Beruflich Dokumente
Kultur Dokumente
ARA6/07
C
ou
CIVILAPPELLATEJURISDICTION
ARBITRATIONAPPEALNO.6OF2007
STATEOFMAHARASHTRA
(attheinstanceofIrrigationDepartment,
ExecutiveEngineer,KoynaDivisionNo.2)
...Appellant.
rt
INTHEHIGHCOURTOFJUDICATUREATBOMBAY.
ig
h
V/s.
1.HINDUSTANCONSTRUCTIONCOMPANY
(LTD.(HCC).
2.ARBITRALTRIBUNALOF:
a)S.N.Jha,b)V.M.Ranade,c)B.S.Panchmukhi
...Respondents.
ba
y
MrA.A.Kumbhakoni,learnedcounsela/wMrsS.V.SonawanelearnedA.G.P.,Mr
ShardulSinghandMrAbhayAnturkarforAppellant.
om
MrAspiChinoy,seniorCounsela/wMrArifDoctori/bM/sHareshJoshi&Co.
forRespondents.
CORAM:R.D.DHANUKAJ.
RESERVEDON:JANUARY09,2013.
PRONOUNCEDON:FEBRUARY01,2013.
JUDGMENT:
Conciliation Act 1996 ( for short herein after referred as 'the Act'), the
Government seekstochallengeanorderandjudgmentdated29th June2006
passedbythelearnedDistrictJudge,Ratnagirirejectingarbitrationapplication
Asmita
1/48
..2..
C
ou
No.44of2003filedbytheGovernmentunderSection34oftheAct.
rt
ARA6/07
2.
TheGovernment hadchallengedanawarddeliveredbytheArbitral
Tribunalallowingsomeoftheclaimsmadebytherespondent (forshortthe
Government isreferredas'Government'andtherespondentisreferredas'the
ig
h
contractor'). Someoftherelevantfactsforthepurposeofdecidingthisappeal
areasunder:
ba
y
powerhouseinICTcontractNo.2tothecontractor.Theamountofthecontract
awardedwasatRs.6825lakh.Boththepartiesenteredintoanagreementon20th
March 1992. Stipulated date of commencement of the work was 20th March
om
1992.Thestipulateddateofcompletionwas19thMarch1997.TheGovernment
grantedextensionoftimetocompletetheworktothecontractortill31stMarch
2000.Theworkwascompletedbythecontractoron31stMarch2000.Thedate
ofcompletionofmaintenanceperiodwas3rdOctober2000.
3.
respectofhiddenexpenses.Thecontractorinvokedarbitrationclause.On27th
Asmita
2/48
..3..
ARA6/07
rt
April1998,firstarbitrationproceedingsstarted.Byanawarddated4thDecember
C
ou
1998,theclaimofthecontractorwaspartlyacceptedbythelearnedarbitrator.
Pursuant to said award, the Government paid sum of Rs.10.2 crore to the
contractor.TheGovernmentdidnotchallengethesaidaward.
On3rdOctober2000,defectliabilityperiodended.Thedisputearose
ig
h
4.
arbitratorwasappointedbytheCentralWaterCommission,NewDelhi.
On26thJune2003,thelearnedarbitratormadeanawardinfavourof
ba
y
5.
thecontractorawardingasumofRs.17,81,25,152/. Beingaggrievedbythe
saidaward,theGovernmentfiledarbitrationapplicationNo.44of2003on22 nd
om
March2003intheCourtofDistrictJudge,Ratnagirichallengingthesaidaward
underSection34oftheAct.Byanorderandjudgmentdated29thJune2006,the
learnedDistrictJudgedealtwithfiveobjectionsraisedbytheGovernment by
way of preliminary objections only and negatived each of such objection and
rejectedthesaidarbitrationapplication. TheGovernmenthasfiledthisappeal
underSection37oftheActforimpugningtheorderandjudgmentdated29th
June2006passedbythelearnedDistrictJudge.
Asmita
3/48
..4..
rt
6.
ARA6/07
C
ou
appearingforthecontractorobjectedtosuchadditionalsubmissionswhichwere
notmadebeforethelearnedDistrictJudge,MrKumbhakonithelearnedcounsel
ig
h
wasnotallowedtoagitatethoseadditionalissues.MrKumbhakoni,thelearned
counsel,thereforedidnotaddressthisCourtonadditionalissuesraisedbythe
GovernmentandaddressedthisCourtonlyonfivepreliminaryobjectionsraised
bytheGovernmentbeforetheDistrictJudgeinthisproceedingsalso.
MrKumbhakoni,thelearnedcounselsubmitsthatthecontractorhad
ba
y
7.
accepted payment under final bill without making any protest and thus the
contractitselfceasetoexist.Thelearnedcounselsubmitsthattheclaimsthus
om
made by the contractor were not arbitrable in view of such accord and
satisfactionduetoacceptanceoffinalbillwithoutprotest.Thelearnedcounsel
submitsthatthecontractorhadacceptedandsigned164thandfinalbilland165th
andfinalbillwithoutprotest.Itissubmittedthatboththesebillsweresignedby
theauthorisedrepresentativeofthecontractorandchequesforfinalbillhadbeen
acceptedandcreditedinthebankaccountofthecontractor.
Asmita
4/48
..5..
rt
8.
ARA6/07
C
ou
contractor,ontheotherhandsubmitsthatthesignatoryto164thand165thbills
wasnotauthorisedtosignanysuchbillsbuthewasauthorisedtosign/acceptRA
bills. The learned counsel submits that under clause 60.8 of the GCC, the
contractorhadsubmittedthedraftfinalbillon30thDecember2000containing3
ig
h
saidclause.ItissubmittedthatpaymentofBOQitemsandExtraitemswasmade
bytheGovernmentaspartof164thandfinalbillandpaymentforpricevariation
ba
y
wasmadeaspartof165thandfinalbill.Itissubmittedthathowever,inrespect
of5claims,nofinalbillwasissuedeitheracceptingorrejectingtheclaimsmade
bythecontractor.Itissubmittedthateventheamountsascertifiedunder164th
om
and165thbillswerepaidbytheGovernmentin34instalments.Itissubmitted
that164thand165thandfinalbillswerenotfinalbillsascontemplatedbyclause
60.8.Thecontractordidnotissuenoclaimcertificate.Itissubmittedthatthus,
therewasnoaccordorsatisfactiononthepartofthecontractorandthusclaims
werearbitrable.
9.
Asmita
..6..
ARA6/07
C
ou
Construction1andmoreparticularlypara9whichreadsthus:
rt
9.Onlybecausetherespondenthasacceptedthefinalbill,thesamewouldnot
mean that it was not entitled to raise any claim. It is not the case of the
Governmentthatwhileacceptingthefinalbill,therespondenthadunequivocally
statedthathewouldnotraiseanyfurtherclaim....
10.
Relyinguponthesaidjudgment,thelearnedcounselsubmitsthat,as
ig
h
thecontractorhadnotunequivocallystatedthathewouldnotraiseanyfurther
claim,contractorwouldbeentitledtoraiseanyclaimandwouldnotbeestopped
orprecludedfromraisinganyclaim.
ba
y
11.
10.13 of the impugned award. It was observed that procedure stated under
clause60.8(b)and(c)wasnotobservedbytheGovernment. Contractoralso
om
didnotsubmitthe'draftstatementofFinalAccounts'asperClause60.8(a)and
didnotpursueitwiththeGovernment forissuanceofsuchcertificateofFinal
AccountasperClause60.8(c).TheArbitralTribunalobservedthatneitherthe
contractornortheGovernmenthereinadheredtotheprovisionsofClause60.8.
Ithasbeenheldthatitwouldhavebeenreasonableonthepartofthecontractor
to expect that the five claims would be considered by the Government
1 2004(5)ALLMR(SC)
Asmita
6/48
..7..
ARA6/07
rt
independentlyandaccepted,partiallyacceptedorrejectedontheirmeritsasthe
C
ou
casemaybeandifthatdecisionoftheGovernment wasnotacceptabletothe
contractor,thedisputecouldthenbereferredtothePanelofArbitratorsasper
Clause66SettlementofDispute.TheArbitralTribunalrenderedafindingthat
thecontractordidnotwaiveitsrighttoreferitsclaimforadjudicationbythe
ig
h
Arbitral panel merely because they had not lodged the protest against the
paymentbytheGovernmentoneither164thandfinalor165thorfinalbill.
TheDistrictJudgehasconsideredthisissueinparagraphs33and34
12.
oftheimpugnedOrderandhasrejectedthecontentionraisedbytheGovernment
13.
ba
y
afterrecordingreasons.
Onperusaloftherecordsproducedbyboththepartiesandonperusal
om
of the award made by the Arbitral Tribunal and order passed by the learned
DistrictJudge,itisclearthattheprocedureunderClause60.8wasnotfollowed
by either party. Thus RA bills 164 and 165 and final bills were rightly not
consideredbytheArbitralTribunalasfinalbills.Itisnotindisputethatthere
wasanyseparatebillpreparedinrespectoffiveclaimsmadebythecontractor.
Inmyview,afterconsideringthefactsandthedocumentsandoninterpretation
ofClause60.8,ArbitralTribunalhasrenderedafindingthattherewasnoaccord
Asmita
7/48
..8..
ARA6/07
rt
andsatisfactionandthecontractorhadnotwaiveditsrighttomakeanyclaims.
C
ou
SuchfindingsrenderedbytheArbitralTribunalandconfirmedbythelearned
DistrictJudgearenotperverse. Inmyview,nointerferenceisthuswarranted
withsuchfindingsrenderedbytheArbitralTribunalandupheldbytheDistrict
ig
h
Judge.
14.
appearingfortheGovernmentisthatClaimNo.1madebythecontractorbefore
ba
y
1998.Itissubmittedthatthoughtheworkinrespectofthisclaimwascompleted
during the pendency of earlier arbitration proceedings, the contractor did not
om
raisethisclaimintheearlierarbitration.
15.
contractorontheotherhandsubmitsthattherewere3Claimsreferredtoearlier
arbitraltribunaland2Claimswereaddedlateron.Itissubmittedthatpresent
Claim No.1 was not matured at that time and could not be included in that
arbitration. ItissubmittedthatmakingpaymentforExtra/deviateditemswith
denovorateanalysisafterapplyingthelabourmarkupandoverheadandprofit
Asmita
8/48
..9..
ARA6/07
rt
markup,asawardedbytheearlierarbitrationpanelwasunderconsiderationat
C
ou
variouslevelsoftheGovernment.ThecontractorinitiatedthesaidClaimon30 th
March1999andthesamewasrecommendedbytheEngineeroftheGovernment.
TheissuewasunderconsiderationatdifferentlevelsoftheGovernmentasthe
GovernmentdidnotpayevenattherateadoptedbytheArbitralTribunalinthe
ig
h
earlierarbitration,thecontractorinvokedarbitrationvideletterdated27th July
2000.Itissubmittedthatthelearnedarbitratorhasrenderedafindingoffact.
ClaimNo.1wasreferredbytheGovernmentitselfforadjudicationofthearbitral
tribunal. The District Judge also rejected this contention advanced by the
Government inparagraph45oftheimpugnedorder. TheDistrictJudgeheld
ba
y
that the disputes referred in 19971998 were distinct than present one and
therefore,noquestionofresjudicataarises.Thelearnedseniorcounselpointed
outthattheonlygroundraisedinarbitrationapplicationfiledunderSection34
om
onthisissuewasthattheClaimwasbarredbytheprinciplesofresjudicata.Itis
pointedoutthatsimilargroundisraisedevenintheappealmemoinground(g).
The learned senior counsel submits that the claim made before the arbitral
tribunal in the second reference was admittedly not made before the arbitral
tribunalinthefirstreference.Therewasnoadjudicationofanysuchclaiminthe
earlierproceedings.Thequestionofapplicabilityoftheprinciplesofresjudicata
therefore,didnotarise.
Asmita
9/48
..10..
Onperusaloftheimpugnedawardaswellastheorderpassedbythe
rt
16.
ARA6/07
C
ou
learned District Judge, it is clear that the finding is rendered by the arbitral
tribunal as well as the learned District Judge that Claim No.1 pertained to
variation in proposed percentages for the labour mark up and overheads and
profitonthesamelinesforextraitemsanddeviateditemswhichhadcroppedup
ig
h
duringtherestofthecontractwork. Ithasbeenheldthatmajorpartofthese
itemshadbeenexecutedevenpriortoreferringtheclaimtotheearlierArbitral
Panel.ThelearnedTribunalobservedthatClaimNo.1hadbeenincludedbythe
ba
y
referenceweredifferent.TheDistrictJudgealsonegativedthecontentionofthe
Governmentontheissuewhilerecordingdetailreasons.Inmyview,asClaim
No.1madeinthepresentproceedingswasnotclaimedadmittedlyintheearlier
om
arbitrationproceedings,therewasnoadjudicationonsuchclaimbytheArbitral
Tribunal,andthus questionofapplicabilityofprinciplesof resjudicata didnot
arise. The only ground raised by the Government in its application under
Section34beforetheDistrictJudgeandinthisappealmemofiledunderSection
37 of the Act, it is urged that the claim was barred by the principles of res
judicata.Inmyview,thereisnomeritinthepleaoftheGovernmentthatClaim
No.1isbarredby resjudicata andthus,thisplearaisedbytheGovernment is
Asmita
10/48
..11..
ARA6/07
C
ou
rt
rejected.
17.
ThenextsubmissionurgedbyMrKumbhakoni,thelearnedcounselfor
theGovernmentisthattheclaimsarebarredbylawoflimitation.Itissubmitted
thattheworkofpressureshaftexcavationwasstartedon9thJuly1993andwas
ig
h
ba
y
om
16thJuly1992andwascompletedon31stMarch1995,whereasissuewasraised
beforetheExecutiveEngineeron4thJune2001.ItissubmittedthatasperClause
11/48
..12..
ARA6/07
rt
C
ou
appealedtotheSuperintendingEngineerwithin30days. Itissubmittedthat
afterpreferringthedisputetoExecutiveEngineer,contractorwaitedfor3years
butdidnotexercisehisrighttofileanappeal.ItissubmittedthatitemNos.3,4
and5wereinexistenceintheyear1998whenthefirstarbitrationtookplace.
ig
h
fromthedatewhentheworkwascompleted. Itissubmittedthatinrespectof
ClaimNos.3,4and5,theworkwascompletedmuchpriorto3yearsbeforethe
ba
y
om
Engineerandalsothedateofinvokingarbitration.Thesaidtableisreproduced
asunder:
Asmita
12/48
..13..
ARA6/07
Work
Ref.to
Rej.by
Ref.to
Rej.by
Ref.To
Rej.By
Arbitration
invoked
Nos.
completed
EE
EE
SE
SE
CE
CE
02.09.97
20.11.00
19.02.94
01.06.01
31.03.95
04.06.01
ig
h
C
ou
rt
Claim
Article137ofPartIIoftheLimitationActreadasunder:
Art.
Descriptionofapplication
Periodof
18
Forthepriceofworkdonebytheplaintiff
forthedefendantathisrequest,whereno
timehasbeenfixedforpayment.
Threeyears
Threeyears
Anysuitforwhichnoperiodoflimitationis
providedelsewhereinthisSchedule.
Thereyears
Whentherighttosue
accrues.
om
55
ba
y
limitation
113
Asmita
Timefromwhich
periodbeginstorun
13/48
..14..
Threeyears
rt
Anyotherapplicationforwhichnoperiodof
limitation is provided elsewhere in this
division.
C
ou
137
ARA6/07
18.
MrKumbhakoni,thelearnedcounselsubmitsthatoncecauseofaction
had commenced, it did not stop. It is submitted that merely because the
ig
h
representationand/orClaimwasmadebythecontractorbeforevariousofficers
were pending and were not decided, cause of action would not stop. The
learnedcounselpressedintoserviceSection9oftheLimitationActinsupportof
thisplea.ThelearnedcounselplacedrelianceuponthejudgmentofthisCourt
decidedon9thOctober2012incaseofAdityaBirlaChemicals(India)Ltd.Vs.
ba
y
TataMotorsLtd.2inArbitrationPetitionNo.1027of2011deliveredbythisCourt
(R.D.Dhanuaka,J.)andmoreparticularlyparagraphs18an19whichreadthus:
om
18. InmyviewclaimmadebytheRespondentwasaclaimsimplicitorfor
2 MANU/MH/1642/2012
Asmita
14/48
..15..
ARA6/07
C
ou
rt
ig
h
19.
JudgmentofSupremeCourtincaseofJ.C.Budhrajavs.Chairman,OrissaMinig
CorporationLtd.AndAnother3andmoreparticularlyparagraphs25and26in
supportofhispleathatlimitationforasuitiscalculatedasonthedateoffilingof
suit,whereasincaseofarbitration,limitationoftheClaimistobecalculatedon
om
ba
y
thedateonwhichthearbitrationisdeemedtohavebeencommenced.
25.
The learned Counsel for the Government submitted that the
limitationwouldbeguntorunfromthedateonwhichadifferencearosebetween
theparties,andinthiscasethedifferencearoseonlywhenOMCrefusedtocomply
withthenoticedated4.6.1980seekingreferencetoarbitration.Weareafraid,the
contentioniswithoutmerit.TheGovernmentisobviouslyconfusingthelimitation
forapetitionunderSection 8(2) oftheArbitrationAct,1940withthelimitation
fortheclaimitself.Thelimitationforasuitiscalculatedasonthedateoffilingof
thesuit.Inthecaseofarbitration,limitationfortheclaimistobecalculatedonthe
dateonwhichthearbitrationisdeemedtohavecommenced.
26.
Section 37(3) oftheActprovidesthatforthepurposeofLimitation
Act, anarbitration isdeemed to have been commenced when one partytothe
arbitration agreement serves on the other party thereto, a notice requiring the
appointmentofanarbitrator.Suchanoticehavingbeenservedon4.6.1980,ithas
tobeseenwhethertheclaimswereintimeasonthatdate.Iftheclaimswere
barredon4.6.1980,itfollowsthattheclaimshadtoberejectedbythearbitrator
on the ground that the claims were barred by limitation. The said period has
nothingtodowiththeperiodoflimitationforfilingapetitionunderSection8(2)
oftheAct.InsofarasapetitionunderSection8(2),thecauseofactionwouldarise
3 (2008)2SupremeCourtCases444
Asmita
15/48
..16..
ARA6/07
C
ou
rt
when the other party fails to comply with the notice invoking arbitration.
Therefore,theperiodoflimitationforfilingapetitionunderSection8(2)seeking
appointmentofanarbitratorcannotbeconfusedwiththeperiodoflimitationfor
making a claim. The decisions of this Court in Inder Singh Rekhi v.
MANU/SC/0271/1988 : Delhi Development Authority [1988]3SCR351 , Panchu
Gopal Bose v. MANU/SC/0385/1994Board of Trustees for Port of Calcutta
[1993]3SCR361 and Utkal Commercial Corporation v. MANU/SC/0028/1999 :
CentralCoalFields[1999]1SCR166alsomakethispositionclear.
ig
h
20.
appointmentofanarbitratorcannotbeconfusedwithperiodoflimitationfor
makingaclaim.ItissubmittedthatthelearnedarbitratoraswellastheDistrict
Judgehavemixedthetwoseparatearticlesoflimitationi.e.applicabletoClaims
andformakingapplicationforappointmentofarbitrator. Thelearnedcounsel
ba
y
submitsthatthelearnedDistrictJudgehasplacedrelianceuponArticle137of
ScheduleI to the Limitation Act and also Article 55 which are not at all
applicabletotheClaimsmade. ItissubmittedthatArticle137appliestothe
om
applicationinCourtandnottotheClaim.Itissubmittedthattherewasnoclaim
forcompensationbeforethelearnedarbitratorwhichwouldfallunderArticle55.
The learned counsel then placed reliance upon the Judgment of this Court
delivered on 16th December 2011 in case of Maharahshtra State Power
GenerationCo.Ltd.Vs.M/s.GeoMillerCo.Pvt.Ltd.inArbitrationPetition
No.466of2006andmoreparticularlyparagraphs2to8whichreadthus:
Asmita
2.Therelevantfactsare,thePetitionerhadfloatedatenderforthedesign,
manufacture, supply, erection, testing and commissioning of the prewater
16/48
..17..
ARA6/07
om
ba
y
ig
h
C
ou
rt
Asmita
3.ThelearnedCounselappearingforthePetitionersubmitsthatthe
learned Arbitratorfailedtoseethattheperiodoflimitationforinvokingthe
arbitrationclausewillbegovernedbyArticle18oftheScheduleoftheLimitation
Act. According to the learned Counsel, the cause of action for invoking the
arbitrationclausewillarisewhentheworkforthepriceofwhichthearbitration
clausehasbeeninvokedwasdoneandthat was in the year1992and
therefore,invocationofthearbitrationclauseinJanuary,2001isbarredbythe
lawofLimitation.ThelearnedCounselreferringtotheprovisionsofSection9of
theLimitationActsubmittedthatoncetheperiodoflimitationiscommence,itwill
runcontinuouslyandtherefore,merelybecausecorrespondencewasgoing
onbetweenthepartiesinrelationtotheamounttobepaid,runningoftheperiod
oflimitationwillnotstop.ThereferencehastobemadebytheRespondentwithin
aperiodofthreeyearsfromthedateonwhichtheworkwascompleted.
4. The learned Counselappearing for theRespondent,ontheother
hand,relyingonseveraljudgmentsincludingthejudgmentofthelearnedsingle
Judgeofthiscourt inthecase ofShri Nyaneshwa Bhiku Dhargalkar v/s.
Executive Engineer, 1999(3) RAJ (B0m) submitted that it is Article 137 of the
LimitationActwhichappliesinthepresentcaseandthattherighttoapplywill
17/48
..18..
ARA6/07
ig
h
C
ou
rt
accruewhenthedisputebetweenthepartiesarose.Accordingtothelearned
Counseltillthenegotiationsbetweenthepartiesweregoingonandasthere
wasnodenialtomakethepaymentintheyear1992,thecauseofactionwillnot
accrueandthereforethearbitrationclausewasinvokedwithintheperiod
oflimitation.ThelearnedCounselalsoreliesonthejudgmentofthelearned
singleJudgeoftheDelhiHighCourtinthecaseofPremPowerConstruction(Pvt)
Ltd.v/s.NationalHydroelectricPowerCorp.Ltd.&Anr.160(2009)DelhiLaw
Times610.PerusalofthejudgmentofthelearnedsingleJudgeofthiscourtinthe
caseofNyaneshwar(supra)andthejudgmentofthelearnedsingleJudge
oftheDelhiHighCourtinthecaseofPremPowerConstructionLtd.(supra)shows
that both have relied on the judgment of the Supreme Court in the case of
Major(Retd.)InderSinghRekhiv/s.DelhiDevelopmentAuthority,(1988)2
SCC338.ThelearnedCounselfortheRespondentalsosubmittedthatinany
casetheperiodoflimitationwouldbegovernedbyArticle113oftheLimitation
Act. Accordingtohim,thecauseofactionwillarisewhentherighttosue
accruesandtherighttosuewillaccruewhenthePetitionerrefusedtomakethe
paymentfortheextraworkafterfinalbill.Thus,therighttosueaccruedinthe
year1999whentherewasrefusaltomakethepayment.
ba
y
om
EveniftherewasrejectionoftheClaimantsclaimforextraworkon
10101995assubmittedbythemthelimitationcannotbesaidtohave
commencedfromthatdate,ifregardbehadtothefactthatevenaccordingtothe
Respondentsthefinalbillwaspreparedaslateason16thDecember,2000.
Thus,accordingtothelearnedArbitratorthecauseofactiondoesnotaccrue
oncompletionofthework.Itdoesnotaccrueevenonrejectionoftheclaim,butit
accrueswhenthefinalbillisprepared.
6.OnbehalfofthePetitionerrelianceisplacedonArticle18oftheLimitation
Act.ThatArticlereadsasunder:
(18)Forthepriceofworkdonebytheplaintiffforthedefendantat
hisrequest,where notimehasbeenfixedfor payment.ThePeriodof
limitationisthree years andthe timebegins torunwhenthe workis
done.
7.PerusaloftheabovequotedArticleshowsthatwhenasuitistobe
instituted for recovery of the price of the work done by the Plaintiff for the
Asmita
18/48
..19..
ARA6/07
C
ou
rt
Defendant,andwhenthereisnotimefixedforpaymenttobemade, the
causeofactionforinstitutingthesuitariseswhentheworkiscompletedand
thesuithastobeinstitutedwithinaperiodofthreeyearsfromtheaccrual
ofcauseofaction.Itisclearfromtherecordthatthepresentdisputewhichwas
referredtoarbitrationisforrecoveryofthepriceoftheextraworkdoneby
theRespondentforthePetitionerattherequestofthePetitionerandthere
wasnotimefixedformakingthepayment. Therefore,accordingtothisArticle,
thecauseofactionwillaccruewhentheworkisdone. Thelearned Counsel
appearingfortheRespondentreliedonArticle113oftheLimitation
Act.
Article113readsasunder:
113.Anysuitforwhichnoperiodoflimitationisprovidedelsewhere
in the Schedule, the period of limitation is three years and the time
beginstorunwhentherighttosueaccrues.
ig
h
om
ba
y
8.PerusaloftheaboveArticlemakesitclearthatthisArticlecomesintoplay
onlyonafindingthatforinstitutionofasuitfortheclaimwhichisinvolvedinthe
presentmatter,thereisnoperiodoflimitationprovidedelsewhereinthe
schedule.Therefore,unlessafindingisrecordedthatArticle18does
notapply,Article113cannotapply.IdonotseeanyreasonwhyArticle18will
notapplytothepresentdispute,becausethepresentdisputeisinrelationtothe
priceoftheworkdonebytheRespondentforthePetitioner.ThelearnedCounsel
fortheRespondentalsocouldnotgiveanyreasonwhyArticle18willnotapply.
Thus,astheworkwascompletedintheyear1992,thecauseofactionin
termsofArticle18willaccruein1992andthereforethereferencewillhavetobe
madewithin a period of 3 years from 1992 unlessaccording to
Respondentthetimegetsextendedbecauseof anyacknowledgement etc.
Admittedlyneitherarbitrationclauseisinvokedwithinthreeyearsfrom1992nor
anyextensionoftheperiodoflimitation is claimed by the Respondent,
and therefore the claim will be barred by the law of limitation. What is
interestingisthatthequestionbeforethelearnedArbitratorwaswhetherthe
claim was made within the period oflimitation. Thelearned
Arbitrator has recorded a finding that the claim is not barred by the law of
limitation, but in the entire award there is no reference to any Article in the
ScheduleoftheLimitationAct,whichappliestothepresentcase.Inmyopinion,
thisisanimpossibility.Anargumentastowhetheraclaimismadewithin
theperiodoflimitationhasalwaystobemadewithreferencetosomeArticlein
theScheduleoftheLimitationAct,withoutreferringtoanyarticleintheSchedule
oftheLimitationAct,afindingeitherthattheclaimisbarredbylimitationoritis
notsobarredisimpossibletoberecorded.
SofarasapplicationofArticle137isconcerned,that Article is in PartII,
relating to applications. For invoking the arbitration clause the limitation
providedbytheLimitationActformakingapplicationwillnotapply,thelimitation
providedbythescheduleforinstitutionofasuitwillapply.Thelearnedsingle
JudgeofthisCourtinhisjudgmentinNyaneshwarcase(supra)andthelearned
Asmita
19/48
..20..
ARA6/07
om
ba
y
ig
h
C
ou
rt
singleJudgeoftheDelhiHighCourtinthecaseofPremPowerConstructionLtd.
(supra)havereliedonjudgmentoftheSupremeCourtinthecaseofInderSingh
Rekhi,referredtoabove.PerusalofthatjudgmentoftheSupremeCourt shows
thattheretheSupremeCourtwasdealingwiththeapplicationmadeunder
Section20ofArbitrationAct,1940,andasunderSection20 oftheArbitration
Act,1940anapplicationwastobemadetothecourt,obviouslyArticle137ofthe
LimitationActwillapply.Butintheschemeofthe1996Actnosuchapplication
iscontemplatedtobemadetoanycourtforinvokingthearbitration
clause. PerusaloftheprovisionsofSection 21 of the Arbitration Act
showsthatArbitralproceedingscommence,unlessthereisanagreementcontrary
betweentheparties,onthedateonwhicharequestforreferenceofthe
disputetoarbitrationisreceivedbytheRespondent.The1996Act
doesnot contemplate anyapplicationtobemadetothecourtforinvoking the
arbitration application and for commencement of arbitration proceedings.
Subsection 2 of Section 43 of the Arbitration Act lays down that for the
purposeoflimitationActanarbitrationshallbedeemedtohavecommencedon
the date referred to in Section 21. Therefore, it is clear that invocation of the
arbitrationclausehastobemadewithintheperiodoflimitationprovidedbythe
LimitationActforinstitutionofasuitonthesamecauseofaction.So
farasanapplicationtobemadeunderSection11isconcerned,that
applicationisnotforinvokingthearbitrationclause.Thatapplicationisfor
appointment of arbitrator, after invoking the arbitration clause.
Invocation of the arbitration clause precedes an application under Section 11.
Therefore,whenanapplicationunderSection11ismade,thatapplicationhasto
bemadewithintheperiodoflimitation,whichisprovidedbytheLimitationAct
forinstitutionofthesuitonthatcauseofaction.AnapplicationunderSection11
cannot be made after expiry of the period oflimitationprovidedfor
institutionofsuitforrecoveryoftheclaim.TheHonbletheChiefJustice
orhisdesignatewillhavetomakeaninquirytofindoutwhethertheappointment
ofArbitratoratthisjuncturewouldbenecessaryasaperiodoflimitationisover.
TheSupremeCourtinitsjudgmentinthecaseofNationalInsuranceCo.Ltd.v/s.
M/s.BogharaPolyfabPvt.Ltd.,AIR2009SC170,hasreferredtotheissues
whichhavetobedecidedbytheChiefJusticeorhisdesignateunder
Section11andtheissueswhichcanbeleftfordecisionbytheArbitrator.Oneof
theissues,accordingtotheSupremeCourtthathastobedecidedbytheHonble
ChiefJusticeorhisdesignateunderSection11iswhethertheclaimisa
dead claim or a live claim. It means that if an objection is raised, when
applicationunderSection11ismade,thatinvocationofthearbitrationclausein
thatcasehasnotbeenmadewithintheperiodoflimitation,thenthat
questionhastobedecidedbytheChiefJusticeorhisdesignate.Thequestionto
beconsideredatthattimeisnotwhetheranapplicationunderSection11
ismadewithintheperiodoflimitation,butwhethertheinvocation
ofthearbitrationclausewasmadewithintheperiodoflimitation.Inmyopinion,
therefore,thereisnoquestionofprovisionsofSection137applyinginsofaras
invocationofthearbitrationclauseandcommencement of the period of
limitationisconcerned.Sofarasthepresentcaseisconcerned,tomy
Asmita
20/48
..21..
ARA6/07
C
ou
rt
minditisclearthatArticle18oftheLimitationActappliesandthereforeasthe
invocationoftheArbitrationclauseisnotwithinperiodofthreeyearsfromthe
dateofcompletionofthework,whichwasintheyear1992,theclaimwasclearly
barredbythelawoflimitation.
21.
RelyinguponthisJudgmentofthisCourt,thelearnedcounselsubmits
that Article18 was applicable to the claims made by the contractor and not
ig
h
StatePowerGenerationCo.Ltd.(supra)andthesaidJudgmentisthusbinding.
ThelearnedcounselalsoplacedrelianceupontheJudgmentofPunjab
ba
y
22.
AndHaryanaHighCourtincaseof JullunderImprovementTrust,Jullunder
Vs.KuldipSingh4andmoreparticularlyparagraphs4and5whichreadthus:
om
4.
Themaincontroversyinthisappealis:whetherthesuitoftheplaintiff
wanwithintimeornot?ItisthecommoncaseofthepartiesthatitisArticle18,
Limitation Act, 1963, which would govern the plaintiffs case. It provides a
limitationofthreeyearsfromthetimetheworkisdone.Thepresentsuitwasfiled
on 921971. According to the plaintiff the cause of action arose to him on
14121967,whenthepaymentofthefinalbill,ExhibitD.19,wasreceivedbyhim
underprotestwhereasthecaseofthedefendantisthattheperiodofthreeyears
would commence from the date the work was done which according to it was
completed on 2891967, as admitted by the plaintiff himself vide, Exhibit D.4,
dated2891967,writteninthisownhandwhereinhehadstatedthat90feetwide
roadunder84acresschemewascompleteand,therefore,hisfinalbill,beprepared
accordingly.Inanycase,accordingtothedefendant,inthefinalbill,ExhibitD.19,
thecertificatetotheeffectthatnecessarydetailedmeasurementshavebeentaken
asrecorded intheMeasurement Book No. 44, was given on 7101967, by the
4 AIR1984PunjabAndHaryana185
Asmita
21/48
..22..
ARA6/07
ig
h
C
ou
rt
EngineerinchargeMohinderSingh,whoappearedasD.W.7.Thus,itwasargued
onbehalfofthedefendingthatevenafterthatdate.i.e.7101967,thepresent
suitfiledon921971,evenafterallowingthenoticeperiodoftwomonthswas
barredbytime.AccordingtothetrialCourt,thecauseofactionwouldarisetothe
plaintiff for the price of the work done only on furnishing of the completion
certificate by the Engineer in charge. The certificate of the Engineer in charge,
accordingtothetrialCourtdidnotbear anydate.Since,according tothetrial
Court thepayment of the lastbill was received by the plaintiff on 14121967,
under protest, the period of limitation will start from that date and that after
allowing the notice period of two months, the suit filed by the plaintiff on
921971,waswithintime.ThetrialCourtalsofoundthattheplaintiffprosecuted
withduediligenceanothercivilproceedingfoundeduponthesamecauseofaction
inaCourtwhichcouldnotgivethereliefand,therefore,hewasentitledtoget,the
period spent inprosecuting those proceedings excluded under S. 14,Limitation
Act,(hereinaftercalledtheAct).
5.
After hearing the learned counsel for the parries, I am of the
consideredopinionthattheplaintiffssuitwasbarredbytime.
23.
ba
y
contractor on the other hand submits that Article18 is not applicable to the
claimsmadebythecontractor. Thelearnedseniorcounselsubmitsthatthe
om
claimsmadebeforethearbitraltribunalwereforenhancementofthepricefor
theworkdoneandthusArticle113ofSchedule1ofLimitaitonActwouldapply.
The learned senior counsel placed reliance upon the Judgment in case of
Gannon Dunkerley And Co. Ltd. v. Union of India5 and more particularly
paragraphs2to11whichreadthus:
2. The Sindri Factory Buildings were to be constructed under the advice and
guidance of M/s. Chemical Construction Corporation of New York. That Firm
madedelayinsupplyingthedrawingsandspecificationswhichinvolvedworkofa
51969(3)SupremeCourtCases607
Asmita
22/48
..23..
ARA6/07
rt
complicatednaturenotincludedintheoriginalcontract.Timeforcompletionof
theworkwasonthataccountextendedtillFebruary26,1950.
3. On September 20, 1950 the Government Company made a demand for
paymentofanenhancedrateof421/2%overthebasicratesstipulatedunderthe
originalcontract.Thisclaimwasmadeonfivegrounds:
1.thattherewasasubstantialdeviationinthenatureofworkofwhich
thedetailedworkdrawingsweresuppliedtotheGovernment Company
afterthedateofthecontract.Theworkinvolvedwasofacomplexnature
requiring highlyskilledlabour,andthatadditional labour andmaterials
notcoveredbythecontractrateswererequired;
2. thattherewasgreatincreaseinthepriceofmaterialsandlabouron
accountofundueprolongationoftheperiodofwork;
3.thattherewasincreaseinthecostoftransportationonaccountofrise
inthepriceofpetrolandincreaseinrailwayfreight;
4.thattheGovernmentofIndiaenteredintoothercontractsincidentalto
theconstructionoftheSindriFactoryatsubstantiallyhigherrateswhich
directly affected the cost of labour and materials of the Government
Companywhohadtocompetewiththeothercontractors;
5. thatadditionalworkorderedtobedoneinvolvedinmanyinstances
quantityofworkseveraltimestheworksetoutinthecontract.
ig
h
ba
y
om
C
ou
4.
ByhisletterdatedSeptember13,1950,theAdditionalChiefEngineer
rejectedtheclaim.InSeptember1954thedisputesrelatingtotheclaimforrisein
costofmaterialandlabourduetodelayinsupplyingdetailedworkdrawings,the
claimarisingfromriseinpriceofpetrolandforincreaseinthecostofmaterialand
labourduetoothercontractorsworkingonthesite,werereferredtoarbitration,
butnottheclaimsforrevisionofratesduetocomplexnatureoftheworkand
increase in the quantity of work. The arbitrator rejected the claims of the
Companyinrespectofthematterswhichwerereferred.
5.
ThereaftertheGovernmentCompanyfiledasuitonAugust9,1956,
against theUnion ofIndia,for adecree for Rs.3,62,674/9/6 being the amount
claimedattherateof421/2%abovethecontractrate,inthealternative,adecree
for Rs.2,44,000/ being the amount claimed at the rate of 28.1% above the
contract rate as recommended by the Executive Engineer, and in the further
alternative,adecreeforRs.1,36,222/attherateof18.17%abovethecontract
rateascertifiedbytheSuperintendingEngineer. TheUnionofIndiacontended,
interalia,thattheclaimwasbarredbythelawoflimitation.
6.
Asmita
The Trial Court held that the claim was not barred by the law of
23/48
..24..
ARA6/07
C
ou
rt
limitation and decreed the claim for Rs. 1,36,222/ as certified by the
Superintending Engineer. Against the decree passed by the Trial Court the
GovernmentCompanyaswellastheUnionofIndiaappealedtotheHighCourt.
7.
Before the High Court, in support of the appeal only the plea of
limitationwaspressedonbehalfoftheUnionofIndia.IntheviewoftheHigh
CourttheclaimwasgovernedeitherbyArticle56orbyArticle115oftheFirst
ScheduletotheLimitationAct,1908,andthesuitnothavingbeenfiledwithin
threeyearsofthedateonwhichtheworkwasdoneandinanyeventofthedate
on which the claim was rejected was barred. The Government Company has
appealedtothisCourtwithcertificate.
8.
TheGovernment Companyhadundertakenunderthetermsofthe
contracttodospecificconstructionworkat"basicrates".TheEngineerincharge
wasbythetermsofClause12oftheagreementcompetenttogiveinstructionsfor
work not covered by the terms of the contract, and it was provided that
remunerationshallbe paidattheratefixedbytheEngineerinchargefor such
additional work, and in case of dispute the decision of the Superintending
Engineer shall be final. It is common ground that the claim made by the
GovernmentCompanywasnotcoveredbythearbitrationagreement,andonthat
account it was not referred to the arbitrator. The claim in suit related to the
revisionofratesduetothecomplexnatureoftheworkandduetoincreaseinthe
quantity of work and also grant of contracts to other competing parties at
substantiallyhigherratesandotherrelatedmatters.
om
ba
y
ig
h
Asmita
9.
Article56oftheFirstSchedule totheIndianLimitationAct,1908,
prescribesaperiodofthreeyears forasuitfor thepriceof,work done bythe
plaintiff for the defendant at his request, where no time has been fixed for
payment,andtheperiodoflimitationcommencestorunfromthedatewhenthe
workisdone.AsuitisgovernedbyArticle56ifitarisesoutofacontracttopay
thepriceofworkdoneattherequestofthedefendant.Theclaiminthepresent
caseisforpaymentatanadditionalrateoverthestipulatedrateinviewofchange
incircumstances,andnotforpriceofworkdonebytheGovernmentCompany.It
istruethatadditionalworkwasdoneattherequestoftheEngineerincharge,but
theclaiminsuitwasnotforthepriceofworkdonebutforenhancedratesinview
ofalteredcircumstances.
10.
Article115oftheFirstScheduletotheLimitationActisaresiduary
articledealing withthe claim for compensation for the breach of any contract,
expressorimplied,notinwritingregisteredandnotspeciallyprovidedfor,inthe
First Schedule. The period of limitation in such cases is three years and it
commences to run when the contract is broken, or where there are successive
breacheswhenthebreachinrespectofwhichthesuitisinstitutedoccurs,orwhere
the breach is continuing when it ceases. The suit filed by the Government
24/48
..25..
ARA6/07
C
ou
rt
Companyisnotasuitforcompensationforbreachofcontractexpressorimplied:
itisasuitforenhancedratebecauseofchangeofcircumstances,andinrespectof
worknotcoveredbythecontract.TheadditionalworkdirectedbytheEngineerin
charge when carried out may be deemed to be done under the terms of the
contract:buttheclaimforenhancedratesdoesnotariseoutofthecontract:itisin
anycasenotaclaimforcompensationforbreachofcontract.
11.
Theclaimisthereforenotcoveredbyanyspecificarticleunderthe
FirstSchedule,andmustfallwithinthetermsofArticle120.TheSolicitorGeneral
appearingonbehalfoftheUnionofIndiacontendedthateveniftheclaimfalls
within the terms of Article 120 of the Limitation Act, it was barred, for, the
GovernmentCompanyhadinthesuitmadeaclaimforworkdonemorethansix
yearsbeforetheinstitutionofthesuit.CounselsubmittedthatunderArticle120
theperiodoflimitationcommencestorunfromthedateonwhichthedefendant
obtainsthebenefitoftheworkdonebytheplaintiff.ButunderArticle120ofthe
LimitationActtheperiodofsixyearsforsuitsforwhichnoperiodoflimitationis
provided elsewhere in the Schedule commences to run when the right to sue
accrues.Inourjudgment,thereisnorighttosueuntilthereisanaccrualofthe
rightassertedinthesuit,anditsinfringement,oratleastaclearandunequivocal
threattoinfringethatrightbythedefendantagainstwhomthesuitisinstituted;
Bolov.KokanandOrs.
24.
ThelearnedcounselsubmitsthattheSupremeCourthadconsidered
ba
y
ig
h
Article120oftheLimitationAct,1908andArticle56whicharecorrespondingto
Article113 and Article18 to the first schedule to Limitation Act 1963. It is
om
submittedthatafterconsideringtheseArticles,theSupremeCourtheldthatthe
periodof6yearsforsuitsforwhichnoperiodoflimitationisprovidedelsewhere
intheSchedulecommencestorunwhentherighttosueaccrues.Itisisheldthat
therewasnorighttosueuntiltherewasaccrualoftherightassertedinthesuit,
anditsinfringement,oratleastaclearandunequivocalthreattoinfringethat
rightbythedefendantagainstwhomthesuitisinstituted.Itissubmittedthat
theSupremeCourthasheldthatinasuitforenhancedratebecauseofchangeof
Asmita
25/48
..26..
ARA6/07
rt
circumstances, and in respect of work not covered by the contract, claim for
C
ou
enhancedratedidnotariseoutofcontractandwouldbethusnotgovernedby
Article56correspondingtoArticle18underLimitationAct1963butwouldbe
coveredbyArticle120(correspondingtoArticle113underLimitationAct1963).
Thelearnedseniorcounselthus,submitsthatthefactsofthiscaseareidenticalto
ig
h
the facts before the Honourble Supreme Court in case of Gannon Dunkerley
(supra)andthusprinciplesoflawlaiddownbytheSupremeCourtaresquarely
applicabletothefactsofthiscaseandarebindingonthisCourt.
25.
ThelearnedseniorcounselalsoplacedrelianceupontheJudgmentof
ba
y
RajashthanHighCourtincaseofStateofRajasthanVs.RamKishan(AIR1977
Rajasthan165),JudgmentofAllahabadHighCourtincaseofStateofU.P.v.
ThakurKundanSingh(AIR1984Allahabad161),JudgmentofGujratHigh
om
CourtincaseofStateofGujratVs.PirojshaWadiareportedin17GujratLaw
Reporter638; bywhichvariousHighCourtshavetakenasimilarviewwhich
hasbeentakenbytheHonourableSupremeCourtincaseofGannonDunkerly
andOrs(supra).
26.
submissionofthecontractorwasthatdisputecouldstartonlyafterrejectionof
Asmita
26/48
..27..
ARA6/07
rt
theclaimbytheGovernment.Itwassubmittedthattheclaimswerependingfor
C
ou
decisionandthuscauseofactionstartedonlyafterdecisionwasfinallytakenby
theGovernment.Itwassubmittedthatlimitationcommencedfromthedateon
whichcauseofactionhadaccrued.
27.
Thearbitraltribunalhasheldthatallthoseclaimseventhoughthere
ig
h
was specific recognisable period of start of incurring of the loss, the same
continuedsincethenduringthecurrencyofthecontract,includingtheextended
periodatleastforClaimNos.1and2.MajorityofthelossincurredforClaimNos.
3,4and5wasknownwhentheitemswerenearlycompletebyMarch1998.Itis
ba
y
heldthatinrespectofClaimNos.1and2,thelosscontinuedtillthecurrencyof
thecontract. ThearbitraltribunalthenheldthatforClaimNos.3,4and5,first
referencetoEngineer'srepresentative(ExecutiveEngineer)wasmadeinFebruary
om
1997andOctober1996andongettingnodecisionwithin60days,thecontractor
couldhavereferredthedisputetohigherlevelandthentothe'Engineer'asper
provisionsofClause66andinvokedthearbitrationwithin220daysatthemost.
Itisfurtherheldthatthiscoursewasnottakenbythecontractorforthereasons
bestknowntohim.Thecontractormighttaketheshelteroftheword'may'inthe
contractormayappealwithin30daystoEngineer'byclaimingthatitwasnot
obligatoryforhimtoappealincasenoreplywasgiventheExecutiveEngineer.
Asmita
27/48
..28..
ARA6/07
rt
Inspiteofsuchfindingrenderedbythearbitraltribunal,itisheldthatthecause
C
ou
ofarbitrationwouldbecauseofactionandtimeoflimitationshouldberecorded
from the date for respective claims. The tribunal held that all five claims in
questionwerenottimebarredonaccountoflimitation.Itwouldbeusefulto
extracttherelevantparagraphsonthisissuefromthearbitralawardwhichareas
ig
h
under:
om
ba
y
Forreferringthedisputetoarbitration,therehadtobeanarbitrationagreement
(clause)andtherehadtobeadispute. Intheinstantcase,Cl66Settlementof
dispute (RTD1/1034) provided for recourse to arbitration. For existence of
'dispute'therehadtobean'assertion'byoneparty&'denial'bytheotherparty.
'Causeofarbitration'aroseintheinstantcasewhenevertherewasrejectionofa
claimbythe'Engineer' (ChiefEngineer Koyna Project) (RTD1/38) Rejection of
inactionbythe'Engineer'srepresentative'i.e.ExecutiveEngineer/Superintending
Engineerdidnot, however, result into'causeofarbitration'. Inwhich case the
claimanthadtoapproachthe'Engineer,furnishrequiredevidenceandonrejection
bythe'Engineer'couldinvokearbitration.
Asmita
QuestionnowbeforetheArbitralPanelwaswhethertheclaimshad
becometimebarredbecauseofthisapparentdelayonthepartoftheclaimantin
notinvokingthearbitrationearlyandpromptly. Theclaimantwassaidtohave
beensufferinglossbecauseofvariousreasonsinrespectofseveralitemsofthe
contract,whichresultedintoinitiatingtheclaimsrightfromthebeginningofthe
contract andcontinued toincur the loss for certainperiod since thenfor some
claims(No.3,4&5)andtillthecompletionofthecontractforsome(ClaimNo.1).
28/48
..29..
ARA6/07
C
ou
rt
LossonaccountofclaimNo.2wassaidtohaveoccurredonlyduringtheextension
period andcontinued till completion of the contract. The claimant could have
pursued theseclaims with therespondent for some reasonable timebut should
havegoneinforsettlementofdisputeasperCl.66eitherwhenitemsfor3claims
(3,4&5)weremostlycompletei.e.after3/98orwhenthecumulativelosseswere
foreseentobebeyondthecapacityoftheclaimanttopullonwithoutimpairingthe
progressofthecontractedwork,whichever wasearlier. IFtheclaimNo.1had
been referred to thearbitration (or even tothe earlier Arbitral panel) claimant
couldhavegotthecompensationintime.ForclaimNo.2,issuecouldhavebeen
pursuedvigorouslywiththerespondentsayduringayearorsoaftergettingthe
first extension and failing to get favourable response (or partial response), the
claimantcouldhaveinvokedthearbitration.
Itcouldnotbeascertainedfromtherecordorfromthedeliberations
duringthemeetingsastowhythislogicalandeasiercoursecouldnotbetakenby
theclaimant.Claimantscontention/argumentonthispointhadconsistentlybeen
that,withoutrejectionoftheclaimsbythe'Engineer',recoursetoarbitrationwas
notopentothem.Inalltheseclaimseventhoughtherewasspecificrecognisable
periodofstartofincurringoftheloss,thesamecontinuedsincethenduringthe
currencyofthecontract,includingtheextendedperiodatleastforclaimNos.1&
2.MajorityofthelossincurredforclaimNos.3,4&5wasknownwhentheitems
werenearlycompleteby3/98.ButforclaimNos.1&2thelosscontinuedtillthe
currencyofthecontract. Questionthenwas,whatshouldbeconsideredasthe
startofreckoningofthetimeoflimitation.ForclaimNos.3,4&5,firstreference
toEngineer'srepresentative(ExecutiveEngineer)wasmadeinFeb97&Oct96.
On getting no decision within 60 days, the claimant could have referred the
disputetohigherlevelandthentothe'Engineer'asperprovisionsofCl.66and
invokedthearbitrationwithinabout200to220daysatthemost.Thiscoursewas
nottakenbytheclaimantforthereasonsbestknowntohim.Theclaimantmight
taketheshelteroftheword'may'inthecontractormayappealwithin30daysto
Engineer'byclaimingthatitwasnotobligatoryforhimtoappealincasenoreply
wasgivenbytheExecutiveEngineer.
om
ba
y
ig
h
Asmita
Therehavebeencitationsstatingthatthecauseofactionandcauseof
arbitrationtobethesameforreckoningthestartoftimeoflimitation.Itwastrue
thatthe'causeofaction',ifitwasotherthanthe'causeofarbitration'couldnotbe
pinpointedasaspecificpointoftimeintheactivityoftheexecutionofthecontract
29/48
..30..
ARA6/07
C
ou
rt
(includingextensions).Losscontinued,negotiations/pursuationscontinued,work
continued but 'cause of arbitration' or invoking the arbitration' were the only
specificeventsinthisactivity.
HencetheArbitralPanelhadcometotheconclusionthat'causeof
arbitration' would be the 'cause of action' and time of limitation should be
reckonedfromthatdateforrespectiveclaims.Henceallthe5claimsinquestion
werenottimebarredonaccountoflimitations.
Onequestionthatrequiredtobeconsideredanddecidedwasthat,
shouldtheclaimantprefertodeferanddelaytheactionofinvokingthearbitration
apparentlyfornoreasonorforsomeotherreasonsbestknowntohim,everwhen
provisionofclauseforsettlementofdisputeexistedinthecontractandcontinued
tomaketherespondent sufferbecause ofanyextraliabilityonaccountofsuch
avoidabledelay.Arbitralpanelhascometoaconclusionthatclaimantshouldnot
beawardedinterestontheclaimsforpastperiodattherateswhichnormally&
reasonablyaclaimantwouldhavebeenentitledto.Itwasdecidedthatforclaim
Nos.1,3,4&5heshouldbegrantedonlypriceescalationasperTenderformulae
up to 3132000 (date of completion of the contract period) by treating that
paymentforamountoftheseclaimswasmadeonthatdate.From142000tothe
dateofreferencetoarbitrationforeachclaim,interestonlyat10%(tenpercent)
perannumshallonlybepaidontheescalatedamount.
28.
ba
y
ig
h
TheDistrictJudgehasdealtwithissueoflimitationinparagraphs35
to37ofitsJudgment. Thecontractorarguedthatlimitationoftheperiodof
om
threeyearshadtobereckonedfromthedateoffinalrejectionbythecompetent
authorityi.e.Engineerinthepresentcase.Itwassubmittedthatinrespectof
alltheclaims,arbitrationwasinvokedwithin30daysafterfinalrejectionbythe
EngineerasperClause66Aofthecontract. Itwassubmittedthatwhenthe
contract was spread over for a period and damage was sustained during the
wholeperiod, thelimitationfortotaldamageswouldcommencefromthedate
when the period of contract ends. It was submitted that the claim for
Asmita
30/48
..31..
ARA6/07
rt
compensationforsuccessivecontinuingbreachesofanycontract,theperiodof
C
ou
threeyearslimitationwouldbecomputedwhenthebreachceasedtooccur.It
wassubmittedthatdisputecouldstartonlyafterthedenialofanassertion.The
contractorsubmittedthatlimitationwouldnotstartfromthedateofentitlement
ofpaymentbutonwhichtheclaimwasmadebythecontractorandwasrejected
ig
h
by the Government and such rejection would be the accrual of the cause of
action. Itwassubmittedthattheclaimswerependingfordecisionforyears
together, thelimitationwouldstartonlyafterthedecisionwascommunicated.
DistrictJudgerenderedafindingthatthecontractorcouldeitherlodgeclaims
with the Government and pursue them for their settlement through the
ba
y
Governmentbynegotiationsorbyculminatingintoinvokingthearbitration.It
isheldthatthecontractorpreferredtotakeearlierrecoursetobeginwithand
continuetoquitesometime. The contractorapproachedSecretary,Irrigation
om
DepartmentandDy.ChiefMinisterduringthatperiodandrecoursetoarbitration
wastakenquitelateaftercompletionoftheworkphysically.TheDistrictJudge
heldthatArticle137oftheLimitationActwouldbeinvokedinthiscase.Relying
uponArticle137,itisheldthattheperiodoflimitationstartswhentherightto
apply accrues under Article137. The District Judge held that the period of
limitationforcommencinganarbitrationrunsfromthedateonwhichcauseof
arbitrationaccruesi.etosayfromthedatewhenthecontractoracquiredeither
Asmita
31/48
..32..
ARA6/07
rt
C
ou
ig
h
held that under Article 55 of the Limitation Act, when the breach was
continuing,thelimitationofthreeyearscommenceswhenitceases.TheDistrict
Judgefinallyheldthatthecauseofactionwouldcommencefrom25thMay2001
when the claim was finally rejected by the Chief Engineer. In my view,
Article55couldnotbeattractedinrespectoftheclaimsmadebythecontractor
ba
y
fortheworkdone.ThelearnedDistrictJudge,however,hasappliedArticle55of
theScheduletotheLimitationActtoalltheclaimswhichshowspatentillegality
om
onthefactoftheJudgmentofthelearnedDistrictJudge.
29.
ThearbitraltribunalhasrenderedafindingthatinrespectofClaim
Nos.3,4and5,theclaimcouldbesaidtohaveinitiatedwhentheconcerneditems
wereexecutedanditcontinuedtillcompletionofeachsuchitem. Thearbitral
tribunalalsorenderedafindingthatacontractorcouldhavepursuedClaimNo.2
with the Government for some reasonable time but shouldhave gone in for
settlementofdisputeasperClause66eitherwhenitemsfor3ClaimNos.3,4and
Asmita
32/48
..33..
ARA6/07
rt
5weremostlycompletei.eafterMarch1998orwhenthecumulativelosseswere
C
ou
foreseentobebeyondthecapacityofthecontractortopullonwithoutimpairing
theprogressofthecontractedwork,whicheverwasearlier.Similarlyinrespect
of Claim No.2, the arbitral tribunal held that issue could have been pursued
vigorouslywiththeGovernment duringtheyearorsoonaftergettingthefirst
ig
h
financialcrunch,heavystrainetc.,followup/pursuationsforsettlementofclaims
onthepartofcontractorwasverypoordespiteprovisionofclauseforarbitration.
ba
y
Thelearnedarbitraltribunalobservedthatitcouldnotbeascertainedfromthe
recordorfromthedeliberationsduringthemeetingsastowhythislogicaland
om
easiercoursecouldbetakenbythecontractor.
30.
Thearbitraltribunalthoughrenderedafindingagainstthecontractor
for gross delay in making a claim and pursuing it, rejected the plea of the
Government forrejectionoftheclaimsonthegroundoflimitation. Onone
hand,thearbitraltribunalobservedthattheGovernment shallnotsufferany
extraliabilityonaccountofavoidabledelayonthepartofthecontractorand
contractorshouldnotbeawardedinterestontheclaimsforpastperiodatthe
Asmita
33/48
..34..
ARA6/07
rt
rateswhichnormallyandreasonablyacontractorwouldhavebeenentitledto.
C
ou
Inmyview,itisclearthattheconclusiondrawnbythearbitraltribunalistotally
inconsistentwiththefinding renderedbythe arbitraltribunal ontheissue of
limitation. Theissueoflimitationhasbeendealtwithwithoutapplicationof
ig
h
mind.
31.
TheDistrictJudgehasrenderedafindinginfavourofthecontractor
onerroneouspremisethatArticle137oftheLimitationActwasapplicabletothe
ba
y
undertheprovisionsofcontract.ApplicationofArticle55totheclaimforwork
done by the District Judge, is totally an erroneous and is on the face of it
perverse.Article137oftheLimitationActappliestotheapplicationsandnotto
om
limitationprovidedbythescheduleforinstitutionofasuitwillapply.ThisCourt
hasheldthatthereisnoquestionofprovisionsofArticle137applyinginsofaras
invocation of the arbitration clause and commencement of the period of
limitationisconcerned.ThisCourtheldthatinrespectoftheclaimforpriceof
extraworkcarriedoutbythecontractor,Article18oftheLimitationActwould
Asmita
34/48
..35..
ARA6/07
rt
applyandnotArticle137.Itisheldthatwhenasuitisinstitutedforrecoveryof
C
ou
thepriceoftheworkdonebytheplaintiffforthedefendant,andwhenthereis
notimefixedforpaymenttobemade,thecauseofactionforinstitutingthesuit
ariseswhentheworkiscompletedandthesuithasbeinstitutedwithinaperiod
ofthreeyearsfromtheaccrualofcauseofaction.Itisheldthatcauseofaction
ig
h
wouldaccruewhentheworkisdone.AfterconsideringArticle113onwhichthe
contractorhasplacedreliance,thisCourtheldthatthesaidArticlecomesinto
playonlyonfindingthatforinstitutionofasuitfortheclaimwhichwasinvolved
ba
y
Article113couldnotapply.ThisCourtheldthatthoughthelearnedarbitrator
hadrecordedafindingthattheclaimwasnotbarredbylawoflimitation,inthe
entire award there was no reference to any Articles in the Schedule of the
om
LimitationAct,whichappliestothatcase.ThisCourtobservedthatsuchfinding
recordedbythelearnedarbitratorwasanimpossibility.
32.
Inmyview,refusaltopaytheamountdemandedbythepetitioner,
wouldnotcommencefreshperiodoflimitationwhichhadalreadycommenced.
InviewofSection9oftheLimitationAct,1963,oncetimeisbeguntorun,no
subsequentdisabilityorinabilitytoinstituteasuitormakeanapplicationstops
Asmita
35/48
..36..
ARA6/07
rt
it.Oncetimestarts,itdoesnotstop.Limitationisextendedonlywhenthereis
C
ou
33.
Itisnotthecaseofthecontractorthattherewasanypartpayment
ig
h
madebytheGovernmentinrespectoftheclaimsinquestionortherewasany
acknowledgmentofliabilitymadebytheGovernmentinfavourofthecontractor
inrespectofsuchclaims.Merelybecause,therewasinactionand/ordelayonthe
partoftheofficersoftheGovernmentinconsideringand/orrejectingtheclaims
madebythecontractor, limitationwouldnotbeextended.Thelimitationhad
ba
y
alreadycommencedwhentheworkwasdoneandthepaymentwasnotmade.It
isnotindisputethattheworkinrespectoftheclaimsinquestionwascompleted
morethanthreeyearspriortothedateofcontractormakingrepresentationtothe
om
concernedofficersoftheGovernment. Inmyview,eveniftheofficersofthe
Governmenthadnotdecidedtherepresentationand/orclaimofthecontractor
withinthetimespecifiedunderClause66,causeofactionhadnotstopped.
34.
mixeduptheissueoflimitationinmakingaclaimandinmakinganapplication
totheCourtforappointmentofarbitrator. ThereferencemadebytheDistrict
Asmita
36/48
..37..
ARA6/07
rt
JudgetoArticle137andArticle55istotallymisplacedandcontrarytolaw.In
C
ou
myview,limitationformakingaclaimandlimitationformakinganapplication
forappointmentofarbitratorcannotbemixedup.
35.
Perusal of the award indicates that Claim No.1 was for revision of
ig
h
ratesdemandedbythecontractoronthebasisthatcertainitemsofworkwhich
were different from those included in BOQ (Bill of Quantities) items were
requiredtobeexecuted.Itwasthecaseofthecontractorthatthereweresome
extra items where rates of item could not be derived from the BOQ rates by
makingappropriatevariations. UnderClause51ofthecontract,theEngineer
ba
y
hadpowerstomakeanyvariationoftheform,qualityorquantityoftheworksor
anypartthereof.Procedureofvaluationofvariationhadbeenspecifiedunder
Clause52 of the contract. Accordingly, the Government had prepared rate
om
analysiswith'labourmarkup'as50%andoverheadandprofitas20%. The
contractor,howeverdemandedthesameas195%and40%respectively. The
learnedlearnedarbitraltribunal,intheimpugnedawardallowedthisclaim. It
wasthepleaoftheGovernmentthatdisputeregardingratesofextra/deviated
itemsstartedwhenthefirstpaymentwasmadepriorto27thJuly1997;whereas
the contractor had invoked arbitration clause on 27th July 2000. It is not in
disputethatthesaidworkwascarriedoutasorderedbytheGovernmentunder
Asmita
37/48
..38..
ARA6/07
rt
Clause51 read with Clause52 of the contract. The said work was thus,
C
ou
contractualworkasorderedbytheGovernment.Thelimitationformakingsuch
claimforratesofsuchextra/deviateditemswillthusarisewhensuchitemofwrk
wasdonebythecontractor,whichinthiscase,muchpriorto27thJuly1997.In
myview,Article18ofScheduletoLimitationActwouldapplytothisclaimand
ig
h
thepleaoflimitationintheimpugnedaward.
36.
InsofarasClaimNo.2isconcerned,perusaloftheawardindicates
ba
y
that the said claim was for compensation for the work carried out by the
contractor beyond the original stipulated date of completion which was 19th
March1997.TheGovernmentgrantedfiveextensionsfortheperiodbetween
om
20thMarch1997makingthesametermsandconditionsapplicableforthework
carriedoutduringtheextendedperiod. Thecontractorthus,oughttohave
38/48
..39..
ARA6/07
rt
contractandextensionwasnecessitatedduetosuchreasonsandthecontractor
C
ou
wasnotboundtocarryoutthebalanceworkonthesametermsandconditions,
cause of action would begin as soon as such breach was committed by the
Government according to the contractor. The learned arbitral tribunal,
however,didnotdecidethisissueintheimpugnedawardbutrejectedthepleaof
ig
h
limitationmerelyonthegroundthattheclaimwasinitiatedon18thMarch1997
i.e the date on which the Government granted extension under the same
conditions of contract and its effect will start from 20 th March 1997 and it
continuedtillactualcompletionofthecontract. Thelearnedarbitraltribunal
consideredthattheEngineerhadrejectedtheclaimon6thSeptember2000and
ba
y
thearbitrationwasinvokedon21stSeptember2000,thustheclaimwasintime.
NoArticleofLimitationActhasbeenreferredbythelearnedarbitraltribunal
while dealing with plea of limitation even in respect of this claim for
om
compensation.
37.
AsfarasClaimNo.3madebythecontractorisconcerned,perusalof
theawardindicatesthatthesaidclaimwasmadeforrevisionofratesforPressure
Shaft Excavation. According to contractor, it encountered various difficulties
duringtheexcavationsofthePressureShaftssuchaschangedsequenceofthe
work,methodandtiming,physicalobstructionsintheworkduetoworkofother
Asmita
39/48
..40..
ARA6/07
rt
C
ou
attributabletothecontractor.Accordingtocontractor,inviewofsuchsituation,
theychangedthescopeofitemandthecontractorpreparedrateanalysisforeach
component of the work based on componentwise expenditure. The learned
ig
h
arbitraltribunalallowedthisclaim.
38.
Perusaloftheawardindicatesthatthisitemwascarriedoutduring
theperiodbetweenJuly1993toMarch1998totheextentof94%.Thedemand
wasmadebeforetheExecutiveEngineeron10thFebruary1997.Itwasrejected
byExecutiveEngineeron17thJuly2000.Inmyview,thecontractoroughtto
ba
y
havemadethisclaimwhenanysuchbreachwascommittedbytheGovernment
resulting in suffering of compensation due to breaches attributable to the
Government.Thecontractorwasnotboundtowaitbeyond60daysfordecision
om
oftheExecutiveEngineer.Inthiscase,itisclearthatthecontractorwaitedfor
decision of Executive Engineer for more than three years and four months.
Limitationoncecommenced,doesnotstop.Thelearnedarbitraltribunalhasnot
referredtoanyArticleofLimitationActwhiledealingwiththistypeofclaim.In
my view, the claim in view of the alleged breaches committed by the
Government,oughttohavemadewithinthreeyearsfromthedateofalleged
breach and claim not having made within three years, was barred by law of
Asmita
40/48
..41..
ARA6/07
C
ou
rt
limitation.
39.
InsofarasClaimNo.4isconcerned,perusalofawardindicatesthat
thesaidclaimwasmadeforfixationoftherateonaccountofvariationinthe
itemofTransformerHallArchConcreteduetotheproblemssuchaschangesin
ig
h
natureofrock,doingadditionalworknotprovidedinthecontract,changesin
sequenceandmethodology,delayinissueofdrawings,increaseinquantitiesetc.,
resultingincontractortoincurextraexpenditurenotcontemplatedintherate
analysis.Thecontractormadethatclaimbywayofcompensationtowardsextra
expensesallegedtohavebeenincurredbyit. Thelearnedarbitraltribunal
ba
y
allowedthisclaim.Thedataplacedonrecordintheawardindicatesthatthis
work was carried out during the period between October 1993 and February
1994. The contractor made a demandbefore the Executive Engineer on 14th
om
October1996.TheExecutiveEngineerrejectedthisclaimon4thNovember2000.
Arbitrationwasinvokedon1stJune2001.Inmyview,thecontractoroughtto
havemadethisclaimwhensuchworkwasdoneandnopaymentwasmadeto
thecontractorforthesame.Thecontractorwasnotboundtowaitfordecision
ofExecutiveEngineerbeyondtheperiodof60dayswhereas,inthis case,he
waited for decision of the Executive Engineer for a period of more than four
years.Inmyview,thisclaimwasonthefaceofitisbarredbylawoflimitation.
Asmita
41/48
..42..
ARA6/07
rt
Thelearnedarbitraltribunalhasnotconsideredthesefactsinproperdirection.
C
ou
40.
InsofarasClaimNo.5isconcerned,thesaidclaimwasmadebythe
ig
h
horizontalnicheshaddelayedtheworkandcausedextraexpensesduetoother
reasons,suchasstoppageofworkofshotcrete,increaseinquantityofrockbolts,
frequentrevisionofdrawings,additionalworks,reductionandomissionofsome
worksetc.necessitatedappropriatedcompensationinfavourofcontractor.The
learned arbitral tribunal allowed this claim for compensation. The award
ba
y
indicatesthatthisworkwasexecutedduringtheperiodbetweenJanuary1993
and September 1995. The contractor made this claim before the Executive
Engineeron14thOctober,1996whichwasrejectedbytheExecutiveEngineeron
om
19thSeptember,2000.Arbitrationclausewasinvokedon6thJune2001.Inmy
view, when the work was carried out and payment was not made by the
Government,causeofactionhadcommenced.Inanyevent,thecontractorwas
notrequiredtowaitforthedecisionoftheExecutiveEngineerformorethan60
dayswhereas for this claim,thecontractorwaitedfordecision for aboutfour
years.Inmyview,theclaimonthefaceofit,isbarredbylawoflimitation.
Asmita
42/48
..43..
rt
41.
ARA6/07
C
ou
Dunkerly(supra)relieduponbythecontractorisconcerned,inmyview,itwas
notthepleaofthecontractorbeforethearbitraltribunalorbeforetheDistrict
JudgethatArticle113oftheLimitationAct(correspondingtoArticle120ofthe
LimitationAct1908)wouldapplytothefactofthiscase.Inmyview,asnosuch
ig
h
pleawasnotraisedbeforethearbitraltribunalplacingrelianceuponArticle113
corresponding to Article120 of Limitation Act 1908, and since no finding is
rendered by the arbitral tribunal applying Article113, contractor cannot be
permittedtoraisesuchpleaforthefirsttimeinthepresentproceedingsunder
Section37oftheActof1996.Pleaoflimitationisamixedquestionoffactand
ba
y
lawandunlesssuchspecificpleabyplacingrelianceuponArticle113wasfirst
raisedbeforethearbitraltribunal,itcannotbeallowedtoberaisedforthefirst
timeinappealunderSection37oftheActof1996.Iam,therefore,oftheview
om
thatrelianceplacedbythelearnedseniorcounselappearingforthecontractorin
caseof GannonDunkerley (supra)isofnoassistancetothecontractorinthe
factsofthiscase.
42.
Inanyevent,consideringthenatureofclaimsmadebythecontractor
i.e.ClaimNos.1to5whichwereallowedbythelearnedarbitraltribunal,itis
clearthattheclaimswereeitherforworkdoneorforcompensationandthus
Asmita
43/48
..44..
ARA6/07
rt
specificArticleforreferringthedisputetoarbitrationwouldbeattractedsuchas
C
ou
ig
h
thecontractor,withgreatrespect,isofnoassistancetothecontractor.
43.
appearingforthecontractoristhatevenifArticle18isapplicabletotheclaims
made bythe contractor,periodof limitation wouldcommence onlywhen the
ba
y
entireworkisdone.Thelearnedseniorcounselsubmitsthattheclaimsmadeby
thecontractorwerenotfortheentireworkdonebythecontractorbutwasonly
inrespectofsomeitemsfromthescopeofentireworkawardedtothecontractor.
om
Thelearnedseniorcounselsubmitsthatonlywhentheentireworkiscompleted,
causeofactionwouldariseformakingclaimsevenforitemsfortheworkdone.
44.
Asmita
..45..
ARA6/07
rt
theotherhandonthisissueinrejoindersubmitsthatthecontractorhadmade
C
ou
claimsinrespectofeachitemsseparatelyanddidnotmakeclaimfortheentire
work. It is submitted that even in the earlier arbitration proceedings, the
contractorhadmadeclaimshavingariseninrespectoftheitemsofthework
done and did not wait till completion of work. The Government had made
ig
h
paymentitemwisetothecontractorandthusitcannotbeconstruedthatcause
ofactionwouldariseonlyafterentireworkwasdoneandnotwhenitemsof
workwasdoneinrespectofwhichthedisputehadalreadyarisen.Clause66(A)
andClause66(b)oftheGeneralConditionsofContractreadasunder:
66A)SETTLEMENTOFDISPUTESARBITRATION:
(A)
IftheContractorconsidersanyworkdemandedofhimtobeoutside
therequirementsofthecontractorconsidersanydrawings,recordorrulingofthe
Engineer'sRepresentativeonanymatterinconnectionwithorarisingoutofthe
Contractorthecarryingoutofworktobeunacceptable,heshouldpromptlyask
the Engineer's representative in writing, for written instructions or decision.
Thereupon the Engineer's Representative shall give his written instructions of
decisionwithinaperiodof60daysofsuchrequest.
om
ba
y
Uponreceiptofthewritteninstructionsordecisions,thecontractorshallpromptly
proceedwithoutdelaytocomplywithsuchinstructionsordecision.
IftheEngineer'sRepresentativefailstogivehisinstructionsordecisioninwriting
withinaperiodof60daysofbeingrequestedoriftheContractorisdissatisfied
withtheinstructionsordecisionoftheEngineer'sRepresentativetheContractor
maywithin30daysafterreceivingtheinstructionsordecisionappealupwardsto
EngineerwhoshallaffordanopportunitytotheContractortobeheardandto
offerevidenceinsupportofhisappeal.TheEngineershallgiveadecisionwithin
aperiodof60daysaftertheContractorhasgiventhesaidevidenceandfurther
documentaryprooftheEngineercallsforinsupportofContractor'sappeal.
IftheContractorisdissatisfiedwiththisdecision,theContractorwithinaperiodof
30daysfromreceiptofthedecisionshallindicatehisintentiontoreferthedispute
toArbitration,aspertheproceduresetoutinClause66(b)below,failingwhich
Asmita
45/48
..46..
ARA6/07
rt
thesaiddecisionshallbefinalandconclusive.
66(b):ARBITRATION:
Intheeventofanydisputeordifferencearisingoutoforinanywayrelatingtoor
concerning these presents or the construction or effect of these presents (the
settlementwhereofhasnotbeenhereinbeforeexpresslyprovidedfor),thesamein
respectofwhichthedecisionisnotfinalandconclusive,shallontheinitiativeof
eitherpartytothecontractbereferredtothreearbitrators,onetobeappointedby
the employer, the second by the contractor and third by the Chairman Central
Water Commission in the case of Indian Contractors. In the case of Foreign
Contractor,thethirdarbitratorwillbedecidedbythetwoarbitratorswithin60
daysoftheirappointment. ThetermIndianContractorshallincludeanIndian
firm or a group of firms or a joint venture eligible for price preference as a
domestictenderer.ThetermForeignContractorshallincludeaforeignfirmora
group of firms and joint venture consortia not eligible for price preference as
domestic tenderer. The Arbitration shall be conducted in accordance with the
provisions of the Indian Arbitration Act 1940 or any statutory modifications
thereof. The arbitration shall be held at such place and time in India as the
arbitrators maydetermine. Ifeither of the parties fail toappoint its arbitrator
withinsixtydaysafterreceiptofnoticefortheappointmentofanarbitratorfrom
theotherpartythentheChairman,CentralWater Commissionshallappoint an
arbitratoronreceiptoftherequestfromtheaggrievedparty. Acertifiedcopyof
theappointmentsmadebytheChairmanCWCshallbefurnishedtobothparties.
ba
y
ig
h
C
ou
om
Thedecisionofthemajorityofthearbitratorsshallbefinalandbindinguponboth
theparties.Theexpenseofthearbitratorsshallbepaidasmaybedeterminedby
thearbitrators.
Performanceunderthecontract,shallifreasonablybepossible,continueduring
thearbitrationproceedingsandpaymentsduetotheContractorbytheEngineer's
representative shall not be withheld, unless they are the subject matter of the
arbitrationproceedings.
All awards shall be in writing and in case of claims equivalent to Rupees one
hundred thousand or more, such awards shall state reasons for the amounts
awarded.
NeitherpartyisentitledtobringaclaimtoarbitrationifitsArbitratorhasnotbeen
appointedbythirtydaysaftertheexpirationofthedefectsliabilityperiod.
45.
Asmita
Perusalofthearbitrationclauseindicatesthatincaseofanydispute,
46/48
..47..
ARA6/07
rt
thecontractorwasrequiredtopromptlyasktherepresentativeoftheGovernment
C
ou
inwriting,forwritteninstructionsordecision.Fromtheperusaloftheclauses,it
is clear that it contemplates dispute tobe referred even during the course of
executionofworkandthecontractorwasnotrequiredtowaittillcompletionof
the work. Perusal of the arbitration clause indicates that the contractor was
ig
h
permittedtoreferthedisputestoarbitrationarisingduringtheexecutionofthe
workandsimultaneouslytocontinuetoperformunderthecontractifreasonably
possible. ThisClauseindicatesthatthecontractorwasnotboundtowaitfor
completionfortheentirework,butcouldhaveinvokedarbitrationpromptlyas
soonasdisputehadariseneveninrespectofitemsofworkoutofentirescopeof
ba
y
work were executed. It is not in dispute that even in respect of the earlier
arbitration arising under the same contract, the contractor had already made
claimsinrespectofsomeoftheitemsofwork.Iamthus,notinclinedtoaccept
om
thesubmissionmadebythelearnedseniorcounselappearingforthecontractor
thatthecauseofactionwouldariseonlywhentheentireworkwascompletedby
thecontractorandnotwhenthepaymentwasnotmadeinrespectoftheitemsof
workdoneoncompletionofthatitem.Inmyview,causeofactionhadarisen
whentheworkwasdoneinrespectoftheitemsofworkdoneandcauseofaction
wouldnotpostponetillthedateofcompletionofentirescopeofworkawardedto
thecontractor.Inmyview,thelearnedarbitraltribunaloughttohavereferredto
Asmita
47/48
..48..
ARA6/07
rt
therelevantArticlewhichwouldbeattractedforthepurposesofdecidingthe
C
ou
issueoflimitation,whichisabsentintheimpugnedaward.ThelearnedDistrict
JudgehasmisdirectedbyapplyingwrongArticletothefactsofthiscase.
46.
Theawardisvitiatedandisinconflictwithpublicpolicyontheissue
ig
h
oflimitation. ViewtakenbythelearnedDistrictJudgeisalsocontrarytolaw
anddeservestobesetaside.I,therefore,passthefollowingorder.
i)
Impugnedorderandjudgmentdated29th June2006passedbythe
learnedDistrictJudge,RatnagiriinArbitrationApplicationNo.44of
2003andtheimpugnedawarddated26th June2003passedbythe
ba
y
learnedarbitraltribunalaresetasideonthegroundoflimitation.
ii) ArbitrationApplicationNo.44of2003filedbytheGovernment is
allowed.
om
iii)Appealisdisposedofinaforesaidterms.Thereshallbenoorderasto
costs.
iv) Respondentisdirectedtorefundtheamountwithdrawnintheabove
matterwithinterest@12% perannumfromthedateof withdrawal till
paymentwithineightweeksofthisorder.
(R.D.DHANUKA,J.)
Asmita
48/48