm the
suitability of the equipment for the application.
This procedure will be applicable for site testing of LV
Switchgear for readiness before the commencement of the
Commissioning activities.
The LV Switchgear and the control devices will be tested
in accordance with the vendor approved procedures,
applicable IEC standards and Project reference
documents.
General
Visual check shall be carried out to confirm the
correctness of the installation, and the equipment
structure is free-of-damage. Mechanical tests shall be
carried out to assure the operation/mechanize of the
mechanical parts. Electrical tests shall be carried out to
confirm either the conductivity or the quality of the
insulation. Functional tests shall carried out verify the
schematic/logic diagram. Protective relays shall be set
and tested in accordance with the requirement of the
system coordination and protective relay setting record.
Punch list, if any, shall be prepared and submitted to the
Vendor. Vendor will replace defective major components
that are critical for the successful operation of the
equipment.
Following is the minimum checks that will be performed
and confirmed:
Doc No.
Rev 0
Page 7 of 12
is
connected
properly
5.1
Test Procedure
a.
VISUAL CHECKS:
Doc No.
Rev 0
Page 8 of 12
MECHANICAL CHECKS:
ELECTRICAL CHECKS:
IR Test on Busbars:
The IR test is to measure the insulation level of the
equipment. This test is done by using a 1000V megger
for 1 minute between each phase to Neutral, each
phase to earth, phase to phase and neutral and earth.
Ductor Test for Busbars:
This test is to ensure the all the busbar joints are
properly aligned jointed and connected firmly. It can be
measured by using a Ductor tester. Keep the probes on
both sides of the busbar joint and apply some pressure
to be sure for better contact and press the test button.
Wait for few seconds to get a stable reading. The
measured values should be less than the specified
values. Refer vendor requirements and table or FAT
reports.
CT & VT TESTS:
CT POLARITY TEST:
Connect +Ve 9V battery to P1 of CT and Ve of 9V
battery to P2 of CT.
Connect the analog ammeter between S1-S2 of CT
secondary.
Doc No.
Rev 0
Page 9 of 12
Doc No.
Rev 0
Page 10 of 12
d.
FUNCTIONAL TESTS:
Doc No.
Rev 0
Page 11 of 12
paralleling
MOMENTARY PARALLELING:
In manual mode, select the breaker to trip and give a
close pulse to the third breaker which is in open
position. Check that the third breaker closes first
achieving paralleling and the selected breaker will trip
within a short period (usually 1 to 3 seconds) as per the
project specification & requirement.
SYNCHRONIZATION:
Check the possibility of closing both the incomers and
bus-coupler breakers through synchronization relay.
INTERTRIP TEST:
Trip the incomer breaker through protection relay and
check a inter trip signal is ready to go to the respective
11kV RMU outgoing breaker.
GENERATOR FEEDER TEST:
Generator feeder functional test shall be in line with the
applicable schematic/logic diagram for Normal mode
operation logic and Test Mode operation logic.
5.2
Punch List
Exceptional punch list shall be created in line with the
punch list definition of categories in order to identify and
place in record the missing materials, pending
engineering discrepancies, field modifications, pending
Doc No.
Rev 0
Page 12 of 12
5.4
IR Test (FM-106)
VT test (FM-110)
Multi meter
Clamp meter
Ductor Tester
Laptop
End of document