Beruflich Dokumente
Kultur Dokumente
post-installed
rebar connections
post-installed
rebar connections
post-installed
rebar connections
Simply qualified.
By Konrad Bergmeister.
Prof. Dr.-Ing. Dr. Konrad Bergmeister is Head of the Department of Civil En-
gineering and Natural Hazards at the University of Life Science and Natural Resources in
Vienna, Austria, including the Institute of Structural Engineering that he headed previously.
He has over 20 years of experience in the field of structural engineering and design and
has led many major infrastructure projects. The main topics of his research work are fastening systems, structural analysis, monitoring and maintenance.
require hooks or bends. A revolutionary new design method has now been
developed on the basis of this research.
Hilti HIT Rebar Design Method
According to structural concrete building codes, the bond strength of cast-in
bars is limited, even where depth of
concrete cover is considerable. Accordingly, in some zones such as in walls
where anchorage depth is often limited,
welded transverse reinforcement or
hooks are used to compensate for the
reduction in available anchorage depth.
The Hilti Rebar Design Method also
makes it possible to reduce anchorage length while maintaining the high
bond strength needed to replace hooks
or welded transverse reinforcement.
Better results through more
detailed research
Research has shown that the bond
strength of bars anchored with Hilti
adhesive mortars is higher than that of
References
post-installed
cast-in
Dr. Jakob Kunz is Scientific Consultant for the Hilti Anchor Business Unit. He
gained his doctorate at the ETH (Swiss Federal Institute of Technology) in Zurich
and Lausanne and has been with Hilti as a research engineer, project manager
and chief scientific officer since 1989. Dr. Jakob Kunz specializes in the fields
of fastening technology and reinforced concrete design. He is a member of fib,
IABSE, ACI and SIA 179
5
Pull-out tests
Hilti offers the possibility of carrying out on-site rebar pull-out tests
to validate expected loads.
Rebar analysis
The Hilti PS 200 Ferroscan System
provides information about existing reinforcement by determining its
position, diameter and depth of coverage without the need for destructive
procedures such as removal of concrete. Hilti PROFIS Ferroscan software
simplifies the job of analyzing the data
obtained. For more information please
refer to www.hilti.com/ferroscan.
*The availability of services may vary from country to country. Please contact Hilti in your area for further information.
Bond strength
Working time
Curing time
Hilti HIT-CT 1
8 40 mm
3.2 m
-5C / 40C
4 h / 12 min
72 h / 4 h
8 25 mm
2m
-10C / 40C
3 h / 2 min
12 h / 30 min
8 25 mm
-10C / 40C
1.5 h / 2 min
12 h / 30 min
Label-free
ETA-08/0105
(only from 5 to 40C)
ETA-08/2020
Town Town business city development, Vienna. With its gross floor area of about 130,000 m2, Town Town is a major business
development in the city of Vienna. The 31,000m2 ground area for this project was created by placing a concrete deck over a
subway line. This involved connecting pre-cast concrete slabs to pre-stressed, pre-cast beams using special internally threaded
sleeves. Hilti HIT-RE 500 was used on site to set 4,000 of these internally threaded anchors with 20 mm reinforcing rods at a
depth of about 50 cm. The most important criteria for specification of this rebar connection method by STRABAG, the Austrian
construction giant, were its tested fire resistance and its ability to take up high loads at a very shallow anchorage depth. The connections were designed in accordance with Eurocode 2 using the Hilti PROFIS Rebar software.
Simply approved.
The Hilti HIT system for professional installations.
Hilti HIT-RE 500, HIT-HY 150
MAX and HIT-CT 1 injectable
mortars have been awarded
ETA approval for use in postinstalled rebar connections.
The stringent approval requirements qualify the mortars for
use in applications where connections are designed in accordance with Eurocode 2 (EC 2).
No matter which Hilti HIT injectable
mortar a design engineer selects, the
reliability of its bonding characteristics
or its compliance with building codes
is never in doubt because the system
has been prequalified through approval.
Current design methods in accordance
with the applicable building codes,
in this case EC 2, can be applied.
10
post-installed
rebar connections
chemical attack).
details.
recommendations.
Whats the main difference between cast-inplace and post-installed reinforcement? While
be drilled.
post-installed
rebar connections
Design
Detection
The latest version of Hilti PROFIS Rebar puts post-installed rebar connection design and the calculation of overlap and anchorage lengths at your fingertips.
Hilti detectors such as the PS 35 indicate the position of reinforcing bars and their concrete cover.
Drilling
Cleaning
Drill faster and more safely with Hilti combihammers and extra-rugged Hilti hammer drill bits or with Hilti high-performance
diamond coring systems.
Hilti HIT Profi Rebar sets keep all the required cleaning accessories conveniently at hand.
Cutting
Setting
Hilti angle grinders featuring Smart Power and fitted with Hilti
AC-D cutting discs are ideal for cutting rebars to length. Alternatively, Hilti cordless reciprocating saws provide total mobility.
Hilti Corporation I 9494 Schaan I Liechtenstein I P +423-234 2111 I F +423-234 2965 I www.hilti.com
Hilti = registered trademark of Hilti Corp., Schaan | W4016 0411 0-en | 1 Printed in Liechtenstein | 2011 | Right of technical and programme changes reserved S. E. & O.