Sie sind auf Seite 1von 7

Gulf Cooperation Council

Interconnection Authority
GCCIA
Engineer

GCC Interconnection Project - Phase I

RM

Site Acceptance Test Report


ENERGY METER

TRANSMISSION & DISTRIBUTION


Bay Ref: RM
Substation: 400kV AL FADHILI
REVISION
PAGE 0
1

SUMMARY
1

PURPOSE OF TESTS

REFERENCE DOCUMENT

SCOPE

METER TERMINLOGY

TEST EQUIPMENT

PRE-REQUISTES

TEST PROCEDURES

RECORD TEST SHEET

8.1 METER INFORMATION

8.2 PROGRAMMED METER SETTINGS


8.3 DISPLAY CHECK

8.4 FINAL CHECK

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name
Date
Doc. No.

Name
Date
REV- 1

Page 1 of 7

Gulf Cooperation Council


Interconnection Authority
GCCIA
Engineer

GCC Interconnection Project - Phase I


Site Acceptance Test Report
ENERGY METER

RM

TRANSMISSION & DISTRIBUTION


Bay Ref: RM
Substation: 400kV AL FADHILI

1 PURPOSE OF TESTS
The purpose of the tests is to check the full functionality of the energy meter. This procedure must be
used with the complete Diameter Test Procedure, which provides the list of all panel wiring tests.
This procedure does not intend to check that all alarms and trips are correctly sent to the DCS or
SCADA level. This part is already developed into dedicated DCS or SCADA Commissioning
procedures.
2 REFERENCE DOCUMENTS
DOCUMENT

DOCUMENT
REFERENCE

VERSION/
DATE

REMARKS

Protection Line Diagram


Schematic Drawing
Service Manual
Operation Manual
3 SCOPE
Substation Name :Diameter:
Bay :
Panel Number :
Meter Denomination in Scheme (RM)
Scheme to be Checked

Meter Functionality Test.

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name
Date
Doc. No.

Name
Date
REV- 1

Page 2 of 7

Gulf Cooperation Council


Interconnection Authority
GCCIA
Engineer

GCC Interconnection Project - Phase I

TRANSMISSION & DISTRIBUTION


Bay Ref: RM
Substation: 400kV AL FADHILI

Site Acceptance Test Report


ENERGY METER

RM
4 TERMINOLOGY
Code ( ANSI)
MAIN, CHECK

Terminology
ENERGY METER

5 TEST EQUIPMENT USED


Sl No
1.

Description

2.

Secondary
Injection Kit
Multimeter

3.

Laptop

Make

Equipment
Sl No.

Calibration
date

Calibration due
date

NA

6. PRE - REQUISITES
PRE-REQUISITES

REMARKS

All Safety Condition Are Ok


All Competent Personnel Available For The Test
Ac & Dc Supply Availability And Security
PPE Safety Available.
All Other Relevant Safety Instructions Been Followed
Coordination With Other Parties ( GIS, Transformer, Etc..)

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name
Date
Doc. No.

Name
Date
REV- 1

Page 3 of 7

Gulf Cooperation Council


Interconnection Authority
GCCIA
Engineer

GCC Interconnection Project - Phase I


Site Acceptance Test Report
ENERGY METER

RM

TRANSMISSION & DISTRIBUTION


Bay Ref: RM
Substation: 400kV AL FADHILI

7. TEST PROCEDURES
The following procedures are written for demonstrating the main functions of the energy meters using
an Omicron test set or similar. This document is to be referred to when performing commissioning
tests in association with the commissioning section of the service manual.
7.1. Operational tests:
7.1.1 Meter Display (Instant Readings)

Program the meter with correct ratio of Current Transformer and Voltage transformer.

Apply rated voltage and check the meter readings and record the different readings such as Phase
to phase voltage and Phase to neutral voltage.

Now apply rated current and check the readings and record.

Apply rated voltage and current with phase angle 0 and check the Power Factor and note the
readings.

Similarly, apply rated voltage and current with different phase angle and note down the readings.

7.1.2 Meter Display (Accumulated Readings)


Apply rated voltage and rated current with Unity power factor for 30 Minutes and check the initial
readings and final readings.
Similarly, apply rated voltage and current with different power factor and noted the readings.

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name
Date
Doc. No.

Name
Date
REV- 1

Page 4 of 7

Gulf Cooperation Council


Interconnection Authority
GCCIA
Engineer

GCC Interconnection Project - Phase I


Site Acceptance Test Report
ENERGY METER

RM

TRANSMISSION & DISTRIBUTION


Bay Ref: RM
Substation: 400kV AL FADHILI

8. RECORD TEST SHEET


8.1 METER INFORMATION
Designation:
Type No.:
Model No :
Serial Number :
Rated Voltage (V)
Rated Current (A)
Frequency (HZ)
Auxiliary Power (V)
8.2 PROGRAMMED METER SETTINGS
CT Ratio:
VT Ratio:
Multiply by Constant:
Primary Watt Hour Constant:
8.3 DISPLAY CHECK
(a) VOLTAGE
Phase

Voltage Applied
(V)

Expected Reading
(kV)

Meter Display Reading


(kV)

Remarks

R-N
Y-N
B-N
R-Y
Y-B
B-R
(b) CURRENT
AREVA T&D

GCCIA / SNCL

Signature

Signature

Name
Date
Doc. No.

Name
Date
REV- 1

Page 5 of 7

Gulf Cooperation Council


Interconnection Authority
GCCIA
Engineer

GCC Interconnection Project - Phase I


Site Acceptance Test Report
ENERGY METER

RM
Phase

TRANSMISSION & DISTRIBUTION


Bay Ref: RM
Substation: 400kV AL FADHILI

Injected Current
(A)

Expected Reading
(kA)

Meter Display Reading


(kA)

Remarks

Angle
(between V&I)

Expected Reading

Meter Display Reading

Remarks

R-N
Y-N
B-N
(c) POWER FACTOR
Phase
R-N
Y-N
B-N
RYB
(d) ACTIVE POWER
Voltage
Phase
Applied (V)

Current
Injected (A)

Angle
(between
V&I)

Expected
Reading

Current
Injected (A)

Angle
(between
V&I)

Expected
Reading

Meter Display
Reading

Remarks

Meter Display
Reading

Remarks

R-N
Y-N
B-N
RYB
(e) REACTIVE POWER
Voltage
Phase
Applied (V)
R-N
Y-N
B-N
RYB
(f) APPRAENT POWER
AREVA T&D

GCCIA / SNCL

Signature

Signature

Name
Date
Doc. No.

Name
Date
REV- 1

Page 6 of 7

Gulf Cooperation Council


Interconnection Authority
GCCIA
Engineer

GCC Interconnection Project - Phase I

TRANSMISSION & DISTRIBUTION


Bay Ref: RM
Substation: 400kV AL FADHILI

Site Acceptance Test Report


ENERGY METER

RM

Voltage
Applied (V)

Phase

Current
Injected (A)

Angle
(between
V&I)

Expected
Reading

Voltage
Applied (V)

Current
Injected (A)

Angle
(between
V&I)

Time
Applied

Expected
Reading

Voltage
Applied (V)

Current
Injected (A)

Angle
(between
V&I)

Time
Applied

Expected
Reading

Meter Display
Reading

Remarks

R-N
Y-N
B-N
RYB
(g) WATT HOUR
Phase

Meter Display
Reading

RYB
(g) VAR HOUR
Phase

Meter Display
Reading

RYB
8.4 FINAL CHECKS
Item
Description

Result

All test equipment, leads, shorts and test block removed safely?

Disturbed customer wiring re-checked?

Alarms reset?

Secondary front cover replaced? (If applicable)

REMARKS

END OF REPORT
AREVA T&D

GCCIA / SNCL

Signature

Signature

Name
Date
Doc. No.

Name
Date
REV- 1

Page 7 of 7