1. BACKGROUND:
There is a proposal to construct a two lane bridge over BILKAWALI KHAD BRIDGE AT
2. OBJECTIVES:
iii)
zone, special attention shall be paid to the performance of bridges under stringent seismic
conditions.
3.1
The consultant shall :
(i)
To collect information about the existing bridge characteristics on this stream and
to submit typical GAD of the same.
(ii)
Prepare the GAD of the proposed bridges showing the type of structure
(preferably integral bridge), span arrangement etc. in consultation with the state
PWD.
(iii)
He shall get the GAD approved from the State PWD with supporting hydraulic
and preliminary bore data including scour calculations.
(iv)
Carry out sub-surface investigations for the proposed bridges as per IRC
guidelines and Ministrys specifications including the guidelines given in the
pocket book for Bridge Engineer.
(v)
Carry out detailed topographical survey of the area (minimum 500 m or either
side of the bridge) using total station.
(vi)
Collection of hydraulic data and fixing hydraulic design parameters e.g.
catchment characteristics, rainfall data, design discharge, scour depth etc.
(vii) Preparation of detail design and drawings of the various components bridges
including a minimum of 500m approaches on both sides for all the bridges,
protection work (if required). Prepare Horizontal and Vertical alignment plan and
cross sections for approach road as per IRC: SP: 19-2001 and other codes,
guidelines and specifications.
(viii) Establish horizontal control points on the ground for the final centerline of the
approaches through reference pillars fixed in concrete and vertical controls
through a series of Bench marks all along the length of approach road.
Investigations should be as per recommendation contained in IRC:SP: 19-2001
guidelines and specifications.
(ix)
Carry out drainage studies indicating general drainage pattern HFL water level,
seepage flow etc. and prepare drainage plan as per IRC guidelines including
location and design of culverts.
(x)
Identification of utility services, prepare shifting plan with cost and tree cutting
details, if required.
(xi)
Preparation of BOQ and cost estimate for the project based on analysis of rates as
per Ministrys Standard Data Book.
(xii) Preparation of tendering documents as per guidelines of Ministry.
(xiii) Liaison with client, Ministry of Road Transport & Highways and the Proof
Consultant which shall be appointed by client for the approval of reports and
design, drawing etc.
(xiv) Detailed drawings shall be prepared to international standards, using CAD. It will
contain all the details required for the execution of the project.
3.2
3.3
It shall be the responsibility of the consultants to get the bridge design approved
from the competent authority after making all necessary modifications. The
consultants shall opt for modern structure type and design methods.
Analysis of the structure can be done by latest acceptable computer aided methods
wherever relevant. Design of section shall be done in MS EXCEL suited to easy
appreciation. Design of various components shall be in conformity with various
TOR
latest IRC codes/ Ministrys guidelines & circulars. The input data, design
parameters, assumptions made and final analysis results for each component of
the structure should be spelt out clearly and proper reference, wherever required,
of various IRC codes etc. shall be indicated for better appreciation of detailed
designs.
3.4
3.5
Reports shall be made on MS WORD and soft copes in CDs shall be submitted
also in addition to printed text.
4.
The project preparation is divided into two stages. Consultant shall be required to
complete, to the satisfaction of the client, stages within the time frame indicate in the
schedule of submission. The stage are:
Stage I:
i)
Study and finalize alternative alignment options to suit the type of structure
proposed and arrange approval of the same form state PWD/ MoRT&H, New
Delhi.
ii)
The design of various components including GAD shall be submitted by the
consultant.
Stage II:
Detailed Project Report (DPR)
VOLUME I
Executive Summary
Project Description
Bridge features
Construction Programme
VOLUME II
Design Calculations
VOLUME-III
Detailed Drawing
VOLUME-IV
Project Cost Estimate & BOQ
VOLUME-V
Contract Document
5.
The client shall provide following data/ information free of cost to the appointed
consultant:
(i)
Quarry chart showing location of quarries/ gravel sources along the road.
TOR
(ii)
6.
Suitable and adequate personnel shall be deployed by the consultant for the work
However, the following man month have been indicated for reference.
Key Personnel
Man Month
Bridge Engineer
Highway Engineer
Hydrologist Cum-Drainage Engineer
Material Engineer-Cum-Geo Technical Engineer
Estimate Surveyor
7.
3
1
1
1
2
The consultant shall furnish to the client the following reports and documents for each
bridge separately. All reports and documents shall be in English.
(a)
(b)
(c)
(d)
(e)
Inception report
PPR
Draft DPR & Land Acquisition data & Plan
Final DPR
Contract Document
8.
SCHEDULE OF SERVICES:
(a)
(b)
(c)
(d)
(e)
9.
PAYMENT SCHEDULE:
i)
ii)
iii)
iv)
v)
vi)
vii)
Inception report
Submission of PPR
Approval of PPR
Submission of draft DPR & LA Plan
Approval of draft DPR
Submission of final DPR
Acceptance of contract document & final
DPR
6 Copies
6 Copies
- 6 hard copies + 2 soft copies
- 6 hard copies + 2 soft copies
- 6 hard copies + 2 soft copies
TOR
PERFORMANCE SECURITY:
Within 21 days of the letter of acceptance, the consultant shall deliver to the
employer a performance security in the form of bank guarantee for an amount equivalent to 5
per cent of the contract price. The bank guarantee will be released at the time of final
payment to the consultant.
11.
The consultants shall be responsible for accuracy of all the data used in project
preparation and estimates prepared by him as part of the project. He shall indemnify the
client against any inaccuracies in the work. For this purpose, he shall furnish bank guarantee
for an amount to the extent for 20 percent of the total consultancy fees to be received by him.
The bank guarantee shall be valid for a period of 2 years from the date of submission of the
final DPR. The final installment of 25 percent of the fees shall be released only on receipt of
this bank guarantee.
TOR
ANNEXURE-I
MINIMUM QUALIFICATION OF KEY PERSONNEL
BRIDGE ENGINEER CUM TEAM LEADER:
The position requires as engineer, preferably with Masters Degree or equivalent in
structural/ bridge engineering, with minimum 15 years experience. The candidate must have
capacity to design bridges with various alternative materials and structural arrangements. He
should have designed independently at least two major bridges (200 m length) of similar
nature. Experience in designing and implementing bridge rehabilitation required. The
candidate must have the experience of planning and monitoring geo-technical and hydraulic
investigations for the bridges and interpreting the findings thereof. He will also act as a
Coordinator.
HIGHWAY ENGINEER
The Engineer will be a graduate in Civil Engineering with at least 15 years of
professional highway engineering experience of handling project preparation and
construction of highway project (preferably National Highway Project) in India or similar
developing countries including project preparation/ construction of major highway/ bridge
projects.
HYDROLOGIST CUM DRAINAGE ENGINEER
The position requires an Engineer who should be a graduate in civil engineering or
science with at least 15 years professional engineering experience including 5 years in
supervising sub-soil investigation for roads and bridges and testing evaluation of highway
construction materials used in modern highway construction techniques. They must be
thoroughly familiar with all the standard laboratory testing procedures adopted in case of
highway projects. Better qualification and experience on above lines will be considered for
higher rating in evaluation.
MATERIAL ENGINEER CUM GEO TECHNICAL ENGINEER
This position requires an Engineer who should be a graduate in Civil Engineering or
science with at least 15 years professional engineering experience including 5 years in
supervising sub-soil investigations for roads and bridges and testing evaluation of highway
construction materials used in modern highway construction techniques. They must be
thoroughly familiar with all the standard laboratory testing procedures adopted in case of
highway projects. Better qualification and experience on above items will be considered for
higher rating in evaluation.
ESTIMATE SURVEYOR
He should be graduate in Civil Engineering/ Diploma in Quantity Surveying from a
recognized University/ Institution. Graduate in Civil Engineering with at least 15 years work
experience or Diploma in Civil Engineering with at least 20 years work experience at
responsible position will also be acceptable. He should have expertise in quantity surveying,
BOQ preparation, tender documentation etc. He should be conversant with the use of
computer software for commuting unit rates, quantities and costs.
TOR
ANNEXURE-II
LETTER OF INVITATION TO CONSULTANT
Subject :TOR FOR ENGAGEMENT OF CONSULTANT FOR PROPOSED
FEASIBILTY
STUDY AND
CONSULTANCY
SERVICES
FOR
THE
CONSTRUCITON OF A BRIDGE OVER BILKAWALI KHAD BRIDGE AT KM.
173/796, JAWALAMUKHI NALLAH BRIDGE AT KM. 184/435, NAKER NALLAH
BRIDGE AT KM. 193/795 & CHEER NALLAH BRIDGE AT KM. 194/817 ON NH-88
UNDER NH DIVISION, HAMIRPUR IN THE STATE OF HIMACHAL PRADESH.
To
_____________________________,
_____________________________,
_____________________________.
Sir,
1.
You are hereby invited to submit technical and financial proposal in separate sealed
envelopes for the above cited work for evaluation.
2.
(i)
To examine the various alternative alignments and to suggest the most suitable one that is
technically feasible and economically viable.
(ii) To suggest innovative and aesthetic structure considering the site requirements.
(iii)
(iv)
Design of various components of bridge as per latest IRC/ BIS/ MORTH Standards/
Guidelines & Specifications. In order to enhance the performance of the bridge under
severe seismic conditions, it shall preferably be integral bridges (Piers monolithic with
superstructure) with no bearings and least number of expansion joints.
(v)
(vi)
3.
Item
Firms experience about the type of assignment
Adequacy of proposed work plan
Qualification and related experience of key personnel
assigned to the project
Equipment/ instrument proposed for use
Computer facility
Total
Marks
15
25
50
5
5
100
It is for the Evaluation Committee to suitable subdivide the marks for the above items for
individual attributes.
A score of 70 marks or more for the technical proposal will be deemed as satisfactory and
the financial bids will be opened only for such proposals. The work shall be awarded to the
lowest financial bidder provided his offer is found to be reasonable.
7.
Financial proposals to be submitted in separate sealed envelope should provide detailed
price breakdown which should take into account the various budget item related to the works.
For example:
(i) Key Personnel
(ii) Other Personnel
(iii) Postage, stationery and
consumables
(iv) Computer time charges
(v) Head office expenses
(vi) Overheads
Man Months
Man Months
other
`
`
`
`
`
`
It is broadly assessed that about 05 man months of technical personnel would be required
for successful completion of the proposed consultancy assignment. However you should fee free
TOR
to submit your financial proposals on the basis of man months and other budget item which you
consider more appropriate for successful completion of the assignment.
(a)
The period of validity of your proposal will be reckoned as 120 days from the stipulated
last date for receipt of proposals that is during which you will maintain without change the
personnel proposal for the assignment and the quoted price. The department will make its best
efforts to select consulting firm within the period.
(b)
Please note that the cost of preparing the proposal and of negotiating the contract
including field visit etc. is not reimbursable as direct cost of assignment.
(c)
Assuring the contract can be satisfactory concluded, you will be expected to commence
the assignment within 07 days from the date of award. The consultancy work should be
completed within three months and the inception report and detailed project report has to be
cleared duly approved by the MORT&H.
(d)
You may please not that invitation to submit proposals have also been sent to other firms.
8.
You may send your proposals individually or jointly with other firms. In case of joint
submission, a letter executed by both parties agreeing to work jointly for the assignment should
be enclosed with your personnel. Please note that in case an individual expert of a firm is shown
associated with more than one firm submitting the proposals, all such firms may be liable for
disqualification.
9.
Your proposal in five copies (Original and four copies) should be delivered to
Er.______________________at the address of Executive Engineer, National Highway Division,
HPPWD, Hamirpur on or before __________________ up to 3:00 P.M. Proposals delivered after
that date will not be considered. The technical proposal shall be opened on the same day at 3:30
P.M. in the presence of the representative of the firms who so ever may like to be present.
10.
Please note that the remuneration you will receive for this contract will be subject to the
normal tax liability.
Please note that National Highway Division, HPPWD, Hamirpur is not bound to select
any of the firms submitting the proposals.
11.
(i)
Whether or not you will be submitting a proposal, and.
(ii)
When you are submitting the proposal, the date and the mode of delivery of the
submission.
Yours Faithfully,
Executive Engineer,
National Highway Division
HPPWD, Hamirpur.
TOR
NAME:
2.
Date of Birth:
3.
4.
Qualification:
5.
6.
7.
Certified that I am available for the above work for this firm throughout the
consultancy period.
Signature:
Name:
Place:
Date:
TOR
HIMACHAL PRADESH
PUBLIC WORKS DEPARTMENT
NO.PW-NHD-HMR-DB-TOR 3 Nos Bridge of NH-88/2014DATED: To
The Superintending Engineer,
National Highway Circle,
HP.PWD., Shahpur (HP).
Subject: -
TOR