Beruflich Dokumente
Kultur Dokumente
IZGRADNJA POSTROJENJA I
PROIZVODNJA ELEKTRINE/TOPLOTNE
ENERGIJE IZ BIOMASE U REPUBLICI SRBIJI VODI ZA INVESTITORE
Dr Branislava Lepoti Kovaevi, dipl.prav.
Dr Dragoslava Stojiljkovi, dipl.ma.in.
Bojan Lazarevi, dipl.el.in.
1 INTRODUCTION ...................................................................................................... 1
1.1 Definition of Biomass/Biogas Fuelled Power Plants .................................................... 2
1.2 Sources of Law ................................................................................................................ 3
2 BIOMASS/BIOGAS POWER PLANTS ..................................................................... 6
2.1 Types of Power Plants .................................................................................................... 6
2.2 Basic Data on Biomass/Biogas....................................................................................... 7
3 POWER PLANT CONSTRUCTION .......................................................................... 8
3.1 Sources of Law ................................................................................................................ 8
3.2 Procedure for Construction of a Power Plant ................................................................ 9
3.2.1 Selection of the Location, Perusal of Valid Planning Documents, and Information
on Location .............................................................................................................. 10
3.2.2 Energy Permit .................................................................................................. 11
3.2.3 Requirements for Connection ........................................................................... 15
3.2.4 Location permit ............................................................................................... 16
3.2.4.1 Procedure for Issuing the Location Permit ................................................. 16
3.2.4.2 Forming the Building Plot ......................................................................... 18
3.2.4.3 Water requirements, water approval, and water permit ............................... 19
3.2.5 Environmental Impact Assessment ................................................................... 23
3.2.6 Technical Documentation ................................................................................ 28
3.2.7 Construction permit ......................................................................................... 33
3.2.8 Construction of a Structure and Technical Inspection of the Structure .............. 34
3.2.9 Operating Permit ............................................................................................. 36
4 ACQUIRING THE RIGHT TO ENGAGE IN THE ACTIVITY OF ELECTRICITY
GENERATION ........................................................................................................... 37
4.1 Investing in a Public Company Generating Electricity .............................................. 38
4.2 Entrusting the Pursuit of Activities of Public Interest ................................................ 39
5 CONCESSIONS ....................................................................................................... 41
5.1 Concession Granting Procedure ................................................................................... 42
5.2 Concession Agreement ................................................................................................. 44
5.3 Obligation to Establish a Concessionary Enterprise ................................................... 45
5.4 Reassignment of Concession ........................................................................................ 46
6 ENERGY LICENCE................................................................................................. 46
7 CONNECTING THE POWER PLANT TO THE GRID............................................ 47
7.1 Connecting the Power Plant to the Electricity Grid .................................................... 47
7.2 Connecting the Power Plant to the District Heating Network .................................... 50
8 OBTAINING THE STATUS OF A PRIVILEGED POWER PRODUCER AND
PERTAINING INCENTIVES...................................................................................... 51
8.1 Obtaining the Status of a Privileged Power Producer ................................................. 51
8.2 Incentives for Power Producers in Biomass/Biogas Power Plants ............................ 54
9 CONCLUSION ........................................................................................................ 56
distinction between the power plants using biomass5 and those using waste6. From
the environmental regulations point of view7, certain types of biomass can be
classified as waste. Therefore, the environmental regulations (the Law on Waste
Management8 and the pertaining by-laws9) call for obtaining the necessary
permits10 from the Ministry of Environment and Spatial Planning for specified
types of biomass while, for other types, this is not a requirement. .
1.1 Definition of Biomass/Biogas Fuelled Power Plants
The power plants fuelled with renewable energy sources that use
biomass/biogas as their fuel are energy facilities used for engagement in the
activities of electricity and/or heat generation. There are different types of
biomass/biogas power plants, depending on whether they generate electricity or
heat or they simultaneously generate heat and power within a combined cycle.
Likewise, there are various types of power plants depending on whether they use
biomass or biogas or a combination of these fuels, in addition to some secondary
fossil fuel.
Biomass/biogas power plants of a capacity of up to 10 MW are considered
as small power plants within the meaning of the Energy Law. 11,12
It should be pointed out that not all power plants that use biomass/biogas
are considered as the plants using renewable energy sources, since biomass can
also be used as a secondary fuel in other types of power plants. In terms of using
5
Power plants having installed capacities of up to 10 MW that utilize only biomass in their
production process, or biomass combined with a secondary fossil fuel, provided that the calorific
value of the biomass used on annual level makes up at least 80% of the total primary fuel the
Decree on Incentives for Electricity Generation Using Renewable Energy Sources and by
Combined Heat-and-Power Generation (Official Gazette of the RoS, No. 99/2009).
6
Power plants that generate electricity using renewable energy sources, except for biomass,
provided that, in the generation process, the calorific value of the used renewable energy sources
at annual level makes up at least 90% of the total primary fuel, and provided that the secondary
fuel used is a fossil fuel, biomass or waste - the Decree on Incentives for Electricity Generation
Using Renewable Energy Sources and by Combined Heat-and-Power Generation (Official Gazette
of the RoS, No. 99/2009). For details, please see Chapter 2.1 hereof.
7
The Rulebook on Requirements for Collection, Transportation, Storage, and Treatment of
Waste Used as Secondary Raw Material or for Energy Generation provides the definition of the
waste used for energy generation. This is the waste that may be recycled, i.e. reused to generate
energy therefrom, i.e. for utilization of biodegradable or heat-treated waste energy for electricity
and/or combined heat-and-power generation (agricultural waste, municipal waste, tires, waste
solvents, waste from refinery plants, biomass, sludge from sludge treatment plants, etc.). For
details, please see Chapter 2.1 hereof.
8
The Law on Waste Management (Official Gazette of the RoS, No. 36/2009).
9
Further to the EU accession process, the Republic of Serbia should incorporate into its
own legislation the provisions of numerous EU Directives including, inter alia, those related to the
waste management as stipulated in the Directive 2000/76/EC of the European Parliament and of
the Council of 4 December 2000, on the incineration of waste. Article 2, paragraph 2, subparagraphs i), ii), iv) of this Directive stipulate which substances are not the subject of the above
Directive.
10
Depending on the specific case, in order to use biomass that can be classified as waste in
accordance with the environmental laws and regulations, it is necessary to obtain the following
permits: the permit for waste collection, the permit for waste transportation, the permit for waste
storage, the permit for waste treatment, and the permit for waste disposal (there is also a provision
for obtaining an integrated permit).
11
The Energy Law (Official Gazette of the RoS, No. 84/04).
12
Further information on types of biomass power plants can be found in Chapter 2 hereof.
2
the renewable energy sources, only the power plants that use biomass/biogas as
their primary fuel can be classified as biomass/biogas power plants.
The activities of electricity, heat, or combined heat-and-power generation
are the activities of public interest. There are specifically prescribed requirements
for acquiring the right to engage in such activities.
Generation of electricity and/or heat using biomass/biogas is considered as
energy generation using renewable energy sources for which the Republic of
Serbia has prescribed certain incentives, and the power producers operating the
power plants on renewable energy sources are considered to be privileged power
producers, provided they meet certain requirements13.
1.2 Sources of Law 14
Construction of biomass/biogas power plants and engaging in the activities
of electricity and/or heat generation in such plants are regulated by numerous
laws and regulations of the Republic of Serbia.
The sources of law of the Republic of Serbia referred to herein can be
divided into two main groups of statutes and regulations, which will be detailed in
further chapters hereof.
The first group of regulations includes those governing the area of
construction of a concrete energy facility and the procedure for obtaining the
Construction Permit for such a facility, as well as the method of determining the
fitness of the facility for use and obtaining of the operating permit for the actual
facility.
The second group of regulations includes those dealing with the acquiring
of the right to engage in electricity and/or heat generation, since this is a two-step
procedure: the first step is to acquire the right to engage in the activities of public
interest, and the second one is to acquire the right to engage in an energy-related
activity.
It should be emphasized that the Law on Concessions15 is the only statute of
the Republic of Serbia, further to which one may simultaneously acquire the right
to construct an energy facility and the right to engage in the activities of public
interest.
Construction of biomass/biogas plants and engaging in activities of
electricity generation in the Republic of Serbia are regulated under the following
laws and regulations: the Law on Planning and Construction16, the Law on Spatial
Plan of the Republic of Serbia17 and relevant Planning Documents18, the Energy
Law, the Law on Ratification of the SEE Energy Community Treaty between the
European Union and the Republic of Albania, the Republic of Bulgaria, Bosnia
and Herzegovina, the Republic of Croatia, the FYR of Macedonia, the Republic
13
of Montenegro, Romania, and the Republic of Serbia and Kosovo, through the
United Nations Interim Administration Mission in Kosovo, pursuant to the United
Nations Security Council Resolution 124419, the Law on Ratification of the
Stabilization and Association Agreement between the EU Member States on the
one hand, and the Republic of Serbia, on the other20, the Law on Ratification of
the Convention on Access to Information, Public Participation in Decisionmaking and Access to Justice in Environmental Matters21, the Decree on
Conditions of Electricity Delivery22, the Decree on Requirements for Obtaining
Privileged Electricity Producer Status and Criteria for Verification of Compliance
with Requirements23, the Decree on Incentives for Electricity Generation Using
Renewable Energy Sources and by Combined Heat-and-Power Generation24, the
Rulebook on Criteria for Issuing Energy Permits, Contents of the Application and
Procedure for Issuing Energy Permits25, the Rulebook on Requirements
Regarding Professional Staff and Terms of Issuing and Revoking Energy
Licenses for Engaging in Energy-related Activities 26, the Energy Sector
Development Strategy of the Republic of Serbia27, the Decree on the
Implementation Program of the Energy Sector Development Strategy of the
Republic of Serbia by 2015 for the Period from 2007-201228, the Law on Public
Companies and Activities of Public Interest29, the Law on Public Utility
Services30, the Law on Waters31, the Decree on Compensation for Water Use,
Water Protection, and Compensation for Excavated Materials from Watercourses
19
The Law on Ratification of the SEE Energy Community Treaty between the European
Union and the Republic of Albania, the Republic of Bulgaria, Bosnia and Herzegovina, the
Republic of Croatia, the FYR of Macedonia, the Republic of Montenegro, Romania, and the
Republic of Serbia and Kosovo, through the United Nations Interim Administration Mission in
Kosovo, pursuant to the United Nations Security Council Resolution 1244 (Official Gazette of the
RoS, No. 62/06).
20
The Law on Ratification of the Stabilization and Association Agreement between the EU
Member States on the one hand, and the Republic of Serbia, on the other (Official Gazette of the
RoS, No. 83/08).
21
The Law on Ratification of the Convention on Access to Information, Public
Participation in Decision-making and Access to Justice in Environmental Matters (Official Gazette
of the RoS, No. 38/09).
22
The Decree on Conditions of Electricity Delivery (Official Gazette of the RoS, No.
107/05).
23
The Decree on Requirements for Obtaining Privileged Electricity Producer Status and
Criteria for Verification of Compliance with Requirements (Official Gazette of the RoS, No.
72/09).
24
The Decree on Incentives for Electricity Generation Using Renewable Energy Sources
and by Combined Heat-and-Power Generation (Official Gazette of the RoS, No. 99/09).
25
The Rulebook on Criteria for Issuing Energy Permits, Contents of the Application, and
Procedure for Issuing Energy Permits (Official Gazette of the RoS, Nos. 23/06 and 113/08).
26
The Rulebook on Requirements Regarding Professional Staff and Terms of Issuing and
Revoking Energy Licenses for Engaging in Energy-related Activities (Official Gazette of the RoS,
Nos. 117/05, 40/06, and 44/06).
27
The Decision on the Energy Sector Development Strategy of the Republic of Serbia by
2015 (Official Gazette of the RoS, No. 44/05).
28
The Decree on the Implementation Program of the Energy Sector Development Strategy
of the Republic of Serbia by 2015, for the Period from 2007-2012 (Official Gazette of the RoS,
Nos. 17/07, 73/07, 99/09, and 27/10).
29
The Law on Public Companies and Activities of Public Interest (Official Gazette of the
RoS, Nos. 25/00, 25/02, 107/05, and 108/05).
30
The Law on Public Utility Services (Official Gazette of the RoS, Nos. 16/97 and 42/98).
31
The Law on Waters (Official Gazette of the RoS, No. 30/10).
4
32
The Decree on Compensation for Water Use, Water Protection, and Compensation for
Excavated Materials from Watercourses for 2010 (Official Gazette of the RoS, No. 17/10).
33
The Rulebook on Contents of Technical Documentation to Be Submitted in the
Procedure for Obtaining Water Approval and Water Permit (Official Gazette of the RoS, No.
3/78).
34
The Law on Environmental Protection (Official Gazette of the RoS, Nos. 135/04 and
36/09).
35
The Law on Strategic Environmental Impact Assessment (Official Gazette of the RoS,
No. 135/04).
36
The Law on Environmental Impact Assessment (Official Gazette of the RoS, Nos. 135/04
and 36/09).
37
The Law on Integrated Pollution Prevention and Control (Official Gazette of the RoS,
No. 135/04).
38
The Law on Air Protection (Official Gazette of the RoS, No. 36/2009).
39
The Law on Waste Management (Official Gazette of the RoS, No. 36/09).
40
The Law on Nature Protection (Official Gazette of the RoS, No. 36/09).
41
The Decree on the List of Projects for which Environmental Impact Assessment (EIA)
Study is Mandatory and the List of Projects for which EIA Study May Be Required (Official
Gazette of the RoS, No. 114/08).
42
The Decree on Types of Plants and Activities Eligible for Issuance of Integrated Permits
(Official Gazette of the RoS, No. 84/05).
43
The Rulebook on Contents of the Application for Decision on the Need for an
Environmental Impact Assessment (EIA) Study and Scope and Contents of EIA Study (Official
Gazette of the RoS, No. 69/05).
44
The Rulebook on Contents of Environmental Impact Assessment Study (Official Gazette
of the RoS, No. 69/05).
45
The Criteria and Standards for Setting Energy License Fees for Engaging in Energyrelated Activities (Official Gazette of the RoS, Nos. 14/06, 40/06,126/07, and 120/08).
46
The Decision on Coefficient Value for Calculation of Energy License Fee for Engaging
in Energy-related Activities for 2010 (Official Gazette of the RoS, No. 109/09).
47
The Rulebook on Contents of Information on Location and Contents of Location Permit
(Official Gazette of the RoS, No. 3/10).
48
The Rulebook on Contents and Procedure for Issuing Construction permits (Official
Gazette of the RoS, No. 26/10).
5
solution, elaborated in the preliminary design that serves as a basis for making the
decision on feasibility of the investment and initiating the procedure for issuing
the Construction Permit.
3 POWER PLANT CONSTRUCTION
3.1 Sources of Law
Regulations on construction of power plants using renewable sources of
energy, which use biomass/biogas as fuel, can be classified in three main groups:
the regulations governing the area of planning and construction of facilities, the
regulations governing the area of environmental protection, and the regulations
governing the area of the energy sector.
The group of the regulations governing the area of planning and
construction of facilities includes: the Law on Planning and Construction, the
Law on Spatial Plan of the Republic of Serbia, the Rulebook on Contents of
Information on Location and Contents of Location Permit, the Rulebook on
Contents and Procedure of Issuing Construction permits, the Rulebook on
Contents and Method of Carrying Out Technical Inspection of Structures and
Issuing Operating Permit, the Rulebook on Contents, Scope, and Method of
Preparing the Preliminary Feasibility Study and Feasibility Study for
Construction of Structures.
Spatial plans (regional spatial plans, spatial plans of the units of local selfgovernment, and spatial plans of areas for special use) and urban development
plans (the urban master plan, general regulating plan, detailed regulating plan) are
planning documents. The regulations governing the area of construction prescribe
the procedure for obtaining the location permit, the Construction Permit, and the
operating permit while planning documents define the objectives of spatial
planning and development, i.e. of spatial development, i.e. whether it has been
planned to construct a certain structure at a certain place in the Republic of Serbia
within a certain time period. The necessary element in order to obtain the above
permits is obtaining the technical requirements for connection to the electricity
grid or to a district heating network, as well as the water requirements, the water
approval and, in certain cases, the water permit as well, which are issued in the
procedure stipulated in the Law on Waters and the regulations adopted under this
Law.
The group of regulations governing the area of environmental protection
includes: the Law on Environmental Protection, the Law on Waters, the Law on
Forests, the Law on Environmental Impact Assessment, the Law on Integrated
Pollution Prevention and Control, the Law on Air Protection, executive
regulations adopted under the above laws, as well as other regulations governing
environmental protection as well as protection and use of natural assets.
The group of regulations governing the area of the energy sector includes:
the Energy Law, executive regulations under this Law, the Energy Sector
Development Strategy of the Republic of Serbia, and the Program of
Implementation of the Energy Sector Development Strategy of the Republic of
Serbia, and other above specified regulations related to the issuing of the energy
license, connection of a structure to the grid and the like.
The Energy Law stipulates that energy facilities may be constructed if the
Minister of Mining and Energy issues the energy permit to the applicant. The
8
The Law on General Administrative Procedure (Official Herald of RoS, Nos. 33/97 and
31/01).
55
Article 208 of the Law on General Administrative Procedure stipulates that the deadline
for issuing of a decision by the competent administrative authority shall be 30 days, if it is not
necessary to follow a special examining procedure, or maximum 60 days as of the date of a duly
submitted application. General deadline for an appeal shall be 15 days as of the date of receipt of
the first-instance decision, unless the law stipulates otherwise. Article 236 of the Law on General
Administrative Procedure stipulates that, in case the administrative authority fails to issue the
administrative decision for which the application has been submitted, upon the expiry of the
deadline for handing down the decision, the applicant shall be entitled to lodge an appeal because
the first-instance application has not been decided on.
9
electric power and technical requirements for connection to the electricity grid,
requirements for connection to the public utility infrastructure, etc.
In order to obtain an energy permit, it is necessary to obtain the Information
on Location.
In any event, the procedure for obtaining the Energy Permit must be
completed prior to submitting the application for the location permit.
In the procedure for obtaining the Construction Permit, for biomass/biogas
power plants of a capacity exceeding 1 MW, preparation of the Environmental
Impact Assessment Study of the facility may be requested and, for capacities
exceeding 50 MW, it is mandatory.
3.2.1 Selection of the Location, Perusal of Valid Planning Documents,
and Information on Location
The first step of a potential investor, or of the person for whose
requirements the structure is constructed and to whom the Construction Permit for
construction of a biomass/biogas power plant will be made out, is certainly
selection of the location. This step must also be related to the analysis of the raw
material potential (biomass or raw materials for production of biogas), which will
be used for generation of electricity/heat in the biomass/biogas power plant.
The second step of the investor is verification as to whether the valid
planning documents envisage construction of an energy facility on the selected
location. One should bear in mind that power plants may also be constructed on
agricultural land, with the previously obtained approval from the Ministry of
Agriculture, Forestry and Water Management.
In the unit of local self-government, whose territory includes the selected
location, one can get for perusal the valid planning document in which it is
possible to check whether construction of energy facilities has been envisaged at
that location. Then, the application for the information on the location shall be
submitted for the desired location, for the purpose of obtaining the data on the
possibilities and limitations with respect to the construction on the reviewed
cadastral lot in line with the valid planning document.
The application for the Information on Location shall be submitted to the
authority in charge of issuing the location permit. A copy of the lot(s) plan shall
be submitted with the application for the information on the location, which has
been previously applied for in the competent real estate cadastral service in the
territory of the municipality. In parallel with the procurement of a copy of the
plan, the recommendation is to also apply for a transcript of the list of title deeds
for the subject cadastral lot(s) from the real estate cadastral service, in order to
identify the owner(s) of the land.
The information on the location, in addition to the name
of the applicant, the number of the cadastral lot, and the
place where it is located, shall also contain56 the data on:
1) The planning document based on which it is issued; 2)
The zone in which it is located; 3) The use of the land; 4)
Regulation and building lines; 5) Codes of construction;
56
An urban design shall be prepared for the formed building plot on the certified cadastral spatial plan. An urban design shall be prepared when that is envisaged in the urban development
plan, the spatial plan of the unit of local self-government, or in the spatial plan of an area of
special use and it shall contain: 1) The requirements for construction on the building plot
including all the special requirements, 2) Conceptual designs, 3) The description, technical
description, and explanation of the solution from the urban design, etc. The urban design may be
prepared by a legal entity or by an entrepreneur registered in the registry for preparation of
technical documentation, and the preparation of the design shall be managed by the town plannerin-charge, an architect. The competent authority of the unit of local self-government shall organize
a public presentation within 7 days, and then the urban design shall be submitted to the Planning
Commission, which shall, within 30 days, check whether the design has been harmonized with the
spatial document and the Law on Planning and Construction. The competent authority of the unit
of local self-government shall issue the certificate that the urban design has been prepared in
compliance with the urban development plan, the spatial plan of the unit of local self-government,
or with the spatial plan of an area of special use and the Law on Planning and Construction.
58
In addition to the energy license, the Energy Law stipulates the procedure for initiation
of the public invitation for tenders. This procedure shall be initiated in case there is no application
for the energy permit for construction of a future facility and the planned time schedule of
construction of energy facilities cannot be ensured, and there is a need to ensure safety in supply
of power. The Government shall decide on the initiation of the public invitation for tenders. The
public invitation for tenders shall be announced by the Ministry of Mining and Energy, or by the
unit of local self-government, according to the procedure regulating concessions.
11
Issuing Energy Permits. 59 The energy permit for construction of facilities for
electricity generation shall be issued by the Ministry of Mining and Energy while,
for construction of facilities for heat generation, it shall be issued by the unit of
local self-government, or by the City of Belgrade, depending on whose territory
the structure is going to be constructed. In case it is a biomass/biogas power plant,
which generates both electricity and heat, the project owner shall have to submit
two applications for the energy permits: to the Ministry of Mining and Energy
the application for the energy license for electricity generation, and to the unit of
local self-government, or to the City of Belgrade for construction of a heat
generating facility.
For electricity generating power plants of a capacity below 1 MW and for
heat generating power plants of a capacity below 1 MW, issuing of the energy
permit has not been envisaged, which means that, for such facilities, the
Construction Permit shall be issued, without following the procedure for issuing
the energy permit.
The application for the energy permit, subject to the
Energy Law, shall contain the data on: 1) The location at
which the power plant is to be constructed; 2) The
deadline for completion of construction; 3) Type and
capacity and energy efficiency; 4) The energy
commodities, which the energy facility will use; 5) The
method of generation and takeover of electricity/heat; 6)
The method of protection of the environment in the course
of construction and operation; 7) The requirements that
are related to the termination of operation; 8) The amount
of planned financial resources for construction and the
method of providing such resources.
The Rulebook on Criteria for Issuing Energy Permits, Contents of the
Application, and Procedure for Issuing Energy Permits specifies the Application
Form for the energy permit, separately for construction of the energy facility for
electricity generation, and separately for construction of an energy facility for
heat generation. Depending on the capacity of a power plant, the application for
the energy permit for construction of the energy facility for electricity generation
shall be submitted, specifically: for rated capacities from 1 MW to 10 MW
Form O-1, or for rated capacities of over 10 MW Form O-2. The application for
the energy permit for construction of an energy facility for heat generation of a
capacity exceeding 1 MW shall be submitted by filling in the Form O-10.
The following data shall be specified in the Application
Form for the energy permit for construction of a power
plant: 1) General data on the applicant (name, address,
state, official registration number of the applicant, tax
identification No., legal and organizational form, data on
59
60
The feasibility study for construction of the energy facility, for which the energy permit
is applied for, shall contain in particular: 1) Objectives of the investment including the basic data
on the investor; 2) The analysis of current state - spatial location of the facility, its function, and
importance in view of the type and capacity of the energy facility; 3) Market analysis the
method of generation, procurement, takeover, and sale of electricity/heat and energy commodities;
4) Technical description of the plant and technological processes operating modes and the
method of exploitation of the plant; 5) The analysis of energy efficiency of the facilities including
the data on electricity/heat and energy commodities to be used; 6) The planned deadline for
construction of the energy facility and service life of the energy facility; 7) The analysis of the
procurement market; 8) The analysis and assessment of the selection of the location, analysis of
possible impacts on the environment including the proposed measures of environmental
protection, relationship with respect to natural, cultural, and historic assets, impact on climate,
surface and ground waters, flora, fauna, and soil; 9) Financial analysis of the assessment including
calculation of the required investments and sources of financing and obligations towards the
sources; 10) Sensitivity analysis and analysis of the risk of the investment; 11) Analysis of the
sources of financing and financial obligations (own funds, domestic sources, foreign and
international sources, guarantees, and liabilities); 12) The analysis of the organizational and staff
capacities (organization, staff potential); 13) Proposed measures concerning the requirements for
and method of regulation of relationships in case of a temporary or permanent termination of
operation, or exploitation of the energy facility; 14) Proposed measures to be undertaken for the
purpose of protection of the energy facility and the proposed measures, which will define all the
required parameters for possible restart of operation of the energy facility at a later stage. By its
contents, this feasibility study is the closest to the Preliminary Feasibility Study including the
general design.
61
The environmental impact assessment is described in more detail in Chapter 3.2.5 hereof.
62
The Energy Law, the Decree on Conditions of Electricity Delivery, the Distribution Grid
Code, and the Transmission Grid Code specify the procedure for connection of the producers
facilities to the electricity grid. Neither the Decree, nor the Codes, or indeed any other regulations
stipulate the procedure for issuing the opinion of the energy entity in charge of transmission, or of
distribution of electricity within the procedure for issuing the energy license. In view of the above
fact, this procedure does not have a specific form, but the economic operator, whose facility
should be connected to the electricity grid, when preparing the application for such an opinion,
should submit as many documents as possible, which are necessary for connection of the facility
to the electricity grid or, if he/she does not have such documents, then at least as many data as
possible, which the specified documents should contain. The application for connection to the
electricity grid has been dealt with in Chapter 7 hereof.
14
The energy permit shall be issued within thirty days from the date of
submitting the application. The unsatisfied party may lodge an appeal against the
decision on the energy permit within seven days from the date of receipt of the
decision.
The energy permit shall be issued for a period of two years and its validity may
be extended at the request of the holder.
3.2.3 Requirements for Connection
Prior to issuing the location permit, it shall also be necessary to obtain the
requirements for connection to the electricity grid and to the heat distribution
network. If the investor fails to obtain the above requirements on his/her own,
the authority in charge of issuing the location permit shall obtain them ex officio
prior to issuing the location permit.
Within the procedure for preparation of the urban development planning
document, the location permit or of the main design for construction of the
facility, at the request of the investor or of the competent authority, the energy
entity to whose system the power producers facility is to be connected, shall
issue the requirements for connection of the producers facility to the electricity
grid. The requirements for connection shall define the possibility for connection
of the producers facility to the electricity grid, or define the electric power and
technical requirements needed for preparation of the main design for
construction of the facility.
The procedure starts when the application is submitted for the requirements
for connection.
The following shall be submitted with the
application: 1) Evidence of the payment of the expenses of
issuing the required requirements for connection as per the
pricelist; 2) Other documentation, which is specified by
the energy entity in the application form for the
requirements for connection.
63
Drafting of the Rulebook amending the Rulebook on Criteria for Issuing Energy Permits,
Contents of the Application, and Procedure for Issuing Energy Permits is under way, according to
which some of the documents, which are required with the application for the energy permit, are
amended. According to that draft, the following shall be submitted with the Application for the
energy permit: 1) The Information on the Location or the location permit issued within a period of
maximum one year (if issued), 2) The Preliminary Feasibility Study, 3) Relevant statement of a
bank that is willing to support the applicant or the investor in financing the construction of the
energy facility, 4) The opinion of the electricity transmission or distribution system operator on
the requirements for and possibilities of connection of the new facility to the system.
64
Prior to the adoption of the new 2009 Law on Planning and Construction, there had been
a discrepancy between the provisions of the Rulebook on Criteria for Issuing Energy Permits,
Contents of the Application, and Procedure for Issuing Energy Permits and the provisions of the
Law on Planning and Construction with respect to the priority in issuing the Except from urban
development plan and issuing of the decision on urban development requirements and the energy
permit. This discrepancy was avoided by deletion of the terms: the decision on urban development
requirements and the excerpt from the urban development plan. Instead of them, the terms: the
location permit and the information on the location were introduced.
15
The technical report, based on the analysis made, shall establish whether
there are electric power and technical conditions for possible future connection of
the facility according to the submitted application.
Based on the technical report, the energy entity, to whose system the facility
of the producer is to be connected, shall issue the decision on the requirements for
connection to the investor in construction of the facility, or to the competent
authority. The requirements for connection shall contain the definition of their
validity period. An appeal may not be lodged against the decision on the
requirements for connection (the decision on the requirements for connection does
not contain the grounds for it or instructions on the legal remedy). The decision on
the requirements for connection shall be issued within the deadline prescribed by
the law65.
3.2.4 Location permit66
The Law on Planning and Construction prescribes that the location permit is
the document, which contains all the requirements and data needed for
preparation of the technical documentation (the preliminary and the main design),
in line with the valid planning document. The location permit is also a
prerequisite for issuing the Construction Permit. Location permits for construction
of power plants for electricity/heat generation from renewable energy sources of a
capacity of 10 MW and over, as well as for combined heat-and-power plants and
for power plants constructed in the protected environs of outstanding cultural
assets, and of cultural assets registered in the Lists of the World Cultural and
Natural Heritage and of facilities in protected areas in compliance with the
decision on protection of cultural assets, as well as of facilities within the
boundaries of a national park and of facilities within the boundaries of protection
of a protected outstanding natural asset, shall be issued by the ministry in charge
of civil engineering affairs, or by the Autonomous Province, and for all other
power plants, by the competent authority of the unit of local self-government
(city/town, municipality) in the territory of which the structure is going to be
constructed.67
3.2.4.1 Procedure for Issuing the Location Permit
The documentation necessary to obtain the location permit for construction
of a power plant is specified in the Law on Planning and Construction. The
following shall be submitted as obligatory exhibits to the Application for the
location permit: 1) A copy of the lot plan (issued within a period of maximum six
65
The deadline for issuing the requirements for connection is 30 days; more about this can
be found in the footnote No. 55 hereof.
66
Related to the obtaining of the documentation necessary for issuing the location permit
for power plants (of up to 10 MW) there are cases of overlapping of the required documentation
(on the right to use the land, technical documentation,...) for issuing certain documents.
67
The structure of a power plant within the boundaries of a national park or within the
boundaries of protection of a protected outstanding natural asset is within the competence of the
Ministry of Environment and Spatial Planning.
16
The Law on Planning and Construction stipulates that the building plot shall
be formed prior to submitting the application for the location permit.
If the authority in charge of issuing of the location permit establishes that
adequate documentation has not been submitted with the application for the
location permit, it shall notify the applicant thereof within eight days. In case the
planning document does not contain all the requirements and data for preparation
of the technical documentation, the competent authority shall obtain them ex
officio, at the expense of the investor. The authorities, or organizations authorized
to issue such requirements and data shall act further to the request of the
competent authority within 30 days.
The competent authority shall issue the location permit within 15 days as of
the date of a duly submitted application or of obtaining the requirements and data,
which it shall obtain ex officio.
The location permit shall particularly contain71: 1) The
name and family name of the investor including personal
identification No., or business name or name of the
investor including the seat and PIB; 2) The number and
surface area of the cadastral lot; 3) The data on the
existing facilities on the lot that need to be removed; 4)
The defined access to a public traffic area; 5) The use of
the structure; 6) Building lines; 7) Codes of construction;
8) Requirements for connection to roads, public utility,
and other infrastructure; 9) Possible and mandatory stages
in the project implementation; 10) List of mandatory parts
of the main design; 11) The name of the planning
document based on which it is issued; 12) The statement
that the legally valid location permit is the basis for
68
This evidence for issuing of the location permit is exactly the same as for issuing the
Construction Permit. As evidence of the ownership right, or of lease of the construction land for
construction or for carrying out of the work on the construction land or on the facility, which is
owned by a number of persons a certified consent of such persons shall also be submitted.
69
When construction of line infrastructure facilities is in question, the decision of the
competent authority establishing the public interest for expropriation, in compliance with a special
law, or the servitude and right-of-way agreement with the owner of the servient estate, shall serve
as the evidence of the ownership right for issuing the location permit.
70
In practice, for obtaining the location permit, the general design (conceptual design) is
prepared and submitted, which contains: technical description of the location, architecture, the
structure and foundation of the structure, the method of heating and cooling the structure,
description of the technical solution for securing excavation of the foundation pit, the terrain and
the adjacent facilities, etc.
71
The Rulebook on Contents of Information on Location and on Contents of Location
Permit.
17
Provisions of the Law on Planning and Construction, in this case, are not quite clear with
respect to the formation of the building plot for construction of a biomass/biogas power plant.
Article 69, paragraph 1, prescribes that, for construction of electric power facilities or equipment,
a building plot of a smaller area may be formed than the area envisaged in the planning document
for the particular zone, provided there is an access to the facility, or equipment, for the purpose of
maintenance and elimination of defects or accidents.
18
Issuing of the water requirements, the water approval, and the water permit is regulated
by the Law on Waters.
19
There is nothing prescribed as to what should be submitted with the application for the
Opinion from RHMS what has been specified herein is a general assessment of the author in line
with the discussions in the specified organization.
20
75
There is nothing prescribed as to what should be submitted with the application for the
Opinion from public water-management enterprises what has been specified is a general
assessment of the author in line with the discussions in the specified organizations.
76
The contents of the documentation, which shall be submitted with the application, are
contained in the form VU, which can be downloaded from the Web site: www.minpolj.gov.rs /
arhiva / vodoprivreda / vodoprivredna akta (Archive / Water Management / Water Documents).
In compliance with the Law on General Administrative Procedure, the authority may request the
Investor to complete the documentation.76
21
Decision. The obtained Decision Issuing the Water Requirements shall be one of
the elements of the location permit.77
Once the location permit has been obtained, one shall proceed with the
preparation of the design documentation the main design of the power plant.
In order to proceed with the following stage obtaining of the Construction
Permit, it is necessary, inter alia, to obtain the Water Approval on the specified
design documentation. The Water Approval shall establish that the technical
documentation the Main Design, has been prepared in compliance with the
water requirements.
The documentation for issuing the water approval shall be
specifically the technical documentation the Main
Design, which shall contain: 1) The technical report; 2)
Computations: hydrological, hydraulic, of stability, level
of pollution, etc.; 3) Graphical exhibits: layout plans,
plans, and cross-sections with the necessary elements for
establishing the impact of the water regime on the
structure and vice versa; 4) Presentation of the natural
water regime; 5) Presentation of the projected water
regime; impact of the structure on the natural and the
projected water regime; 6) The impact of the natural and
projected water regimes on the structure. The approvals of
the Ministry of Health and of the Ministry of Environment
and Spatial Planning shall also be submitted along with
the above application.
The following shall be submitted with the application for
the water approval on the main design: 1) The Decision
Issuing the Water Requirements; 2) The Main Design; 3)
The report on the review of the design; 4) Other
documents, which are required in the Decision Issuing the
Water Requirements.78
The water approval shall cease to be valid if, within two years from the date
of its obtaining, the application for the Construction Permit is not submitted to the
competent authority. The decision establishing expiry of validity of the water
approval shall be handed down by the authority, which has issued the water
77
Exceptionally, subject to Article 118, of the Law on Waters, the authority in charge of
issuing the water requirements may request from the applicant to obtain the opinion of the
Ministry of Environment and Spatial Planning and/or of a specialized scientific institution
(establishments, institutes, etc.). For the facilities and works in a territory of a spa resort, the
applicant shall obtain the opinion of the ministry in charge of the affairs of tourism. There is no
specifically prescribed procedure for obtaining the above opinions.
78
To assist an applicant, the list of all the required documentation for obtaining the water
documents can be found on the Web site of the Ministry of Agriculture, Forestry and Water
Management: www.minpolj.gov.rs Link: Arhiva Vodoprivreda - Vodna akta - Obrazac zahteva
VS (Archive - Water Management Water Documents - Application Form VS). Exhibits that
shall be submitted can be downloaded from the Web site of the Ministry of Agriculture, Forestry
and Water Management, Form VDP. In compliance with the Law on General Administrative
Procedure, the authority may request the Investor to complete the documentation.
22
approval. An appeal may be lodged against this decision to the minister within 15
days as of the date of submitting the decision.
Once the structure has been constructed, and prior to obtaining the
operating permit, it is necessary to submit the application for the Water Permit to
the Ministry of Agriculture, Forestry and Water Management, or to the competent
authority. The Water Permit is required for the exploitation and use of waters and
natural and artificial watercourses, lakes, and ground waters, for discharge of
waters and other substances into natural and artificial watercourses, lakes, ground
waters, and public sewers, as well as in case of increase of the capacity of the
already existing structure for the increase of the quantity of in-taken and
discharged waters, changed nature and quality of discharged waters. This License
shall be issued for a period of maximum 15 years so that, maximum two months
prior to its expiry, its validity should be extended if there is the issued Decision
on Water Permit. The right acquired on the basis of the Water Permit may not be
assigned to any third party without the consent of the issuing party, and this right
shall terminate: upon expiry of the validity thereof, by waiver of the right, and by
failure to exercise the right without justified reasons for over 2 years.
The following shall be submitted with the application for
the water permit: 1) The water approval; 2) Evidence of
fulfillment of the requirements from the water approval;
3) The technical documentation based on which the
structure has been constructed, including all the
modifications and additions made in the course of
construction; 4) The report of the commission on the
completed technical inspection of the constructed
structure or plant; 5) The opinion of the public watermanagement enterprise concerning the fulfillment of the
requirements from the water approval, the impact of the
structure on the water regime, the impact of the water
regime on the structure, and the requirements for issuing
the water permit. In case some other documents are also
required, which depends on the specific features of the
structure, the Investor, after submitting the application,
shall be subsequently notified by the Ministry to complete
the documentation.79
3.2.5 Environmental Impact Assessment
Environmental impact assessment is a very important element in the process
of construction of a power plant. Within the procedure for obtaining the energy
permit, it is necessary to make a study of possible impacts on the environment
including the proposed measures for protection of the environment.
79
To assist an applicant, the list of all the necessary documentation for obtaining the water
documents can be found on the Web site of the Ministry of Agriculture, Forestry and Water
Management: www.minpolj.gov.rs Link: Arhiva Vodoprivreda - Vodna akta - Obrazac zahteva
VD (Archive Water Management Water Documents Application Form VD). In compliance
with the Law on General Administrative Procedure, the authority may request from the Investor to
complete the documentation.
23
80
The necessary element for issuing the Construction Permit for power plants of a capacity
of 50 MW or over is assessment of the impact on the environment made in a clearly defined
format the format of the Environmental Impact Assessment Study for the power plant. For
power plants of a capacity of 1-50 MW, the Environmental Impact Assessment Study is
mandatory if the competent authority80 finds it necessary.
81
Plants generating electricity, steam, hot water, technological steam or heated gases, using
all types of fuels, as well as plants driving operating machines (thermoelectric power plants,
district heating plants, gas turbines, plants with internal combustion engines, and other combustion
equipment, including steam boilers) of a capacity of 50 MW or over.
82
Plants generating electricity, steam, hot water, technological steam or heated gases
(thermoelectric power plants, district heating plants, gas turbines, plants with internal combustion
engines, other combustion equipment), including steam boilers, in combustion plants using all
types of fuels of a capacity from 1 to 50 MW.
83
The competent authority, within the procedure for environmental impact assessment for a
power plant of 10 MW and over, is the Ministry of Environment and Spatial Planning, or the
competent authority of the Autonomous Province, if the power plant is located in the territory of
the Autonomous Province. The competent authority in the procedure for environmental impact
assessment for a power plant of up to 10 MW is the competent authority of a unit of local selfgovernment.
24
The Application Form concerning the need to assess the impact of a project on the
environment is specified in the Rulebook on Contents of the Application Concerning the Need for
Impact Assessment and Contents of the Application for Determining Scope and Contents of the
Environmental Impact Assessment Study.
85
The second-instance authority, in the procedure against the decision of the competent
authority of a unit of local self-government is the Ministry of Environment and Spatial Planning,
or the competent authority of the Autonomous Province if the power plant is located in the
territory of the Autonomous Province.
25
Application for determining the scope and contents of the impact assessment
study to the competent authority, in the prescribed form.
The specified application shall contain: 1) The data on the
project owner, 1a) The description of the location, 2) The
description of the project, 3) Presentation of the main
alternatives that have been analyzed, 4) The description of
the environmental factors that may be exposed to the
impact, 5) The description of possible major harmful
impacts, 6) The description of the measures envisaged for
the purpose of prevention, mitigation, and elimination of
major harmful impacts, 7) Non-technical summary of data
from 2) to 6), 8) Data on possible difficulties encountered
by the project owner in collecting the data and
documentation, 9) Other data and information at the
request of the competent authority. The following
documentation shall be submitted with the specified
application: 1) The excerpt from the urban development
plan or verified urban design, or the decision on urban
development requirements issued within a period of
maximum one year, 2) The preliminary design, or the
excerpt from the preliminary design, 3) Graphical
presentation of the macro- and micro-location, 4)
Requirements and approvals of other competent
authorities and organizations obtained in compliance with
a special law, 5) Evidence of payment of the Republic
administrative fees and duties, and 6) Other evidence at
the request of the competent authority.
Within 10 days, the competent authority shall notify the interested public
about the submitted application. The interested parties shall submit their
respective opinions within 15 days as of the date of receipt of the notification.
Within 10 days, the competent authority shall hand down the decision on the
scope and contents of the impact assessment study. The decision shall be
submitted to the project owner and to the interested public within 3 days.
The project owner and the interested public may lodge an appeal, and the
competent second-instance authority shall hand down the decision within 30 days
from the date of receipt of the appeal.
The detailed procedure for making of the Environmental Impact
Assessment Study for a biomass/biogas power plant is regulated by the Law on
Environmental Impact Assessment and by the bylaws under this Law86. This Law
stipulates that the concrete impact assessment study for a biomass/biogas power
plant is an integral part of the documentation, which shall be submitted with the
application for the Construction Permit or with the report on commencement of
the project implementation (construction, carrying out of the work, change of
technology, change of activity, and other activities).
86
The bylaws of the Law on Environmental Impact Assessment that are binding for this
issue are the Rulebook on Contents of the Application Concerning the Need for Impact
Assessment and Contents of the Application for Determination of Scope and Contents of the
Environmental Impact Assessment Study and the Rulebook on Contents of Environmental Impact
Assessment Study.
26
Detailed prescribed contents of the study are contained in the Rulebook on Contents of
the Environmental Impact Assessment Study.
27
88
29
30
The preliminary feasibility study specifies the spatial, environmental, social, financial,
market, and economic justifiability of the investment for the variant solutions defined in the
general design, based on which the planning document shall be adopted, as well as the decision on
justifiability of the investment in preliminary work for the Preliminary Design and for making the
Feasibility Study. It is mandatory for the facilities referred to in Article 133 of the Law on
Planning and Construction, which include the facilities for electricity/heat generation from
renewable energy sources of a capacity of 10 MW and over, as well as combined heat-and-power
plants.
90
The feasibility study determines the spatial, environmental, social, financial, market, and
economic justifiability of the investment for the selected solution, elaborated in the preliminary
design, based on which the decision on justifiability of the investment shall be handed down. It is
mandatory for the facilities referred to in Article 133 of the Law on Planning and Construction,
which include the facilities for electricity/heat generation from renewable energy sources of a
capacity of 10 MW and over, as well as combined heat-and-power plants.
31
91
If the Report on the completed review of the Main Design is positive, i.e. there are no
remarks that would give rise to the amendments of the design documentation, the specified
company shall affix its seal on the actual design - on the first page thereof, evidencing the
completed review, which shall be signed by the designer in charge of the review.
32
33
34
construction of facilities for which the approval for construction is issued by the
ministry, or by the Autonomous Province.
Obligations of the contractor shall be as follows: prior to the
commencement of the work, to sign the Main Design, to designate the Contractorin-charge by the decision, to provide, to the contractor-in-charge, the
Construction Contract and the documentation based on which the structure is
going to be constructed, to provide preventive measures for safe and sanitary
work in compliance with the law. The contractor shall be obliged to carry out the
work according to the documentation based on which the Construction Permit has
been issued, to organize the construction site in the manner, which will ensure
access to the location, to ensure safety of the structure and persons at the
construction site and its environs, to provide evidence of the quality of the work
carried out, to keep the daily progress record, the program and progress record,
and to provide the inspection book, to secure the facilities and environs in case of
suspension of the work. At the construction site, it is necessary to have the
construction contract, the Decision on designation of the contractor-in-charge,
and the main design at all times, i.e. to have the documentation based on which
the project is developed. The investor shall provide supervision in the course of
construction of the structure or of carrying out of work for which the Construction
Permit has been issued.
Supervision may be exercised by the person, who fulfills the requirements
prescribed by the Law on Planning and Construction for the designer-in-charge or
for the contractor-in-charge. The persons, who are employed in a company, or in
another legal entity or in an entrepreneurs shop, which is the contractor on that
structure, the persons, who exercise the inspection supervision, and the persons,
who work on the tasks of issuing of the Construction Permits in the authority in
charge of issuing Construction Permits, may not participate in exercising the
supervision over the structure.
Fitness of a structure for use shall be established through technical
inspection. Technical inspection of a structure shall be carried out upon
completion of construction of the structure, within 30 days as of the date of
submitting the Application for the technical inspection of the structure to the
ministry in charge of civil engineering affairs, or to the local self-government, or
to a the unit of local self-government (depending on the capacity of the facility, or
on the competent authority, which has issued the Construction Permit). Such
inspection of facilities shall be carried out by the commission, which shall be
formed by the competent authority, or by other legal entity assigned to engage in
such activities and which is registered in the relevant registry for engaging in such
activities. 92 The work of the Commission shall be paid by the investor. The
Commission shall issue the Report/Finding of the Commission for technical
inspection. In case of the facilities for which the environmental impact assessment
study has been made, a person, who is an expert in the area that is the subject of
92
the study, and who has acquired higher education in an adequate field, or at a
course, at the postgraduate academic studies - master, specialist academic studies,
or at undergraduate studies lasting minimum five years, must participate in
carrying out of the technical inspection. The costs of the work of the Commission
shall be paid by the investor. Minutes shall be taken of the technical inspection,
which shall be signed by the members of the commission.
If, for the purpose of establishing of the fitness of a structure for use,
previous tests must be performed and checking of installations, equipment, plants,
stability or safety of the structure, equipment, and plants for environmental
protection, equipment for fire protection or other tests, or if that is stipulated in
the technical documentation, the commission for technical inspection, or the
entity who has been assigned to carry out the technical inspection, may propose to
the competent authority to allow setting of the facility into trial operation,
provided it has established that the requirements for that have been met.
The decision on approval of setting the facility into trial operation shall
specify the duration of the trial operation, which may not exceed one year, as well
as the obligation of the investor to monitor the results of the trial operation and,
upon the expiry of the trial operation, to submit the data on its results to the
competent authority.
In the course of the trial operation of the facility, the commission for
technical inspection, or the entity, which has been assigned to carry out the
technical inspection, shall verify whether the requirements for issuing the
operating permit have been met and, upon expiry of the deadline for the trial
operation, it shall submit its report to the authority in charge of issuing of the
operating permit.
3.2.9 Operating Permit
A facility may be used after the operating permit has been previously
obtained.
The authority in charge of issuing the operating permit is the authority in
charge of issuing the Construction Permit. Such an application for a structure 50
meters high and over, when a power plant facility is located in protected environs
of an outstanding immovable cultural asset and of cultural assets registered in the
Lists of the World Cultural and Natural Heritage and of facilities in protected
areas in compliance with the decision on protection of cultural assets, as well as
of facilities within the boundaries of a national park and of facilities within the
boundaries of protection of a protected outstanding natural asset, in compliance
with the law, and for a power generating facility using renewable sources of
energy of a capacity of 10 MW and over, as well as for combined heat-and-power
plants, shall be submitted to the Ministry in charge of construction affairs and, if
such a facility is located in the territory of the Autonomous Province, the
application shall be submitted to the competent authority of the Autonomous
Province. As to the facilities of a capacity below 10 MW, the application shall be
submitted to the competent authority of the unit of local self-government.
The operating permit shall be issued when it is established that the facility
or a part of the facility, which can be independently used is fit for use. The
operating permit shall be issued within seven days from the date of receipt of the
finding of the commission, which stipulates that the facility is fit for use.
36
The operating permit shall also contain the warranty period for the facility
and certain types of works specified in a special regulation. (The Decision on
Minimum Warranty Periods for Certain Types of Constructed Investment Projects
or Works Carried Out on Such Structures (Official Herald of SRS, No. 2/74).
The procedure for obtaining the operating permit involves two stages. An
appeal may be lodged, within 15 days as of the date of submitting the decision, to
the Ministry in charge of construction affairs, or to the Autonomous Province if
the facility is constructed in the territory of the Autonomous Province.
No appeal may be lodged against the decision on the operating permit,
when the decision-maker is the ministry in charge of civil engineering affairs, or
the competent authority of the Autonomous Province, but an administrative suit
may be instituted within 30 days from the date of its submittal.
After acquiring the right to engage in the activity of electricity generation, an energy
entity, which produces electricity, shall contact the Ministry of Agriculture, Forestry and Water
Management or the Secretariat for Agriculture, Water Management and Forestry (if the entitys
seat is in the territory of the Autonomous Province of Vojvodina) with a request to define the
amount of the fee for utilization of surface, ground, and mineral waters and to calculate the water
utilization fee. This fee is defined only for a public electric power enterprise.
94
The current legislation of the Republic of Serbia does not include any provisions
regarding the modalities for acquiring the right to engage in an activity of public interest within a
combined heat-and-power generating facility. Since granting of the right to electricity generation
is within the remit of the Republic (the Ministry of Mining and Energy) and granting of the right
to heat (steam and hot water) generation is within the remit of a local self-government unit, and
that there are no provisions that would regulate, e.g. the prevailing business activity, until the
regulation that would regulate this area is adopted, the economic operator engaged in both
activities within the same facility should acquire the right to engage in both activities of public
interest from the competent authority.
37
Serbia for the activity of electricity generation. However, the right to heat
generation shall be acquired by concluding the Assignment Agreement with the
competent local self-government authority, in compliance with the regulations
passed by the assembly of the municipality, or of the city/town.
The Law on Public Companies and Activities of Public Interest stipulates
the obligation of a public company or any other economic operator, when
utilizing the goods of public interest (waters and watercourses included), to pay a
fee for utilization of such goods.
It should be pointed out that, for engaging in the activity of electricity
generation, in addition to acquiring the right to engage in such an activity as an
activity of public interest, it is also necessary to get a license to engage in this
activity, as an energy-related activity. The license for engaging in the activity of
electricity generation is issued by the Energy Agency of the Republic of Serbia.
For engaging in the activity of heat generation, in addition to acquiring the
right to engage in such an activity as an activity of public interest, it is also
necessary to obtain the license to engage in this activity. The license for engaging
in the activity of heat generation is issued by the competent authority of the local
self-government unit or by a city/town, or by the City of Belgrade.95
4.1 Investing in a Public Company Generating Electricity
According to the Law on Public Companies and Activities of Public
Interest, the Republic of Serbia shall establish a public company to engage in the
activities of public interest. These activities shall be implemented by the Republic
of Serbia through the Government. Consequently, by virtue of its actual
foundation, the Public Company is entitled to engage in the activity of electricity
generation. The situation is similar at the local self-government level. According
to the Law on Public Utility Services, municipalities shall set up Public Utility
Companies to provide public utility services. Therefore, it follows that, by virtue
of its actual foundation, a public utility company is entitled to engage in the
activities of steam and hot water generation (heat).
A public company represents an organizational form of an economic
operator, which has no assets of its own, but is the beneficiary of the assets of the
Republic of Serbia96, which means that its only asset is the right to use the stateowned property. Therefore, no other party, except the State itself, is entitled to
invest in a public company until such company has translated its assets into stocks
or shares, i.e. until it has undergone corporatization.
However, a public company may establish affiliated companies (a joint
stock company or a limited liability company), within the framework of its own
activities. A company affiliated to a public company is entitled to engage in
activities of public interest, provided it has been founded by the public company
for the purpose of pursuing the activities of public interest. Together with the
public company, an interested third party could establish a new joint venture
company. However, a better legally founded case would be for the third party to
95
38
Investments in affiliated companies are made in compliance with the Company Law
(Official Gazette of the RoS, No. 125/04).
98
A public companys approval of the decision on pricing policy or tariffs proposed by its
affiliated company is considered preliminary only since, according to the Energy Law, the final
approval of the electricity tariffs or prices of services for tariff buyers is granted by the
Government.
39
with the law, technical, and other regulations); 2) Staff capacity (the employees
working at the power plant shall have the necessary qualifications and other
prescribed skills); 3) Occupational safety measures in place; 4) Implementation of
prescribed requirements and methods of protection and improvement of the
environment.
The Assignment Agreement shall include the following
provisions concerning: 1) Work and business operation of
the economic operator entrusted with the subject activity;
2) Rights and obligations regarding the utilization of stateowned assets for pursuit of activities of public interest, in
line with the Law; 3) The economic operators obligation
to provide the conditions for uninterrupted, regular, and
high-quality satisfying of the needs of the users of such
products and services; 4) Mutual rights and obligations of
the contracting parties in situations when economic or
other conditions for pursuit of activities of public interest
are not provided; 5) Mutual rights and obligations in case
of a disruption in the business operation of the economic
operator; 6) Other rights and obligations and issues of
relevance for pursuit and protection of public interest.
For the purpose of monitoring and control of the pursuit of the activity of
electricity generation, the following documents of the economic operator, with
which the Government has concluded the assignment agreement, shall be subject
to its approval: 1) The Articles of Association; 2) Tariffs (pricing policy, tariff
system, etc.); 3) Any other decisions in accordance with the statutes and
regulations and the concluded Assignment Agreement.
It is important to highlight the characteristics of the Assignment Agreement:
1) There is no provision in the Law for a tendering procedure; 2) The Law does
not stipulate the obligation to specify the location for engaging in the activity of
electricity generation (unless the Agreement refers to a concrete facility); 3) The
Law does not stipulate a maximum duration of engaging in the activity of public
interest (if it is not defined in the Agreement); 4) The Law does not stipulate the
scope of engagement in such an activity; 5) The Law does not stipulate the
obligation to pay any fee for engagement in an activity of public interest.
Up to now, the Ministry of Mining and Energy has not entered into a single
procedure of negotiating an assignment agreement for electricity generation from
renewable sources.99
The Law on Public Utility Services prescribes that a municipal assembly
may outsource its public utility services to another enterprise or entrepreneur, in
compliance with the Law and the statutes passed by the municipal assembly100.
The method to regulate the outsourcing of the activities of public utility services
99
The Ministry of Mining and Energy has concluded Assignment Agreements in the field
of natural gas distribution with the economic operators none of which is a public company, after
they had obtained the licenses for engaging in such activities.
100
The Law on Public Utility Services stipulates that rendering of public utility services,
such as steam and hot water generation and supply, for example, shall be outsourced to another
economic operator in cases when establishing a public utility company would not be reasonable,
having in mind the scope of works and the number of beneficiaries involved.
40
5 CONCESSIONS
Concessions represent a form of granting and exercising: the right to
construct, maintain, and utilize public utility facilities for the purpose of
providing public utility services, the right to construct, maintain and utilize
energy and other types of facilities for the purpose of electricity and/or heat
generation, as well as the right to engage in other activities of public interest.
Concessions may also be granted for pursuit of the activity of electricity
generation on the already constructed power plants for engaging in the activities
of heat and/or electricity generation.
101
41
It should be pointed out that the concession rights may be obtained for the
whole business cycle or for individual segments thereof, i.e.: 1) For construction
of a power plant and engaging in the activities of heat and/or electricity
generation, and 2) Solely for pursuit of the activities of heat and/or electricity
generation within an already constructed power plant.
The procedure for granting a concession and modalities of exercising the
concession rights are precisely regulated in the Law on Concessions. A
concession agreement shall form the legal ground for the concession. The
procedure for concluding such an agreement is much more detailed than the
procedure for conclusion of the assignment agreement, thus providing better legal
security. On the other hand, in view of the prescribed deadlines and stages, the
concession granting procedure may take much longer than the one for entrusting
the pursuit of activities of public interest by means of the assignment agreement.
A concession may be granted for maximum 30 years.
It is prescribed that the regulation of the requirements and the procedure for
concession granting shall be based on the principles of equal and fair treatment of
all participants in the procedure for concession granting and selection of the
concessionaire, free market competition, and autonomy of will of the contracting
parties.
5.1 Concession Granting Procedure
The proposal for granting a concession shall be submitted to the
Government by the Ministry of Mining and Energy or by the competent authority
of the Autonomous Province if the subject matter of the concession is situated in
the territory of the Autonomous Province. The proposal for concession granting
may also be submitted by a local self-government unit for the facilities within its
own territory. The initiative for granting a concession may also be submitted by
any interested person.
The proposal for granting a concession shall include
particularly the following: 1) The subject matter of the
concession; 2) Assessment of its feasibility and the amount
of the investment; 3) Tentative duration of the concession
period; 4) Basic requirements for implementation of the
concession; 5) Proposed amount of the fee; 6) Purpose of
exploiting the subject matter of the concession; and 7)
When the proposal is submitted by an interested party, the
data on that party as well (name of the company, personal
name, evidence of registration).
If the subject matter of a concession is the construction, maintenance, and
operation of a power plant of a strategic importance for the Republic of Serbia or
to which international importance is attached, the Government shall submit the
proposal for granting the concession involved to the National Assembly of the
Republic of Serbia.
Based on the position of the Government (i.e. of the National Assembly) on
the intention to grant a concession and based on economic, financial, social, and
other indicators, the Ministry of Mining and Energy shall draw up a Proposal for
Issuance of a Concession Deed, which it shall submit to the Government.
42
44
The Concessionaire shall undertake to assign all its rights and obligations
resulting from the concession agreement to a separate concessionary enterprise.
The concessionary enterprise shall always be organized as a for-profit
corporation (either a joint stock or a limited liability company) performing the
concession agreement.
Since the Law on Concessions does not include any provisions stipulating
possible transfer of shares or stocks of the concessionary enterprise to a third
party, consequently, the conclusion may be drawn that such transactions are
neither prohibited nor conditioned by it.
Changes of the seat and status changes of the concessionary enterprise shall
be subject to approval by the founder.
The concessionary enterprise shall also obtain the license for pursuit of the
activities of heat and/or electricity generation.
5.4 Reassignment of Concession
A concession shall only be reassigned by means of a contract and upon
mandatory approval granted by the Concedent or otherwise such a contract shall
be deemed null and void. After the rights and obligations from the concession
agreement have been assigned to the concessionary enterprise, only the
concessionary enterprise shall have the right to reassign all the rights and
obligations to a third party through a contract, upon approval granted by the
Concedent.
6 ENERGY LICENCE
An Energy License is a permit issued by the Energy Agency of the Republic
of Serbia for engaging in an energy-related activity. The Energy License is an
administrative decision confirming fulfillment of the requirements prescribed
under the Energy Law and the Rulebook on Requirements Regarding Professional
Staff and Terms of Issuing and Revoking of Energy Licenses for pursuit of
energy-related activities. It is the last in a series of legal documents required for
engaging in energy-related activities. The energy license must be possessed by the
entity already in possession of a power plant, which has acquired the right to
engage in the activity based on the assignment agreement for pursuit of the
activity of public interest or based on the concession agreement.
The requirements for obtaining the energy license shall
include: 1) Registration in the Business Registry; 2)
Fulfillment of the technical requirements with respect to
the power plant itself (electric power, fire-prevention, and
environmental protection ones), including proprietary
rights or the right to use the actual plant; 3) The required
staff capacity available; 4) The required financial
resources have been made available (evidence of
solvency, balance sheet, etc.); 5) The energy entity has not
been denied the energy license in the past three years; 6)
46
The license fee is set by the Energy Agency decisions, specifically: the Criteria and
Standards for Setting Energy License Fees for Engaging in Energy-related Activities (Official
Gazette of the RoS, Nos. 14/06, 40/06,126/07, and 120/08, and the Decision on Coefficient Value
for Calculation of the Energy License Fee for Engaging in Energy-related Activities for 2010
(Official Gazette of the RoS, No. 109/09).
105
http://www.aers.org.rs/Index.asp?l=1&a=36
106
Article 145 of the Energy Law.
47
the standards and technical regulations concerning the criteria for access to and
use of power plant facilities, equipment, and plants.
The energy entity, to whose system the power producers facility is to be
connected, shall approve the connection if it establishes that the equipment and
installations within the facility to be connected meet the requirements prescribed
by the laws and statutes, technical, and other regulations governing the
requirements for and method of exploitation of such facilities.
The facility shall be connected to the electricity transmission and/or
distribution system on the basis of the approval issued by the energy entity to
whose system the facility is going to be connected. The approval for connection
to the electric power system is an administrative decision issued in the form of a
Decision stipulating the terms and conditions that the applicant, the electricity
producer, shall fulfill in order to acquire the right to supply electricity to the
electric power system. The approval for connection shall be issued in the form of
a Decision, further to the application submitted by a natural person or by a legal
entity or by an entrepreneur.
The Energy Agency had adopted the Methodology for determining the costs
of connection to the grid107 and, based on this Methodology, the energy entity to
whose system power plants shall be connected, has adopted its own decision
specifying connection charges.
The application for access to and use of the system shall be submitted to the
energy entity in charge of electric power transmission or distribution, to whose
grid the power plant is to be connected.
The application shall be accompanied by the following
data on: 1) The name of owner of the facility or the holder
of the right to use the facility (for natural persons: the
name and place of residence, personal identification No.
and, for legal persons or entrepreneurs: business name or
name, seat, PIB, official registration No., account number,
and the name of the responsible person; 2) The facility,
for the connection of which, issuing of the approval for
connection is applied for (the address, type, location of the
facility, and the use of the facility); 3) Estimated time of
connecting the facility. In addition, it shall be required to
submit the data on: 1) The total installed capacity of the
facility, the number and power of generating units, source
voltage, and block transformer; 2) Expected annual and
monthly output; 3) Protection and measuring equipment;
4) The energy license and the license for engaging in the
activity of electricity generation for the facilities of a
capacity exceeding 1 MW (consequently, it follows that
one shall first obtain the license for engaging in the
activity, and only then apply for connection of the energy
facility to the grid).
107
The Decision on Establishing the Methodology for and Criteria and Manner of Setting Costs
of Connection to the Electricity Transmission and Distribution Systems (Official Gazette of the
RoS, Nos. 60/60, 79/06, and 114/06).
48
It is interesting that both the Energy Law and the Decree on Conditions of Electricity
Delivery prescribe that a facility is connected to the grid after conclusion of the power purchase
agreement, which is concluded between an energy entity and the electricity buyer. These
provisions should be stated precisely both in the Law and in the Decree, because they suggest that
the electricity buyers are always the ones that are connected to the electricity grid, which does not
always have to be the case, and it does not always have to be the power purchase agreement that is
to be concluded on the occasion of every connection to the electricity grid but just the agreement
on electricity transmission or on distribution via the grid. The actual sale of electricity, under the
conditions of an open electricity market and under the conditions when a power plant is connected
to the transmission or to the distribution system, does not have to be an integral part of the
electricity transmission or distribution activity.
109
In this case, the electricity Buyer is a public enterprise in charge of generation,
distribution of and trade in electricity.
110
The Power Purchase Agreement shall be based on a template drafted by the Buyer and
approved by the Ministry of Mining and Energy.
111
The Power Purchase Agreement shall be based on a template drafted by the Buyer and
approved by the Ministry of Mining and Energy.
49
112
Further information on obtaining the status of a privileged power producer can be found
in Chapter 8 hereof.
113
Further information on obtaining the status of a privileged power producer can be found
in Chapter 8 hereof.
114
The special regulations shall be deemed to include the regulations of a local selfgovernment unit related to the method of engaging in the public utility activity of heat (steam and
hot water) generation and of securing proper rendering of such service, its continuity, and the
rights and obligations of the public utility operator in charge of distribution and supply of heat.
Such regulations shall include the Operating Rules of the heat distributor, if they have been
adopted.
50
Article 9 of the Decree on Requirements for Obtaining Privileged Electricity Status and
Criteria for Verification of Compliance with Requirements.
51
this Decree, and 2) The power producer engaged in the activity in multiple power
plants shall submit the application for the status of the privileged producer for
each such power plant separately.
A legal entity or an entrepreneur may obtain the status of the privileged
producer for the following types of power plants: a power plant that, in its
production process, utilizes biomass or biomass combined with any secondary
fossil fuel or waste, provided that the calorific value of the biomass used on
annual level makes up at least 80% of the total primary fuel, and a combined heatand-power plant that utilizes fossil fuels or fossil fuels combined with some
renewable energy source or waste, provided it reaches the total annual efficiency
ratio in excess of the corresponding value of a minimum total annual efficiency
ratio of a combined heat-and-power plant (according to the Table provided in the
Decree). The Decree also prescribes the method of determining the total annual
electricity output of the power plant for which the application is submitted for the
status of the privileged power producer, as well as the obligation of such producer
to have electricity measuring units installed in the power plant production units,
i.e. in each power plant separately. The total net electricity generated shall be
determined as the total electricity supplied to the electricity grid during one
calendar year, i.e. the total realized annual production of electricity within the
power plant less the plants own annual consumption and losses within the power
plant. Annual net production of heat shall be determined as the total heat supplied
to the heat distribution system within a calendar year, i.e. the total realized annual
heat generation of the power plant less the plants own annual consumption and
losses within the power plant. The Decree also prescribes the necessary
documentation to be submitted with the application for obtaining this status, as
well as definitions of all the necessary terms (primary energy, primary fuel,
calorific value of consumed fuel, calorific value of consumed fuel mixture, total
annual efficiency ratio).
The actual application procedure for obtaining the status of a privileged
power producer, as stated above, is defined by the Energy Law whereby the
procedure involves two stages. The application shall be submitted to the Minister
of Mining and Energy, who shall issue a decision within 30 days from the date of
filing the application.
The application for the status of the privileged producer
shall be accompanied by the following documentation: 1)
A copy of the license for engaging in electricity
generation activity in case the power plant is of a capacity
of 1 MW or over; 2) A copy of the contract with the
license holder in case the power plant is of a capacity of 1
MW or over, and the producer is not the license holder; 3)
The as-built design of the power plant facility; 4) A copy
of the agreement on access to and use of the distribution
or to the transmission system and, in case of power plants
of special characteristics with combined heat-and-power
generation, also a copy of the agreement on connection to
and takeover of heat, signed with the competent energy
entity or other economic operators; 5) The Operating
Permit; 6) The data on the person in charge of the power
plant operation.
52
Along with the application for the status of the privileged producer, for each
and every combined heat-and-power plant where the share of fossil fuels in the
total primary fuel exceeds 20%, in addition to the above documentation, the
following shall be submitted: (1) Expected annual production of heat, including
monthly production schedules; 2) Expected values of the total annual efficiency
ratio. The discontented party may lodge an appeal against such a decision to the
Government within 15 days from the date of submitting the decision. The Law
also stipulates the obligation of the Ministry of Mining and Energy to keep the
Registry of Privileged Power Producers.
53
2.
3.
Installed Capacity
(P) (MW)
up to 0.5 MW
from 0.5 MW up to
5 MW
from 5 MW up to
10 MW
up to 0.2 MW
from 0.2 MW up to
2 MW
over 2 MW
Incentive/Feed-in Tariff
(cEUR/1 kWh)
13.6
13.845 0.489*P
11.4
16.0
16.444-2.222*P
12.0
6.7
Agreement shall be considered terminated upon expiry of the thirtieth day from
the date when the Buyer receives the notice to that effect in writing. The
privileged producer, who has concluded the Agreement, shall not pay any
remuneration for the services of balancing to the Buyer and shall not be obliged to
pay for the service of electricity readout.
Readings of electricity at the privileged producers shall be taken by the
energy entity to whose grid the privileged producer is connected, in such a way
that readings shall be taken every first day in a month and not later than by every
fifth day in a month; the readout data for the previous month shall be submitted
both to the privileged producer and to the Buyer. Prior to the conclusion of the
agreement, the energy entity, to whose grid the privileged producer is to be
connected, shall have another obligation, to take, at the request of the privileged
producer or of the Buyer, the initial readout of the electricity meter. This
obligation shall be fulfilled within three days from the date of receipt of such an
application. 116
The Decree stipulates certain obligations of the Buyer: 1) To conclude the
agreement117 within 30 days from the date of submitting a written application for
conclusion of the Power Purchase Agreement, and 2) To provide the service of
balancing to the privileged producer without any remuneration. It also prescribes
that the Buyer shall be entitled to remuneration of expenses resulting from the
specified obligations. The amount of such expenses shall be determined on the
basis of energy quantities set out in the Energy Balance of the Republic of Serbia
for the forthcoming year. The Decree prescribes the method of calculation of such
expenses and the method of their remuneration. The Buyer shall be reimbursed
for the specified expenses by disclosing the same in the prices of electricity for
tariff buyers.118
The Buyer shall be obliged to notify the Ministry of Mining and Energy and
the Energy Agency about the revenues collected from remunerations and from
sales of electricity purchased from the privileged producers, as well as about the
costs related to the obligation to purchase the electricity from the privileged
producers.
The prescribed mechanism does not create any possibility for privileged
electricity producers to sell the electricity to future qualified buyers directly on
the market - at market prices, if competitive enough. Although it is not
specifically regulated, the above mechanism also establishes the obligation of the
energy entity, to whose electricity grid the privileged electricity producer from a
biomass/biogas power plant is connected, to ensure takeover of such electricity in
the grid.
116
At the time of writing this text, the energy entities operating the distribution grids are
affiliated companies of the Buyer.
117
The stipulated obligation to conclude the Power Purchase Agreement is set forth in the
Decree. In view of the fact that the Decree is an executive regulation, for the time being, breaches
or economic offences have not been prescribed as yet, for the case when the Buyer fails to fulfill
its obligation prescribed in the Decree and fails to conclude this Agreement within the prescribed
time or fails to conclude it at all.
118
The prices of electricity for tariff buyers shall be set by the Decision, which shall be
issued by the Public Company in charge of generation, distribution, and trade in electricity (PC
EPIS), based on the Methodology for Setting Tariff Elements for Pricing Electricity for Tariff
Customers (Official Gazette of the RoS, Nos. 68/06, 18/07, and 116/08), and on the Tariff System
for Calculation of Electricity for Tariff Buyers (Official Gazette of the RoS, Nos. 1/07, 31/07,
50/07, 81/07, 21/08, and 109/09) handed down by the Energy Agency of the Republic of Serbia.
The approval of this Decision shall be granted by the Government.
55
9 CONCLUSION
Construction of a biomass/biogas power plant and engaging in the activity
of electricity and/or heat generation shall represent the entire process required for
the operation of such an energy facility. Establishing an affiliated company of a
public utility company, assigning the right to engage in the activity of public
interest, and concessions represent the three ways of acquiring the right to engage
in the activity of electricity and/or heat generation in biomass/biogas power
plants.
Further to the comparative analysis of legal aspects of all the three
modalities of engaging in the activity of electricity and/or heat generation in
biomass/biogas power plants, there are certain legal gaps and discrepancies with
respect to the interrelationship among these three legal institutes. Consequently, it
follows that there is an ample space for discretionary powers of the competent
authorities in these procedures, particularly when selecting the modality for
acquiring the right to engage in such an activity.
Depending on whether electricity or heat is generated, the competences of
the authorities that are in charge of protection of the public interest differ. In case
of electricity generation, it is to do with the energy-related activity, which is the
activity of public interest, which is within the competence of the Republic of
Serbia. If we are talking about heat generation, we are talking about a public
utility service, which is within the remit of a local self-government unit. This
means that engaging in the energy-related activity in biomass/biogas power plants
is regulated in different ways depending on the product of such a power plant.
Another peculiarity is acquiring the right to engage in the energy-related activity
that involves a co-generation process - combined heat-and-power generation
within the same plant. In this case, since two activities are in question, the nonenergy entity should apply to different authorities in order to acquire the right to
engage in both activities and, until both procedures have been completed, which
should finally yield a functionally achievable result in practice, it cannot start
generating electricity/heat, since the process is functionally undivided. Only in the
case of combined-heat-and-power process, the procedure for acquiring the license
119
to engage in energy-related activities calls for the energy entity to submit the
application to only one authority: the Energy Agency.
The procedure of granting the concession for construction of a
biomass/biogas power plant and simultaneous engaging in the activity of
electricity and/or heat generation offers a better legal security to investors than
other methods of acquiring such rights, because the interested party shall acquire
its right in a single, clearly defined procedure. The procedure for granting the
concession for construction of a power plant and simultaneous engaging in the
activity of electricity and/or heat generation is more time-consuming than a
separate procedure for obtaining the permit for construction of a power plant and
conclusion of the assignment agreement entrusting the activity of electricity
and/or heat generation. Related to the above stated, one should take into account
that, in the latter case, these are two separate procedures and that there is a period
of construction of the actual facility in between, so that such a phased procedure
does not provide sufficient legal security that it will be completed within a short
time and with a definite success.
It is necessary to point out the fact that investment in an affiliated company
of a public company for electricity and/or heat generation in the concrete power
plant(s), although it is subject to approvals by the Government, involves relatively
clear and short procedures. However, it cannot be affirmed with certainty that the
parent public company will allow the investor to hold a majority share. In such a
case, there is no choice but to precisely define and protect the rights of the
investor in the investment agreement. The risk of such an investment lies in the
dependence of the public company on daily political influences and the will of the
Government, which may issue an invitation for tenders in order to grant a
concession for engaging in the activities of the parent public company or which
can privatize the parent public company and thereby jeopardize the investors
rights in the affiliated company.
57